auckland council statement of evidence of william (bill ... and project rosedale (tbm (epbm) and...
TRANSCRIPT
Under the Resource Management Act 1991 In the matter of Notices of Requirement to enable the construction, operation and maintenance of the City Rail Link
Between
Auckland Transport Requiring Authority
and
Auckland Council Consent Authority
Statement of Evidence of William (Bill) Russell Newns
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
1
Qualifications and Experience
1. My full name is William (Bill) Russell Newns.
2. I am a Chartered Engineer registered with the Engineering Council of
the UK (No. 518790) and I am a member of the Hong Kong Institute of
Engineers (No.M00374030) and the Institute of Professional Engineers
in New Zealand (1011478).
3. My academic qualifications include a Bachelor of Science degree in
Geology from the City of London Polytechnic in 1990, a Master of
Science degree in Mining Engineering from the Camborne School of
Mines in 1994 and a Diploma in Arbitration from the University College
Dublin, gained in 2004.
4. I am the technical secretary and committee member of the
New Zealand branch of the Australasian tunnelling society.
5. I have over twenty years of professional services experience which
includes the design and construction supervision of major civil
engineering projects.
6. My major international civil engineering project experience over the last
two decades includes:
(a) Lantau Airport Railway Mass Transit Railway Corporation Hong
Kong (MTRC) (Tung Chung and Tsing Yi Stations and Tsing Yi
Tunnels (Drill and Blast) (Design + Build (D+B));
(b) Tseung Kwan O Extension MTRC (Black Hill Tunnels and Pak
Shing Kok Tunnels, D+B);
(c) Route 3 Tai Lam Road Tunnels (D+B and caverns);
(d) Tai Lam rail tunnel and caverns (D+B);
(e) Quarry Bay Congestion Relief Works in Hong Kong MTRC
(Tunnel Boring Machine (TBM), D+B and caverns in dense urban
Central Business District (CBD) with modifications to existing live
rail station and many sensitive receivers);
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
2
(f) Dhoby Ghaut Tunnels in Singapore (Earth Pressure Balance
TBM) (EPBM) for metro rail;
(g) Dublin Port Tunnels (TBM + cut and cover tunnels and caverns
beneath residential areas); and
(h) Adelaide Desalination Plant - intake and outfall tunnels (TBM,
slurry and ground treatment to control groundwater ingress).
7. I currently hold the position of Technical Director at Aurecon, a
company I joined in 2005 since moving to New Zealand.
8. My design and construction experience in New Zealand includes the
Browns Bay Trunk Sewer Replacement (extensive pipe-jacking using
micro-TBM, slurry), Project Hobson (TBM (EPBM) and associated
shafts) and Project Rosedale (TBM (EPBM) and access shafts and
outfall structures) and the Huntly North Shaft (caisson sinking and shaft
sinking to 161m).
9. Since 2006, I have also been closely involved in the planning and
subsequent procurement of the Waterview Connection Tunnels (large
diameter TBM tunnel). From 2006-2008 I was the design manager for
concept levels designs for two and three lane running tunnels using
TBM covering all engineering disciplines including fire and life safety.
I also prepared settlement assessments for the AEE. For the 2011
procurement I developed and amended the Minimum Requirements for
the underground works and the TBM (specifications) during
procurement and also prepared the geotechnical baseline report. I also
evaluated both alliance proponent tenders in terms of technical and
programme risk.
10. I have been almost continuously involved with active construction
including supervision of major projects in “greenfield” and urban areas
as either Engineer or Engineer’s Representative or Designer or
Designer’s representative. These projects have typically included TBM
tunnelling, drill and blast operations for quarrying and tunnelling, major
earthworks, diaphragm, secant pile and sheet pile wall installations,
sequential excavation for large diameter caverns, shaft sinking,
pipejacking and major utility diversions. I have therefore direct and
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
3
extensive experience of all of the proposed methods of construction
required for the City Rail Link project.
Background and role
11. The City Rail Link (CRL) project is a 3.4km underground passenger
railway (including two tracks and three underground stations) running
between Britomart Station and the North Auckland Line (NAL) in the
vicinity of the existing Mount Eden Station. The CRL also requires an
additional 850m length of rail modifications within the NAL. The stations
included in the CRL NoR have been temporarily named Aotea Station,
Karangahape Station, and Newton Station.
12. Aurecon NZ Ltd was engaged by Auckland Transport (in February
2012) as Principal Advisor (PA) for the CRL project. The PA is led by
Aurecon NZ Ltd and comprises the principal partners of Aurecon NZ
Ltd, Mott MacDonald, Jasmax and Grimshaw. The PA reports directly
to Auckland Transport’s Infrastructure Delivery work stream which is
responsible for delivery of the CRL project. The PA is also supporting
the Notice of Requirement (NoR) and Property work streams.
13. Since February 2012 I have been the Design Manager for the PA team
for CRL which developed the NoR Concept Design. In that capacity,
and with the assistance of the PA team of engineers and architects and
Auckland Transport’s team of planners and expert advisors I have been
responsible for developing the NoR concept designs and the indicative
construction methodology and programme.
14. I was also involved in a similar capacity (albeit with a smaller team) for
the CRL Project in 2008 for ARTA1 and Kiwirail2 which established the
alignment within Albert Street.
15. I am familiar with the project location, track alignment and the site
specific locations for each proposed station. I have walked the
proposed route and visited all proposed station sites many times and
1 The former Auckland Regional Transport Authority.
2 New Zealand Railways Corporation.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
4
am familiar with the context within which the CRL station concept
designs have been developed.
16. I have read the Code of Conduct for Expert Witnesses as contained in
the Environment Court Consolidated Practice Note (2011), and I agree
to comply with it as if this hearing was before the Environment Court.
My qualifications as an expert are set out above. I confirm that the
issues addressed in this brief of evidence are within my area of
expertise. I have not omitted to consider material facts known to me
that might alter or detract from the opinions expressed.
Scope of Evidence
17. My evidence will address the CRL Concept Design for the Notices of
Requirement (NoR) in respect of the existing land use constraints. In
more detail, my evidence will cover:
(a) The Concept Design - Principles and Process;
(b) Design Constraints;
(c) The Concept Design;
(d) Indicative construction methodologies including worksite locations
and activities;
(e) An indicative construction programme;
(f) Response to submissions;
(g) Response to Planner’s Report; and
(h) Proposed conditions.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
5
City Rail Link (CRL) – Concept Design Principles and Process
18. The CRL alignment and design has been developed with reference to a
range of design considerations and physical constraints, particularly
topography, ground conditions and man-made structures including
building substructures and significant utilities. The Concept Design
Report (CDR)3 contains a description of the concept design developed
for the CRL Project. In addition, the CDR contains the indicative
construction methodology and programme.
19. The concept design also establishes engineering and architectural
design parameters which will provide an ‘envelope’ for future design
iterations as the CRL project moves through its various design phases.
20. The concept design has been informed by two past studies for the
CRL, namely:
(a) CBD Rail Tunnels – Aotea Station Extension Study, 2008,
prepared by Aurecon (formerly Connell Wagner), ARTA;
(b) Auckland CBD Rail Link Study – Option Evaluation Report, 2010,
and Concept Design for Preferred Alignment and Station
locations, 2010, prepared by Aecom, Parsons Brinckerhoff; and
Beca (APB&B), ARTA and KiwiRail.
21. An objective for the Design team was to establish design ‘robustness’
in consideration of options. This typically involves considerations of
cost, flexibility and practicality in view of a reasonably high level of
uncertainty or risk. Elements of uncertainty may include for example
the understanding of ground conditions and the position and nature of
utility services particularly within the CBD.
22. Another key objective has been to determine a coherent set of designs
across the architectural and engineering disciplines. In that respect,
the Design of underground railways including underground stations is
particularly interdependent with design aspects having significant
influences on other design aspects.
3 Appendix 13: Volume 3 CRL NoR suite of documents.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
6
23. In order to support the NoR process, the concept design should be
robust (as described above) but flexible so as not to overly constrain
construction techniques, methods or staging particularly for temporary
construction activities (which enable provision of the permanent CRL
structures) as this is where the constructor can add significant value
during the tendering and procurement phases of the project.
24. Therefore, reasonable construction tolerances have been provided
within the NoR concept design using local knowledge and experience
of the range of techniques that may be applied and inputs from the
wider PA team. An objective in that process is the identification and
characterisation of key constraints.
25. The design of the permanent works is driven primarily by the rail
alignment which is largely fixed at either end by the existing rail
infrastructure.
26. The location of station precincts was determined by the 2010 APB&B
Option Evaluation Study. Therefore the Concept Design alignment was
developed from determining the position (and length) of the rail station
platforms within the governing geometric rules for rail grades
(described below).
27. Following confirmation of the station platform positions, options for
station form were established and preferred options selected (as
discussed in the evidence of Mr John Fellows). These were then
considered alongside potential alignment constraints of the adjoining
rail tunnels (running tunnels) which I also describe below (e.g. existing
infrastructure such as building basements, the Orakei Main Sewer and
the Central Motorway Junction).
28. The Concept Design rail alignment is thus one possible solution with a
degree of design flexibility within the NoR envelope. Having said that,
the alignment flexibility has fairly narrow tolerances given the overall
challenge of topography as noted above but also given the knock-on
impacts to the overall scheme. A general principle was to maximise the
extent of the rail alignment within road reserve, where practicable.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
7
29. A fuller description of the options analysis that was undertaken is
provided in the report authored by Auckland Transport titled City Rail
Link: 2012 Option Evaluation Summary Report.4
Design Constraints
30. The following are the key technical considerations that have informed
the concept design rail alignment:
(a) Minimum desirable speed (50km/hr);
(b) Maximum vertical grade (compensated for curvature) of the
alignment within tunnels (3.5%);
(c) Maximum vertical grade at stations (1%); and
(d) Platform length at stations (150m).
31. It is characteristic of CRL that rail gradients are near the maximum limit
(3.5%) for Electric Multiple Units (EMU) in order to connect Britomart to
the NAL at Mt Eden, a vertical climb of some 70m.
32. The CRL electrification will be integrated into the Auckland rail system
25 kV AC traction power network.
33. Signalling and a range of information and communication technologies
have been applied to the indicative CRL design. Section 3 of the CDR
provides a list of the matters that have been taken into account.
34. Key physical constraints, being natural or man-made features, and
which have been considered as part of the concept design include:
(a) Natural topography (which results in an approximate 70m vertical
climb between Britomart and the NAL);
4 Appendix 13: Volume 3 CRL NoR suite of documents.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
8
(b) Geological conditions5;
(c) Significant structures and buildings including:
(i) The Central Post Office (CPO) in Lower Queen Street;
(ii) The Zurich Building (21 Queen Street) and the HSBC
building;
(iii) Bluestone retaining wall on Albert Street (Wyndham Street
to midway between Durham and Victoria Street West) and
Lower Albert Street;
(iv) Access to and structural foundation constraints of buildings
lining the route particularly Albert Street;
(v) Central Motorway Junction Motorway Structures;
(vi) Heritage buildings and structures scheduled under the New
Zealand Historic Places Act or Auckland Council District
Plans (including the bluestone retaining wall in Albert
Street); and
(vii) Other sensitive buildings or buildings classified as having
character merit by either the New Zealand Historic Places
Trust or Auckland Council;
(d) Utilities including:
(i) The Watercare Orakei Main Sewer on Victoria Street West;
(ii) Vector Tunnel at Mayoral Drive;
(iii) The Auckland Council 1500-1665mm stormwater drain in
Albert Street;
5 Investigations indicate the presence of fill, alluvial clays and silts and below these the
bedrock of East Coast Bays Formation (ECBF) (in various states of weathering) along the
alignment. Basalt rock and ash is present in the South near Mt Eden.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
9
(iv) The Watercare 375mm bulk water supply main in Pitt
Street;
(v) The Watercare 1300mm bulk water supply main in Nikau
and Ruru Streets; and
(vi) The Auckland Council 1950mm stormwater drain in Nikau
and Ruru Streets;
(e) Existing operating rail lines at Britomart and NAL; and
(f) Major road intersections.
35. With respect to the various technical matters and physical constraints
listed above, I note that the concept design detail has been developed
at a high level. As such, further more detailed investigation and design
work is required. This work will likely include a combination of further
site investigation into underlying ground conditions, detailed
vulnerability assessments of buildings and utilities and further design
and constructability reviews.
Worksites
36. Appendix A to my evidence indicates the locations of the proposed
worksites along the length of the proposed CRL route. With reference
to Figure 1 below the worksite locations are described as:
(a) A - North Auckland Line Surface Connections (west);
(b) B - North Auckland Lines Surface Connections (east);
(c) C - Mt Eden TBM worksite;
(d) D1 – Newton Station (Mt Eden Road Main Entrance Shaft);
(e) D2 – Newton Station (Dundonald Street Egress and Ventilation
Shaft);
(f) E1 – Karangahape Road Station (Beresford Square Main
Entrance Shaft);
1527
5585
_Evi
denc
e B
ill N
ewns
FIN
AL
(2)
Sta
tem
ent o
f Evi
denc
e of
Will
iam
(B
ill)
Rus
sell
New
ns
10
Figu
re 1
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
11
(g) E2 – Karangahape Road Station (Mercury Lane Egress and
Ventilation Shaft);
(h) F – Albert Street South including Aotea Station;
(i) G - Albert Street North to Customs Street;
(j) H –Downtown Shopping Centre, Lower Albert Street and Queen
Elizabeth II Square; and
(k) J - Britomart Station.
37. Worksites A, B and C, adjacent to the NAL corridor are envisaged to
support the entire CRL construction programme as it is envisaged that
the rail fitout will be largely undertaken from this end of the Project.
Fitout activities for stations will largely occur at each station supplied
from either end.
The Concept Design
38. In this section of my evidence I describe the rail alignment and
associated design and construction considerations which have been
developed for the CRL project.
39. The indicative construction methodologies and sequence for the CRL
project has been developed for the purposes of defining the land
required for the construction works, informing the Assessment of
Environmental Effects (AEE) accompanying the Notices of
Requirement (NoR), identifying actual and potential effects resulting
from the construction of the CRL and any potential management
methods, to appropriately mitigate such effects. The methodologies
have assisted in defining the proposed designation footprint and
enabled various technical experts to undertake assessments relevant
to the project so that the potential effects of the project can be
understood and avoided, remedied or mitigated including through the
use of appropriate management measures.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
12
40. Section 3.2 of the CDR sets out the indicative alignment design and I
attach the indicative route plan and rail concept drawings as
Appendix A to my evidence.
41. I will now describe the concept design and indicative construction
methodology for each section of the CRL starting at the northern end
(Britomart).
Britomart Station Precinct
42. To suit operational requirements to maintain terminating rail services
within Britomart Station, platforms 1 and 5 will be used to connect the
CRL to the NAL.
43. It is noted that the track along this section of the alignment sits at a
depth of approximately 10m. The method of construction in this
location is expected to be “cut and cover” using diaphragm walls for
watertightness (refer indicative construction methodology below) given
the shallow depth and as the alignment runs through old reclamation fill
hydraulically connected to the Waitemata Harbour.
44. Cut and cover methodologies are typically employed where there is
insufficient/unsuitable ground cover to enable tunnelling without
disproportionate cost and risk.
45. Cut and cover construction techniques involve the installation of two
walls (sheet, soldier or secant piles or diaphragm walls) after which the
ground between is excavated. Depending on the depth of the
excavation, propping may be required across the excavation width at
periodic intervals to enable a safe environment for construction of the
permanent works which may (other than for sheet piles) comprise part
of the permanent works themselves. These vertical walls are required
where the ground is not self-supporting in soils and fill which overlie the
underlying bedrock or where there is insufficient space for an open cut.
It is noted that excavation in the underlying East Coast Bays Formation
(ECBF) bedrock will be required using mechanical excavators. The
ECBF may be supported either with vertical supports in the form of
soldier piles and or local rock bolts and/or shotcrete as required by the
exposed conditions.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
13
46. ‘Cut-off’ walls will be required to seal groundwater during the temporary
phase of construction for the section of works beneath the CPO
connecting to the existing secant pile walls of Britomart Station. These
cut off walls install a barrier of relatively impermeable clays. This
operation is likely to require temporary closure of Galway Street and
Tyler Street at different times for a period of the order of 1-2 months.
47. The most complex part of the required modifications to Britomart
Station involves underpinning foundations of the CPO building to
remove foundation clashes. This is a very sensitive heritage building
which was modified and strengthened for seismic resistance during
Britomart construction. In developing the structural modifications for
CRL the PA team has involved engineers who designed and oversaw
construction of the structural modifications for Britomart. I consider that
the scale (and risks) of the modifications to the CPO needed for the
CRL are of a similar order as those that were necessary as part of the
original modifications for Britomart Station.
48. The running tunnels pass westward from under the CPO into a cut and
cover structure (refer below) within Queen Street that houses
ventilation equipment required for fire and life safety purposes for
Britomart Station. The alignment then passes into Queen Elizabeth
Square and runs below the existing basement level of the Downtown
Shopping Centre site, generally heading southwest to the corner of
Customs and Albert Street. A feature of this part of the route is the
presence of a reverse curve6 in order to reduce impacts upon adjacent
buildings (namely the Zurich building) and to reduce the operational rail
footprint required through the Downtown Shopping Centre site by
bringing the running tunnels closer together.
49. The locations for construction sites in this area are centred around the
Downtown shopping centre. (Refer Drawings 101 and 102 in
Appendix A attached). These may be in place for 3 to 4 years which is
a similar timeframe to that required to demolish and re-develop the
entire building site.
6 A series of two curves in opposite directions.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
14
50. The Downtown Shopping centre would be demolished in order for CRL
to be constructed and it naturally becomes a CRL worksite.
51. The most efficient arrangement and use of the Downtown Shopping
Centre as a worksite will be dependent upon the final design and
programme of the re-developed Downtown Shopping Centre.
However, we have developed the NoR designs around the 2008
Westfield development that incorporates a multi-level car parking
basement.
52. There are various means of providing equivalent service access to the
basement level of 21 Queen Street which is currently from Albert Street
during construction by using temporary ramps and decks around the
CRL works.
53. A worksite in Lower Albert Street may be used to serve the Albert
Street cut and cover excavations and the worksite can operate
independently of the Downtown Shopping Centre demolition and re-
development.
54. If the Downtown shopping centre site has been redeveloped then this
would put greater emphasis on and constrain the worksites (particularly
in respect of construction vehicle movements) between Lower Albert
Street and Queen Elizabeth II Square. This is because a benefit of the
Downtown Shopping centre as a worksite during CRL construction (in
terms of traffic movements) comes from linking Queen Elizabeth
Square with Lower Albert Street.
55. The QEII worksite is necessary to support construction works across
Lower Queen Street and the adjacent Britomart modification works and
CPO underpinning.
56. The Worksites are envisaged to be operating up to 24 hours a day 7
days a week. However, not all activities would be undertaken 24/7 and
some activities would only be undertaken between the hours of 7am
and 7pm.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
15
57. The Worksites can be used to stockpile construction materials and
generally to support construction activities and are anticipated to
include;
(a) General storage of construction materials;
(b) Fuel storage;
(c) Reinforcing steel storage, bending and fixing;
(d) Bentonite and cement for grout and piled wall construction;
(e) Pile casings;
(f) Spoil stockpiling from the excavation. However spoil will be taken
for off-site consented disposal on a daily basis;
(g) Construction plant e.g., piling rigs, mobile cranes, shotcreting
plant, compressors etc;
(h) Maintenance facilities and stores;
(i) Water treatment plant; and
(j) Site offices and workers’ facilities.
58. It is worth noting that larger worksites are less constrained, i.e. are
typically more productive and are less dependent upon external traffic
movements in order to operate efficiently, i.e. to supply labour and
materials and to remove spoil.
59. It is expected that ready batched concrete and shotcrete will be brought
to these worksites as will the material used to backfill the ‘bottom-up’
cut and cover tunnels.
60. Based on the indicative programme and the need to support the Lower
Albert Street cut and cover works, the Downtown site demolition and
reconstruction, and the Queen Elizabeth Square cut and cover tunnels
it is expected that vehicle movements to the site will be a maximum of
around 200 truck movements to site per day – the majority of which
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
16
(say 75%) being associated with off-site spoil removal using rigid trucks
carrying the equivalent of 8m3 of spoil only.
61. It is noted that Ian Clark has assumed more movements (about 25%
more) in his assessment and I consider this is appropriate in order to
provide flexibility to the project programme and robustness of his
assessment.
Albert Street Running Tunnels
62. The CRL alignment needs to have relatively tight curves to connect
Britomart with Albert Street. The radius of the curve is in the order of
130m. The vertical alignment of this section of the route sits at a depth
of approximately 18m below existing ground level along this section of
the route. At the southern end of this section of the CRL (prior to
connecting to the proposed Aotea Station) the alignment needs to pass
above the Orakei Main sewer that runs across Albert Street at Victoria
Street. Passing below (deepening the alignment) would mean
unacceptably high rail gradients in order to connect to the NAL at Mt
Eden.
63. An alignment for concept design was selected to avoid (to the East) the
Bluestone Wall situated at the top of Durham Street (refer below).
64. The horizontal (plan) alignment generally sits within the centre of Albert
Street to enable practicable traffic access to be provided to adjacent
properties during construction (refer Drawings 10, 11 and 12 in
Appendix A and below). The design acknowledges that ground
conditions within Albert Street are variable. Just past the old cliff line
(Customs Street) rockhead (the upper surface of unweathered bedrock)
is near to the surface. By Swanson Street the rockhead level dips and
there is an infilled channel of softer alluvium and weathered bedrock
which extends south to beyond Aotea Station. These softer soils are
one of the main reasons for the two existing retaining walls which are
present in Albert Street, the Bluestone Wall (refer below) and the Lower
Albert Street retaining wall adjacent to Aotea Station. The variable
level of rockhead and limited ground cover are significant risk factors to
mined tunnelling within the lower parts of Albert Street as softer ground
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
17
and less ground cover requires more complicated support and results
in slower tunnelling progress. Along Albert Street the tunnels are
expected to be constructed by cut and cover methods (already
described) and the choice of this method is heavily influenced by the
presence of an old stormwater line within the rail envelope (i.e. the
operational space required for the trains, egress and maintenance
walkways and rail systems). The stormwater line extends for the full
length of Albert Street and may clash with rail alignments between
Customs Street and Victoria Street. As-built records indicate the
stormwater line is in the order of 2m in diameter but there is also an
associated large pump chamber present within Customs Street. There
remains considerable uncertainty with regard to the presence of steel
within the pipeline. Steel may also be present as a result of temporary
works left in the ground outside the permanent lining. This uncertainty,
and the pipe’s position (particularly where it is above the rail alignment
in the northern part of Albert Street) presents significant risks for
tunnelling methods other than cut and cover.
65. The stormwater line was diverted as part of the America’s Cup
programme into Swanson Street. The East-West connection to
Swanson Street would also clash with the rail alignment and so would
be required to be diverted ahead of tunnel construction. This may be
undertaken using a new pipejacked line further to the East of Albert
Street, connecting again at Swanson Street. The presence of the new
line itself then presents a further constraint to rail alignments within
Albert St.
66. Enabling works are required to clear clashes with street furniture and
perhaps remove building canopies where necessary. A critical step is
the provision of guide walls and to clear and divert utility services as
necessary to ensure continuity of supply. These enabling activities will
be undertaken in linear blocks of around 100m long on the east and
west sides of the street in turn. Each block would be expected to take
about 3 weeks to complete. These activities are analogous to a minor
utility trench diversion in the CBD and around 2m deep. The activities
involve installing temporary traffic management, removing any street
furniture and canopies etc that clash, saw-cutting the road surface and
excavation with hand tools to expose services.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
18
67. Temporary guide wall supports may be installed (sheet piles or a ‘drag-
box’). Once excavated to confirm that piling will not strike any services,
the trench would be backfilled with a sand cement mix (a guide wall for
piling). Fixings for the subsequent installation of the traffic barrier
between the construction zone and the service lane may then be
installed for the construction hoarding. Once the guide wall is
complete, the hoarding and traffic barrier could be erected to isolate the
construction works from the service lane which may be largely serviced
from the northern end of Albert St, although construction access and
egress from the Albert St service lane will be required.
68. The construction of the soldier piles will be undertaken inside the newly
placed construction hoardings using a 65t piling rig achieving around
5m linear progress per day.
69. Once the piles are installed, excavation starting from the North end of
Albert St and working progressively South to install the first level of
propping (between east and west walls) and waling beams that run
longitudinally along the walls would be undertaken.
70. Excavation would proceed in lifts (between each strut level nominally at
4m vertical spacing) serviced from a principal worksite at the North end
of Albert St. The walers would be coupled to the soldier piles and
props would be placed between the walers at the end of each
excavation stage. Excavation would then recommence beneath the
newly placed prop/strut.
71. Once the excavation is at the required level for the rail alignment a
water proofing membrane would be placed and a reinforced concrete
base slab poured. The walls and roof of the cut and cover tunnel would
then be undertaken and the waterproofing membrane sealed around
this. The membrane would be protected and backfilling operations
would commence undertaken in lifts to ensure suitable compaction.
This would involve light excavators (25T 150hp) and earth compactors
(12.5t 150hp)
72. The duration of this activity is likely to be 8-10 months with backfilling
occurring around prop removal over about 16 weeks.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
19
73. The dimensions of the cut and cover tunnels have been carefully
considered within Albert Street in order to provide vehicle service lanes
of minimum 3m width, and pedestrian walkways of minimum 1.5m
width either side of the central construction trench (and the construction
hoarding) at the ‘tightest’ location in the vicinity of the Durham Street
Bluestone Wall but also on the West side of Albert Street between
Swanson Street and Customs Street. Elsewhere along this section of
Albert Street there is the ability to provide wider walkway widths as
required.
74. The dimensions of the cut and cover trench have been designed in
view of the indicative ground conditions assuming ‘soldier piles’
(although other wall retention methods are possible). This method
uses ‘augers’ to excavate the ground. The resulting cylindrical hole is
replaced with a reinforced concrete column (the ‘pile’) at varying
longitudinal spacing depending upon the ground stiffness. Gaps
between piles (if any) may be filled with shotcrete as the excavation
progresses.
75. Inside the soldier pile walls the permanent rail ‘box’ structure will be
constructed (as described above) which will comprise a waterproofing
membrane, followed by a cast-in situ reinforced concrete structure
which will house the rail envelope. The rail envelope comprises the
area required for the new trains currently being built for the Auckland
rail network and associated space proofing for Over Head Line
Equipment (OHLE) rail services and emergency and maintenance
access provisions.
76. Once the excavation and propping of the trench is complete (prop
spacing and the walls themselves will be designed to suit excavation
plant) the waterproofing and cast-in situ structures may be placed.
This structure may then be backfilled up to the previous street level.
77. Works within Albert Street will be inside a construction hoarding in the
middle of the street. Staging of the works may require secondary
construction access points but it is envisaged that access to the
worksite will primarily be from the North across the Customs Street
intersection. Construction laydown would be possible within the
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
20
hoarding itself and also within the demolished Downtown site and / or
the Lower Albert Street area within the designation footprint.
78. This section of CRL construction is expected to take approximately
24 months including reinstatement to current ground levels.
Aotea Station
79. In terms of the form of Aotea station a series of guiding principles were
developed and these are described in section 3.4 of the CDR. Mr John
Fellows provides further detail in his evidence. Below I describe the
principal constraints around Aotea Station which are a mixture of
subsurface constraints and existing surface ground use constraints.
80. The design constraints include;
(a) The Orakei Main Sewer in Victoria Street which constrains the rail
alignment vertically from the south;
(b) The presence of significant number of utilities running East West
in the pavements of Wellesley and Victoria Street and also North
South under the pavements in Albert Street. It is to be
determined whether the disruption associated with utilities could
be undertaken as enabling works, but the indicative programme
assumes that they are undertaken as part of the main CRL
works;
(c) The stormwater line that impacts the running tunnels in Albert
Street described above;
(d) The Lower Albert Street retaining wall which constrains the
station walls to the East due to the presence of underpinning
piles that were used to strengthen the wall (with an additional
concrete skin) in the 1980s;
(e) A number of buildings (identified by Auckland Transport’s Built
Heritage Expert Bruce Petry) as being of heritage or character
status;
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
21
(f) The ground conditions;
(g) Access to properties on the East of Albert Street via Lower Albert
Street and at surface level;
(h) Access to the properties on the West side of Albert Street; and
(i) Traffic and pedestrian movements across Wellesley and Victoria
Streets.
81. Previously the NoR had assumed that utilities would be diverted prior to
CRL allowing a quadrant methodology at the road intersections. A
changed construction methodology from that originally described in the
ITA has been developed allowing concurrent utility diversions would
require the closure of the major intersections of Wellesley and Victoria
Streets. This facilitates a much less encumbered worksite and
programme benefits for CRL. It is also preferable from a risk
perspective in that the Aotea station top slab can be constructed
monolithically7 across the principal East West span providing structural
durability.
82. The Station requires cut and cover construction largely because of its
shallow depth, the adverse ground conditions and the width of the
station box itself (as described by John Fellows).
83. It is assumed that ‘top-down’ construction method may be used
(although bottom up construction using propping and temporary traffic
decks are considered feasible). The ‘top-down’ method is a variation of
cut and cover tunnelling, again using propped diaphragm walls or
secant/soldier pile walls through soft ground to penetrate the bedrock
below. It is used where wall deflections are particularly critical or where
the surface must be returned to its former use as soon as possible (e.g.
the busy road intersection).
84. Once the walls have been installed, construction of the station ‘roof’
can commence. The installation of the roof top slab effectively stiffens
the wall and minimises deflections. Upon completion of the roof,
7 A single concrete pour.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
22
subsequent excavation activities can be undertaken beneath the roof
slab from pre-designated access points through the roof slab.
85. These will include construction of the concourse and base slabs and
the excavation of the intervening material. It is expected that this can
be achieved with excavators in the softer soils and possibly
roadheaders in the ECBF rock.
86. In terms of a construction sequence this is envisaged to comprise the
following stages.
87. The main construction site for the Aotea Station will be established
adjacent to the entrance at Wellesley Street. The buildings at this
location will be demolished using large hydraulic excavators, say a CAT
336E or similar (200kW motor). This activity would be expected to
take around 6-12 weeks.
(a) This area will be the main worksite for Aotea station and will
remain active throughout construction of CRL. This will serve to
remove excavation spoil from the site, receive and stockpile
construction materials and provide construction facilities for
construction staff. The Worksites are envisaged to be operating
up to 24 hours a day 7 days a week depending upon the shift
pattern adopted. It is assumed for the indicative programme that
the bulk of production occurs during a six day working week;
(b) Elements stored on site and features of the site are anticipated to
include:
(i) General storage of construction materials;
(ii) Fuel storage;
(iii) Reinforcing steel storage, bending and fixing;
(iv) Bentonite and cement for grout and piled wall construction;
(v) Pile casings;
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
23
(vi) Spoil stockpiling from the excavation. However spoil will be
taken for off-site consented disposal on a daily basis;
(vii) Construction plant e.g., piling rigs, mobile cranes,
shotcreting plant, compressors etc.;
(viii) Station fitout materials and major plant;
(ix) Maintenance facilities and stores;
(x) Water treatment plant; and
(xi) Site offices and workers’ facilities.
88. The construction sequence for Aotea Station is staged around access
to the Crowne Plaza Hotel and its car park (i.e., around the existing
entrance way circled above). Wellesley St will be closed for a period of
around 12 months to enable the utility diversion, and piling activities
and construction of the roof of the station box. Whilst it is closed
access to the hotel at surface and Lower Albert St level will be from the
North.
89. The station box walls will be on the West side of the underpinned
Lower Albert St wall. This will require removal of the wall down to the
level of the existing Lower Albert St road level prior to piling. Any
existing decking planks on the Crowne Plaza side would be removed.
The ground on the West side of the wall would be removed and the wall
demolished progressively using a combination of mechanical
excavators and hydro-demolition to reduce noise to expose the existing
1200 diameter piles under the wall.
90. A steel piling deck and frame connected to the existing piles may then
be installed to enable the new 1050 diameter piles for Aotea Station
box to be installed.
91. Contiguous piled walls through the soft material at surface into bedrock
will be made. The piles are assumed to be between 15-20m long and
900-1050 thick, installed using a 65T or 90T piling rig (400-500kW
motors). Smaller diameter soldier piles maybe required for utility
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
24
services that remain in place during construction. The piling duration is
expected to be of the order of 12-16 weeks
92. Once the piles are installed installation of the roof slab can commence.
Once the station roof slab is in place this will largely separate
construction noise below from surface activities. Based on the
evidence of Mr Clark it is acceptable that Wellesley Street intersection
may be completely closed and used as a worksite for an estimated
period of approximately 12 months. Access to and from Crowne Plaza
at surface level and from the lower Albert Street service level can be
provided from Victoria Street during this period. In a similar way the
vehicle access to Skycity (car-parking and services access) from Albert
Street can be maintained.
93. Again based on the analysis undertaken by Mr Clark the Victoria Street
intersection may also be completely closed (though this cannot be done
unless the Wellesley Street intersection is functioning), and used as a
worksite. Access to Crowne Plaza Hotel and Sky City at surface level
would be from Wellesley Street. The Lower Albert Street service level
can be accessed from Wellesley Street. The period of closure of
Victoria Street intersection is expected to be longer at approximately
16-18 months given a greater extent of construction undertaken during
that phase.
94. Excavations and installation of concourse and base slabs would occur
largely beneath the station upper slab serviced from the main worksite.
The estimated duration of the civil works at Aotea Station is around four
years with a further year for fitting out of mechanical and electrical
systems and architectural finishings and system commissioning. Test
running and trial running of the new CRL link may take a further ten
months prior to opening of CRL.
95. The impacts upon the local road network have been assessed by Ian
Clark and are addressed in his evidence. It is assumed that ready
mixed concrete and shotcrete will be supplied to site. Based on the
indicative programme it is expected that vehicle movements will be a
maximum of around 150 truck movements to site per day (with
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
25
corresponding numbers returning from site) comprising of spoil
removal, material delivery peaking during major concrete pours.
TBM Running Tunnels
96. From Aotea Station through to Newton Station, via Karangahape
Station, running tunnels are envisaged to be constructed using an
earth pressure balance TBM (I describe this later in my evidence). The
length of this section is approximately 2.1km with a minimum depth to
track of 15m and a maximum depth to track of 40m.
97. There is an overall rise of approximately 45m between Aotea and the
NAL. Key considerations which have influenced the design and
alignment of the tunnels that connect the stations and the depth of the
stations are the maximum gradients for operations and the need to
provide appropriate clearance beneath the Central Motorway Junction
structure.
98. The indicative tunnel design is detailed at section 3.3 of the CDR. The
concept design for the two tunnels has been developed to meet the key
technical parameters introduced earlier in my evidence (at paragraph
34) along with the list introduced at section 2.1 of the CDR.
99. An appropriate tunnel cross section provides for the kinematic
envelope8 of the new trains currently being built for the Auckland rail
network and associated space proofing for Over Head Line Equipment
(OHLE). A non-ballasted concrete track slab is proposed largely to
reduce track maintenance requirements. In the vicinity of some
sensitive vibration sensitive receivers track isolation measures may be
necessary as described in Mr James Whitlock’s evidence.
100. Egress and emergency access is provided for on the insides of the rail
tunnels. The minimum width of the egress walkway is proposed to be
850mm and this is subject to confirmation with the New Zealand Fire
Services. Cross passages between the running tunnels are proposed
at spacings to be confirmed with the New Zealand Fire Services.
8 A kinematic envelope is the design space occupied by a rail vehicle when in motion. It is
developed from considerations of speed, rail curvature and rail cant (superelevation).
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
26
101. As stated in paragraph 88 of my evidence, the running tunnels
connecting Newton Station to Aotea Station are assumed to be
constructed with an ‘earth pressure balance’ tunnel boring machine
(TBM) with an outer diameter of around 7m. The TBM can be
described as a tunnelling ‘factory’. The key components are the
cutterhead, the working chamber (plenum chamber, a pressure
chamber also used for ‘mixing’ and conditioning the spoil as required),
the screw conveyor and the steel shield which contains the TBM
hydraulic plant, precast concrete lining erection equipment, and
construction personnel. Thrust rams bearing on pre-cast concrete
lining rings (each ring comprising several segments) force the rotating
cutter head and the associated cutting tools into the ground.
102. The characteristics of the spoil reflect both the in-situ properties of the
ground, the mechanical excavation process (including any spoil
conditioning, refer below) and the presence of groundwater. I note that
groundwater extraction will be the subject of a subsequent resource
consent process.
103. It is anticipated that the substantial majority of spoil arising from the
driven tunnels will be East Coast Bays Formation sandstone and
siltstone. I note that spoil disposal sites selection may be the subject of
a subsequent resource consent process.
104. The pre-cast segmental lining will be made of high quality durable
reinforced concrete. Joints between the pre-cast elements
incorporating durable compression gaskets would provide the tunnel
lining with a suitable level of watertightness.
105. The pre-cast segmental lining would be erected within the tail shield of
the TBM and connected with temporary bolts during construction. The
cutter head excavates at a diameter greater than that necessary for
passage of the shield and erection of the permanent works lining. The
resulting annulus between the outside of the segments and the
excavation is filled with a cementitious grout.
106. Construction of cross passages will require that the pre-cast lining is
‘broken-out’ and additional mining operations undertaken to form the
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
27
space required. The mining will likely be undertaken with track-
mounted roadheaders or hydraulic hammers for excavation. The
current indicative construction methodology therefore assumes that
cross passage openings in the segmental lining would be constructed
using steel segments which would be a similar thickness to the
concrete segments in order to fit the TBM. Also the tunnel bores are
separated a minimum of 0.5 diameters (3.5m) to maintain them within
the Vincent Street road corridor. This tunnel separation is maintained
within the road reserve adjacent Federal Street and along Vincent
Street before the tunnel separation is increased in the approaches to
Karangahape Road station. (Beyond Karangahape Road Station the
tunnels are brought closer together beneath Ian McKinnon drive before
splaying once more in the approaches to Newton Station.)
107. Experience from Project Rosedale and Project Hobson has
demonstrated the suitability of Earth Pressure Balance TBM (EPBM)
tunnelling techniques in Auckland geology with minimal environmental
effects, e.g., vibration and settlement. A larger EPBM will soon
commence tunnelling for the Waterview Connection project.
108. TBM construction sequence peak vibration and potential re-radiated
noise occurs during the excavation of the ground. The duration of this
peak vibration and noise is dependent upon the length of each pre-cast
concrete segment which is installed progressively as the tunnel is
constructed to form ‘rings’. Assuming a 1.5m long segment length,
excavation would typically take about 40 minutes per ‘shove’ but may
be up to an hour.
109. The actual tunnel production rate is a complex mix of existing physical
conditions, design and engineering constraints and human factors.
For the purposes of developing a reasonably conservative programme
it is assumed that the duration to tunnel 100m with the TBM may take
up to 2 weeks.
110. The TBM running tunnels will be accessed from the worksite at the NAL
connection (southern end of the CRL). This area will also house the
spoil handling facilities with tunnel spoil being removed using road
trucks. It is recognised that truck removal is the most likely and
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
28
practicable means of spoil removal. It will also generate the most
adverse effects and therefore has been adopted for the assessment of
the NoR.
111. The indicative site layout shows a configuration using conveyors (also
adopted for Waterview Connection). Rail locomotives could also be
used, particularly as the mined platform tunnels (refer below) provide
the opportunity for sidings to allow multiple locomotives to be used.
Some of the curve radii behind the TBM may also favour the adoption
of rail locomotives but this choice is really up to the constructor.
112. Segments for the permanent tunnel lining and the grout used to fill the
gap between the lining and the ground would also be supplied from the
NAL connection worksite (refer paragraph 133).
113. Materials and labour would be supplied to the TBM using either tracked
vehicles (with temporary invert slabs) or rail locomotives.
114. The concrete segments of the lining would be ‘pre-cast’ in a specialist
facility off-site with the segments brought to the site and stored.
115. The worksite has been configured notionally to contain suitable areas
to stockpile all of the materials necessary to support the tunnel
production with daily deliveries expected. The majority of vehicle
movements to and from the site would be expected to be associated
with off-site spoil disposal (as discussed below).
Karangahape and Newton Stations
116. My colleague Mr John Fellows will describes the station designs in
more detail in his evidence. However, I provide below a brief summary
to provide some context. The form of Karangahape Road and Newton
Station has been influenced by the surface constraints, the depth of the
alignment and the ground conditions, in particular the characteristics of
the weak rock within which the majority of CRL will be constructed.
117. At both Newton and Karangahape Road there are a number of Heritage
Buildings surrounding the stations. These buildings will experience
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
29
ground movement (settlement) as a result of CRL and the effects upon
the buildings are discussed in the evidence of Mr Craig Stevenson.
118. At Karangahape Road the platform level is around 32m from surface
and the station is designed around a vertical transportation concept
using escalators. The platform tunnels are accessed from tunnels
emanating from a central concourse which in turn is accessed from
inclined escalator shafts which connect to surface. There is a main
entrance in Beresford Square and a secondary entrance in Mercury
Lane.
119. During construction the Beresford Square entrance will support piling
and excavation operations and the shaft may also be used to access
the platform tunnels. Once the tunnelling is complete this shaft may be
used to effect the fitout of the station.
120. Building demolition is required for the Supper Club using large
hydraulic excavators, for example a CAT 336E as part of the
excavation works within the piled walls required for the entrance.
121. Contiguous piled walls are assumed through the soft material at
surface into bedrock. The piles are assumed to be around 18m long
and 900 thick installed using a 65T piling rig (400kW motor). The
duration of piling would be expected to last for around 8-12 weeks
depending upon the final depth and extent of the entrance shaft along
Beresford St. Peak noise and vibration would be expected to be
greatest whilst the piling rig is in front of the property which would
progress at an average rate of 5 linear metres per day.
122. Shaft excavation would be assumed to use a similar excavator as was
used to clear the site.
123. Depending upon the final design of the entrance a primary lining of
shotcrete and rock nails may be placed as the excavation proceeds
beneath the piles.
124. The permanent lining could be cast in lifts from the base of the shaft.
This would be supplied by ready mix concrete trucks.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
30
125. During construction the Mercury Lane entrance in addition to
construction of the shaft would be used to remove the majority of the
platform tunnel spoil (handled at the adjacent construction site).
During construction the shaft may be used to access the platform
tunnels.
126. Building demolition is required for several buildings in the area using
large hydraulic excavators, for example a CAT 336E.
127. Contiguous piled walls are assumed through the soft material at
surface into bedrock. The piles are assumed to be around 18m long
and 900 thick installed using a 65T piling rig (400kW motor). The
duration of piling would be expected to last for around 12-16 weeks.
128. Shaft excavation would be assumed to use a similar excavator as was
used to clear the site. It would be expected given the depth of the shaft
a gantry crane would be used to hoist a skip from the shaft. The skip
would discharge onto a loading platform where a front end loader would
(say CAT 938K, 130kW) be used to load haulage trucks for off-site
disposal.
129. Depending upon the final design of the entrance a primary lining of
shotcrete and rock nails may be placed as the excavation proceeds
beneath the piles.
130. The permanent lining could be cast in lifts from the base of the shaft.
This would be supplied by ready mix concrete trucks.
131. At Newton Station the platform depth is about 40m from surface. Given
the transit times to surface, and also the increased spatial requirements
arising from escalator concepts, the design has assumed that lifts will
be used instead of escalators. From the central lift concourse the
platform tunnels are accessed from connecting tunnels.
132. The location of Newton Station has been designed to avoid the
Watercare reservoir located to the east of Symonds Street, and the
alignment was moved as far to the west as other geometric constraints
would allow and still achieve the Mt Eden connections described below.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
31
133. The platform tunnels for both stations are around 12m in diameter
which is spatially adequate for the trackway (the trains’ kinematic
envelope) all services (overhead and to the sides) and the required
platform width.
134. There is not a lot of experience in large diameter tunnel excavations in
Auckland’s geology, and the largest constructed to date is around 8m.
There are of course larger tunnels within New Zealand, such as the
Mt Victoria Tunnel, the Kaimai Tunnel, and the Terrace Tunnels and
more recently the Johnstones Hill Tunnels - all in different geology.
135. The ECBF forms the bedrock of Auckland which is an intrinsically
complex sedimentary rock. The intrinsic complexity arises from the
depositional environment of the rock, which was often chaotic. When
excavated the rock separates along bedding planes but also along
joints shears and faults which are present to a greater or lesser degree.
136. It is a weak rock meaning that it has a compressive strength typically
an order of magnitude (ten times less than) typical concrete. However,
given the bedding plane discontinuities and other potential separation
planes from faults and joints etc., it has all the complexities of stronger
rocks, i.e., that blocks can fall out under gravity which presents health
and safety risks to miners.
137. From my experience overseas with caverns (up to 25m in diameter) I
have experienced the difficulties of constructing larger diameter tunnels
when the ground strength is low, as is the case here. Smaller diameter
tunnels are simpler to construct in terms of staging, and are less risky
because the demands placed upon the ground are reduced.
Minimising risk is a key driver behind the reduced size of the platform
tunnels of the Concept Design as compared to the APB&B Concept
Design.
138. The ECBF characteristics also influence the separation distance
between tunnels, known as the pillar width, i.e. the pillar of ground
remaining between tunnels.
139. In programme terms, the platform tunnels are scheduled to be
completed (in terms of temporary lining at least) prior to the TBM
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
32
arrival. This avoids the risks inherent in breaking out temporary linings
and enlarging the tunnels from the smaller TBM diameter circa 7m to
the platform tunnel size circa 12m. Again I have experience of both
methods and confirm that the adopted methodology is superior from a
safety in design perspective.
140. There are two shafts for each station at Karangahape Road and
Newton station, comprising the main entrance shaft and a secondary
egress shaft. The secondary shaft is provided for fire life safety
purposes but also to discharge vitiated air from the station. (Air quality
effects are discussed in the evidence of Camilla Borger). Where
practicable, underground stations have ventilation plants that discharge
at surface at both ends. (These design aspects are described by John
Fellows in his evidence).
141. Labour, material and spoil will be required to be supplied and removed
from each shaft location.
142. The Dundonald St shaft when operational will be a secondary egress
shaft and plant room area for the station. During construction the shaft
may be used to access the platform tunnels but these may also be
accessed from the Mt Eden side which may be preferable given the
larger scale of the worksite and its ability to manage greater traffic
movements associated with spoil.
143. Excavation plant and shaft excavation concepts are similar to that
described for Karangahape Station above.
144. It is expected that ready batched concrete and shotcrete will be brought
to site.
145. It has been assumed in the indicative methodology for Karangahape
Road Station that construction access to the platform tunnels will be
from the secondary shaft in Mercury Lane, which will be configured to
handle the majority of the tunnel spoil. (Refer Drawing 152 in
Appendix A). This enables earlier access to the UP main platform
tunnel and therefore is likely to provide more construction programme
flexibility. It is noted that even with reduced widths the platform tunnel
excavations are significant undertakings requiring careful construction
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
33
management. An indicative worksite layout is attached in Appendix A.
The site is configured around a gantry crane and skip hoist supplying a
spoil handling yard which in turn supplies dump trucks that remove
spoil from site.
146. At Newton Station the Dundonald Street shaft (refer Drawing 201 in
Appendix A) is constrained in terms of road access. The main shaft
excavation will benefit from the carpark (which I understand is
controlled by Auckland Transport) adjacent to the Watercare reservoirs
in terms of extended construction laydown and spoil handling areas.
147. Mr Clark has assessed the traffic effects of this for each shaft location
in his evidence but initial estimates are that both station locations may
at peak experience truck movements of around 100 trucks per day.
148. The Worksites are envisaged to be operating up to 24 hours a day 7
days a week. It is assumed for the indicative programme that the bulk
of production occurs during a six day working week.
149. Elements stored on site and features of the site are anticipated to
include:
(a) General storage of construction materials;
(b) Fuel storage;
(c) Reinforcing steel storage, bending and fixing;
(d) Bentonite and cement for grout and piled wall construction;
(e) Pile casings;
(f) Station fitout materials and major plant;
(g) Spoil stockpiling from the excavation. However spoil will be taken
for off-site consented disposal on a daily basis;
(h) Construction plant e.g., piling rigs, mobile cranes, shotcreting
plant, compressors etc.;
(i) Water treatment plant;
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
34
(j) Maintenance facilities and stores; and
(k) Site offices and workers’ facilities.
150. The shaft walls will be supported in a similar manner to the cut and
cover tunnels excavations described above, i.e., using piles or
diaphragm wall panels. The walls may either be for the full depth of the
shaft or sufficiently deep into rock to enable a safe working
environment during excavation. Previous projects in Auckland (Hobson
and Rosedale) for example have a collar of piles through the soft
overlying sediments with the rock walls supported with rockbolts and
mesh down to the required level. These shafts have extended to
similar depths. Ultimately shaft walls will be made sufficiently
watertight by placing internal reinforced concrete structures with
external waterproofing membranes to minimise impacts upon
maintenance during operation.
151. The platform tunnels may be excavated using hydraulic excavation
plant and the ground stabilised as the excavation proceeds using
rockbolts and or shotcrete installed close to the shaft or tunnel face.
The 12m diameter tunnels may require top headings and benching as
opposed to a full face excavation. This is to suit the reach of
excavation plant and also as the heading operation is the most
important phase of tunnel construction, i.e., when the tunnel heading is
stable, the bench can be removed relatively easily and quickly.
152. Permanent support for the platform tunnels may comprise a cast in-situ
reinforced concrete lining with a waterproofing membrane erected
before concrete placement that would enable the structures to be
designed to resist water ingress.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
35
Southern Tunnel Portals and NAL Connection
153. From Newton Station the CRL rail geometry is particularly constrained
with tight horizontal curves and steep vertical gradients and little
flexibility given the need to connect to the existing NAL infrastructure.
The existing NAL rail infrastructure needs modification in terms of re-
grading (raising and lowering) of rail track and grade separation of two
local roads Normanby Road and Porters Avenue.
154. The two lines (the UP and DOWN CRL mainlines, or ‘mains’, the
railtracks) need to split to provide east and west facing links. This
requires ‘turnouts’ trackwork which widen the rail envelope (refer
above) and an underground ‘flat’ crossover junction.
155. The existing NAL tracks will be repositioned to allow the CRL tracks to
rise up between the NAL tracks. There will be temporary track
alignments (and some temporary closures) to allow for operation of the
NAL during construction of the permanent structures.
156. The topography is at its highest point around Newton Station and drops
off sharply to the South in the vicinity of the NAL where the topography
is gentler. The landforms are of course heavily influenced by the
underlying geology described later.
157. A combination of mined tunnels, shafts, cut and cover tunnels and
trenches are required here. There are also extensive surface works
required particularly at the Southern extent of the scheme including
excavations and retaining walls, service diversions, local roadworks
and road bridge modifications (Mt Eden) and road bridge installation for
road rail grade separation (Normanby Road and Porters Avenue) and
footbridge installation (Ngahura Street)
158. In 2008 Project Clearwater installed a large diameter (circa 2m
diameter) stormwater main connecting to a shaft in Flower Street and
running down Nikau Street to Ruru Street. The alignment of this
stormwater utility (installed using pipejacking equipment) clashes at rail
level across both CRL mainlines requiring diversion. The presence of
the shaft in Flower Street also complicates tunnelling for the UP main in
this area.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
36
159. At this location rockhead drops away sharply to the south (mirroring the
topography) and weathered rocks and alluvium come closer to the top
of the CRL tunnels which increases the need for tunnel temporary
supports and the overall risks of tunnelling.
160. By the junction with Nikau Street and Flower Street the CRL UP main
tunnel would need to be around 14m diameter. This is a relatively large
diameter for a weak rock such as the East Coast Bay Formation
requiring careful design and construction monitoring. As the tracks
diverge to the South the tunnel diameters would increase accordingly
and the combination of lack of ground cover and weakening ground
above makes mined tunnelling much more difficult.
161. These adverse geological conditions are risk factors to the CRL project
and in combination with the large tunnel diameters required has
influenced the preferred choice for the NoR of cut and cover methods in
this area.
162. The complexity and extent of the rail geometry required and the shallow
and variable ground cover has driven the Concept Design towards cut
and cover tunnels and therefore the need to acquire the properties at
this location. The final position of the mined tunnel cut and cover
portals (i.e., where the tunnel headwall sits in the temporary
construction state) is a matter of further ground investigation, more
detailed design, cost and risk analysis.
163. The UP main West link and the DOWN main East link cross each other
in the centre of the block of properties bounded by Ruru, Nikau,
Shaddock Street and Flower Street. This flat junction would require its
own shaft around 15m deep, linked either side with cut and cover
tunnels sized for individual rail tunnels.
164. Around Shaddock and Ruru Street the geology at surface becomes
basalt from Mt Eden’s volcano. Aurecon’s ground investigation team,
have interpreted, based on ground investigations undertaken to date for
CRL and elsewhere in Auckland, that basalt flows have infilled old
valleys and so may extend beneath the excavations required for CRL in
this area. (Refer Figure 2 below)
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
37
165. Basalt is a hard rock and can be broken mechanically. However, in my
experience of blasting operations overseas it is a much more effective
method in terms of time of excavation than say hydraulic breakers.
Figure 2 Interpreted extent of basalt around Mt Eden Station
166. Trench excavation in basalt at the NAL may be up to 100m long, 10-
12m deep and 7m wide at the base. Blasting would involve the
operation of drilling rigs to drill blast holes. Decked charges with
instantaneous charge weight of between 1-3kg of bulk emulsion
explosive may be trialed to develop site specific attenuation constants.
One of the reasons to adopt blasting in my opinion is that effective
blasting may reduce the period of disturbance (in comparison with
multiple rockbreakers) with very limited risks.
167. Blasting may take advantage of the strength of the basalt to blast in
vertical panels. Fragmentation, i.e., the size of the rock fragments
resulting from the blast may be a secondary consideration to creating
the trench excavations through the basalt flows. In any event it is
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
38
anticipated that post blasting, large hydraulic breakers and mechanical
excavators will be required to remove the broken basalt. This will be up
to 100T with 400kW motors.
168. I will describe the surface works and staging for CRL connection to the
NAL in two halves, East and West. However, it is worth noting that by
the time CRL will be constructed the NAL will be an electrified railway.
Therefore, not only does construction have to consider the safety risks
associated with physical clashes with running trains but also the need
to avoid electrical overhead lines and the risks of construction plant
striking those overhead lines.
169. For the East facing links (EFL) the NAL is assumed to be staged in
three phases. However, before construction begins site enabling works
will be required. These include:
(a) Erection of construction site fences along the rail corridor;
(b) Service protection or diversion works at Mount Eden Road,
Normanby Road and along Boston Road; and
(c) Clearance and levelling of the site along the north side of the rail
corridor.
170. Phase 1 NAL slewed to North to enable installation of retaining walls
and track lowering to the South. Normanby Road would be closed for a
period of around 6 months during this phase as it is not possible to
maintain a level crossing given that the NAL must be lowered around
2m. Construction of the road over rail bridge (grade separation)
benefits from the lowering of the NAL and the necessary modifications
to the local road connections required to raise the road level of the
order of 2m are reduced.
171. Mt Eden Road would not be modified by CRL construction works during
the period that Normanby Road is closed. The traffic effects of this
have been addressed by Mr Clark in his evidence.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
39
172. It is worth noting that Normanby Road level crossing has a high priority
for grade separation on safety grounds irrespective of CRL based on
assessments by Auckland Transport and KiwiRail.
173. Phase 2 NAL moved back to the South to the newly re-graded
alignment to enable excavations and retaining structures for CRL East
facing links. The NAL DOWN main has a temporary alignment at this
stage. The benefit of this staging step is that the constructor has a
worksite discrete from the electrified rail corridor adjacent to the South
and may construct the walls and excavations necessary for CRL to the
North.
174. During this phase modifications to the northern abutment of Mt Eden
Bridge can be made which will involve piling adjacent to the bridge to
replace existing ground anchors, the staged removal of the ground
anchors and the installation of the CRL cut and cover tunnels.
175. Phase 3 The NAL Down main is moved onto to its permanent
alignment above the CRL tracks. Excavation over a 100m stretch of
track will be required requiring the temporary closure of the NAL at the
eastern extent of the project for the section of line that merges the NAL
and CRL to tie-in with existing grades. It would be expected that this
would be undertaken during a Christmas ‘block of line’ over a period of
a few weeks.
176. For the West Facing Links the grade separation of Porters Avenue
requires the lowering of the both NAL mainlines and the raising of
Porters avenue. In the indicative methodology this requires two
temporary alignments for the NAL DOWN main and one temporary
alignment for the CRL UP main and the closure of Porters Avenue for
between 2 and 3 years. Before the main construction begins site
enabling works will be required. These include:
(a) Erection of construction site fences along the rail corridor;
(b) Service protection or diversion works at Porters Avenue, Fenton
Street and Haultain Street;
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
40
(c) Clearance and levelling of the site along both sides of the rail
corridor; and
(d) Development of temporary property accesses along Fenton
Street, Haultain Street and Porters Avenue.
177. Phase 1 In the first stage the balconies on the South side of 3 Ngahura
Street would need to be removed to construct the outer southern
retained walls required to lower the NAL. The outer walls that enable
NAL lowering and the Northern inner wall and the bridging structures
which enable the NAL DOWN main to pass over the CRL west facing
links and the inner southern walls for the CRL can be constructed.
Porters Avenue is closed to traffic. A series of weekend block of line
closures are likely to be required as the piles for the inner wall gets
closer to the NAL alignment.
178. Phase 2 In the second stage the tracks are slewed to the North and
South. The northern inner walls can be constructed and excavation
required for CRL within the rail corridor can be undertaken with access
from the CRL cut and cover tunnels.
179. Phase 3 The NAL up main is placed on its permanent alignment within
the inner and outer retaining walls.
180. Phase 4. In the fourth and final stage excavation to enable the NAL
DOWN mains to be placed on the lowered permanent alignment a
Christmas period block of line will be necessary to minimise disruption.
The reinstatement of Fenton and Haultain Streets can occur and the
road over railbridge at Porters Avenue can also be re-instated.
181. The temporary construction site at the NAL connection between Ruru
Street and Ngahura Street will likely be the main work site for the TBM
assembly and launch and also serve to provide the stockpiling for rail
fitout. (Refer Drawing 220 in Appendix A).
182. It will house the main site offices (likely to be a number of offices) and
associated vehicle parking. It may also be used to store large pre-cast
or fabricated elements which may not be able to be stored at the
individual site storage areas due to size restraints.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
41
183. The number of truck movements at the worksite are likely to be
dominated by the excavations for the cut and cover tunnels. Including
the TBM spoil activities (refer below) and assuming that these coincide
with the cut and cover activities this may be up to 400 truck movements
exiting the site per day. It is noted that this estimate has several
variables, i.e., the excavation production rate, the number of active
excavation fronts, the bulking factor (i.e., how much greater in volume
the excavated spoil is after excavation) and the capacity of the trucks
used to remove the spoil.
184. It is anticipated that TBM-excavated material will be disposed off site
and allowing for the bulking which happens when ground is excavated
(a bulking factor of 1.8) the TBM tunnels may generate up to
210,000m3 of spoil.
185. For the purposes of illustrating the sensitivity of programme
assumptions in relation to truck movements If the TBM achieves a peak
advance rate of 10 rings per shift, 30m per day for a week, (180m a
week) this would result in the need to remove around 11,500m3 per
week if all spoil were removed from site. In practise it is common to
stockpile spoil on site unless continuous truck access can be provided.
However, assuming spoil trucks operate for 12 hours per day and truck
and trailer units can carry up to 15m3 of spoil per load, this would
require around 10-12 truck trips per hour in each direction.
186. All trucks would enter and leave the worksite via dedicated and secure
access points. From the worksite, the route to the disposal site will
depend on the most appropriate location to receive this material at the
time when construction commences. Mr Clark discusses this in his
evidence.
187. The Worksite is envisaged to be operable up to 24 hours a day 7 days
a week (although tunnelling production is assumed to be over 11 shifts
and 6 days a week) and up to 20 hours per day. A 20 hour per day
TBM operation accounts for two 10 hour work shifts and allows for
maintenance to be carried out in the remaining 4 hours if required.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
42
188. The segments would be constructed off-site in an existing pre-cast
concrete facility and then transported to site to be stockpiled.
189. Elements stored on site and features of the site are anticipated to
include:
(a) General storage of construction materials;
(b) Fuel storage;
(c) Reinforcing steel storage, bending and fixing;
(d) Bentonite and cement for grout and piled wall construction;
(e) Pile casings;
(f) Spoil stockpiling from the excavation. However spoil will be taken
for off-site consented disposal on a daily basis;
(g) Construction plant e.g., piling rigs, mobile cranes, shotcreting
plant, compressors etc.;
(h) Precast concrete TBM lining segments;
(i) Rail fitout materials;
(j) Maintenance facilities and stores; and
(k) Site offices and workers’ facilities.
The Indicative Construction Programme
190. As for any construction programme it is important to understand that
not all construction activities can overlap, i.e., the commencement of
some activities in a construction programme may depend upon the
completion of others and delays in one activity may therefore introduce
start-up delays in subsequent activities.
191. In general, the underground civil construction precedes mechanical and
electrical systems installation which precedes commissioning and
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
43
testing of the rail safety systems which then enable the railway to
commence operation.
192. Briefly, the indicative construction methodology anticipates a 5 to 6
year construction timeframe and I consider this to be a reasonable and
feasible programme for the works anticipated. I consider the key
features and interdependencies of the programme to include:
(a) Preparation of the Construction Environmental Management Plan
(CEMP);
(b) Utility replacements where necessary and diversions as enabling
works (This may precede the main construction works for CRL
so as to remove programme risks);
(c) Mobilisation of construction staff and plant;
(d) Preparation of worksites including property demolition particularly
at Mt Eden where the logistics to support the linear TBM
tunnelling operation are to be established;
(e) Shaft excavation and support rates for mining platform tunnels at
Newton and Karangahape Road stations;
(f) Sequencing of Mt Eden cut and cover construction, i.e., wall
installation sequence and excavation rates in basalt;
(g) Tunnelling production rates (sequential excavation and support)
mined stations. It is important that the ‘up-main’ platform tunnel
in Newton Station be completed prior to arrival of the TBM;
(h) TBM delivery and commissioning (around 18 months) during
which time the NAL worksite will be focussed on preparing the
logistical support for the TBM and construction of the UP MAIN
platform tunnel in Newton Station. The TBM tunnelling when in
production is in relatively short lengths of less than 1km between
stations and around 3.2km in total;
(i) Sequencing of Albert Street intersections and construction of
Aotea Station, i.e., wall installation sequence and excavation
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
44
rates. Key considerations have included the diversion of utilities
and management of traffic impacts during construction on the
local road network, maintaining appropriate public transport
service levels, providing vehicular and pedestrian access to
buildings in the CBD (refer to the evidence of Mr Ian Clark for a
full understanding of the impacts of construction on transport);
(j) Station and rail systems fit out and commissioning of mechanical
and electrical systems; and
(k) Systems integration and rail test running.
193. The concept design anticipates that the longest duration civil
construction activity is Aotea Station. In simple terms this means that it
is expected that the overall programme for opening CRL would depend
upon completion of the civil works within Aotea Station.
194. The main points affecting the indicative construction methodology in
relation to the Albert Street and Aotea Station area (refer diagram) are:
(a) The complete closure of Wellesley Street (11-12 months)
undertaken first and reinstated;
(b) The complete closure of Victoria Street (16-18 months)
undertaken second and re-instated;
(c) A full or partial closure of Customs Street for a period of
approximately 6-9 months (undertaken last); and
(d) The remaining section of running tunnel within Albert Street is
undertaken concurrently with the Wellesley and Victoria Street
Intersection works (24 months).
195. Overall, I consider the concept design and the indicative construction
methodology are reasonably and appropriately conservative.
Response to submissions
196. I have reviewed all submissions that relate to the CRL Concept Design,
in particular those matters that relate to the design and construction of
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
45
the CRL. I have grouped these submissions according to the concerns
raised, and address each concern in the sub-headings below. Under
each sub-heading I also indicate which submitters raised that concern.
197. In response to submissions, there are some minor design clarifications
and methodology modifications to those indicated by the CDR that are
feasible within the NoR ‘envelope’ of land requirement and effects as
described below.
198. The majority of concerns arise from property access and proximity
effects from construction. There are sixteen submissions that I have
specifically addressed9.
Disruption Around Britomart Station
199. I have met representatives of the Tenham Body Corporate (116)who
were concerned about the construction impacts and in particular as it
pertains to my evidence the duration of closure of Tyler St and access
generally to their property. The indicative impacts are outlined in
paragraph 46 above whilst pedestrian access will be possible at all
times vehicle access will be disrupted temporarily.
Cut and cover construction within Albert Street
200. Foodstuffs (118) is concerned about the potential disruption to its store
in Queen Street which is serviced from Albert Street. It is also
concerned about the East/West movement of pedestrians at Swanson
Street. The Albert Street methodology was developed specifically to
maintain serviceable access to all the properties adjoining Albert Street.
A specific consideration was the separation of the majority construction
traffic movements from the general traffic in the service lanes within
Albert Street. I describe this in paragraph 63 above. Mr Clark in his
evidence describes how traffic flows will be affected by the indicative
construction methodology. As for East/West pedestrian movements 9 Submissions: PAL Properties (28) Tenham Body Corporate (116) Foodstuffs (118) Ministry
of Justice (122) Stamford Plaza (71) Chapman Tripp (96) Quay West Suites (95) MediaWorks
(79) Department of Corrections (98) Stamford Residences (70) Precinct Properties NZ Ltd (81)
Auckland Methodist Church (219) Sky City Entertainment Group (88) East Family Trust (249)
James KirkPatrick Ltd (236) New Zealand Heritage Places Trust (72) Samson (89).
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
46
across Albert Street this may be provided using pedestrian walkways
across the cut and cover trench with due consideration for security and
safety measures to protect the general public from the worksite and
vice versa.
201. In addition to the concerns expressed by Foodstuffs above (118) the
Ministry of Justice (MoJ) (122) is concerned about potential disruption
to services supply to the building. I describe an indicative methodology
in paragraph 58 that will generally enable continuity of supply.
However, I note there are risks associated with this which are
inevitable, but are similar to any utility works which may occur in a CBD
location at any time. I expect that most of the utility diversions will be
undertaken prior to the main civil works mobilising but some service
diversions, particularly where only minor diversions are practicable,
may need to be concurrent. Throughout all works in and around live
services industry standard risk management methods would be
developed and applied involving the utility providers i.e., service
identification and carefully controlled safe methods of work as
described in the CEMP.
202. I met Ministry of Justice representatives with other CRL colleagues and
their main concerns expressed were associated with potential access
disruptions but also noise and vibration effects upon Court activities.
Mr Whitlock and Mr Fitizgarld address these effects in their evidence.
203. Stamford Plaza and Residences (70 and 71) have similar concerns as
Foodstuffs but wish to put restrictions upon construction traffic
movements. As described in the response to Foodstuffs it is envisaged
that the majority of construction traffic movements (those for the bulk of
the earthworks removal and backfilling) will occur within the trench and
separated from the general traffic within Albert Street services lanes,
i.e., from Lower Albert Street, or from the Downtown shopping centre
site.
204. Quay West (95) and Chapman Tripp (96) are also concerned about
access restrictions for vehicles and pedestrians. The indicative
methodology described between paragraphs 50 to 64 above provides
for access to Mills Lane from the southbound service lane adjacent to
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
47
the CRL works. Traffic from Mills lane may join Albert Street from
Swanson Street but may for a time as discussed in paragraphs 68 -74
above need to be diverted into Queen Street via Wyndham Street when
North-South traffic flows are prevented by the closure of Victoria Street.
East West pedestrian movements at Swanson Street can be
accommodated by providing a pedestrian walkway as described in
paragraph 143 a) i) above.
205. Quay West is concerned regarding construction site provisions. The
intentions for construction sites have been clarified in paragraph 63
above.
206. Chapman Tripp seeks restrictions on construction traffic on Swanson
Street, Federal Street and Wolfe Street. The outline methodology
above has been discussed with Chapman Tripp in terms of worksites at
either end of Albert Street with concentrations of construction traffic at
these ends. Traffic matters are addressed in Mr Clark’s evidence.
207. I have met representatives of James Kirkpatrick Ltd (236) and
discussed their submission with them. Their property is close to the
Victoria Street intersection. There are several options to provide
continuous access to their site during construction. Another item of
their submission discussed was the potential for loss of support, i.e.,
adverse effects upon their building from adjacent CRL construction.
The CRL works in Albert Street (and elsewhere), in my opinion are no
different to any CBD development where deep basement excavations
are required. The existing building owner is entitled to a right of
support and the designer and constructor are liable for repairs for any
damage should that be observed to occur. This highlights the need for
pre-construction building condition assessments and design and
construction monitoring that is sensitive to the building condition.
(Building vulnerability is covered in more detail by Mr Stevenson.)
208. I have met representatives of SkyCity (88) and discussed their
submission with them. They are generally supportive of CRL but are
concerned with disruption to their business.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
48
209. As described in paragraph 68-74 above and in the evidence of Mr
Clark, access to their staff car park and service entrance on Albert
Street. can be provided during construction. Their further input to the
process will occur via the CEMP and communications plan process.
210. They also raised concerns about construction noise and vibration which
is addressed by the evidence of Messrs. Whitlock and Fitzgerald.
211. Skycity in discussing their submission mentioned a desire to link their
operation with CRL for events that occur particularly at weekends given
limited mode choice for patrons (limited PT links, taxis and of course
cars). Connections to the concourse level in Albert Street are possible
(with due regard for operational security) given the flexibility of the cut
and cover method of construction.
212. The aspects of the Precinct (81) submission that are covered by my
evidence include construction staging, construction methods and
proximity to construction sites.
213. Precinct is concerned about the negative effects within the CBD of
using the Downtown site as a worksite for the 5-6 years period of CRL
construction. This site and its criticality to CRL construction has been
recognised since 2008 when a collaborative alignment was developed
between Kiwirail/ARTA and the previous owners of the site (Westfield).
I have already stated above that CRL will need to demolish the
Downtown shopping centre. However, the intentions and timing of the
oversite redevelopment (which itself may take several years to
construct) remain unclear.
214. Precinct is also concerned about the effects of construction in Albert
Street, and specifically asks that TBMs in Albert Street be considered
as an alternative for the Albert Street cut and cover methodology. The
construction programme described above anticipates the use of an
EPBM to excavate the ECBF rock serviced from a construction
worksite at Mt Eden. This type of tunnelling machine would not be
suitable to remove the Albert Street stormwater line, as demolition of
the line would likely repeatedly tear the belt conveyors used to
transport spoil behind the TBM cutterhead stopping the TBM advance.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
49
215. Alternative TBM alignments that avoid the stormwater line are feasible
but have inferior geometry and would be extremely close to the existing
line and any new diverted line. In terms of the hierarchy of Design
objectives we have placed a high importance upon rail geometry in
order to realise the benefits over the 100 year Design life and minimise
maintenance impacts.
216. If the Downtown site were unavailable (due to for example the
redevelopment of the Downtown site incorporating elements of CRL,
such alternative alignments would require the use of Lower Albert
Street as a TBM construction site to avoid complicating the critical path
activities of Aotea Station. This would be an extremely constrained
site.
217. It is far from clear at this time that such alternatives offer significant or
indeed any advantages in terms of construction costs and risks. I note
that any tunnelled alignments will be of limited extent within Albert
Street and the major Albert Street intersections (Customs, Victoria and
Wellesley) would remain as cut and cover construction and therefore it
may be expected that the resulting impacts upon utilities and traffic
would also largely remain. The NoR Process requires a reasonable yet
robust methodology given the inevitable uncertainty which surrounds a
design in its early stages of development. During my career I have
assessed both methods of construction on a number of occasions (cut
and cover and driven tunnels) and have strongly advocated driven
tunnel methods where the advantages have been clear (good
examples being the Waterview Connection and the Auckland Harbour
Crossing). However, given the CBD context and the relatively shallow
depth of the cut and cover tunnels and given the extent of the cut and
cover works in Albert St for Aotea Station, the benefits are highly
doubtful to me. Tunnelling may introduce further and greater risks to
construction which may prove to be unacceptable to Auckland
Transport, the constructor and their insurers given the engineering
certainty provided by the cut and cover method proposed.
218. However, the above assessment is not intended to imply that there is
complete ‘closure’ of the constructability options. It is stressed that the
actual ‘means and methods’ and durations of construction adopted may
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
50
change to suit the developing CRL design and the skills experience and
capability of the constructor and the ability for the construction team
including AT and stakeholders to manage adverse effects.
219. I have met representatives of New Zealand Heritage Places Trust and
discussed their submission with them as it pertains to the Bluestone
Wall in Albert Street. They are generally supportive of CRL but are
concerned about potential effects upon the wall. In outlining the
indicative methodology it was agreed that in order to achieve the best
outcome for the wall a collaborative process to develop common
understanding of the heritage and engineering constraints, issues and
risks arising will be undertaken. This process will examine the benefits
and disbenefits of a range of options that are possible in order to
develop an optimum methodology to ensure the best outcome for the
wall during construction.
220. I have met representatives of Samson (89) and discussed their
submission with them. They are generally supportive of CRL but are
concerned with disruption to their tenants’ businesses around
Karangahape Road and Newton Station. A more detailed appraisal of
the vehicle access measures will need to be developed across the
Beresford Street worksite but it is expected that vehicle access to their
properties may remain.
(a) Samson’s other major concern is the NoR 2 and supporting
information does not provide sufficient certainty as to the
shallowest depth of the NoR 2 substrata designation. Samson
argues will have adverse impacts on the current profitability and
future development potential of its properties. Which, Samson
would like to be financially compensated for by Auckland
Transport. Samson raised concerns over
(b) (3.6a) NoR 4 “ although labelled sub-strata”, will in fact relate to
surface land and sub-strata below the surface land, to the
maximum depth of NoR2
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
51
(c) (3.6b) “there will be no NoR 3 type strata or buffer designation in
relation to land affected by NoR 4 alone or in combination in with
NoR2".
(d) Samson states in (4.12) the CRL NoR is not clear about the
nominated distance; “is it five meters or is another depth, or
varies according to specific circumstances of the land in
question”.
(e) Samson states in (4.14) that five meters is about 1.5 levels of
basement for a commercial building, some buildings have
basements that exceed 20 or more meters in depth eg: Ironbark
Building 150 Karangahape Road.
(f) (4.18) In Part 4 of the NoR, Samson stipulates the “sub strata
layer extends from the surface to at or below the NoR2 sub-strata
layers- in this layer will contan the tunnel and Karangahape
Station”
(g) In (4.19) Samson argues that there appears to be no NoR 3 type
“strata or buffer designation proposed under this private land and
will not have a buffer layer between the surface and the sub
strata layer”. That will impact on i’s future development potential
for the site.
221. I confirm that the 5m depth below natural ground level was defined as
part of the NoR process was established to enable small scale
construction above the CRL subsurface structures. Even so certain
works being undertaken within this 5m zone (i.e. heavy compaction)
may cause an adverse effect further underground and possibly onto
CRL subsurface structures. The nature of the works proposed would
therefore need to be considered by AT on a case by case basis.
222. Beneath this 5m zone incursion from more significant developments
maybe allowable subject to detailed assessment of the proposed
development and consideration of the effects upon the CRL subsurface
structures.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
52
223. Similar overseas rail tunnel projects establish conservative loading
controls to:
(a) Control investigation and construction activities (loading and
unloading) depending on tunnel depth and tunnel design.
(b) Facilitate negotiation and approval by the tunnel owner, with
developers required to substantiate and gain approval for any
ground loading or unloading proposals.
224. It will be necessary to consider the following scenario’s
(a) construction of the CRL prior to any adjacent development and
what constraints (if any) the presence of CRL structures may
present to adjacent land developers, and
(b) construction of developments prior to construction of the CRL.
225. The following principles arise:
(a) Development that occurs prior to tunnel construction must not
place physical obstacles (such as foundations) in the path of the
future tunnel nor should any subsurface structures constructed
disturb the ground to a degree whereby they introduce
construction risks. (It is assumed that new developments,
because of building code compliance requirements are
reasonably robust with respect to the effects of adjacent
tunnelling).
(b) Development that occurs after the tunnel has been constructed
should not damage the tunnels or reduce their durability, either by
direct contact, or by inducing deformations.
226. For future development more than 5 metres below Natural Ground
Level, the detailed interaction between future buildings or structures
and their potential impact upon CRL would need to be reviewed by AT.
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
53
227. The loading of future buildings or structures imposed on the tunnel will
vary depending on the following:
(a) Building height, size, mass and proximity to the tunnel;
(b) Foundation design of the proposed development;
(c) Geotechnical conditions supporting the building and surrounding
the tunnel; and
(d) Separation between the tunnel and the proposed foundations
228. The objective will be to obtain building foundations, designed to keep
loading and stress changes on the tunnels to a minimum. The selection
of foundation type by a building designer depends on the loads
imposed by the proposed development and subsurface ground
conditions. Generally, the concentration of applied foundation stresses
increases with the following foundation types:
(a) Raft slab foundations – provide optimum distribution of building
loads
(b) Pad or spread footings – offer good control of load distribution
(c) Piled foundations below 5 metres – may yield concentrated
loading that requires special consideration
229. The Department of Corrections (DoC) (98) are very concerned about
secure access to the prison using Lauder Road. The CDR suggested
that a temporary level crossing could be re-instated to the East of the
existing Normanby Road crossing using DoC land. We have met
representatives of DoC and explained that this is not possible given
that the NAL at this location will need to be lowered by around 4m and
it will be necessary to close Normanby Road as described above. The
raising of the road by approximately 2m above the CRL and NAL tracks
will require modifications to access to various adjoining properties
including the Dilworth Trust and the Tram Lease site. It is noted that
the Normanby Road crossing has rated very highly in the list of
priorities (on safety grounds) for road/rail grade separation in recent
work undertaken by Auckland Transport. It is re-iterated that CRL will
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
54
reduce the scale of impacts upon the local road network because of the
track lowering (approximately 4m) required by the CRL geometry.
230. The final configuration of the revised road layout will need to be
developed in conjunction with these landowners and Council. Mr Clark
will address the local road impacts in his evidence.
231. The main concern of PAL properties (28) is that the rail alignment is
directly under Eclipse apartments and not road reserve. PAL
properties suggests that inadequate consideration of alternatives has
occurred. I confirm that it is possible to increase the plan offset
distance to the Eclipse apartments without significantly affecting the
Karangahape Station platform position. The reductions in
environmental effects will be discussed by Craig Stevenson.
232. The principal concern in the Mediaworks (79) submission is
construction and operational vibration which is addressed by the
evidence of Mr Whitlock and Mr Matthew Harrison of SLR. I can
comment on vibrations arising through construction during construction
blasting as I have extensive experience of preparing blast risk
assessments for construction projects in Hong Kong, Dublin and the
United States in sensitive locations proximal to sensitive receivers such
as residences, offices and rail operational control rooms and
associated vibration sensitive equipment and am familiar with the
standards that may be used to both predict vibration and limit the
effects of vibration to reasonable levels. I also have practical
experience of mitigation techniques to limit the adverse effects of
blasting such as vibration and air overpressure and the derivation of
site specific blasting attenuation constants.
233. Since lodgement of the NoR further ground investigations have been
completed by Auckland Transport which have defined extensive basalt
flows at Mt Eden. The best practicable option to remove the basalt
(refer figure 1 above) is blasting.
234. It is customary in Auckland to use the German Standard DIN 4150 for
the assessment of blasting effects on buildings or structures. This is a
very conservative standard in comparison to British Standards, the
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
55
United States Bureau of Mines guidance and the local standards
developed in Hong Kong by the various authorities there, including the
Mass Transit Railway Corporation and the Hong Kong Mines
Department.
235. The basalt excavation at the NAL may be up 100m long, 10-12m deep
and 7m wide at the base and so this is a significant amount of basalt to
excavate using mechanical methods such as hydraulic breakers.
236. Using the blast attenuation constants of Australian Standard AS 2187:2
and assuming that a peak vibration level recorded by Marshall Day
within the TV3 studios of 0.9mm/s is an acceptable limit (as it may
reflect daily ambient conditions in the vicinity of the studio) this should
enable reasonable trials for blasting to be undertaken from the southern
‘dive’ structures required for the West facing links of CRL to the NAL
some 100m from the TV3 building (sensitive receivers all around the
site would of course be considered).
237. It is noted also that turnout tunnels of approximately 15m diameter are
required beneath the TV3 building requiring the use of roadheaders.
The adverse effect of these semi-continuous vibrations is addressed in
the evidence of Mr. Whitlock and Mr Harrison. I note that TV3 allowed
a team of CRL advisors including myself to visit the studio in operation
on the 21st June 2013 to better understand the operations, which was
informative.
Response to Planner’s Report
238. Auckland Council has raised several issues in respect of the
construction assumptions which I have clarified above.
239. Council experts have considered the settlement assessment to be
reasonable if not conservative. In our experience volume loss of 1%
(incorporating all the elements that contribute to volume loss) is a
reasonably conservative starting point and is readily achievable with
good workmanship. We note that London’s Crossrail has adopted
0.5% and 1% within the tunnelling contract specifications without the
need to mandate closed mode operation. Notwithstanding we have
undertaken sensitivity tests at higher assumed volume loss
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
56
percentages (1.5%) and do not consider the issue particularly
significant in terms of impacting the conclusions we have reached or
the Designation footprint.
240. We note that further investigation of building vulnerability and further
analysis of the effects of tunnel construction will be undertaken which
may lead to the specification of sections of the work that may require
‘closed mode’ operation.
Proposed Conditions
241. A suite of conditions is proposed in the evidence of Ms Fiona Blight.
242. The conditions referring to Construction Management Plan (CEMP)
relate to managing the effects of the Project during construction.
The conditions cover the following matters:
(a) The Communications and Consultation Plan(s);
(b) The procedures to be followed to manage the effects during
construction, to be managed under Construction Environmental
Management Plan (CEMP);
I am comfortable with the proposed condition.
CONCLUSIONS
243. Overall, I consider the concept design and the indicative construction
methodology are reasonably and appropriately conservative.
244. In my view the majority of potential adverse effects which arise during
construction will be temporary and can be addressed and managed via
the CEMP process. The CEMP will provide a robust process for
managing adverse effects that may occur during construction.
William (Bill) Russell Newns 2 July 2013
15275585_Evidence Bill Newns FINAL (2) Statement of Evidence of William (Bill) Russell Newns
57
Appendix A – Drawings
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:5
00
510
20m
ALBE
RT S
T PR
ECIN
CTTE
MPOR
ARY
TRAF
FIC
MANA
GEME
NT LA
YOUT
NORT
HERN
ZON
EDW
-NRS
-PC-
0010
B
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
ONB.
NEW
NS
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NSB
28.06
.13PE
DEDS
TRIA
N CR
OSSI
NG W
IDTH
REV
ISED
B.NE
WNS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0010.dwg Plot Date: 6/28/2013 5:43:42 PM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-STNM, 228072-XR-C-DR-STRC, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-TOPO, 228072-XR-C-NRS-ALBERT-WELCLOSED-TTM-1, 228072-XR-C-DR-STRC-AOTE-WALLLE
GEND
ALIG
NMEN
TDE
SIGN
ATIO
N
PROP
OSED
PED
ESTR
IAN
PATH
PROP
OSED
VEH
ICLE
TRA
FFIC
LANE
PROP
OSED
VEH
ICLE
TRA
FFIC
DIR
ECTI
ON
PROP
OSED
PED
ESTR
IAN
ROAD
CRO
SSIN
GPR
OPOS
ED P
EDES
TRIA
N CR
OSSI
NG
KEY
PLA
N
1.8m
WID
E PR
OPOS
EDPE
DEST
RIAN
PAT
H (T
YP.)
3.0m
WID
E PR
OPOS
ED V
EHIC
LETR
AFFI
C LA
NE (T
YP.)
INDI
CATI
VE P
EDES
TRIA
N CR
OSSI
NG
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:5
00
510
20m
ALBE
RT S
T PR
ECIN
CTTE
MPOR
ARY
TRAF
FIC
MANA
GEME
NT LA
YOUT
SOUT
HERN
ZON
E (W
ELLE
SLEY
CLO
SED)
DW-N
RS-P
C-00
11A
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
ONB.
NEW
NS
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0010-0011.dwg Plot Date: 6/27/2013 4:27:26 PM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-STNM, 228072-XR-C-DR-STRC, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-TOPO, 228072-XR-C-NRS-ALBERT-WELCLOSED-TTM-1, 228072-XR-C-DR-STRC-AOTE-WALLLE
GEND
ALIG
NMEN
TDE
SIGN
ATIO
N
PROP
OSED
PED
ESTR
IAN
PATH
PROP
OSED
VEH
ICLE
TRA
FFIC
LANE
PROP
OSED
VEH
ICLE
TRA
FFIC
DIR
ECTI
ON
PROP
OSED
PED
ESTR
IAN
ROAD
CRO
SSIN
GPR
OPOS
ED P
EDES
TRIA
N CR
OSSI
NG
KEY
PLA
N
1.8m
WID
E PR
OPOS
EDPE
DEST
RIAN
PAT
H (T
YP.)
3.0m
WID
E PR
OPOS
EDVE
HICL
E TR
AFFI
CLA
NE (T
YP.)
REFE
R TO
DRA
WIN
GS 22
8072
-DW
-NRS
-PC-
0015
AND
0016
FOR
LAYO
UTS
AT C
ROW
NE P
LAZA
ROA
D LE
VEL A
ND S
ERVI
CE LA
NE LE
VEL
PROP
OSED
PED
ESTR
IAN
ROAD
CRO
SSIN
GS
PEDE
STRI
AN P
ATH
ENDS
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:5
00
510
20m
ALBE
RT S
T PR
ECIN
CTTE
MPOR
ARY
TRAF
FIC
MANA
GEME
NT LA
YOUT
SOUT
HERN
ZON
E (V
ICTO
RIA
CLOS
ED)
DW-N
RS-P
C-00
12A
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
ONB.
NEW
NS
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0012.dwg Plot Date: 6/27/2013 4:00:31 PM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-STNM, 228072-XR-C-DR-STRC, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-TOPO, 228072-XR-C-NRS-ALBERT-VICCLOSED-TTM-1KE
Y P
LAN
1.8m
WID
E PR
OPOS
EDPE
DEST
RIAN
PAT
H (T
YP.)
3.0m
WID
E PR
OPOS
ED V
EHIC
LETR
AFFI
C LA
NE (T
YP.)
LEGE
NDAL
IGNM
ENT
DESI
GNAT
ION
PROP
OSED
PED
ESTR
IAN
PATH
PROP
OSED
VEH
ICLE
TRA
FFIC
LANE
PROP
OSED
VEH
ICLE
TRA
FFIC
DIR
ECTI
ON
REFE
R TO
DRA
WIN
GS 22
8072
-DW
-NRS
-PC-
0020
AND
0021
FOR
LAYO
UTS
AT C
ROW
NE P
LAZA
ROA
D LE
VEL A
ND S
ERVI
CE LA
NE LE
VEL
PROP
OSED
PED
ESTR
IAN
ROAD
CRO
SSIN
GS
PEDE
STRI
AN P
RIOR
ITY
ROAD
CROS
SING
WIT
H CO
NTRO
LLED
VEHI
CLE
ACCE
SS
PEDE
STRI
AN P
RIOR
ITY
ROAD
CROS
SING
WIT
H CO
NTRO
LLED
VEHI
CLE
ACCE
SS
EXIS
TING
BRI
TOMA
RT S
TATI
ON
QUEEN ST
GALW
AY S
T
TYLE
R ST
CUSTOMS ST WEST
FORT LANE
LOWER ALBERT ST
QUEEN ST
ALBERT ST
CUSTOMS ST WEST
COMMERCE ST COMMERCE ST
CUST
OMS
ST E
AST
QUAY
ST
6.93
2.35
Lock
to L
ock
Tim
eTr
ack
Wid
th: ::m
eter
sR
TS-1
8 TO
UR
CO
AC
H
6.0
2.50
2.50
Ste
erin
g A
ngle
44.2
:
12.6
0
Lock
to L
ock
Tim
e
Del
iver
y V
anW
idth
Trac
k
Ste
erin
g A
ngle
0.72
3.50
met
ers
::2.
102.
10
:46
.2:
6.0
6.00
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:5
00
510
20m
BRIT
OMAR
T W
ORKS
ITE
STAG
E 1
ENAB
LING
WOR
KS A
ND D
EMOL
ITIO
NDW
-NRS
-PC-
0101
A
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0101.dwg Plot Date: 6/27/2013 3:52:31 PM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPONO
TES
1.DO
NOT
SCA
LE F
ROM
THE
DRAW
ING.
2.ST
ATIO
NS S
HOW
N IN
DICA
TIVE
LY. A
RCHI
TECT
SDR
AWIN
GS T
AKE
PREC
EDEN
CE.
KEY
PLA
N
LEGE
ND
CRL O
NLY
VEHI
CLE
ROUT
EBO
TH C
RL A
ND P
UBLIC
VEH
ICLE
ROU
TE
WOR
KSIT
E AR
EA A
T EA
CH S
TAGE
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
TO H
OBSO
N &
FANS
HAW
E
TO H
OBSO
N &
FANS
HAW
E
ZURI
CH B
UILD
ING
ACCE
SS R
EMAI
NS
BUILD
INGS
ON
PREC
INCT
SIT
EAR
E DE
MOLIS
HED
DOW
N TO
GROU
ND F
LOOR
SLA
B LE
VELS
CONS
TRUC
TION
SIT
E FO
RBU
ILDIN
G DE
MOLIT
ION
AND
ALBE
RT S
T CU
T AN
D CO
VER
CONS
TRUC
TION
LAYD
OWN
AREA
FOR
CUT
-OFF
WAL
LSAN
D BR
ITOM
ART
WOR
KS
RTS-
18 T
OUR
COAC
H
6m D
ELIV
ERY
VAN
PROP
ERTY
SER
VICE
ACC
ESS
- MAI
NTAI
NED
TO S
UIT
CONS
TRUC
TION
SEQ
UENC
E PROP
ERTY
CARP
ARK
ACCE
SS
EXIS
TING
BRI
TOMA
RT S
TATI
ON
QUEEN ST
GALW
AY S
T
TYLE
R ST
CUSTOMS ST WEST
FORT LANE
LOWER ALBERT ST
QUEEN ST
ALBERT ST
CUSTOMS ST WEST
COMMERCE ST COMMERCE ST
CUST
OMS
ST E
AST
QUAY
ST
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:5
00
510
20m
BRIT
OMAR
T W
ORKS
ITE
STAG
E 2
DW-N
RS-P
C-01
02A
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0102.dwg Plot Date: 6/27/2013 3:50:39 PM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPONO
TES
1.DO
NOT
SCA
LE F
ROM
THE
DRAW
ING.
2.ST
ATIO
NS S
HOW
N IN
DICA
TIVE
LY. A
RCHI
TECT
SDR
AWIN
GS T
AKE
PREC
EDEN
CE.
KEY
PLA
N
LEGE
ND
CRL O
NLY
VEHI
CLE
ROUT
EBO
TH C
RL A
ND P
UBLIC
VEH
ICLE
ROU
TE
WOR
KSIT
E AR
EA A
T EA
CH S
TAGE
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
TO H
OBSO
N &
FANS
HAW
E
TO H
OBSO
N &
FANS
HAW
E
WOR
KSIT
E FO
R AL
BERT
ST
CUT
AND
COVE
R
WOR
K AC
TIVI
TIES
�BR
ITOM
ART.
PILI
NG A
ND T
RANS
FER
STRU
CTUR
ES�
QE2 S
QUAR
E/QU
EEN
ST. C
UT A
ND C
OVER
TUN
NELS
�PR
ECIN
CT U
TILIT
Y DI
VERS
ION
PILIN
G/RE
TENT
ION
WOR
KS.
GROU
NDW
ORKS
FOR
OVE
R-SI
TE D
EVEL
OPME
NT
WOR
KSIT
ES F
ORBR
ITOM
ART,
QE2 S
QUAR
EAN
D PR
ECIN
CT W
ORK
CONS
TRUC
TION
LAYD
OWN
AREA
FOR
CUT
-OFF
WAL
LSAN
D BR
ITOM
ART
WOR
KS
SUSP
ENDE
D DE
CK A
BOVE
ACCE
SS T
O AL
LOW
CRL
VEHI
CLE
MOVE
MENT
WELLESLEY ST WESTWELLESLEY ST WEST
MAYORA
L DRIV
E
MAYO
RAL D
RIVE
ELLESLEY ST WESTWELLESLEY ST WEST
MAYO
L DRI
VEOR
AL
WELLESLEYSTWEST WELLESLEYSTWEST
8m M
ED
IUM
RIG
ID T
RU
CK
1.25
:::
6.0
sec
2.50
m2.
50 m
:
5.00
8.00
WID
THTR
AC
KLO
CK
TO
LO
CK
TIM
ES
TEE
RIN
G A
NG
LE37
.3°
0.72
3.506.00
6m D
ELI
VE
RY
VA
N
:::
6.0
sec
2.10
m2.
10 m
:
WID
THTR
AC
KLO
CK
TO
LO
CK
TIM
ES
TEE
RIN
G A
NG
LE46
.2°
1.25
0.30
4.351.
338.
90
4.20
13.0
3
17m
SE
MI T
RA
ILE
R
:::
6.0
sec
2.50
m2.
50 m
:
TRA
CTO
R /
TRA
ILE
R W
IDTH
TRA
CTO
R /
TRA
ILE
R T
RA
CK
LOC
K T
O L
OC
K T
IME
STE
ER
ING
AN
GLE
23.8
°:
AR
TIC
ULA
TIN
G A
NG
LE70
.0°
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:2
50
2.55
10m
AOTE
A W
ORKS
ITE
DW-N
RS-P
C-01
30B
1:250
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NSB
04.07
.13FO
R DI
SCUS
SION
B.NE
WNS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0130.dwg Plot Date: 7/4/2013 10:42:58 AM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPO, 228072-XR-C-NRS-ALBERT-VICCLOSED-TTM-1NO
TES
1.DO
NOT
SCA
LE F
ROM
THE
DRAW
ING.
2.ST
ATIO
NS S
HOW
N IN
DICA
TIVE
LY. A
RCHI
TECT
SDR
AWIN
GS T
AKE
PREC
EDEN
CE.
KEY
PLA
N
LEGE
ND
CRL O
NLY
VEHI
CLE
ROUT
EBO
TH C
RL A
ND P
UBLIC
VEH
ICLE
ROU
TE
WOR
KSIT
E AR
EAS
AS LA
BELL
ED
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
TWO
WAY
SER
VICE
LANE
USE
DW
HEN
VICT
ORIA
ST
WES
T CL
OSUR
E
SPOI
L HAN
DLIN
G
SITE
OFF
ICE
PLAN
T,EQ
UIPM
ENT,
WOR
K SH
EDS
MATE
RIAL
S,LA
YDOW
NAS
SEMB
LY
EXIS
TING
CAR
PARK
STO
BE
REMO
VED
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:2
50
2.55
10m
BERE
SFOR
D W
ORKS
ITE
DW-N
RS-P
C-01
51A
1:250
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0151.dwg Plot Date: 6/27/2013 11:23:46 AM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-XTNT, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPO
NOTE
S1.
CAR
SHOW
N IS
90 P
ERCE
NTILE
CAR
.
KEY
PLA
N
CRL O
NLY
VEHI
CLE
ROUT
EBO
TH C
RL A
ND P
UBLIC
VEH
ICLE
ROU
TE
WOR
KSIT
E AR
EA
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
LEGE
ND
TO A
ND F
ROM
MOTO
RWAY
S
THIS
ROA
D HA
S AN
ENT
RYPO
INT
FOR
CARS
AT
THE
SOUT
HERN
END
PLAN
T,EQ
UIPM
ENT,
WOR
K SH
EDS
MATE
RIAL
S,LA
YDOW
NAS
SEMB
LY
SPOI
L HAN
DLIN
G
SITE
OFFI
CES,
AMEN
ITIE
S
7000
5000
HERI
TAGE
SIT
EHO
ARDE
D OF
F
CAR
PARK
SRE
MOVE
D
CAR
PARK
SRE
TAIN
ED
5000
POTE
NTIA
L GAT
E LO
CATI
ON T
OSE
CURE
ACC
ESS
TO H
ERIT
AGE
SITE
.
POTE
NTIA
L GAT
ELO
CATI
ON T
OSE
CURE
ACC
ESS
TO H
ERIT
AGE
SITE
ACCE
SS T
O PR
OPER
TY C
ARPA
RK U
NAVA
ILABL
E DU
RING
CONS
TRUC
TION
PHA
SE
SING
LE LA
NE A
CCES
S W
ITH
WID
TH A
LLOW
ANCE
FOR
LOW
SPE
ED P
ASSI
NG
1.8m
WID
E PE
DEST
RIAN
ACC
ESS
TO P
ROPE
RTIE
S
5000
1.8m
WID
E PE
DEST
RIAN
ACC
ESS
TO P
ROPE
RTIE
S
SHAF
T CO
NSTR
UCTI
ON W
ITHI
N PI
TT S
TIS
UND
ERTA
KEN
IN 2
HALF
S AN
DCO
NTRO
LLED
VEH
ICLE
CRO
SSIN
GW
HEN
CONS
TRUC
TING
EAS
T SI
DE
HOPETOUN ST
BERE
SFOR
D SQ
PITT ST
EAST
ST
MERC
URY
LANE
CROSS ST
CANADA ST
EAST
ST
29
32
38
23-3
1
25-2
7
24
20
1
1816
14
2
11-1
3
12
9
8
3
246-
254
256
53.5
53.5
53.0
52.5
52.0
52.5
54.0
20
23-3
1
38
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
0
SCAL
E 1:2
50
2.55
10m
MERC
URY
LANE
WOR
KSIT
E
DW-N
RS-P
C-01
52B
1:250
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NSB
04.07
.13FO
R DI
SCUS
SION
B.NE
WNS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0152.dwg Plot Date: 7/4/2013 11:04:01 AM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-XTNT, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPO
KEY
PLA
N
CRL O
NLY
VEHI
CLE
ROUT
EBO
TH C
RL A
ND P
UBLIC
VEH
ICLE
ROU
TE
WOR
KSIT
E AR
EA
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
LEGE
ND
TO MOTORWAYS
FROM
PITT
ST
PLAN
T,EQ
UIPM
ENT,
STOR
E
MATE
RIAL
S AN
DGE
NERA
L LAY
DOW
N
UNLO
ADIN
G AR
EA
OVER
HEAD
SPO
IL CO
NVEY
OR
SPOI
L HAN
DLIN
G
SITE
OFFI
CES,
AMEN
ITIE
S
NEW
TON
STAT
ION
5
3
16
12
3
6
2
33
2
52
11
56
54
48
44
29-3
1
40
30
27
22-2
6
63
4
61
59
55
53
51
49
45
41
33
25
27
23
19
24
12
25
2
23
1
2
22
21
2 4
20
6 6A
8
265
3
230-
250
5
257
9
25
226-
228
253
249
14
224
245-
247
18
243
16
12
241
14
239
13-1
7
237
206-
210
10
233
15
3
229
8
10
227
9
225
223
7
44
8
2
5
221
6
2-6
3
4
215
2
153 151
102/1
84-4
28/18
4
147
145 14
3-14
9
101/1
84-4
27/18
4
211-
213
141
139
209
3
205
136A
-136
E
203-
207
136
201
176
197-
199
128
195
174
193
44A-
44P
191
31
189
1/42-
30/42
183A
77-1
85
1/40-
3/40
29
1/70-
7/70
6
KHYBER PASS RD
NEWTON RD
MT EDEN RD
NEW N
ORTH
RD
SAIN
T BE
NEDI
CTS
ST
DUND
ONAL
D ST
HOHIPERE ST
SYMO
NDS
ST
BASQUE RD
NIKAU
ST
FLOWER ST
NEW NORTH RD
2550
2600
2650
2700
2750
2800
2850
2900
00
50
100
00
50
100
2550
2600
2650
2700
2750
2800
2850
2900
270027027277007007002700700
18
010
226626
86-
228
1.25
6.55
11.0
0
11m
LA
RG
E R
IGID
TR
UC
K :::
6.0
sec
2.50
m2.
50 m
:
WID
THTR
AC
KLO
CK
TO
LO
CK
TIM
ES
TEE
RIN
G A
NG
LE37
.4°
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
1/70-
7/70
0
SCAL
E 1:5
00
510
20m
NEW
TON
WOR
KSIT
ES
DW-N
RS-P
C-02
01A
1:500
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
OND.
MOCK
ETT
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: Z:\CADD\PHASE 3\DRGS\TP2 NRS\PC\228072-DW-NRS-PC-0201.dwg Plot Date: 6/28/2013 8:21:50 AM Name: Brin Hingston Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-XTNT, 228072-XR-C-DR-ALGN, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-STRC, 228072-XR-C-DR-DSGN, 228072-XR-C-DR-TOPOKE
Y P
LAN
176 CR
L ONL
Y VE
HICL
E RO
UTE
BOTH
CRL
AND
PUB
LIC V
EHIC
LE R
OUTE
WOR
KSIT
E AR
EA A
T EA
CH S
TAGE
SURF
ACE
DESI
GNAT
ION
PUBL
IC V
EHIC
LE R
OUTE
VEHI
CLE
ROUT
E W
ITHI
N W
ORKS
ITE
WOR
KSIT
E HO
ARDI
NG
CRL V
EHIC
LE W
ORKS
ITE
EGRE
SS
WOR
KSIT
E GA
TE
LEGE
ND
NOTE
S1.
DO N
OT S
CALE
FRO
M TH
E DR
AWIN
G.2.
STAT
IONS
SHO
WN
INDI
CATI
VELY
. ARC
HITE
CTS
DRAW
INGS
TAK
E PR
ECED
ENCE
.
TEMP
ORAR
Y GA
NTRY
EXIS
TING
MT E
DEN
PLAT
FORM
GATE
14
20
19
18
17
16
5
13
8-12
7
621
MT EDEN RD
BREN
TWOO
D AV
E
WYNYARD RD
NGAHURA ST
HAUL
TAIN
ST
FENT
ON S
T
PORTERS AVE
AKIR
AHO
ST
KORARI ST
SHAD
DOCK
ST
ENFI
ELD
ST
MT EDEN RD
RURU ST
FLOWER ST
AKIR
AHO
ST
NEW N
ORTH
RD
NIKA
U ST
RURU ST
SHAD
DOCK
ST
NIKA
U ST
ER ST
FLOWER ST
NEW
NOR
TH R
D
MT EDEN RD
MT EDEN RD
CLI
ENT
DA
TE
TITL
E
REV
ISIO
N D
ETA
ILS
DA
TER
EVA
PPR
OVE
D
CH
ECK
ED
APP
RO
VED
PRO
JEC
TD
RA
WN
DES
IGN
ED
2280
72PR
OJE
CT
No.
SCA
LESI
ZE
DR
AW
ING
No.
REVA1
CITY
RAI
L LIN
K
07.5
1530
m
SCAL
E 1:7
50
MT E
DEN
WOR
KSIT
E
DW-N
RS-P
C-02
20A
1:750
PREL
IMIN
ARY
NOT
FOR
CONS
TRUC
TION
B.HI
NGST
ONB.
NEW
NS
B.NE
WNS
A28
.06.13
FOR
DISC
USSI
ONB.
NEW
NS
Cad File: \\nzaklpfs02\nzakl_crl_project\CADD\PHASE 3\DRGS\TP7 DR\CS\228072-DW-DR-CS-1357.dwg Plot Date: 6/27/2013 9:21:50 AM Name: Bruce Li Xrefs: 228072-XR-G-A1HS, 228072-XR-C-Aerial_Photo, 228072-XR-C-DR-BNDY, 228072-XR-C-DR-STNM, 228072-XR-C-DR-XTNT, 228072-XR-C-DR-Keyplan_1000, 228072-XR-C-DR-BLDG-FOOT, 228072-XR-C-DR-STRC, 228072-XR-C-DR-Legend-AL
NOTE
S1.
DO N
OT S
CALE
FRO
M TH
E DR
AWIN
G.
KEY
PLA
NW
ORK
ZONE
AREA
(m2)
4TU
NNEL
VEN
TILA
TORS
-5
SPOI
L ARE
A - H
ARDS
TAND
FOR
LOAD
ING
AND
BINS
1500
6SE
GMEN
T ST
ORAG
E YA
RD18
007
SITE
OFF
ICES
, WOR
KSHO
P, S
TAFF
AME
NITI
ES,
1500
SECU
RITY
, GEN
ERAL
8-12
EQUI
PMEN
T ST
ORE,
MECH
ANIC
AL S
TORE
, ELE
CTRI
CAL
STOR
E, O
XY S
TORE
2
0013
PIPE
AND
BRA
CKET
STO
RAGE
460
14RA
IL AS
SEMB
LY Y
ARD
500
16AI
R CO
MPRE
SSOR
S
5017
GROU
T BA
TCHI
NG P
LANT
130
18GE
NERA
L STO
RAGE
/LAYD
OWN
YARD
475
19BU
NDED
CHE
MICA
L ARE
A
6020
WAT
ER T
REAT
MENT
PLA
NT 6
6021
POW
ER S
UPPL
Y, S
WIT
CHIN
G, D
IST.
ETC
200
LEGE
ND:
SITE
BOU
NDAR
Y/FE
NCE
ACCE
SS R
OADS
GATE
ENTR
Y RO
UTE
EGRE
SS R
OUTE
WHE
ELW
ASH
SPOI
L AND
SEGM
ENT
TRUC
K EX
IT
TO MOTO
RWAYS
EXIS
TING
VEH
ICLE
CRO
SSIN
GAN
D AC
CESS
WAY
WIT
H GA
TE
18m
18m
20m
SPOI
LBI
NSP
OIL
BIN
SPOI
LCO
NVEY
ORSP
OIL
LIFTI
NGPL
ANT
GATE
GATE
SPOI
L AND
SEG
MENT
TRUC
K SI
TE E
NTRY
PARK
ING
AREA
SEGM
ENTS
PLA
CED
ON T
UNNE
LTR
ANSP
ORT
SYST
EM
35m
SPAN
GANT
RY
4m
CURR
ENT
NAL T
RACK
POSI
TION
SRA
IL ℄
FENC
E
STAF
F AND
TRUC
KS TU
RN IN
STAFF SITE ENTRY
STAF
F EX
ITON
LY -
NOTR
UCKS
SEGM
ENTS
PLA
CED
ON T
UNNE
LTR
ANSP
ORT
SYST
EM