awpr scheme testing · asam3 - awpr scheme testing economic and environmental murtle, milltimber...

14
TRANSPORT SCOTLAND AWPR Scheme Testing Summary: This report provides a synopsis of the scheme testing comparison carried out by MVA Consultants for the Scottish Executive prior to the announcement on 1 December 2005 that the AWPR would be taken forward on the Milltimber Brae Route with a spur south to Stonehaven. The report was provided to assist in the decision making process and contains technical information.

Upload: others

Post on 16-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

TRANSPORTSCOTLAND

AWPR Scheme Testing

Summary: This report provides a synopsis of the scheme testing comparison carriedout by MVA Consultants for the Scottish Executive prior to the announcement on 1December 2005 that the AWPR would be taken forward on the Milltimber Brae Routewith a spur south to Stonehaven. The report was provided to assist in the decisionmaking process and contains technical information.

Page 2: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

I~

ASAM3 - AWPR Scheme Testing

Economic and Environmental

Murtle, Milltimber and Milltimber Brae Upgrade (N29)

> This presentation contains the following analysis of AWPR mode1 runs using ASAM3:

> Economic Analysis

> Accident Analysis

> Environmental Analysis

> The information has been prepared to a general specification and to provide indicativeresults for an additional scheme option - Milltimber Brae upgrade (N29).

> The scheme has been included in the absence of detailed engineering assessment andthe costs have been prepared in the absence of detailed design, but approximate and in

accordance with previous alignment test options.

> Further information can be tailored\refined to suit if required following a review of the

contents.

1

Page 3: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

I~> Economic assessment has been undertaken using the TUBA ec6nomic software

package version 1.6c. This version used the following parameters:

> Modelling is based on 2010 and 2025 forecast demand model runs;

> Costs Benefits are discounted to 2002 prices;

> Costs calculated in the absence of engineering design;

> 30 and 60 year appraisal undertaken with and without Optimism Bias;

> 3.5% discount rate;

> No residual Value adjustments;

> Annualisation factors of :

> 616 AM Peak Hours;

> 3978 Inter Peak Hours; and

> 683 PM Peak Hours.

I~Efftclency Pre.nt Value or Benefit to ColI:

Bene'UatpY8) CoS8(PVC) RaUo (BCR)

Emclancy Pre.nt Value of Bene"' to eo.&.neJlr.(pVB) CoeIa(pYC) Rallo (BCR)

Mur'tle (p03)v.Ra' c._

__ .~, . (R04)MlJUlmbe, B •.•• (N2O)"

~rc._(R04)

MlllllmbM era. IJpgnlda(N29) .,. R.t Ce_ (R04)

97~7

1171921

281176

341094

412928

3.•••

2.818

2.838

>

>

For all test options, Murtle Route (P03)demonstrates the highest BCR value.

Milltimber Brae Upgrade (N29) costs

have been estimated as Militimber+B797

upgrade and therefore mayover-estimate costs.

EftIciency Pre.n! Value ot Benent k) CcHII

Benenw{pVB) Coa{pVC) Rado(BCR)

Emclancy Pre.nt Value 01 a_noJlIIO eo.Beneflt8 (PVB) Colts (pYC) Rallo (BCR)

•. 302

273140 5.~

Where appropriate, optimism bias has

been applied to the costs at a rate of

32%, in line with the DFT guidance.

Although N29 does not produce the

highest BCR, it does produce the

highest Efficiency Benefits by around

20%.

> It would be envisaged that a refinement

of costs for N29 would result in a cost

reduction and consequent BCR

increase.

>

>

4.653

5.833

3.791

4.787

4.592

3.741

7.555

407547

212168

352130

313298

214323

974207

984367

1819236

1950735

1171921

1819236

1950735

1""",,

Mur'tI.(P03) ••••R.,C..(RO<)

MllldmberBrH(H20)_

AlII c.. (R04)

MinImbet' Brae Upgrade(N29) vaR.I Ca. (R04)

yurt. (P03)nRarc..·_ (RO<)

MllltimberBr .•• (N20) ••••

ReI c._ (R04)MlJlllmber BrH lJpgt'aM

(N29) ••••R.rc..(R04)

60 Vear (No OIIlImllm 81 •• )

Murla (p03).,.Rarc._(A")

UllJtlmberB •.•• (N2O)v"-1M' c._ (R04)

.- MWllmt* BrH Upgrade

(N29) va Ref c..CROll

30 Vear (No Optlmllm BI •• )

2

Page 4: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

I~> Accident assessment undertaken using the ACCDNT software package.

> ACCDNT model conforms to the NESAICOBA 11 (Network Evaluation from Surveys andAssignments/Cost Benefit Analysis conditions set out in the 2002 NESA Manual in theDesign Manual for Roads and Bridges.

> Three categories of personal injury accident are: fatal, serious and slight.

> Accident rates quoted are per year.

I~Nurrber d Accident Casualtias Forecast

AccIdent Sa. Year Ref. Ce_ Ref. Ca_ Mlllttmber Brae MlllUmber Brae MIllUmber Bra. Mllttlmber BraeType (2002) (2010) (2025) Murtle (2010) Murtle (2025) (2010) (2025) Upgrod. (2010) Upgrod. (2025)Fewl 17 13 13 '3 '2 '2 '2 '2 11

Serlou '65 120 118 116 113 116 113 115 112Slight 1208 '245 1218 1210 1179 1213 1180 '202 1172Totall 1389 1378 '349 '338 '304 1340 '304 ,= '296

Change in Accident Casualties Forecast

AccIdent Ref. Ca_ Ref. Ca. Mllltimber Mllltimber Brae MIllUmber Brae Mllltimber Bra.Type (2010) (2025) Mu01I. (2010) Mul1l. (2025) Bro. (2010) (2025) Upgrade (2010) Upgrade (2025)Fatal -4 -4 -, -, -, ., ., .,

Serloua -45 -47 -5 -6 -5 -6 -5 -6--Slight 37 10 -34 -40 -32 -39 -42 -46

Total ·11 -40 -40 -45 -38 -45 -46 -53

Cost of Accidents Forecasts (£1,000s)Be. V.ar

(2002)£74,241£74,241

V •• r20102025

Rof. c.ao£74.800E98,408

Murtle£72,013£94,120

MIIIUmberBr ••

E72,055E94,065

Mllttlmbererae Upgrade

E71,698£:93,7'9

Cha.!28 in cOsts of Accidents Forecasts (£1,0005)

Year20102025

Ref. ea.E649

£24,167

Murtl_·<2,878-£4,281

MllltimberBro.

·<2,836·E4,343

MIliUmberBra. Upgrade

-£3.192-E4,689

3

Page 5: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

> Accident rates per km of road link type are forecast to reduce over time (this is fixedwithin accident analysis and therefore, despite increases in traffic flows, it is stillanticipated that numbers of accidents will decrease.)

> All three scheme (Murtle, Milltimber and Milltimber Brae upgrade) demonstrate areduction in accident casualties over the Reference Case (R04). This is consistent forboth the 2010 and 2025 forecast years and a consequence of moving traffic away fromurban links~unctions to more rural un-interrupted flow.

> The Milltimber Brae scheme (N20) gives a similar number of casualty reductions to theMurtle scheme in both forecast years.

> The Milltimber Brae Upgrade scheme (N29) gives additional casualty reductions overand above those of the Murtle and Milltimber Brae schemes.

> Each test option reduces the categories of casualties (fatal, serious and slight) belowReference Case levels and the majority of reductions are in slight casualties in everycase.

IMCW

> The Reference Case scenario illustrates that although accident casualties are forecastto decrease over time, the costs associated with each casualty will rise over time,leading to a total increase in accident costs.

> The Murtle (P03) and Milltimber Brae (N20) schemes reduce accident costs belowReference Case levels in each forecast year by a similar amount.

> The Milltimber Brae Upgrade scheme (N29) produces a further reduction in futureaccident costs with respect to the Reference Case over and above those of the Murtleand Milltimber Brae schemes.

4

Page 6: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

> The environmental analysis in this report is based on the 2010 model year. Similaranalysis can also be undertaken for other modelled years.

> Environmental analysis has been undertaken using the ENEVAL software package.

> ENEVAL conforms to the guidance and methodologies described in Design Manual forRoads and Bridges, Volume 11, Section 3.

> ENEVAL is capable of analysing link and user defined region based:

> Carbon Monoxide (CO);

> Hydrocarbons (THC);

> Various oxides of Nitrogen (NOx);

> Particulates (PM10); and

> Carbon Dioxide (C02) emissions.

> Results for CO2 and NOx are presented in both tabular and graphical format in this report.

Key to diagrams:

C02 EMISSIONSMY~ versus Reference Case

• increase•••• decrease

The following maps show increases anddecreases of link based emissions for CO2and NOx relative to the Reference Case or toanother Test Option.

As can be seen from the key above, greenrepresents the magnitude of decrease, whilered represents the increases in emissions.

Please note that these maps do not representdispersion models.

5

Page 7: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

Milltimber Brae Upgrade (N29)

Percentage change in Regional CO2emissions shown below.

MiltimberBrae Upgrade

-5%-9%-8%14%-4%2%

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

Link based CO2 emissions (tonnes per km)increase along the AWPR alignment anddecrease within Aberdeen City and AberdeenSouth relative to the Reference Case (2010).

Murtle Alignment (P03)

Percentage change in Regional CO2emissions shown below.

MurtleAlignment

-5%-9%-5%13%-2%3%

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

Link based CO2 emissions (tonnes per km)increase along the AWPR alignment anddecrease within Aberdeen City relative to theReference Case (2010).

6

Page 8: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

Percentage change and difference in RegionalCO2 emissions are shown below.

Milltimber Brae Upgrade (N29)compared to Murtle Alignment (P03)

%Difference

0%0%

-4%0%

-2%-1%

MiltimberBrae

Upgrade-5%-9%-8%14%-4%2%

MurtleAlignment

-5%-9%-5%13%~2%3%

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

Compared to Murtle Alignment, link basedCO2 emissions (tonnes per km) increases onthe A96 and (as one would expect) the 8979while the A90 South between Charleston andStonehaven CO2 emission decreases.

Percentage change in Regional NOxemissions shown below.

Milltimber Brae Upgrade (N29)

Link based NOx emissions (tonnes per km)increase along the AWPR alignment,decrease within Aberdeen City and along A90South relative to the Reference Case (2010).

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

Miltimber BraeUpgrade

-4%-8%-7%12%-3%2%

7

Page 9: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

Murtle Alignment (P03)

Percentage change in Regional NOxemissions shown below.

Link based NOx emissions (tonnes per km)increase along the AWPR alignment anddecrease within Aberdeen City relative to theReference Case (2010).

MurtleAlignment

-4%-8%-4%11%-1%3%

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

Percentage change and difference in RegionalNOx emissions are shown below.

Milltimber Brae Upgrade (N29)compared to Murtle Alignment (P03)

Compared to Murtle Alignment, link basedNOx emissions (tonnes per km) increase onthe A96 and (as one would expect) the 8979while the A90 South NOx emissions decrease.

%Difference

0%0%

-3%1%

-2%-1%

MiltimberBrae

Upgrade-4%-8%-7%12%-3%2%

MurtleAlignment

-4%-8%-4%11%-1%3%

Aberdeen City CentreAberdeen NorthAberdeen SouthAberdeenshire NorthAberdeenshire SouthTOTAL

8

Page 10: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

> The following graphs illustrate the percentage change in CO, THC, NOx, PM10 and CO2

emissions of the three different AWPR alignments relative to the Reference Case for

2010.

> These alignments are:

> Murtle Alignment (P03);

> Milltimber Brae Alignment (N20); and

> Milltimber Brae Upgrade (N29).

> The results are classified by modelregions. The illustration on this pageprovides a key to the regions.

> This region system is inherited from theASAM model development and could bealtered to suit if required and further

analysis can be undertaken todemonstrate emissions figures at a moreaggregate\disaggregated level.

> Key:

o Aberdeen City

f} Aberdeen North

@ Aberdeen South

e Aberdeenshire North

o Aberdeenshire South

9

Page 11: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

20%

'5%

10%

j 5%

iJ 0%~

-5%

-10%

-15%

[] "-irtle Nignmenl • Mllimber Brae C Mltimber Brae Upgrade

20%

10%

1 5%

i~ 0%

-5%

-10%

-15%

~e Alignment. "'lUmber Brae [] ",Ilimber Brae Upgrade I

10

Page 12: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

20%

15%

10%

I 5%

!j:] 0%

-5%

-10%

-15%

C M.lr1Ie Alignmenl. "'timber Brae CMtlimberBrae Upgrade

20""" --

15%

10% ..•.-

I5%

j:] 0%

-5%

-10%

-15%

D MJr1Ie Alignment. M!timber Brae C Mltimber Brae Upgrade

11

Page 13: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

20''/0

15%

5%

0%

·5%

-10%

-15%

C MH1Ie Alignment • MI~mber Brae [] Mllimber Brae Upgrade

> The table below presents the percentage change in all emissions relative to theReference Case.

> In terms of the total emissions, Milltimber Brae Upgrade produces the lowest value whilethe Murtle alignment produces the highest of the three test options analysed.

COTHCNOXPM10C02

MurtleAlignment

1.3%0.1%2.7%4.8%3.0%

MilltimberBrae

0.9%-0.2%2.3%4.3%2.6%

MilltimberBrae

Upgrade0.2%

-0.8%2.1%3.7%2.3%

N.S, Negative number represents reduction while positive numbers represent increase in emissions compared to theReference Case.

12

Page 14: AWPR Scheme Testing · ASAM3 - AWPR Scheme Testing Economic and Environmental Murtle, Milltimber and Milltimber Brae Upgrade (N29) > This presentation contains the following analysis

> If it is agreed that further investigation should be made into the Milltimber Brae upgrade(N29) option:

> A refined definition of the scheme, including junction layouts at Charleston andMilltimber and link specification between these locations should be undertaken;

> Consequent revisions to the Capital and Land Purchase costs associated with thescheme should be prepared;

> A refined economic, operational and (if required) environmental summary couldthen be prepared.

13