bem mar04-may04 (forensic engineering)
TRANSCRIPT
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
1/44
CONCRETE DURABILITY PROVISIONS IN DESIGN
CODES: ARE THEY REALLY ADEQUATE?
FAILURE OF STRUCTURES
LESSONS LEARNED FROM HIGHLAND TOWERS
ROUTE TO BE AN ACCREDITED CHECKER
THE WTO AND THE SOUTH: IMPLICATIONS AND
RECENT DEVELOPMENTS (PART 1)
L E M B A G A
J U R U T E R A
MALAYSIA
THE BOARD OF ENGINEERS MALAYSIA LEMBAGA JURUTERA MALAYSIA
KDN PP11720/9/2003 ISSN 0128-4347 VOL.21 MARCH-MAY 2004 RM10.00
FORENSIC ENGINEERING
FORENSIC ENGINEERING
CONCRETE DURABILITY PROVISIONS IN DESIGN
CODES: ARE THEY REALLY ADEQUATE?
FAILURE OF STRUCTURES
LESSONS LEARNED FROM HIGHLAND TOWERS
ROUTE TO BE AN ACCREDITED CHECKER
THE WTO AND THE SOUTH: IMPLICATIONS AND
RECENT DEVELOPMENTS (PART 1)
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
2/44B U L E T I N I N G E N I E U R 4
c o
n t e n t
s
Volume21
March-May2004
L E M B A G A
J U R U T E R A
MALAYSIA
16
42
12
46
6 President’s Message
Editor’s Note
8 Announcement
Cover Feature
9 Concrete Durability Provisions In Design Codes:
Are They Really Adequate?
14 Failure Of Structures
21 Lessons Learned From Highland Towers
Guidelines
28 Route To Be An Accredited Checker
Update
30 Asian And Pacific Decade Of Disabled Persons
2003-2012
Engineering & Law
31 Work Programme – A Contractual Perspective
(Part 1)
Feature
39 Best Management Practices On Soil Erosion And
Sediment Control In The Construction Industry
(Part 2)
46 The WTO And The South: Implications And
Recent Developments (Part 1)
Health
54 Detox For Health
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
3/44
Editor’s Note
B U L E T I N I N G E N I E U R 6
Members of the Board of Engineers Malaysia(BEM) 2003/2004
President YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar
RegistrarIr. Ashari bin Mohd Yakub
SecretaryIr. Dr. Judin bin Abdul Karim
Members of BEM YBhg. Tan Sri Dato’ Ir. Md Radzi bin Mansor
YBhg. Datuk Ir. Santhakumar Sivasubramaniam YBhg. Dato’ Ir. Dr. Hj. Abdul Rashid bin Maidin
YBhg. Datu Ir. Hubert Thian Chong Hui YBhg. Dato’ Ir. Ashok Kumar Sharma
YBhg. Datuk Ir. Md Sidek bin Ahmad YBhg. Datuk Ir. Hj. Keizrul Abdullah
YBhg. Dato’ Ir. Kok Soo ChonIr. Ho Jin WahIr. Yim Hon Wa
Ir. Prof. Ow Chee ShengIr. Mohd Aman bin Hj Idris
Ir. Hj. Abu Bakar bin Che’ ManIr. Prof. Abang Abdullah bin Abang Ali
Tuan Hj. Basar bin JuraimiAr. Paul Lai Chu
Editorial Board
Advisor YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar
Chairman YBhg Datuk Ir. Shanthakumar Sivasubramaniam
EditorIr. Fong Tian Yong
Members YBhg. Dato’ Ir. Ashok Kumar SharmaIr. Prof. Madya Dr. Eric Goh Kok Hoe
Ir. Prof. Ishak bin Abdul RahmanIr. Prof. Dr. Ruslan HassanIr. Prof. Dr. K. S. Kannan
Ir. Nitchiananthan BalasubramaniamIr. Mustaza bin Hj. SalimIr. Md Amir bin KasimIr. Dr Lee Say ChongIr. Chan Boon TeikIr. Choo Kok Beng
Publication OfficerPn. Nik Kamaliah bt. Nik Abdul Rahman
Assistant Publication OfficerPn. Che Asiah bt. Mohamad Ali
Design and ProductionInforeach Communications Sdn Bhd
Buletin Ingenieur is published by the Board of Engineers Malaysia (Lembaga Jurutera Malaysia)
and is distributed free of charge to registeredProfessional Engineers.
The statements and opinions expressed in thispublication are those of the writers.
BEM invites all registered engineers to contributearticles or send their views and comments to the
following address:
Publication CommitteeLembaga Jurutera Malaysia,Tingkat 17, Ibu Pejabat JKR
Kompleks Kerja Raya Malaysia,Jalan Sultan Salahuddin
50580 Kuala LumpurTel: 03-2698 0590 Fax: 03-2692 5017
E-mail: [email protected] [email protected] site: http://www.bem.org.my
Advertising/SubscriptionsSubscription Form is on page 52
Advertisement Form is on page 53
President’s Message
No one would want to see a structure collapseor fail, but the fact remains that failures do occur.When a structure collapses, the finger is invariablypointed at the structural engineer. But what isneeded in the first place is to determine the exactcause of the failure through forensic engineering.The goal of a forensic programme is to positivelyidentify the sequence of events leading to ultimatefailure.
Within the broad field of engineering, the practice of forensicengineering involves the investigation of failures of buildings,structures, pipelines, foundations, airplanes, manufacturing equipment,vehicles, bridges, flood control facilities, and other engineered products.Forensic engineers examine broken parts and bring together a list of probable failure mechanisms to be investigated. The final step inforensic engineering is to use analytical and testing tools to confirm
the findings of fact.A number of difficulties can arise when litigation commences if
the cause of failure has not been investigated adequately. Where thereis an overriding need to consider the cause of an engineering failure,fire or other scientific problem, there is considerable merit in engaginga forensic engineer or scientist to consider the cause in isolation. Theforensic engineer becomes an expert witness in support of the findings.A good forensic engineer will investigate any incident in a structured,scientific manner. He will be skilled in collecting and recording evidencein a manner that will withstand scrutiny.
There is a need to develop this area of forensic engineering as anexpert consultancy service.
TAN SRI DATO’ Ir. HJ. ZAINI BIN OMAR
President
BOARD OF ENGINEERS MALAYSIA
The introduction of extra pages in the December2003 issue has attracted positive comments from ourreaders. The Publication Committee will continue tofocus on policy, guidelines, good practices, issues andgeneral information related to the engineeringprofession.
In view of the new structure of contents, there wasa proposal to change the name of the publication as the name ‘buletin’may not adequately convey the contents anymore. Readers are welcome
to forward their views and suggestions to the Publication Committee.
Ir. Fong Tian Yong
Editor
KDN PP11720/9/2003 ISSN 0128-4347 VOL. 21 MARCH-MAY 2004
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
4/44
With the implementation of a newly
approved Continuing Professional Development
(CPD) Programme, which is in line with aprovision of the amended Engineers Act (2002),
the Board of Engineers Malaysia (BEM) invites
potential out-sourced and accredited course
providers (including those providing in-house
training courses/programmes) to register with
the BEM.
For details of registration, please refer to the
BEM’s CPD Policy, Guidelines for CPD Course
Providers and Course Endorsement requirements
which can be obtained from the office of the
BEM. The Application Form is also available upon
request.
Registration As Accredited CPDCourse Provider
L E M B A G A
J U R U T E R A
MALAYSIA
Announcement
International Conference on“Planning, Design andConstruction of Hardened andProtective Facilities”(HARDFAC 2004)Date: April 14 – 16, 2004
Venue: Hyatt Saujana Hotel, SubangOrganiser: Science and Technology
Research Institute for Defence (STRIDE),Ministry of Defence
Contact: [email protected]
Fee: RM1550
ASEAN Australian EngineeringConference 2004Date: May 26-28, 2004
Venue: Sutera Harbour Convention Centre,Kota Kinabalu
Organisers: IEM & Institution of Engineers Australia
Contact Person: Ms. Liz Khoo, Eric PringleAssociates Public Relations Sdn Bhd
Tel: 603-2161 7144
Fax: 603-2161 8209
E-mail: [email protected]
Even
t
Calenda
r
PublicationCalendar
The following list is thePublication Calendar forthe year 2004. While wenormally seek contributionsfrom experts for eachspecial theme, we are alsopleased to accept articlesrelevant to themes listed.
Please contact the Editor orthe Publication Officer in
advance if you would liketo make such contributionsor to discuss details anddeadlines.
June 2004: WATER
September 2004: ENVIRONMENT
December 2004: STRUCTURES
B U L E T I N I N G E N I E U R 8
Mechanical & ElectricalConsulting Engineers
130C, Jalan Thamby Abdullah, Brickfields,
G.P.O. Box 12538, 50782 Kuala Lumpur, Tel : 22749900, 22749895, 22749896
JURUTERA PERUNDING LC
SDN. BHD.
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
5/44B U L E T I N I N G E N I E U R 8
Are They Really Adequate?
In the 1930s, when the boom in concrete construction
began, it was generally believed that concretestructures typically designed for a design life of 50
years or so would actually last much longer with
little or no maintenance. However, that belief was
squashed when reports of premature deterioration of
concrete in tunnels, marine structures and bridge decks
were made known. It has become a worldwide problem
today. The widespread premature deterioration and
durability issues affecting many concrete structures have
eroded public confidence in the use of concrete as a
construction material. It is now prudent to critically re-
assess the provisions in design codes on concrete
durability.
CODE REQUIREMENTS ON DURABILITY
In the present design codes, durability requirements
for concrete structures are largely based on the
conventional method of specifying arbitrarily certain
limiting values e.g. concrete grade, minimum cement
content, maximum water-cement ratio, cover thickness,
and maximum structural crack width. This so-called
deemed-to-satisfy approach of specifying for concrete
“durability” frequently yields concrete performance thatis not always satisfactory. Chloride-induced corrosion of
reinforcement continues to represent the single largest
cause of deterioration of concrete structures worldwide.
Based on substantial data available from field performance,
exposure trials and laboratory tests on concrete, many
researchers are convinced that the current code
requirements do not provide adequate resistance to
chlorides, even when properly implemented. In the light
of current research, the deemed-to-satisfy rule for concrete
“durability” in the present codes can be challenged.
Strength versus Durability
In many codes and specifications, the compressive
strength of concrete is often used as a criterion for
durability. Though it may give some indication of the
potential durability of concrete, it cannot be a generally
valid criterion for several reasons. For example, thecompressive strength of a concrete cube or cylinder
constitutes the mean value of a property of an entire cross-
section of the specimen, whereas concrete durability is
governed primarily by the properties of the concrete cover
(covercrete). Concretes of the same strength grade may
differ in their durability resistance against chloride
penetration, carbonation and sulphate attack. Now, it is
generally accepted that concrete durability is largely
governed by the resistance of concrete cover to the ingress
of aggressive media. So, the emphasis should be on the
means of achieving a good quality concrete cover or ‘skin’
of the structure.
Cracks versus Durability
Cracks are inherently present in concrete due to
overstress, environmental effects and chemical reactions.
These cracks may range from wide and deep cracks on
the concrete surface, down to microcracks at the
aggregate-cement paste interface in the concrete. Although
these cracks do not generally affect the structural capacity,
they are rather harmful from the viewpoint of durability.
When the cracks are limited in number and size, they
are discontinuous and do not pose any direct effect onthe durability of concrete. However, with time, they have
the potential of becoming continuous (or interconnected)
and enlarged under the influence of stress or due to
leaching. These interconnected cracks can serve as main
conduits for transport of harmful external ions and gases
into the concrete. Concrete, thus, becomes vulnerable to
the processes of deterioration, as it gradually loses its
watertightness in the course of its service life.
Shrinkage cracks are often limited through the use of
a larger quantity of steel reinforcement, as permitted in
many codes. Mehta (1997) believed that this simply
transforms the wider surface cracks into many finer cracks
and microcracks in the concrete. The microcracks and
pores can form an interconnected pathway for ingress of
aggressive substances into the concrete.
By Ir. Dr. Lim Char Ching,
Senior Assistant Director, Forensic Engineering Unit,
PWD Malaysia
Concrete Durability Provisions In Design Codes:
Are They Really Adequate?
Concrete Durability Provisions In Design Codes:
B U L E T I N I N G E N I E U R 9
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
6/44B U L E T I N I N G E N I E U R 10
Crack Width Limits
It has been well established that corrosion of
reinforcements in concrete is dependent on crack width
and cover thickness, amongst other factors. For durability,
many codes would specify 0.3 mm as limiting crack width
for reinforced concrete structures. For marine exposure,
the minimum concrete cover given in the codes may range
from 40 mm to 60 mm. Assuming other factors being the
same, Table 1 illustrates the interplay between crack width
and cover on concrete durability.
Examples 1 and 2 illustrate a comparison of a single
parameter (either crack width or cover) on concrete
durability. In both cases, the comparison is straight
forward. Example 3 illustrates a comparison between bothcrack width and cover on concrete durability. In this
case, the assessment of concrete durability becomes
complicated.
It should be pointed out that crack width and cover
thickness are inter-dependent. For a given stress level in
the steel bar and keeping other variables constant, crack
width increases with cover thickness. Nowadays, high
tensile bars with yield strength of 460 MPa and above are
commonly used as reinforcements in concrete. In this
case, crack width larger than expected may develop when
a large cover is adopted. Of course, 0.3 mm crack width
can still be achieved with a large cover, provided the steel
is designed with much lower stress than permitted. In
this case, optimum use of high tensile bars as
reinforcements in concrete is not achieved.
The influence of both parameters, surface crack width
(Wcr ) and cover thickness (C), should be considered in
totality, i.e., one dependent on the other. This is in contrast
with the durability requirements given in many design
codes, in which surface crack width and cover provisions
are recommended to be independent of the other.
Lim et al (2000) proposed the crack width-to-cover
ratio (Wcr /C) as an indicator for assessing durability performance of a cracked reinforced concrete in a marine
environment. He concluded that it is desirable to minimise
Wcr /C of a cracked reinforced concrete in order to enhance
Table 1 : Interplay between Crack Width and Concrete Cover on Durability
Example 1:Structure A 0.3 60Structure B 0.2 60
Example 2:Structure A 0.3 60Structure B 0.3 40
Example 3:Structure A 0.3 60Structure B 0.1 40
Crack ConcreteWidth Cover Remarks(mm) (mm)
A and B having different crack width butsame concrete cover.B is more durable than A.
A and B having same crack width butdifferent concrete cover.A is more durable than B.
A and B having different crack width andconcrete cover.Which is more durable, A or B?
Figure 1 : Service Life Prediction Model
Initiation Period
Service Life
Propagation Period
Acceptable Limit
Degree of Corrosionin Steel
its durability performance in a marine
environment. A value of Wcr /C not
exceeding 0.005 is recommended.
DESIGNING CONCRETE TO LAST
Durability of concrete structures in
hostile environments have been the
concern of practising engineersworldwide. While there has been an
immense progress in the
understanding of the causes of, and
solutions to problems found in
concrete structures in recent years, the
subject is not well recognised.
Concrete structures can be designed
and built to last for many generations.
This noble aspiration can be achieved
by engineers, utilising state-of-the-art knowledge in
concrete technology.
The Concept Of Service Life
The concept of service life prediction for concrete
structures is now becoming an area of increasing interest
for engineers. In this respect, durability of concrete plays
an important role. Prediction models have been developed
to predict and quantify structural service life based on
material resistance and environmental loads. The service
life of a structure is defined as the period of time after
installation until such time when costly repair becomes
necessary.
For concrete structures in marine environments, theresistance of concrete to chloride-induced corrosion largely
controls its long-term durability performance. Concrete
deterioration due to chloride-induced corrosion can be
represented by a simple service life model consisting of
an initiation stage and a propagation stage , shown in
Figure 1.
The initiation stage is the time from initial exposure
until depassivation of steel in concrete. This is largely
dependent on the rate at which chlorides penetrate into
concrete. The propagation stage is the time from the onset
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
7/44B U L E T I N I N G E N I E U R 11
of steel corrosion until a specified acceptable “deterioration
limit” in concrete has been reached, e.g. first visible
cracking on the concrete surface or first spalling.
Many engineers have associated service life of concrete
structures primarily with the initiation stage, to maintain
structural safety and serviceability, acceptable appearance,
and without having to incur unforeseen high costs for
repair. Currently, some concrete structures around the
world have been designed using this concept, e.g. the GreatBelt Link Bridge in Denmark with 100 years of service
life! It is foreseen that within the next few years,
reliability-based service life designs may be incorporated
in today’s ordinary design procedures for concrete
structures.
Blended Cement Technology
The term ‘blended cement’ is used to include both
the products of blending of one or more mineral
admixtures with an Ordinary Portland Cement (OPC). The
process of blending can be achieved either by inter-
grinding the mineral admixture(s) with cement clinker,
or by blending the mineral admixture(s) with OPC.
The wide range of binder systems, namely, Portland
cements and blended cements available in many parts
of the world provides opportunities for the best concrete
to be chosen for a particular environment. Fly ash, slag
and silica fume are the three commonly available mineral
admixtures used in blended cements. With proper
dosage, these blends can be effective in enhancing the
performance of concrete in high chloride and sulphate
conditions. They have been found to improve the
resistance of concrete to chloride penetration and toreduce corrosion rate of steel reinforcement.
Improvements of the order of three to five times are not
uncommon. Blended cements also showed great potential
in reducing expansion and loss of strength of concrete
exposed to sulphate condition.
The use of blended cement concrete has been
recognised by most national standards and codes of
practice on concrete structures. In general, fly ash and
slag are used in blended cements for durability and long-
term engineering properties. Silica fume is used when
both early age engineering properties and durability are
needed. The common dosages of these mineral
admixtures vary between 20 and 40% for fly ash, between
35 and 80% for slag and five and 10% for silica fume.
The optimum dosages are obviously dependent upon
specific technical requirements and cost consideration
relevant to a particular application.
In the past, the lack of knowledge in blended cement
technology had resulted in structures with premature
deteriorat ion. Today, it is possible to tailor-make
improved quality concrete using blended cement
technology for many applications. Blended cement
concrete has proven worldwide to enhance workability of fresh concrete and durability properties of hardened
concrete. However, blended cement concretes also have
their disadvantages and limitations too. A particular
type of blended cement concrete may be suitable for
one application but not for the other. Selective usage of
these materials is recommended.
Performance-based Specification
Present specifications for concrete works are largely
method-based, in that they describe how works should be
carried out on site, e.g., placing and curing of fresh
concrete. The acceptance criteria for concrete at site aresolely based on tests carried out on “specially” prepared
specimens of fresh concrete. The specification “assumes”
that the workmanship in preparing the test specimens
would be the same as that in the works. This assumption
is seldom true. Furthermore, the test specimens are
subjected to a controlled curing regime and environmental
condition, compared with the concrete placed at site. It is
obvious that the quality of hardened concrete in the
structure is generally different from the test specimens.
The method-based specification has been proven to be
inadequate in addressing durability issues affecting
concrete structures. The specification cannot guarantee
a satisfactory “performance” of hardened concrete in the
structure.
A concrete structure designed for a specific service
life should be complemented with a performance-based
specification. This is to ensure that the hardened concrete
“performs” in an environment for which it is expected to
meet the service life requirement. The specification should
focus on tests to be carried out on in-situ hardened
concrete. The test results should become the basis for
accepting or rejecting the concrete at site. Improved
performance-based specifications are being developed inmany countries. However, suitable short-term
“performance” tests necessary for such specifications are
not yet available.
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
8/44
BEM
B U L E T I N I N G E N I E U R 12
CONCLUSION
Concrete structures exposed to marine environments
have been found to suffer mainly from corrosion of the
reinforcing steel. It is necessary for engineers to
understand the importance and mechanisms of chloride-
induced corrosion of steel in concrete. The effect of the
quality of concrete on the resistance to chloride
penetration, chloride threshold and corrosion rate of the
reinforcing steel are critical in determining the service
life of structures in this environment. The concept of
service life prediction for concrete structures is becoming
an area of increasing interest for engineers. Therefore, a
good understanding of the concept and its application in
structural design is essential to ensure that optimum
concrete performance is achieved before a costly repair to the structure becomes necessary.
When designing concrete for durability performance,
attention must be paid to both the performance standards
required as well as selecting a set of compatible compliance
criteria. This is to ensure that the hardened concrete
“performs” in an environment for which it is expected to
meet the service life requirement. The specifications should
focus on tests to be carried out on in-situ hardened
concrete. The test results should become the basis for
accepting or rejecting the concrete at site. Improved
performance-based specifications are being developed.
However, suitable short-term “performance” tests
necessary for such specifications are not yet available.
With the availability of mineral admixtures in many
parts of the world, it is now possible to tailor-make
improved quality concrete for most applications. A good
knowledge of blended cement technology is necessary to
ensure its full potential in being utilised for making durable
concrete.
REFERENCES
[1] Mehta, P.K. (1997), ‘Durability-Critical Issues for
the Future’, Concrete International , pp. 27-33.
[2] Rostam, S. (1996), ‘High Performance Concrete
Cover - Why It is Needed and How to Achieve It
in Practice’, Construction and Building Materials,
Vol. 10, No. 5, pp. 407-421.
[3] Sarja, A. (1996), ‘Towards Practical Durability
Design of Concrete Structures’, Proceedings of
the 7th Int. Conference on Durability of BuildingMaterials and Components, Edited by C.
Sjostrom, Sweden, pp. 1237-1247.
[4] Rostam, S. and Shiessl, P. (1993), ‘Next
Generation Design Concepts for Durability and
Performance of Concrete Structures’, Proceedings
of the 6th International Conference on Durability
of Building Materials and Components, Japan.
[5] RILEM Technical Committee 130-CSL (1996),
‘Durability Design of Concrete Structures’, Edited
by Sarja, A. and Vesikari, E., E & FN SPON.
[6] Lim, C.C., Gowripalan, N. and Sirivivatnanon,
V., ‘Chloride Diffusivity of Concrete Cracked in
Flexure’, Cement and Concrete Research, Vol. 30,
No. 5, pp. 725-730, May 2000.
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
9/44B U L E T I N I N G E N I E U R 14
By Ir. Tee Horng Hean, B.Eng. (Hons), MSc (Eng.), MBA, M.I.E.M.
Failure Of Structures
Many young engineers have never witnessed
structural failure. A structural failure may
have adverse consequences on the parties
involved in the construction of the structure.
For instance, a former school bus driver brought up a
negligence suit against a contractor who constructed a
unipole tower, which collapsed on his bus while he was
driving at the junction of Jalan Segambut and Jalan
Kuching (NSTP, March 6 2001). According to the findings,
the unipole could only withstand a wind speed of 19.2
metres per second and in Kuala Lumpur, wind speeds of as high as 35.5 metres per second have been recorded
(NSTP, March 6 2001). The best remedy for young
engineers, if in doubt of their design criteria and to avoid
any structural failure, is to ascertain the facts from reliable
sources.
What Is A Structure?
Basically, a structure is a system for transferring loads
from one place to another and nature can show examples
of structures that support loads (Seward, 1998, p.2).
Professor Harry H. West also noted that structure describes
much of what is seen in nature such as a fern leaf, an oak
tree, shrub with ribbed branches, spider webs, etc. (West,
1993, p.4). A tall tree in a rainforest, for instance, forms
buttresses (see Photo 1). A structural engineer would
definitely know that by forming these buttresses, the huge
moments (a form of force that causes bending) induced at
the base of the tree can be resisted, and as such, this
cantilever-tree can grow to a considerable height to resist
the force imposed by winds.
Engineers do make use of this phenomenon and it is
quite common to see them adopting stiffeners to resist
certain amounts of moment at a stanchion base, for
instance (see Photo 2). If engineers adopt structuralengineering knowledge, why is it that there is still failure
of structures? Some of the causes of structural failure are
discussed in the following topics.
A structural engineer’s dream is to design structures which are fit for their intended uses. No engineerwould want to see a structure collapse or fail, unless that engineer is an engineer researching incauses of failure. Some common causes of structural failure are discussed in this paper. This paper isnot intended to discredit any parties (architects, engineers, developers, advertisers, etc.) and as such,some photographs may appear doctored to protect the anonymity of the parties involved. The intentionof writing this paper is to jog the young engineer’s memory on the importance of engineeringfundamentals, and failure to observe these engineering fundamentals taught in school could be disastrous.
Photo 2: A stanchion with a stiffener
Photo 1: A tall tree with buttresses
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
10/44B U L E T I N I N G E N I E U R 15
Underestimating Loads
Sometimes, designers may underestimate the load that
would be imposed upon their structure when the structure
is in operation. A good example is the unipole structure
that collapsed as described earlier. The unipole structure
could only withstand wind pressures of not exceeding q
= 0.613 x 19.22 = 226N/m2 but in the area where the
collapse of the unipole occurred, wind pressures of as
high as q = 0.613 x 35.52 = 773N/m2 have been recorded.
Various structural elements are likely to be overstressed
when designers underestimate the load that would be
imposed on their designed structure. Consequently, their
structure is susceptible to collapse.
Connections
Surprisingly, research has shown that 30% of structural
failures are caused by defective detailed design of the
joints between structural members (Seward, 1998, p.232).
For instance, a simple system of hoarding with structural
elements being connected with undersized bolts may look
perfectly sturdy (see Photo 3). However, due to the use of
undersized bolts (see Photo
4 and Photo 5), connecting
the horizontal and verticalstructural members, the bolts
were sheared off, causing the
horizontal elements to be
disconnected and resulting in
the cantilever effect (see
Figure 1). Bearing in mind
that in a ‘cantilever’ system,
the stress intensity
experienced by the structure
can be as large as four times
of that of the ‘continuous’
system.
This is precisely what
happened to this hoarding
and since the bolts were
sheared off, the domino
Photo 3: A typical ‘continuous’ hoarding system
Photo 4: A sheared off bolt with the size of one’s thumbnail
Photo 5: A small bolt used to connect structural elements
Figure 1: Change of structural system due to sheared bolt
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
11/44B U L E T I N I N G E N I E U R 16
effect of excessive
bending of the steel
hoarding sheet (see Photo
6 ), the structural members
being subjected to
excessive bending and the
footing being pulled off
the ground (see Photo 7 )
occurred.
In short, failure of connections can lead to a
change in the structural
system, and in turn, have
adverse domino effects.
Photo 6: Failure of a simple hoarding
structure
Inconsistent Design, Detailing And Construction
A structural engineer deals with numbers in his
structural design, which may be Greek to a layman, a
draughtsperson or even the contractor. In order tocommunicate his design to the contractor, structural
drawings are produced. At times, the structural engineer
may not be the one producing the structural drawings
but his draughtsperson would be the one drafting it.
Somehow or rather, miscommunication may occur and
designs do not tally with the drawings. There may be
times when young engineers may draft the drawings but
drafted them incorrectly. It is quite common to note
that engineers analyse a reinforced concrete structure
as a pin-joint or simply supported but in his or her detail,
a fixed support is being provided. The consequence of
proceeding with construction would be similar as that
of the hoarding where a change of structural system may
occur.
A good example of a pin-joint can be seen in a see-
saw (see Photo 8).
Photo 8: A pin-joint
Photo 7: A footing being pulled off the ground
For instance, a lamppost when properly fixed to the
ground (see Photo 9), is perfectly sturdy and most
engineers would analyse the lamp-post as a fixed
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
12/44B U L E T I N I N G E N I E U R 17
Not Considering Elements In Contact With Structure
When columns are supported by relatively small
footings and the soil surrounding the footings is of
compressible soil, a structural engineer should analyse
the columns as pin-jointed (Winter & Nilson, 1979, p.392).
Similarly, if the soil surrounding the footings is stiff and
incompressible, then the structural engineer should analyse
the columns as fixed.
Photo 9: A lamp-post
Photo 13: Close-up view of footing of Photo 12
Photo 10: A collapsed lamp-post
Photo 11: Lamp-post not properly fixed to the ground (Close-up of Photo 10)
Photo 12: A collapsed signboard
cantilever. But due to improper detailing or construction,
this lamp-post behaved like a pin-joint (similar to the
see-saw) and some lateral force had induced the collapse
of the lamp-post (see Photo 10 and Photo 11).
Structural engineers would analyse a signboard,
assuming it to be fixed but sometimes, due to the soil
conditions, it is not possible to have a fixed joint. For
instance, one would analyse this signboard as fixed (see
Photo 12), but due to the fact that the soil is soft and
compressible, after a heavy shower and due to strong wind
forces the footing of this signboard can easily be pulled
out when the post is not adequately penetrated into theground (see Photo 13). The strong wind has imposed a
stress that is higher than that allowed by the soil, and
consequently, the footing behaved as a pin-joint.
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
13/44
Photo 15: Soft and compressible soil (Close-up of Photo 14)
Photo 14: A deflected signboard
Similarly, the following signboard was erected in soft
and compressible soil and consequently, excessive
deflection is experienced and one could easily pull down
the whole signboard without much effort (see Photo 14
and Photo 15).
Following the above argument, we can deduce that if
a structural element were to be anchored into a brick-
wall, it is considered fixed so long as the stresses
transferred to the brick-wall at the joint do not exceed
the stress of the brick. On the other hand, if the appliedforce on the structural element is excessive, causing the
stresses transferred to the brick-wall at the joint to exceed
the allowable stress of the brick, this element now behaves
like a pin-joint (similar to the see-saw). This is one of
the aspects often overlooked and has to be taken into
consideration in structural engineering designs. metres collapsed after a gust of strong wind (see Photo
16 ). A rough free body diagram of this structure is shown
in Figure 2.
After running a simple structural analysis on the above
structure by applying a wind force with a speed of 35.5
metres per second, it was noted that the structure would
not have collapsed if undersized angles were not used.From the site condition, it was observed that the angles
gave way and experienced excessive twisting and buckling
(see Photo 17 ).
Photo 16: Collapse of a signboard
Providing Undersized Members
Though it seldom happens, there are times when
undersized members are used. These undersized members
would most definitely experience excessive stress. When
certain structural members cannot withstand the forcesthat are imposed upon them, the structure would be
imminent of collapse. For instance, the following
signboard measuring approximately 20 metres by 16.5 Figure 2: Free body diagram of signboard
Photo 17: Twisting and buckling of undersized angles
B U L E T I N I N G E N I E U R 18
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
14/44
Due to the fact that the angles failed, the above
structural system changed from a triangular frame (see
Figure 3) to a cantilever.
The change of the structural system has caused thecantilever to experience a high bending stress near the
footing. This high bending stress cannot be resisted by
the welding provided between the I-beam and the baseplate
(see Photo 18), and consequently, the toppling of the
signboard occurred. Besides that, this high stress has
caused the web of the I-beam to tear (see Photo 19).
Lack Of Maintenance
Many people have the misconception that structures
do not need any maintenance. This is totally incorrect.
Whatever the structures are made of, whether steel, timber
or reinforced concrete, they need constant maintenance.
Steel structures, for instance, are susceptible to corrosion
while timber structures can be destroyed by a colony of
termites. Without maintaining a structure, slowly butsurely, defects would occur. If these defects are left
unattended, it would lead to further serious defects and
in the end, a structural collapse may be possible due to
the weakening of the structural members.
Overlooking The Third Dimension
Every single object, be it a ball, a car or a structure,
can move in three different directions, namely left to right,
up to down and backward to forward. All structures,
except for space frames, can be analysed and designed by
simplifying them into two-dimensional structures. There
may be the possibility that engineers can overlook one of
the three dimensions. When this occurs, the structure is
only structurally sound in two dimensions but can fail in
the third dimension.
Constructing An Unstable (Mechanism) Structure
There are times when a structure is erected but is
unstable. This is especially frequent in roof trusses. Many
a time, the centre line of the structural members do not
meet and thus, forming a structural system which is not atruss. For instance, the following structural framework
(see Photo 20) was constructed and it was noted that there
was no triangulation of the framework, which was of
necessity for roof trusses. The structure looked sturdy
when erected. Even when the roofing sheets were installed
(see Photo 21), the structure still looked stable.
Unfortunately, during the monsoon season, heavy rain
and strong wind were inevitable and they both imposed
additional load on the structure, which consequently
collapsed (see Photo 22). Most textbooks on structural
mechanics would note that most trusses would require a
system of triangulation in order for the structure to be
stable, and in this case (see Photo 20), the collapsed
structure did not have any form of triangulation system.
Not Consulting An Engineer
Obviously, this point needs no explanation whatsoever.
There are times when constructors would defy the
instructions of engineers and proceed with construction,
without realising that they could be constructing a
collapse-prone structure.
Worst of all, there are owners who never even engagea structural engineer but ‘copy’ the sizes of a structure
from another construction site to erect their own. This
can be very dangerous as the site conditions vary.
Figure 3: Change of structural system
Photo 19: Tearing of I-beam’s web
Photo 18: The weld between the I-beam and baseplate
gave way
B U L E T I N I N G E N I E U R 19
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
15/44
Conclusion
The paper discussed only some of the common factors
as to why structures fail. There can be lots of other factors
including minor mistakes such as dimensioning a
structural member longer than it is supposed to be, usingthe wrong units (imperial/metric), not following the
construction drawings, mixing of high tensile and mild
steel reinforcements for reinforced concrete structures,
reducing the lever arm of a reinforced concrete structural
element when workers step on the steel reinforcements,
providing inadequate anchorage length for reinforcement
bars, etc. which can lead to structural failure. The other
cause of possible failure in the structure is misuse of the
erected structure. One of the best ways for young engineers
to avoid making the mistakes discussed in this paper is to
ascertain the facts from reliable sources.
The fundamentals of engineering should be applied inthe design of all engineering structures. Overlooking the
design of even a minute part of a structure such as
connections can be disastrous.
Photo 21: Roofing sheets installed to timber frame
REFERENCES
Harry, H. West, 1993, Fundamentals of Structural Analysis, John Wiley & Sons, New Jersey.
NSTP, 6 March 2001, New Straits Times Press,
March 19 Decision by Court on Negligence Suit ,
[Online], Available from URL: http: //www.lexis-
nexis.com/universe [Accessed: 18 November
2003]
Seward, D., 1998, Understanding Structures –
Analysis, Materials, Design, Second Edition,
MacMillian, Hampshire.
Winter, G. & Nilson, A. H., Design of Concrete
Structures, Ninth Edition, McGraw Hill, New
York.
Photo 20: An unstable timber truss structure without proper triangulation system
Photo 22: Collapse of timber structure
BEM
B U L E T I N I N G E N I E U R 20
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
16/44B U L E T I N I N G E N I E U R 21
Lessons Learned From
Highland TowersBy Murgan D. Maniam, Pengarah Undang-Undang, Majlis Perbandaran Pulau Pinang
Highland Towers, as is collectively known,
consisted of three blocks of apartments known
as Blocks 1, 2 and 3. It was constructed
between 1975 and 1978. Directly behind the
three blocks was a steep slope. A stream (‘the east stream’)
originating upslope from the Metrolux land flowed across
part of the slope.
On Saturday, December 11, 1993, about 15 years later,
after 10 days of continuous rainfall, a landslide occurred
resulting in the collapse of Block 1. Forty-eight people
were recorded dead. Immediately after the collapse of Block 1, the residents of Blocks 2 and 3 were prevented
from entering their apartments by MPAJ for fear of the
instability of these two buildings. A few days later, they
were allowed in but only to collect their personal
valuables. At that time, their apartments were looted
and subsequently vandalized.
Seventy-three owners and occupiers of the Blocks 2
and 3 apartments brought an action against 10 defendants
in negligence, nuisance, strict liability under the rule in
Rylands v. Fletcher and breach of statutory duty. The
Plaintiffs alleged inter alia that they had been unable tore-occupy Blocks 2 and 3 emanating from the collapse of
Block 1, as the result of MPAJ’s pre and post-collapse
acts and omissions.
The 10 Defendants were as follows:
(i) 1st Defendant - Developer
(ii) 2nd Defendant - Draftsman who was engaged
by the developer as the
Architect for the project
(iii) 3rd Defendant - 2nd Defendant’s brother
engaged by the 1st Defendant
as the Engineer for the project
(iv) 4th Defendant - Majlis Perbandaran
Ampang Jaya
(v) 5th Defendant - Arab-Malays ian Bank –
owner of 50 lots of bungalow
land directly at the rear of
Highland Towers
(vi) 6th Defendant - Tropic - company that carried
out clearing works on the 5th
Defendant’s land in 1992
(vii) 7th Defendant - owner of Metrolux land (the
higher land adjacent to the 5th
Defendant’s land)
Architects and engineers owe a professional obligation to the public and their profession to
conduct themselves and practise their profession in accord with ethical standards. Local authorities
are also required to act reasonably and in accordance with the law.
Clients and the public place trust and confidence in the competence and skills of the professionalarchitects and engineers. Generally, both the professionals depend on the personal confidence of
the client in their technical competence; and the confidence of the public at large in the integrity
and ethical conduct of the professions as a whole.
It is the purpose of this paper to examine the decision of the High Court and the Court of
Appeal in respect of the roles played by the architect, engineer, developer and the local authority
in the development of the Highland Towers, and to learn the observations and rulings of the two
courts to give a greater insight and understanding of their respective roles.
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
17/44B U L E T I N I N G E N I E U R 22
(viii) 8th Defendant - Project Manager for the 7th
Defendant and was in charge
of the development of the
Metrolux land.
(ix) 9th Defendant - Selangor State Government
(x) 10th Defendant - Director of Lands and Mines,
Selangor
JUDGMENT OF THE HIGH COURT
The High Court found the 1st, 2nd, 3rd, 4th, 5th, 7th and 8th
Defendants liable and apportioned liability in the following
percentages :
(i) 1st Defendant - 15%
(ii) 2nd Defendant - 10%
(iii) 3rd
Defendant - 10%
(iv) 4th Defendant - 15%
(v) 5th Defendant - 30%
(vi) 7th & 8th Defendants - 20%
After due consideration, the court ruled that the
landslide that brought down Block 1 was a rotational
retrogressive slide emanating from the high wall behind
the second tier car park. The High Court also decided
that Block 1 had collapsed due to a landslide causedprimarily by water which emanated from the damaged
pipe culvert, and the inadequate and unattended drains
on the 5th Defendant’s land.
The judgment of the High Court has since been reported
as Steven Phoa Cheng Loon & Ors v Highland Properties
Sdn. Bhd. & Ors (2000) 4 MLJ 200.
LIABILITY OF THE 2ND DEFENDANT – THE ARCHITECT
The 2nd Defendant was an Architectural Draftsman.
He drew and submitted the layout plans for and on behalf
of the 1st Defendant. The 2nd Defendant knew that he was
not a fully qualified and registered architect. When the
layout plan was approved subject to conditions, the 2nd
Defendant prepared and submitted the building plans.
The 2nd Defendant, whilst submitting the layout plans
and building plans, had held himself out as a registered
architect. The local authority, by some error on their part
in not checking the 2nd Defendant’s credentials had in
fact permitted him to submit such plans.
CF was issued for the three blocks on the following dates:
(i) Block 1 - 29.9.1978
(ii) Block 2 - 6.11.1981
(iii) Block 3 - 24.5.1985
The Plaintiffs alleged that the 2nd Defendant had held
himself out to be a suitably qualified, competent and skilled
person to design, prepare and sign architectural and other
building plans. In the performance of this task, the 2nd
Defendant has breached a common law duty of care to
the Plaintiffs to take reasonable care and diligence in
ensuring that:
(i) the drainage required and rubble walls and theearthworks were adequately and properly
designed, supervised during its construction and
in compliance with the requirements as set by
the authorities;
(ii) by the same acts or omissions, the 2nd Defendant
had created a nuisance on the hill slope behind
Highland Towers.
The 2nd Defendant argued that he did not owe such
duty of care to the Plaintiffs. Furthermore, even if suchduty of care exists, it was not breached. He explained
that he was only engaged to design the three apartment
blocks and was never involved in the design, supervision
and construction of drains, rubble walls and earthworks
within and outside of Highland Towers site; he submitted
that the 1st Defendant (Developer) carried out these works.
He played no part in them. He also submitted that the
intervening acts of the 4th, 5th, 7th and 8th Defendants in
altering the condition of the area caused the collapse of
Block 1 and exempted from liability.
A building draftsman is only permitted under the Architect’s Act 1967 to design buildings of no more than
two storeys in height and limited floor space. In this case,
each block of Highland Towers consisted of 12 storeys
with a built area far exceeding that allowed for a building
draftsman to undertake. The 2nd Defendant managed to
induce a relevant Government department to grant him a
‘specially authorised person’ status under a repealed
enactment (the Architect Ordinance 1951) which he
claimed entitled him to summit and oversee construction
works of three apartment blocks.
The court held that this would make no difference to
the duty of care the 2nd Defendant owed. James Foong J
said:
‘When this Defendant had represented himself as a
qualified architect to all and sundry, as displayed by
his actions, then he must be judged according to the
character he had assumed.’
The extent of his duty, said the judge:
‘Is primarily to his client because he has a contractual
relationship with him. But in law, an architect is
also liable to anyone who is sufficiently proximate
and whom the architect could foresee that his act
and/or omission would cause damage to that person.
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
18/44B U L E T I N I N G E N I E U R 23
….. At the time when this Defendant exercised his
duty as an architect for the Highland Towers project,
he must have foreseen that the apartments he built
would be sold, and purchasers, their servants and or
agents would be occupying them. ….. he must have
or ought to have them in contemplation when he
was directing his mind to his acts and/or omissions.’
By this, a duty of care existed between the 2nd
Defendant and the Plaintiffs.
The 2nd Defendant had also argued that he had no
responsibility for the drainage or earthworks or anything
else beyond the design and supervision of construction
of the apartment blocks. To this, the judge held:
‘I think the 2nd Defendant is under a serious
misapprehension that an architect is engaged just
to design and supervise the construction of a building
and need not bother with the surrounding area where
the building is to be erected. Surely the primary
consideration for the construction of any building,or structure for that matter, besides the aesthetics
aspect, is the safety of the building. To achieve this,
the condition of the land on which the building is to
be built as well as those in the vicinity must be
considered and evaluated, particularly if it has
potential adverse effects to the building planned.’
‘…… He must ensure that no soil from the hill slope
would come crashing down on his designs. …..’
‘…… the 2nd
Defendant did foresee the danger of not exercising his professional skill, care and diligence
in attending to the initial and basic factors regarding
drainage and the stability of the hill slope. As an
architect, or someone who represented himself as
one, he must have foreseen the dangers that if no
proper, adequate and sufficient drainage system and
retention walls were built, there would be danger to
the buildings erected below. Yet he neglected this
basic duty. The intervening acts of the third parties
may not be foreseen by him, but if a proper, adequate
and sufficient drainage system and retaining walls
were implemented and erected, then the collapse of Block 1 may not even have occurred.’
On the facts, the court found the 2nd Defendant had
breached his duty of care to the Plaintiffs. The 2nd
Defendant was held to have ‘failed in his duty as an
architect and had also refused to comply with the
requirements imposed by the authorities on the drainage
of the area. Besides that, he had also colluded with the
1st and 3rd Defendants (Developer and Engineer) to obtain
CF for the three apartment blocks of the Highland Towers
without fulfilling the conditions as set out by the 4
th
Defendant (MPAJ).
The 2nd Defendant argued that the Plaintiffs’ claim
for pure economic loss i.e. compensation to make good
the defective building or for a replacement thereof which
the 2nd Defendant was engaged to build cannot be
maintained.
The court held that a claim for pure economic loss can
be maintained against a Defendant, and therefore ruled
that the Plaintiffs’ claim for negligence and nuisance is
established against the 2nd Defendant.
LIABILITY OF THE 3RD DEFENDANT – THE ENGINEER
The 3rd Defendant was a qualified civil engineer. The
2nd Defendant appointed the 3rd Defendant, who was his
brother, to be the consulting engineer for Highland Towers.
Initially, the 3rd Defendant’s scope of works was restricted
to the structural aspect of the three blocks. But
subsequently, the 3rd Defendant was engaged by the 1 st
Defendant to submit proposals over the drainage of the
area. His drainage plan was approved. He was also
retained by the 1st Defendant to design and supervise the
construction of two retaining walls on the Highland Towers
site.
The Plaintiffs claimed that the 3rd Defendant wasnegligent for the following reasons:
(i) designing unsuitable foundations;
(ii) lack of care and concern of the hill and slope;
(iii) issuing a notice to the authorities confirming the
drainage works was completed when only a
fraction of it was done.
By the above acts of preparing, designing andsupervising the construction of Highland Towers and the
drainage system of the Highland Towers site, he was
negligent and had caused nuisance to them.
The 3rd Defendant had used rail piles welded together
as foundation to support the three apartment blocks. This
type of piles, which was considered inferior to concrete
piles, was accepted in the engineering and building
industry to support high-rise buildings at the material
time. Thus, no fault can be attributed to the 3rd Defendant
in using the rail piles as he was only adhering to the
accepted professional practice at that time.
However, there was lack of consideration by the 3rd
Defendant to the hill and the slope directly behind the
three blocks. The court ruled that the 3rd Defendant should
have reasonably foreseen the danger of a landslide
producing a lateral load against the foundation of the
building. For this, he should have exercised care to either
design and construct a foundation to accommodate the
lateral load or ensure that the slope was reasonably stable.
Failure to do so is a breach of his duty of care he owes to
the Plaintiffs since his duty was to ensure the safety of
the buildings he designed and built.
The 3
rd
Defendant’s attempt to deny liability on theground that he relied on the 1st Defendant to ensure that
other retaining walls were constructed properly was
unsuccessful. The judge found that it was encumbent
upon the 3rd Defendant to enquire and ascertain whether
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
19/44
the work was that of a qualified professional and what its
impact might be on the safety of his own building. The
judge agreed with a passage from the judgment of Bingham
LJ in the case of Eckersley v. Binnie (1988) 18 Con LR 1
@ p.80
‘…… a professional man should command the corpus
of knowledge which forms part of the professional
equipment of the ordinary member of his profession.He should not lag behind other ordinarily assiduous
and intelligent members of his profession in knowledge
of new advances, discoveries and developments in his
field. He should have such awareness as an ordinarily
competent practitioner would have of the deficiencies
in his knowledge and the limitations of his skill. He
should be alert to the hazards and the risk inherent
in any professional task he undertakes to the extent
that other ordinarily competent members of the
profession would be alert. He must bring to any
professional task he undertakes no less expertise, skill,
and care than other ordinarily competent members of his profession would bring, but need bring no more.
The standard is that of the reasonable average. The
law does not require of a professional man that he be
a paragon combining the qualities of polymath and
prophet.’
Although the drainage plan was approved by the
authorities, it was not fully implemented by the 1 st
Defendant. The reasons offered by the 3rd Defendant for
this failure were:
(i) shortage of financial resources of the 1st
Defendant;
(ii) the need to bring down the road level to fit the
drains; and
(iii) prohibition on rock blasting in the area
Nevertheless, the court ruled that whatever the excuse
may be, it did not entitle and warrant the 3rd Defendant to
issue a notice to the authorities stating that the entire
approved drainage proposal was implemented when only 10% was completed. This was a gross violation of his
duty of care which, as a consultant engineer for the three
blocks, he owes to the Plaintiffs as purchasers of Highland
Towers, particularly when this approved drainage system
was so fundamental to the safety of the building. The
judge issued a powerful condemnation by saying as
follows:
‘I have reiterated my strong sentiments against this
type of attitude of professionals whose only
consideration is to guard and secure their own interest rather than their duties and obligations to those closely
affected and the public on which so much faith and
reliance are placed on them to carry out their
professional duties. I need not elaborate further except
to remind this Defendant that he has to live out the
rest of his life knowing truly well that he had
contributed to the tragedy of Highland Towers.’
The 3rd Defendant was found liable in negligence
and nuisance.
LIABILITY OF THE 1ST DEFENDANT – THE DEVELOPER
The Plaintiffs claimed the 1st Defendant liable in negligence
for the following reasons:
(i) Not employing reasonably fit, competent, skilled
and qualified persons to design, draw, sign and
submit architectural and engineering drawings
and plans for the construction of Highland Towers
and the hill slope behind it;
(ii) Not vetting through their appointments to ensure
that they are competent and possess such skill
for the task they are employed to undertake whichinvolves enquiries and investigations into their
credentials and qualifications;
(iii) Constructing insufficient and inadequate
retaining walls on the Arab-Malaysian land and
the Highland Towers site without considering the
surrounding terrain, soil condition and drainage
requirement;
(iv) Constructing drains that were insufficient to effect
proper and adequate drainage of water run-offson the slope and those originating from the East
Stream;
(v) Diversion of the East Stream from its natural path
to the pipe culvert which ran horizontally across
the hill slope directly above the three blocks;
(vi) Obtaining CF to occupy the three blocks when
the drainage system in the Highland Towers site
and the Arab-Malaysian land was incomplete.
The court relied upon the dictum of Lord Finlay LC inGreenock Corp. v. Caledonian Rly Co. (1917)AC 556 which
is quoted by Abdul Hamid FJ in the Federal Court case of
Seong Fatt Sawmills Sdn. Bhd. v. Dunlop Malaysia
Industries Sdn. Bhd. (1984) 1 MLJ 286 @ p 291.
‘It is the duty of anyone who interferes with the course
of the stream to see that the works which he substitutes
for the channel provided by nature are adequate to
carry off the water brought down even by extraordinary
rainfall, and if damage results from the deficiency of
the substitute which he has provided for the natural channel, he will be liable .’
The court exonerated the 1st Defendant from the
allegation that they were responsible for the negligence
B U L E T I N I N G E N I E U R 24
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
20/44
of their consultants after appointment . The court held
that the 1st Defendant would only be liable if the works
involved were ‘of an extra hazardous nature’ which was
not the case here.
The court held that the 1st Defendant were liable in
negligence and nuisance.
LIABILITY OF THE 4TH DEFENDANT –
MAJLIS PERBANDARAN AMPANG JAYA (MPAJ)
The High Court held MPAJ liable in respect of the
following :
(i) At the planning and design stage of Highland
Towers, MPAJ had not taken reasonable care, skill
and diligence in checking the plans submitted to
ascertain whether they are reasonably fit for the
purpose it was intended for. This included matters
relating to water courses, streams and rivers in
the vicinity of the Highland Towers site, Arab
Malaysian land and the surroundings which wereunder the jurisdiction of MPAJ.
(ii) At the construction stage of the Highland Towers,
MPAJ failed to exercise reasonable care, skill and
diligence to ensure the drainage system and the
rubble walls on Arab Malaysian land were
adequately provided for and/or constructed in a
workman-like manner before the issuance of the
Certificate of Fitness to the three apartment
blocks;
(iii) MPAJ failed to maintain and upgrade drains and
rubble walls on Highland Towers site and Arab
Malaysian land, and to provide adequate drainage
requirement to water courses, streams and rivers
after the Highland Towers was constructed;
(iv) MPAJ failed to take remedial measures to remove,
rectify and/or minimise the hazards posed on the
Arab-Malaysian land and the surroundings after
the collapse of Block 1;
(v) MPAJ failed to prevent vandalism and theft atBlocks 2 and 3 in the aftermath of the collapse
of Block 1;
(vi) MPAJ failed to maintain the East Stream which
was under its jurisdiction;
According to the court, MPAJ owes a duty of care to
the Plaintiffs to use reasonable care, skill and diligence to
ensure that the hill slope and the drainage thereon were
properly accommodated before approving building or
other related plans, and during construction stage, tocomply with and to ensure the implementation of the
drainage system. Then, when Certificate of Fitness was
applied for, there should be proper and thorough inspection
on whether the buildings so built were safe in all aspects
and not just confined only to the structure, and after the
Highland Towers was erected, to ascertain drainage
requirement in the area was adequate to ensure slope
stability behind Block 1. Subsequent to the collapse of
Block 1, measures should have been taken to prevent
recurrence of the tragedy to Blocks 2 and 3.
The court found that MPAJ owed a duty of care to the
Plaintiffs and that this duty had been breached resulting
in damages.Upon establishing that MPAJ was negligent, the High
Court was influenced by Sec.95(2) of the SDB Act 1974,
which provided an immunity to the Plaintiffs’ claims and
the passage in Dr. Abdul Hamid Abdul Rashid & Anor v.
Jurusan Malaysia Consultant & Ors (1997) 3 MLJ 546 :
‘If there is any fear that this approach may encumber
the local authorities to pay out substantial claims
due to their negligence in granting approvals or
inspecting building works, there is s 95 of the Street,
Drainage & Building Act 1974 (Act 133) which
prohibits such authorities to be sued.’
In discussing the above Sec. 95(2), the High Court
pointed that Parliament can create an exemption from
liability for certain acts committed by local authorities
and its officers. James Foong J said:
‘It is my view that s 95(2) of the 1974 Act is just
such a piece of legislation to exempt the local authority
and its officer from negligent act related to and
connected with certain specified activities. In our
case, since the acts of the 4th
Defendant found to be negligent by this court are within those specified
activities under s 95(2) of the 1974 Act, immunity
applies to the 4th Defendant.
Further, the High Court explained that Sec. 95(2) covers
situations:
(i) ‘whatsoever arising out of building or other works
carried out’ by the 4th Defendant in accordance
with the provision of the said Act.
(ii) ‘or by reason of the fact that such building worksor the plans thereof are subject to inspection and
approval’.
The acts of negligence of which MPAJ was accused of
inter alia, approval of plans, inspection and issue of CF
were all covered by this immunity. Thus Sec. 95(2) applies
to acts/omissions committed by MPAJ pre-collapse .
However, the immunity could not cover the post- collapse
actions of MPAJ and for these, they were liable.
MPAJ had undertaken to prepare a master drainage
plan to ensure the safety of Blocks 2 and 3. After a periodof one year, there was no sight or news of such a plan.
MPAJ offered no explanation as to why its promise was
not met. Thus, MPAJ was held liable for post-collapse
management of the situation which included failure to
B U L E T I N I N G E N I E U R 25
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
21/44
prevent vandalism and theft in Blocks 2 and 3 as well as
failure to produce the master drainage plan. MPAJ was
also liable in nuisance by reason of its failure to maintain
properly a stream which formed part of the drainage
system of the area.
JUDGMENT OF THE COURT OF APPEAL
The 1st,
2nd
, 6th
, 9th
and 10th
Defendants did not appealagainst the decision of the High Court. The 3rd, 4th, 5th, 7th
and 8th Defendants appealed against that decision.
MPAJ filed an appeal to the Court of Appeal against
the whole decision of the High Court except that part
which decided that MPAJ was not liable for all pre-
collapse acts by virtue of Sec. 95 of the SDB.
Although the High Court excluded liability for pre-
collapse acts on the part of MPAJ on the basis of Sec.
95(2) of the SDB, MPAJ had raised the grounds of appeal
in the Court of Appeal that independently of Sec. 95(2) of
the SDB, MPAJ had not been negligent at all because :
(i) at the planning and design stage, MPAJ had relied
on the skill and diligence of the Architect (2nd
Defendant) who submitted those plans as well as
the various Government agencies which vetted
those plans.
(ii) at the construction stage of the Highland Towers,
MPAJ had relied on the skill and diligence of the
1st, 2nd and 3rd Defendants to supervise the said
construction and had relied on the Certificates
of the Architect (2nd
Defendant) that all the workshad been completed in compliance with the
approved plans.
(iii) the Highland Towers and the surrounding areas,
after completion and after Certificate of Fitness
had been issued, had been maintained by the 1st
Defendant.
(iv) the drains in Highland Towers and the Arab
Malaysian land were never in the control of
MPAJ.
(v) the East-Stream was diverted from its natural
course by the 1st Defendant as found by the High
Court.
(vi) the drainage of the Highland Towers and the
Arab-Malaysian land was functioning effectively
until the 5th Defendant took over the Arab-
Malaysian land.
(vii) at no time did the Plaintiffs complained to MPAJ
of the dangers of the state of the drains in theHighland Towers and the Arab-Malaysian land.
In considering the appeal of MPAJ against liability,
the Court of Appeal ruled that there are two separate
matters that must be addressed. These are the pre-collapse
and post-collapse liability.
The Court of Appeal observed that assuming that there
was a duty on the 4th Defendant (MPAJ) to act in a
particular manner towards the property of the Plaintiffs
post-collapse, such duty must find its expression in public
and not private law. Accordingly, if there had been a
failure on the part of MPAJ to do or not to do something
as a public authority, the proper method is to proceed by way of application for judicial review. Thus the High
Court’s finding that MPAJ was liable for negligence after
the collapse was set aside.
Next, the Court of Appeal looked at the pre-collapse
position. The Plaintiffs submitted that Sec. 95(2) did not
apply to the facts as MPAJ had directed the East Stream
to be diverted from its natural course. The carrying out
of these works created a danger to the Plaintiff’s property.
Accordingly, this is not a case of inspection or approval
of building or other works or the plans thereof. This is a
case where a danger was expressly created by MPAJ. The
Court of Appeal agreed with this submission and set asidethe indemnity granted to MPAJ by the High Court for
negligence before the collapse.
The Court of Appeal ruled that there is no proposition
of law that a local authority such as MPAJ may never
owe a common duty of care to the third party. It all
depends on the particular circumstances. The kind of
harm that was foreseeable by the 5th Defendant was equally
foreseeable by the MPAJ. Upon the evidence and the
relevant principles, it was clear that MPAJ, as a reasonable
local authority must have foreseen the danger created by
diverting the East Stream would probably be a landslideof the kind that happened and that in such event resultant
harm, including financial loss of the kind suffered by the
Plaintiffs would occur.
The Court of Appeal dismissed the appeals of the 3rd,
5th, 7th and 8th Defendants and affirmed the apportionment
of liability made by the High Court amongst the
Defendants.
The judgment of the Court of Appeal has since been
reported as Arab- Malaysian Finance Bhd. v Steven Phoa
Cheng Loon & Ors (2003) 1 MLJ 567. It appears that the
Court of Appeal has departed from the clear finding of
fact by the High Court that it was the 1st Defendant whodiverted the East-Stream and substituted their own finding
that it was MPAJ who diverted the East-Stream.
Furthermore, although the High Court made a very clear
finding of fact that it was the 1st Defendant who diverted
the East-Stream, the Court of Appeal declared that it was
MPAJ that diverted the East-Stream. The Court of Appeal
held that MPAJ owed a common law duty of care to the
Plaintiffs to avoid pure economic loss. It also held that
MPAJ is a Joint Tortfeasor along with the other Defendants.
It was argued that at all material times, MPAJ did not
have qualified people to deal with planning application.The role of MPAJ was that of an intermediary by
forwarding that application to the respective departments,
district technical departments e.g. JKR, Health, State
Planning Departments and other authorities relating to
B U L E T I N I N G E N I E U R 26
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
22/44
that particular application. There was clear evidence
that MPAJ had relied upon the skill of the Architect (2nd
Defendant), the Engineer (the 3rd Defendant) and the
Developer (1st Defendant) as well as the checking of the
accuracy of the said plans by the relevant departments
(the 9th and 10th Defendants). The High Court held that
Sec. 95(2) SDB protected MPAJ for all acts of MPAJ pre-
collapse, including the checking of the accuracy of the
plans submitted and the failure to detect any danger inthe said plans.
However, the Court of Appeal held that Sec. 95(2) SDB
does not apply to the facts of the present case since MPAJ
had directed that the East-Stream be diverted from its
natural course and that such an act of MPAJ was caught
by the doctrine of Kane v New Forest District Council
(2001) 2 All ER 914. In Kane , the local authority
specifically required the footpath to be created. In the
present case, it was the 3rd Defendant on behalf of the 1st
Defendant who submitted the plans relating to the drains
to be implemented on the 5th Defendant’s land. In Kane ,
all the parties including the local authorities were awarethat the construction of the footpath would be dangerous.
Despite the said knowledge of danger, the local authority
went ahead with the construction of the footpath.
However, in the present case, the drainage plan was
conveyed by MPAJ to JPS. JPS recommended approval
of the drainage plan. Thus the issue of danger in the
present case did not arise at all.
Furthermore, in Kane there was no equivalent statutory
provision such as Sect. 95(2) of the SDB. In Kane , it was
also argued that local authorities enjoyed blanket
immunity in law in respect of anything done in the exercise
of the planning functions. Thus it can be said, that the
Court of Appeal had erred in relying on Kane as a basis
for depriving MPAJ the indemnity afforded by Sec.95(2)
of the SDB.
CONCLUSION
The judgments of the High Court and the Court of
Appeal cannot be lightly regarded. They discuss the causes
of the collapse of Block 1 which may arise from a variety
of circumstances. Every architect, engineer and developer
must never allow an unsafe condition to persist or develop
at the construction site. They should also ensure at all
times that there is no threat to public health and welfare
and remember two assets which are vital to the practice
of their profession – their integrity and their ability.
On February 6th, 2004, the Federal Court has granted
MPAJ leave to appeal to the Federal Court on four main
issues inter alia whether Sec. 95(2) of the SDB is wideenough to provide immunity to a local authority in
approving the diversion of a stream and in failing to detect
any danger or defect in the building and drainage plans
relating to the development submitted by the architect
and/or engineer on behalf of a developer.
Local authorities will welcome the decision of the
Federal Court as it would put to rest the debate as to
whether Sec.95(2) of the SDB provides absolute immunity
or qualified immunity.
SUMMARY
The decisions of the High Court and the Court of Appeal confirmed that architects and engineers have a duty
to secure the safety, health and welfare of the public in the performance of their professional services.
The architects and engineers owe a duty to exercise the skill, care and diligence which may reasonably be
expected of a person of ordinary competence, measured by the professional standard of the time. Thus an
architect’s and engineer’s general inexperience and lack of knowledge do not furnish a valid excuse for unprofessional
conduct.
The architects and engineers are to be judged by the professional standards prevailing at the time the work
was done, not by what may be known or accepted at a later date, or what may be seen only with the benefit of
hindsight.
The courts emphasised that every architect and engineer owe a duty to third parties to ensure that they aresufficiently qualified to undertake the assignments for which they accept professional responsibility. The architects
and engineers must also know when to seek a competent specialist in areas outside their expertise.
In this case, the Court of Appeal was unable to see how MPAJ could possibly escape liability for requiring the
diversion of the East Stream. This infers that a local authority should not direct or do anything to make the site
dangerous; otherwise it will be liable.
Although the courts did not discuss in the ground of the Judgment the certification given by the architects and
engineers on the plans submitted by them to exonerate MPAJ, these professionals’ duty must always be reflected
on the plans, by requiring the architects and engineers to certify that they are responsible for supervising the
construction of the project to ensure that it is built in accordance with the approved plans, specifications and
drawings.
The local authorities should be entitled to rely on the certificate executed by the architects and engineers and
to hold them responsible for the structural design, safety and supervision of the project. This would enable the
architects and engineers to retain control over the design and erection procedures so as to be able to advise the
contractor of any special construction or safety consideration. BEM
B U L E T I N I N G E N I E U R 27
coverfeature
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
23/44B U L E T I N I N G E N I E U R 28
INTRODUCTION
The guidelines herein are to assist Professional Engineers seeking registration as Accredited Checkers ingeotechnical and/or structural engineering works. They are in furtherance of Section 10B of theRegistration of Accredited Checker, Registration of Engineers (Amendment) Act 2002 [Act A1158].
QUALIFICATIONS FOR REGISTRATION AS AN ACCREDITED CHECKER
Any person applying for registration as an Accredited Checker shall:i) be a Professional Engineer registered under the Act in the civil, structural or geotechnical engineering
discipline;ii) have at least 10 years’ relevant practical experience in the design or construction of buildings;iii) have adequate experience in one of the following:
a) Geotechnical1) Foundations;2) Retaining Systems and Reinforced Soil Structures; and3) Slope Engineering and Embankments
b) Structural1) Buildings exceeding five storeys;2) Buildings of unconventional construction with spans exceeding 10 metres; and
3) Buildings that will result in complex interactions with existing buildings
iv) by virtue of his/her ability and standing in the profession, or specialised knowledge or practicalexperience in civil, structural or geotechnical engineering he/she is deserving of such registration,provided thata) during the period of seven years immediately preceding the date of his/her application, he/she has
been engaged in geotechnical or structural design after registration as a Professional Engineer; andb) for a continuous period of one year immediately preceding the date of his/her application,
he/she has gained such practical experience in the relevant field in Malaysia; and
v) have attended and passed the interview conducted by the Accredited Checkers Committee.
APPLICATION FOR REGISTRATION
Applications shall:i) be made in Form B3;ii) be accompanied by true copies of documentary evidence showing that the applicant possesses the
necessary qualifications and the practical experience;iii) be accompanied by three copies of relevant design report done by him/her; andiv) be accompanied by a processing fee of RM50 per application in money order/bank draft/cheque
made payable to the Board of Engineers Malaysia
REGISTRATION
a) Registration Fee
A registration fee of RM300 will be charged for those who have attended and passed the interview.
Route To Be An Accredited Checker By Accredited Checker Committee, Board of Engineers Malaysia
g u i d e l i n e s
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
24/44B U L E T I N I N G E N I E U R 29
b) Renewal Fee
Every Accredited Checker desirous of renewing his/her registration under the Act shall:i) submit to the Board an application for renewal in Form H on or before January 31st of the year
following the year of the expiration of his/her registration;ii) submit the payment in money order, bank draft or cheque made payable to theBoard of Engineers
Malaysia; and
iii) have paid up his/her annual renewal fee as Professional Engineer.
The annual renewal fee is:
Category A: Those below 60 years old RM200Category B: Those 60 years and above RM100
REMOVAL FROM THE REGISTER
Section 16 of the Registration of Engineers (Amendment) Act 2002 [Act A1158] provides for the removalfrom the Register, the name and other particulars of:
a) any registered Engineer who has died;b) any registered Engineer , other than a Graduate Engineer, or Engineering consultancy practice who
has failed to renew his or its registration within one month of the expiry of the registration;c) any registered Engineer whose registration has been cancelled under paragraph 15(1A)(d); ord) any registered Engineer whose registration has been effected by reason of any mistake or error made
by the Board in considering his application for registration.
APPEALS
All appeals shall be submitted to the Appeal Board, Board of Engineers Malaysia (constituted underSection 20, Registration of Engineers (Amendment) Act 2002 [Act A1158]).
BEM
FLOWCHART OF THE ROUTE TO BE
AN ACCREDITED CHECKER
Be a registered Professional Engineer under the Registration of Engineers Act 1967 inthe civil, structural or geotechnical engineering discipline.
HAS
Minimum 10 years’ relevant practical experience in the design or construction of buildings.
Minimum seven years’ experience in geotechnical or structural design afterregistration as Professional Engineer
Minimum one year experience in the relevant field gained in Malaysia.
Attended the Interview conducted by Accredited Checkers Committee
AND PASSED
Accredited Checker
g u
i d e
l i n e s
-
8/17/2019 BEM Mar04-May04 (Forensic Engineering)
25/44
Update
B U L E T I N I N G E N I E U R 30
In May 2002, ESCAP adopted the resolution
“Promoting an inclusive, barrier-free and rights-
based society for people with disabilities in the Asianand Pacific regions in the 21 st century”. The
resolution also proclaimed the extension of the Asian and
Pacific Decade of Disabled Persons 1993-2002, for another
decade, 2003-2012.
In October 2002, Governments at the High-level
Intergovernmental Meeting to Conclude the Asian and
Pacific Decade of Disabled Persons 1993-2002, adopted
the “Biwako Millennium Framework for Action towards
an Inclusive, Barrier-free and Rights-based Society for