better performance in project management! the almost complete guide
DESCRIPTION
An example of some (in this version not entirely complete) training handouts about Project Management. Some additions based on contributions from 'slideshare' users have been included! Ein Beispiel (Auszug) für Teilnehmerunterlagen zu einem Projekt Management Kurs. Diese Version enthält einige neue Folien! Vielen Dank dafür bei den jeweiliegen 'contributors'!TRANSCRIPT
B tt P fBetter Performance in Project Management (PM)in Project Management (PM)the almost complete guide…p g
Axel Böhm
Performance Improvement, definitionPerformance Improvement, definition2
The American Society of Training & Development (ASTD) defines
Performance Improvement as "the process of identifyingPerformance Improvement as the process of identifying
and analyzing important organizational and individual
performance gaps, planning for future performance
improvement, designing and developing cost-effective and p , g g p g
ethically justifiable interventions to close performance
i l ti th i t ti d l ti thgaps, implementing the interventions and evaluating the
financial and non-financial results."
PROJECT MANAGEMENTPROJECT MANAGEMENTMODULE TOPICS
Module 1: What is a project & what is managementModule 2: PMI’s nine project management knowledge areasModule 3: The triple constraintModule 4: The project life cycleModule 5: Project selectionjModule 6: Project environment , factors, stakeholders and actorsModule 7: Defining scopeModule 8: SMART ObjectivesModule 8: SMART ObjectivesModule 9: Risk management and project assumptionsModule 10: Project charterModule 11: Responsibilities and work breakdown structuresModule 11: Responsibilities and work breakdown structuresModule 12: Project scheduling
PROJECT MANAGEMENTPROJECT MANAGEMENTMODULE TOPICS
Module 13: Controlling and monitoringModule 14: Project management softwareModule 14: Project management softwareModule 15: Project closeModule 16: PMI’s project management maturity modelM d l 17 Th j t t d j t t tModule 17: The project team and project structureModule 18: Project communicationsModule 19: Additional interesting informationModule 20: What’s nextModule 21: Bibliography and links to the www
Please note:Please note:5
Besides its function as a PowerPoint presentation, this handout is meant
to give participants additional information related to Project
Management.
The sequence of pages (if presented) might change due to the actual flow
of the training.
A copyright note: ‘The content is based on the American Society for
Training and Development (ASTD) and the Project Management Institute
(PMI) training workshop series and is supplemented with material from
Pro Consulting and Training (Pro Consulting and Training).
The copyright for the pictures used is with the respective owner.
MODULE 1 WHAT IS A PROJECT & WHATMODULE 1: WHAT IS A PROJECT & WHAT IS MANAGEMENT?
What is a Project?What is a Project?7
“A temporary endeavor undertaken to create a unique product or service.”*
Term Means that a Projecttemporary Has a beginning and endendeavor Involves effort workendeavor Involves effort, workto create Has an intention to produce something
(project "deliverables"unique One of a kind, rather than a collection of
identical itemsidentical itemsproduct Tangible objects, but could include things like
computer software, film or stage worksservice Might include the establishment of a day-care
center for instance but not its daily
*2000 PMBOK Guide (p. 4).
center, for instance, but not its daily operations.
What is a Project? Some more ‘definitions’What is a Project? Some more definitions8
A project is a package of activities in a specific sector, carried out in a set region, within a limited period of time, by project executing agencies (which may be supervised by politically answerable institutions and supported by funding and consultative agencies), with the aim of obtaining certain results, g g ), g ,which will lead to an agreed project purpose.
A project may form part of an overall program.
Several projects may be packaged where they cover similar sectoral, organisational or geographical area.
Programmes may include projects which work in the same sector, sub-sectorProgrammes may include projects which work in the same sector, sub sector or region, and which can be put together to make a clearly defined concept. Such projects may be promoted through the same executing agency.
Certain deliveries of materials and equipment or other inputs in support ofCertain deliveries of materials and equipment, or other inputs in support of sectoral or sub-sectoral objectives, may also be financed as programs.
There is no sharp distinction between projects, packages of projects and programsprograms.
What is Management?What is Management?
Th ti l
9
Theoretical scope
Mary Parker Follett (1868–1933), who wrote on the topic in the early
twentieth century and defined management as "the art of getting things
done through people".
One can also think of management functionally, as the action of measuring a
quantity on a regular basis and of adjusting some initial plan; or as the
actions taken to reach one's intended goal. This applies even in situations
where planning does not take place.
What is Management?What is Management?10
From this perspective, Henri Fayol considered management to
consist of five functions:
Planning
OrganizingControlling
LeadingCoordinating gg
Project Management…Project Management…11
Your Turn:Your Turn: 12
What is ‘performance’?What is a Project & what is Management?j g
…………
MODULE 2: PMI’S NINE PROJECT MANAGEMENT KNOWLEDGE AREAS
AND WHAT IS PROJECT- AND WHAT IS PROJECT MANAGEMENT?
PMI’s Ni P j t M t K l d ANine Project Management Knowledge Areas
14
1. Integration Management2. Scope Managementp g3. Time Management4. Cost Management5. Quality Management6. Human Resource Management7 Communications Management7. Communications Management8. Risk Management9 Procurement Management9. Procurement Management
#1- Project Integration Management#1 Project Integration Management15
The ’elements’:
Building the Project PlanProject ExecutionIntegrated Change Control
Bringing it all together: Project Management “Nerve Center”!Project Management Nerve Center !
#2 - Project Scope Management#2 Project Scope Management16
Staying vigilant in defining and containing scope throughout the project!
Project InitiationS l iScope PlanningScope DefinitionScope VerificationScope Change Control
#3 - Project Time Management#3 Project Time Management17
Determining What Gets Done and When through:
Activity Definition
Activity SequencingActivity Sequencing
Activity Duration Estimating
Schedule Development
Schedule Control
#4 - Project Cost Management#4 Project Cost Management18
Planning for Resources
Estimating CostsEstimating Costs
Creating the Budget
Managing/Controlling
the Budget
#5 - Project Quality Management#5 Project Quality Management19
Quality Planning
Quality AssuranceQuality Assurance
Quality Control
#6 - Project Human Resource Management#6 Project Human Resource Management20
Organizational PlanningStaff AcquisitionqTeam Development
#7- Project Communications Management#7 Project Communications Management21
Keeping Stakeholders informed (and involved!)( )
Communications PlanningCommunications PlanningDissemination of InformationProgress ReportingProgress ReportingAdministrative Closure
#8 - Project Risk Management#8 Project Risk Management22
Expect the Unexpected!
Risk Management PlanningRisk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk AnalysisQuantitative Risk Analysis
Risk Response Planning
Risk Management and Control
#9 - Project Procurement Management#9 Project Procurement Management23
For Projects Using Outside Resources:
Procurement PlanningSolicitation PlanningSolicitationSource SelectionContract AdministrationContract Closeout
Your Turn: What We Know AlreadyYour Turn: What We Know Already24
Look back over your previous experience in project management!
How many of the nine knowledge areas did you use? (Probably all nine!)( y )
Take a quick inventory and point to your most successful application and the most difficult one tosuccessful application and the most difficult one to manage!
Pick up at least one new tip from others right now!
So what is Project Management?So what is Project Management?
The use of resources to accomplish project objectives which25
• Applying knowledge, competencies and skills
The use of resources to accomplish project objectives, which includes:
pp y g g , p
• Defining, planning, scheduling and controlling
• Leadership, communicating and coordinatingLeadership, communicating and coordinating
• Starting up and dissolving project teams
• Balancing requirements, schedule and resources• Balancing requirements, schedule and resources
• Being sensitive to people
• Managing both deliverables and processes• Managing both deliverables and processes
So what is Project Management?So what is Project Management?
A Systematic Process for Managing Project Implementation26
1. Understand the project2. Structure the organization
A Systematic Process for Managing Project Implementation
3. Build the team4. Analyze the context5. Refine objectives, scope, and other project parameters6. Prepare the work breakdown structure (WBS), Responsibility Matrix, and
Master Summary Schedule7. Plan and schedule with critical path method (CPM) 8 Obtain management approval8. Obtain management approval 9. Design control and reporting systems
(Time, Cost, Resources, Scope, Performance and Quality)10. Organize procurementg p11. Execute and control the work12. Terminate the project
Your Turn:Your Turn:27
What are the 9 PM Knowledge Areas…………………………
MODULE 3: THE TRIPLEMODULE 3: THE TRIPLE CONSTRAINT
The Triple ConstraintThe Triple Constraint
The three constraints that all projects are facing and29
CostTime
The three constraints that all projects are facing and that are constantly overlooked /underestimated
CostTime
OR, IN PLAINFast Cheap
Quality/Scope
PLAINENGLISH
ast Cheap
Good
Triple Constraint Trade-OffsTriple Constraint Trade Offs30
Cost
Quality/Scope
Constraint Req ired Adj stment Alternati es (One orConstraint Change
Shorter Time Higher Cost Reduced Quality or Narrowed Scope
Required Adjustment Alternatives (One or Combination of Both)
Reduced Cost More Time Reduced Quality or Narrowed Scope
Higher Quality or Increased Scope
More Time Higher Costp
Triple Constraint: Setting PrioritiesTriple Constraint: Setting Priorities
Priority Matrix
31
Constraint 1 2 3 MeasurementTimeCostQ lit /S
Priority Matrix
Quality/Scope•Must be set by customer and sponsor near startup.•May change over time, but a change is a significant event!
E l f C l t d P i i t M t i f C t ti P j tConstra int 1 2 3 Measurement
Time XBuilding must be completed by October 31 of this year to
Example of a Comple te d Pr ior i ty Matr ix for a Construction Proje ct
Xaccommodate corporate move.
Cost X Costs for the project must not exceed $22.5 million.
Quality/Scope X Must provide workspace for 120 call
If these are the established priorities and measurements, what are some of the implications for the project if the project starts running late or shows signs of
Quality/Scope X p pcenter staff.
exceeding budget?
Your Turn:Your Turn:32
What are the triple constraints?………
MODULE 4: THE PROJECT LIFEMODULE 4: THE PROJECT LIFE CYCLE
The Project Life CycleThe Project Life Cycle34
General Form of a Project Life Cycle
Ph 1 Ph 2 Ph 3 Ph Ph " "
Project
Phase 1 Phase 2 Phase 3 Phase... Phase "n"
Project Life Cycles Are Like Snowflakes!Project Life Cycles Are Like Snowflakes!
Si l Th Ph P j t Lif C l
35
Simple Three-Phase Project Life Cycle
Project
Initiation Execution Close-Out
Project
Initiation Execution Close Out
Nine-Phase Project Life Cycle
Formulate Concept Evaluate Concept Verify Scope Design Construct Deploy Maintain Close
Project
Formulate Concept Evaluate Concept Verify Scope Design Construct Deploy Maintain Close
Project Life Cycles Are Like Snowflakes!Project Life Cycles Are Like Snowflakes!36
Program/ProjectIdentification
Completion &Evaluation Phase PCM Model
Project Life Cycles Are Like Snowflakes
C i I
37
Continuous Improvement
Lessons
Project
Lessons Learned
I iti ti D fi iti Pl i I l t ti Cl
Project
Initiation Definition Planning Implementation Closure
Project Life Cycles Are Like SnowflakesProject Life Cycles Are Like Snowflakes
IDENTIFICATION38
IDENTIFICATION
PREPARATIONPREPARATION
APPRAISALAPPRAISAL
NEGOTIATIONNEGOTIATION
IMPLEMENTATION
ILO/UN Model
EVALUATION
Project Life Cycles Are Like SnowflakesProject Life Cycles Are Like Snowflakes39
ILO/UN Model
Implementation
Project Life Cycles Are Like SnowflakesProject Life Cycles Are Like Snowflakes40
PreparationIdentification Approval Financing Implementation Operations
Ex PostEvaluation
Phase orStage
Product orProcess orDeliverable
Pre-feasi-bilityStudy
ProjectProfile
Preparedand
Budgetfor
F iFeasibility Project Donor Final Cons-
Feasi-bilityStudy
yStudy/PreliminaryDesign
jProposalforProjectFinancing
Agreementincluded inCapital Budget
Design truction
Decisionmaker
1 2 3 4 5 6 7
SectorMinistry
SectorMinistry,PlanningUnit and
SectorMinistry
Central PlanningUnit andMinistry
FinancingInstitution
SectorMinistry
SectorMinistry
Ministryof Finance
yof Finance
Typical Project Life Cycle for a Technical Cooperation Country Program/ProjectTechnical Cooperation Country Program/Project
Benefits of a Project Life CycleBenefits of a Project Life Cycle41
• Establishes a common framework for developing the project!
• Defines the system for managing projects, including phases and decisionDefines the system for managing projects, including phases and decision
points!
P id l f th d l t !• Provides a common language for the development process!
• Institutionalizes a management system!
• Improves communication, coordination and control!
These points do hold true for any type of project!
ILO/UN
The Project Life Cycle we will use…The Project Life Cycle we will use…
Project Life Cycle Used in this Workshop42
Project Life Cycle Used in this Workshop
Project
Initiation Definition Planning Implementation Closure
Phase PurposeInitiation Introduce project to attain approval and create project
charterD fi iti D t j t d li bl d th d fDefinition Document project scope, deliverables, and methods for
containing scope.Planning Create plan documenting the activities required to
complete the project, along with sequence of activities, resources assigned to the activities, and resulting schedule and budgets.
Implementation Execute and manage the plan, using artifacts created in the planning phase.
Closure Formally review the project, including lessons learned and turnover of project documentationturnover of project documentation.
Your Turn:Your Turn:43
Which ‘steps/sequences’ you will find in a Project Life Cycle (make sure you get them in the right order) ?
…………
MODULE 5: PROJECT SELECTION
How Projects Come to BeHow Projects Come to Be…45
Project selection can be a difficult process, especially when there
are a large number of potential projects competing for scarce
money.
Some selection methods are highly intuitive; others try to addSome selection methods are highly intuitive; others try to add
rigor through more scientific selection processes.
Sacred Cows and Pressing Needsg
S l i ‘ i i ’ b
46
Some selection ‘criteria’ can be:
“Sacred Cow” selection—Senior Management wants it!
(it may often turn out well; many visionary projects
start here)!
Business opportunity (make more money)!
Savings potential (save more money)!
Keeping up with competition (example, many e-commerce projects were
in response to competitor’s initiatives)!p p )
Government or regulatory requirements!
Disaster recovery initiatives! URGENCY!!!Disaster recovery initiatives! URGENCY!!!
An Important Selection CriterionAn Important Selection Criterion
S it Ch k
47
Sanity Check:
Does the project fit in with the stated goals of the organization?
Which of the following meet this criterion? Why or why not?
A i l j i b lli l fAn environmental group proposes a project to raise money by selling aerosol cans of a powerful new pesticide.
A video store chain proposes to develop a web site for ordering and distributing deo sto e c a p oposes to de e op a eb s te o o de g a d d st but gvideos.
A bank offers a free rifle to anyone opening a new savings account.
A restaurant equipment manufacturer decides to introduce a line of high-end refrigerators for the consumer market.
Selection ToolsSelection Tools48
Numeric Method DescriptionPayback Period Determines how quickly a project
recoups its costsrecoups its costsNet Present Value Estimates the current worth of
anticipated cash flows resulting from the project
Unweighted Selection Scores multiple projects against a set of selection criteria, with all criteria being equal
Weighted Selection Scores multiple projects against a setWeighted Selection Scores multiple projects against a set of selection criteria, with each criterion assigned a numeric weight
Pairwise Priorities Rank ordering a number of candidatePairwise Priorities Rank ordering a number of candidate projects by systematically comparing one with each of the others
Weighted CriteriaWeighted Criteria
Item t
49
Item
Criteria
0 0 0
Wei
ght
0 0
0 0 00 0
0 0 00 0
0 0 0 0 0
0 0 00 0
0 0 0 0 0
Total: 0Total: 0 Total: 0 Total: 0 Total: 0
Weighted Criteria (example, using scale of 1-5)
Item t
50
Item
Criteria4 5 3
Wei
ght
Project A Project B Project C
2 3 5
Good ROI 3 12 15 9 0 0
CEO Lik It 5 10 15 25 0 0
5 4 2
CEO Likes It 5 10 15 25 0 0
Provide Better 4 20 16 8 0 0
4 4 5
Better Service
4 20 16 8 0 0
Match New Initiatives of 3 12 12 15 0 0Competition
12 12 15 0 0
0 0 0 0 0
Our Winner!!(hmmmm…)
Total: 0Total: 54 Total: 58 Total: 57 Total: 0
( )
Unweighted Criteria (example, using scale of 1-5)
51
Item
CriteriaProject A Project B Project C
Good ROI 4 5 3 0 0
2 3 5 0 0CEO Likes It 2 3 5 0 0
Provide Better 5 4 2 0 0Provide Better Service
5 4 2 0 0
Match New Initiatives of 4 4 5 0 0
Our Winner!!(Still! So the Initiatives of
Competition
0 0 0 0 0
boss was right..)
Total: 0Total: 15 Total: 16 Total: 15 Total: 0
Forced Pair Comparisons for PrioritiesForced Pair Comparisons for Priorities
All i di id l t k d li t f did t j t (
52
Allows individuals or groups to rank order lists of candidate projects (or anything, for that matter!)SimpleWorks well for fewer than 20 items
1 -- 2
1 -- 3 2 -- 3
1 -- 4 2 -- 4 3 -- 4
1 -- 5 2 -- 5 3 -- 5 4 -- 5
1 -- 6 2 -- 6 3 -- 6 4 -- 6 5 -- 6
1 -- 7 2 -- 7 3 -- 7 4 -- 7 5 -- 7 6 -- 7
1 -- 8 2 -- 8 3 -- 8 4 -- 8 5 -- 8 6 -- 8 7 -- 8
1 -- 9 2 -- 9 3 -- 9 4 -- 9 5 -- 9 6 -- 9 7 -- 9 8 -- 9
1 -- 10 2 -- 10 3 -- 10 4 -- 10 5 -- 10 6 -- 10 7 -- 10 8 -- 10 9 -- 10
Item Scores1 2 3 4 5 6 7 8 9 10
How to use the Forced Pair ComparisonsHow to use the Forced Pair Comparisons
Generate list of items
53
Generate list of items.
For project selection, this will be the list of candidate projects.
Number the items for identification purposes.
Use the grid to compare each item with the other items on the list, circling the item g p , gthat is the more preferred of the two. (You must make a choice for each pair!)
Count the number of times each item was circled and enter its score on the bottom line of the gridline of the grid.
Rank order the list using the scores you have derived. The item with the highest score is #1. The item with the second-highest score is #2. (In case of a tie, you may g ( , y yeither do a mini-grid for the tied items, or refer to your original preference when you were circling the items in the grid above.)
Use less than a full grid for fewer than 10 items; expand grid for more itemsUse less than a full grid for fewer than 10 items; expand grid for more items.
How to Use Forced Pair ComparisonsExample:
54
1. Middlemarch
Seven Books I Have Always Wanted to Read and Haven’t
2. Ulysses3. Remembrance of Things Past
W d P4. War and Peace5. Moby Dick
Anna Karenina6. Anna Karenina7. Pride and Prejudice
How to Use Forced Pair ComparisonsE l ( ti d)
1 2
Example (continued):55
1 -- 2
1 -- 3 2 -- 3
1 -- 4 2 -- 4 3 -- 41 -- 4 2 -- 4 3 -- 4
1 -- 5 2 -- 5 3 -- 5 4 -- 5
1 -- 6 2 -- 6 3 -- 6 4 -- 6 5 -- 6
1 -- 7 2 -- 7 3 -- 7 4 -- 7 5 -- 7 6 -- 7
1 -- 8 2 -- 8 3 -- 8 4 -- 8 5 -- 8 6 -- 8 7 -- 8
1 -- 9 2 -- 9 3 -- 9 4 -- 9 5 -- 9 6 -- 9 7 -- 9 8 -- 9
1 -- 10 2 -- 10 3 -- 10 4 -- 10 5 -- 10 6 -- 10 7 -- 10 8 -- 10 9 -- 10
1 2 3 4 5 6 7 8 9 10
2 5 1 4 2 1 6
Item Scores
* ** Break ties. In this case, #1 and #6 as well as #3 and #6 were tied.
Ties were broken merely by referring to previous choice made in the grid.
How to Use Forced-Pair ComparisonsExample (concluded):
R k d Li t f th S B k I H Al W t d t R d d H ’t
56
1. Pride and Prejudice
Ranked List of the Seven Books I Have Always Wanted to Read and Haven’t
2. Ulysses 3. War and Peace
Middl h4. Middlemarch 5. Moby Dick
Remembrance of Things Past6. Remembrance of Things Past 7. Anna Karenina
Practice: Placing Priorities on a Short Listg57
1 -- 2
1 -- 3 2 -- 3
1 -- 4 2 -- 4 3 -- 4
1 -- 5 2 -- 5 3 -- 5 4 -- 5
1 -- 6 2 -- 6 3 -- 6 4 -- 6 5 -- 61 -- 6 2 -- 6 3 -- 6 4 -- 6 5 -- 6
1 -- 7 2 -- 7 3 -- 7 4 -- 7 5 -- 7 6 -- 7
1 -- 8 2 -- 8 3 -- 8 4 -- 8 5 -- 8 6 -- 8 7 -- 8
1 -- 9 2 -- 9 3 -- 9 4 -- 9 5 -- 9 6 -- 9 7 -- 9 8 -- 9
1 -- 10 2 -- 10 3 -- 10 4 -- 10 5 -- 10 6 -- 10 7 -- 10 8 -- 10 9 -- 10
1 2 3 4 5 6 7 8 9 10Item Scores
Your Turn:Your Turn:58
How projects come to be? What could be selection methods?
………………
MODULE 6: PROJECT ENVIRONMENT FACTORSENVIRONMENT, FACTORS,
STAKEHOLDERS AND ACTORS
Project Environment…Project Environment…
D t f t P j t i S t
60
Do not forget a Project is a System …
The Environment
The Project
Inputs Processes Outputs
The Project
Inputs Processes Outputs
Project Environment…Project Environment…
S t i S t
61
… a System in a System…
The Environment
InputsThe Project Organization
Inputs Processes Outputs
The Project
Inputs
Inputs Processes Outputs
Outputs
Customers or
Outputs
or Beneficiaries
Project Environment…Project Environment…62
The Environment
Actors and Factors as Inputs and Outputs
OutputsThe Project
Organization
Inputs
A ti
Reports
The P j t
O ga at oSupplies Facilities School
Accounting Project Improved instructionMoney
Labor
Government
Improved economic growthGovernment
agencies
g
Project Environment…Project Environment…63
OutsideEnvironment
(outside of parent organization)
Actors (Stakeholders) and Factors as Inputs and Outputs
A t
Actors• people• institutions
Inputs and Outputs
Project
Actors• ...
Inputs Outputs
Factors• climate• inflation
Factors
• ...
Stakeholders: Actors with an interest in or who could be impacted by the project
Project Environment…Project Environment…
P j C l M
64
Project Cycle Management
feed
back
QU
ALITY at EX
feedback
XIT in the 20000s
Project Environment…Project Environment…
St P f E i t l A l i
65
1. Scan environment and identify
Step: Process for Environmental Analysis
yactors/factors; in terms of inputs and outputs; geopolitically and by sector!
2. Screen in terms of dependency, risk,
The Environment
The Project
2. Screen in terms of dependency, risk, and power!
3. Identify problem and beneficial actors and factors!
Inputs Processes Outputs
and factors!
4. Develop strategies and act!
5. Repeat throughout implementation!
Boundary
p g p
Project Environment…Project Environment…
St S A t d F t
66
Step: Screen Actors and Factors
1. List them
2. Rate them in terms of:
D d H i t t?• Dependency: How important?
• Risk: Likelihood something will go wrong
• Power: Degree of control or influence• Power: Degree of control or influence
Assign High, Low, or Medium rating to each in a matrix/tabelg g , , g /
Project Environment…Project Environment…
A & F M i
67
Degree of dependency
Degree of risk
Degree of power
Degree of problem
Actors & Factors Matrix
dependency risk power problem
Actor 1 medium high high
Actor 2 low medium low
Actor 3 high high low high
Factor 1 low medium low
Factor 2 low high low
Factor 3 high high lowFactor 3 high high low
Project Environment…Project Environment…
D fi iti f d d
68
Definition of dependency
• How important is the actor or factor to the successful completion p pof the project!
Definition of risk
• the chance that something will go wrong (hinder the completion of the project in a significant way)!completion of the project in a significant way)!
Project Environment…Project Environment…69
Definition of Power: Ability to make something occur; ability to get
someone to do something one wants done!
Control
POWER:High = controlMedium influence Control
I fl
Medium = influenceLow (none) = appreciation
Influence
AppreciationAppreciation
Project Environment…Project Environment…
Af A l i D l S i d A
70
After your Analysis Develop Strategies and Act
Use general STRATEGIES:
• Reduce dependency
• Reduce risk
Formulate Specific ACTIONS
??• Reduce risk
• Increase power
• Capitalize on beneficial acto s and facto s
???
actors and factors
Project Environment…Project Environment…71
Use Linkages to Increase Influence
Formal InformalFormal
• committees
• project coordinator
• meetings
• plans• project coordinator
• task forces
• incorporation or merger
p
• teambuilding
• personalityp g• rewards
Project Environment…Project Environment…72
Continuously Scan the Project Environment
Scanning is not a one-time event
Circumstances change
Keep current
• list of problem actors and factors,
• Strategies and
• contingency plans!
Project Environment…Project Environment…73
Worksheet 1: Sector AnalysisProject:Sectors Actors FactorsInfrastructureTechnologyFinancialCommercialCommercialPolitical/LegalPhysical
Project Environment…Project Environment…
W k h t 2 A t F t G id
74
Worksheet 2: Actor Factor Grid
Project:
Degree of Degree of risk Degree of Degree of dependency Degree of risk power problem
Actors
Factors
H=HighM M diM=MediumL=Low
Project Environment…Project Environment…
W k h t 3 M i P bl A t & F t
75
Worksheet 3: Managing Problem Actors & Factors
Project:
Decreasing Decreasing Increasing Linkagesdegree of dependency
Decreasing degree of risk degree of
power
LinkagesFormal/Informal
Actors
Factors
Project StakeholdersProject Stakeholders
“I di id l d i ti th t ti l76
“Individuals and organizations that are actively involved in the project, or whose interest may be positively or negatively affected as a result of project pos t e y o egat e y a ected as a esu t o p ojectexecution or project completion.”
2000 PMBOK Guide
Short list
P oject benefactoProject benefactorProject requestorProject manager and teamProject manager and teamThose affected by the project
Project Stakeholders: Partial List of Candidates for Stakeholder RolesCandidates for Stakeholder Roles
P j t b f t d t
77
Project benefactor and upper managementProject sponsorProject office/project advisory boardsExecutive management
P j t tProject requestorProject manager and team
If a team member has a line manager, he or she is a key stakeholder as well. (They hold the strings for your team member.)
Internal ConsultantsInternal ConsultantsLegalAuditTelecommunicationsIT infrastructureIT infrastructure Quality assuranceHuman Resources Department
External entities affected by the projectCustomersCustomersVendorsGovernmental agenciesOther regulatory bodies
Identifying Project Stakeholdersy g j
Potential Stakeholders
78
Potential StakeholdersStakeholders Inside the Team
Stakeholders Within the OrganizationStakeholders Within the Organization
Stakeholders Outside the Organization
Project StakeholdersProject Stakeholders
Putting even more detail to the stakeholder79
Putting even more detail to the stakeholder…
Analyse the characteristics of the group e.g.:
Composition (homogenous or in-homogeneous group in regard to ethnic, social, religious and cultural factors);
Status of the group (informal, formal, social status, legal status, organisational structure, etc.);
Purpose of their existence and main functions;Purpose of their existence and main functions;
Needs; Motives and interests, openly expressed or hidden;
Hopes, wishes, expectations - fears, apprehensions, reservations;
Attitudes (opinions, prejudices, taboos, etc.) towards project related factors, e.g. change, progress, work, strangers;
Potentials and deficiencies/Strength and weaknesses of the group (e.g. knowledge, skills, behaviour, commitment, etc.); );
Resources (power, possessions, influence, monopolies, connections); What could the group contribute to or withhold from the project?
Implications for the planningImplications for the planning.
PCM
Your Turn:Your Turn:80
Project stakeholders how to identify and categorizing them?
…………………
MODULE 7: DEFINING SCOPE
Defining ScopeDefining Scope
P d S P j S
82
Product Scope versus Project Scope
Product Scope: The sum of the features that make up theProduct Scope: The sum of the features that make up the product or service created by the project.
Project Scope: All of the activities and resources required to produce the target product or service.
Preliminary Context Diagrams: D t tiDeconstruction
Wid t
83
ManageEnterprise
SellWidgets
ManageSystems
MaintainAccounts
RunHR
WidgetWorld
Enterprise
ManageSales
SupportSales
SellProduct
Widgets
SupportSystems
DevelopSystems
DesignWebsites
Systems(IT Dept)
Accounts
HireStaff
DevelopCourses
MaintainEmployee Records
HR
Sales(Our Context)
y y p y
• Here we’ve drilled down into the Widget World organization and depicted the major functions within the companyfunctions within the company.
• Ideally, the top level should encompass the entire organization.
• We have been charged with evaluating a flawed sales support system that provides automated training and support to the sales staff. The scope of the training product is therefore the box labeled “Support Sales.”
Scope (Context) Diagrams D fi i th E d P d tDefining the End Product
84
IT DeptSales Staff Ad Hoc Product and
Procedures Inquiries
Usage Statistics
Login and Lesson Participation
Ad Hoc Product and
Sales Staff Information and Access
Sales Staff Performance Support
Training Product
Sales Managers
Sales Support Permissions
Course Lessons, Assessments, and
LearnerEvaluations
Sales Staff Participation
Sales Staff P ti i ti d
Evaluations a t c pat oand Progress
Reports
Course Development
Group
HR Department
ContentUpdates
Participation and Progress Reports
Scope (Context) Diagrams Defining the End Product (continued)
85
The software product, usually drawn as a rounded-corner square, and always in the center of the graphic
Software Product
center of the graphic
One rectangle for each class of individual (e.g., customer) or organization (e.g., HR) Individuals Who
I Wi h that might interact with the software solution
One rectangle (with an extra line inside
Interact With Software Product
g (the top) for each class of system (e.g., your HR System) that may interact with the software product
Systems That Interact With
Software Product
One arrow for each major class of information that flows to or from the software product
Scope (Context) Diagrams( li d t j t t h d ith d li f th d t)(applied to project team charged with delivery of the product)
86
IT Systems SupportHR Dept Requirements
Request for Infrastructure
Approvals/$
Projectto Develop
Internal Focus Group
Completed System Interim Versions
to DevelopSales Staff Support
System
Focus Group Participants
Progress ReportsRecommendations/
Approvals
Internal Web Sales
TemplateDesigns
Design Group
SalesManagers
ContentRules
Scope (Context) Diagram(applied to project team charged with delivery of the product -(applied to project team charged with delivery of the product -continued)
87
The name of the software development project, usually appearing in the center of the graphic as a rounded-corner square
Software Development
Project
One rectangle for each class of individual (e.g., project sponsor) or organization (e.g., IT Department) that may interact with your
Any Individuals or Organizations
Interacting With Department) that may interact with your software development project team in developing the software product
One rectangle (with an extra line inside the top)
Interacting With Project Team
One rectangle (with an extra line inside the top) for each class of system (e.g., a course module library) that be used by the software development project team in developing the software product
Systems That Interact With Project
Team
p
One arrow for each major class of information h fl f f d lthat flows to or from software development
project team
Your Turn:Your Turn:88
How to define Scope?………
MODULE 8: SMART OBJECTIVES
Writing SMART ObjectivesWriting SMART Objectives90
S pecific
Objectives should be stated in terms that include some quantitative target for the end product.S pecific
M There should be some way of actually testing whether or not that stated target has been met.Measurable
A The desired objective must be one that is actually possible to achieve within the time and cost parameters provided.A ttainable
ac e e t t e t e a d cost pa a ete s p o ded
R The desired objective should relate directly to the organization's b siness needs and stated missionR elevantbusiness needs and stated mission.
T The boundaries for completion date of the desired objective should be either a specific date or time or an "offset" from the T ime-Bound
beginning of the project. (For example, must be completed within five months of project launch.)
MODULE 9: RISK MANAGEMENT ANDAND
PROJECT ASSUMPTIONS
Risk ManagementRisk Management
Project Management Institute (PMI) Definition:
92
Project Management Institute (PMI) Definition:
"an uncertain event or condition that, if it occurs, has
a positive or negative effect on a project objective”,a positive or negative effect on a project objective ,
requires that both opportunities and threats be
addressed to maximize/minimize these
advantages/disadvantages.
How to handle them:
Risks that may affect the project for better or worse
can be identified and organized into risk categories.
Risk categories should be well defined and shouldRisk categories should be well defined and should
reflect common sources of risk for the industry or
application area.
Risk ManagementRisk Management
Ri k t i i l d th f ll i
93
Risk categories include the following:
• Technical, quality, or performance risks —such as reliance on unproven or complex technology, unrealistic performance goals, changes to the
h l d i d d d d i h jtechnology used or to industry standards during the project
• Project-management risks —such as poor allocation of time and resources, inadequate quality of the project plan, poor use of project , q q y p j p , p p jmanagement disciplines
• Organizational risks —such as cost, time, and scope objectives that are internally inconsistent, lack of prioritization of projects, inadequacy or y , p p j , q yinterruption of funding, and resource conflicts with other projects in the organization
• External risks —such as shifting legal or regulatory environment, labor External risks such as shifting legal or regulatory environment, labor issues, changing owner priorities, country risk, and weather. Force majeure risks such as earthquakes, floods, and civil unrest generally require disaster recovery actions rather than risk management.
Risk ManagementRisk Management94
A risk breakdown structure (RBS) provides a hierarchical way to organize risks, proceeding from an overview of risks associated with an entire project to general categories and individual risks. The method, developed by Project Management Professional Solutions Ltd. Director of Consultancy David Hillson, mirrors the work breakdown structure.
As part of this first step in the risk management process, an organization might specify the methods used to actually identify risks. For example, brainstorming sessions might identify "communication" problems under "management risk while financial models might evaluate "financial" uncertainties under "commercial risk.''
In the next steps, specific risks are identified within each of the named categories along with some ranking of their severity and strategies for managing those risks. As these strategies are successfully mapped, project managers gain a better understanding of the levels of risk prevalent within alt areas of a project, and they're able to work systematically to reduce those risks.
Source: D.A. Hillson's "The Risk Breakdown Structure as an Aid to Effective Risk Management," presented in June at the PMI Europe 2002 Conference, Cannes, France.
Risk ManagementRisk Management
A i k b kd t t (RBS)
95
A risk breakdown structure (RBS)
Risk ManagementRisk Management
Risk Identification WorksheetRisk Identification WorksheetEnter risk scenario (how an event could jeopardize project outcome).Rate probability, impact, and degree of control using
Scenario:
Probability Impact Control Index
Risk Identification WorksheetRisk Identification Worksheet
Rate probability, impact, and degree of control using rating scale of:
1 = Low2 = Medium3 = High
Probability Impact Control Index
Financial Impact:
Action to be Taken: Ignore Eliminate ManagegCompute risk index using formula:
Mitigations:
Contingencies:
Probability * ImpactControlRisk Index =
If possible, enter financial impact.Determine actions to take:
Ignore (do nothing)Eliminate (sidestep)
Manager of This Risk:
Eliminate (sidestep)Manage
For managed risks, indicate mitigations and contingencies and assign risk manager.L ti t k th
Date:Actions Taken
Action:
Log actions taken as they occur.
Risk Managementg
Giving Risks Priorities97
Risk ID Risk Scenario Probability Impact Control IndexRisk Priority Worksheet
Maintain inventory of all risks identified—updating probabilities, impacts, and controls if changes occur.Giving Risks Priorities
Risk ID Risk Scenario Probability Impact Control Index1 Key stakeholders unavailable during project definition phase 2 3 2 32 Vendors late in delivering required software for security system 2 2 1 43 Loss of key team member in middle of project 1 3 2 1.54 Power failure due to seasonal storms 1 3 1 3
5 Final regulations controlling administration of new system late 2 3 1 66 Scope changes require additional tasks and resources 2 3 2 3
Focus attention on the risks with the highest indices!!!
Risk ID Risk Scenario Probability Impact Control Index5 Final regulations controlling administration of new system late 2 3 1 62 Vendors late in delivering required software for security system 2 2 1 4
Risk Priority Worksheet
1 Key stakeholders unavailable during project definition phase 2 3 2 34 Power failure due to seasonal storms 1 3 1 3
6 Scope changes require additional tasks and resources 2 3 2 33 Loss of key team member in middle of project* 1 3 2 1.5
Your Turn: Project Risk Scenariosj
Risk Identification Worksheet
98
1. Individually identify and jot down four possible risk scenarios this
Scenario:
Probability Impact Control Index
Risk Identification Worksheet
project might face.
2. Share these within your group and create a Risk Priority
Probability Impact Control Index
Financial Impact:
Action to be Taken: Ignore Eliminate Manage
Worksheet of your pooled risks.
3. Score the risks.
4 For the top two brainstorm at
Mitigations:
Contingencies:4. For the top two, brainstorm at least one mitigation and one contingency.
5 Use the Risk IdentificationManager of This Risk:
5. Use the Risk Identification Worksheet as a guide, but you do not need to complete one for this exercise.
Date:Actions Taken
Action:
Project Assumptions PCMProject Assumptions
H d PCM d fi f l d h dl A i ‘?
C
99
How does PCM define, formulate and handle ‚Assumptions‘?
A ti D fi itiAssumption Definition:
Conditions/factors that must exist/are important if the program/project is to succeed but which are not under theprogram/project is to succeed, but which are not under the direct control of the project, because they do not have e.g. :
• a mandate for it and or
• did choose not to control it and or
• are outside the projects intervention.• are outside the projects intervention.
Project AssumptionsProject Assumptions100
Risk Project Management Institute (PMI) Definition:
Assumption PCM Definition:
"an uncertain event or condition
that, if it occurs, has a positive or
Conditions/factors that must exist/are important if the program/project is to succeed,, , p
negative effect on a project
objective”, requires that both
program/project is to succeed, but which are not under the direct control of the project, because they do not have e.g. :
opportunities and threats be
addressed to maximize/minimize
y g
• a mandate for it and or
• did choose not to control it and these advantages/disadvantages. or
• are outside the projects interventionintervention.
Project Assumptions PCMProject Assumptions
Wh fi d d h d A i ?
C
101
Where to find and how to word Assumptions?
• Assumptions can be derived from a variety of analytical tools, such Stakeholder Analysis Problem/Objective Tree Analysis ofsuch Stakeholder Analysis, Problem/Objective Tree, Analysis of Alternatives, SWOT, just to name a few.
• Assumptions will be worded as positive conditions (i.e. like p p (‘Results/Outputs’).
• Assumptions will be weighted according to their importance and probability
• One uses the IF-AND-THEN logic, to make sure that the Assumption is on the right level: e g IF an Activity is done ANDAssumption is on the right level: e.g. IF an Activity is done AND the Assumption comes true, THEN the Result/Output will be achieved.
Project Assumptions PCMProject Assumptions C
102
Project AssumptionsProject Assumptions
A ti ti d
103
Assumptions, continued
There might be quite a number of potentially important Assumptions, which we have to make about any Result/Output or even Activity and it is neither useful nor possible to list them all. What is required is the specification of the most important Assumptions for each level of the hierarchy.
Generally, the significance of these Assumptions - i.e. the ability of the factor to affect achievement rises through the hierarchy Uncertainty will rise at the ‘Result/Output’ toachievement - rises through the hierarchy. Uncertainty will rise at the Result/Output to ‘Goal/Purpose’ linkage level and will become very significant at the ‘Goal/Purpose’ to ‘Overall Goal’ linkage level. Uncertainty at this level is high, because the achievement of the ‘Overall Goal’ depends upon the achievement of one or more complementary inputs.
Some additional remarks
Avoid to many Assumptions in your LogFrame. Those that are important and can be ‘managed’ by the implementation team have to be at least monitored and they might even become additional Activities, which have to be carried out!which have to be carried out!
Sometimes planning teams have a tendency to 'shy-away' from stating Assumptions. Do not fall into that trap either! Even some manageable Assumptions might turn into Killer Assumptions if they are ignored!
Risk ManagementRisk Management
Finding Risks/Assumptions using a PEST analysis104
Finding Risks/Assumptions using a PEST analysisIt is a tool that strategy consultants use to scan the external macro-environment in which an organisation or company operates. PEST is an acronym for the following factors:for the following factors:
Political factorsEconomic factorsEconomic factorsSocial factors, andTechnological factors.
PEST factors play an important role in the value creation opportunities of a strategy. However they are usually beyond the control of the corporation and must normally be considered as either threats or opportunities Remember macronormally be considered as either threats or opportunities. Remember macro-economical factors can differ per continent, country or even region, so normally a PEST analysis should be performed per country. In the table on the following page you find examples of each of these factors.y p
Risk ManagementRisk Management
Example PEST matrix105
Example PEST matrixPolitical (incl. Legal)
factors Economic
factors Social factors
Technological factors
Environmental regulations and protection Economic growth Income distribution Government research
spendingand protection g spending
Tax policies Interest rates & monetary policies
Demographics, Population growth rates, Age distribution
Industry focus on technological effort
International trade regulations and Government Labour/ social mobility New inventions and regulations and restrictions spending Labour/ social mobility development
Contract enforcement lawConsumer protection
Unemployment policy Lifestyle changes Rate of technology
transfer
Employment laws TaxationWork/career and leisure attitudes
Life cycle and speed of technologicalEmployment laws Taxation leisure attitudes
Entrepreneurial spirit technological obsolescence
Government organization and attitude Exchange rates Education Energy use and costs
Competition regulation Inflation rates Fashion, hypes(Changes in) Information p g , ypTechnology
Political Stability Stage of the business cycle
Health consciousness & welfare, feelings on safety
(Changes in) Internet
Safety regulations Consumer Living conditions (Changes in) Mobile Safety regulations confidence Living conditions Technology
Risk ManagementRisk Management
Oth f t ‘ th t b i l d d
106
Internal factors External factors
Other ‚factors‘ that can be included…
o Designo Procedures + decision makingo Financeso Physical structure
o Government policyo Economic backgroundo Social background
Framework for external M+E ofo Physical structureo Organizational structureo Manpowero Information system
o Framework for external M+E of performance
Sustainability factorsyo Vision, Mission, Mandate
o Policy supporto Appropriate technologyo Institutional and management capacityg p yo Economic and financial viabilityo Socio-cultural and gender issueso Environmental protection
Project AssumptionsProject Assumptions107
Almost every lesson includesthe reminder “Don’t Assume!!”
Turn that around and make it“Document Assumptions!”
Don’t expect others to read your mind.Capture as many assumptions as possible to include in your initial project charter.Don’t be surprised if others do not share all yourDon t be surprised if others do not share all your assumptions. This is the time to resolve differences—before the project is underway!
Your Turn:Your Turn:108
What are Risks and Assumptions and how to deal with them?
…………………
MODULE 10: THE PROJECTMODULE 10: THE PROJECT CHARTER
The Project CharterThe Project Charter
Th j h i h j ’ “li d b i ”
110
The project charter is the project’s “license to do business.”
It should come from someone outside the project itself withIt should come from someone outside the project itself with funding-access, resource-assignment, and decision-making authority sufficient to support the project.
This person is usually known as the project sponsor.
Why Have a Project Charter?Why Have a Project Charter?
P i l d i h h j d
111
Primary purpose: to get approval to proceed with the project and obtain sufficient approval for resources to move to the next phase of the project.
Communicate to stakeholders and other interested parties the i i d bj ti f th j tmission and objectives of the project.
Communicate to the project team what they are expected toCommunicate to the project team what they are expected to accomplish.
Project Charter ComponentsProject Charter Components
Project Mission112
Project Mission Project ScopeProject ObjectivesProject ObjectivesProject AssumptionsProject ConstraintsjMilestonesProject RisksStakeholdersSignature Page Granting Authority to ProceedIn some organizations, the project charter is an evolving document. Many of the components listed will change as the project moves into the project definition phase.
Your Turn: Starting the CharterYour Turn: Starting the Charter
List at least Three SMART Objectives
113
List at least Three SMART Objectives.
Project Assumptions List at least three Project Assumptions.
Project Constraints See Project Priority Matrix in Appendix. List any other constrain
P j PhProject PhasesIndicate the phases of the proposed project.
Milestones List major milestones for project identified so far. (Include at st ajo esto es o p oject de t ed so a ( c ude atleast five throughout the life of the project.)
Project Risks Attach Risk Identification Worksheets and Risk Priority
Stakeholders Attach Potential Stakeholders WorksheetAttach Potential Stakeholders Worksheet.
Signature Page Granting Authority to Proceed
Obtain signatures of Project Sponsor and Project Manager.
Project Sponsor Signature:Project Manager Signature:
The LogFrame, P j t C l M t T la Project Cycle Management Tool
114
Project Description
Objectively Verifiable
Indicators (OVI)
Means of Verification (MoV)
Assumptions
Overall Goal Why is it important for the country/society
Project Purpose What are the needs for the target group/beneficiaries
Outputs/Results
What will be the results
Activities What will the project do to achieve the results
Inputs Costs, etc
PCM
The LogFrame, what can it be used for?The LogFrame, what can it be used for?
It is an aid to logical thinking and an instrument by which a strategy
115
It is an aid to logical thinking and an instrument, by which a strategy,
product, program, project and implementation process may be
structured and described for planning and analytical purposesstructured and described for planning and analytical purposes.
It can be used as well for or be the basis for a M+E system or oven a
M t I f ti S t (MIS) O d fi ith itManagement Information System (MIS). One can define with it
services/products, budgets, breakdown of responsibilities and use it for
further operational planningfurther operational planning.
If prepared correctly, the LogFrame is a concise document, easy to use
and to apply, and eventually lessening the workload of those responsible
for the various phases of the project cycle. It serves as a ‘project
charter’!
Your Turn:Your Turn:116
What is the Project Charter?………………
MODULE 11: RESPONSIBILITIES ANDMODULE 11: RESPONSIBILITIES AND WORK BREAKDOWN STRUCTURES
Responsibility Matrix (RM)Responsibility Matrix (RM)
What is it?118
What is it?
A tool for clarifying organizational roles and responsibilities
Every organizational role is clear to members of the team and the coEvery organizational role is clear to members of the team and the co-operating partners!
Each work package has an clearly identified “owner” ,in order that no two groups think they are responsible for the same work package!groups think they are responsible for the same work package!
Why is it the RM important?
It promotes discussion and agreement about roles, responsibilities and organizational relationships!
It clarifies who is responsible for each work package!It clarifies who is responsible for each work package!
It is the source of information for preparing the master summary schedule and CPM plan!
Responsibility Matrix (RM)Responsibility Matrix (RM)119
Why is it the RM important?
It promotes discussion and agreement about roles, responsibilities and organizational relationships!
It l ifi h i ibl f h k k !It clarifies who is responsible for each work package!
It is the source of information for preparing the master summary schedule and CPM plansummary schedule and CPM plan
Responsibility Matrix (RM)Responsibility Matrix (RM)120
WBS P oject
Organizational unit, example
WBS element Owner Architect Government Contractor
Projectmanager
Plan A W C C C
Site A C W A
Code
Does workW =
Must be consultedC =
ApproveA = ApproveA =
Information onlyI =
Responsibility Matrix (RM)Responsibility Matrix (RM)121
How to do it…
Draw a matrix (grid)
List WBS elements down the left hand side columnList WBS elements down the left-hand side column
List organizational units along the top row
Use codes for level of involvement
Discuss and agree on rolesg
Assigning Responsibilities: R ibilit M t iResponsibility Matrix
C f f k d i d h j
122
Cross-reference of tasks and resources assigned to the project (RACI chart), another example.
Project Item Sponsor Project Manager Project Team Project OfficeProject Definition A A R IRisk Management A R R CDetailed Design A R R CWeekly Web Bulletin I R R I
etc.
R R iblR = Responsible
A = Accountable
C = Consulted
fI = Informed
Work Breakdown StructuresWork Breakdown Structures123
Breaking down the elephant…
Tail Legs Body Head
Work Breakdown StructuresWork Breakdown Structures
W k B kd S (WBS ) h l i h i i i
124
Work Breakdown Structures (WBSs) help organize the activities required to meet the objectives of the project.
Focus is on deliverables!
May be organized by:
phase of the projectcomponent
Work Breakdown StructuresWork Breakdown Structures125
1 Step: List major activities
8 Steps to prepare a OP/WBS
1. Step: List major activities
2. Step: Break activities down into manageable tasks
3. Step: Clarify sequence and dependencies3. Step: Clarify sequence and dependencies
4. Step: Estimate start-up/time, duration and completion of Activities
5. Step: Summarize scheduling of major Activities5. Step: Summarize scheduling of major Activities
6. Step: Define milestones
7. Step: Define expertise/personnel requiredp p /p q
8. Step: Allocate tasks/responsibilities among the team
Work Breakdown StructuresWork Breakdown Structures
Ph B d WBS
126
Phase-Based WBS
Partial WBS for Software Project Based on Phase
Customer Relationship Management System
Planning
Project Management
Client Interviews
Requirements
Logical Design Logical Design
Design
etc.
Build
g
Reporting
Administration
Review of Current Workflows
Business ObjectivesProcess Models
Use Cases
g g
Process Models
Use Cases
g g
Meetings
Documentation Planning
Preliminary Test Planning
Documentation Planning
Use Cases
Logical Data Models
Use Cases
Physical Data Models
Training Requirements
Work Breakdown StructuresWork Breakdown Structures
C B d WBS
127
Partial WBS for Luxury Townhouse Complex by ComponentComponent-Based WBS
IYHTAYCAI* Village Project(*If you have to ask, you can't affort it)
Planning
Project Management
Townhouse Units
Buildings
Water and Sewers
Land Planning
Advertising
Sales and Marketing
Reporting
Administration
M ti
Clubhouse
Gatehouses
P Sh
Roads and Access Lanes
Retention Ponds
18 H l G lf C
Association Declarations
General Legal
Meetings
Documentation Planning
Pro Shop
Documentation Planning
Maintenance Staffing Requirements
18-Hole Golf Course
Permits and Inspections
Permits and Inspections
Work Breakdown StructuresWork Breakdown Structures128
Project Management - Level 2
Level 3 Level 4
Project Start and Finish Contract AwardComplete Project
Project Management WBS element
Meetings and Reviews
Kick-off meetingMonthly/Quarterly Project ReviewsCorporate ReviewsIn-Process ReviewClose-out MeetingAction Item Tracking System
WBS element decomposition, example
ReportsMonthly Progress ReportAnnual ReportBudget/Financial Status Report
Plans
Project CharterMaster ScheduleProject Plan (Current and Future Phases)Ri k M t d Oth PlRisk Management and Other PlansProject Financing and Budget
Controle
Schedule TrackingCost TrackingEarned Value ManagementVariance AnalysisCorrective ActionCorrective ActionWork-Arounds
AdministrativeProject Management OfficeSpace/RelocationCorrespondence Control System
P j SProcurement/Purchasing
Project Support Subcontract ManagementContract Management
Work PackagesWork Packages
L l l f WBS i ll d W k P k if f h
129
Lowest level of WBS is called a Work Package, if further deconstruction into activities is possible.
May be assigned as a subprojectMay be subordinated into WBS structure for estimating purposes
A ti iti t thi l l b th b i f ti d d tiActivities at this level become the basis for time and duration estimates.
Work PackagesShould the WP be decomposed further?
Y /N I th d t i th f t d d ti ti t ?
130
Yes/No Is there need to improve the accuracy of costs and duration estimates?
Is there more than one individual responsible for the work contents?
Is there a need to cost-out activities internal to the WP?
Is there a need to know precisely the timing of activities internal to the WP?
Are there any dependencies between the internal activities and or other WP‘s?
Are there any significant time breaks in the execution of the work processes internal to the work elements?
Do resource requirements within the WP change over time?
D th i it diff th i t l d li bl ithi th k l t?Do the pre-requisites differ among the internal deliverables within the work element?
Are there any acceptance criteria applicable before completion of the entire WP?
Can a portion of the work to be performed within the WP be scheduled as a unit?
Are there any specific risks that require focussed attention to a portion of the WP. requiring further division to separate them?
Is the WP understood clearly and completely to the satisfaction of various stakeholders?
The Master Summary Schedule (MSS)The Master Summary Schedule (MSS)
What is it?131
What is it?
A schedule of summary activities (lif l b h d l )(life-cycle sub-phases and process elements)
Combination of WBS and process structureIt d ib k l t ( bj t ) d tiIt describes work elements (objects) and actions
It is written in nouns and verbs
Why is it important?
For CPM planning: It will disaggregate summary ti iti i t ti iti f CPMactivities into activities for CPM
It is useful for reporting to senior management
The Master Summary Schedule (MSS)The Master Summary Schedule (MSS)
How does a MSS looks like?132
WEEKSCODE RESP.
From WBS
How does a MSS looks like?
Summary
Plan (A)
Site (C)
4 8 12 16 20 24
Prepare
Prepare
From WBS
10
20Activities
( )
Foundation (C)
Frame (C)
Roof (SC)
Construct
Construct
30
40
50 Roof (SC)
Systems (SC)Plumbing (P)Electrical (E)Telephone (T)
Construct
Construct
I t ll
50
60
Project mgt (PM) Install70
Continuous activity
The Master Summary Schedule (MSS)The Master Summary Schedule (MSS)133
Convert WBS into outline and use as labels for left axis
How to prepare the MSS
Use unit of time for control period along horizontal axis and draw timeline
Use terminology from process structure whenever possible to name summary activities
Identify assign duration (time) draw label and code summaryIdentify, assign duration (time), draw, label and code summary activities (process sub-phases and process elements) for each work package.
SummarySummary
F k f l i b d t
134
WBS Work breakdown structure
MSS M t h d l
Framework for planning budgets, schedules and control systems
MSS Master summary schedule
RM Responsibility matrix
Draft overall schedule
Clarify roles and responsibilitiesRM Responsibility matrix Clarify roles and responsibilities
Next step:Next step:
Detailed planning and scheduling and assigning resources at the activity levelthe activity level
Sources of Project Activities: BrainstormingSources of Project Activities: Brainstorming135
More Sources of Project Activities: UsingTemplates
136
Don’t reinvent the wheel!
As you get more projects underAs you get more projects underyour belt, work with other project teams to develop templates for WBS’s to use as a starting point.
Remember, no two projects are ever exactly alike (remember the “unique” in the definition of a project)! The template should be a starting point—to be tailored to the specific needs of the current g p pproject.
Even with the time spent in tailoring, templates can be enormousEven with the time spent in tailoring, templates can be enormous time-savers.
Your Turn:Your Turn:137
What is a RM and a WBS and how to manage them?
………………...
MODULE 12: PROJECT SCHEDULING
Project SchedulingProject Scheduling139
The Program (or Project) Evaluation and Review Technique,
commonly abbreviated PERT, is a model for project management
designed to analyze and represent the tasks involved in completing a
given project.
Project SchedulingProject Scheduling
PERT i
140
PERT an overview
PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task and identifying the minimum time needed to complete the totalneeded to complete each task and identifying the minimum time needed to complete the total project.
PERT was developed primarily to simplify the planning and scheduling of large and complex j t It bl t i t t i t b ki it ibl t h d l j t hilprojects. It was able to incorporate uncertainty by making it possible to schedule a project while
not knowing precisely the details and durations of all the activities. It is more of an event-oriented technique rather than start- and completion-oriented and it is used more in R&D-type projects where time, rather than cost, is the major factor.p ojects e e t e, at e t a cost, s t e ajo acto
This project model was the first of its kind, a revival for scientific management, founded in Fordism and Taylorism. Only DuPont corporation's critical path method was invented at roughly th ti PERTthe same time as PERT.
The most recognizable feature of PERT is the "PERT Networks", a chart of interconnecting timelines. PERT is intended for very large-scale, one-time, complex, non-routine projects.y g , , p , p j
Project SchedulingProject Scheduling
C ti
141
Conventions
A PERT chart is a tool that facilitates decision making; The first draft of a PERT chart will number its events sequentially in 10s (10 20 30 etc ) to allow the laterchart will number its events sequentially in 10s (10, 20, 30, etc.) to allow the later insertion of additional events.
Two consecutive events in a PERT chart are linked by activities which areTwo consecutive events in a PERT chart are linked by activities, which are conventionally represented as arrows in the diagram above.
The events are presented in a logical sequence and no activity can commence untilThe events are presented in a logical sequence and no activity can commence until its immediately preceding event is completed.
The planner decides which milestones should be PERT events and also decidesThe planner decides which milestones should be PERT events and also decides their “proper” sequence.
A PERT chart may have multiple pages with many sub-tasks.y p p g y
Project SchedulingProject Scheduling
Terminology
142
Terminology
A PERT event: is a point that marks the start or completion of one or more tasks. It consumes no time and uses no resources. It marks the completion of one or more tasks and is not “reached” until all of the activities leading to that event have beentasks and is not reached until all of the activities leading to that event have been completed.
A predecessor event: an event (or events) that immediately precedes some other event without any other events intervening It may be the consequence of more thanevent without any other events intervening. It may be the consequence of more than one activity.
A successor event: an event (or events) that immediately follows some other event ith t th t i t i It b th f thwithout any other events intervening. It may be the consequence of more than one
activity.
A PERT activity: is the actual performance of a task. It consumes time, it requires resources and it can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be completed until the event preceding it has occurred.
Project SchedulingProject Scheduling
Terminology
143
Terminology
Optimistic time (O): the minimum possible time required to accomplish a task assuming everything proceeds better than is normally expectedtask, assuming everything proceeds better than is normally expected
Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).task, assuming everything goes wrong (but excluding major catastrophes).
Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.a task, assuming everything proceeds as normal.
Expected time (TE): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the implication being that , g y g p ( p gthe expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time).
TE = (O + 4M + P) ÷ 6
Project SchedulingProject Scheduling144
Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will d l th hi f th t i l t b t l t th tdelay the reaching of the terminal event by at least the same amount.
Critical Activity: An activity that has total float equal to zero. Activity with zero float does not mean it is on critical pathzero float does not mean it is on critical path.
Lead time : the time by which a predecessor event must be completed in order to allow sufficient time for the activities that must elapse before aorder to allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed.
Lag time: the earliest time by which a successor event can follow a specificLag time: the earliest time by which a successor event can follow a specific PERT event.
Project SchedulingProject Scheduling145
Slack: the slack of an event is a measure of the excess time and resources available in achieving this event. Positive slack(+) would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slackschedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule.
Fast tracking: performing more critical activities in parallel g p g p
Crashing critical path: Shortening duration of critical activities
Float or Slack is the amount of time that a task in a project network can be delayed without causing a delay - Subsequent tasks – (free float) or Project Completion – (total float)
Project SchedulingProject Scheduling
I l ti PERT
146
Implementing PERT
The first step to scheduling the project is to determine the tasks that the project requires and the order in which they must be completed The orderproject requires and the order in which they must be completed. The order may be easy to record for some tasks (e.g.
When building a house the land must be graded before the foundation canWhen building a house, the land must be graded before the foundation can be laid) while difficult for others (There are two areas that need to be graded, but there are only enough bulldozers to do one).
Additionally, the time estimates usually reflect the normal, non-rushed time. Many times, the time required to execute the task can be reduced for an additional cost or a reduction in the quality.an additional cost or a reduction in the quality.
Project SchedulingProject Scheduling147
I thi l th t k l b l d th h S t k b dIn this example there are seven tasks, labeled a through g. Some tasks can be done concurrently (a & b) while others cannot be done until their predecessor task is complete (ccannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (a), the most likely or normal time estimate (m), and the pessimistic ti ti t (b) Th t d ti (T ) i t d i th f l ( + 4 + b) /6time estimate (b). The expected time (TE) is computed using the formula (a + 4m + b) /6.
Project SchedulingProject Scheduling148
A G tt Ch t t d i Mi ft P j tA Gantt Chart created using Microsoft Project.
Note (1) the critical path is in red, (2) the slack is the black lines connect non-critical activities, (3) when using MSP, you must use the task ID when labeling predecessor activities, and (4) since S t d d S d t k d ( d ib d b ) b th G tt h tSaturday and Sunday are not work days (as described above) some bars on the Gantt chart are longer if they cut through a weekend.
Project SchedulingProject Scheduling
Network Diagrams and Critical Path Analysis149
Once you’ve determined the activities for the project and estimated their durations, network diagrams are the next step for creating
Network Diagrams and Critical Path Analysis
their durations, network diagrams are the next step for creating the project schedule.
Th t tThere are two types:
1. Activity on Arrow (AOA) - nodes on the diagram connect1. Activity on Arrow (AOA) nodes on the diagram connect arrows and represent activities
2 A ti it N d (AON) d t ti iti th t2. Activity on Node (AON) - nodes represent activities that are connected by arrows showing the precedence of activities
Project SchedulingProject Scheduling
N k Di E l A i i A (AOA)
150
Task Duration Predecessor(s)A 8 days -B 6 d 1
Network Diagram Example Activity on Arrow (AOA)
B 6 days 1C 3 days 1D 0 days 3E 12 days 4F 5 days 2F 5 days 2G 5 days 6H 5 days 7I 0 days 5,8
F (5d) H (5d)
A (8d)
B (6d)
E (12d)
F (5d) G (5d) H (5d) I (0d)
C (3d) D (0d)
Critical path is A-B-F-G-H-I, with total duration of 29 days.There is one non-critical path A-C-D-E-I, with total duration of 23 days.p C , 3 y
NOTE: Task A has no slack because it is on the critical path.
Project SchedulingProject Scheduling151
Task Duration Predecessor(s)A 8 days -B 6 days 1
Network Diagrams and Critical Path Analysis
B 6 days 1C 3 days 1D 0 days 3E 12 days 4F 5 days 2G 5 d 6G 5 days 6H 5 days 7I 0 days 5,8
Once again, the critical path is A-B-F-G-H-I, with total duration of 29 days.There is one non-critical path A-C-D-E-I, with total duration of 23 days.
NOTE: Task A has no slack because it is on the critical pathNOTE: Task A has no slack because it is on the critical path.
Your turn…Your turn…152
Project SchedulingProject Scheduling153
Networked Tasks
Rule #1: In forward pass, ES = latest EF of predecessorRule #2: In backward pass, LF = earliest LS of successorsRule #3: Task is CRITICAL if ES=LS and EF=LS (no Slack)Rule #4: Task is NON-CRITICAL if ES<>LS and Slack = LS – ES (or LF – EF)
Project SchedulingProject Scheduling154
Project SchedulingProject Scheduling155
Your Turn:Your Turn:156
How to manage Project Scheduling?………………
MODULE 13: CONTROLLING ANDMODULE 13: CONTROLLING AND MONITORING
Controlling and MonitoringControlling and Monitoring158
Controlling has two ‚meanings‘:
• Management Accounting• Management Accounting
and or a
• Steering and co-ordination concept
Monitoring is an ongoing analysis of project progress towards achieving
planned results with the purpose of improving management decision
making.
Controlling and MonitoringControlling and Monitoring159
Definition of Management Accounting
According to the Chartered Institute of Management Accountants (CIMA) Management Accounting is:According to the Chartered Institute of Management Accountants (CIMA), Management Accounting is:
"the process of identification, measurement, accumulation, analysis,
preparation, interpretation and communication of information used by
management to plan, evaluate and control within an entity and to assure
appropriate use of and accountability for its resources”.
Controlling and MonitoringControlling and Monitoring160
Management accounting also comprises the preparation of financial reports for non management groups such as shareholders, creditors, regulatory agencies and tax authorities" (CIMA Official Terminology)creditors, regulatory agencies and tax authorities (CIMA Official Terminology)
The aims of management accountancy are:
• Formulating strategies• Planning and constructing business activities
Helps in making decision• Helps in making decision• Optimal use of resources• Supporting financial reports preparation
S f di• Safeguarding assets
Controlling and MonitoringControlling and Monitoring161
Steering and Co-ordination
Main task of controlling is to guard the e.g. economic efficiency of aMain task of controlling is to guard the e.g. economic efficiency of a company/an organization, but not to guarantee it!
Other tasks include: e gOther tasks include: e.g.
• designing and operating qualitative and quantitative steering instrumentsinstruments,
• the arrangement of control factors and variables, • the coordination of the flow information, • analysis and interpretation of results/findings andanalysis and interpretation of results/findings and • the assistance in the decision making process.
Controlling and MonitoringControlling and Monitoring162
Definition of ‘Monitoring’ from the World Bank…
“A continuing function that uses systematic collection of data onA continuing function that uses systematic collection of data on
specified indicators to provide management and the main
t k h ld f i d l t i t ti ithstakeholders of an ongoing development intervention with
indications of the extent of progress and achievement of
objectives and progress in the use of allocated funds”
Controlling and MonitoringControlling and Monitoring163
Monitoring is a continuous and or periodic surveillance of the achievements and its effects of project/program Objectives and Impacts observing the:
• Overall Goal
D l t G l• Development Goal
• Project Purpose
• External factors (Assumptions)
• Unplanned events
• Impacts and as well on the
• Physical implementation of the project deliverables
PCM
Controlling and MonitoringControlling and Monitoring164
Monitoring, h i dwhat is covered……
PCM
Controlling and Monitoring PCMControlling and Monitoring
E g Impact Monitoring as part of the PCM concept
C
165
E.g. Impact Monitoring as part of the PCM concept
feed
back
QU
ALITY at EX
feedback
XIT in the 20000s
Controlling and MonitoringControlling and Monitoring166
Be accrepo
The main objectives of rnin
g fro
m
erie
nce
ccountable and
position ourselvesThe main objectives of
Monitoring (+Evaluation)
Lear
expe
s
Build capacities
Making better informed decisions
Controlling and MonitoringControlling and Monitoring167
Designing Control and Reporting Systems (Time, Cost, Resources and Scope (Performance and Quality)1. Design a management control and reporting1. Design a management control and reporting
system to:
(a) manage the project’s progress and adherence to plan interms of time, cost, resources and scope (performanceterms of time, cost, resources and scope (performanceand quality) (given an approved implementation plan);and
(b) control the project’s scope & design.( ) p j p g
2. Make appropriate changes in the current operationalplan and in the baseline plan.
Controlling and MonitoringControlling and Monitoring
Principles of Project Control Cargo Ship Analogy168
Principles of Project Control - Cargo Ship Analogy
DestinationCaptain questions
1 What is the plan?1. What is the plan?(What is our planned course?)
2. What are the actuals? (What is our present position?)
3. What are the variances? Why?(Are we on course or off course?)
4. What are the trends and how do they
Externalinfluence
yextrapolate to the future?
5. What actions are required?
Actual travel Position surveyed
Start of journey
Controlling and MonitoringControlling and Monitoring
Project Control (CPM picture)169
Project Control (CPM picture)
Baseline plan = Schedule + Budget + Resources + Scope
Approved at start of implementation
Used to set “course” and to assess progress
Current operation plan = result of day-to-day changes and decisions
Slightly g yahead ofschedule
Today lineToday line
Controlling and MonitoringControlling and Monitoring
P j t C t l (CPM i t )
170
Project Control (CPM picture)
Planned Budget to Week 4 $110
A t l C t t W k 4 $150Actual Cost to Week 4 $150
Difference ($ 40)
Slightly g yahead ofschedule
Today lineToday line
Controlling and MonitoringControlling and Monitoring
j l ( i )
171
Project Control (CPM picture)
Earned Value = Budgeted Value of Work Complete
Planned Budget to Week 4 $110 Earned Value $120
Actual Cost to Week 4 $150 Actual Cost $150
Difference ($ 40) Over Budget ($ 30)
Slightly g yahead ofschedule
Today lineToday line
Controlling and MonitoringControlling and Monitoring172
Time (Schedule) Cost (Budget)
ProjectRectangleg
Scope (Performance and Quality ) = Work done that meets specifications
Resources
specifications
Controlling and MonitoringControlling and Monitoring173
Set the control period for the frequency of updating
Project Control Process
Determine the level of detail at which control will be exercised
Control 4 key variablesy
time (schedule)
cost (budget)
resources (people, materials, equipment)
scope (performance & quality)Adjust the current operational plan and revise the baseline plan if necessary
Controlling and MonitoringControlling and Monitoring174
Control of schedule is based on the activity plan
Controlling Schedule (Time)
Control of schedule is based on the activity plan.
How much work is completed relative to plan?
Measure progress at end of each control period. Count as complete only work that meets specifications! W k di tl t k di b h tWork directly on network diagram or bar chart.Pay special attention to activities on critical path.
Controlling and MonitoringControlling and Monitoring
Schedule: Key Questions 1 & 2175
Schedule: Key Questions 1 & 21) What are the actuals?
a) start dates?
b) finish dates of completed activities?b) finish dates of completed activities?
c) progress of incomplete activities?
d) anticipated completion of incomplete activities?) p p p
2) What was the plan?
a) t t d t ?a) start dates?
b) finish dates?
c) duration?c) duration?
Controlling and MonitoringControlling and Monitoring
Schedule: Key Questions 3 & 4176
3) What are the variances (ahead or behind)?Why was there a variance?
Schedule: Key Questions 3 & 4
Why was there a variance?
a) planned start vs. actual start dates
b) planned finish vs. actual finish dates or anticipatedb) planned finish vs. actual finish dates or anticipatedcompletion
c) planned duration vs. actual or anticipated duration
4) Wh t th t d d h d th t l t t th4) What are the trends and how do they extrapolate to the future?
a) at the project level?a) at the project level?
b) at the subproject (component) level?
c) Are variances staying the same?
Controlling and MonitoringControlling and Monitoring
Controlling Schedule: Trend Graph177
Expected Total Durations
Controlling Schedule: Trend Graph
30
35in
Wee
ks
20
25
Du
rati
on i
10
15
Pro
ject
D
0
5
W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 W 11 W 12 W 13 W 14 W 15 W 16 W 17 W 18
Pla
nn
ed P
Actual Weeks into Project
P
Controlling and MonitoringControlling and Monitoring
S h d l K Q i 4
178
Schedule: Key Question 4 (continued)
4) What are the trends and how do they extrapolate to the ) y pfuture?
d) Check the critical path
e) Predict the future
1. Anticipate likely start/finish dates
2. Estimate time to completion
Controlling and MonitoringControlling and Monitoring
Schedule: Key Question 5
179
Schedule: Key Question 5
5) What actions are required?5) What actions are required?
a) Act on information (Analyze the WHY!)
b) Make decisionsb) Make decisions
1. Modify current operational plan as needed
2 M dif b li l if2. Modify baseline plan if necessary
Controlling and MonitoringControlling and Monitoring180
Schedule: Summary of the Process
1) Review the actual performance (work complete)
2) Compare to the planned schedule
3) Determine the schedule variance (gap)
4) Analyze trends and extrapolate to the future
a) Check the expected project completion date
b) Predict the future — Analyze why?5) Take action
a) Modify the current operational plan as required
b) Modify the baseline plan if necessary
Controlling and MonitoringControlling and Monitoring
C t lli S (P f d Q lit )
181
Controlling Scope (Performance and Quality)
Performance = work completed that meets or exceeds specifications. (Quality)
Performance is measured by determining if a scheduled activity is completecomplete.
Activities that do not meet specs are not complete.
It’s harder to assess performance for project with less tangible deliverables.
C l i i il h f h d lControl process is similar to that for schedule.
Controlling and MonitoringControlling and Monitoring
Measuring Performance: Percent Complete182
Measuring Performance: Percent CompletePercent complete is:
A S mma RatioA Summary Ratio
Built up from completed work of all components
Diffi l ( i ll f l ibl d li bl )Difficult to use (especially for less tangible deliverables)
and
Do not base percent complete on time and budget
(50% of time and 50% of budget is often not equal to 50% complete!)complete!)
Must actually measure progress (work accomplished)
Use Earned Value as a better measure of performanceUse Earned Value as a better measure of performance
Controlling and MonitoringControlling and Monitoring
C lli R
183
Resources are:
Controlling Resources
PeopleEquipmentMaterialsMaterialsFacilities
Th jThe project manager must:
Strive to hold functional managers to their commitments to provide required resourcesprovide required resourcesTrack the actual resources assigned to their projectCompare the actual resources with the resource plan
Controlling and MonitoringControlling and Monitoring
C lli C (B d )
184
Sound cost control begins with a realistic budget.
Controlling Cost (Budget)
Plan what needs to be done and then budget!Th d l b d t b d th t l !Then develop a budget based on that plan!It is a mistake to budget first and then try to make the project fit the budget without reducing scope!
Controlling and MonitoringControlling and Monitoring
Analyzing Cost (Budget): 5 Key Questions185
Analyzing Cost (Budget): 5 Key Questions
At the end of each control period ask:
1) Wh t th t l ?1) What are the actuals?What did we actually spend? (commitments treated as expended)
2) What is the plan (budget)?What did we plan to spend?
3) What are the variances? Why?How does planned cost compare with actual cost?
4) What are the trends and how do they extrapolate into the future?
5) What actions are required?5) What actions are required?
Controlling and MonitoringControlling and Monitoring
A l i C (B d )
186
Analyzing Cost (Budget)
Three ways to analyze expenditures:
Type of expenditure (labor, capital, materials)Organization (engineering operations)Organization (engineering, operations)Project component (activity, work package, subproject)
Computers can generate a variety of reports and combinations.
Controlling and MonitoringControlling and Monitoring
C A l i G h Th S C
187
Cost Analysis Graph: The S-Curve
Cumulative $
1101101009080
Plan and Budget
8070605050403020
Time1 2 3 4 5 6 7 8 9 10 11 12 13 14
2010
Controlling and MonitoringControlling and Monitoring
Money/Time: Earned Value188
Estimated TotalCost to CompleteCumulative $
TodayLine
Money/Time: Earned Value
11010090 Plan and Budget
{90807060
gActual Cost of Work Performed
O B d V i
{
60504030
Over Budget Variance$30
Earned Value
{302010
BehindScheduleVariance, 2 weeks
Earned Value(Budgeted Cost of Work Complete)
Time1 2 3 4 5 6 7 8 9 10 11 12 13 14
Controlling and MonitoringControlling and Monitoring
D fi i i f E d V l
189
Earned value integrates time performance and actual cost
Definitions of Earned Value
Earned value integrates time, performance, and actual cost information into one metric.
Definition 1: the budgeted value of work complete at a point in time.Definition 2: the value of the actual work completed pexpressed in terms of current budgeted dollars.
Overcomes problems with percent complete.Overcomes problems with percent complete.
Controlling and MonitoringControlling and Monitoring190
Status: End of Week 4Schedule
Cross Hatchshows completion
Total Budget
Task A 50 60 50
Actual CostCost
Task BTask CTask DTOTAL
5010
0110
8010
0150
7010
5135O 0 50 35
Controlling and MonitoringControlling and Monitoring191
Planned Budget, Actual Cost, and Earned Value by Week
Note: l d
Earned value for task B for Week 4 is 25 plus 10 from
PlannedBudget W1 W2 W3 W4 W5 W6 W7Task A 25 25Task B 25 25 20 Week 5 for a Total of 35.
And actual cost is 35 plus 10 from Week 5 for a
Task B 25 25 20Task C 10 TotalActualCost 30 30 45 45 150 Total of 45.Cost 30 30 45 45 150EarnedValue 25 25 35 35 120
= 30 30
overrun
Controlling and MonitoringControlling and Monitoring
Wh d f $30 f ?
192
Budget Actual Overrun
Where does overrun of $30 come from?
Task A, Weeks 1 + 2 $50 $60 $10T k B W k 3 4 $50 $80 $30
Budget Actual Overrun
Task B, Weeks 3 + 4 $50 $80 $30
=$40
less
Task B, $10 of Week 5Task B, $10 of Week 5 completed ahead of schedule in Week 4 - $10
= $30= $30
Controlling and MonitoringControlling and Monitoring193
Cumulative Note:
Earned Value Calculation
Total Budget
T k A 50 60 50
Cumulative Budget
W4ActualCost
EarnedValue
50
Note:
Actual Cost is 150 whereas E d V lTask A
Task BTask C
505010
608010
507010
506010
Earned Value is 120.
Task DTOTAL
0110
0150
5135
0120
Variance=40 Variance=30Variance=40 Variance=30
Controlling and MonitoringControlling and Monitoring
Actual expenditure (Cost of work performed to date) = $150194
Cash flow:
Actual expenditure (Cost of work performed to date) = $150
Actual expenditure $150
Planned expenditure $110
Variance (cash flow overrun) +$40Variance (cash flow overrun) +$40
Budget:
Cost of work performed to date: $150
Earned value: budgeted value of work
performed to date: $120
V i (b d t ) +$30Variance (budget overrun) +$30
$30$120
= 25% Over
Controlling and MonitoringControlling and Monitoring
Example: Estimated Cost to Completion195
Cost of remaining work exceeds plan:
Example: Estimated Cost to Completion
Variance as percent of actual: 30/150 = 25%
Actual = $150
E d l t d t $120Earned value to date: = $120
Variance, 25% = +$30
Original total budget is $135 minus earned value of $120 equals $15 to complete.
Adjusted cost to complete: $15 plus 25% = ($15 + $3.75 ) = $18.75 + $150 = $168.75
Note: The project will end over budget
Final cost = Original Budget + Variance to date + Cost to complete
Controlling and MonitoringControlling and Monitoring196
Actual $ vs Budget $ (rate of spending)
Comparisons
Actual $ vs. Budget $ (rate of spending)Actual work in place vs. Planned work in place (performance and schedule progress)Actual $ vs. Earned Value (cost/schedule/performance)Estimated cost to complete vs. Original budget (forecasted total budget)total budget)Estimated time to complete vs. Original schedule (forecasted schedule)
Controlling and MonitoringControlling and Monitoring
Estimating Cost to Completion197
What is the cost to complete Task G?
1. Planned budgeted cost
Estimating Cost to Completion
1. Planned budgeted costOriginal budgeted cost: 1 unit of cost / unit of workEstimated cost to complete:
2 units of work x 1 unit of cost = 2 cost units
2. Most recent costLast cost for 2 units: 4.1Estimated cost to complete next two units at same rate:Estimated cost to complete next two units at same rate:
4.1 cost units
3. Average costFi t 2 it 3 9 (A (3 9 4 1) / 4 2 it)First 2 units: 3.9 (Average = (3.9 + 4.1) / 4 = 2 per unit)Next 2 units: 4.1Estimated cost to complete:
2 units of work x average cost per unit =2 units of work x average cost per unit =2 units of work x 2 units of cost = 4 cost units
Controlling and MonitoringControlling and Monitoring
Estimating Cost to Completion Trend Analysis ( ti d)
198
4. Trend analysis
Week 1 Cost for G: 3 9 units
Estimating Cost to Completion Trend Analysis (continued)
Week 1 Cost for G: 3.9 units
Week 2 Cost for G: 4.1 units
Increase Week 1 to 2: 0.2 units
(5% increase Week 1 to 2 in cost per 2 units of G)
Week 3 Cost for G: Week 2 cost plus 5%
= 4.1 units + 0.2 = 4.3 units
Controlling and MonitoringControlling and Monitoring
Estimating the Total Cost for Task G199
Estimated Cost to Completion + Actual to DateE ti t d T t l C t t C l ti
Estimating the Total Cost for Task G
= Estimated Total Cost at Completion
Our assumptions about cost to completion affect our estimate of total cost atcompletionp
MostRecent Cost
AverageCost
TrendCost
OriginalEstimateCost
8.0 8.0 8.08.0
4 1 4 34 0 2.0
Actual
E t C 4.1 4.34.0 2.0
12.1 12.0 12.3 10.0
Actual to Date 3 9 + 4 1 = 8
Est. Com.
Actual to Date 3.9 + 4.1 = 8
Controlling and MonitoringControlling and Monitoring
Anticipating Control Challenges200
Anticipating Control Challenges
Control problems (challenges) result from:
Budgeting first and planning second
Poor initial planning
Everyday challenges of project management in a changing environment
Predictable types of control problems (challenges):Predictable types of control problems (challenges):
Cost
ProgressProgress
Plan
AdministrationAdministration
Controlling and MonitoringControlling and Monitoring201
Cost-Related Control Challenges
1. Accounting systems not project-oriented!
2. Delays in getting information!
3. Commitments not tracked!
4. Down payments not accounted for!4. Down payments not accounted for!
Controlling and MonitoringControlling and Monitoring
P R l d C l Ch ll
202
Progress-Related Control Challenges
Assessing progress is easier for some projects than others:
How tangible are the activities?
How easy is it to determine if quality standards are met?
How can incomplete work be measured?
50/50 rule!
Percent complete!
Rework can be an issueRework can be an issue
Controlling and MonitoringControlling and Monitoring
P R l d C l Ch ll
203
Progress-Related Control Challenges (continued)
Changes in scope (crawl)
Baseline plan (definition)
Three views of the baseline planp
Concrete plan
Rubber planRubber plan
Rational plan
Reasons for changing the baseline plang g p
a change in scope of project
a change in the environmenta change in the environment
Controlling and MonitoringControlling and Monitoring
d i i i
204
Administrative Issues
Avoid too much detail!
Focus on the future, not the past !
Manage, don’t monitor!Manage, don t monitor!
Pay attention to early warnings!
T k h i th M it i fl ti t d iTrack changes in the economy: Monitor inflation rates and price
escalation!
Controlling and MonitoringControlling and Monitoring
Causes of Cost Overruns and Schedule Slips205
Causes of Cost Overruns and Schedule Slips
Bad estimates
InflationInflation
Delayed management decisions
Poor management controlPoor management control
Changes in design (scope)
Shortage of planned resourcesg p
Force Majeure (war, riot, revolution, disaster)
Problems with suppliers
Changes in environment
Underestimate of risks
Controlling and MonitoringControlling and Monitoring
S P i i l
206
Summary: Principles
The Project Manager is like the captain of a ship.
PM must manage (not only monitor) the project rectangle:
time (schedule)( )cost (budget)resources
( f d lit )scope (performance and quality)
The control period determines how often the project’s status is dassessed.
Earned value integrates time, cost and performance.
Controlling and MonitoringControlling and Monitoring
S 5 K Q ti
207
Summary: 5 Key Questions
Key questions concerning time, cost, resources and quality of performance (scope):(scope):
1. What are the actuals?
2. What is the plan?
3. What are the variances? Why?
4. What are the trends and how do they extrapolate into the future?
5. What actions are required?q
Controlling and MonitoringControlling and Monitoring208
Summary: Types of Plans
Current operational plan
Day-to-day plan
Adjusted regularly
Goal is to match baseline plan
Baseline planBaseline plan
Approved project plan
Approaches to revisionApproaches to revision• concrete• rubber• rational
Controlling and MonitoringControlling and Monitoring
Summary: Think Ahead!209
Summary: Think Ahead!
The project manager must constantly be thinking ahead and actively managing:actively managing:
Time to completionCost to completionCost at completionQuality of performance to specifications (scope)Quality of performance to specifications (scope)
Your Turn:Your Turn:210
Controlling and Monitoring how and what to do?………………
MODULE 14: PROJECTMODULE 14: PROJECT MANAGEMENT SOFTWARE
A Word About Software & other Tools212
• Many people assume that project management is all about management software.
• That’s like saying that residential construction is all about hammers!
• Such tools will often make your work ysimpler and handle complex calculations with ease.
• However, without a solid ,understanding of PM concepts, the tools often provide an illusion of project control that does not exist.
• Learn the concepts, then the tool.
Project Management SoftwareProject Management Software213
Project Management SoftwareProject Management Software214
Project management software is a term covering many types of software
(open source and commercial) , including: h d li• scheduling,
• cost control and • budget management, • resource allocation, • collaboration software, • communication, co u cat o ,• quality management and • documentation or administration systems,
hi h d t d l ith th l it f l j twhich are used to deal with the complexity of large projects.
Link to open source project management software http://www.project-open.org
Project Management SoftwareProject Management Software
T k f j f
215
Tasks of project management software
Scheduling
One of the most common tasks is to schedule a series of events, and the complexity of this task can vary considerably depending on how p y y y p gthe tool is used. Some common challenges include:
• Events which depend on one another in different ways or dependenciesEvents which depend on one another in different ways or dependencies• Scheduling people to work on, and resources required by, the various
tasks commonly termed resource scheduling• Dealing with uncertainties in the estimates of the duration of each taskg• Arranging tasks to meet various deadlines• Juggling multiple projects simultaneously to meet a variety of
requirementsq
Project Management SoftwareProject Management Software216
Tasks of project management software
Calculating critical pathCalculating critical path
In many complex schedules, there will be a critical path, or series of events that depend on each other and whose durations directlyof events that depend on each other, and whose durations directly determine the length of the whole project (see also critical chain).
f li i (f l dSome software applications (for example, Dependency Structure Matrix solutions) can highlight these tasks, which are often a good candidate for any optimization effort.
Project Management SoftwareProject Management Software
T k f j f
217
Tasks of project management software
Providing information
Project planning software needs to provide a lot of information to various people, to justify the time spent using it. Typical p p , j y p g yprequirements might include:
• Tasks lists for people, and allocation schedules for resourcesTasks lists for people, and allocation schedules for resources• Overview information on how long tasks will take to complete• Early warning of any risks to the project• Information on workload, for planning holidays, p g y• Evidence• Historical information on how projects have progressed, and in
particular, how actual and planned performance are relatedp p p
Project Management SoftwareProject Management Software218
Approaches to project management software
• DesktopDesktop• Web-based• Personal• Single UserSingle User• Collaborative• Integrated• Non specialized• Non specialized
Your Turn:Your Turn:219
Project Management Software, what is it good for?………………
MODULE 15: PROJECT CLOSE
You’ve already seen the value of this!You ve already seen the value of this!
POST PROJECT REVIEW221
POST-PROJECT REVIEWProject Name:
Overall Evaluation of the Project What was the overall mission of the project? Provide a short description based on your understanding of the project.p j p y g p j
All in all would you say that the project was successful? Why or why not?All in all would you say that the project was successful? Why or why not?
How close was the project to meeting its scheduled completion date?How close was the project to meeting its scheduled completion date?
How close was the project to being completed within budget?
Did the project meet its final stated objectives? Why or why not?
Post-Project Review (continued)Post Project Review (continued)
Project Management Issues
222
j gDid the project have a sponsor? If so, what was his or her role during the project?
Wh t t l d t h i d i l i d t ki th j t?What tools and techniques were used in planning and tracking the project?
Did the scope of the project change after the project was underway? If so, what was the overall impact of the change of scope? How were changes approved?
How was project status communicated during the course of the project?How was project status communicated during the course of the project?
How were risks managed for the project? Were they identified ahead of time? Did any unforeseen occurrerences hinder the progress of the project?p g p j
At the end of the project, was there a formal lessons-learned process or any sort of review similar to the one used here?
Post-Project Review (continued)j ( )
Collaboration and Team Issues
223
Collaboration and Team IssuesHow effective was the overall leadership of the project? Did the project manager have the resources and support required to be as effective as she or he could be?
In general, how well did the team members collaborate? Why was this so?
Did team members work together in a single physical area or were they physically separated?Did team members work together in a single physical area or were they physically separated?
What were the primary modes of team communication? Which ones worked best? Which ones worked least well?
Were all team members available at the times they were needed for project work or status meetings? What impact did this have on the project?
Were all stakeholders and subject matter experts available to answer questions when needed? What impact did this have on the project?
Post-Project Review (continued)Post Project Review (continued)
Technology and Knowledge Management Issues
224
gy g gHow did technology help (or hinder) the progress of the project?
Were any new technologiy tools introduced for this project?
Was any kind of project management software, such as Microsoft Project, used for the project? What are the ways it was used (for example, scheduling, reporting, and cost reporting).
What other tools (word-processors, spreadsheets, presentation software, or diagramming tools) were used in the project?
Was the project team able to obtain adequate advice and technical support for the technology tools used in the project? How could it improve?
Are there any areas about which you would like to learn more in order to make you more effective in working on your next project?Are there any areas about which you would like to learn more in order to make you more effective in working on your next project? What resources are available for obtaining that knowledge or skill?
Participant Name:
Participant Signature:
Evaluation Date:
Stakeholders Report/CelebrationStakeholders Report/Celebration
C i t R lt225
Communicate Results
Pinpoint Successespo t Successes
Propose Maintenance/Corrective Measures if neededMeasures if needed
share contributing success factorspresent plans for corrective actionp p
“Sharpen the Saw” for the future Project Best PracticesProject Best Practices
Celebrate Successes!!!!
Your Turn:Your Turn:226
Project Close, how to mange it?………………
MODULE 16: PMI’S PROJECTMODULE 16: PMI S PROJECT MANAGEMENT MATURITY MODEL
Project Management Maturity Model (PMMM)Project Management Maturity Model (PMMM)
PMI d fi i t th “S t ti d t i d i t f
228
PMI defines process improvement as the “Systematic and sustained improvement of processes and thus the products they produce.”
The Five Levels of PMMM:
Level 1—Initial ProcessLevel 1—Initial ProcessProject management practices are ad hoc and inconsistent within organization.
Level 2—Repeatable ProcessProject management practices are commonly understood and followed but mostProject management practices are commonly understood and followed, but most knowledge is commonly understood rather than documented.
Level 3—Defined ProcessProject methodology usually in place, with written guidelines for project j gy y p g p jdeliverables and processes.
Level 4—Managed ProcessSystematic collection of project performance data to set baselines for
f lperformance goals.
Level 5—OptimizationProactive approach applying metrics and best practices to achieve highest level of project excellence.project excellence.
Rewards of PMMMRewards of PMMM229
The promise of continuous process improvement through
repeatable processes, benchmarking, and optimization.
To break the triple constraint and to be:
F t !! Ch !!Faster!! Cheaper!!
Gooder oops Better!!!Gooder.. oops, Better!!!
Your Turn:Your Turn:230
What is the PMMM?………………
MODULE 17: THE PROJECT TEAM
Team work and team work modelsTeam work and team work models232
Team work and team work modelsTeam work and team work models
Wh i ?
233
What is a team ?
‚group’ ‚team’
Term is derived from sociology Term is derived from psychology
Major task: (identifying) clearing relationships Major task: Problem solving
α - Ω hierarchy No hierarchy
Friendship Comrades (high degree of reliability)p (high degree of reliability)
Lots of emotions Few emotions
Team work and team work modelsTeam work and team work models
4 Stages of team development234
S 4
As below As below + High flexibility+ Appropriate leadership
4 Stages of team development
Stage 4Mature team
+ Appropriate leadership+ Maximum use of abilities+ Developing priorities+ Needs (incl. social) considered
Stage 3Consolidating team
As below + Methodological working+ Agreed procedures+ Established ground/basic rulesg /
Stage 2Experimenting team
Experimentation takes places. Risky issues are debated/discussed. Wider options are considered. Personal feelings are raised. Concern for others is shown.
Stage 1Undeveloped team
Feelings not dealt with. Workplace is for work only. Established lines prevail. Nobody ‘rocks the boat’. Poor listening. Weaknesses are covered up. Unclear objectives. Low involvement in planning. Bureaucracy. Boss makes most of the decisions.
Team work and team work modelsTeam work and team work models
S f h d l / h d
235
Belbin‘s team model
Some of the most common team models/approaches used
Patrick Lencioni, dysfunctional teamsMyers-Briggs Type Indicator (MBTI)
Team work and team work modelsTeam work and team work models
Description
236
Description
Based on the saying, «no one is perfect but a team can be», the Belbin method is a rational and rigorous tool that allows individuals and groups to reach their fulla rational and rigorous tool that allows individuals and groups to reach their full potential.
After identifying the roles of each individual, you increase the efficiency of the team by changing its composition or the way it works internally.y g g p y y
Objectives
To made a rapid diagnosis of the business, the team and the individual according to the Belbin method.
To enable each individual to develop and make full use of his potential within his p pworking team.
To encourage cohesion and communication and to promote team spirit.
Team work and team work modelsTeam work and team work models
Th B lbi th d i b d 3 ti i
237
• The self-perception form: determines the preferred roles, the roles that
The Belbin method is based on 3 questionnaires:
e se pe cept o o dete es t e p e e ed o es, t e o es t atcan be carried out and the roles to be avoided.
• The observers’ form: through appraisals by at least 4 observers, this g pp y ,questionnaire goes beyond the subjective nature of the self-perception report.
•• The job observation form: identifies the main personal characteristics required to fulfill the target role.
Team work and team work modelsTeam work and team work models238
Team work and team work modelsTeam work and team work models239
Inattention
Patrick Lencioni’s ‘approach to team work’
Inattention to
RESULTS
Avoidance of
Dysfunctional teams show typically the following elements in an ascending order and in different degrees of severeness. Avoidance of
ACCOUNTABILITY
Lack of With the help of a questionnaire and some guided group
COMMITMENT
Fear of CONFLICT
work/consultancy the team can determine the weak elements an then act accordingly.
CONFLICT
Absence of TRUST
Team work and team work modelsTeam work and team work models240
The Myers-Briggs Type Indicator (MBTI) assessment is a psychometric
questionnaire designed to identify certain psychological differences according q g y p y g g
to the typological theories of Carl Gustav Jung.
Applications of the MBTIApplications of the MBTI
The indicator is frequently used in the areas of career counseling, pedagogy,
group dynamics, employee training, leadership training, life coaching,
executive coaching, marriage counseling, Workers' compensation claims and
personal development.
Team work and team work modelsTeam work and team work models241
The 16 personality types of the Myers-Briggs Type Indicator® instrument are listed here as they are often shown in what is called a “type
Favorite world: Do you prefer to focus on the outer world or on your own inner
they are often shown in what is called a type table.”
world? This is called Extraversion (E) or Introversion (I).Information: Do you prefer to focus on the basic information you take in or do you prefer to interpret and add meaning? This is called Sensing (S) or Intuition (N).Decisions: When making decisions do you prefer to first look at logic andDecisions: When making decisions, do you prefer to first look at logic and consistency or first look at the people and special circumstances? This is called Thinking (T) or Feeling (F).Structure: In dealing with the outside world, do you prefer to get things decided or do you prefer to stay open to new information and options? This is called Judging (J) or Perceiving (P).Your Personality Type: When you decide on your preference in each category, you have your own personality type which can be expressed as a code with four lettershave your own personality type, which can be expressed as a code with four letters.
Your Turn: Using the questionnaire…Your Turn: Using the questionnaire…242
Use the provided questionnaire andquestionnaire and
evaluate your…
Moving up into ManagementMoving up into Management243
For employees who are promoted into management,
FATAL ASSUMPTIONS
Success as an individual contributor will translate into management success!promoted into management,
many anticipate new avenues for professional growth and leadership
translate into management success!
It's out of my control-someone else could and should fix this!growth and leadership.
But an increasing number of b th d
Being the expert is the most important factor for my credibility
managers - both new and experienced - report facing many obstacles when making
It’s the rational and logical approach or solution that counts!
a complete transition into management roles.
The people I manage are just like me in their thinking, expectations, priorities and goals!
Competent people do not need help!Competent people do not need help!
Project Structure and Organization…Project Structure and Organization…244
Organization is:
To Accomplish Objectives
Structuring
People jPeople
Project Structure and Organization…Project Structure and Organization…
Division of Laborol245
Specialization Functional processesLi t ffy
-Fa
yo
Line vs. staff
Scalar Processes
Theo
ry
Hierarchical structureChain of commandUnity of controlA th it d ibilitem
ent
Authority and responsibilitySpan of control
Organizational StructureMan
ag
Around objectives and activities, not individualsTable of organization (chart)Written position descriptionC
lass
ic
Written position descriptionC
Project Structure and Organization…Project Structure and Organization…246
Functional Organization
zati
ons
orga
niz
Projectized Organization
ypes
of
maj
or t
y
Matrix Organization
Thre
e
Project Structure and OrganizationProject Structure and Organization247
MatrixFunctional
Weak Matrix Balanced Matrix
Strong Matrix
Organization Type
Project Characteristics
Projectized
nd is
t
Project Manager’s Authority
Percent of j
— Limited Low to Moderate
Moderate to
High
High to Almost Total
ctur
e an
proj
ects
Project Personnel
Assigned Full-time to Project
Work
— 0-25% 25-50 % 50-85%
85-100%
nal s
tru
nce
on p
Common Titles for Project Manger’s
Project Manager’s Role
—
—
Part-Time Full-Time
Full-Time Full-Time
Project Manager
Project Manager/ Project
ManagerProject
Manageraniz
atio
infl
uen
Project Manger s Role
Project Management Administrative Staff Part-time — Part-Time Full-Time Full-time
g/ Project Officer
g /Project
Coordinator
Manager Manager
Org
a
Reference: Adapted from Project Management Body of Knowledge, Project Management Institute, 1996.
Your Turn:Your Turn:248
Team, Structure and Organization, what and why is it so important?
…………
MODULE 18: PROJECTMODULE 18: PROJECT COMMUNICATIONS
Communication Made Simple
The Two Floor Rule250
The Two-Floor Rule
Every stakeholder should receive information at just the right level of detail for them!
High-level managers won’t want to see all the gory details of the g g g yproject!
Your team members need to see a great deal more!Your team members need to see a great deal more!
If your level of reporting is appropriate, and one of your stakeholders steps into the elevator and asks about the status ofstakeholders steps into the elevator and asks about the status of the project, you should be able to brief him or her by the time the elevator stops two floors away!
Communication Plan251
Communication Format Frequency DistributionTeam Briefing Restricted Intranet Daily at 9:00 Team and stakeholders
with access to secure j t i fproject info area
Weekly Web Bulletin Internal Intranet Weekly Team, sponsor, senior management
Technical Incident Email Immediately after Webmaster, IT Report Incident DepartmentBudget and Schedule Detail
Spreadsheets and Detailed Gantt Chart
Bi-Weekly Sponsor, Senior Management
Accomplishments and Email and Intranet Weekly All internal stakeholderscco p s e ts a dSetbacks
a a d t a et ee y te a sta e o de s
Schedule Milestones Email and Intranet Weekly All internal stakeholders
Cost to Date Email and Intranet Weekly All internal stakeholdersCost-to-Date Milestones
Email and Intranet Weekly All internal stakeholders
Current Top 5 Risks Email and Intranet Weekly All internal stakeholders
Some Simple ToolsSome Simple Tools252
Accomplishments and Setbacks for Period Starting 2/9/04 – 2/15/04
Accomplishments for
Period Setbacks for Period
Some Simple Tools (continued)Some Simple Tools (continued)
253
Schedule Milestones as of 2/15/2004
ID Milestone Scheduled Actual VarianceID Milestone Scheduled Completion
Actual Completion
Variance in Days
Some Simple Tools (continued)Some Simple Tools (continued)
254
Cost-to-Date Milestones as of 2/15/20042/15/2004
ID Milestone Scheduled Cost to Date
Actual Cost to Date
Cost-to-Date VarianceDate Date Variance
Some Simple Tools (continued)Some Simple Tools (continued)
255
Top Five Risks as of 2/15/2004
Rank/Previous
Rank
Risk Status Activities This Period
Activities Planned for Next PeriodRank Next Period
And Don’t Forget…And Don t Forget…
Example of a Completed Priority Matrix for a Construction Project
256
Constraint 1 2 3 Measurement
TimeBuilding must be completed by October 31 of this year to accommodate corporate move
Example of a Completed Priority Matrix for a Construction Project
accommodate corporate move.
Cost Costs for the project must not exceed $22.5 million.+
Changes to either are significant!
Project Reporting to Top ManagementVi l f P j t St t R iVisuals for a Project Status ReviewInformation Requirements of Top Management
257
Information Requirements of Top Management
A Wh t i th j t b k d?Overview: Schedule & Cost-2P j t T 3A. What is the project background?
Project Appraisal-5
Project Terms-3Organization-4
Project Appraisal 5Major Milestones-6B. What does our “Customer” think?
Schedule Status-7R P f 8Resource Performance-8Value of Work Accomplished-9
C. What do our management systems say?
C C i i l P bl 10Current Critical Problems-10Anticipated Critical Problems-11
D. What are the critical problems?
Reporting…Reporting…
Overview258
S O N D J F M A M J J A S O N D J F M A
Overview
SCHEDULE:
COST:
P R O J E C T
University Computer LabUniversity Computer LabSchedule StatusCost StatusMeeting Date
Reporting…Reporting…
T
259
Description
Terms…
Under signed contract (#123-4) with university to design, assemble, install and test hardware and software for university computer lab.
TTerms
Cost $811.0 K + Incentive Fee
545.3 K Direct Cost
105 6 K Indirect (Overhead)105.6 K Indirect (Overhead)
160.1 K Projected Profit
40.55 K I. F.* 5 percent of Budgeted Cost for
Performance Quality and Target DeliveryPerformance Quality and Target Delivery
( -1 percent per Week Late Delivery)
200.6 K Max Profit including Incentive Fee
*I. F. = Incentive Fee
Reporting…Reporting…260
B. BULB, FINANCIAL
J. BROWNPROJECT MANAGER
Project
Organization
J. RAPPS, MGT. SYS.
S. MATZ, MGR.SOFTWARESYSTEMS
R. RACE, MGR.DESIGN
E. SELLER, MGR.MARKETING F. FITS, MGR
ASSEMBLY
B. BLAT, MGR.INSTALLATION
R. WATTS, MGRTEST
O. CHECK, MGRQ.C.
R. CLEAN, DIR.UNIVERSITY
COMPUTER LABCustomer
S. ADAMSDEPUTY
DIRECTOR
J. JONNS, MGR.DEVELOPMENT
N. NESS, MGR.SYSTEMS
P. PETERS, MGR.APPLICATIONS
Reporting…Reporting…261
Major Milestones
S O N D J F M A M J J A S O N D J F M A
Major Milestones
Start
Design review
Spec. (Final)
Start Procurement
Finish Test PartsAllParts available
Finish AssemblyFinish Assembly
Ship
Install
Test
Approval
Reporting…Reporting…
S h d l
262
Remarks
Schedule Status
S O N D J F M A M J J A S O N D J F M A
ScheduleStatus
Software Systems
Redesignof
Test equip.Design
P
ModemsDelayed
Procure-ment
Assembly
Installation
Q.C.
Test
Reporting…Reporting…263
Remarks
Resource Performance
J F M A M J J A S O N D
Resource Performance
Cost Overrun ($30K)
00)
1000
800
900
811841Target Cost
Projected Cost @ Comp. ($841K)
Dol
lars
(00 800
600
700
811
700680 Budget
Actual Cost
670 Earned Value
500
er
100
alen
t M
anpo
we
80
60
40
Planned
Equi
va
20
Actual
Reporting…Reporting…
Current Problems264
TestingProblem: System test equipment fails to measure telecom output signals at the
required sensitivity
Current Problems
required sensitivity.Impact: Schedule may slip by two weeks because of redesign of test
equipment.Resolution: Review test criteria with customer with the objective of relaxing
specifications.Responsibility: J. Powers, Systems Engineer
Receiver AvailabilityReceiver Availability
Problem: Customer furnished modems are currently one week late. Impact: Item is critical and will cause day-by-day slippage
in end item delivery starting first of Septemberin end item delivery starting first of September.Resolution: Support receiver manufacturer with our engineer to solve interface
problems.Responsibility: F. Funk, Design Engineer
Reporting…Reporting…
Anticipated Problem(s)265
Cost Overrun: Redesign of Test Equipment
Anticipated Problem(s)
Problem: Design changes are resulting in projected cost overrun of $30K
Impact: Loss of part of incentive fee
Resolution: Tighter configuration control and offset from expected under-run
from power protection equipment
Responsibility: J. Brown, Project Manager
Installation
Problem: Additional slippage in other projects will cause resource stacking problems within installationproblems within installation
Impact: Compound project slippage and possible loss of incentive fee
Resolution: Reschedule conflicting projects or acquire additional manpower
Responsibility: B Blat Director InstallationResponsibility: B. Blat, Director, Installation
Your Turn:Your Turn:266
What has to be communicated?………………
MODULE 19: ADDITIONAL INTERESTING INFORMATION
What makes a good Project Manager?What makes a good Project Manager?268
MethodologicalMethodological competency
Technical competency
Personality competency
Correct handling of a
task/job requires ...
The text book answer…
S i l tSocial competency
Motivation…Motivation…269
Who needs motivation?
26%
55%
Employees not engaged in their job
Employees actively disengaged in their jobs55%
19%
in their jobs
Employee engaged in their jobs
Source: Gallup Management Journal, 2001
Amazing Information…Amazing Information…
2 h i th ti d h f i f ti
270
2 hours is the average time per day managers search for information.50 % of the information has no value to the managers (IT managers were the least likely to feel the information they receive has value-despite spending the most time trying to find it.59 % of managers who say they miss out on information that might be valuable to them almost every day because it exists somewhere else in y ythe company-and they just can't find it. Part of the problem may lie in the way managers are gathering and storing all that information. Only 16% of respondents said they use a collaborative workplace toolOnly 16% of respondents said they use a collaborative workplace tool, such as their company's Intranet.
Source PMI 2007
The top 9 causes for project failureThe top 9 causes for project failure
Source PMI 2007
271
4,31 P i ti
Source PMI 2007
28,05,2
4,8
4,4,
1. Poor commuincation
2. Insufficient resource planning
3. Unrealistic schedules
6,74. Poor project requirements
5. Lack of stakeholder buy in
9,8
6. Undefined project success/clusre criteria
7. Unrealistic budgets
8. Insufficient or non risk planning18,0
13,2
8. Insufficient or non risk planning
9. Lack of control/change process
Project Management Concepts/ApproachesProject Management Concepts/Approaches
Prince 2272
Prince 2History
PRINCE2 i d i d f th li PRINCE j t t th d hi hPRINCE2 is derived from the earlier PRINCE project management method, which
was initially developed in 1989 by the Central Computer and Telecommunications
Agency (CCTA) as a UK Government standard for information systems (IT) project ge cy (CC ) as a U Go e e t sta da d o o at o syste s ( ) p oject
management; however, it soon became regularly applied outside the purely IT
environment.
PRINCE2 was released in 1996 as a generic project management method.
PRINCE2 has become increasingly popular and is now a de facto standard for
project management in the UK. Its use has spread beyond the UK to more than 50
other countries. The most current revision was released in 2009 by the Office of
Government Commerce.
Project Management Concepts/ApproachesProject Management Concepts/Approaches
Prince 2273
Prince 2
Description of the PRINCE2 method: The graphic below shows the processes involved in managing a PRINCE2 project and how they link with each other, creating the normal content of a PRINCE2 project.
Project Management Concepts/ApproachesProject Management Concepts/Approaches
Prince 2274
Prince 2
Total Quality Management (TQM)Total Quality Management (TQM)275
W. Edwards Deming made the ‘Shewhart’ cycle as a TQM model/tool popular:
Plan: Design or revise business process components to improve results
Do: Implement the plan and measure its performanceits performance
Check: Assess the measurements and report the results to decision makers
Act: Decide on changes needed to improve the process
Action Plan: Plan – Do- Check - ActAction Plan: Plan Do Check Act
U i th ‘Sh h t’ l t b ild A ti Pl
276
Action PlanAction Plan
Using the ‘Shewhart’ cycle to build an Action Plan
When should it be completed
To whom to report
Stage/Degree of Progress
With whom to cooperate/work together
Who will Plan, Do, Check, Act
ActivityNr.
P
When should it be completed
To whom to report
Stage/Degree of Progress
With whom to cooperate/work together
Who will Plan, Do, Check, Act
ActivityNr.
P
P
DAC
1
P
DAC
1
PDAC
2
PDAC
2
ACT
CHECK
PLANDO
APCD
P = Action Planned; D = Start of Action/Intervention/Do; C = Check if suitable/Control;
A = Act on Activity Achieved/Measure integrated or corrective action if not completed/achieved
Action Plans: PCM Operational PlanAction Plans: PCM Operational Plan
An example for an Operational Plan’ as it is used in PCM277
Plan of Operation for Project name: Monitoring symbols: Date prepared: Project number: Date adjusted:Partner organisation(s): By:
An example for an ‚Operational Plan as it is used in PCM
g ( ) yResult 0: Project management activities Time in quarters Resources required
ActivitiesObjectively Verifiable Indicators
Responsibilities 1/99 2/99 3/99 4/99 1/2000 2/2000 3/2000 4/2000 Man-power
Finances, partner
Finances, other Remarks
R lt 0 b t t l 0Result 0 sub-total 0
PCM
Some important definitionsSome important definitions278
strat·e·gystrat·e·gy (stràt¹e-jê) nounplural strat·e·gies1. a. The science and art of using all the forces of a nation to execute approved plans as effectively as possible during peace or war b The science and art of military command as applied to the overall planning and conduct of large scale combat operationswar. b. The science and art of military command as applied to the overall planning and conduct of large-scale combat operations.2. A plan of action resulting from strategy or intended to accomplish a specific goal. See synonyms at plan.3. The art or skill of using stratagems in endeavors such as politics and business.
[French stratégie, from Greek stratêgia, office of a general, from stratêgos, general. See stratagem.]
strategical - adjectivebehaving: tactical, strategicalcunning: tactical, strategical, deep-laid, well-plannedwarlike: operational, strategical, tactical[1]warlike: operational, strategical, tactical[1]
strat·a·gemstrat·a·gem (stràt¹e-jem) noun1. A military maneuver designed to deceive or surprise an enemy.2 A clever often underhand scheme for achieving an objective See synonyms at artifice2. A clever, often underhand scheme for achieving an objective. See synonyms at artifice.[Middle English, from Old French stratageme, from Old Italian stratagemma, from Latin stratêgêma, from Greek, from stratêgein, to be a general, from stratêgos, general : stratos, army + agein, to lead.]
Some important definitionsSome important definitions
plan
279
planplan (plàn) noun1. A scheme, program, or method worked out beforehand for the accomplishment of an objective: a plan of attack.2. A proposed or tentative project or course of action: had no plans for the evening.3. A systematic arrangement of important parts; an outline or a sketch: the plan of a story.4 A d i di d t l h i th t t t f thi4. A drawing or diagram made to scale showing the structure or arrangement of something.5. In perspective rendering, one of several imaginary planes perpendicular to the line of vision between the viewer and the object being depicted.
verbplanned, plan·ning, plans verb, transitive1. To formulate a scheme or program for the accomplishment, enactment, or attainment of: plan a campaign.2. To have as a specific aim or purpose; intend: They plan to buy a house.3. To draw or make a graphic representation of.verb, intransitiveverb, intransitiveTo make plans.
[French, alteration (influenced by plan, flat surface). See plain, of plant, ground plan, map (from planter, to plant, from Latin plantâre, from planta, sole of the foot).]
plan¹ner noun— plan¹ner noun
Synonyms: plan, blueprint, design, project, scheme, strategy. The central meaning shared by these nouns is “a method or program in accordance with which something is to be done or accomplished”: has no vacation plans; a blueprint for the reorganization of the company; social conventions that are a product of human design; an urban-renewal project; a new scheme for power conservation; a strategy for capturing a major market share.
Strategies…Strategies…280
How to do the Analysis of Alternatives/Strategies
Step 1 Identify Objectives you do not want to pursue. Those thatStep 1 Identify Objectives you do not want to pursue. Those that are not desirable or achievable.
Step 2 Identify differing ‘Means and Ends’ ladders as possibleStep 2 Identify differing Means and Ends ladders, as possible alternative project strategies or project components.
PCM
Strategies…Strategies…
Step 3: Assess which Alternative/Strategy in your opinion
281
Step 3: Assess which Alternative/Strategy in your opinion represents an option to have a successful project by using criteria such as:
Expected contribution to key policy objectives/development prioritiesBenefits to Target GroupsComplementary with other ongoing or planned interventionsLocal ability to meet recurrent costsFinancial and economic cost – benefitContribution to institutional capacity buildingTechnical feasibilitySocial/Environmental impact
You might expand the list with e.g. : time horizon, sustainability and other relevant criteria
PCM
Strategies…Strategies…
Sample matrix282
Assessment Matrix (ad criteria if necessary)
Weighing factor
%
Politically acceptable
Economically efficient/effective (national
Priority of the Target
Group
Follow-up costs/
additional costs
Gender impact
Environ-mental impact
Sample matrix
necessary) (national level)
costs
Alternative/Strategy
AA
Alternative/Strategy
B
Alternative/Alternative/Strategy
C
Sum
Assessment Symbol
+, ++,+++ ; -, --, ---
PCM
Some times misinterpreted…Some times misinterpreted…283
A simple way to distinguish among effectiveness, efficacy and efficiency:
Efficiency: doing the "right" things
Effectiveness: getting things doneg g g
Effectivity: a level of getting things done
Efficacy: Doing things "right"
Sustainability is a characteristic of a process or state that can be maintained at a certain level indefinitely.
Efficacy: Doing things right
be maintained at a certain level indefinitely.
Ignorance…Ignorance…284
Problems known
An I b
to management 4 %
Problems known Iceberg of Ignorance
to managers 9 %
Problems known to supervisors 74 %
Problems known to front line staff 100%
Todays PM quality needs…Todays PM quality needs…285
The superiorThe superior Project Manger…
The Ideal Project ManagerThe Ideal Project Manager286
T t f /t k tiAge
Ascetic
What managers should do/have/be
S i l tCommunication competency
Team-orientationSelf-steering
Cost consciousnessTo transfer/take action
F ilEthics
Civil courageParticipative leadership
Capability to handle conflictsSocial competency
Ch t tProject management experience
Being open towards information technologyAuthoritarian leadership
LoyaltyFamily
-40,0 -20,0 0,0 20,0 40,0 60,0
StrategyEntrepreneurship
VisionChange management competency
, , , , , ,
Ten critical factors for project successTen critical factors for project success287
1) PROJECT MISSION: A clear sense of direction with clear initial goals
2) TOP MANAGEMENT SUPPORT: A willingness and ability to provide resources, authority
and influenceand influence
3) PROJECT/SCHEDULE & PLAN: A detailed specification and schedule for project
implementation
4) CLIENT CONSULTATION Ad t i ti lt ti d ti li t i t4) CLIENT CONSULTATION: Adequate communication, consultation and active listening to
and with the client.
5) PERSONNEL: Necessary personnel were selected, recruited and trained.
6) TECHNICAL TASKS: Required technologies and expertise were available.
7) CLIENT ACCEPTANCE: Final project was sold to the end user.
8) MONITORING & FEEDBACK: Provision of comprehensive information at each ) p
implementation stage.
9) TROUBLESHOOTING: An ability to handle unexpected crises and plan deviations.
Ten critical factors for project successTen critical factors for project success
The 10 CSF’s their sequence and interdependence288
The 10 CSF s, their sequence and interdependence
Some simple but useful check‘sSome simple but useful check s
Ch kli j h i i
289
Checklist project characteristicsCheck whether your project is really a project…
Is there a project specific organization?Is there a clearly defined starting and ending point?Is there a clear conceptual project formulation?Is the assignment of tasks complex?
h l l l ‘f d ’ i hIs there a clearly spelt out ‘form and content’ in the target (description)?
If you can at least answer three questions with a solid YES, then you are on the safe side!
Some simple but useful check‘sSome simple but useful check s
A d f k f k
290
A good frame work for team work
Good team compositionCo-operative working relationshipGive and take relationship (being able to make good compromises)Give and take relationship (being able to make good compromises)Jointly defined and accepted target(s)Joint description and definition of tasks and jobsp jJointly developed ‚laws of the game‘Good purposeful communication between the team members
If you can at least answer three questions with a solid YES, then you are on the safe side!
Some simple but useful check‘sSome simple but useful check s291
Is the target definition un-ambigious and complete
Yes Partially No
Target establishment was done ‚three dimensionally‘(Target content; Target degree; Target time)
Target is clear and traceableg
Target is measurable
Target is complete (target system and hierachy)
Target is unambigious
Target is realistically achieveable
Target is accepted by all‘Target is accepted by ‚all‘
Target has been re-confirmed with ‚donor/contractor‘
Target is written downTarget is written down
Some simple but useful check‘sSome simple but useful check s292
Has your project been planned holistically and or a holistic approach
CONTEXT LEVEL Yes Partially No
Project specific organization
Process and task responsibilities are clearly defined and assigned to specific staff
Structured action
Systematic planning
Continuous monitoring
Consistent cause analysis
Comprehensive Information Management
SOCIAL LEVEL Y P ti ll NSOCIAL LEVEL Yes Partially No
Getting acceptance for the project(work)
Confidence building amongst working partners/team etc.
Active involvement of ALL (stakeholders project team etc ) into the projectActive involvement of ALL (stakeholders, project team etc.) into the project
Participative leadership
Strengthening of personal responsibility
Increasing/facilitating motivationg/ g
MODULE 20: WHAT’S NEXT?
Personal Action PlanPersonal Action Plan
Thi l i l d d h i i h l
294
This plan is your plan and you need not share it with anyone else in the workshop.
However, find a colleague with whom you can share your plan.
Make this “Project Management In the First Person” and set out to put in place the steps you listed to meet your stated goals.
Lots of success in the future!!
Personal Action PlanPersonal Action Plan
Personal Self E al ation and Action Plan for Follo Up after This Workshop
295
Personal Self-Evaluation and Action Plan for Follow-Up after This WorkshopThese are the knowledge areas and skills that I already knew and had reinforced by this workshop.
Th th k l d d kill th t t th t I ill bThese are the knowledge areas and skills that were new to me that I will be able to use in my project work in the future.
These are the knowledge areas and skills introduced in the workshop on which I might need a refresher to use comfortably.g y
Personal Action Plan (continued)Personal Action Plan (continued)
Th h k l d d kill h d (
296
These are the knowledge areas and skills that were not covered (or not covered in sufficient detail), but about which I would like to learn more.
These are the steps I plan to take immediately.
These are the steps I want to take within the next six months
These are goals related to project management that I want to achieve within hthe next two years.
MODULE 21: BIBLIOGRAPHY
BibliographyBibliography
• Adams John R and Campbell Bryan Roles and Responsibilities of the Project Manager 4th Edition
298
• Adams, John R., and Campbell, Bryan, Roles and Responsibilities of the Project Manager, 4th Edition, Project Management Institute, 1990
• Baker, Sunny and Kim, The Complete Idiot's Guide to Project Management, New York, NY: Alpha Books, 1998.
• Bennatan E M On Time Within Budget: Software Project Management Practices and Techniques 3rd• Bennatan, E.M, On Time Within Budget: Software Project Management Practices and Techniques, 3rd Edition, New York, Wiley. 2000.
• Brooks, Fredrick. The Mythical Man-Month. Addison Wesley. 1995. • DeWeaver, Mary F. and Gillespie, Lori C., Real-World Project Management: New Approaches for
Adapting to Change and Uncertainty New York: Quality Resources 1997Adapting to Change and Uncertainty. New York: Quality Resources, 1997.• Dinsmore, Paul C., Human Factors in Project Management. New York: AMACOM, 1990.• Doyle, Michael and Straus, David, How to Make Meetings Work, New York: Jove Books, 1982.• Greer, Michael, The Manager's Pocket Guide to Project Management, Amherst, MA: HRD Press, , , g j g , , ,
1999.• Greer, Michael, The Project Manager's Partner: A Step-by-Step Guide to Project Management,
Amherst, MA: HRD Press, 1996.• Haynes, Marion E., Project Management. Crisp Publications, 1989. y , , j g p ,• Laufer, Alexander and Hoffman, Edward J., Project Management Success Stories: Lessons of Project
Leadership, New York, Wiley. 2000.• Lewis, James P., Fundamentals of Project Management. New York: AMACOM, 1997.
Lock Dennis Project Management (Sixth Edition) New York: Wiley 1996• Lock, Dennis, Project Management (Sixth Edition). New York: Wiley, 1996.
Bibliography
• Martin Paula and Tate Karen Getting Started in Project Management New York Wiley 2001
299
• Martin, Paula and Tate, Karen. Getting Started in Project Management. New York, Wiley, 2001.• Meredith, Jack R. and Mantel, Jr., Samuel J., Project Management: A Managerial Approach. 5th
Edition. New York. Wiley. 2003.• Penner, Donald. The Project Manager’s Survival Guide. Battelle Press, 1994. , j g ,• Peters, Tom, Reinventing Work: The Project 50: Fifty Ways to Transform Every "Task" Into a Project
That Matters. New York. Alfred A. Knopf, 1999.• Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK
Guide) 2000 Edition 2001Guide) -- 2000 Edition, 2001.• Roberts, W. Leadership Secrets of Attila the Hun. Warner Books, 1987. • Schrage, Michael. Shared Minds: The New Technologies of Collaboration. New York: Random
House. 1990. • Thomsett, R. People and Project Management. Yourdon Press, 1980. • Verzuh, Eric. The Fast Forward MBA in Project Management: Quick Tips, Speedy Solutions, and
Cutting-Edge Ideas. New York, Wiley. 1999.• Wideman, R. Max (Editor). Project and Program Risk Management: A Guide to Managing Project
Risks and Opportunities. Project Management Institute, 1992. • Wysocki, Robert K. et al, Building Effective Project Teams. New York: Wiley, 2001. • Wysocki Robert K et al Effective Project Management New York: Wiley 1995Wysocki, Robert K. et al, Effective Project Management. New York: Wiley, 1995.
NOT A MODULE WHAT OTHERS DONOT A MODULE: WHAT OTHERS DOEXAMPLE ILO/UN/WB
Project IDENTIFICATIONProject IDENTIFICATION
JOINT BORROWER (CAS) /BANK (PCD) INVOLVEMENT
301
JOINT BORROWER (CAS) /BANK (PCD) INVOLVEMENT
SOURCES
BANK COUNTRY / SECTOR WORKBANK COUNTRY / SECTOR WORK
COUNTRY OFFICES
PRIOR PROJECTSPRIOR PROJECTS
MULTILATERAL / BILATERAL AGENCIES
ILO/UN/WB
Project IDENTIFICATIONProject IDENTIFICATION 302
JOINT BORROWER / BANK INVOLVEMENT
PROVIDES OUTLINE OF PROJECT
BENEFICIARIES
ALTERNATIVESALTERNATIVES
ISSUES
PROCESSING REQUIREMENTS
ILO/UN/WB
Project PREPARATIONProject PREPARATION303
RESPONSIBILITY OF BORROWER
AVAILABLE ASSISTANCE (TECHNICAL/FINANCIAL)BORROWER (own resources)
BANKPREVIOUS LOANS (technical assistance)PREVIOUS LOANS (technical assistance)RETROACTIVE FINANCING
PROJECT PREPARATION FACILITY
TECHNICAL ASSISTANCE LOANSENGINEERING LOANS
MULTILATERAL/BILATERAL AGENCIES (e.g. Grants from donors: USAID, Japan, etc.)
ILO/UN/WB
Project PREPARATIONProject PREPARATION304
STUDIES (TECHNICAL, SOCIOLOGICAL, ENVIRONMENTAL, FINANCIAL)
TASK (SURVEYS MAPPING)TASK (SURVEYS, MAPPING)
FINAL DESIGNS, BIDDING DOCUMENTS
STAFFING AND TRAINING
OFFICE EQUIPMENT, VEHICLESOFFICE EQUIPMENT, VEHICLES
ILO/UN/WB
Project APPRAISALProject APPRAISAL305
RESPONSIBILITY OF BANKMULTI-DISCIPLINARY TEAM (Field)PROJECT APPRAISAL DOCUMENT (PAD)PROJECT APPRAISAL DOCUMENT (PAD)
ECONOMIC ANALYSISBENEFIT TO COUNTRYPOVERTY ALLEVIATION
TECHNICALREVIEW OF DESIGNS, COST ESTIMATESIMPLEMENTATION SCHEDULE
ILO/UN/WB
Project APPRAISALProject APPRAISAL306
INSTITUTIONALCAPABILITY TO IMPLEMENT PROJECTTRAINING STAFF NEEDSTRAINING, STAFF NEEDS
FINANCIALPROJECT FINANCIAL VIABILITY
SOCIOLOGICALSOCIOLOGICALBENEFICIARIES
ENVIRONMENTAL
ILO/UN/WB
NEGOTIATION /BOARD PRESENTATIONBOARD PRESENTATION
307
PREPARATION OF LEGAL AGREEMENT
COVENANTS / CONDITIONALITIESCOVENANTS / CONDITIONALITIESSCHEDULES
PRESENTATION TO EXECUTIVE DIRECTORS
SIGNING
EFFECTIVENESS
ADVANCE CONTRACTING / RETROACTIVE FINANCING
ILO/UN/WB
Implementation/SupervisionImplementation/Supervision308
IMPLEMENTATION IS RESPONSIBILITY OF BORROWER
BANK RESPONSIBILITYBANK RESPONSIBILITY
MONITOR PROGRESS
ADVISE
ENSURE LOAN PROCEEDS USED FOR PURPOSE INTENDED
ENSURE PROCUREMENT IS ECONOMIC AND PROVIDES FAIR OPPORTUNITIES
ILO/UN/WB
Implementation/SupervisionImplementation/Supervision309
SUPERVISION METHODOLOGY
FIELD VISITS
REVIEW AND APPROVE
CONSULTANT SELECTION
BID DOCUMENTS
CONTRACT AWARDSCONTRACT AWARDS
CHANGES IN SCOPE/COSTS
ILO/UN/WB
Project EvaluationProject Evaluation310
COMPLETION REPORT PREPARED BY:
BANK OPERATIONS STAFF
DESK AND FIELD REVIEWS
RE-ESTIMATES COST/BENEFITS
INCLUDES BORROWER’S COMMENTS
ANALYSIS OF SUCCESS AND FAILURES
ILO/UN/WB
Project EvaluationProject Evaluation
AUDIT REPORT BY INDEPENDENT DEPARTMENT OF BANK (OED)
311
AUDIT REPORT BY INDEPENDENT DEPARTMENT OF BANK (OED)
SPECIAL REVIEWS BY OED
ANALYSIS USED FOR FUTURE PROJECT DESIGN
EVALUATION OF IMPACTEVALUATION OF IMPACT
AUDIT REPORT BY INDEPENDENT DEPARTMENT OF BANK (OED)
SPECIAL REVIEWS BY OED
ANALYSIS USED FOR FUTURE PROJECT DESIGNANALYSIS USED FOR FUTURE PROJECT DESIGN
EVALUATION OF IMPACT
ILO/UN/WB
NOT A MODULE: TRAINER THINGS
Never forget…Never forget…313
Projects are made for people and made by people…
Remind yourself…Remind yourself…314
Fix your focus…
… constantly!
The ’egg drop’ projectThe egg drop project
f
315
Suitable for: Team work – Decision making, Planning/Co-ordination/ Co-operation, Working under ‘pressure’, Monitoring + Evaluation.
G k M iGroup work: Maximum seven persons per group.One person from each group will get the assignment to be a neutral observer/monitor on how the group performs and has to act strictly neutral (see observer sheet)neutral (see observer sheet).
Task: Produce a package, only from the materials provided, that will prevent that an egg that is enclosed in it will break if itwill prevent that an egg that is enclosed in it will break, if it is dropped from a fixed height (of 2.50 meter)!
The ’egg drop’ projectThe egg drop project
Ti il bl 30 i t t t d bl !
316
Time available: 30 minutes, not extendable!
Material supplied to complete the task:Material supplied to complete the task:
- One fresh (not boiled) egg- 25 drinking straws (plastic),
125 f ‘ t h t ’- 125 cm of ‘scotch-tape’
No other material then the supplied one is allowed (e.g.Scissors, pocket knifes, additional padding material, etc.!Sc sso s, poc et es, add t o a padd g ate a , etcNo manipulation on the egg (e.g. blowing it out, boiling it, etc.)!You are not allowed to visit any competing group!You are not allowed to conduct any pre- test!
The ’egg drop’ projectThe egg drop project
Working steps:
317
Working steps:
• Assign tasks/functions to person in your group/team (e.g. designer, engineer, manager, material supplier/holder etc) and label the group member visibly, so that she/he can be easily identified.
• Design a package only from the materials supplied, with an egg inside, so that the egg will survive a drop from a height of 2 50 meterthat the egg will survive a drop from a height of 2.50 meter.
Stand for the contest:
S l t b f t h h t d k ( ith th i id ) f h i htSelect a member of your team who has to drop your package (with the egg inside) from a height of 2.50 meter! The winning group will be that one, where the egg is not broken!
* In case of a ‘draw’ situation the audience will select the ‘winner’, based on additional criteria, , ,such as ‘overall group performance, product appearance’ etc.
Trainer things…Trainer things…318
The form of management = mis-managment
Imagine: An advisor knows 96 different positions and no women is interestedAn advisor knows 96 different positions and no women is interested
What happens when we learn?What happens when we learn?319
V E“diencephalon” We do not send/exchange information but signalsg
I N
Values20 % of impulses are new
80 % are from our inventory’ValuesInterestsExpectationsNeeds
80 % are from our ‚inventory
Often used container metaphor – Morse code; sender and receiver is wrong
Better Performance i P j t M t (PM)in Project Management (PM)
320
Things that can go wrong…Things that can go wrong…
Murphy's Laws
321
Murphy s Laws
1. If anything can go wrong, it will.
2. If there is a possibility of several things going wrong, the one that will cause the
most damage will be the first one to go wrong.
3 If anything just cannot go wrong it will anyway3. If anything just cannot go wrong, it will anyway.
4. If you perceive that there are four possible ways in which something can go wrong,
and circumvent these, then a fifth way, unprepared for, will promptly develop.
5. Left to themselves, things tend to go from bad to worse.
6. If everything seems to be going well, you have obviously overlooked something.
7. Nature always sides with the hidden flaw.
8. Mother nature is a bitch.
Wisdom…Wisdom…322
You don’t need to know everything, but you should y g, yknow who does….
H F dHenry Ford
Team work…Team work…323
Do you want to do donkey work
t k?or team work?
What was planned…?What was planned…?324
Chasing the plan…Chasing the plan…325
THE TARGET ACHIEVED?
Working the pyramide
WHAT and HOWQuality Management
WHEN and COSTSWHEN and COSTSBudget
WHO and HOW MUCHCapacity Plan
WHAT until WHENOperation Chart
WHATStructured Project Planj
WHYClear Target
Chasing the plan…Chasing the plan…326
If reality hits you…
Changing plans (because reality has its own plan), does not mean you have planned badly! It is your obligation to adjust to reality!
Just graffiti…Just graffiti…327
Just graffiti…Just graffiti…328
Just graffiti…Just graffiti…329
Just graffiti…Just graffiti…330
Just graffiti…Just graffiti…331
Just graffiti…Just graffiti…332
Just graffiti…Just graffiti…333
Be aware…Be aware…334
What we have done this week…
…Project Managementj g
An Engineering and P j t M t M lProject Management Marvel
335
The Burj Dubai
http://www.burjdubai.com/