awareness 2007 fidi1c

Upload: alex-angkawijaya

Post on 07-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 Awareness 2007 FIDI1C

    1/31

    decorient

    PT Decorient Indonesia

    Contractual Awareness Course

    10 December 2007

    FIDIC

    Federation Internationale des Ingenieurs Counseils

    FIDIC FIDIC FIDIC FIDIC FIDIC

    FIDIC FIDIC FIDIC FIDIC FIDICFederation Internationale des Ingenieurs Counseils

  • 8/4/2019 Awareness 2007 FIDI1C

    2/31

    decorient

    PT Decorient Indonesia 2

    OBJECTIVE

    1. Know where to find FIDIC general conditions in a contract

    document.

    2. Know what FIDIC is.

    3. Know several General Conditions of Contract (GCC).4. Aware that FIDIC GCC can be freely modified.

    5. Aware that one can not refer to FIDIC if it is not chosen.

    6. Know the principles of risk allocation by FIDIC.

  • 8/4/2019 Awareness 2007 FIDI1C

    3/31

    decorient

    PT Decorient Indonesia 3

    CONTRACT DOCUMENTS

    1. The Agreement;

    2. Form of Tender and Attachments;

    3. Special Conditions of Contract;

    4. General Conditions of Contract;5. Method of Measurement;

    6. Bill of Quantities;

    7. Drawings;

    8. Specifications;

    9. Correspondences.

  • 8/4/2019 Awareness 2007 FIDI1C

    4/31

    decorient

    PT Decorient Indonesia 4

    ORDER OF PRIORITY

    1. In case of discrepancy between several documents forming part of theContract Document, an order of priority should be used.

    2. Order of priority is set by the Employer.

    3. Typical order of priority:

    1. The Agreement;2. Letter of Award;

    3. Form of Tender;

    4. Special Conditions of Contract;

    5. General Conditions of Contract;

    6. Specification;

    7. Drawings;

    8. Bill of Quantity.4. A description in low priority document must be checked against

    contradicting description in higher priority document, e.g: Thickness of glass is 8 mm in the Bill of Quantity, but is 10 mm in the

    Specification 10 mm thick shall be used

  • 8/4/2019 Awareness 2007 FIDI1C

    5/31

    decorient

    PT Decorient Indonesia 5

    DISCREPANCY VS COMPLIMENTARY

    1. If the Specification says 10 mm thick glass and Drawing shows 8

    mm thick glass, then this is discrepancy.

    2. If the Specification says 10 mm thick glass and Drawing does not

    mention anything, then this is not a discrepancy, butcomplimentary.

  • 8/4/2019 Awareness 2007 FIDI1C

    6/31

    decorient

    PT Decorient Indonesia 6

    GENERAL CONDITIONS OF CONTRACT

    Is the rules of the game, contain amongst others:

    The rights and responsibility of the Employer;

    The authorities of the Engineer (Employers Project Manager);

    The rights and responsibility of the Contractor; Allocation of risks;

    Procedure for assuring quality;

    Procedure for assuring timely execution;

    Measurement and payment;

    Variation; Insurance;

    Dispute resolution;

    Etc.

  • 8/4/2019 Awareness 2007 FIDI1C

    7/31

    decorient

    PT Decorient Indonesia 7

    STANDARD FORMS OF GENERAL

    CONDITIONS1. FIDIC (Federation Internationale des Ingenieurs Counseils);

    2. JCT (Joint Contracts Tribunal);

    3. ICE (Institution of Civil Engineers);

    4. SIA (Singapore Institute of Architect);

    5. AIA (American Institute of Architect);

    6. Standard Form for Use in Hongkong.

  • 8/4/2019 Awareness 2007 FIDI1C

    8/31

    decorient

    PT Decorient Indonesia 8

    FIDIC

    Federation Internationale des Ingenieurs Counseils (FIDIC) means

    International Federation of Consulting Engineers.

    Founded in 1913 by 3 national associations of independentconsulting engineers within Europe. Today FIDIC membership

    numbers 74 Members Associations around the world (1 member

    association for each country).

    From Indonesia: INKINDO.

  • 8/4/2019 Awareness 2007 FIDI1C

    9/31

    decorient

    PT Decorient Indonesia 9

    COMMON USEOF FIDIC GCC

    Projects with loan from the World Bank.

    Private funded building projects in Indonesia where the QS is DLS,

    EC Harris, Korra.

  • 8/4/2019 Awareness 2007 FIDI1C

    10/31

    decorient

    PT Decorient Indonesia 10

    SEVERAL FIDIC GCC

    FIDIC GCC for Construction

    1st edition 1957

    2nd edition 1969

    3rd edition 1977

    4th edition 1987 amended 1992

    5th edition 1999

    FIDIC GCC for Design and Build FIDIC GCC for EPC and Turnkey

  • 8/4/2019 Awareness 2007 FIDI1C

    11/31

    decorient

    PT Decorient Indonesia 11

    FREE CHOICE

    The Employer is free to choose which FIDIC he will use. He

    can use FIDIC 1969 like Qatar Embassy.

    Later version of FIDIC does not automatically overrule earlier

    revision.

    If a contract does not use FIDIC Conditions of Contract,

    parties to the contract can not rely on FIDIC clauses.

    However, FIDIC may be appealing to fill out the void left by an

    incomplete conditions of contract. Thus FIDIC is not a governing rule, it becomes rules for the

    parties who chose it.

  • 8/4/2019 Awareness 2007 FIDI1C

    12/31

    decorient

    PT Decorient Indonesia 12

    FREE MODIFICATION

    FIDIC General Conditions of Contract is freely modified by

    the Employer, by the use of Conditions of Particular

    Application (or Special Conditions of Contract). e.g:

    FIDIC GCC states that Employer shall provide a proof of his

    ability to pay the Project.

    Particular Application can delete this provision.

  • 8/4/2019 Awareness 2007 FIDI1C

    13/31

    decorient

    PT Decorient Indonesia 13

    RISK INVENTORY

    1. Ambiguity or discrepancy of contract document.

    2. Delay issue of drawing or instruction from the Employer.

    3. Delay submission of Contractors Documents.4. Employers compliance with planning, zoning and other

    permit for Permanent Works.

    5. Compliance with any regulation for the execution of the

    Works by the Contractor.

  • 8/4/2019 Awareness 2007 FIDI1C

    14/31

    decorient

    PT Decorient Indonesia 14

    RISK INVENTORY

    6. Employers delay in giving right of access to the Site.

    7. Non performance of Contractors subs.

    8. Interrelationship with other parties in the Project.9. Employer error in giving points of reference or bench

    marks.

    10. Contractors failure to collect or interpret Site Data.

    11. Unforeseeable Physical condition.

  • 8/4/2019 Awareness 2007 FIDI1C

    15/31

    decorient

    PT Decorient Indonesia 15

    RISK INVENTORY

    12. Delay or failure of the Employer to give free issued

    materials .

    13. Finding of geological or archaeological interest.

    14. Nominated Subcontractor.

    15. Engineer delaying tests.

    16. Retesting of defective workmanship or materials.

    17. Variation.

    18. Delays caused by authority.19. Suspension of Work.

  • 8/4/2019 Awareness 2007 FIDI1C

    16/31

    decorient

    PT Decorient Indonesia 16

    RISK INVENTORY

    20. Defective design.

    21. Defective material or workmanship.

    22. Change in legislation.

    23. Delayed certification and payment.

    24. Fluctuating exchange rate.

    25. Fluctuating market price of goods or services.

    26. Termination by the Employer.

    27. Non payment or bankruptcy of Employer.28. Bodily injury, sickness or death during Construction.

  • 8/4/2019 Awareness 2007 FIDI1C

    17/31

    decorient

    PT Decorient Indonesia 17

    RISK INVENTORY

    29. Damage to property other than the Works.

    30. Damage to the Works caused by Employers Risks.

    31. Breach of intellectual property.

    32. Deductibles of insurance and amount not recovered from

    insurance.

  • 8/4/2019 Awareness 2007 FIDI1C

    18/31

    decorient

    PT Decorient Indonesia 18

    RISK ALLOCATION

    WHAT DO YOU THINK IS FAIR AND REASONALBE

    FOR THE EMPLOYER AND THE CONTRACTOR IF

    THE FOLLOWING RISKS OCCUR??

  • 8/4/2019 Awareness 2007 FIDI1C

    19/31

    decorient

    PT Decorient Indonesia 19

    RISK ALLOCATION

    1. Ambiguity or discrepancy of contract document Ambiguity and discrepancy between contract document is the

    risk of the Employer.

    The Contractor based his price on the order of priority. If other interpretation is required, the Engineer will issue aVariation order.

    2. Delay issue of drawing or further instruction from theEmployer

    The Employer must provide drawing or instruction withinreasonable time to enable the Contractor to proceed with theWorks without interruption. If drawing or instruction aregiven late and disrupt the Works, the Contractor can requestadditional cost and or extension of time.

  • 8/4/2019 Awareness 2007 FIDI1C

    20/31

    decorient

    PT Decorient Indonesia 20

    RISK ALLOCATION

    6. Employers delay in giving right of access to the Site

    Can result in additional cost and delay. Employer is

    responsible .

    7. Non performance of Contractors subs

    Can result in additional cost and delay. Contractor is

    responsible.

    8. Interrelationship with other parties in the Project

    Employer, employers contractors, authority must be allowedreasonable opportunity to carry out their works. If

    Contractor incurs Unforeseeable Cost, he will be reimbursed.

  • 8/4/2019 Awareness 2007 FIDI1C

    21/31

    decorient

    PT Decorient Indonesia 21

    RISK ALLOCATION

    9. Employer error in giving points of reference or bench

    marks.

    Setting out of the Works by Contractor using points of

    reference supplied by the Employer. Contractor must use

    reasonable effort to check accuracy. If errors are found afterthat, after reasonable effort of an experienced contractor, then

    Employer will reimburse Contractor for additional cost or

    delay.

    10. Contractors failure to collect or interpret Site Data

    If data is supplied by the Employer, then the Employer isresponsible for accuracy of such data, but the Contractor is

    responsible for interpretation of such data.

    If data is incomplete, Contractor must complete by itself

  • 8/4/2019 Awareness 2007 FIDI1C

    22/31

    decorient

    PT Decorient Indonesia 22

    RISK ALLOCATION3. Delay submission of Contractors Documents

    This can result in additional cost or delay. All to be borne by

    the Contractor.

    4. Employers compliance with planning, zoning and otherpermit for Permanent Works.

    Unavailability of permanent permit can create additional cost

    and extension of time. This is to be borne by the Employer.

    5. Compliance with any regulation for the execution of the

    Works by the Contractor. This is Contractors responsibility

  • 8/4/2019 Awareness 2007 FIDI1C

    23/31

    decorient

    PT Decorient Indonesia 23

    RISK ALLOCATION

    11. Unforeseeable Physical condition

    In event of adverse physical conditions which is not

    foreseeable by an experienced contractor, delay and

    associated cost is compensated by the Employer.

    But if unforeseen is more favorable, there will be costreduction, with total reduction shall not reduce Contract

    Price.

    12. Delay or failure of the Employer to give free issued

    materials

    Employer is responsible for the delay or additional cost

    arising

  • 8/4/2019 Awareness 2007 FIDI1C

    24/31

    decorient

    PT Decorient Indonesia 24

    RISK ALLOCATION

    13. Finding of geological or archaeological interest

    Fossils shall be treated as required by the Engineer and

    associated cost or delay will be reimbursed.

    14. Nominated Subcontractor

    Nominated Subcontractor (NSC) is a contractor nominated

    by the Employer but enters into subcontract with the

    Contractor.

    Performance of NSC is Contractors responsibility.

    15. Engineer delaying tests Testing of the Works is carried out in the presence of

    Engineer with prior appointment. If Engineer delays,

    associated cost and delay will be reimbursed.

  • 8/4/2019 Awareness 2007 FIDI1C

    25/31

    decorient

    PT Decorient Indonesia 25

    RISK ALLOCATION

    16. Retesting of defective workmanship or materials

    Contractor is responsible.

    17. Variation

    Contractor gets additional (reduction of) cost and extension

    (or reduction) of time for completion.

    18. Delays caused by authority

    Contractor shall follow formal procedure thoroughly. If there

    is a delay, this is considered delay by authority. If this is

    considered unforeseeable, additional time for completion(only) will be given.

  • 8/4/2019 Awareness 2007 FIDI1C

    26/31

    decorient

    PT Decorient Indonesia 26

    RISK ALLOCATION

    19. Suspension of Works

    Extension of time and additional cost is given, except if the

    suspension by Engineer is caused by Contractors default.

    20. Defective design

    Employer is responsible.

    21. Defective materials or workmanship

    Contractor is responsible.

  • 8/4/2019 Awareness 2007 FIDI1C

    27/31

    decorient

    PT Decorient Indonesia 27

    RISK ALLOCATION

    22. Change in Legislation

    Contract Price will be adjusted, up or down, following

    changes in legislation.

    If change in legislation causes delay of performance or

    additional cost, this shall be reimbursed to the Contractor.

    23. Delayed certification and payment

    Delay certification entitles the Contractor to suspend the

    Works after notification, and to terminate.

    Delay in payment entitles the Contractor to suspend the

    Works after notification and to terminate. In addition,

    Contractor entitles to interest.

  • 8/4/2019 Awareness 2007 FIDI1C

    28/31

    decorient

    PT Decorient Indonesia 28

    RISK ALLOCATION

    24. Fluctuating exchange rate

    Contractors risk as far as foreign currency expenses.

    25. Fluctuating market price

    It is an option to always adjust the Contract Price based on

    indices of prices.

  • 8/4/2019 Awareness 2007 FIDI1C

    29/31

    decorient

    PT Decorient Indonesia 29

    RISK ALLOCATION

    26. Termination by Employer

    Employer is entitled to terminate the Contract and remove

    Contractor from site, if the Contractor is in substantially

    breaches the Contract.

    27. Non payment or bankruptcy of Employer Contractor can terminate the Contract if Employer not

    paying or bankrupt.

    Contractor gets payment for works executed plus payment of

    loss of expected profit and other losses.

  • 8/4/2019 Awareness 2007 FIDI1C

    30/31

    decorient

    PT Decorient Indonesia 30

    RISK ALLOCATION

    28. Bodily injury, sickness or death

    Contractor is responsible for any injuries etc. to any person,

    from whatever cause, except caused by Employers willful act,

    negligence or breach of Contract.

    Thus, sickness of Employers personnel due to unexplainedcause must be all taken care of by the Contractor.

    29. Damage to property other than the Works

    Employer is responsible for damage to property other than

    the Works, from whatever cause, except caused by

    Contractors willful act, negligence or breach of Contract.

  • 8/4/2019 Awareness 2007 FIDI1C

    31/31

    decorient

    PT Decorient Indonesia 31

    RISK ALLOCATION

    30. Damage the Works due to Employers Risks (e.g. force

    majeure)

    Damage to the Works by force majeure is at Employers cost.

    31. Breach of intellectual property

    The party in breach is responsible.

    32. Deductible and amount not recovered by Insurance

    Becomes the responsibility of the party where the risk lies.

    Thus, in case of force majeure, the Employer will bear the

    deductible and any amount not recovered by Insurance