bem mar04-may04 (forensic engineering)

Upload: francis-boey-wei-lun

Post on 06-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    1/44

    CONCRETE DURABILITY PROVISIONS IN DESIGN

    CODES: ARE THEY REALLY ADEQUATE?

    FAILURE OF STRUCTURES

    LESSONS LEARNED FROM HIGHLAND TOWERS

    ROUTE TO BE AN ACCREDITED CHECKER

     THE WTO AND THE SOUTH: IMPLICATIONS AND

    RECENT DEVELOPMENTS (PART 1)

       L   E   M   B   A   G   A

      J    U    R   U    T    E    R   A   

    MALAYSIA

    THE BOARD OF ENGINEERS MALAYSIA LEMBAGA JURUTERA MALAYSIA

    KDN PP11720/9/2003 ISSN 0128-4347 VOL.21 MARCH-MAY 2004 RM10.00

    FORENSIC ENGINEERING 

    FORENSIC ENGINEERING 

    CONCRETE DURABILITY PROVISIONS IN DESIGN

    CODES: ARE THEY REALLY ADEQUATE?

    FAILURE OF STRUCTURES

    LESSONS LEARNED FROM HIGHLAND TOWERS

    ROUTE TO BE AN ACCREDITED CHECKER

     THE WTO AND THE SOUTH: IMPLICATIONS AND

    RECENT DEVELOPMENTS (PART 1)

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    2/44B U L E T I N I N G E N I E U R 4

          c       o 

          n        t       e       n        t 

          s 

    Volume21

    March-May2004

       L   E   M   B   A   G   A

      J    U    R   U    T    E    R   A   

    MALAYSIA

    16

    42

    12

    46

    6 President’s Message

    Editor’s Note

    8 Announcement

    Cover Feature

    9 Concrete Durability Provisions In Design Codes:

    Are They Really Adequate?

    14 Failure Of Structures

    21 Lessons Learned From Highland Towers

    Guidelines

    28 Route To Be An Accredited Checker

    Update

    30 Asian And Pacific Decade Of Disabled Persons

    2003-2012

    Engineering & Law

    31 Work Programme – A Contractual Perspective

    (Part 1)

    Feature

    39 Best Management Practices On Soil Erosion And

    Sediment Control In The Construction Industry

    (Part 2)

    46 The WTO And The South: Implications And

    Recent Developments (Part 1)

    Health

    54 Detox For Health

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    3/44

    Editor’s Note

    B U L E T I N I N G E N I E U R 6

    Members of the Board of Engineers Malaysia(BEM) 2003/2004

    President YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar

    RegistrarIr. Ashari bin Mohd Yakub

    SecretaryIr. Dr. Judin bin Abdul Karim

    Members of BEM YBhg. Tan Sri Dato’ Ir. Md Radzi bin Mansor

     YBhg. Datuk Ir. Santhakumar Sivasubramaniam YBhg. Dato’ Ir. Dr. Hj. Abdul Rashid bin Maidin

     YBhg. Datu Ir. Hubert Thian Chong Hui YBhg. Dato’ Ir. Ashok Kumar Sharma

     YBhg. Datuk Ir. Md Sidek bin Ahmad YBhg. Datuk Ir. Hj. Keizrul Abdullah

     YBhg. Dato’ Ir. Kok Soo ChonIr. Ho Jin WahIr. Yim Hon Wa

    Ir. Prof. Ow Chee ShengIr. Mohd Aman bin Hj Idris

    Ir. Hj. Abu Bakar bin Che’ ManIr. Prof. Abang Abdullah bin Abang Ali

    Tuan Hj. Basar bin JuraimiAr. Paul Lai Chu

    Editorial Board

    Advisor YBhg. Tan Sri Dato’ Ir. Hj Zaini Omar

    Chairman YBhg Datuk Ir. Shanthakumar Sivasubramaniam

    EditorIr. Fong Tian Yong

    Members YBhg. Dato’ Ir. Ashok Kumar SharmaIr. Prof. Madya Dr. Eric Goh Kok Hoe

    Ir. Prof. Ishak bin Abdul RahmanIr. Prof. Dr. Ruslan HassanIr. Prof. Dr. K. S. Kannan

    Ir. Nitchiananthan BalasubramaniamIr. Mustaza bin Hj. SalimIr. Md Amir bin KasimIr. Dr Lee Say ChongIr. Chan Boon TeikIr. Choo Kok Beng

    Publication OfficerPn. Nik Kamaliah bt. Nik Abdul Rahman

    Assistant Publication OfficerPn. Che Asiah bt. Mohamad Ali

    Design and ProductionInforeach Communications Sdn Bhd

    Buletin Ingenieur is published by the Board of Engineers Malaysia (Lembaga Jurutera Malaysia)

    and is distributed free of charge to registeredProfessional Engineers.

    The statements and opinions expressed in thispublication are those of the writers.

    BEM invites all registered engineers to contributearticles or send their views and comments to the

    following address:

    Publication CommitteeLembaga Jurutera Malaysia,Tingkat 17, Ibu Pejabat JKR

    Kompleks Kerja Raya Malaysia,Jalan Sultan Salahuddin

    50580 Kuala LumpurTel: 03-2698 0590 Fax: 03-2692 5017

    E-mail: [email protected] [email protected] site: http://www.bem.org.my

    Advertising/SubscriptionsSubscription Form is on page 52

    Advertisement Form is on page 53

    President’s Message

    No one would want to see a structure collapseor fail, but the fact remains that failures do occur.When a structure collapses, the finger is invariablypointed at the structural engineer. But what isneeded in the first place is to determine the exactcause of the failure through forensic engineering.The goal of a forensic programme is to positivelyidentify the sequence of events leading to ultimatefailure.

    Within the broad field of engineering, the practice of forensicengineering involves the investigation of failures of buildings,structures, pipelines, foundations, airplanes, manufacturing equipment,vehicles, bridges, flood control facilities, and other engineered products.Forensic engineers examine broken parts and bring together a list of probable failure mechanisms to be investigated. The final step inforensic engineering is to use analytical and testing tools to confirm

    the findings of fact.A number of difficulties can arise when litigation commences if 

    the cause of failure has not been investigated adequately. Where thereis an overriding need to consider the cause of an engineering failure,fire or other scientific problem, there is considerable merit in engaginga forensic engineer or scientist to consider the cause in isolation. Theforensic engineer becomes an expert witness in support of the findings.A good forensic engineer will investigate any incident in a structured,scientific manner. He will be skilled in collecting and recording evidencein a manner that will withstand scrutiny.

    There is a need to develop this area of forensic engineering as anexpert consultancy service.

    TAN SRI DATO’ Ir. HJ. ZAINI BIN OMAR

    President 

    BOARD OF ENGINEERS MALAYSIA

    The introduction of extra pages in the December2003 issue has attracted positive comments from ourreaders. The Publication Committee will continue tofocus on policy, guidelines, good practices, issues andgeneral information related to the engineeringprofession.

    In view of the new structure of contents, there wasa proposal to change the name of the publication as the name ‘buletin’may not adequately convey the contents anymore. Readers are welcome

    to forward their views and suggestions to the Publication Committee.

    Ir. Fong Tian Yong

    Editor 

    KDN PP11720/9/2003 ISSN 0128-4347 VOL. 21 MARCH-MAY 2004

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    4/44

    With the implementation of a newly

    approved Continuing Professional Development

    (CPD) Programme, which is in line with aprovision of the amended Engineers Act (2002),

    the Board of Engineers Malaysia (BEM) invites

    potential out-sourced and accredited course

    providers (including those providing in-house

    training courses/programmes) to register with

    the BEM.

    For details of registration, please refer to the

    BEM’s CPD Policy, Guidelines for CPD Course

    Providers and Course Endorsement requirements

    which can be obtained from the office of the

    BEM. The Application Form is also available upon

    request.

    Registration As Accredited CPDCourse Provider 

       L   E   M   B   A   G   A

      J    U    R   U    T    E    R   A   

    MALAYSIA

     Announcement

    International Conference on“Planning, Design andConstruction of Hardened andProtective Facilities”(HARDFAC 2004)Date:  April 14 – 16, 2004

     Venue:  Hyatt Saujana Hotel, SubangOrganiser:  Science and Technology

    Research Institute for Defence (STRIDE),Ministry of Defence

    Contact:  [email protected]

    Fee: RM1550

    ASEAN Australian EngineeringConference 2004Date: May 26-28, 2004

     Venue: Sutera Harbour Convention Centre,Kota Kinabalu

    Organisers: IEM & Institution of Engineers Australia

    Contact Person: Ms. Liz Khoo, Eric PringleAssociates Public Relations Sdn Bhd

    Tel: 603-2161 7144

    Fax: 603-2161 8209

    E-mail: [email protected]

    Even

    t

    Calenda

    r

    PublicationCalendar 

    The following list is thePublication Calendar forthe year 2004. While wenormally seek contributionsfrom experts for eachspecial theme, we are alsopleased to accept articlesrelevant to themes listed.

    Please contact the Editor orthe Publication Officer in

    advance if you would liketo make such contributionsor to discuss details anddeadlines.

     June 2004: WATER

    September 2004: ENVIRONMENT

    December 2004: STRUCTURES

    B U L E T I N I N G E N I E U R 8

    Mechanical & ElectricalConsulting Engineers

    130C, Jalan Thamby Abdullah, Brickfields,

    G.P.O. Box 12538, 50782 Kuala Lumpur, Tel : 22749900, 22749895, 22749896

     JURUTERA PERUNDING LC

    SDN. BHD.

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    5/44B U L E T I N I N G E N I E U R 8

     Are They Really Adequate?

    In the 1930s, when the boom in concrete construction

    began, it was generally believed that concretestructures typically designed for a design life of 50

     years or so would actually last much longer with

    little or no maintenance. However, that belief was

    squashed when reports of premature deterioration of 

    concrete in tunnels, marine structures and bridge decks

    were made known. It has become a worldwide problem

    today. The widespread premature deterioration and

    durability issues affecting many concrete structures have

    eroded public confidence in the use of concrete as a

    construction material. It is now prudent to critically re-

    assess the provisions in design codes on concrete

    durability.

    CODE REQUIREMENTS ON DURABILITY

    In the present design codes, durability requirements

    for concrete structures are largely based on the

    conventional method of specifying arbitrarily certain

    limiting values e.g. concrete grade, minimum cement

    content, maximum water-cement ratio, cover thickness,

    and maximum structural crack width. This so-called

    deemed-to-satisfy   approach of specifying for concrete

    “durability” frequently yields concrete performance thatis not always satisfactory. Chloride-induced corrosion of 

    reinforcement continues to represent the single largest

    cause of deterioration of concrete structures worldwide.

    Based on substantial data available from field performance,

    exposure trials and laboratory tests on concrete, many 

    researchers are convinced that the current code

    requirements do not provide adequate resistance to

    chlorides, even when properly implemented. In the light

    of current research, the deemed-to-satisfy rule for concrete

    “durability” in the present codes can be challenged.

    Strength versus Durability

    In many codes and specifications, the compressive

    strength of concrete is often used as a criterion for 

    durability. Though it may give some indication of the

    potential durability of concrete, it cannot be a generally 

     valid criterion for several reasons. For example, thecompressive strength of a concrete cube or cylinder 

    constitutes the mean value of a property of an entire cross-

    section of the specimen, whereas concrete durability is

    governed primarily by the properties of the concrete cover 

    (covercrete). Concretes of the same strength grade may 

    differ in their durability resistance against chloride

    penetration, carbonation and sulphate attack. Now, it is

    generally accepted that concrete durability is largely 

    governed by the resistance of concrete cover to the ingress

    of aggressive media. So, the emphasis should be on the

    means of achieving a good quality concrete cover or ‘skin’

    of the structure.

    Cracks versus Durability

    Cracks are inherently present in concrete due to

    overstress, environmental effects and chemical reactions.

    These cracks may range from wide and deep cracks on

    the concrete surface, down to microcracks at the

    aggregate-cement paste interface in the concrete. Although

    these cracks do not generally affect the structural capacity,

    they are rather harmful from the viewpoint of durability.

     When the cracks are limited in number and size, they 

    are discontinuous and do not pose any direct effect onthe durability of concrete. However, with time, they have

    the potential of becoming continuous (or interconnected)

    and enlarged under the influence of stress or due to

    leaching. These interconnected cracks can serve as main

    conduits for transport of harmful external ions and gases

    into the concrete. Concrete, thus, becomes vulnerable to

    the processes of deterioration, as it gradually loses its

    watertightness in the course of its service life.

    Shrinkage cracks are often limited through the use of 

    a larger quantity of steel reinforcement, as permitted in

    many codes. Mehta (1997) believed that this simply 

    transforms the wider surface cracks into many finer cracks

    and microcracks in the concrete. The microcracks and

    pores can form an interconnected pathway for ingress of 

    aggressive substances into the concrete.

    By Ir. Dr. Lim Char Ching,

    Senior Assistant Director, Forensic Engineering Unit,

    PWD Malaysia 

    Concrete Durability Provisions In Design Codes:

     Are They Really Adequate?

    Concrete Durability Provisions In Design Codes:

    B U L E T I N I N G E N I E U R 9

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    6/44B U L E T I N I N G E N I E U R 10

    Crack Width Limits

    It has been well established that corrosion of 

    reinforcements in concrete is dependent on crack width

    and cover thickness, amongst other factors. For durability,

    many codes would specify 0.3 mm as limiting crack width

    for reinforced concrete structures. For marine exposure,

    the minimum concrete cover given in the codes may range

    from 40 mm to 60 mm. Assuming other factors being the

    same, Table 1 illustrates the interplay between crack width

    and cover on concrete durability.

    Examples 1 and 2 illustrate a comparison of a single

    parameter (either crack width or cover) on concrete

    durability. In both cases, the comparison is straight

    forward. Example 3 illustrates a comparison between bothcrack width and cover on concrete durability. In this

    case, the assessment of concrete durability becomes

    complicated.

    It should be pointed out that crack width and cover 

    thickness are inter-dependent. For a given stress level in

    the steel bar and keeping other variables constant, crack 

    width increases with cover thickness. Nowadays, high

    tensile bars with yield strength of 460 MPa and above are

    commonly used as reinforcements in concrete. In this

    case, crack width larger than expected may develop when

    a large cover is adopted. Of course, 0.3 mm crack width

    can still be achieved with a large cover, provided the steel

    is designed with much lower stress than permitted. In

    this case, optimum use of high tensile bars as

    reinforcements in concrete is not achieved.

    The influence of both parameters, surface crack width

    (Wcr ) and cover thickness (C), should be considered in

    totality, i.e., one dependent on the other. This is in contrast

    with the durability requirements given in many design

    codes, in which surface crack width and cover provisions

    are recommended to be independent of the other.

    Lim et al (2000) proposed the crack width-to-cover 

    ratio (Wcr /C) as an indicator for assessing durability performance of a cracked reinforced concrete in a marine

    environment. He concluded that it is desirable to minimise

     Wcr /C of a cracked reinforced concrete in order to enhance

    Table 1 : Interplay between Crack Width and Concrete Cover on Durability

    Example 1:Structure A 0.3 60Structure B 0.2 60

    Example 2:Structure A 0.3 60Structure B 0.3 40

    Example 3:Structure A 0.3 60Structure B 0.1 40

    Crack ConcreteWidth Cover Remarks(mm) (mm)

    A and B having different crack width butsame concrete cover.B is more durable  than A.

    A and B having same crack width butdifferent concrete cover.A is more durable  than B.

    A and B having different crack width andconcrete cover.Which is more durable, A or B?

    Figure 1 : Service Life Prediction Model 

    Initiation Period

    Service Life

    Propagation Period

    Acceptable Limit

    Degree of Corrosionin Steel

    its durability performance in a marine

    environment. A value of Wcr /C not

    exceeding 0.005 is recommended.

    DESIGNING CONCRETE TO LAST

    Durability of concrete structures in

    hostile environments have been the

    concern of practising engineersworldwide. While there has been an

    immense progress in the

    understanding of the causes of, and

    solutions to problems found in

    concrete structures in recent years, the

    subject is not well recognised.

    Concrete structures can be designed

    and built to last for many generations.

    This noble aspiration can be achieved

    by engineers, utilising state-of-the-art knowledge in

    concrete technology.

    The Concept Of Service Life

    The concept of service life prediction for concrete

    structures is now becoming an area of increasing interest

    for engineers. In this respect, durability of concrete plays

    an important role. Prediction models have been developed

    to predict and quantify structural service life based on

    material resistance and environmental loads. The service

    life of a structure is defined as the period of time after 

    installation until such time when costly repair becomes

    necessary.

    For concrete structures in marine environments, theresistance of concrete to chloride-induced corrosion largely 

    controls its long-term durability performance. Concrete

    deterioration due to chloride-induced corrosion can be

    represented by a simple service life model consisting of 

    an initiation stage   and a  propagation stage , shown in

    Figure 1.

    The initiation stage is the time from initial exposure

    until depassivation of steel in concrete. This is largely 

    dependent on the rate at which chlorides penetrate into

    concrete. The propagation stage is the time from the onset

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    7/44B U L E T I N I N G E N I E U R 11

    of steel corrosion until a specified acceptable “deterioration

    limit” in concrete has been reached, e.g. first visible

    cracking on the concrete surface or first spalling.

    Many engineers have associated service life of concrete

    structures primarily with the initiation stage, to maintain

    structural safety and serviceability, acceptable appearance,

    and without having to incur unforeseen high costs for 

    repair. Currently, some concrete structures around the

    world have been designed using this concept, e.g. the GreatBelt Link Bridge in Denmark with 100 years of service

    life! It is foreseen that within the next few years,

    reliability-based service life  designs may be incorporated

    in today’s ordinary design procedures for concrete

    structures.

    Blended Cement Technology

    The term ‘blended cement’ is used to include both

    the products of blending of one or more mineral

    admixtures with an Ordinary Portland Cement (OPC). The

    process of blending can be achieved either by inter-

    grinding the mineral admixture(s) with cement clinker,

    or by blending the mineral admixture(s) with OPC.

    The wide range of binder systems, namely, Portland

    cements and blended cements available in many parts

    of the world provides opportunities for the best concrete

    to be chosen for a particular environment. Fly ash, slag

    and silica fume are the three commonly available mineral

    admixtures used in blended cements. With proper 

    dosage, these blends can be effective in enhancing the

    performance of concrete in high chloride and sulphate

    conditions. They have been found to improve the

    resistance of concrete to chloride penetration and toreduce corrosion rate of steel reinforcement.

    Improvements of the order of three to five times are not

    uncommon. Blended cements also showed great potential

    in reducing expansion and loss of strength of concrete

    exposed to sulphate condition.

    The use of blended cement concrete has been

    recognised by most national standards and codes of 

    practice on concrete structures. In general, fly ash and

    slag are used in blended cements for durability and long-

    term engineering properties. Silica fume is used when

    both early age engineering properties and durability are

    needed. The common dosages of these mineral

    admixtures vary between 20 and 40% for fly ash, between

    35 and 80% for slag and five and 10% for silica fume.

    The optimum dosages are obviously dependent upon

    specific technical requirements and cost consideration

    relevant to a particular application.

    In the past, the lack of knowledge in blended cement

    technology had resulted in structures with premature

    deteriorat ion. Today, it is possible to tailor-make

    improved quality concrete using blended cement

    technology for many applications. Blended cement

    concrete has proven worldwide to enhance workability of fresh concrete and durability properties of hardened

    concrete. However, blended cement concretes also have

    their disadvantages and limitations too. A particular 

    type of blended cement concrete may be suitable for 

    one application but not for the other. Selective usage of 

    these materials is recommended.

    Performance-based Specification

    Present specifications for concrete works are largely 

    method-based, in that they describe how works should be

    carried out on site, e.g., placing and curing of fresh

    concrete. The acceptance criteria for concrete at site aresolely based on tests carried out on “specially” prepared

    specimens of fresh concrete. The specification “assumes”

    that the workmanship in preparing the test specimens

    would be the same as that in the works. This assumption

    is seldom true. Furthermore, the test specimens are

    subjected to a controlled curing regime and environmental

    condition, compared with the concrete placed at site. It is

    obvious that the quality of hardened concrete in the

    structure is generally different from the test specimens.

    The method-based specification has been proven to be

    inadequate in addressing durability issues affecting

    concrete structures. The specification cannot guarantee

    a satisfactory “performance” of hardened concrete in the

    structure.

     A concrete structure designed for a specific service

    life should be complemented with a performance-based 

    specification. This is to ensure that the hardened concrete

    “performs” in an environment for which it is expected to

    meet the service life requirement. The specification should

    focus on tests to be carried out on in-situ hardened

    concrete. The test results should become the basis for 

    accepting or rejecting the concrete at site. Improved

    performance-based specifications are being developed inmany countries. However, suitable short-term

    “performance” tests necessary for such specifications are

    not yet available.

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    8/44

    BEM

    B U L E T I N I N G E N I E U R 12

    CONCLUSION

    Concrete structures exposed to marine environments

    have been found to suffer mainly from corrosion of the

    reinforcing steel. It is necessary for engineers to

    understand the importance and mechanisms of chloride-

    induced corrosion of steel in concrete. The effect of the

    quality of concrete on the resistance to chloride

    penetration, chloride threshold and corrosion rate of the

    reinforcing steel are critical in determining the service

    life of structures in this environment. The concept of 

    service life prediction for concrete structures is becoming

    an area of increasing interest for engineers. Therefore, a

    good understanding of the concept and its application in

    structural design is essential to ensure that optimum

    concrete performance is achieved before a costly repair to the structure becomes necessary.

     When designing concrete for durability performance,

    attention must be paid to both the performance standards

    required as well as selecting a set of compatible compliance

    criteria. This is to ensure that the hardened concrete

    “performs” in an environment for which it is expected to

    meet the service life requirement. The specifications should

    focus on tests to be carried out on in-situ hardened

    concrete. The test results should become the basis for 

    accepting or rejecting the concrete at site. Improved

    performance-based specifications are being developed.

    However, suitable short-term “performance” tests

    necessary for such specifications are not yet available.

     With the availability of mineral admixtures in many 

    parts of the world, it is now possible to tailor-make

    improved quality concrete for most applications. A good

    knowledge of blended cement technology is necessary to

    ensure its full potential in being utilised for making durable

    concrete.

    REFERENCES

    [1] Mehta, P.K. (1997), ‘Durability-Critical Issues for 

    the Future’, Concrete International , pp. 27-33.

    [2] Rostam, S. (1996), ‘High Performance Concrete

    Cover - Why It is Needed and How to Achieve It

    in Practice’, Construction and Building Materials,

     Vol. 10, No. 5, pp. 407-421.

    [3] Sarja, A. (1996), ‘Towards Practical Durability 

    Design of Concrete Structures’,  Proceedings of 

    the 7th Int. Conference on Durability of BuildingMaterials and Components, Edited by C.

    Sjostrom, Sweden, pp. 1237-1247.

    [4] Rostam, S. and Shiessl, P. (1993), ‘Next

    Generation Design Concepts for Durability and

    Performance of Concrete Structures’, Proceedings

    of the 6th International Conference on Durability 

    of Building Materials and Components, Japan.

    [5] RILEM Technical Committee 130-CSL (1996),

    ‘Durability Design of Concrete Structures’, Edited

    by Sarja, A. and Vesikari, E., E & FN SPON.

    [6] Lim, C.C., Gowripalan, N. and Sirivivatnanon,

     V., ‘Chloride Diffusivity of Concrete Cracked in

    Flexure’, Cement and Concrete Research, Vol. 30,

    No. 5, pp. 725-730, May 2000.

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    9/44B U L E T I N I N G E N I E U R 14

    By Ir. Tee Horng Hean, B.Eng. (Hons), MSc (Eng.), MBA, M.I.E.M.

    Failure Of Structures

    Many young engineers have never witnessed

    structural failure. A structural failure may 

    have adverse consequences on the parties

    involved in the construction of the structure.

    For instance, a former school bus driver brought up a

    negligence suit against a contractor who constructed a

    unipole tower, which collapsed on his bus while he was

    driving at the junction of Jalan Segambut and Jalan

    Kuching (NSTP, March 6 2001). According to the findings,

    the unipole could only withstand a wind speed of 19.2

    metres per second and in Kuala Lumpur, wind speeds of as high as 35.5 metres per second have been recorded

    (NSTP, March 6 2001). The best remedy for young

    engineers, if in doubt of their design criteria and to avoid

    any structural failure, is to ascertain the facts from reliable

    sources.

    What Is A Structure?

    Basically, a structure is a system for transferring loads

    from one place to another and nature can show examples

    of structures that support loads (Seward, 1998, p.2).

    Professor Harry H. West also noted that structure describes

    much of what is seen in nature such as a fern leaf, an oak 

    tree, shrub with ribbed branches, spider webs, etc. (West,

    1993, p.4). A tall tree in a rainforest, for instance, forms

    buttresses (see Photo 1). A structural engineer would

    definitely know that by forming these buttresses, the huge

    moments (a form of force that causes bending) induced at

    the base of the tree can be resisted, and as such, this

    cantilever-tree can grow to a considerable height to resist

    the force imposed by winds.

    Engineers do make use of this phenomenon and it is

    quite common to see them adopting stiffeners to resist

    certain amounts of moment at a stanchion base, for 

    instance (see Photo 2). If engineers adopt structuralengineering knowledge, why is it that there is still failure

    of structures? Some of the causes of structural failure are

    discussed in the following topics.

    A structural engineer’s dream is to design structures which are fit for their intended uses. No engineerwould want to see a structure collapse or fail, unless that engineer is an engineer researching incauses of failure. Some common causes of structural failure are discussed in this paper. This paper isnot intended to discredit any parties (architects, engineers, developers, advertisers, etc.) and as such,some photographs may appear doctored to protect the anonymity of the parties involved. The intentionof writing this paper is to jog the young engineer’s memory on the importance of engineeringfundamentals, and failure to observe these engineering fundamentals taught in school could be disastrous.

    Photo 2: A stanchion with a stiffener 

    Photo 1: A tall tree with buttresses 

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    10/44B U L E T I N I N G E N I E U R 15

    Underestimating Loads

    Sometimes, designers may underestimate the load that

    would be imposed upon their structure when the structure

    is in operation. A good example is the unipole structure

    that collapsed as described earlier. The unipole structure

    could only withstand wind pressures of not exceeding q

    = 0.613 x 19.22 = 226N/m2  but in the area where the

    collapse of the unipole occurred, wind pressures of as

    high as q = 0.613 x 35.52 = 773N/m2 have been recorded.

     Various structural elements are likely to be overstressed

    when designers underestimate the load that would be

    imposed on their designed structure. Consequently, their 

    structure is susceptible to collapse.

    Connections

    Surprisingly, research has shown that 30% of structural

    failures are caused by defective detailed design of the

     joints between structural members (Seward, 1998, p.232).

    For instance, a simple system of hoarding with structural

    elements being connected with undersized bolts may look 

    perfectly sturdy (see Photo 3). However, due to the use of 

    undersized bolts (see Photo

    4 and Photo 5), connecting

    the horizontal and verticalstructural members, the bolts

    were sheared off, causing the

    horizontal elements to be

    disconnected and resulting in

    the cantilever effect (see

    Figure 1). Bearing in mind

    that in a ‘cantilever’ system,

    the stress intensity 

    experienced by the structure

    can be as large as four times

    of that of the ‘continuous’

    system.

    This is precisely what

    happened to this hoarding

    and since the bolts were

    sheared off, the domino

    Photo 3: A typical ‘continuous’ hoarding system

    Photo 4: A sheared off bolt with the size of one’s thumbnail 

    Photo 5: A small bolt used to connect structural elements 

    Figure 1: Change of structural system due to sheared bolt 

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    11/44B U L E T I N I N G E N I E U R 16

    effect of excessive

    bending of the steel

    hoarding sheet (see Photo

    6 ), the structural members

    being subjected to

    excessive bending and the

    footing being pulled off 

    the ground (see Photo 7 )

    occurred.

    In short, failure of connections can lead to a

    change in the structural

    system, and in turn, have

    adverse domino effects.

    Photo 6: Failure of a simple hoarding 

    structure 

    Inconsistent Design, Detailing And Construction

     A structural engineer deals with numbers in his

    structural design, which may be Greek to a layman, a

    draughtsperson or even the contractor. In order tocommunicate his design to the contractor, structural

    drawings are produced. At times, the structural engineer 

    may not be the one producing the structural drawings

    but his draughtsperson would be the one drafting it.

    Somehow or rather, miscommunication may occur and

    designs do not tally with the drawings. There may be

    times when young engineers may draft the drawings but

    drafted them incorrectly. It is quite common to note

    that engineers analyse a reinforced concrete structure

    as a pin-joint or simply supported but in his or her detail,

    a fixed support is being provided. The consequence of 

    proceeding with construction would be similar as that

    of the hoarding where a change of structural system may 

    occur.

     A good example of a pin-joint can be seen in a see-

    saw (see Photo 8).

    Photo 8: A pin-joint 

    Photo 7: A footing being pulled off the ground 

    For instance, a lamppost when properly fixed to the

    ground (see  Photo 9), is perfectly sturdy and most

    engineers would analyse the lamp-post as a fixed

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    12/44B U L E T I N I N G E N I E U R 17

    Not Considering Elements In Contact With Structure

     When columns are supported by relatively small

    footings and the soil surrounding the footings is of 

    compressible soil, a structural engineer should analyse

    the columns as pin-jointed (Winter & Nilson, 1979, p.392).

    Similarly, if the soil surrounding the footings is stiff and

    incompressible, then the structural engineer should analyse

    the columns as fixed.

    Photo 9: A lamp-post 

    Photo 13: Close-up view of footing of Photo 12 

    Photo 10: A collapsed lamp-post 

    Photo 11: Lamp-post not properly fixed to the ground (Close-up of Photo 10) 

    Photo 12: A collapsed signboard 

    cantilever. But due to improper detailing or construction,

    this lamp-post behaved like a pin-joint (similar to the

    see-saw) and some lateral force had induced the collapse

    of the lamp-post (see Photo 10 and Photo 11).

    Structural engineers would analyse a signboard,

    assuming it to be fixed but sometimes, due to the soil

    conditions, it is not possible to have a fixed joint. For 

    instance, one would analyse this signboard as fixed (see

    Photo 12), but due to the fact that the soil is soft and

    compressible, after a heavy shower and due to strong wind

    forces the footing of this signboard can easily be pulled

    out when the post is not adequately penetrated into theground (see Photo 13). The strong wind has imposed a

    stress that is higher than that allowed by the soil, and

    consequently, the footing behaved as a pin-joint.

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    13/44

    Photo 15: Soft and compressible soil (Close-up of Photo 14) 

    Photo 14: A deflected signboard 

    Similarly, the following signboard was erected in soft

    and compressible soil and consequently, excessive

    deflection is experienced and one could easily pull down

    the whole signboard without much effort (see Photo 14

    and Photo 15).

    Following the above argument, we can deduce that if 

    a structural element were to be anchored into a brick-

    wall, it is considered fixed so long as the stresses

    transferred to the brick-wall at the joint do not exceed

    the stress of the brick. On the other hand, if the appliedforce on the structural element is excessive, causing the

    stresses transferred to the brick-wall at the joint to exceed

    the allowable stress of the brick, this element now behaves

    like a pin-joint (similar to the see-saw). This is one of 

    the aspects often overlooked and has to be taken into

    consideration in structural engineering designs. metres collapsed after a gust of strong wind (see Photo

    16 ). A rough free body diagram of this structure is shown

    in Figure 2.

     After running a simple structural analysis on the above

    structure by applying a wind force with a speed of 35.5

    metres per second, it was noted that the structure would

    not have collapsed if undersized angles were not used.From the site condition, it was observed that the angles

    gave way and experienced excessive twisting and buckling

    (see Photo 17 ).

    Photo 16: Collapse of a signboard 

    Providing Undersized Members

    Though it seldom happens, there are times when

    undersized members are used. These undersized members

    would most definitely experience excessive stress. When

    certain structural members cannot withstand the forcesthat are imposed upon them, the structure would be

    imminent of collapse. For instance, the following

    signboard measuring approximately 20 metres by 16.5 Figure 2: Free body diagram of signboard 

    Photo 17: Twisting and buckling of undersized angles 

    B U L E T I N I N G E N I E U R 18

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    14/44

    Due to the fact that the angles failed, the above

    structural system changed from a triangular frame (see

    Figure 3) to a cantilever.

    The change of the structural system has caused thecantilever to experience a high bending stress near the

    footing. This high bending stress cannot be resisted by 

    the welding provided between the I-beam and the baseplate

    (see Photo 18), and consequently, the toppling of the

    signboard occurred. Besides that, this high stress has

    caused the web of the I-beam to tear (see Photo 19).

    Lack Of Maintenance

    Many people have the misconception that structures

    do not need any maintenance. This is totally incorrect.

     Whatever the structures are made of, whether steel, timber 

    or reinforced concrete, they need constant maintenance.

    Steel structures, for instance, are susceptible to corrosion

    while timber structures can be destroyed by a colony of 

    termites. Without maintaining a structure, slowly butsurely, defects would occur. If these defects are left

    unattended, it would lead to further serious defects and

    in the end, a structural collapse may be possible due to

    the weakening of the structural members.

    Overlooking The Third Dimension

    Every single object, be it a ball, a car or a structure,

    can move in three different directions, namely left to right,

    up to down and backward to forward. All structures,

    except for space frames, can be analysed and designed by 

    simplifying them into two-dimensional structures. There

    may be the possibility that engineers can overlook one of 

    the three dimensions. When this occurs, the structure is

    only structurally sound in two dimensions but can fail in

    the third dimension.

    Constructing An Unstable (Mechanism) Structure

    There are times when a structure is erected but is

    unstable. This is especially frequent in roof trusses. Many 

    a time, the centre line of the structural members do not

    meet and thus, forming a structural system which is not atruss. For instance, the following structural framework 

    (see Photo 20) was constructed and it was noted that there

    was no triangulation of the framework, which was of 

    necessity for roof trusses. The structure looked sturdy 

    when erected. Even when the roofing sheets were installed

    (see Photo 21), the structure still looked stable.

    Unfortunately, during the monsoon season, heavy rain

    and strong wind were inevitable and they both imposed

    additional load on the structure, which consequently 

    collapsed (see Photo 22). Most textbooks on structural

    mechanics would note that most trusses would require a

    system of triangulation in order for the structure to be

    stable, and in this case (see Photo 20), the collapsed

    structure did not have any form of triangulation system.

    Not Consulting An Engineer

    Obviously, this point needs no explanation whatsoever.

    There are times when constructors would defy the

    instructions of engineers and proceed with construction,

    without realising that they could be constructing a

    collapse-prone structure.

     Worst of all, there are owners who never even engagea structural engineer but ‘copy’ the sizes of a structure

    from another construction site to erect their own. This

    can be very dangerous as the site conditions vary.

    Figure 3: Change of structural system

    Photo 19: Tearing of I-beam’s web 

    Photo 18: The weld between the I-beam and baseplate 

    gave way 

    B U L E T I N I N G E N I E U R 19

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    15/44

    Conclusion

    The paper discussed only some of the common factors

    as to why structures fail. There can be lots of other factors

    including minor mistakes such as dimensioning a

    structural member longer than it is supposed to be, usingthe wrong units (imperial/metric), not following the

    construction drawings, mixing of high tensile and mild

    steel reinforcements for reinforced concrete structures,

    reducing the lever arm of a reinforced concrete structural

    element when workers step on the steel reinforcements,

    providing inadequate anchorage length for reinforcement

    bars, etc. which can lead to structural failure. The other 

    cause of possible failure in the structure is misuse of the

    erected structure. One of the best ways for young engineers

    to avoid making the mistakes discussed in this paper is to

    ascertain the facts from reliable sources.

    The fundamentals of engineering should be applied inthe design of all engineering structures. Overlooking the

    design of even a minute part of a structure such as

    connections can be disastrous.

    Photo 21: Roofing sheets installed to timber frame 

    REFERENCES

    Harry, H. West, 1993, Fundamentals of Structural  Analysis, John Wiley & Sons, New Jersey.

    NSTP, 6 March 2001, New Straits Times Press,

    March 19 Decision by Court on Negligence Suit ,

    [Online], Available from URL: http: //www.lexis-

    nexis.com/universe [Accessed: 18 November 

    2003]

    Seward, D., 1998, Understanding Structures –

     Analysis, Materials, Design, Second Edition,

    MacMillian, Hampshire.

     Winter, G. & Nilson, A. H., Design of Concrete 

    Structures, Ninth Edition, McGraw Hill, New

     York.

    Photo 20: An unstable timber truss structure without proper triangulation system

    Photo 22: Collapse of timber structure 

    BEM

    B U L E T I N I N G E N I E U R 20

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    16/44B U L E T I N I N G E N I E U R 21

    Lessons Learned From

    Highland TowersBy Murgan D. Maniam, Pengarah Undang-Undang, Majlis Perbandaran Pulau Pinang 

    Highland Towers, as is collectively known,

    consisted of three blocks of apartments known

    as Blocks 1, 2 and 3. It was constructed

    between 1975 and 1978. Directly behind the

    three blocks was a steep slope. A stream (‘the east stream’)

    originating upslope from the Metrolux land flowed across

    part of the slope.

    On Saturday, December 11, 1993, about 15 years later,

    after 10 days of continuous rainfall, a landslide occurred

    resulting in the collapse of Block 1. Forty-eight people

    were recorded dead. Immediately after the collapse of Block 1, the residents of Blocks 2 and 3 were prevented

    from entering their apartments by MPAJ for fear of the

    instability of these two buildings. A few days later, they 

    were allowed in but only to collect their personal

     valuables. At that time, their apartments were looted

    and subsequently vandalized.

    Seventy-three owners and occupiers of the Blocks 2

    and 3 apartments brought an action against 10 defendants

    in negligence, nuisance, strict liability under the rule in

    Rylands v. Fletcher   and breach of statutory duty. The

    Plaintiffs alleged inter alia that they had been unable tore-occupy Blocks 2 and 3 emanating from the collapse of 

    Block 1, as the result of MPAJ’s pre and post-collapse

    acts and omissions.

    The 10 Defendants were as follows:

    (i) 1st Defendant - Developer  

    (ii) 2nd Defendant - Draftsman who was engaged

    by the developer as the

     Architect for the project

    (iii) 3rd Defendant - 2nd  Defendant’s brother 

    engaged by the 1st Defendant

    as the Engineer for the project

    (iv) 4th Defendant - Majlis Perbandaran

     Ampang Jaya

    (v) 5th Defendant - Arab-Malays ian Bank –

    owner of 50 lots of bungalow

    land directly at the rear of 

    Highland Towers

    (vi) 6th Defendant - Tropic - company that carried

    out clearing works on the 5th

    Defendant’s land in 1992

    (vii) 7th Defendant - owner of Metrolux land (the

    higher land adjacent to the 5th

    Defendant’s land)

    Architects and engineers owe a professional obligation to the public and their profession to

    conduct themselves and practise their profession in accord with ethical standards. Local authorities

    are also required to act reasonably and in accordance with the law.

    Clients and the public place trust and confidence in the competence and skills of the professionalarchitects and engineers. Generally, both the professionals depend on the personal confidence of 

    the client in their technical competence; and the confidence of the public at large in the integrity

    and ethical conduct of the professions as a whole.

    It is the purpose of this paper to examine the decision of the High Court and the Court of 

    Appeal in respect of the roles played by the architect, engineer, developer and the local authority

    in the development of the Highland Towers, and to learn the observations and rulings of the two

    courts to give a greater insight and understanding of their respective roles.

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    17/44B U L E T I N I N G E N I E U R 22

    (viii) 8th Defendant - Project Manager for the 7th

    Defendant and was in charge

    of the development of the

    Metrolux land.

    (ix) 9th Defendant - Selangor State Government

    (x) 10th Defendant - Director of Lands and Mines,

    Selangor 

     JUDGMENT OF THE HIGH COURT

    The High Court found the 1st, 2nd, 3rd, 4th, 5th, 7th and 8th

    Defendants liable and apportioned liability in the following

    percentages :

    (i) 1st Defendant - 15%

    (ii) 2nd Defendant - 10%

    (iii) 3rd

     Defendant - 10%

    (iv) 4th Defendant - 15%

    (v) 5th Defendant - 30%

    (vi) 7th & 8th Defendants - 20%

     After due consideration, the court ruled that the

    landslide that brought down Block 1 was a rotational

    retrogressive slide emanating from the high wall behind

    the second tier car park. The High Court also decided

    that Block 1 had collapsed due to a landslide causedprimarily by water which emanated from the damaged

    pipe culvert, and the inadequate and unattended drains

    on the 5th Defendant’s land.

    The judgment of the High Court has since been reported

    as Steven Phoa Cheng Loon & Ors v Highland Properties

    Sdn. Bhd. & Ors (2000) 4 MLJ 200.

    LIABILITY OF THE 2ND DEFENDANT – THE ARCHITECT

    The 2nd Defendant was an Architectural Draftsman.

    He drew and submitted the layout plans for and on behalf 

    of the 1st Defendant. The 2nd Defendant knew that he was

    not a fully qualified and registered architect. When the

    layout plan was approved subject to conditions, the 2nd

    Defendant prepared and submitted the building plans.

    The 2nd Defendant, whilst submitting the layout plans

    and building plans, had held himself out as a registered

    architect. The local authority, by some error on their part

    in not checking the 2nd Defendant’s credentials had in

    fact permitted him to submit such plans.

    CF was issued for the three blocks on the following dates:

    (i) Block 1 - 29.9.1978

    (ii) Block 2 - 6.11.1981

    (iii) Block 3 - 24.5.1985

    The Plaintiffs alleged that the 2nd Defendant had held

    himself out to be a suitably qualified, competent and skilled

    person to design, prepare and sign architectural and other 

    building plans. In the performance of this task, the 2nd

    Defendant has breached a common law duty of care to

    the Plaintiffs to take reasonable care and diligence in

    ensuring that:

    (i) the drainage required and rubble walls and theearthworks were adequately and properly 

    designed, supervised during its construction and

    in compliance with the requirements as set by 

    the authorities;

    (ii) by the same acts or omissions, the 2nd Defendant

    had created a nuisance on the hill slope behind

    Highland Towers.

    The 2nd Defendant argued that he did not owe such

    duty of care to the Plaintiffs. Furthermore, even if suchduty of care exists, it was not breached. He explained

    that he was only engaged to design the three apartment

    blocks and was never involved in the design, supervision

    and construction of drains, rubble walls and earthworks

    within and outside of Highland Towers site; he submitted

    that the 1st Defendant (Developer) carried out these works.

    He played no part in them. He also submitted that the

    intervening acts of the 4th, 5th, 7th and 8th Defendants in

    altering the condition of the area caused the collapse of 

    Block 1 and exempted from liability.

     A building draftsman is only permitted under the Architect’s Act 1967 to design buildings of no more than

    two storeys in height and limited floor space. In this case,

    each block of Highland Towers consisted of 12 storeys

    with a built area far exceeding that allowed for a building

    draftsman to undertake. The 2nd Defendant managed to

    induce a relevant Government department to grant him a

    ‘specially authorised person’ status under a repealed

    enactment (the Architect Ordinance 1951) which he

    claimed entitled him to summit and oversee construction

    works of three apartment blocks.

    The court held that this would make no difference to

    the duty of care the 2nd Defendant owed.  James Foong J 

    said:

    ‘When this Defendant had represented himself as a

    qualified architect to all and sundry, as displayed by 

    his actions, then he must be judged according to the 

    character he had assumed.’ 

    The extent of his duty, said the judge:

    ‘Is primarily to his client because he has a contractual 

    relationship with him. But in law, an architect is

    also liable to anyone who is sufficiently proximate 

    and whom the architect could foresee that his act 

    and/or omission would cause damage to that person.

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    18/44B U L E T I N I N G E N I E U R 23

    ….. At the time when this Defendant exercised his

    duty as an architect for the Highland Towers project,

    he must have foreseen that the apartments he built 

    would be sold, and purchasers, their servants and or 

    agents would be occupying them. ….. he must have 

    or ought to have them in contemplation when he 

    was directing his mind to his acts and/or omissions.’ 

    By this, a duty of care existed between the 2nd

    Defendant and the Plaintiffs.

    The 2nd Defendant had also argued that he had no

    responsibility for the drainage or earthworks or anything

    else beyond the design and supervision of construction

    of the apartment blocks. To this, the judge held:

    ‘I think the 2nd   Defendant is under a serious

    misapprehension that an architect is engaged just 

    to design and supervise the construction of a building

    and need not bother with the surrounding area where 

    the building is to be erected. Surely the primary 

    consideration for the construction of any building,or structure for that matter, besides the aesthetics

    aspect, is the safety of the building. To achieve this,

    the condition of the land on which the building is to

    be built as well as those in the vicinity must be 

    considered and evaluated, particularly if it has

     potential adverse effects to the building planned.’ 

    ‘…… He must ensure that no soil from the hill slope 

    would come crashing down on his designs. …..’ 

    ‘…… the 2nd 

     Defendant did foresee the danger of not exercising his professional skill, care and diligence 

    in attending to the initial and basic factors regarding

    drainage and the stability of the hill slope. As an

    architect, or someone who represented himself as

    one, he must have foreseen the dangers that if no

     proper, adequate and sufficient drainage system and 

    retention walls were built, there would be danger to

    the buildings erected below. Yet he neglected this

    basic duty. The intervening acts of the third parties

    may not be foreseen by him, but if a proper, adequate 

    and sufficient drainage system and retaining walls

    were implemented and erected, then the collapse of Block 1 may not even have occurred.’ 

    On the facts, the court found the 2nd Defendant had

    breached his duty of care to the Plaintiffs. The 2nd

    Defendant was held to have ‘failed in his duty as an

    architect and had also refused to comply with the

    requirements imposed by the authorities on the drainage

    of the area. Besides that, he had also colluded with the

    1st and 3rd Defendants (Developer and Engineer) to obtain

    CF for the three apartment blocks of the Highland Towers

    without fulfilling the conditions as set out by the 4

    th

    Defendant (MPAJ).

    The 2nd Defendant argued that the Plaintiffs’ claim

    for pure economic loss i.e. compensation to make good

    the defective building or for a replacement thereof which

    the 2nd  Defendant was engaged to build cannot be

    maintained.

    The court held that a claim for pure economic loss can

    be maintained against a Defendant, and therefore ruled

    that the Plaintiffs’ claim for negligence and nuisance is

    established against the 2nd Defendant.

    LIABILITY OF THE 3RD DEFENDANT – THE ENGINEER

    The 3rd Defendant was a qualified civil engineer. The

    2nd Defendant appointed the 3rd Defendant, who was his

    brother, to be the consulting engineer for Highland Towers.

    Initially, the 3rd Defendant’s scope of works was restricted

    to the structural aspect of the three blocks. But

    subsequently, the 3rd Defendant was engaged by the 1 st

    Defendant to submit proposals over the drainage of the

    area. His drainage plan was approved. He was also

    retained by the 1st Defendant to design and supervise the

    construction of two retaining walls on the Highland Towers

    site.

    The Plaintiffs claimed that the 3rd  Defendant wasnegligent for the following reasons:

    (i) designing unsuitable foundations;

    (ii) lack of care and concern of the hill and slope;

    (iii) issuing a notice to the authorities confirming the

    drainage works was completed when only a

    fraction of it was done.

    By the above acts of preparing, designing andsupervising the construction of Highland Towers and the

    drainage system of the Highland Towers site, he was

    negligent and had caused nuisance to them.

    The 3rd Defendant had used rail piles welded together 

    as foundation to support the three apartment blocks. This

    type of piles, which was considered inferior to concrete

    piles, was accepted in the engineering and building

    industry to support high-rise buildings at the material

    time. Thus, no fault can be attributed to the 3rd Defendant

    in using the rail piles as he was only adhering to the

    accepted professional practice at that time.

    However, there was lack of consideration by the 3rd

    Defendant to the hill and the slope directly behind the

    three blocks. The court ruled that the 3rd Defendant should

    have reasonably foreseen the danger of a landslide

    producing a lateral load against the foundation of the

    building. For this, he should have exercised care to either 

    design and construct a foundation to accommodate the

    lateral load or ensure that the slope was reasonably stable.

    Failure to do so is a breach of his duty of care he owes to

    the Plaintiffs since his duty was to ensure the safety of 

    the buildings he designed and built.

    The 3

    rd

     Defendant’s attempt to deny liability on theground that he relied on the 1st Defendant to ensure that

    other retaining walls were constructed properly was

    unsuccessful. The judge found that it was encumbent

    upon the 3rd Defendant to enquire and ascertain whether 

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    19/44

    the work was that of a qualified professional and what its

    impact might be on the safety of his own building. The

     judge agreed with a passage from the judgment of Bingham

    LJ in the case of  Eckersley v. Binnie (1988) 18 Con LR 1

    @ p.80

    ‘…… a professional man should command the corpus

    of knowledge which forms part of the professional 

    equipment of the ordinary member of his profession.He should not lag behind other ordinarily assiduous

    and intelligent members of his profession in knowledge 

    of new advances, discoveries and developments in his

     field. He should have such awareness as an ordinarily 

    competent practitioner would have of the deficiencies

    in his knowledge and the limitations of his skill. He 

    should be alert to the hazards and the risk inherent 

    in any professional task he undertakes to the extent 

    that other ordinarily competent members of the 

     profession would be alert. He must bring to any 

     professional task he undertakes no less expertise, skill,

    and care than other ordinarily competent members of his profession would bring, but need bring no more.

    The standard is that of the reasonable average. The 

    law does not require of a professional man that he be 

    a paragon combining the qualities of polymath and 

     prophet.’ 

     Although the drainage plan was approved by the

    authorities, it was not fully implemented by the 1 st

    Defendant. The reasons offered by the 3rd Defendant for 

    this failure were:

    (i) shortage of financial resources of the 1st

    Defendant;

    (ii) the need to bring down the road level to fit the

    drains; and

    (iii) prohibition on rock blasting in the area

    Nevertheless, the court ruled that whatever the excuse

    may be, it did not entitle and warrant the 3rd Defendant to

    issue a notice to the authorities stating that the entire

    approved drainage proposal was implemented when only 10% was completed. This was a gross violation of his

    duty of care which, as a consultant engineer for the three

    blocks, he owes to the Plaintiffs as purchasers of Highland

    Towers, particularly when this approved drainage system

    was so fundamental to the safety of the building. The

     judge issued a powerful condemnation by saying as

    follows:

    ‘I have reiterated my strong sentiments against this

    type of attitude of professionals whose only 

    consideration is to guard and secure their own interest rather than their duties and obligations to those closely 

    affected and the public on which so much faith and 

    reliance are placed on them to carry out their 

     professional duties. I need not elaborate further except 

    to remind this Defendant that he has to live out the 

    rest of his life knowing truly well that he had 

    contributed to the tragedy of Highland Towers.’ 

    The 3rd Defendant was found liable in negligence

    and nuisance.

    LIABILITY OF THE 1ST DEFENDANT – THE DEVELOPER

    The Plaintiffs claimed the 1st Defendant liable in negligence

    for the following reasons:

    (i) Not employing reasonably fit, competent, skilled

    and qualified persons to design, draw, sign and

    submit architectural and engineering drawings

    and plans for the construction of Highland Towers

    and the hill slope behind it;

    (ii) Not vetting through their appointments to ensure

    that they are competent and possess such skill

    for the task they are employed to undertake whichinvolves enquiries and investigations into their 

    credentials and qualifications;

    (iii) Constructing insufficient and inadequate

    retaining walls on the Arab-Malaysian land and

    the Highland Towers site without considering the

    surrounding terrain, soil condition and drainage

    requirement;

    (iv) Constructing drains that were insufficient to effect

    proper and adequate drainage of water run-offson the slope and those originating from the East

    Stream;

    (v) Diversion of the East Stream from its natural path

    to the pipe culvert which ran horizontally across

    the hill slope directly above the three blocks;

    (vi) Obtaining CF to occupy the three blocks when

    the drainage system in the Highland Towers site

    and the Arab-Malaysian land was incomplete.

    The court relied upon the dictum of Lord Finlay LC  inGreenock Corp. v. Caledonian Rly Co. (1917)AC 556 which

    is quoted by Abdul Hamid FJ in the Federal Court case of 

    Seong Fatt Sawmills Sdn. Bhd. v. Dunlop Malaysia

    Industries Sdn. Bhd. (1984) 1 MLJ 286 @ p 291.

    ‘It is the duty of anyone who interferes with the course 

    of the stream to see that the works which he substitutes

     for the channel provided by nature are adequate to

    carry off the water brought down even by extraordinary 

    rainfall, and if damage results from the deficiency of 

    the substitute which he has provided for the natural channel, he will be liable .’

    The court exonerated the 1st  Defendant from the

    allegation that they were responsible for the negligence

    B U L E T I N I N G E N I E U R 24

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    20/44

    of their consultants after appointment . The court held

    that the 1st Defendant would only be liable if the works

    involved were ‘of an extra hazardous nature’ which was

    not the case here.

    The court held that the 1st Defendant were liable in

    negligence and nuisance.

    LIABILITY OF THE 4TH DEFENDANT –

    MAJLIS PERBANDARAN AMPANG JAYA (MPAJ)

    The High Court held MPAJ liable in respect of the

    following :

    (i) At the planning and design stage of Highland

    Towers, MPAJ had not taken reasonable care, skill

    and diligence in checking the plans submitted to

    ascertain whether they are reasonably fit for the

    purpose it was intended for. This included matters

    relating to water courses, streams and rivers in

    the vicinity of the Highland Towers site, Arab

    Malaysian land and the surroundings which wereunder the jurisdiction of MPAJ.

    (ii) At the construction stage of the Highland Towers,

    MPAJ failed to exercise reasonable care, skill and

    diligence to ensure the drainage system and the

    rubble walls on Arab Malaysian land were

    adequately provided for and/or constructed in a

    workman-like manner before the issuance of the

    Certificate of Fitness to the three apartment

    blocks;

    (iii) MPAJ failed to maintain and upgrade drains and

    rubble walls on Highland Towers site and Arab

    Malaysian land, and to provide adequate drainage

    requirement to water courses, streams and rivers

    after  the Highland Towers was constructed;

    (iv) MPAJ failed to take remedial measures to remove,

    rectify and/or minimise the hazards posed on the

     Arab-Malaysian land and the surroundings after 

    the collapse of Block 1;

    (v) MPAJ failed to prevent vandalism and theft atBlocks 2 and 3 in the aftermath of the collapse

    of Block 1;

    (vi) MPAJ failed to maintain the East Stream which

    was under its jurisdiction;

     According to the court, MPAJ owes a duty of care to

    the Plaintiffs to use reasonable care, skill and diligence to

    ensure that the hill slope and the drainage thereon were

    properly accommodated before approving building or 

    other related plans, and during construction stage, tocomply with and to ensure the implementation of the

    drainage system. Then, when Certificate of Fitness was

    applied for, there should be proper and thorough inspection

    on whether the buildings so built were safe in all aspects

    and not just confined only to the structure, and after the

    Highland Towers was erected, to ascertain drainage

    requirement in the area was adequate to ensure slope

    stability behind Block 1. Subsequent to the collapse of 

    Block 1, measures should have been taken to prevent

    recurrence of the tragedy to Blocks 2 and 3.

    The court found that MPAJ owed a duty of care to the

    Plaintiffs and that this duty had been breached resulting

    in damages.Upon establishing that MPAJ was negligent, the High

    Court was influenced by Sec.95(2) of the SDB Act 1974,

    which provided an immunity to the Plaintiffs’ claims and

    the passage in Dr. Abdul Hamid Abdul Rashid & Anor v.

     Jurusan Malaysia Consultant & Ors (1997) 3 MLJ 546 :

    ‘If there is any fear that this approach may encumber 

    the local authorities to pay out substantial claims

    due to their negligence in granting approvals or 

    inspecting building works, there is s 95 of the Street,

    Drainage & Building Act 1974 (Act 133) which

     prohibits such authorities to be sued.’ 

    In discussing the above Sec. 95(2), the High Court

    pointed that Parliament can create an exemption from

    liability for certain acts committed by local authorities

    and its officers.  James Foong J said:

    ‘It is my view that s 95(2) of the 1974 Act is just 

    such a piece of legislation to exempt the local authority 

    and its officer from negligent act related to and 

    connected with certain specified activities. In our 

    case, since the acts of the 4th

     Defendant found to be negligent by this court are within those specified 

    activities under s 95(2) of the 1974 Act, immunity 

    applies to the 4th Defendant.

    Further, the High Court explained that Sec. 95(2) covers

    situations:

    (i) ‘whatsoever arising out of building or other works

    carried out’ by the 4th Defendant in accordance 

    with the provision of the said Act.

    (ii) ‘or by reason of the fact that such building worksor the plans thereof are subject  to inspection and 

    approval’.

    The acts of negligence of which MPAJ was accused of 

    inter alia, approval of plans, inspection and issue of CF

    were all covered by this immunity. Thus Sec. 95(2) applies

    to acts/omissions committed by MPAJ  pre-collapse .

    However, the immunity could not cover the post- collapse 

    actions of MPAJ and for these, they were liable.

    MPAJ had undertaken to prepare a master drainage

    plan to ensure the safety of Blocks 2 and 3. After a periodof one year, there was no sight or news of such a plan.

    MPAJ offered no explanation as to why its promise was

    not met. Thus, MPAJ was held liable for post-collapse

    management of the situation which included failure to

    B U L E T I N I N G E N I E U R 25

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    21/44

    prevent vandalism and theft in Blocks 2 and 3 as well as

    failure to produce the master drainage plan. MPAJ was

    also liable in nuisance by reason of its failure to maintain

    properly a stream which formed part of the drainage

    system of the area.

     JUDGMENT OF THE COURT OF APPEAL

    The 1st,

    2nd

    , 6th

    , 9th

     and 10th

     Defendants did not appealagainst the decision of the High Court. The 3rd, 4th, 5th, 7th

    and 8th Defendants appealed against that decision.

    MPAJ filed an appeal to the Court of Appeal against

    the whole decision of the High Court except that part

    which decided that MPAJ was not liable for all pre-

    collapse acts by virtue of Sec. 95 of the SDB.

     Although the High Court excluded liability for pre-

    collapse acts on the part of MPAJ on the basis of Sec.

    95(2) of the SDB, MPAJ had raised the grounds of appeal

    in the Court of Appeal that independently of Sec. 95(2) of 

    the SDB, MPAJ had not been negligent at all because :

    (i) at the planning and design stage, MPAJ had relied

    on the skill and diligence of the Architect (2nd

    Defendant) who submitted those plans as well as

    the various Government agencies which vetted

    those plans.

    (ii) at the construction stage of the Highland Towers,

    MPAJ had relied on the skill and diligence of the

    1st, 2nd and 3rd Defendants to supervise the said

    construction and had relied on the Certificates

    of the Architect (2nd

     Defendant) that all the workshad been completed in compliance with the

    approved plans.

    (iii) the Highland Towers and the surrounding areas,

    after completion and after Certificate of Fitness

    had been issued, had been maintained by the 1st

    Defendant.

    (iv) the drains in Highland Towers and the Arab

    Malaysian land were never in the control of 

    MPAJ.

    (v) the East-Stream was diverted from its natural

    course by the 1st Defendant as found by the High

    Court.

    (vi) the drainage of the Highland Towers and the

     Arab-Malaysian land was functioning effectively 

    until the 5th  Defendant took over the Arab-

    Malaysian land.

    (vii) at no time did the Plaintiffs complained to MPAJ

    of the dangers of the state of the drains in theHighland Towers and the Arab-Malaysian land.

    In considering the appeal of MPAJ against liability,

    the Court of Appeal ruled that there are two separate

    matters that must be addressed. These are the pre-collapse 

    and  post-collapse liability.

    The Court of Appeal observed that assuming that there

    was a duty on the 4th  Defendant (MPAJ) to act in a

    particular manner towards the property of the Plaintiffs

    post-collapse, such duty must find its expression in public 

    and not private law. Accordingly, if there had been a

    failure on the part of MPAJ to do or not to do something

    as a public authority, the proper method is to proceed by way of application for judicial review. Thus the High

    Court’s finding that MPAJ was liable for negligence after 

    the collapse was set aside.

    Next, the Court of Appeal looked at the pre-collapse

    position. The Plaintiffs submitted that Sec. 95(2) did not

    apply to the facts as MPAJ had directed the East Stream

    to be diverted from its natural course. The carrying out

    of these works created a danger to the Plaintiff’s property.

     Accordingly, this is not a case of inspection or approval

    of building or other works or the plans thereof. This is a

    case where a danger was expressly created by MPAJ. The

    Court of Appeal agreed with this submission and set asidethe indemnity granted to MPAJ by the High Court for 

    negligence before the collapse.

    The Court of Appeal ruled that there is no proposition

    of law that a local authority such as MPAJ may never 

    owe a common duty of care to the third party. It all

    depends on the particular circumstances. The kind of 

    harm that was foreseeable by the 5th Defendant was equally 

    foreseeable by the MPAJ. Upon the evidence and the

    relevant principles, it was clear that MPAJ, as a reasonable

    local authority must have foreseen the danger created by 

    diverting the East Stream would probably be a landslideof the kind that happened and that in such event resultant

    harm, including financial loss of the kind suffered by the

    Plaintiffs would occur.

    The Court of Appeal dismissed the appeals of the 3rd,

    5th, 7th and 8th Defendants and affirmed the apportionment

    of liability made by the High Court amongst the

    Defendants.

    The judgment of the Court of Appeal has since been

    reported as Arab- Malaysian Finance Bhd. v Steven Phoa

    Cheng Loon & Ors (2003) 1 MLJ 567. It appears that the

    Court of Appeal has departed from the clear finding of 

    fact by the High Court that it was the 1st Defendant whodiverted the East-Stream and substituted their own finding

    that it was MPAJ who diverted the East-Stream.

    Furthermore, although the High Court made a very clear 

    finding of fact that it was the 1st Defendant who diverted

    the East-Stream, the Court of Appeal declared that it was

    MPAJ that diverted the East-Stream. The Court of Appeal

    held that MPAJ owed a common law duty of care to the

    Plaintiffs to avoid pure economic loss. It also held that

    MPAJ is a Joint Tortfeasor along with the other Defendants.

    It was argued that at all material times, MPAJ did not

    have qualified people to deal with planning application.The role of MPAJ was that of an intermediary by 

    forwarding that application to the respective departments,

    district technical departments e.g. JKR, Health, State

    Planning Departments and other authorities relating to

    B U L E T I N I N G E N I E U R 26

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    22/44

    that particular application. There was clear evidence

    that MPAJ had relied upon the skill of the Architect (2nd

    Defendant), the Engineer (the 3rd  Defendant) and the

    Developer (1st Defendant) as well as the checking of the

    accuracy of the said plans by the relevant departments

    (the 9th and 10th Defendants). The High Court held that

    Sec. 95(2) SDB protected MPAJ for all acts of MPAJ pre-

    collapse, including the checking of the accuracy of the

    plans submitted and the failure to detect any danger inthe said plans.

    However, the Court of Appeal held that Sec. 95(2) SDB

    does not apply to the facts of the present case since MPAJ

    had directed that the East-Stream be diverted from its

    natural course and that such an act of MPAJ was caught

    by the doctrine of Kane v New Forest District Council 

    (2001) 2 All ER 914. In Kane , the local authority 

    specifically required the footpath to be created. In the

    present case, it was the 3rd Defendant on behalf of the 1st

    Defendant who submitted the plans relating to the drains

    to be implemented on the 5th Defendant’s land. In Kane ,

    all the parties including the local authorities were awarethat the construction of the footpath would be dangerous.

    Despite the said knowledge of danger, the local authority 

    went ahead with the construction of the footpath.

    However, in the present case, the drainage plan was

    conveyed by MPAJ to JPS. JPS recommended approval

    of the drainage plan. Thus the issue of danger in the

    present case did not arise at all.

    Furthermore, in Kane  there was no equivalent statutory 

    provision such as Sect. 95(2) of the SDB. In Kane , it was

    also argued that local authorities enjoyed blanket

    immunity in law in respect of anything done in the exercise

    of the planning functions. Thus it can be said, that the

    Court of Appeal had erred in relying on Kane  as a basis

    for depriving MPAJ the indemnity afforded by Sec.95(2)

    of the SDB.

    CONCLUSION

    The judgments of the High Court and the Court of 

     Appeal cannot be lightly regarded. They discuss the causes

    of the collapse of Block 1 which may arise from a variety 

    of circumstances. Every architect, engineer and developer 

    must never allow an unsafe condition to persist or develop

    at the construction site. They should also ensure at all

    times that there is no threat to public health and welfare

    and remember two assets which are vital to the practice

    of their profession – their integrity  and their ability.

    On February 6th, 2004, the Federal Court has granted

    MPAJ leave to appeal to the Federal Court on four main

    issues inter alia whether Sec. 95(2) of the SDB is wideenough to provide immunity to a local authority in

    approving the diversion of a stream and in failing to detect

    any danger or defect in the building and drainage plans

    relating to the development submitted by the architect

    and/or engineer on behalf of a developer.

    Local authorities will welcome the decision of the

    Federal Court as it would put to rest the debate as to

    whether Sec.95(2) of the SDB provides absolute immunity 

    or qualified immunity.

    SUMMARY

    The decisions of the High Court and the Court of Appeal confirmed that architects and engineers have a duty 

    to secure the safety, health and welfare of the public in the performance of their professional services.

    The architects and engineers owe a duty to exercise the skill, care and diligence  which may reasonably be

    expected of a person of ordinary competence, measured by the professional standard of the time. Thus an

    architect’s and engineer’s general inexperience and lack of knowledge do not furnish a valid excuse for unprofessional

    conduct.

    The architects and engineers are to be judged by the professional standards prevailing at the time the work 

    was done, not by what may be known or accepted at a later date, or what may be seen only with the benefit of 

    hindsight.

    The courts emphasised that every architect and engineer owe a duty to third parties to ensure that they aresufficiently qualified to undertake the assignments for which they accept professional responsibility. The architects

    and engineers must also know when to seek a competent specialist in areas outside their expertise.

    In this case, the Court of Appeal was unable to see how MPAJ could possibly escape liability for requiring the

    diversion of the East Stream. This infers that a local authority should not direct or do anything to make the site

    dangerous; otherwise it will be liable.

     Although the courts did not discuss in the ground of the Judgment the certification given by the architects and

    engineers on the plans submitted by them to exonerate MPAJ, these professionals’ duty must always be reflected

    on the plans, by requiring the architects and engineers to certify that they are responsible for supervising the

    construction of the project to ensure that it is built in accordance with the approved plans, specifications and

    drawings.

    The local authorities should be entitled to rely on the certificate executed by the architects and engineers and

    to hold them responsible for the structural design, safety and supervision of the project. This would enable the

    architects and engineers to retain control over the design and erection procedures so as to be able to advise the

    contractor of any special construction or safety consideration.   BEM

    B U L E T I N I N G E N I E U R 27

    coverfeature

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    23/44B U L E T I N I N G E N I E U R 28

    INTRODUCTION

    The guidelines herein are to assist Professional Engineers seeking registration as Accredited Checkers ingeotechnical and/or structural engineering works. They are in furtherance of Section 10B of theRegistration of Accredited Checker, Registration of Engineers (Amendment) Act 2002 [Act A1158].

    QUALIFICATIONS FOR REGISTRATION AS AN ACCREDITED CHECKER

    Any person applying for registration as an Accredited Checker shall:i) be a Professional Engineer registered under the Act in the civil, structural or geotechnical engineering

    discipline;ii) have at least 10 years’ relevant practical experience in the design or construction of buildings;iii) have adequate experience in one of the following:

    a) Geotechnical1) Foundations;2) Retaining Systems and Reinforced Soil Structures; and3) Slope Engineering and Embankments

    b) Structural1) Buildings exceeding five storeys;2) Buildings of unconventional construction with spans exceeding 10 metres; and

    3) Buildings that will result in complex interactions with existing buildings

    iv) by virtue of his/her ability and standing in the profession, or specialised knowledge or practicalexperience in civil, structural or geotechnical engineering he/she is deserving of such registration,provided thata) during the period of seven years immediately preceding the date of his/her application, he/she has

    been engaged in geotechnical or structural design after registration as a Professional Engineer; andb) for a continuous period of one year immediately preceding the date of his/her application,

    he/she has gained such practical experience in the relevant field in Malaysia; and

    v) have attended and passed the interview conducted by the Accredited Checkers Committee.

    APPLICATION FOR REGISTRATION

    Applications shall:i) be made in Form B3;ii) be accompanied by true copies of documentary evidence showing that the applicant possesses the

    necessary qualifications and the practical experience;iii) be accompanied by three copies of relevant design report done by him/her; andiv) be accompanied by a processing fee of RM50 per application in money order/bank draft/cheque

    made payable to the Board of Engineers Malaysia

    REGISTRATION

    a) Registration Fee

    A registration fee of RM300 will be charged for those who have attended and passed the interview.

    Route To Be  An Accredited Checker By Accredited Checker Committee, Board of Engineers Malaysia 

     g   u  i d  e  l i n e  s

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    24/44B U L E T I N I N G E N I E U R 29

    b) Renewal Fee

    Every Accredited Checker desirous of renewing his/her registration under the Act shall:i) submit to the Board an application for renewal in Form H on or before January 31st of the year

    following the year of the expiration of his/her registration;ii) submit the payment in money order, bank draft or cheque made payable to theBoard of Engineers

    Malaysia; and

    iii) have paid up his/her annual renewal fee as Professional Engineer.

    The annual renewal fee is:

    Category A: Those below 60 years old RM200Category B: Those 60 years and above RM100

    REMOVAL FROM THE REGISTER

    Section 16 of the Registration of Engineers (Amendment) Act 2002 [Act A1158] provides for the removalfrom the Register, the name and other particulars of:

    a) any registered Engineer who has died;b) any registered Engineer , other than a Graduate Engineer, or Engineering consultancy practice who

    has failed to renew his or its registration within one month of the expiry of the registration;c) any registered Engineer whose registration has been cancelled under paragraph 15(1A)(d); ord) any registered Engineer whose registration has been effected by reason of any mistake or error made

    by the Board in considering his application for registration.

    APPEALS

    All appeals shall be submitted to the Appeal Board, Board of Engineers Malaysia (constituted underSection 20, Registration of Engineers (Amendment) Act 2002 [Act A1158]).

    BEM

    FLOWCHART OF THE ROUTE TO BE

    AN ACCREDITED CHECKER

    Be a registered Professional Engineer under the Registration of Engineers Act 1967 inthe civil, structural or geotechnical engineering discipline.

    HAS

    Minimum 10 years’ relevant practical experience in the design or construction of buildings.

    Minimum seven years’ experience in geotechnical or structural design afterregistration as Professional Engineer

    Minimum one year experience in the relevant field gained in Malaysia.

    Attended the Interview conducted by Accredited Checkers Committee

      AND PASSED

    Accredited Checker

       g     u 

        i    d    e 

        l    i   n   e    s

  • 8/17/2019 BEM Mar04-May04 (Forensic Engineering)

    25/44

    Update

    B U L E T I N I N G E N I E U R 30

    In May 2002, ESCAP adopted the resolution

    “Promoting an inclusive, barrier-free and rights-

    based society for people with disabilities in the Asianand Pacific regions in the 21 st  century”. The

    resolution also proclaimed the extension of the Asian and

    Pacific Decade of Disabled Persons 1993-2002, for another 

    decade, 2003-2012.

    In October 2002, Governments at the High-level

    Intergovernmental Meeting to Conclude the Asian and

    Pacific Decade of Disabled Persons 1993-2002, adopted

    the “Biwako Millennium Framework for Action towards

    an Inclusive, Barrier-free and Rights-based Society for