back pressure steam turbine generators
DESCRIPTION
Toshiba Back PressureTRANSCRIPT
BACKPRESSURE STEAM TURBINE-GENERATORS: TECHNOLOGY AND MARKET
OPPORTUNITIESPresentation to
Regional CHP Center/Initiative Face-to-Face MeetingOak Ridge National Laboratory
Washington DCMay 2, 2006
Sean CastenChief Executive Officer
161 Industrial Blvd.Turners Falls, MA 01376
www.turbosteam.com
Creating Value from Steam Pressure
Understanding 75% of US power generation in 30 seconds or less…
Rankine Power PlantRankine Power Plant
Fuel(Coal, oil, nuclear, gas, etc.)
High Pressure Steam
Heat to atmosphere
Low Pressure
Steam
Low Pressure
Water
Pump
Boiler
Cooling Tower
High Pressure
Water
Electricity to Grid
Steam Turbine Generator
Understanding thermal energy plants in 30 seconds or less…
Thermal Energy PlantThermal Energy PlantPressure Reduction Valve(s)
Fuel
High Pressure Steam
Heat to load
Low Pressure
Steam
Low Pressure
Water
Boiler Pump
Boiler
Thermal load (kiln, dormitory, etc.)
High Pressure
Water
The opportunity
Fuel
Heat to load
Boiler Pump
Boiler
Thermal Load
Electricity to Plant Bus
IsolationValve Isolation
Valve
Steam Turbine Generator
Several non-intuitive benefits of this approach.
• Operating Savings: The presence of the thermal load makes this generation ~ 3X as efficient as the central power it displaces.• More efficient than most other CHP technologies because all of input
energy is recovered (comparable to a gas turbine that uses 100% of hot exhaust gas as hot air for a process).
• Capital Savings: Since 75% of the power plant is already built, the effective (marginal) capital costs are quite low.• 1,000 MW Rankine plant typical capital costs ~ $1 billion ($1,000/kW)• 1 MW steam turbine generator integrated into existing facility typical
installed capital costs ~ $500,000 ($500/kW) • Turbosteam has done fully installed systems for as little as $300/kW
• Similar logic applies to non-fuel operating costs, since most of Rankine cycle O&M are in the boiler and cooling tower. Turbine-generator O&M costs are negligible.• Long term Turbosteam service contract on 1 MW unit ~ 0.1 c/kWh
Key differences from other CHP technologies.
• Defined by how the downstream thermal energy is used, not by the technology itself• Backpresssure = use LP steam. Condensing = dump LP steam
• Nationally, the dominant power generation technology• 75% of US power-only plants are steam turbines (MW basis)• 32% of all US CHP plants are steam turbines (MW basis)
• System economics depend upon heat recovery• Only regulated utilities (or waste heat/fuel applications) install
condensing turbines; all others rely on backpressure
• T:E ratio usually >10 for BPTGs (compare to 2 – 5 for other prime movers). • BPTG target markets fundamentally different from engines,
turbines, etc.
Operational and design considerations are backwards from “power first” CHP
• Design for thermal load, take power as near-free byproduct– Power-first approaches design for power need, take heat as byproduct
• “Recycled” commodity is the kWh, but heat costs $– In a power-first approaches heat is the recycled commodity
• Can design to 100% of thermal load, but rare to be able to design for 100% of electrical load.
– Power-first can be sized to electric demand, only recover heat that can be locally used.
• Power production can be base-loaded or thermal following depending on size relative to thermal load, but generally cannot follow electric load
– Power-first is exactly inverted from this approach
BUT – the two approaches can be synergistic. UMCP gas turbine + HRSG+ backpressure steam turbine is a great example.
Other design possibilities
• Thermal balance & fuel costs sometimes lead to excess steam in certain applications. When this happens, can make economic sense to combine BP and CX approaches to maximize power.
ElectricityHP Steam
LLP Steam to condenser
HP Steam
Condensing (CX) Configuration Backpressure/Condensing (BP+CX) Configuration
Electricity
LLP Steam to condenserLP Steam
to load
• Thermal plants are usually suboptimally designed for CHP. BPTG design often includes increases in boiler pressure and/or reductions in distribution pressure to boost power output. At the (confusing)extreme, this can enable condensing turbines in backpressure operation.
• Like all CHP, STGs (both CX and BP) can be designed to provide ancillary benefits in addition to kWh savings (e.g., enhance reliability, power factor)
We have installed 111 systems in the U.S., and 178 worldwide since 1986.
>10,000 kW
5001 – 10000 kW
1001 – 5000 kW
501 – 1000 kW
1 – 500 kW
NonNon--U.S.U.S.
• 17 countries• 67 installations• 37,091 kW
Worldwide installations, by industry
• Chemical/Pharmaceuticals 28• Food processing 21• Lumber & Wood Products 20• District Energy 19• Petroleum/Gas Processing 17• Colleges & Universities 16• Pulp & Paper 11• Commercial Buildings 10• Hospitals 8• Waste-to-Energy 6• Military Bases 5• Prisons 2• Textiles 1• Auto manufacturing 1
Some (heavily qualitative) thoughts on market opportunities
• Historically, market has been dominated by big energy users. Very common to see existing, 50+ year old BP (or extraction) installations of 10+ MW in integrated pulp & paper mills, big chemical plants, petroleum refineries.
• Conventional wisdom has long been that the economics don’t make sense at < 10 MW size range.– CW driven by a combination of historic utility hassle, the relative lack of
system integrators (like Turbosteam) who are interested in <10 MW projects and the relative lack of focus on energy costs in other industries
• CW is no longer valid. The market opportunity is therefore in those industries that:1. Have appropriate thermal/electrical needs2. Have not historically considered BPTGs because of CW
Where Turbosteam sees the biggest market opportunities
• In industries where individual facilities are big enough to have steady thermal loads, but not so big as to have historically focused on energy.– Paper mills (pulp and paper mills are more likely to have already invested)– Mid size (petro)chemical plants: formaldehyde, carbon black, etc.– Ethanol dry mills (wet mills are more likely to have already invested)– <10 MW opportunities in big facilities that flew under the radar of previous energy
investments
• In institutional applications where energy costs, reliability and environmental impact are becoming more important drivers.– Universities– Hospitals– Prisons
• In regions where there have been recent sudden increases either in energy costs or regulatory friendliness through barrier removal or incentive creation (ACEEE: volatility drives efficiency investments more than absolute energy cost)– Southeastern US – recent electric rate spikes– Ontario – big new gov’t incentives– VT, CT: states to watch
However, the design challenge posed by opportunities is different from that of power-first CHP.
• In a power-first application, the power generation is a fairly standard device, but the heat recovery unit requires custom-engineering
– Can pick a prime mover and power output fairly quickly, but then have an infinite number of ways to design the heat-recovery unit: there is no such thing as a standard, mass-produced heat recovery steam generator.
• In a heat-first application, the steam boiler is a fairly standard device,but the power-recovery unit requires custom engineering
– Boilers can be picked by frame size, but then have an infinite # of ways to design the steam turbine-generator, each with unique capital & operating cost characteristics: there is no such thing as a standard, mass-produced steam turbine.
Example of turbine-generator design complexities
Midwest Steel Mill PRV reduces 900 psig steam down to 150 psig for plant-wide distribution
50
100
150
200
250
300
350
1/1/
2003
2/1/
2003
3/1/
2003
4/1/
2003
5/1/
2003
6/1/
2003
7/1/
2003
8/1/
2003
9/1/
2003
10/1
/200
3
11/1
/200
3
12/1
/200
3
Stea
m F
low
, mlb
s/hr
640
660
680
700
720
740
760
780
800
820
Inle
t Ste
am T
emp,
o F
Steam FlowSteam Temperature
Design for Peak flow?• 11.9 MW rated power• 43.3 million kWh/yr• $1.4 million annual savings• 3 year simple payback
Design for baseload?• 2.4 MW rated power• 21.0 million kWh/yr• $672 K annual savings• 2.7 year simple payback
Sample customer’s financial optimization
0%5%
10%15%20%25%30%35%40%45%50%
150 200 250 300
Design Steam Flow (mlbs/hr)
15-y
ear R
OA
Gross ROAMarginal ROA
6.5 MW$1.44 million/year savings
10 MW$1.59 million/year savings
Optimal system is designed here to balance desires for rapid capital recovery, high annual cash generation AND effective use of free cash.
Rules of thumb for opportunity screening
Typical ValuesTypical Values Extreme ValuesExtreme Values
Target Financial Return <2 years simple payback from energy savings
Above-market returnsand/or
Non-financial drivers
Inlet Steam Pressure >150 psig 15 psig
Pressure drop across turbine-generator
>100 psig(P-ratio >3) 15 psig
Steam flow >10,000 lbs/hr 2,500 lbs/hr
Annual steam load factor >6 months/year 3 months/year
Local electricity rate >6 c/kWh >1.7 c/kWh