Page 1: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

August 28, 2009

Federal Emergency Management Agency

Public Assistance

Arbitration Process

Page 2: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

2 August 28, 2009

Briefing Objectives…

Review Section 601 of the American Recovery & Reinvestment Act of 2009 (ARRA)

Discuss 44 CFR §206.209

Explain the Eligibility Criteria for Arbitration

Detail the Time Limits & Timeframes

Describe the Process

http://www.fema.gov/government/grant/pa/arbitration.shtm

Page 3: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

3 August 28, 2009

The ARRA…

Became Law on February 17, 2009

Establishes an Arbitration Option

Included a Provision Designed to Expedite the Resolution of Disputed Projects

Applies only to Hurricane Katrina & Rita Disasters

Project Costs Must Be Greater Than $500,000

Page 4: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

4 August 28, 2009

Arbitration is Limited to…

DR-1603-LA

DR-1604-MS

DR-1605-AL

DR-1606-TX

DR-1607-LA

Gulf Coast Katrina & Rita Disasters

Page 5: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

5 August 28, 2009

44 CFR §206.209 Published on August 31, 2009

Provides Time Frames

Sets Arbitration Criteria

Establishes Arbitration Procedures

Provides Final Agency Action

Establishes Responsibility for Arbitration Expenses

Page 6: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

6 August 28, 2009

Requirements for an Arbitration Request…

FEMA Determinations or Decisions Made On or After February 17, 2009

No Final Decision Prior to February 17, 2009

Projects Must Cost More Than $500,000

Statutory Time Limits for Appeals Apply

Pending Appeal Must Be Withdrawn by Applicant by October 30, 2009

Page 7: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

7 August 28, 2009

1st Appeal, Time Limits…

Applicant Must Request, in writing, Arbitration within 60 Days of August 31, 2009 (October 30, 2009)

Appeals Pending a Decision on 2/17/09 Must be Withdrawn, in writing, within 60 Days of August 31, 2009 (October 30, 2009)

1st Appeals Pending a Decision On 2/17/09

Arbitration is In Lieu Of Filing or Continuing a 1st or 2nd Appeal

Page 8: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

8 August 28, 2009

2nd Appeal, Time Limits…

2nd Appeals Pending or in Receipt of Final Decisions on or After February 17, 2009 - Applicant Must Request Arbitration, in writing, by October 30, 2009

If Applicant opts for Arbitration - 2nd Appeal Must be Withdrawn, in writing, by October 30, 2009

2nd Appeals Pending a Decision On 2/17/09

Arbitration is In Lieu Of Filing or Continuing a 1st or 2nd Appeal

Page 9: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

9 August 28, 2009

Time Limits for a Determination…

After August 31, 2009 - The Applicant Must Request Arbitration, in writing, within 30 Days of the Determination in Dispute

Disputes Must Be Eligible for an Appeal Per Time Limits in 44 CFR §206.206

Arbitration is In Lieu Of Filing or Continuing a 1st or 2nd Appeal

Page 10: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

10 August 28, 2009

Arbitration Panel…

US Civilian Board of Contract Appeals (CBCA)

Panel is Composed of Three Arbitrators

Panel for each Appeal Chosen By the Arbitration Administrator

Arbitration Administrator Notifies All Parties of Names of Arbitrators on the Panel

Page 11: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

11 August 28, 2009

Content of Request for Arbitration… Written Statement of Dispute and Request for Arbitration

All Documentation Supporting the Applicant’s Position All information necessary for the arbitration panel to

make an informed decision There is no limit on amount of documentation that may

be provided Applicants are encouraged to describe their claims in

sufficient detail to make the circumstances of the dispute clear to the arbitration panel

Withdrawal of Pending Appeal, if Applicable

Disaster Number

Name and Address of Applicant’s Authorized Representative or Counsel

Page 12: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

12 August 28, 2009

Submission by Applicant…

Must Submit Written Request & Documentation Simultaneously to Grantee, the FEMA Regional Administrator and Arbitration Administrator

Within 30 Calendar Days of Receipt of Notice of the Determination

Appeals Pending a Decision on 2/17/09 and 2nd Appeal Decisions Between 2/17/09 – 10/30/09 The Applicant Must Request Arbitration within 60 Days

From Date Final Rule Was Published – October 30, 2009

Submit a Withdrawal of the Pending Appeal, if Applicable by October 30, 2009

Page 13: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

13 August 28, 2009

Submission by Grantee… Within 15 Days of Receipt of Request from Applicant

Forward Name and Address of the Grantee’s Authorized Representative or Counsel Simultaneously to: FEMA Regional Administrator

Arbitration Administrator

Applicant

May Forward a Written Recommendation in Support or Opposition to the Applicant’s Request Simultaneously to:

FEMA Regional Administrator

Arbitration Administrator

Applicant

Page 14: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

14 August 28, 2009

Submission by FEMA… Within 30 Days of Receipt of Request from Applicant

Simultaneously Forward FEMA’s Response to:

Grantee

Arbitration Administrator

Applicant Written Submission to Include:

Memorandum in Support FEMA’s Response

A Copy of the Project Worksheet

All Supporting Documentation

Name and Address of Authorized Representative or Counsel

Page 15: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

15 August 28, 2009

Arbitration Panel’s Responsibilities…

Provide a Docket Number for Each Request for Arbitration it Receives

Arbitration Administrator Selects 3 Members for the Arbitration Panel

Contacts All Parties to set up a Preliminary Conference by Telephone

Set the Date and Location for the Hearing if a Hearing Has Been Requested

Render Final Determination Based on Relevant Written Materials and Oral Presentations, if any.

Page 16: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

16 August 28, 2009

Preliminary Conference… Held Within 10 Days After Panel Receives

FEMA’s Response to the Request for Arbitration

Teleconference with All Parties

Purpose: Address Future Conduct of the Case

Clarification of Disputed Issues

Possible Arbitrator Disqualification

Schedule of Hearings and Hearing Location if Requested Applicant and/or FEMA Must Request Hearing Prior to

Preliminary Conference

Other Administrative Matters

Page 17: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

17 August 28, 2009

Hearing… Name of Presenter if Hearing is Requested

Hearing Held Within 60 Calendar Days After Preliminary Conference

Oral Presentation In Person

Or by Telephone

All Parties Must be Able to Simultaneously Hear All Other Participants

The Parties May Not Engage in Discovery or Provide Additional Paper Submissions at the Hearing

Panel May Request Additional Written Materials from Either Party And Parties May Make Request to Submit Additional Written Materials Following the Hearing.

Discretion to Grant Request Rests with the Panel.

Page 18: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

18 August 28, 2009

Review by the Arbitration Panel…

Will Consider All Relevant Written Materials

Will Consider Oral Presentations

Panel May Seek Independent Expert Advice Engineers

Architects

Subject Matter Experts

Page 19: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

19 August 28, 2009

Finality of Decision…

Majority of the Panel Will Constitute a Final Decision

Final Decision is Binding for All Parties

No Further Administrative Review

Not Subject to Judicial Review Except as Permitted by 9 U.S.C. 10

Page 20: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

20 August 28, 2009

Definitions… Appeal – Two-level Procedure under 44 CFR §206.206 to

Resolve an Agency Determination with an Agency Decision

Application – A Project Worksheet Before it is Approved

ARRA – American Recovery & Reinvestment Act of 2009

CBCA – US Civilian Board of Contract Appeals

Decision – Outcome of an Appeal or Arbitration Request

Determination – Non Appealed FEMA Action in Dispute

Docket Number – Tracking Number Provided by the CBCA

Page 21: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

21 August 28, 2009

Definitions, cont… Final Rule – Regulations Based on Section 601 of the ARRA

Hearing – Oral Presentation Requested by the Applicant or FEMA

Panel – The Arbitration Panel from the CBCA

Preliminary Conference – Panel Initiated Teleconference With All Parties

Project – Project Worksheet May Include More Than One Site May Include More than One Project Worksheet

Time Limit – Number of Days to File an Appeal, Arbitration Request or Issue a Decision

Page 22: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

22 August 28, 2009

Where to submit?

Civilian Board of Contract Appeals

Mailing Address1800 F Street, NWWashington, DC 20405

Street AddressSixth Floor1800 M Street, NWWashington, DC 20036

Page 23: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

23 August 28, 2009

From Louisiana, please also send your request to:

FEMA

ATTN:  Gary JonesActing Regional Administrator800 N. Loop 288Denton, Texas 76209

State

ATTN: Mark RileyDeputy Director Governor's Office of Homeland Security and Emergency Preparedness (GOHSEP)7667 Independence BlvdBaton Rouge, LA 70806

Page 24: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

24 August 28, 2009

If you have any administrative questions regarding the CBCA's process, you may contact the Clerk of the Board at: Phone (202) 606-8800; and Fax (202) 606-0019. See also the CBCA’s webpage at www.cbca.gsa.gov.

Page 25: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

25 August 28, 2009

Questions ?

Page 26: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

26 August 28, 2009

Links

http://www.fema.gov/government/grant/pa/arbitration.shtm

www.fema.gov

http://www.louisianapa.com/

http://www.cbca.gsa.gov/

Page 27: August 28, 2009 Federal Emergency Management Agency Public Assistance Arbitration Process

August 28, 2009