PROJECT TITLE: PROJECT LOCATION: ITEM SCOPE OF WORK DAYS 1-7 8-14 DURATION Jan 1 - Jan 7 Jan 8 - Jan 14 I. PRELIMINARIES II. EARTHWORKS/DEMOLITION WORKS III. CONCRETING AND FORMWORKS IV. MASONRY WORKS V. CEILING WORKS VI. WALL FINISHES VII. FLOOR FINISHES VIII. WATERPROOFING IX. CARPENTRY WORKS X. PVC DOORS AND JAMBS XI. PAINTING WORKS XII. METAL WORKS XIII. GLASS AND GLAZING XIV. STRUCTURAL WORKS XV. SITE DEVELOPMENT WORKS XVI. OTHERS - CIVIL WORKS XVII. PLUMBING WORKS XVIII. ELECTRICAL WORKS XIX. MECHANICAL WORKS

Upload: frederickvvelasco

Post on 08-Nov-2015

6 views

Category:

Documents


3 download

DESCRIPTION

Bar Charts, S Curve, Cash Flow

TRANSCRIPT

Sheet1PROJECT TITLE:PROJECT LOCATION:ITEMSCOPE OF WORKDAYS1-78-1414-2122-2829-35AMOUNTDURATIONJan 1 - Jan 7Jan 8 - Jan 14Jan 15 - Jan 21Jan 22 - Jan 28Jan 29 - Feb 4I.PRELIMINARIES150,000.00II.EARTHWORKS/DEMOLITION WORKS130,000.00III.CONCRETING AND FORMWORKS230,550.00IV.MASONRY WORKS340,500.00V.CEILING WORKS300,055.00VI.WALL FINISHES450,000.00VII.FLOOR FINISHES468,900.00VIII.WATERPROOFING5,000.00IX.CARPENTRY WORKS450,450.00X.PVC DOORS AND JAMBS90,500.00XI.PAINTING WORKS105,200.00XII.METAL WORKS55,000.00XIII.GLASS AND GLAZING100,000.00XIV.STRUCTURAL WORKS300,000.00XV.SITE DEVELOPMENT WORKS100,050.00XVI.OTHERS - CIVIL WORKS25,000.00XVII.PLUMBING WORKS1,200,000.00XVIII.ELECTRICAL WORKS1,450,550.00XIX.MECHANICAL WORKS2,300,500.008,252,255.00

Sheet2

Sheet3