atp 11a
DESCRIPTION
ATPTRANSCRIPT
Document History
Version Author Date Remarks
Version 1.0 Ashish Shukla 3-Sep-2015 New ATP 11B procedure for 850 Mhz
Version 1.1 Ashish Shukla 11-SEP-2015 Modification in Slide 36 Remark about Existing Antenna Swap and Transfer to ware house
Agenda
Work Order Assignment Management Flow chart
Example on WO Assignment Management Flow
Procedure to use SITEFORGE using tab in field
WO Assignment Management Flow(ATP-11A)
Install and usage of various Login
Procedure to use SITEFORGE using tab in field
Introduction to Work Order Assignment Management
Work Order Assignment Management is also known as WAS.
WAS is going to help users in automating the Work Order(WO) flow in asystematic manner using a portal called SITEFORGE.
Using this portal each level of Management employees will receive andexecute their WO or Task assigned to them.
Helps to trace the network status through online mode.
Provides Visual steps to guide users on progress and upcoming steps.
Improves productivity & complete visibility.
Helps users to monitor Parameter Compliance Index(Planned Vs. Actual).
Helps users to Search/Filter Sites & WO based on various parameters.
WO assignment management flow
Samsung QE“Accept”
“On hold” with issue list to eNB
Eng
Pre-ATP11A is acknowledged by eNB Engjoint ATP11A is performed (FE + eNB Eng)Report is modified on Tab ,if required (FE)
Joint-ATP11A is completed & report is uploaded on server. Samsung eNB er. to
certify
SOLPAR field er. Executes task(Pre ATP 11A) & saves it in tab & uploads to server once in coverage & notify
to eNB Eng.
CH assigns the WO to respective Samsung AM
1. AM assign Samsung eNBengineer & QE for that Site
2. Assign various tasks of that WO to single or multiple SOLPAR
SOLPAR PM assigns task to SOLPAR field engineer
RJIL Circle CTO
Accept/Reject
Task is auto-closed in SITEFORGE
End
Responsibility:
GIS/SIITE
FORGE;
Notification:
Samsung CH
Responsibility:Sam
sung CH;
Notification:Samsun
g AM, RJIL CTO
Responsibility:
Samsung Am
Notification:
Samsung CM
Responsibility:
SOLPAR PM
Notification :Samsung
AM & Samsung eNB
er.
Responsibility:
SOLPAR field
engineer
Notification: Samsung
eNB er. & SOLPAR PMResponsibility:
SOLPAR FE &
SAMSUNG eNB er.
Notification: Samsung
AM & SOLPAR PM
On Hold with
justification Response:Sam
sung QE
Notification:
Samsung-Reg
QM,AM,CM;
SOLPAR-PM,FE
SAMSUNG AM will Accept
Responsibility:
Samsung AM
Notification:
Regional
QM,SAMS
CM,Circle RJIL
CTO
Accept
Responsibility:
Circle RJIL CTO
Notfication:
Samsung
CH,AM;System(
GIS,REIMS)
Reject
AcceptResponsibility:
SAMSUNG AM
Notification:
SOLPAR PM,
SAMSUNG CH
WO is created & issued to respective SAMSUNG CH by RJIL
Login creation - introductionObjective
• Procedure to install and use (Work Allocation System –WAS [Siteforge]) in Samsung Galaxy Tab 3 8” by Solpar field engineers
• Steps
User (Solpar field engr.) creation by : Solpar Project manager
Intimation mail to field engineer : From Siteforge team ([email protected])
Click activation link
Login to Siteforge and change password (default password is with project manager)
Download and install .apk (installation file).
Start using the siteforge by clicking the icon.
Login creation – accessing the site first time
If the mail is accessible in the TAB
Click on Activation Link
If the mail is not accessible in the TAB (eg. Official mail not configured in the the TAB)
Open explorer, type below link in the address barhttps://siteforge.ril.com/siteforge/jsp/index.jsp
Login creation – password change
Change the password
Default password would be available with your project manager
Changing security setting
Before downloading the installation file, change the security setting
•Go to TAB setting
•Turn on Blocking mode •Tick Unknown sources check box
Download and install installation file (.apk) file
•Click ‘Download Apk’, •Once downloaded, go to notifications and click .apk file•Select install
Installation Scenario
Field Engineer need to answer the above question that they have installed Multiband or Penta Band during 850 Mhz Installation
Antenna Make & Model
Enter the Information based on ACE/ROSENBERGER Model Type Used
Antenna Height incuding building height and tower foundation height in Case of RTP/RTT/RTD
EDIT
EDIT
Site Inventory List
Field Engineer need to capture the Serial number of all the site inventory for 850 Mhz
Capture the 850 Mhz L9CA serial Number
Capture 850 Mhz RRH Serial Number for all Three sectors
Capture 850 Mhz Antenna Serial Number for all Three sectors
Site Inventory List
Capture 850 Mhz Antenna Serial Number for all Three sectors
Incase of Pentaband / Muntiband Antenna capture the serial number of all the three RET in all the 3 Sectors
Remarks
Add remarks about the work done if any
Click Next
Incase of existing antenna are swapped with new antenna then SOLPAR need to mention the YES/NO , and also confirm that they are sent back to
warehouse .