BCD input from WG2
WG2 12/08/2005H. Hayano
Chris Adolphsen
Terry Garvey
Hitoshi Hayano
![Page 2: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/2.jpg)
Summary of BCD input
WG2 R&D activities: EU: TTF(XFEL) US: SMTF,SLAC R&D Asia: STF --> will be summarized by regional directors
![Page 3: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/3.jpg)
WG2: Main Linac
![Page 4: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/4.jpg)
WG2: Main LinacModulatorKlystronCavity packageGradientCryomodule configurationRF distributionCryogenicsTunnel curvatureTunnel layout
By WG5
Revisited by BCD task force
![Page 5: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/5.jpg)
Modulator
![Page 6: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/6.jpg)
Modulator
Baseline
Alternatives
Bouncer-compensated pulse transformer modulator
Marx-style generator,
DTI (Direct switch),DC-to-DC converter
![Page 7: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/7.jpg)
Klystron
![Page 8: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/8.jpg)
Klystron
Baseline
Alternatives
10MW multi-beam klystron
10MW sheet beam klystron,5MW Inductive Output Tube,10MW 12 beam MBK
![Page 9: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/9.jpg)
Cavity
WG5
![Page 10: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/10.jpg)
Cryomodule configuration
![Page 11: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/11.jpg)
Cryomodule configuration
Baseline10MW klystron drives 24 TESLA cavities. considering 7% WG loss and 11% overhead for 35MV/m operation
Cavities divided into three cryomodules,Quad package in every 4-th cryomodules, Cos(2)type Quad + corrector windings+BPM, supported from GRP at center post, <10µm bunch-to-bunch resolution BPMCavity spacing 283mm Contradiction with GG2-BCD!
![Page 12: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/12.jpg)
Cryomodule configuration
Alternatives
12 cavities in one cryomodule,Cavity spacing 250mm~180mm,HOM readout,Quad-BPM in separate cryostat,Putting movers on center support post and cryomodule support,Reduce Quad aperture to ~35mm,1µm resolution BPM
![Page 13: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/13.jpg)
RF distribution
![Page 14: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/14.jpg)
RF distribution
Baseline
Alternatives
TESLA-TDR like distribution system, circulators and tuners(3-stub or E-H) in each cavity.
Elimination of circulators.
![Page 15: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/15.jpg)
Cryogenicsystem
![Page 16: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/16.jpg)
Cryogenic system
Baseline
Alternatives
TESLA-TDR like layout, except refrigerator spacing (but likely 5km).Maintenance length is half of the refrigerator spacing.
U-tube or turn around for more shorter maintenance length,
![Page 17: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/17.jpg)
Tunnelcurvature
![Page 18: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/18.jpg)
Tunnel curvature
Baseline
Alternatives
The linac will follow the curvature of the earth, unless site-specific reason dictates otherwise.
Laser-straight linac,Straight-line segments.
![Page 19: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/19.jpg)
Tunnellayout
![Page 20: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/20.jpg)
Tunnel layout
Baseline
Alternatives
RF sources to be located outside the beam tunnel, to be distributed along a second tunnel or surface gallery that run parallel or near by the beam tunnel.Three WR650 WG to each rf unit (one WG per cryomodule)
TESLA-TDR like layout.
Contradiction with RF distribution BCD!
![Page 21: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/21.jpg)
BCD RF unit
![Page 22: BCD input from WG2 WG2 12/08/2005 H. Hayano Chris Adolphsen Terry Garvey Hitoshi Hayano](https://reader033.vdocuments.net/reader033/viewer/2022051417/5697c0091a28abf838cc7112/html5/thumbnails/22.jpg)
BCD RF unit cartoon
Bouncer modulatorMulti-beam klystron Pulse transformer
LLRF & instrumentationRF waveguides
cryomodulesRF distribution
Rey.hori