atucara kontrak layout
TRANSCRIPT
-
8/2/2019 Atucara Kontrak Layout
1/8
GROUP MEMBERS
MUHAMMAD ABDUL HAIKAL B MOHTAR 13PKA11F2010
MOHD SHAMIR HANIF B M SABRI 13PKA11F2011
WAN MOHD RIDHUAN B WAN ISMAIL 13PKA11F2015
AHMAD TARMIZI B MOHKTER 13PKA11F2016
-
8/2/2019 Atucara Kontrak Layout
2/8
If the regular progress of the works or any part thereof hasbeen materially affected by reason as stated under Clause
43 (c),(f) or (i) hereof (and no other).
Clause 43
(c) By reason of directions given by the S.O consequential upondisputes with neighbouring own provided the same is no due to
any act negligence or default of the contractor or otherwise the
causing of the project delay
(f) The contractor shall not receive within a reasonable time of
S.O directives, plans, required levels etc or direction with respectto the nomination Sub-contractor or Nominated Supplier.
(i) by delay on the part of artist , tradesmen or others engaged by
the government in executing work not forming part of the
contract
-
8/2/2019 Atucara Kontrak Layout
3/8
` the Contractor has incurred direct loss and or expense
for which he would not be reimbursed by a payment
made under any other provision in this Contract.
` the Contractor shall within one (1) month of the
occurrence of such event of circumstance give notice in
writing to the S.O. of his intention to claim for such direct
loss or expense together with an estimate of the amountof such loss and or expense, subject always to Clause 48
hereof.
` Clause 48;-
(a) submission of claim documents
(b) Final Certificate
(c) sums to be certified in the final certificate
(d) Terms and Conditions of Issuance of Final Certificate
-
8/2/2019 Atucara Kontrak Layout
4/8
Sub-clause (a)- DEFECTS LIABILITY PERIOD` Defect liability period is 12 months (projects in excess of
RM50, 000.00) as stated in the contract documents after
the date of practical completion of the work given to
contractors by the S.O which defects, imperfections or
deficiencies or other damage whatsoever that mayappear and also due to materials or goods or
workmanship shall be executed by the contractor as
soon as possible.
` if a fault occurs after 12 months or a year or the datespecified in the contract all independent contractors
responsibility.
-
8/2/2019 Atucara Kontrak Layout
5/8
Sub- Clause (b) SCHEDULE OF DEFECTS
` any defect, imperfection, shrinkage or any other faultwhatsoever which may appear during the Defect LiabilityPeriod to be made by the Contractor , shall be specified bythe S.O, in the Schedule of Defects which shall deliver to theContractor not later than fourteen (14) days after theexpiration of the Defects Liability Period.
` The defects, imperfection, shrinkage or any other faultwhatsoever specified in the Schedule of Defects shall bemade good by the Contractor at his own costs and to becomplete within a reasonable time but in case not later thanthree (3) months after the receipt of the said Schedule.
` Provide that the S.O. shall not be allowed to issue anyfurther instruction requiring making good of any defect,imperfection, shrinkage or any other fault whatsoever afterthe issue of the said Schedule of Defects or after fourteen(14) days from the expiration of the said Defects LiabilityPeriod, whichever is the later.
-
8/2/2019 Atucara Kontrak Layout
6/8
Sub- Clause (c) DEFAULT OF THE CONTRACTOR
` If the Contractor shall fail to comply with either sub-
clause (a) or (b) or both within the time so specified, the
materials or works so effected may be good in such
manner.
` The S.O. may think fit, in which case the costs thereby
incurred shall be deducted from the sum remaining to be
paid to the Contractor or failing such remainder it shall
be recoverable from the Performance Bond or as a
liquidated demand in money.
-
8/2/2019 Atucara Kontrak Layout
7/8
Sub- clause (d)- ADDITIONAL POWER OF THE S.O.
` If any defect, imperfection, shrinkage or any other fault
whatsoever be such that, in the opinion of the S.O., it shall beimpracticable or inconvenient to the Government to have the
Contractor to remedy the same, the S.O. shall ascertain the
diminution in the value of the Works due the existence of such
defects.
` The imperfections, shrinkage or any other fault whatsoever and
deduct the amount of such diminution from the sum remaining
to be paid to the Contractor or failing such remainder it shall
be recoverable from the Performance Bond or as a liquidated
demand in money.
-
8/2/2019 Atucara Kontrak Layout
8/8
Sub clause (e) - Certificate of Completion of Making
Good Defects.
when in the opinion of the S.O. the Contractor has made
good the defect, imperfection, shrinkages or any other
fault whatsoever which he is required to make good
under sub-clauses (a) or (b), or both.
the S.O. shall issue a certificate to that effect, and the
date named in such certificate shall be the date on which
the Contractor has completed making good such defects,
imperfections, shrinkages or any other fault whatsoever.
The Certificate shall be referred to as the Certificate of
Completion of Making Good Defects.