awareness 2007 fidi1c
TRANSCRIPT
-
8/4/2019 Awareness 2007 FIDI1C
1/31
decorient
PT Decorient Indonesia
Contractual Awareness Course
10 December 2007
FIDIC
Federation Internationale des Ingenieurs Counseils
FIDIC FIDIC FIDIC FIDIC FIDIC
FIDIC FIDIC FIDIC FIDIC FIDICFederation Internationale des Ingenieurs Counseils
-
8/4/2019 Awareness 2007 FIDI1C
2/31
decorient
PT Decorient Indonesia 2
OBJECTIVE
1. Know where to find FIDIC general conditions in a contract
document.
2. Know what FIDIC is.
3. Know several General Conditions of Contract (GCC).4. Aware that FIDIC GCC can be freely modified.
5. Aware that one can not refer to FIDIC if it is not chosen.
6. Know the principles of risk allocation by FIDIC.
-
8/4/2019 Awareness 2007 FIDI1C
3/31
decorient
PT Decorient Indonesia 3
CONTRACT DOCUMENTS
1. The Agreement;
2. Form of Tender and Attachments;
3. Special Conditions of Contract;
4. General Conditions of Contract;5. Method of Measurement;
6. Bill of Quantities;
7. Drawings;
8. Specifications;
9. Correspondences.
-
8/4/2019 Awareness 2007 FIDI1C
4/31
decorient
PT Decorient Indonesia 4
ORDER OF PRIORITY
1. In case of discrepancy between several documents forming part of theContract Document, an order of priority should be used.
2. Order of priority is set by the Employer.
3. Typical order of priority:
1. The Agreement;2. Letter of Award;
3. Form of Tender;
4. Special Conditions of Contract;
5. General Conditions of Contract;
6. Specification;
7. Drawings;
8. Bill of Quantity.4. A description in low priority document must be checked against
contradicting description in higher priority document, e.g: Thickness of glass is 8 mm in the Bill of Quantity, but is 10 mm in the
Specification 10 mm thick shall be used
-
8/4/2019 Awareness 2007 FIDI1C
5/31
decorient
PT Decorient Indonesia 5
DISCREPANCY VS COMPLIMENTARY
1. If the Specification says 10 mm thick glass and Drawing shows 8
mm thick glass, then this is discrepancy.
2. If the Specification says 10 mm thick glass and Drawing does not
mention anything, then this is not a discrepancy, butcomplimentary.
-
8/4/2019 Awareness 2007 FIDI1C
6/31
decorient
PT Decorient Indonesia 6
GENERAL CONDITIONS OF CONTRACT
Is the rules of the game, contain amongst others:
The rights and responsibility of the Employer;
The authorities of the Engineer (Employers Project Manager);
The rights and responsibility of the Contractor; Allocation of risks;
Procedure for assuring quality;
Procedure for assuring timely execution;
Measurement and payment;
Variation; Insurance;
Dispute resolution;
Etc.
-
8/4/2019 Awareness 2007 FIDI1C
7/31
decorient
PT Decorient Indonesia 7
STANDARD FORMS OF GENERAL
CONDITIONS1. FIDIC (Federation Internationale des Ingenieurs Counseils);
2. JCT (Joint Contracts Tribunal);
3. ICE (Institution of Civil Engineers);
4. SIA (Singapore Institute of Architect);
5. AIA (American Institute of Architect);
6. Standard Form for Use in Hongkong.
-
8/4/2019 Awareness 2007 FIDI1C
8/31
decorient
PT Decorient Indonesia 8
FIDIC
Federation Internationale des Ingenieurs Counseils (FIDIC) means
International Federation of Consulting Engineers.
Founded in 1913 by 3 national associations of independentconsulting engineers within Europe. Today FIDIC membership
numbers 74 Members Associations around the world (1 member
association for each country).
From Indonesia: INKINDO.
-
8/4/2019 Awareness 2007 FIDI1C
9/31
decorient
PT Decorient Indonesia 9
COMMON USEOF FIDIC GCC
Projects with loan from the World Bank.
Private funded building projects in Indonesia where the QS is DLS,
EC Harris, Korra.
-
8/4/2019 Awareness 2007 FIDI1C
10/31
decorient
PT Decorient Indonesia 10
SEVERAL FIDIC GCC
FIDIC GCC for Construction
1st edition 1957
2nd edition 1969
3rd edition 1977
4th edition 1987 amended 1992
5th edition 1999
FIDIC GCC for Design and Build FIDIC GCC for EPC and Turnkey
-
8/4/2019 Awareness 2007 FIDI1C
11/31
decorient
PT Decorient Indonesia 11
FREE CHOICE
The Employer is free to choose which FIDIC he will use. He
can use FIDIC 1969 like Qatar Embassy.
Later version of FIDIC does not automatically overrule earlier
revision.
If a contract does not use FIDIC Conditions of Contract,
parties to the contract can not rely on FIDIC clauses.
However, FIDIC may be appealing to fill out the void left by an
incomplete conditions of contract. Thus FIDIC is not a governing rule, it becomes rules for the
parties who chose it.
-
8/4/2019 Awareness 2007 FIDI1C
12/31
decorient
PT Decorient Indonesia 12
FREE MODIFICATION
FIDIC General Conditions of Contract is freely modified by
the Employer, by the use of Conditions of Particular
Application (or Special Conditions of Contract). e.g:
FIDIC GCC states that Employer shall provide a proof of his
ability to pay the Project.
Particular Application can delete this provision.
-
8/4/2019 Awareness 2007 FIDI1C
13/31
decorient
PT Decorient Indonesia 13
RISK INVENTORY
1. Ambiguity or discrepancy of contract document.
2. Delay issue of drawing or instruction from the Employer.
3. Delay submission of Contractors Documents.4. Employers compliance with planning, zoning and other
permit for Permanent Works.
5. Compliance with any regulation for the execution of the
Works by the Contractor.
-
8/4/2019 Awareness 2007 FIDI1C
14/31
decorient
PT Decorient Indonesia 14
RISK INVENTORY
6. Employers delay in giving right of access to the Site.
7. Non performance of Contractors subs.
8. Interrelationship with other parties in the Project.9. Employer error in giving points of reference or bench
marks.
10. Contractors failure to collect or interpret Site Data.
11. Unforeseeable Physical condition.
-
8/4/2019 Awareness 2007 FIDI1C
15/31
decorient
PT Decorient Indonesia 15
RISK INVENTORY
12. Delay or failure of the Employer to give free issued
materials .
13. Finding of geological or archaeological interest.
14. Nominated Subcontractor.
15. Engineer delaying tests.
16. Retesting of defective workmanship or materials.
17. Variation.
18. Delays caused by authority.19. Suspension of Work.
-
8/4/2019 Awareness 2007 FIDI1C
16/31
decorient
PT Decorient Indonesia 16
RISK INVENTORY
20. Defective design.
21. Defective material or workmanship.
22. Change in legislation.
23. Delayed certification and payment.
24. Fluctuating exchange rate.
25. Fluctuating market price of goods or services.
26. Termination by the Employer.
27. Non payment or bankruptcy of Employer.28. Bodily injury, sickness or death during Construction.
-
8/4/2019 Awareness 2007 FIDI1C
17/31
decorient
PT Decorient Indonesia 17
RISK INVENTORY
29. Damage to property other than the Works.
30. Damage to the Works caused by Employers Risks.
31. Breach of intellectual property.
32. Deductibles of insurance and amount not recovered from
insurance.
-
8/4/2019 Awareness 2007 FIDI1C
18/31
decorient
PT Decorient Indonesia 18
RISK ALLOCATION
WHAT DO YOU THINK IS FAIR AND REASONALBE
FOR THE EMPLOYER AND THE CONTRACTOR IF
THE FOLLOWING RISKS OCCUR??
-
8/4/2019 Awareness 2007 FIDI1C
19/31
decorient
PT Decorient Indonesia 19
RISK ALLOCATION
1. Ambiguity or discrepancy of contract document Ambiguity and discrepancy between contract document is the
risk of the Employer.
The Contractor based his price on the order of priority. If other interpretation is required, the Engineer will issue aVariation order.
2. Delay issue of drawing or further instruction from theEmployer
The Employer must provide drawing or instruction withinreasonable time to enable the Contractor to proceed with theWorks without interruption. If drawing or instruction aregiven late and disrupt the Works, the Contractor can requestadditional cost and or extension of time.
-
8/4/2019 Awareness 2007 FIDI1C
20/31
decorient
PT Decorient Indonesia 20
RISK ALLOCATION
6. Employers delay in giving right of access to the Site
Can result in additional cost and delay. Employer is
responsible .
7. Non performance of Contractors subs
Can result in additional cost and delay. Contractor is
responsible.
8. Interrelationship with other parties in the Project
Employer, employers contractors, authority must be allowedreasonable opportunity to carry out their works. If
Contractor incurs Unforeseeable Cost, he will be reimbursed.
-
8/4/2019 Awareness 2007 FIDI1C
21/31
decorient
PT Decorient Indonesia 21
RISK ALLOCATION
9. Employer error in giving points of reference or bench
marks.
Setting out of the Works by Contractor using points of
reference supplied by the Employer. Contractor must use
reasonable effort to check accuracy. If errors are found afterthat, after reasonable effort of an experienced contractor, then
Employer will reimburse Contractor for additional cost or
delay.
10. Contractors failure to collect or interpret Site Data
If data is supplied by the Employer, then the Employer isresponsible for accuracy of such data, but the Contractor is
responsible for interpretation of such data.
If data is incomplete, Contractor must complete by itself
-
8/4/2019 Awareness 2007 FIDI1C
22/31
decorient
PT Decorient Indonesia 22
RISK ALLOCATION3. Delay submission of Contractors Documents
This can result in additional cost or delay. All to be borne by
the Contractor.
4. Employers compliance with planning, zoning and otherpermit for Permanent Works.
Unavailability of permanent permit can create additional cost
and extension of time. This is to be borne by the Employer.
5. Compliance with any regulation for the execution of the
Works by the Contractor. This is Contractors responsibility
-
8/4/2019 Awareness 2007 FIDI1C
23/31
decorient
PT Decorient Indonesia 23
RISK ALLOCATION
11. Unforeseeable Physical condition
In event of adverse physical conditions which is not
foreseeable by an experienced contractor, delay and
associated cost is compensated by the Employer.
But if unforeseen is more favorable, there will be costreduction, with total reduction shall not reduce Contract
Price.
12. Delay or failure of the Employer to give free issued
materials
Employer is responsible for the delay or additional cost
arising
-
8/4/2019 Awareness 2007 FIDI1C
24/31
decorient
PT Decorient Indonesia 24
RISK ALLOCATION
13. Finding of geological or archaeological interest
Fossils shall be treated as required by the Engineer and
associated cost or delay will be reimbursed.
14. Nominated Subcontractor
Nominated Subcontractor (NSC) is a contractor nominated
by the Employer but enters into subcontract with the
Contractor.
Performance of NSC is Contractors responsibility.
15. Engineer delaying tests Testing of the Works is carried out in the presence of
Engineer with prior appointment. If Engineer delays,
associated cost and delay will be reimbursed.
-
8/4/2019 Awareness 2007 FIDI1C
25/31
decorient
PT Decorient Indonesia 25
RISK ALLOCATION
16. Retesting of defective workmanship or materials
Contractor is responsible.
17. Variation
Contractor gets additional (reduction of) cost and extension
(or reduction) of time for completion.
18. Delays caused by authority
Contractor shall follow formal procedure thoroughly. If there
is a delay, this is considered delay by authority. If this is
considered unforeseeable, additional time for completion(only) will be given.
-
8/4/2019 Awareness 2007 FIDI1C
26/31
decorient
PT Decorient Indonesia 26
RISK ALLOCATION
19. Suspension of Works
Extension of time and additional cost is given, except if the
suspension by Engineer is caused by Contractors default.
20. Defective design
Employer is responsible.
21. Defective materials or workmanship
Contractor is responsible.
-
8/4/2019 Awareness 2007 FIDI1C
27/31
decorient
PT Decorient Indonesia 27
RISK ALLOCATION
22. Change in Legislation
Contract Price will be adjusted, up or down, following
changes in legislation.
If change in legislation causes delay of performance or
additional cost, this shall be reimbursed to the Contractor.
23. Delayed certification and payment
Delay certification entitles the Contractor to suspend the
Works after notification, and to terminate.
Delay in payment entitles the Contractor to suspend the
Works after notification and to terminate. In addition,
Contractor entitles to interest.
-
8/4/2019 Awareness 2007 FIDI1C
28/31
decorient
PT Decorient Indonesia 28
RISK ALLOCATION
24. Fluctuating exchange rate
Contractors risk as far as foreign currency expenses.
25. Fluctuating market price
It is an option to always adjust the Contract Price based on
indices of prices.
-
8/4/2019 Awareness 2007 FIDI1C
29/31
decorient
PT Decorient Indonesia 29
RISK ALLOCATION
26. Termination by Employer
Employer is entitled to terminate the Contract and remove
Contractor from site, if the Contractor is in substantially
breaches the Contract.
27. Non payment or bankruptcy of Employer Contractor can terminate the Contract if Employer not
paying or bankrupt.
Contractor gets payment for works executed plus payment of
loss of expected profit and other losses.
-
8/4/2019 Awareness 2007 FIDI1C
30/31
decorient
PT Decorient Indonesia 30
RISK ALLOCATION
28. Bodily injury, sickness or death
Contractor is responsible for any injuries etc. to any person,
from whatever cause, except caused by Employers willful act,
negligence or breach of Contract.
Thus, sickness of Employers personnel due to unexplainedcause must be all taken care of by the Contractor.
29. Damage to property other than the Works
Employer is responsible for damage to property other than
the Works, from whatever cause, except caused by
Contractors willful act, negligence or breach of Contract.
-
8/4/2019 Awareness 2007 FIDI1C
31/31
decorient
PT Decorient Indonesia 31
RISK ALLOCATION
30. Damage the Works due to Employers Risks (e.g. force
majeure)
Damage to the Works by force majeure is at Employers cost.
31. Breach of intellectual property
The party in breach is responsible.
32. Deductible and amount not recovered by Insurance
Becomes the responsibility of the party where the risk lies.
Thus, in case of force majeure, the Employer will bear the
deductible and any amount not recovered by Insurance