atlas pixel detector pixel support tube interfaces lbnl internal pst review e. anderssen, lbnl
Embed Size (px)
TRANSCRIPT

ATLAS Pixel Detector
Pixel Support Tube Interfaces
LBNL Internal PST ReviewE. Anderssen, LBNL

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorOverview
• Structures and Position in ATLAS• Internal Interfaces
– Rail Geometry/Sliders/Roller– Pixel to PST Mounts– PP1/PP0
• Mount/External Interfaces– PIXEL to SCT Mount Block– Forward End Support Flexures

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPST Key Structures
Hoop Hat Stiffeners(section view)
30
45 10
SCT Flexuresand mount pads
Forward End Flexures Forward A
Forward C
Barrel
PST FlangesPP1 End Plug

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPixel Package—Internal Interfaces
Service and Beampipe Support
Service and Beampipe Support
Pixel Detecto
r
PP0
PP1
PP1
Beam pipe SupportRail Sliders
Beam pipe SupportRail Sliders
Pixel FrameRollers
Pixel Mounts

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPackage interfaces to PST
• Package has Several Physical Interfaces to PST– Rail Sliders/Rollers on Frame and Service/Beampipe Support– Pixel Mount Blocks– PP1 End Plate
• Installation Configuration– Frame Rollers engaged, Pixel Mounts not Yet Engaged– Rails Supports Entire Detector– PP1 Fixed Portion Clears Internal Dimensions of PST
• Installed Configuration– Frame Rollers Disengaged, Pixel Mounts engaged– Rails Continue to support Services and Beampipe– PP1(s) are Supported By PST end Flanges

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorInner Detector Layout

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel Detector

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPatch Panel Zero
PPO region preliminary layout—cable routing and assembly sequence not completed
Nominal routing for tubes shown here—allows access to rails and pixel supports (discussed later)
Pixel Mount Block Access
Frame RollersService Sliders

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPatch Panel One
PP1 layout determines final length of the Forward section of the PST—Layout of region is preliminary, and will require physical modeling to complete

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorMount Interfaces and Geometry
• Pixel detector is supported on mounts integrated into Flange of the Barrel PST
• Barrel PST is mounted to the Barrel SCT via Flexures and fixed Support– Mount Pad integrated with Flange of Barrel PST directly couples
SCT and Pixels decoupling as much as possible the shell of the PST• Forward PST sections are mounted to the Barrel PST
via a flange, and supported at their ends from the PST Support structure (formerly Beampipe support)
• Rails discussed later, however for completeness:– Pixel Detector rides in with package on rails and transitions to
mounts in the Barrel section of the PST– Remainder of Package (Service/Beampipe support Structure)
remains on rails

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorMount Schematic
• Pixel Support Tube Mounts to SCT Interface Block Via a Flexure• Pixel Detector Mounts to PST Barrel Via the Pixel Mount
SCT Not shown here
Pixel Detector
SCT Interface Block
Pixel Mount
Flexure
Missing Integrated Model with both PST and Pixel Detector Frame

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel Detector
Interface to SCT Interlink(Barrel PST support)
• Pixel Support Tube is supported by Three Flexures and One “Fixed Support”– All Flexures and the Fixed Support have identical bolted and pinned
interfaces with PST Barrel and SCT Interface Block
• Interface Blocks which penetrate the SCT Thermal Enclosure are mounted to the SCT Interlink
• All Interface Blocks are identical – Brief modification of the end of the interlink to accommodate– Penetration through SCT Barrel Thermal enclosure standardized

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel Detector
Proposal for SCT - Pixel Interface- 4 Blocks fastened to the SCT horizontal interlinks- Adjustement, if needed, by shimming or machining PST blocks
DimensionIs OK
Slide of E. Perrin
Need to Make integrated Model/Interface Drawing with relevant parts of SCT

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel Detector
SCT Inner thermal enclosure- I propose to fix the TE inner cylinder directly to Barrel 3
- To save space.- To try to simplify penetrations and sealing.
Flexure
PST BARREL MOUNT PAD
3mm Shim (0-6mm As REQ)
R240
R253.5
Z 780

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorManufacturing and Assembly implications
• Flexures Mount Directly to SCT Interface Block (prior to PST Insertion)
• Mounting Pixel Support Tube requires access to inside of Barrel PST– Pins and bolts into Flexure are accessed through cutout– “Adjustment” is by shimming (horizontal) and flexure replacement
(vertical) – Adjustment only required in emergency in pit—nominally PST is
centered in SCT
• Above implies that set of pre-machined flexures will be required
• Pinned interfaces require accurate mating and alignment of interfaces
• Proposed solution is to Bond PST mount Pads in place– Depending on Schedule either Transfer Tooling or Bond in place

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorManufacturing Accuracy by Bonding
• Whether SCT or Mistress tool is used depends on Schedule
• Bond Gap can currently account for +/- 200, but can easily accommodate up to 1mm if required (need to change some nominal dimensions)
Bond Between Mount Block and PST Mount Pad can be made last
Mistress tool or SCT AS Built

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorInterface Geometry
780
803
PST MountFlexure
253.5
SCT Barrel 3And Interlink

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorMount Block Analysis
• Flexures chosen for tight packaging Accurate manufacture and predictability of analysis
• Large Factors of Safety against yield at maximum foreseen loads
• Have assumed that loads from Integrated SCT/PST model represent worst case loads (2mm end deflections of PST)

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorHow Much Float is needed
• Fixed Point to End of SCT yields an internal stress
– Due to CTE mismatch on the order of 1-2ppm/C
• Fixed point to end of Cryostat yields an External load on the ID Barrel via the SCT
– There is potentially a large CTE mismatch between Cryostat and the Pixel Support Tube
– Case where Cryostat raised 10C above no-power condition, and where Support tube CTE is unusually high (>1ppm/C)
• Flexures need to assure minimal loads at these extensions yet remain stiff in the orthogonal directions
fixed
1.6m120
4.25m @ +1ppm/C2.65m @ +1ppm/C
4.25m @ +23ppm/C1.2mm
2.65m @ +23ppm/C 700
-20C
-20C
+30C

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorBarrel Flexure Analysis
0.5/N0.17/N
2.3/N
50N
147N
150N
75 25
115

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorNeeded Load Set on Flexure
Fx
Fz
Fy
My
Mz
Mx
Direction LoadRequired
LimitLoad
Fx 121N 450N(~250)
Fy 211N 2.3kN
Fz 68N 400(150N)*
Mx 322N.m 750Nm
My 189N.M 24.6Nm
Mz 53N.m 19.6Nm
flex
*Load at 400 deflection—stop prevents further travel preventing plastic deformation of flexure. Load then transfers to bolted joint which has a limit loadEqual to Fy.
No limit in Fy foreseen due to high factor of SafetyLimits in X,Z make FoS similar to Fy (bolted interface)

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorDesign of flexure against Failure
• Flexure Yields in Z- Travel at ~400 deflection– Stops included to limit travel to 400 or less
• Fy Ultimate for Flexure depends on Tensile stress area of Webs on Flexures
– Area of webs ~20mm2 – area of Bolt M6 ~20mm2
• Fx will have limits built into interface pads as shown in figure above on right
• Built Prototype Flexure without Stops to verify plastic limits
• Will test Stiffness of Flexure with TVH system
Fy=5.2kLbf
M6 Fast
ener
FX
Fx
Fz
Fy
My
Mz
Mx
Flexu
re
PST M
ou
nt P
AD
Limit to <150
Shim

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorForward Flexure
Plastic Limit stop will be incorporated in design, and integrated withFlex lock mechanism necessary for lock-out during Installation ofPixel Detector
80

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPixel Support Condition on PST
• This is an attempt at a pseudo-kinematic mount condition• Three points are fixed, with one adjustable in height—
nominally this is one of the ‘flat’ mounts• Mounts will be adjusted in co-planarity to match mount
surfaces—reducing twist of frame

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPixel Frame Mounts
• Prototype of Pixel mounts developed
• Axle and Bearing design refined
– Angular contact bearings– Ceramic race – Ceramic Balls– Titanium Shaft
• Contact analysis shows one ball can take full detector load (no brinnelling)
• Statistical tolerance analysis shows 5 or more balls in contact
• Shaft is Full Hard 6Al4V Ti alloy with Nitrided Surface

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorInterface to Pixel Frame Endplate
• Three mounts fixed, One adjustable vertically• Two dowel pins, Three mounting screws• Holes machined in Ears of Endplate• Endplate registered to End frame by tight
shoulder screws in same ear

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPixel Mount Block and preload spring

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorPreload Flexure
• Flexure Designed for 105N Preload– Nominally equals detector mass
plus some margin
• Deflection at preload nominally 1mm– Large compliance allows for
moderate machining and misalignment tolerances
• Factor of Safety against yield at Max flex design travel 1.7

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel Detector
Flexure
PST BARREL MOUNT PAD R240
SCT Interface surface
pixel
40 Budget
Mount Deflection Budget• Gravity Deflection Budget of 40 is assumed80Hz assumed for
vibrational stability• Flexure/Mount Pad-Flange/Pixel mount all contribute• Assumed 20 for Pixel mount, 20 for rest

September 2002Internal Review
E. Anderssen LBNL
ATLAS Pixel DetectorDeflection of Mounts
• Tip deflection of Long Shaft is 20.
• Angle change of shaft from pillow block adds 8.
• Nominal budget for Pixel mount was 20.
– Long shaft is coupled with short PST interface block
– Short shaft has less shaft deflection but more PST Pad windup
• Total Budget of 40 between SCT and Pixels is shared between these mounts and the PST mount pad
• Total budget is close to met—see Neal’s talk