beam transfer systems
DESCRIPTION
Beam Transfer Systems. J.Borburgh , E.Carlier , L.Ducimetière , B.Goddard , V.Mertens , et al. Outline: Brief reminder of LHC activities Plans for “backbone” machines (PSB, PS, SPS) Plans for other facilities (AD, ISOLDE, CTF3) Conclusions. LHC. Presenting only work - PowerPoint PPT PresentationTRANSCRIPT
Beam Transfer Systems
J.Borburgh, E.Carlier, L.Ducimetière, B.Goddard, V.Mertens, et al.Outline:Brief reminder of LHC activitiesPlans for “backbone” machines (PSB, PS, SPS)Plans for other facilities (AD, ISOLDE, CTF3)Conclusions
SPS
LHC
PS• Presenting only work▫ requiring access to the machines▫ with priority 1 (= absolutely mandatory), priority 2 (= highly recommended)
• Not discussing work ongoing in parallel for▫ projects▫ refurbishment of spares following exchange
… competing for same manpower
Brief reminder of LHC activities• Completion of staged MKB installation (1 tank = 2 magnets per
side) + electronics and controls
• Overhaul of remaining 20 MKD/ 20 MKB generators and magnet entry boxes
• Replacement of a (small) number of MKI as function of progress with mitigation studies and tests on heating, UFOs, …
• 2 x TCDQ upgrade to beyond nominal performance
• Lots of electronics and controls improvements (HW/SW)
• LBDS tests and reliability run to be firmly planned in
LHC: TCDQ• Remove existing 2 tanks (per beam) and girder• Create space and install new 3 tank solution with
girder• Consolidation of electronics and controls (split of
reference/interlock logic)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Construction of new TCDQs Exchange/installation
Support needs
► DGS-RP
► EN-HE
► EN-EL
► TE-VSC
► BE-ABP
► BE-CO
► EN -STISchedule still to be confirmedInstall TCDQ sufficiently robust for 7 TeV and ultimate intensity
New TCDQ
2013 2014
1
PSB: extraction septum BE.SMH • Exchange one extraction septum (preventive)• Consolidation of electronics and controls (including full recabling)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Construction Lab testing Exchang
e
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-COAdvance work from LS2 (2 GeV compatible)
2013 2014
2
PSB: kicker KFA10-20 • Replacement of hydraulic group (ready since
2011)• Consolidation of electronics and controls
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Replacement/ cabling Tests
Support needs
DGS-RP
► EN-HE
► EN-EL
TE-VSC
BE-ABP
► BE-COReliability & safety in case of fire
2
In principle no machine access required
2013 2014
PS: dummy septum 15, SMH16 and SEH23 • Exchange of SEH23 preventive, (w elimination of oil) and
SMH16• Replace feedthrough and connect 3M Fluorinert station• Install dummy septum 15 & provide electronics and controls
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Construction Dummy septum 15 Modify
3M station
Install dummy15
Exchange SEH23
Support needs
► DGS-RP
► EN-HE
► EN-EL
► TE-VSC
► BE-ABP
► BE-CO
2013 2014
1
Dummy septum 15 will protect SMH16 (MTE)
PS: MTE hybrid kickers• Re-cabling + overhaul of CT electronics and controls , eradication of CAMAC• Overhaul of RSG HV switches + magnet feedthroughs
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Replacement/ cabling Tests
Support needs
► DGS-RP
► EN-HE
► EN-EL
► TE-VSC
BE-ABP
► BE-COCompatibility MTE and CT
2013 2014
2
SPS: LSS1 kickers • Equip MKDV2, MKQH, MKQV with gap shielding• Exchange one MKP kicker magnet + change HV irradiated cables • Change control cables in LSS1+ MKDV electronics, controls & HV power supplies
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Remove
Reinstall
DC cond.
Test
Support needs
► DGS-RP
► EN-HE
► EN-EL
► TE-VSC
► BE-ABP
BE-COBeam impedance reduction, consolidation, diagnostics
2013 2014
1
SPS: LSS2 septa• Dismantling of TPSN and subsequent installation of
TPST• Exchange of ZS4, 3 MST and 4 MSE
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Construction TPST Exchange
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-COConsolidate TPST : greater mechanical stability, easier alignment
Preventive exchange of ZS and MS
2013 2014
1
SPS: MKE LSS4 & LSS6 • Exchange last kicker magnet / LSS4 + PFN retuning + G-64 eradication• Change vacuum gauge / LSS6 (implies full reconditioning)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Exchange
DC cond.
Tests
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-COBeam impedance reduction
2013 2014
1
SPS: LSS6 septa• Exchange of 3 MST (preventive)• Exchange of ZSTF (for further studies)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Exchange
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-CO
2013 2014
1
AD: displacement of kicker generators• Moving of full platform into future new building• Re-cabling, renovation of electronics and controls• Replacement of mineral oil by Ester oil
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Move Cabling
Support needs
DGS-RP
► EN-HE
► EN-EL
TE-VSC
BE-ABP
► BE-CONeed to free space for ELENA construction
2013 2014
1
AD: extraction septum SM05/07 Open roof of AD Replace leaking septum by spare, followed by bake-out Close AD roof and shielding
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Repl
.
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-COSchedule driven by availability of HE and VSC
1
2013 2014
Controls upgrade (ACCOR project)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Upgrade TESTS
2013 2014
Support needs
DGS-RP
EN-HE
► EN-EL
TE-VSC
BE-ABP
► BE-CO
1
Migration to FESA & InCAIn principle no machine access required
• Eradication of LynxOS/PowerPC Platform & MIL1553 from SPS (and LHC)
• Renovation of kickers and septa in AD
Other facilities (ISOLDE, CTF3)• ISOLDE – motor protection for hydraulics• CTF3 – help with installation of fast feedback
kickers (from Oxford)
01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04Installation
Support needs
► DGS-RP
► EN-HE
EN-EL
► TE-VSC
► BE-ABP
BE-COCTF3 : First feedback/feed-forward tests in 2013
2013 2014
2
Conclusions• Important share of LS1 work to make LHC equipment fit for 7
TeV and higher intensities.• Also many high priority activities in the injectors.• 2012 preparation work will be decisive.• Most activities in injectors compatible with present access
planning (Except some kicker magnet conditioning in SPS and septa work in region 15-16 of the PS).
• Good coordination with and support by HE, EL, VSC, ABP, CO, RP, … essential.
• Detailed preparation plannings coming forward.• List of requirements (test times) and constraints (access) being
worked out and communicated.