best practice guidance/media/files/british-gypsum/broch… · best practice guidance openings...

19
Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire LE12 6HX Email: [email protected] british-gypsum.com Approved February 2021 BPG-OFS-3.4

Upload: others

Post on 19-Oct-2020

29 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire

Best practice guidanceOpenings within fire rated systems

Technical Support TeamEast Leake Loughborough Leicestershire LE12 6HXEmail: [email protected] british-gypsum.com

Approved February 2021 BPG-OFS-3.4

Page 2: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire

Approved February 2021 BPG-OFS-3.4

Best practice guidanceOpenings within fire rated systems

This guidance has been prepared with the context of allowing any fire stopping solution that has been successfully tested in an appropriate standard flexible supporting construction to be utilised within our GypWall partitions, GypLyner IWL and ShaftWall systems. The design principles contained within the appropriate BS EN test standard have been adopted throughout this document as it is the most up to date guidance available. This is irrespective of whether the project specification is designed to BS 476-22:1987 or the more up to date BS EN 1364-1:2015.

In all cases, if additional test information is available from the fire stopping manufacturer which extends the field of application, this may allow the guidance to be varied. This will need to be considered on a case by case basis by the relevant approving authority who then takes the design responsibility for the overall system.

1. Service penetration seals1.1 Reference is made to BS EN 1366-3:2009, in conjunction with fire test evidence undertaken by British Gypsum on GypWall partitions, GypLyner IWL and ShaftWall to formulate the following guidance. Openings for service penetration seals should be formed in accordance with current British Gypsum fire stopping approved details AD-605-001 and AD-605-003. Openings must be framed out with the transom sections fixed to full height Gypframe studs. It is best practice to line the reveals to match the specification of the wall, however guidance should be sought from the fire stopping manufacturer to determine if this is required. If the aperture is not lined to match the specification of the partition or lining, the fire stopping material must in all cases fully cover any exposed metal framework in order to maintain the fire and acoustic performance of the system.

1.2 The transom members forming the opening must be supported on both sides by full height Gypframe studs. This maximises the structural stability in terms of lateral loads and the limiting deflection criteria based on industry standard L/240@200Pa and the stiffness requirements in accordance with BS 5234-2:1992.

1.3 The width of an opening is limited to the distance achieved by the partial removal of a single Gypframe stud. The opening span is measured from inside faces of the opening, refer to table opposite. This limitation is based on fire test evidence available to British Gypsum. It may be possible to construct wider openings by following the principles of existing British Gypsum typical non-fire rated opening details TY-782-ZZZZ-03 and TY-782-ZZZZ-05, if the fire stopping manufacturer has suitable test evidence for wider openings within a flexible supporting construction. This is subject to approval by the relevant approving authority.

MAXIMUM CLEAR OPENING SIZES*

GYPFRAME STUD TYPE

GYPROC PLASTERBOARD

LINING (MM)

CLEAR OPENING WIDTHS

STUD CENTRES (MM)

600 400 300

Gypframe ‘C’

Unlined 1161 761 561

1 x 12.5 1136 736 536

2 x 12.5 1111 711 511

1 x 15 1131 731 531

2 x 15 1101 701 501

3 x 15 1071 671 471

Gypframe ‘I’

Unlined 1162 762 562

1 x 12.5 1137 737 537

2 x 12.5 11112 712 512

1 x 15 1132 732 532

2 x 15 1102 702 502

3 x 15 1072 672 472

Gypframe ‘AcouStud’

Unlined 1156 756 556

1 x 12.5 1131 731 531

2 x 12.5 1106 706 506

1 x 15 1126 726 526

2 x 15 1096 696 496

3 x 15 1066 666 466

* With a single stud interrupted by the opening based on different board thicknesses

Page 3: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire

Best practice guidanceOpenings within fire rated systems

1.4 When selecting an appropriate fire stopping solution, it is important that the fire stopping manufacturer is aware of the partition system type, this will enable them to confirm the solution is within the field of application for that product. This is important as fire stopping tests conducted within a standard flexible supporting construction may not directly cover the end use conditions and need to be considered by the fire stopping provider, e.g. ShaftWall systems are required to be tested in both directions.

2. Multiple service penetration seals2.1 When referencing the British Gypsum approved fire stopping details AD-605-001 and AD-605-003, the design principle we have applied allows each opening within a partition featuring a number of openings can be constructed so there is no potential adverse effect on adjacent openings. This allows any fire stopping solution tested in an appropriate flexible supporting construction to be included within the same partition. The design should also maintain the limiting deflection criteria to within industry standard L/240@200Pa and stiffness requirements of BS 5234-2:1992.

2.2 Where multiple penetrations occur in a partition, consideration should be given to the structural integrity of the system. Openings wider than 600mm (i.e. preventing full height Gypframe studs) should be no closer than 300mm between openings. The margin between each opening should utilise 3 x Gypframe ‘I’ studs where the margin is less than 600mm, refer to AD-605-005.

2.3 The minimum distance between openings when one above another is 200mm, in accordance with BS EN 1366-3:2009.

3. Fire rated door sets, riser doors and access panels3.1 The design principle we have applied is each opening within a partition featuring a fire rated doorset, riser door or access panel is constructed such, that there is no potential adverse effect on any adjacent openings when in the fire condition. The dimensions included within BS EN 1366-3:2009 and BS EN 1634-1:2014 have been adopted. This allows any fire rated doorset that has been tested in an appropriate flexible supporting construction to be included within this guidance.

3.2 Service openings above a door must not clash with the Gypframe jamb stud, refer to AD-605-012. If jamb studs are not continuous a suitably qualified person, e.g. structural engineer, should be consulted for advice on an alternative substructure to support the door set. This is necessary to ensure both the partition and doorset are structurally sound in the cold state and may require the inclusion of structural posts by others.

3.3 The minimum distance between the top of a door frame and the bottom of a service opening is 200mm in accordance with BS EN 1366-3:2009. It may be possible to reduce this dimension if the doorset and /or fire stopping manufacturer has fire test evidence carried out within a flexible supporting construction.

3.4 The minimum distance between adjacent fire rated doorsets, riser doors or access panels is 300mm in accordance with BS EN 1634-1:2014. It may be possible to reduce this dimension if the doorset manufacturer has fire test evidence carried out within a flexible supporting construction, refer to AD-605-013.

3.5 The installation method and construction detail of the fire rated doorset, riser door or access panel should exactly match the installation method of the fire tested solution, or be within the direct field rules set out in BS EN 1634-1:2014.

3.6 For riser doors and access panels where a four sided opening is required, refer to AD-605-014.

4. Ducts incorporating mechanical fire dampers4.1 Refer to the relevant sections of BS EN 1366-2:2015 Fire Resistance Tests for Service Installations: Fire Dampers. British Gypsum have conducted a limited number of fire tests with damper installations to demonstrate the suitability of the dry lining systems as suitable flexible supporting constructions. Each damper must have been fire tested by the manufacturer and it is the responsibility of the relevant approving authority to ensure compatibility when installed within a British Gypsum system.

4.2 British Gypsum have generic details to show the principle construction of the partition incorporating a damper installed up to maximum weight 57kg and opening width 1400mm AD-605-002 and AD-605-010, but each damper must be installed in accordance with the damper manufacturers installation guidance and substantiation. To maintain the integrity of the partition, openings must be formed using British Gypsum opening details suitable for the required width.

Approved February 2021 BPG-OFS-3.4

Page 4: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire

Best practice guidanceOpenings within fire rated systems

Glossary of terms

Ducts Incorporating Fire DampersDesigned to close at given temperature causing the duct to fall away whilst damper remains in position thus preventing passage of smoke and flame.

Field of ApplicationThe process of direct or extended application uses rules which are essentially based on a worst case scenario and interpolation techniques.

Fire Rated DoorsetA complete component designed and tested as a whole system.

Fire-stoppingA system used to maintain the fire resistance of a fire-separating element where services pass through.

Flexible Supporting ConstructionHorizontal or vertical supporting construction consisting of studs, including linings and optional insulation.

PenetrationAn aperture in a fire-separating element with one or more services passing through.

Penetration SealA system used to maintain the fire resistance of a fire-separating element where services pass through.

Relevant Approving AuthorityThe body responsible for enforcing Building Regulations on a project.

Riser Doors & Access PanelsFire rated removable panels installed within a four sided aperture.

Structural PostSteel member designed and supplied by others to add to the structural performance of a partition.

System OwnerPerson or organisation who owns the performance evidence of a system.

Approved February 2021 BPG-OFS-3.4

Standards Referenced throughout this guidance;BS 476-20:1987 Fire tests on building materials and structures

BS EN 1364-1:2015 Fire resistance tests for non-loadbearing elements, walls

BS EN 1366-2:2015 Fire resistance tests for service installations, fire dampers

BS EN 1366-3:2009 Fire resistance tests for service installations, penetration seals

BS EN 1634-1:2014 Fire resistance tests for door and shutter assemblies

BS 5234-2:1992 Partitions, specification for performance requirements for strength and robustness

Page 5: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 6: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 7: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 8: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 9: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 10: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 11: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 12: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 13: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 14: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 15: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 16: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 17: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 18: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire
Page 19: Best practice guidance/media/Files/British-Gypsum/Broch… · Best practice guidance Openings within fire rated systems Technical Support Team East Leake Loughborough Leicestershire