Belize Municipal Development Project (P111928)
Mid-term Review Mission – June 10 – 14, 2013
Aide Memoire
I. Introduction
1. A World Bank team led by Yoonhee Kim (Team Leader and Sr. Urban Economist) and comprised of
Maritza Rodriguez (Sr. Financial Management Specialist), Noreen Beg (Sr. Environmental
Safeguards Specialist), Yingwei Wu (Sr. Procurement Specialist), Kimberly Vilar (Social
Development Specialist), Anna Okola (Transport Specialist) and Keren Charles (Operations Analyst
Consultant) undertook the Mid-term Review (MTR) Mission of the Project from June 10 – 14, 2013.
2. The mission team held discussions with Ms. Yvonne Hyde (CEO, Ministry of Finance and Economic
Development), Ms. Candelaria Morter (CEO, Local Government), Mr. Eugene Palacio (Director,
Local Government), Mr. Errol Gentle (CEO, Ministry of Works and Transport), Mr. Lawrence
Sylvester (CEO, Ministry of Housing and Urban Development) Ms. Beverly Castillo (CEO, Ministry
of Natural Resources and Agriculture, MNRA) and Ms. Gina Young (MNRA), the Mayors and Town
Council representatives of Belmopan, Benque Viejo del Carmen, Corozal, Dangriga, Orange Walk,
Punta Gorda, and Santa Elena/San Ignacio, as well as Daniel Cano (Executive Director, Belize Social
Investment Fund, SIF) and the Project Implementation Unit (PIU).
3. The mission carried out site visits for Phase 1 and Phase 2 works in all seven Town Councils as part
of the Mid-term Review Mission. The mission expresses appreciation for the kind support extended
to the Bank team during the mission (a detailed list of people met is provided in Annex 2). A wrap-
up meeting was held with the Project Steering Committee (PSC) to discuss the key findings of the
mission. In particular, the mission focused on reflecting lessons learnt and experiences from the
Project’s implementation up to date and the completion of the Phase 1 program.
4. This aide-memoire summarizes the findings, recommendations and agreements reached during the
mission and it is subject to confirmation by World Bank management. The aide-memoire will be
publicly disclosed once finalized.
5. Key Project Data and Performance Rating
Key Project Data Key Performance Rating
Previous Current
Board
Approval
Date
September 16,
2010
Progress towards
achievement of Project
Development Objectives
Satisfactory Satisfactory
Effectiveness
Date
January 25,
2011
Overall Implementation
Progress
Moderately
Satisfactory
Satisfactory
Closing Date November 30,
2015
Disbursed US$ 2.6 million US$ 4.7 million
Loan Amount US$ 15 million % Disbursed 17% 31%
II. Implementation Status Overview
6. As of May 31, 2013, the Project has disbursed about US$ 4.7 million, equivalent to approximately
31% of the loan amount. Since the last supervision mission in December 2013, the PIU has disbursed
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
US$ 2.1 million. Another US$ 2.2 million (including US$ 0.46 million operating cost) has been
committed for the implementation of Phase 1 sub-Projects, consisting of 50% of the total loan.
III. Key Findings from Mid-Term Review Mission
7. Main Achievement of the Project up to date: The mission was pleased to note the following
achievement up to date.
a. The project is well underway to achieve its development objective (to improve access to
basic municipal infrastructure and to enhance municipal management in selected town and city
councils of Belize).
b. The project has completed all Phase 1 investment (except Dangriga market sub-
component), resulting in the rehabilitation of 19 streets (some 7.3 km) and refurbishment of the
Punta Gorda Town Hall
c. Mobilization and implementation of five TA components: Revenue Enhancement,
Financial Management, Asset Management and Maintenance Plan, Urban Development Plan,
Communication Strategy, and Road Safety and Public Awareness. The TA programs have begun
to demonstrate tangible results and benefits to enhance TCC’s capacity for municipal
management. Some examples include: a) color coded land use maps was developed for the seven
(7) municipalities under the BMDP to assist with the consultancy to prepare the municipal
development plans; b) diagnostic report on the performance of their revenue sources including a
comparative analysis of the performance and administration of revenue sources including
property tax and trade license fees; and c) the participation of Mayors, Deputy Mayors and
Administrators of all TCCs in a two-day peer sharing workshop on Best Practices for revenue
collection and management, among others.
d. Phase 2 preparation is well underway according to the implementation plan including
meeting the requirements of the second phase eligibility criteria and counterpart contribution
e. Enhanced project implementation capacity of the PIU in all aspects (technical, financial,
procurement, project management, safeguards policies) and continued institutional efforts to
maintain high level of transparency (e.g. FM disclosure, website, etc). The Bank also
acknowledges guidance and oversight provided by the Project Steering Committee
f. Overall project’s ratings for Progress towards Project Development Objective and
Implementation Progress are satisfactory.
8. Key Recommendations and Lessons Learnt for the Remaining Project Implementation:
a. Phase 2 Project Appraisal and Investment Prioritization: the mission noted that while
investment prioritization was adequately carried out following a consultative and participatory
process, some of the proposed investments appear to lack technical, economic, and financial
assessment. In particular, the proposed project appraisal documents should strengthen alternative
investments that were considered and document better social, economic, technical, and
environmental justification for the proposed investment for TCCs.
3
b. Design Review: the mission recommends carrying out a thorough design review
including: a) site visits to validate the adequacy of design; b) sharing site designs with the TCs for
review; c) utilizing external peer review is encouraged to ensure the best quality of designs.
c. Contract/construction Management: the mission stressed the importance of enhancing
contract and construction management by the PIU. Based on the review of Dangriga market sub-
component, the mission recommends adequate documentation of any issues raised during the site
visits by the PIU technical staff; proactive communication and clarification of any contractual
issues by the PIU; and maintaining signed minutes of the discussion between the PIU, contractors
and TCs. In particular, while SIF retains supervision and project management roles (Dangriga,
small works), it is important to maintain logs of instructions to contractors. Such records are
critical not only for the determination of delays in future, if relevant, but also importantly to
ensure compliance and implementation by contractor, and aid in subsequent follow up visits.
d. Capacity building and technical assistance components for TCCs: there is a need to
build a closer dialogue and policy linkage with the Ministry of Local Government and the
Ministry of Natural Resources and Agriculture. In particular, important progress has been made
for revenue enhancement TA (with the support from international and local consultants) and
MLG can play a significant leadership towards accomplishing the objective of the TA and
ensuring that the project’s support for revenue enhancement can be sustained and continued. In
addition, an interim protocol for information sharing relating to land ownership between TCCs
and the MNRA was agreed and the mission recommends following upon and monitoring this
during the project implementation.
e. Ensuring participatory project implementation throughout the entire project cycle:
the mission stressed that the key development impact that the Project aims to achieve is enhanced
transparency and accountability for TCCs. The Project has built several mechanisms to allow this
(e.g. investment prioritization through participatory process, establishing project monitoring
committee and grievance mechanisms, and making financial statement public). The remaining
project implementation should continue to support participatory process and transparency and the
Bank team will provide adequate support as needed.
IV. Implementation Status by Project Component
Component 1: Municipal Infrastructure Investments
9. Completed and ongoing Phase 1 works. The mission visited Phase 1 Project sites under
implementation in all seven TCs (Annex 3 includes a detailed list of site visit locations and dates and
Annex 4 provides implementation status of Phase 1 works.) During the site visits the mission met with
mayors, Town Council representatives, as well as affected stakeholders. The mission found the quality of
construction generally satisfactory and suggested a few minor areas of improvement in safety measures
(such as pavements) and quality of materials used (such as paint for street markings). Key discussion
and issues raised during the site visit are:
a. Belmopan –The Bank concurs with TC Mayor’s recommendation that the SIF shares the site
designs with the Belmopan TCC’s engineer.
b. Belmopan, Benque Viejo del Carmen – The paint on some streets started to fade away,
which indicate that the PIU should evaluate and determine the best paint options for street
rehabilitation works. The Bank recommends following up with contractors and/or putting
4
corrective measures for all streets supported under Phase 1. In addition, maintenance options
could be considered to have the roads re-painted regularly.
c. Punta Gorda – The site visit to the proposed Phase 2 streets revealed room for improvement
in the vetting process for sub-Projects. In particular, the selection and prioritization of
Hopeville road, which is expected to benefit directly 86 households, was not clear. Meanwhile,
the West St (VOA Sts), which was considered during the public participation process, was not
included in the prioritized list. The mission emphasized the importance of carrying out
economic, social and technical evaluation, along with community interests and overall public
good in the weighting and final prioritization of sub-Projects.
d. The mission noted some complementary works for Phase 1 street rehabilitation envisaged
under Phase 2, such as sidewalk and additional drainage along the street. The mission
recommended the PIU proceed with the complementary works under a separate shopping
package.
10. Dangriga Market Sub-Component. The mission discussed with the PIU both supervision and
ongoing work contracts in great detail. Site visits to ongoing works for rehabilitation and expansion of
existing market highlighted that no engineer is on site to supervise works and there has been considerable
delay in project construction (40% completion rate as estimated by SIF). The contractor reports that his
team has been working full time with a crew of about 21 men; however, due to ongoing issues related to
non-payment, the crew size is variable. The mission discussed options available for SIF to successfully
complete works without more delay, including possible contract termination and the status-quo. In order
to decide on a way forward, it was agreed that SIF will assess the feasibility and likelihood of the
existing contractor to complete construction without further delay (e.g. assessing financial condition,
credit arrangement, quality of ongoing construction, and revised work plan for completion) by
June, 21, 2013, consult with the PSC and the mayor, and inform the Bank of the proposed steps to
take and solution by the end of June, 2013. With no supervision firm for last several months and
concerns regarding the contractor’s capacity, the mission also noted there is potential that quality of the
works may have been compromised. At the present time, with no supervision firm on board, SIF has
been performing the supervision functions as well as Project Management, leading to potential
contentious scenarios in the attribution of delays between the contractor and SIF.
11. The mission discussed a long pending issue of supervision contract for Dangriga Market. After
the review by the Bank’s team, it was decided that while 100% payments of the contract had been made
to ATA by PIU, deliverables had been only partially made under Interim Report #3 for Dangriga.
Furthermore, it was decided that the PIU had overpaid the supervision firm at the amount of BZ$21,641
with BZ$11,656 overpaid for Interim #3 and BZ$9,985 for final payment. It was further agreed that SIF
will determine any deduction to be applied to the refund taking into account additional visit by the firm
and communicate to the Bank the justification for the final amount for the refund by Friday, June 21,
2013. The case of supervision contact for Dangriga Market highlights the importance of understanding
the difference between time-based and lump sum contracts and improving the SIF’s contract management.
12. Selection of Phase 2 investments: The mission noted that while investment prioritization was
adequately carried out following consultative and participatory process, some of the proposed investments
appear to lack technical, economic, and financial appraisal. In particular, the proposed project appraisal
documents should strengthen alternative investments that were considered and document better technical,
economic, and environmental justification for the proposed investment. The mission recommended the
PIU review all the selected sub-projects, carry out additional assessment that would justify all the
proposed subprojects (e.g. value for money), document social, economic, environmental benefits of the
proposed projects, adjust sub-projects prioritization following the analysis, and carry out another public
5
consultation process as needed to close the loop on the final investment programs. It was noted that
enhanced project appraisal document and investment prioritization would ensure greater level of
legitimacy and transparency for the project. It was agreed that the PIU will provide a revised phase 2
project appraisal documents reflecting earlier comments by the Bank communicated by email and
observations made during the mission by July 31, 2013 for the Bank’s no objection.
13. Eligibility Criteria for 2nd
Phase Investment; the mission was informed that all the TCCs have
met the required eligibility criteria for the 2nd
phase investment. They include:
a. That the process for the formal adoption of a Municipal Growth Plan by the Town or City
Council after a conducting a series of prior public meetings have been initiated. That the process
for the preparation of a physical asset maintenance plan and corresponding budget and
incorporation of maintenance budget in the Annual Town or City Council budget have been
initiated
b. Conduct monthly Council meetings of which at least one should be open to the general
public every two months starting from October 2012
c. Conduct public Town meetings at least once every six months as required by law starting
from October 2012
d. Submission of monthly financial reports to MLLGRDINEM and the publication of such
reports as required by law starting October 2012.Reduction in the overdraft facility maintained by
the Town or City Council to within 90% of the overdraft limit as approved by the Ministry of
Finance by Q3 2011 and for any investment applied for after July 31, 2012 a further reduction to
within 75%; and
e. Hiring of a qualified accountant using a transparent selection process based on clearly
defined qualifications and experience and using Terms of Reference previously agreed with BSIF
and the WB.
It was agreed that the PIU will provide the Bank team with the evidence of meeting all the 2nd
phase
investment criteria by June 28, 2013. It was reiterated that no sub-project can proceed without meeting
the eligibility criteria.
14. Lump-sum based supervision –The mission noted the recommended approach for Phase 2
supervision is time based contracting method. SIF noted difficulties, mainly capacity constraints for the
oversight of such contracts. SIF confirmed that to date, the majority of contracts are implemented lump
sum given the relatively small size of contracts (typically under ½ million). The mission agreed that
recognizing the concerns of SIF, and the relatively small contracts envisioned, lump sum may be
considered. In this scenario, the mission recommended more detailed estimates on the part of SIF to have
better comfort on the expected supervision effort and thus manage better upfront costs estimates, which
may also revise upwards to reflect risk transfer to consultant (who assumes full risk for construction
delays, which could be caused by any number of factors).
Component 2: Technical Assistance and Capacity Building for TCCs, MLLGRDN and MNRA
15. Revenue Enhancement (RESP) and Financial Management: The Revenue Enhancement TA
has advanced well and has made a satisfactory progress. Some specific achievements up to date are:
LGO and UPO are located in the Ministries of Local Government and Natural Resources: Terms
of Reference and Memorandum of Understanding between BSIF and the Government Ministries
have been agreed to. Agreements include office accommodation and sharing of transportation
and accommodation during field work.
LGO worked closely with TCCs, MLG, SIF and Consultants to implement the following capacity
building initiatives between April 2011 and May 2013: Revenue Enhancement Support Program,
6
Computer and Information Technology Network Upgrade Support, Training in QuickBooks
Usage and Municipal Development Plans.
LGO Terms of Reference revised at the request of the Ministry of Local Government in March
2013 to reflect greater alignment with specific project related activities.
Terms of Reference developed for the procurement of the technical expertise necessary to
develop the Municipal Development Plans.
Color coded land use maps developed for the seven (7) municipalities under the BMDP to assist
with the consultancy to prepare the municipal development plans.
Activities coordinated with consultants, government agencies, Non-Governmental Organizational
and other relevant stakeholders involved in developing the Municipal Development Plans.
16. The mission was informed that final reports on the progress and outcome under the TA
consultancy is under preparation and the team will support an international expert during the final
consultation and dissemination of the final report scheduled end July, 2013. In addition, the team noted
that the training for the use of QuickBooks for accounting has improved financial management for the
TCs. The Bank noted, however, a need to integrate revenue side management together with expense side
and proposed working during the remaining project implementation to ensure the interface and integration
of the financial system in TCCs. Furthermore, the mission was informed that the MLG is planning to
carry out a strategic review of the Ministry’s roles and work plan to support TCCs in enhancing municipal
management capacity. The mission highlighted the importance of institutionalizing revenue enhancement
efforts within the Ministry and agreed that the Bank team will have a follow-up discussion with the
Ministry end July, 2013. Lastly, the mission was informed of the ongoing efforts by MNRA to update the
quality of property registration and cadastral information for town councils. Following the discussion, the
mission agreed with the MNRA on the interim protocol to allow sharing relevant information with TCCs
for revenue enhancement efforts. It was agreed that Urban Planner under the project will follow up and
communicate with the TCCs on the interim protocol.
17. Municipal Growth Plan, Asset Maintenance Plan and Traffic Management: the
consultancies have been just mobilized and the mission highlighted that the PIU send all the main
deliverables for the Bank’s technical review and comments. The mission was pleased to note that the TA
activity is well under way with formulation of local working group consisting of town councils members,
civil society and private sector.
Component 3: Project Management
18. Contract Management – the mission recommends hiring additional staff to focus on contract
compliance aspects, working closely with Project Coordinator and Project Engineers. SIF noted a
previous attempt to hire personnel, but due to the stringent requirements (a legal background was
stipulated) the advertisement did not yield interest or responses. The mission recommends reviewing the
ToR and selection criteria to allow more flexibility. The mission recognizes that there may be few local
staff with in depth experience in procurement in multi-lateral funded projects. A more general profile is
strongly recommended, allowing for on-the-job training on specific WB policies. In the opinion of the
mission, a legal background should not be a requisite, but rather focus on the profile of the person for
example attention to detail, organization skills, assertiveness, and effective oral and written
communication skills, in addition to basic qualifications/education/experience that permits adequate
performance.
19. Monitoring and Evaluation – the mission reviewed the existing framework for M&E including
revising baseline and target values and adjusting indicators. The detailed M&E indicators are provided in
Annex 6.
7
Financial Management (FM)
20. Internal Controls. The Project FM Unit continues to be well staffed with experienced,
competent and accredited accountant professionals, who exercise due diligence and care keeping in mind
key internal control features, including segregation of duties for key processes.
21. Budget and Interim Unaudited Financial Reports (IUFRs) The mission appreciates that the
Project’s IUFRs until March 2013 were submitted to the Bank on time and included comprehensive
information. The submitted figures have been reconciled with Bank account records in Client Connection
and banking statements. SIF periodically prepares easy-to-read summaries of FM reports of the Project
to provide to its major stakeholders, such as TCs and PSC. The summary reports highlight the Project’s
progress in terms of financial indicators and disbursement as well as compares projections with actual
figures. SIF continues to post and update Project financial information on the SIF website, openly
disclosing key data in line with the Project transparency requirements established in the Bank’s Access to
Information Policy.
22. External Audits. The mission reviewed internal control issues highlighted by auditors in the
management letter for the period April 2011/March 2012 and was pleased to note that SIF resolved and
closed all of the items. The mission met with the external audit team. The audit work for the current
period, as of March 2013 is in advanced stage and no delay in report submission is foreseen. As of the
date of the mission, no material weakness has come to the auditor’s attention, although they flagged the
need to improve contract projections to reduce instances for contract amendments changing the total cost
of a specific consulting firm. SIF and the Bank have found the performance of the audit firm as
satisfactory; consequently, since the firm audits SIF as an entity, SIF management will present a motion
to the Board to approve an extension for next audit period, with the corresponding adjustments in the
inflation rate.
23. Disbursement. The mission was pleased to note that the Project disbursement rate has
accelerated to a perfect match of 50% for this mid-term review disbursed and committed. The mission
randomly reviewed payment documentation and files, which were complete and orderly archived. It was
noted that payment clauses should be reviewed by the Finance Officers and clearly understood by the
Project Team, to mitigate risks of improper payments. The mission discussed the format of the table to
include in the request restructuring for reallocation among disbursement categories.
Procurement Management
24. Procurement Capacity. The mission reviewed the capacity of the SIF implementing the Project
procurement. In January 2013 SIF recruited a new Procurement Officer responsible for all procurement
activities including identification and selection of contractors, and oversight of the bidding process for the
Project. The Bank procurement mission in February 2013 conducted a thorough capacity assessment of
procurement staff and made recommendations to ensure technical quality reassurance in procurement
implementation. Besides intensive job training by the Bank’s senior procurement specialist, the
Procurement Assistant participated in the procurement workshops in the region for 2013. The
Procurement Officer should take formal procurement training within the year of 2013. As an action to
further strengthen the capacity of procurement, the hiring of contract management staff has been agreed
upon by SIF.
25. Procurement Plan (PP). The mission reviewed the progress of the procurement plan and agreed
with the proposed updates by SIF based on the need for the implementation of the Project for Phase 2.
8
The updated PP incorporating the agreements shall be submitted to the Bank by July 14, 2013 for no-
objection and publication.
26. Procurement Supervision: The mission reviewed the on-going and completed procurement
processes and contracts under Phase 1, which made substantial contribution to the robust improvement in
the Project’s disbursement. The planning for Phase 2 was discussed reflecting the experience and lessons
learnt. Detailed discussion on procurement supervision is attached in Annex 7.
27. Procurement Post-review: The procurement post-review (PPR) was conducted during the
mission of February 11-14, 2013. The civil works for street rehabilitation contracts via shopping were
post reviewed by the Bank with sample of three contracts at the total amount of US$ 165,734.58
equivalent. The MTR mission conducted the physical inspection. The review has concluded that
procurement activities carried out under the Project are in compliance with arrangements agreed in the
Project financing agreement and no major issue were found regarding procurement.
Social Safeguards
28. Resettlement Plans:
a. Lessons learnt: The location of the temporary relocation, both in Dangriga and Corozal,
seemed during the preparation of the plan, to be adequate to maintain the same level of
income; all three plans would have benefited from more supervision and hands-on
intervention. SIF’s delegation of decision-making to the municipalities was too early in
the process, for example, leaving communication with Project-affected people mainly in
the hands of the town council with minimal supervision or delegating to the Belmopan
town council the resolution of the taxi relocation.
b. Area of Development for Second Half of Project Implementation: To carry out an
analysis regarding the income lost by the Project –affected people and the present and
future fees they have to pay the Town Council as rent as well as user fees to devise an
income restoration program within the Dangriga Abbreviated Resettlement Plan; to use
the analysis to define an Income Restoration Program to be consulted with the Project-
affected people and town council within the Plan and update it accordingly; Regular
visits by SIF’s social officer will be carried out to all sites with active works; updates on
the implementation of the plans will be prepared and documented by SIF.
29. Social accountability - Project Monitoring Committees (PMCs):
a. Lessons learnt: During Phase One, the PMCs were effective, to a certain extent, in being
the SIF’s contact person from the community to give third party reports on the progress
of the works. However, they did not completely fulfill the original monitoring function,
given that they did not close the accountability loop by reporting back to the community
members who they represent after their visits to the site and meetings with SIF or the
Town Council; (ii) Project Monitoring Committees need to be strengthened and more
closely supervised by SIF.
b. Area of Development for Second Half of Project Implementation: During the second
phase of the Project, the SIF will develop and implement a strengthening proposal for the
Project Monitoring Committees (PMC), with World Bank support and
guidance. Increased supervision from SIF’s social officer is also recommended.
30. Grievance Redress Mechanism:
9
a. Lessons learnt: The first tier of the sub-Projects’ grievance redress mechanism can only
be the PMC if they have been strengthened and have a good working relationship (in the
appropriate language) with the Project-affected people.
b. Area of Development for Second Half of Project Implementation: A new first tier
mechanism will be devised for Dangriga’s current plan and Phase Two’s plans. A
bilingual contact person, preferably a social worker, will be assigned to the Dangriga
market to communicate with the affected people on a regular basis. Similarly, in the
other towns, a contact person will be assigned. When appropriate, bilingual contact
persons will be assigned. Moreover, the SIF will contact the Ombudsman and Legal
Office to brief him/her on the Project and possible grievances he/she might receive.
31. Indigenous Peoples Framework:
a. Lessons learnt: Culturally appropriate consultation was not carried out
consistently. The Project’s framework is broad in scope and mostly emphasizes the
importance of the cultural aspects of communication and consultation. However,
consultations with Project-affected people as well as broader community during
participatory governance activities were not necessarily carried out in the most culturally
appropriate manner. For example, bilingual staff was not hired to ease communication
with Project-affected people whose first language is not English. Also, in one case, the
mission noted that consultations for second phase Projects could have been more
culturally appropriate.
b. Area of Development for Second Half of Project Implementation: These
responsibilities should be championed by SIF and not delegated to the
municipalities. The SIF will safeguard that communication is provided in a culturally
appropriate manner, according to the Project’s Indigenous Peoples Framework. In the
same manner, town hall meetings and other participatory events within the MDP’s
activities will follow the framework.
32. Communication strategy:
a. Lessons learnt: Citizen participation in local decision-making is in its beginning stages
under the Project due to several factors.
b. Area of Development for Second Half of Project Implementation: Communications
strategy will be adapted to focus on strengthening the municipalities’ accountability
mechanisms.
33. Participatory decision-making processes:
a. Lessons learnt: With the exception of Belmopan, all other Town Councils reported that
their town hall meetings participation could have been better; therefore the decisions
resulting from these meetings could have relied on a more robust participatory exercise.
b. Area of Development for Second Half of Project Implementation: SIF will supervise
these participatory processes more closely, to ensure that participation is meaningful.
Environmental Safeguards
34. Compliance with Bank safeguard policies is satisfactory.
10
35. The mission reviewed compliance with the Belize Municipal Development Plan Environmental
Management Framework, dated June 2010, and followed up on progress since the previous
implementation mission in December 2012. Sub-Projects that require oversight of safeguard compliance
include:
a. Road and pavement rehabilitation works (including associated drainage) in Belmopan, San
Ignacio/Santa Elena, Orange Walk, Corozal, Dangriga, Benque Viejo, and Punta Gorda.
b. Market construction including provision of wastewater disposal for sanitary block and solid and
liquid waste management for fish market waste at Dangriga.
c. Construction of town hall building in Punta Gorda.
36. The mission commends the Project Engineers tasked with monitoring environmental
management. As requested during the last mission, monitoring reports of environmental management of
civil works Projects that are currently under implementation have been included in the overall progress
reports. A separate detailed EMP has been prepared for the market construction at Dangriga Market and
will be disclosed in the Bank InfoShop and on the SIF website. For Phase 2 Projects, the follow-up
screening form in the ESMF will be completed for each sub-Project prior to the start of civil works, and
where required, an EMP checklist will be prepared (utilizing the format followed for the Dangriga Market
EMP).
37. Phase 1 road and pavement rehabilitation. On the whole, adequate health and safety measures
have been adopted (provision of Personal Protective Equipment and adequate road signage and
notification of roadworks). Dust control spraying is undertaken on a daily basis. Construction waste has
been disposed of promptly and in an appropriate manner. No trees were removed as a result of the
roadworks.
38. The mission commends the Project Team for its excellent initiative in consulting the Institute of
Archaeology/National Institute of Culture and History with regard to the gun turrets, which had formed
part of Fort Barlee (adjacent to the roadworks in Corozal). This led to the turrets being protected and
fortified, and signposted as a Heritage Landmark. (The cavities identified under the turrets are a natural
geological formation, and are confirmed to be of no historic or cultural significance.
39. The mission recommends the PIU to take the following actions:
a. Ensure that where relevant, drains are covered with grilles, both for pedestrian safety, and to
prevent accumulation of solid waste leading to blockage and backup from silt traps at the
shoreline.
b. Reduce the height of the inverts in the flat slope drain running towards the sea from Corozal
market to ensure smooth flow and disposal of wastewater. When corrective works are
completed, flush the drain (using water from the fire station pump) and cover the drain with
grilles.
c. Upon completion of all sub-Projects in Phase 1, prepare a summarized completion report of
environmental mitigation measures followed, lessons learned (e.g., ensure that drains are tested
by contractors to ensure that effluent waters flow through to the outtakes.)
40. Market construction at Dangriga. The new market is still under construction. The sanitary
block under construction will have a biological filtration system (solid waste will be collected in a septic
tank and appropriately disposed of, and aggregates will filter liquid waste, which will drain into a tile
pond). The solid waste from the fish market will be collected in a depository for regular collection for use
as composting. The liquid waste from the fish market will be sent to a soak-away system, before
biological filtration to the soil. The design of the building (roof and floor drains) incorporates adequate
rainwater drainage measures. Stainless steel has been utilized in food stall design, instead of tiles, for
sanitary purposes (no cracks harboring bacteria, etc.). The temporary toilet drains into a self-contained
11
impermeable septic tank, which will be removed upon completion of the Project. In terms of
environmental measures, sheet siding has been placed along the banks of the adjacent canal to prevent
erosion. A detailed EMP has been prepared for this sub-Project and will be disclosed in the World Bank
InfoShop and in-country on the SIF website (a copy will also be given to the Town Council and made
available to the public).
41. The mission recommends the PIU to take the following actions:
a. Ensure that installation of soak-aways, grease traps, and septic tank are properly installed, by
on-site supervision during the process.
b. Undertake a baseline water quality analysis of the ambient water quality in Dangriga Canal and
upstream. Samples will be analyzed for coliforms and Ph-level, and follow-up samplings will
be taken three months after the market is operational, and again six months thereafter.
c. Install siltation barrier to prevent solid waste in the canal from entering the open sea.
42. Construction of town hall building in Punta Gorda (completed). The building meets all
environmental compliance standards, but the mission recommends that the PIU replace the wooden
covers currently placed on drain entry points with grilles as soon as feasible to allow for rainwater to enter
the drains, thereby preventing stagnation with resultant health risks.
43. Phase 2 Investments. Going forward, the mission recommends the PIU to take the following
action during Phase 2 of the Project:
a. Future sub-Projects must have a brief EIA (where required by Government of Belize (GoB)
environmental regulations and/or World Bank OPs) and/or an EMP checklist prepared and
disclosed prior to the start of works. Consultation with local stakeholders on the EIA/EMP must
take place and be documented in an annex to the EIA/EMP. Given that this is a Category B
Project (with limited environmental impact), preparation of environmental documentation and
periodic progress reports can be included in the TOR for the design consultant/supervision
engineer.
___________________________ ____________________________
Yvonne S. Hyde Yoonhee Kim
CEO Ministry of Finance and Task Team Leader, World Bank
Economic Development
12
Annex 1a: Action Plan
Relevant Activities Recommendation/Action Responsible
Agency
Due Date
1 Project Management
– Dangriga Market
The SIF will communicate to the
Bank the justification for the final
amount for the refund for the
supervision works at the Dangriga
Market.
PIU By June 21, 2013
2 Project Management
– Dangriga Market
Regarding the Dangriga Market
contractors, the SIF will confer with
legal professionals and the Project
Steering Committee (PSC) on the
next steps and inform the Bank of
the decision.
PIU By June 28, 2013
3 FM: Request for
reallocation among
disbursement
categories
Prepare Table with Disbursement
Categories for Reallocation.
PIU By June 21, 2013
Second Phase
Investment
Prioritization and
Appraisal
Provide a revised phase 2 project
appraisal documents for the Bank’s
no objection
PIU By July 31, 2013
Second Phase
Investment
Prioritization and
Appraisal
Provide the Bank team with the
evidence of meeting all the 2nd
phase investment criteria
PIU June 28, 2013
6 Procurement The updated procurement plan
incorporating the agreements shall
be submitted to the Bank for no-
objection and publication.
By July 14, 2013
7 Procurement C14: Traffic Management Training
Module (QCBS-Lump sum):
Swedish National Road Consulting
AB (SWEROAD) contract to start.
By end of June, 2013
8 Procurement C32-33: Preparation of
Designs, Technical Specifications,
Cost Estimates and supervision for
Structures (Small Works) in
Corozal, Orange Walk and Benque
Viejo (CQS): to open. The
consultancy is advertised in the
local press with a deadline.
By June 14, 2013
(opening date)
By June 28, 2013
(deadline for
advertisement)
9 Procurement C34-35: Preparation of
Designs, Technical Specification,
Cost Estimates and Supervision of
Municipal Streets Rehabilitation
(Small Works) in Corozal, Orange
Walk, Benque Viejo & San
By June 14, 2013
13
Ignacio/Santa Elena and Belmopan
(CQS): to open
10 Procurement C36: Preparation of Designs,
Technical Specifications and Cost
Estimates for the Rehabilitation of
Municipal streets in Belmopan,
Punta Gorda, Dangriga, Corozal,
Orange Walk, Benque Viejo & San
Ignacio/Santa Elena (LCS): to open.
By June 14, 2013
11 Social Safeguards Conduct Income Restoration
analysis and submit to the Bank.
The new Income Restoration
Program will be in effect by August
1st (the original works completion
deadline).
PIU By June 28, 2013
12 Social Safeguards Update the Plan to reflect the new
provisions for the first tier of
grievance redress mechanism and
the income restoration plan.
PIU By June 28, 2013
13 Social Safeguards Propose a work plan for phase two
incorporating lessons learned
covering resettlement, culturally
appropriate consultation,
accountability/participation, and
grievance redress mechanisms.
PIU By June 28, 2013
14 Environmental
Safeguards
Ensure that where relevant, drains
are covered with grilles.
PIU By end of Phase 1
Project
Commissioning
15 Environmental
Safeguards
Reduce the height of the inverts in
the flat slope drain running towards
the sea from Corozal market to
ensure smooth flow and disposal of
wastewater. When corrective works
are completed, flush the drain
(using water from the fire station
pump) and cover the drain with
grilles.
PIU By end-July
16 Environmental
Safeguards
Upon completion of all sub-Projects
in Phase 1, prepare a summarized
completion report of environmental
mitigation measures followed and
any lessons learned
PIU Upon Phase 1 Project
Commissioning
17 Environmental
Safeguards
Provide details on next available
Safeguards training workshop for
Project engineers (or approve
environmental management training
courses)
WB By end-July
14
18 Environmental
Safeguards
Dangriga Market: Ensure that
installation of soak-aways, grease
traps, and septic tank are properly
installed, by on-site supervision
during the process.
Undertake a baseline water quality
analysis of the ambient water
quality in Dangriga Canal and
upstream.
Install siltation barrier to prevent
solid waste in the canal from
entering the open sea.
PIU Timing dependent on
construction schedule
First sampling by end-
July
Prior to completion of
civil works
19 Environmental
Safeguards - Phase 2
sub-Projects
Future sub-Projects must have a
brief EIA (where required by GoB
environmental regulations and/or
World Bank OPs) and/or an EMP
checklist prepared and disclosed
prior to the start of works.
Consultation with local
stakeholders on the EIA/EMP must
take place and be documented in an
annex to the EIA/EMP.
PIU Prior to
commencement of
civil works on Phase
2 sub-Projects
15
Annex 1b: Action Plan Update from Last Mission (December 2012)
Relevant
Activities
Recommendation/Action Responsible
Agency
Due Date Status
1 Environmental
Safeguards
Ensure that road crews at Corozal
are provided with protective
headwear by the contractor, and
with protective footwear for those
operating heavy machinery (e.g.,
drills)
PIU By end of
December
2012
Done
2 Environmental
Safeguards
Confirm that the cavity under 1st
North Street in Corozal is not
culturally or historically important;
Check with the Department of
Archaeology that there is no
concern about filling the cavity with
concrete
PIU By end of
December
2012
Done
3 Environmental
Safeguards
Provide brief environmental
compliance progress reports for
Phase 1 roads Projects, and provide
a completion report upon
completion of subProjects
PIU By end of
March 2012
Done
(Summarized
completion
report to be
prepared upon
completion of
ALL sub-
Projects)
4 Environmental
Safeguards
Advise on progress of the initiative
to plant Bermuda grass along earth-
lined drains for erosion control
PIU At PIU’s
discretion
At PIU’s
discretion
5 Environmental
Safeguards
Provide brief environmental
compliance progress reports for
Dangriga market
PIU By mid-
January
2013, mid-
May 2013,
and in July
2013
Detailed EMP
prepared, and
will be disclosed
by end-June
6 Environmental
Safeguards
Undertake a baseline water quality
analysis of the ambient water
quality in Dangriga Canal; upon
completion of the works,
periodically assess the point source
water quality at the sanitary block
and soak-away
PIU/TC By end of
February
2013
Baseline
assessment to be
conducted by
end- July.
Periodic testing
to follow upon
market
becoming
operational
7 Environmental
Safeguards
Prepare and disclose brief EIA
(where required) and EMP for
future subProjects
PIU Upon
selection of
Phase 2
subProjects
Upon selection
of Phase 2
subProjects
8 Environmental
Safeguards
Provide details on next available
Safeguards training workshop for
WB By end of
December
Pending (timing
of workshop
16
Project engineers 2012 was during
Project mission)
17
Annex 2: List of People Met
Belize Social Investment Fund
Daniel Cano Executive Director
Ernest Raymond Project Coordinator
Nellie Trench Finance Unit Coordinator
Christine Lopez-King Senior Accounts Officer
Evan Dakers Social Specialist
Carolyn Crawford Procurement Specialist
Keisha Rodriguez Urban Planner
Lionel Jiminez Engineer
Francisco Gonzalez Engineer
Clifford King Local Government Officer
Ministry of Finance and Economic Development
Yvonne Hyde CEO
Ministry of Natural Resources and Agriculture
Beverly Castillo CEO
Gina Young Physical Planner
Ministry of Local Government
Candelaria Morter CEO
Eugene Palacio Director
Project Steering Committee (PSC)
Yvette Alvarez Ministry of Finance Representative
Lawrence Sylvester CEO, Ministry of Housing and Urban Development
Errol Gentle CEO, Ministry of Works and Transport
Mayors
Simeon Lopez Mayor of Belmopan
Miguel Velasquez Mayor of Benque Viejo del Carmen
Hilberto Campos Mayor of Corozal
H. Gilbert Swaso Mayor of Dangriga
Kevin Bernard Mayor of Orange Walk
Anthony Fuentes Mayor of Punta Gorda
John August Jr. Mayor of Santa Elena/San Ignacio
Town Councils
Enrique Carballo Executive Secretary, Belize Mayors’ Association
Javier Novelo Engineering Assistant, Belmopan TC
Angela Wade City Administrator, Belmopan TC
Sebastian Morales Revenue Manager, Belmopan TC
Carolene Arzu Accountant, Belmopan TC
Johukeoui Jones Traffic Manager, Belmopan TC
Carmencita Sosa Accountant, Benque Viejo del Carmen TC
Melly Coyol Town Administrator, Benque Viejo del Carmen TC
Elva Perez Deputy Mayor, Corozal TC
18
Rafael Castillo Councilor, Corozal TC
Gilroy Howard Flores Deputy Mayor, Dangriga TC
Timothy Westley PME, Dangriga TC
Paul S. Francisco Ag. Town Administrator, Dangriga TC
Simon Paulino Deputy Mayor Punta Gorda TC
Ludwig Palacio Town Administrator, Punta Gorda TC
Wilfredo Wina Traffic Management, Santa Elena/San Ignacio TC
Karen Fernandez Town Administrator, Santa Elena/San Ignacio TC
Melanie Danilezyk Revenue Manager, Santa Elena/San Ignacio TC
Horwath Belize, LLP
Lisa Zayden Audit Team Leader
Jessie Huang Audit Team Member
Catherine Castillo Audit Team Member
19
Annex 3: List of Site Visit Locations and Dates
June 10, 2013
- Belmopan: Easter Bus Terminal one-way street and Taxi Parking, Nimli Punit Street,
Hummingbird Extension, Raccoon Street
June 11, 2013
- Benque Viejo del Carmen: Church Street, Church Hill Street, Burns Street, Independence Street,
Juanito Pongorast Capital Park
- Santa Elena/San Ignacio: West Street, Eden Street
- Orange Walk: Aviles Street, Santa Familia, Central Park
- Corozal: 1st North Street (Police Station), Punta Gorda Street, Zuzuc Street, 1
st South Street
June 12, 2013
- Dangriga: Market Rehabilitation/Extension
- Punta Gorda: Pampana Street, Robert Pennell Street, Town Hall/Administrative Building
Rehabilitation, Hopeville Street, West Street
20
Annex 4: Status of Phase 1 Projects
Component 1, Phase 1 Sub-Project Status
Project Sites
Length
Designed
(m)
Length
Constructed
(m)
Town/City Contractor
Percent
Completed
(%)
Start Date of
the Contract
(NTP)
Completion
Date
Bus Terminal Area 308 195*1 Belmopan Belize Roadway Construction 100 8/13/12 12/11/12
18th St 497 260 San Ignacio Castillo Equipment 100 8/20/12
Avilez Lane 137 110 Orange Walk M&R Construction 100 8/20/12 11/19/12
Tangerine St 134 160
Zuzuc St 201 280 Corozal Imer Hernandez Dev. Co. Ltd. 100 8/20/12 11/19/12
Church St 750 750 Benque Viejo del
Carmen
Imer Hernandez Dev. Co. Ltd. 100
10/3/13 10/4/13 Churchill St 750 750
Burns St 450 450
Eden St 627 280 San Ignacio/Santa
Elena
West St 237 584
Robert Pennell St 274 160 Punta Gorda
Pampana St 375 375
San Ignacio St 349 350 Orange Walk De' Mars Construction 100 9/24/12 12/23/12
Nim Li Punit St 272 250*2
Belmopan
A&N Construction
100
10/4/12 3/3/13 Hummingbird Dr 76 180 100
Raccoon St 435 325*3 100
Punta Gorda St 402 500 Corozal
100
1st North St 195 195*4 100
Santa Familia St 776 615*5 Orange Walk 40
Notes:
1. Sidewalks were added on both sides.
2. 1/2 length paved with HMA, other half with 2-layer 1/2" chip seal.
3. Shorten to adjust for additional drains added to Nim Li Punit St and Hummingbird Drive.
4. Added some 200m of 0.6m wide lined drains and some 240m of 1m wide lined drains.
5. Portion of Audinette Alley not in Orange walk Town therefore, this portion was eliminated,
only 200m paved, 160m of 0.6m wide lined drain added on both sides,
sub-base & base added over 615m length.
21
Annex 5: Proposed Phase 2 Projects
The proposed phase 2 Projects and lengths in order of north to south, west to east are:
1. Corozal:
- Market (1,500m2) Expansion and Rehabilitation
- 6th Ave (85m) and 1
st St South (180m) Rehabilitation
- Fort Barlee south turrets (2) Rehabilitation
- Sport Complex (12,000m2) Expansion and Rehabilitation
2. Orange Walk:
- Central Park (2,400 m2) Rehabilitation
- Park Streets (1,800 m2) (North Park St/80m, South Park St/80m and Lover’s Lane/70M)
Rehabilitation
- Santa Familia St Rehabilitation
3. Benque Viejo del Carmen:
- Juanito Gongora St (545m), Independence St (530m) Rehabilitation
- 1,100m long by 1.2m wide Sidewalks (1,320m2)
4. San Ignacio/Santa Elena:
- Carmelita St (312m), Bishop Edmund St (45m), Martin Galvez St, and Cahal Pech St
(428m) Rehabilitation
- Salazar St (548m), Eden St (480m) Rehabilitation
5. Belmopan:
- Water Reservoir Streets (Barton Creek St/370m, Blue Creek St/290m, Garbutt
Creek/440m, Haulover Creek/380m, Mussel Creek/450m, and Roaring Creek/520m)
Rehabilitation
- Chiquibul St (240m) and Almond Blvd (280m) Rehabilitation
6. Dangriga:
- Trucking Blvd (355m) and Gadsby Ramos St (732m) Rehabilitation
7. Punta Gorda:
- Melendrez Blvd (350m), R. K. Pennell Blvd (320m), Mangrove St (310m), Wild Cane
St (350m) Rehabilitation
22
Annex 6: Monitoring and Evaluation
Data Collection Matrix
Project /
Intermediate
Outcome
Indicators
Base-
line
Target Values Data Collection and Reporting
Comments YR 1 YR 2 YR 3 YR 4 YR 5
Frequency
and
Reports
Data
Collection
Instruments
Responsibility
for Data
Collection
Number of
beneficiaries with
access to improved
quality of basic
municipal
infrastructure
(direct and indirect
Project
beneficiaries
(number), of
which is female
(percentage).
0
Direct Direct Direct Direct Direct
Annual
Sub-Projects
completion
reports
PIU-SIF
The data collected in
year 1 is for the two (2)
Pilot Projects in
Belmopan and San
Ignacio/Santa Elena.
The data for year 2 has
not been revised for
population increases
over the past 6 month
period
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
49
% 51%
49
% 51%
3,500 -
-
-
Indirect Indirect Indirect Indirect Indirect
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
Ma
le
Fem
ale
49
% 51%
49
% 51%
146,172
153,683 -
- -
Number of towns
successfully
completing
investments in first
and second phases
0 0 6.00 -
- -
End of
phase 1
and end of
the Project
Project
Completion
Reports
PIU-SIF
Six (6) TCCs have
successfully completed
investments in phase 1
(Belmopan, Benque,
Corozal, Orange Walk,
Punta Gorda, and
SI/SE). Phase 2 is to
commence in year 3
At least four
TCC’s each have
achieved four out
of seven
intermediate
outcome indicators
of component 2
0 0 4.00 -
- - Annual
Compilation
of different
progress
reports such
as financial
reports
submitted to
PIU-SIF
The four (4) TCCs that
achieved at least four
out of the seven
intermediate outcome
indicators of
component 2 are:
Corozal, Belmopan,
23
MLLGRD Benque, and Dangriga.
Intermediate
Outcome
Indicators
Baseline YR 1 YR 2 YR 3 YR 4 YR 5
Frequency
and
Reports
Data
Collection
Instrument
s
Responsibility
for Data
Collection
Comments
Km of drainage
financed under the
Project
0 0 10.1 -
- -
Semi-
annual
Sub-Projects
completion
reports
PIU-SIF
Km of
rehabilitated roads
under the Project
0 0 5.18 -
- -
Semi-
annual
Sub-Projects
completion
reports
PIU-SIF
Number of
improved
intersections under
the Project
0 58 -
- -
Semi-
annual
Sub-Projects
completion
reports
PIU-SIF
Number of traffic
signs financed
under the Project
0 107 -
- -
Semi-
annual
Sub-Projects
completion
reports
PIU-SIF
Number of towns
and cities that
comply with terms
and conditions of
sub-Project
agreement
0
7 7 -
- -
Semi-
annual
Sub-Projects
completion
reports
PIU-SIF
Number of towns
and cities that
have adopted
MGP
0 0 0 -
- -
Semi-
annual
Minutes of
Town Hall
Meetings
MLLGRD
Number of towns
increasing own
revenue collection
Local
revenue
collected
in 2009
0 0 -
- -
Semi-
annual
Financial
Reports
submitted to
MLLGRD
MLLGRD
Belize City and San
Pedro Town have been
included. The period
(April to July) will be
compared for
2011/2012 and
2012/2013 as
recommended by
24
consultant
Number of towns
with qualified
accountants on
staff
0
7 9 -
- -
Semi-
annual
Towns and
Councils
submit
information
to
MLLGRD
MLLGRD
Belize City and San
Pedro Town have been
included
Number of towns
submitting
required financial
reports
0
9 9 -
- -
Semi-
annual
Financial
Reports
submitted to
MLLGRD
MLLGRD
Belize City and San
Pedro Town have been
included
Number of towns
using a
computerized
financial reporting
system
0
1 9 -
- -
Semi-
annual
Reports
submitted to
PIU PC
MLLGRD
Belize City and San
Pedro Town have been
included.
Number of towns
with a physical
asset maintenance
plan and
corresponding
budgets
0 0 0 -
- -
Semi-
annual
Financial
Reports
submitted to
MLLGRD
MLLGRD
Number of towns
with roads and
safety procedures
0 0 0 -
- -
Semi-
annual
Reports
submitted to
PIU PC
Number of towns
and city councils
that have received
training from the
Local Government
and Urban
Planning Officers
0 9 9 -
- -
Semi-
annual
Reports
submitted to
PIU PC
MLLGRD and
MNRE
Belize City and San
Pedro Town have been
included
Number of TCC’s
provided with
spatial data sets
showing land
0
7 7 -
- -
Semi-
annual
MNRE
Internal
Reports
MNRE
25
parcels
Percentage of sub-
Projects that meet
SIF’s service
standards in
accordance with
the OM
0 100% 100% -
- -
Semi-
annual
SIF PIU
Internal
reports
PIU-SIF
Procurement and
FM duties are
executed in
accordance with
national and
World Bank
guidelines
0 yes yes -
- -
Semi-
annual
SIF PIU
Internal
reports/
Financial
Audits
PIU-SIF
26
Annex 7: Procurement Review
Phase 1
For contracts of major TA packages under Component 2:
i. C11: Municipal Growth Plan (QCBS-Lump sum): Contract was signed in December
2012 with a proposed completion date of December 2013. Technical Assistance to prepare
the Municipal Development Plans is being provided by the firm, Institute for International
Urban Development (I2UD). Commencing their work on January 2, 2013, I2UD submitted
their Draft Inception Report on February 4, 2013 and the Final Inception Report on March
1, 2013 that incorporated stakeholder comments. The consultants submitted the draft
Municipal Development Plan Strategy for review on Thursday, April 4, 2013 and the final
document was submitted on May 6, 2013.
ii. The preparation of the Municipal Development Plans was launched on May 9, 2013 at the
First National Workshop. Module 1 - Municipal Assessment commenced in all seven (7)
municipalities on May 13, 2013 with cluster workshops and follow-up sessions conducted
by the consultants. The total amount for this Project is BZD$687,359.72. The total
outstanding amount left of this contract is BZD$494,939.79.
iii. C14: Traffic Management Training Module (QCBS-Lump sum): Swedish National
Road Consulting AB (SWEROAD) was selected as consultant for this Project. Matters
relating to the association were clarified during contract negotiation and contract went for
signature. The contract is to start by the end of June 2013. The total contract amount is
BZD$729,630.50.
iv. Physical Asset Maintenance Plan (QCBS-Lump sum): The contract was signed in April
2013 total contract amount is BZD$432,415.00, with the consulting firm Hydroplan. The
first payment of BZD$37,432.50 has been paid to the consultant with the submission of the
first draft Inception Report. The consultant has recently submitted the final Inception
Report to the PIU for their review. This contract has not had any contractual issues thus
far. The procurement method used was QCBS. Outstanding balance left on this contract is
BZD$394,982.50
b. Project activities related to “Refurbishment of Buildings”:
i. C2-3: Consulting services for design and technical inspection for buildings signed
with ATA in lump-sum contract was reviewed by Mission, given the non-compliance with
the contract conditions. While 100% payments of the contract had been made to ATA by
PIU, deliverables had been only partially made under Interim Report #3 for Dangriga. It
was agreed that the 20% payment for Interim Report #3 be split between PG and Dangriga
based on supervision of civil works contracts, based on which the overpaid amount was
calculated as BZ$21,641 with BZ$11,656 overpaid for Interim #3 and BZ$9,985 for final
payment. The refund decision is subject to the fiduciary consideration by PIU’s Financial
Management team. The lessons from ATA contract were discussed to avoid similar
contract management issues.
ii. W-3: Civil works contract for PG under NCB procedures was signed on March 22,
2012 at US$ 212,575, and completed in September 2012, on schedule.
iii. W-5: Civil works for Dangriga under NCB procedures was reviewed by the mission in
April 2012, especially on the post qualification for the lowest evaluated bid, K & G
27
Construction. Bank gave no-objection to the contract award to K & G issued on May 4 and
contract was signed on May 24, 2012 at US$ 668,675 (BZ1,377,349.50). The contract has
been delayed substantially. Though GCC46.1 for the liquidity penalty could be applied not
exceeding the total liquidity of 5% of the contract price, the reason causing the delay has
not been agreed. The Project is assessing the contract status from technical and contractual
point of view and will decide the next steps by the end of June.
c. Project activities related to “Rehabilitation of Streets”:
i. C5-10: Preparation of Designs, Technical Specifications and Cost Estimates for
Rehabilitation of Municipal Streets: Contract was signed November 2011 with
Anthony Thurton & Associates at total contract sum was BZ$299,757.94. The contract
has been completed.
ii. C5-10: Supervision of Municipal Street Rehabilitation of street works: Contract was
signed in July 2012 with TECHNIPLAN at the total contract amount is BZ $774,519.00.
The contract is time-based and managed within the ceiling of the contract. There is an
outstanding balance of BZ$108,542.74 for reimbursable expenses.
d. Civil works for the street were tendered under NCB (2 packages) and shopping (5 packages)
procedures, based on design and supervision under C5-10 consulting services. The PIU has
requested that the Bank increases the thresholds for both NCB and shopping for works, from
US$ 1.0 million per NCB tender to US$ 1.5 million per NCB tender, and for shopping from
US$ 100,000 to US$ 150,000. The Bank provided no-objection to the increase threshold in
May, 2012, which has accelerated the implementation of the Phase 1 construction works. The
following NCB packages were reviewed at the mission:
i. W 9: Rehabilitation of streets in Benque Viejo, San Ignacio and Punta Gorda
Town (NCB): The contractor Imer Hernandez Development Company signed contract on
the August 16, 2012 with a start date of September 2, 2012, at the total contract price is
BZ$2, 320, 630.65. An amendment totaling US$49,562.51 was added to the contract for
adjustment to rebuild existing concrete lined drains, to replace a culvert in Benque and
primer for asphalt coat to streets.
ii. W 11: Rehabilitation of streets in Benque Viejo, San Ignacio and Punta Gorda
Town (NCB): The contract was signed in September 2012 with A & N Construction at
the total contract amount of BZ$2,183,809.65. The contract is 97% completed with
works to be concluded in August 2013. An amendment totaling BZ$99,125.02 was
approved for additional works for drains in Orange Walk and Corozal due to poor designs
by the Design Consultant. The outstanding balance for payment is BZ$504,220.95.
Phase 2
e. C32-33: Preparation of Designs, Technical Specifications, Cost Estimates and
supervision for Structures (Small Works) in Corozal, Orange Walk and Benque Viejo
(CQS): The consultancy is advertised in the local press with a deadline of June 28, 2013. The
deadline was extended an additional week due to limited amount of EOIs received. The
proposed opening date is June 14, 2013.
f. C34-35: Preparation of Designs, Technical Specification, Cost Estimates and
Supervision of Municipal Streets Rehabilitation (Small Works) in Corozal, Orange Walk,
Benque Viejo & San Ignacio/Santa Elena and Belmopan (CQS): The consultancy was
28
advertised starting May 17, 2013 with a deadline of June 3, 2013. The proposed opening is
June 14, 2013.
g. C36: Preparation of Designs, Technical Specifications and Cost Estimates for the
Rehabilitation of Municipal streets in Belmopan, Punta Gorda, Dangriga, Corozal,
Orange Walk, Benque Viejo & San Ignacio/Santa Elena (LCS): The consultancy was
advertised starting May 1st, 2013 with a deadline of May 31
st, 2013. The deadline was extended
an additional week due to limited amount of EOIs received. The proposed opening date is June
14, 2013.