axter hydropack and sedum mat installation and maintenance ... · axter hydropack and sedum mat...
TRANSCRIPT
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 1
AXTER HYDROPACK AND SEDUM MAT
INSTALLATION AND MAINTENANCE
GUIDE
June 2009
HYDROPACK
HYDROPACK trays are designed to be placed next to each other directly onto the waterproofing
membrane.
HYDROPACK trays are linked together using the attachment system between modules on the “male”
sides of each tray.
It is important to position the ‘V’ shaped attachment profiles
carefully so that the trays are correctly attached with no space
between them and so that water can pass easily from one tray
to another. (The fixing system is designed to allow circulation
of water from tray to tray). If there is a space between two trays it is because a ‘V’ shaped
hook is not in the correct position. In this case lift the tray and
re-position it so it slots into the neighbouring tray.
DIRECTION IN WHICH TRAYS SHOULD BE LAID: Installation should take place from left to
right by positioning the first tray with “male” hooks pointing to the edge of the roof (towards the verge).
Install subsequent trays in a row before coming back to install the adjacent row, and so on.
“male” side of
the tray
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 2
Slide each tray carefully into position next to the neighbouring tray without allowing too much of an angle
during the installation procedure; this reduces the risk of catching the filter layer of the adjacent tray on
the fixing lip situated at the base of the attachment channels.
INSTALLATION PATTERN
It is not necessary to install the HYDROPACK trays in a staggered formation. This would make the
installation procedure more complex and would necessitate detailed and lengthy cutting along upstands.
We recommend a traditional pattern of installation (corner to corner, side by side).
NOTE: the trays are designed to allow them to be joined in a perpendicular fashion short side with long
side) to allow a simple installation pattern.
NO! OK!
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 3
SLOPING ROOFS
When laying Hydropack on slopes > 10° provision must be made to restrict slippage. This is normally in
the form a perforated metal angle bonded to the deck at a height just below that of the HYDROPACK
tray.
STERILE AREAS
Codes of practice governing green roof areas require that an area of a minimum 40cm square with no
sedum be left around rainwater outlets.
A min 40cm wide strip must also be left round upstands and at edges to facilitate water run-off, reduce
fire risk and to allow access to waterproofing details.
When the slope of the roof is greater than 3%, special measures should be taken in accordance with the current standards.
Green zone
Sterile zone
Separation screen
Vent pipe
Rain water outlet
Movement joint
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 4
These sterile areas should then be filled with min 20 / 40 washed rounded gravel.
Where the edge of the roof is not protected by a parapet or other upstand then a perforated metal or
aluminium angle must be bonded to the waterproofing.
WATERING AFTER INSTALLATION
HYDROPACK trays are delivered with varying levels of substrate saturation and water levels in the water
reservoir (depending on the amount of rainfall prior to despatch from the nursery). Transportation of the
trays also leads to a certain amount of “stress” of the plants.
Watering should take place once the trays have been installed. This will fill the water reservoir in the trays.
A site visit should take place approximately one month after installation to check that the vegetation is in
good condition.
See Maintenance Programme on page 6.
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 5
SEDUM MAT
1 Unroll the pre-cultivated mats on the substrate ensuring that:
• the rolls are unrolled in a staggered formation, as shown below.
Roll size: 2m x 1.2m approximately.
mat
• that the sections of mat are positioned as closely as possible to each other, bearing in mind
that there will be a slight shrinkage of the mat in dry periods.
• the substrate on which the mat is installed is not deformed in any way (to avoid air pockets
appearing under the sedum mat). To achieve this, walk along the side of the rolls already
installed and press down with a rake before unrolling more mat.
It is imperative that the mat is unrolled within 24 hours of arrival on site at the latest. If for some reason
installation will not be finished within this time, do not leave the mat rolled up. The vegetation will
wither through lack of air.
2 Cut the mat where necessary with a sharp cutter or knife, taking care not to damage the
waterproofing membrane during the process.
A site visit should take place approximately one month after installation to check that the vegetation is in
good condition.
The recommended number of inspections is two per year.
See Maintenance Programme on page 6.
Cut sections
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 6
MAINTENANCE PROGRAMME
Two visits should be made after installation of the vegetation:
• the first a month later to ensure that the vegetation is in a good condition and to observe any anomalies.
• the second 3 to 6 months later to verify the root growth and to effect any reinstatement that may be necessary.
After the initial maintenance described above, during the first year it is recommended that at least two
maintenance visits are made to the roof each year. The first should be at the beginning of spring and the
second in the autumn, after leaf fall.
The table below gives an indicative work plan for each visit.
During installation
Standard maintenance
Remove all vegetation, debris etc from rainwater outlets and on the
sterile areas. � �
Manually remove any herbaceous material that may be detrimental to
the waterproofing (woody shrubs…). � �
Remove any leaves (leaves may stifle the vegetation and block rain
water outlets). � �
Manually remove any aesthetically unpleasing vegetation which may
affect the waterproofing membranes (e.g. grass..).
Optional
Dead head the sedum. Optional Optional
Use of Fertiliser: It is recommended that a slow release fertiliser is
applied to the Hydropack at the start of spring and to the sedum mat
twice a year (25gm/m2), preferably in March and September.
A product such as Osmocote Exact (produced by Scotts) with a
formula NPK 15-9-9 should be applied by a hand spreader to ensure
even coverage.
�
Water after installation of the packs/mats: especially during
prolonged dry periods or periods of high temperatures. Take care
not to over water.
�
Water during summer periods or prolonged dry periods. As required
Re-plant any missing sedum fragments . As required As required
Minimum number of maintenance visits per year. 2
Axter Hydropack and Sedum Mat Installation and Maintenance Guide 7
Important reminders:
The principal conditions that restrict growth of sedum:
- An excess of shade
- Excess of water or prolonged dry periods
- The proximity of glazed bays
Access to water is required for each roof. This will enable watering to take place when required (notably during times of prolonged dry weather).
For further information or assistance please do not hesitate to contact Axter Ltd.
Axter Ltd, West Road, Ransomes Europark, Ipswich Suffolk IP3 9SX Tel: 01473 724056 Fax: 01473 723263; email: [email protected]
www.axter.co.uk