bgrr/hfbr decommissioning projects - bnl

28
BGRR/HFBR Decommissioning Projects Chuck Armitage Director Environmental Restoration Projects Community Advisory Council November 2010

Upload: others

Post on 15-Nov-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

BGRR/HFBR Decommissioning Projects

Chuck ArmitageDirector

Environmental Restoration Projects

Community Advisory Council November 2010

2

Briefing TopicsBGRR

• Graphite removal completion and celebration• Biological shield• Engineered cap

HFBR• Stabilization • Underground utilities• Fan houses• Stack

3

Graphite Pile Removal Project in 2 Minutes

4

Graphite Pile Removal Complete

5

BGRR Celebration – Press Conference

6

BGRR Celebration – Tour

7

BGRR Bioshield

8

BGRR Preparations for Bioshield Removal

9

BGRR Preparations for Bioshield Removal

10

BGRR -- Look Ahead

Achieve ROD End State by Sept 2011Complete by 6/2011

• Remove biological shield• Install engineered environmental cap and

monitoring system

1111

HFBR Operations – Reactor Confinement Building – Experimental Level

1212

HFBR Stabilization – Reactor Confinement Building – Experimental Level

1313

HFBR Stabilization – Reactor Confinement Building – Equipment Level

1414

HFBR Stabilization – Reactor Confinement Building – Operations Level

1515

HFBR Stabilization – Reactor Confinement Building – Leak Detection

1616

HFBR Stabilization – Reactor Confinement Building – Lights Off, Door Locked

1717

HFBR Stabilization – Reactor Confinement Building – Lights Off, Door Locked

1818

HFBR Stabilization – Final Status Survey of Outside Area

19

Excavation of HFBR Underground Air Exhaust Duct

20

Survey of Excavated HFBR Underground Duct

21

Fan House (Building 704) Demolition

22

Fan House Demolition

23

Fan House Below Ground Structure Demolition

24

Fan House Site Restoration

2525

Stack Demolition

Demolition contract awardedContractor mobilization underwayMast climber system to support work platformHoist system to move equipment and personnel

26

HFBR -- Look Ahead

Achieve ROD Long-term Intermediate End State by September 2011

Completed Confinement Building stabilization and shifted to low maintenance state – 8/25/2010 –complete transition to EPD and SC in 2011Completed Fan House 704 demolition (10/2010)Complete Underground Utilities (2/2011)Stack Demolition – start (11/2010) - complete (2/2011)Fan House 802 demolition - start 1/2011 –complete (4/2011)

2727

Skyline Changes – September 2011

28

ARRA Funding – Opportunities and Challenges

Original ARRA Funding $42M Success has created added ARRA Funding• Total ARRA $70.8M

Additional funding comes with added scope and accelerated completion • Meet HFBR and BGRR ROD states Sept 2011• New work sequencing• More work simultaneously• More integration for common real estate• Waste shipment and disposal