Barking and Dagenham Council Planning Committee Supplementary Report Date: 10 th September 2021 Application No: 21/00297/FULL Ward: Village Address: Tesco Express, Railway Hotel Shafter Road, Dagenham, Barking And Dagenham, RM10 8AJ Development: Conversion of existing roof space, with elevated ridge line and new dormers; three storey side extension; rear extension at first and second floor levels; together with associated alterations to provide an enlarged storeroom to ground floor retail accommodation, and six new residential units (Class C3). Applicant: Bluewater Investments Limited Summary: This supplementary report covers the following matters and should be read in conjunction with the published Committee report: Additional consultation response received by LBBD Transport An update to the heads of terms in relation to highways contributions. Additional Consultation Response Following the publication of the committee report, a supplementary consultee response has been received from LBBD Transport dated 09.09.21 and is listed below: The main concern is lack of pedestrian accessibility facilities, pavement, multiple vehicle movements, deliveries, builders’ merchants’ access and illegal parking and car dominant environment. Location Google Screen Shots:

Upload: others

Post on 02-May-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Barking and Dagenham Council Date: 10th September 2021

Barking and Dagenham CouncilPlanning Committee Supplementary Report

Date: 10th September 2021

Application No: 21/00297/FULL Ward: Village

Address: Tesco Express, Railway Hotel Shafter Road, Dagenham, Barking And Dagenham, RM10 8AJ

Development: Conversion of existing roof space, with elevated ridge line and new dormers; three storey side extension; rear extension at first and second floor levels; together with associated alterations to provide an enlarged storeroom to ground floor retail accommodation, and six new residential units (Class C3).

Applicant: Bluewater Investments Limited

Summary:

This supplementary report covers the following matters and should be read in conjunction with the published Committee report:

Additional consultation response received by LBBD Transport

An update to the heads of terms in relation to highways contributions.

Additional Consultation Response

Following the publication of the committee report, a supplementary consultee response has been received from LBBD Transport dated 09.09.21 and is listed below:

The main concern is lack of pedestrian accessibility facilities, pavement, multiple vehicle movements, deliveries, builders’ merchants’ access and illegal parking and car dominant environment.

Location Google Screen Shots:

Page 2: Barking and Dagenham Council Date: 10th September 2021

Highway Works Indicative Costings:

Detailed Design, and community engagement - £4k Kerb Realignment, pedestrian drop kerb access alongside New Entry Treatment

Table at Shafter Road Junction with Rainham Road South creating a “gateway” to the residential community destination - £20k

New Kerb line providing pedestrian space delineation circa 50m, new surfacing and strategically placed bollards to maintain existing parking bay access and provide safe pedestrian areas mitigating conflict of movements occurring - £10k

New Street Trees, Greenery complementing the surrounds - £2k New Road Signage and Markings £1k

Total £37k

Page 3: Barking and Dagenham Council Date: 10th September 2021

Note:Any Lighting upgrades deemed complimentary will be covered by Highway AuthorityAny Parking realignment, amendments to Legal Orders and associated costs covered by Highway Authority.

Purely as an Indicative guide to Deliverables:

Officer comment: Since the publishing of the Committee report, ongoing consultation has been undertaken with LBBD Transport in relation to safety mitigation measures at the site. Officers have sought an additional contribution that goes above and beyond those already recommended in the published report. The applicant has acknowledged the consultee response and has made an offer for an additional £10,000 to provide the following:

New Kerb line providing pedestrian space delineation circa 50m, new surfacing and strategically placed bollards to maintain existing parking bay access and provide safe pedestrian areas mitigating conflict of movements occurring

Page 4: Barking and Dagenham Council Date: 10th September 2021

Officers acknowledge that this falls short of the full amount requested by LBBD transport. Due regard has however been given to the applicant’s commitment to address these matters through the above financial contribution of £10,000.00; in addition to the heads of terms and conditions relating to car par parking permit free agreement and delivery and servicing management plan which have been welcomed by officers and considered acceptable.

Planning Obligations

The additional head of term is therefore listed in relation to the required financial contribution and scope of works:

5. Prior to the commencement of the development, the applicant shall pay a sum of £10,000 to go towards the completion of highways works including: new Kerb line fronting Shafter Road, new surfacing and bollards to existing parking bay access and introduction of pedestrian areas.

Recommendation:

The Officer recommendation remains unchanged.

Contact OfficerNathaniel Soneye-Thomas

Title:Principal Development Management Officer