Page 1: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 1

BGV cooling :BGV cooling :test & installation planstest & installation plans

point 8 LHC tunnel

Page 2: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 2

reminderreminder

estimated length = 20m, by Yvon Muttoni

insulation: Armaflex 48m Will cut to exact length in

situ

chillerchiller

manifold boxmanifold box

UA43UA43RA43RA43

Page 3: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 3

Future testsFuture tests

Point 8:

1.check of manifold integrity (closed-loop test), check for frost and leaks

2.connect external PT100 in manifold and test

3.connect to network and test remote control

4.integrate PrestoA80 winCC control to BGV winCC

5.define approximate valve adjustements for flow equalization

6.cross check 4 visual flow-meters with Petr's flowmeter

7.test with dummy restrictions (simulating modules) on all 4 lines.

8.test interlock from gas flow

do we need filters on chiller ?

Page 4: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 4

Future tests: LHC tunnelFuture tests: LHC tunnelInstall1: (chiller & manifold)

1.transport chiller and manifold (with closed loops) from point to LHC-TNL

2.make electrical connection of chiller

3.connect TL to chiller (finalize insulation after Tests!)

4.fix manifold in tunnel floor (bolts ?), connect TL to manifold (finalize insulation after Tests!)

5.connect PT100 cable (chiller <=> manifold)

6.connect compressed air to manifold

7.connect interlock cable (chiller <=> airflow)

8.connect network cable for Presto A80

Test1:

1.fill chiller, circulate, refill, check coarse losses (have enough C6F14)

2.test air flow to manifold, test interlock from gas flow

3.check circulation, frost & leaks => if success, finalize insulation

4.test external PT100

5.test remote control

Install2: (manifold <=> detectors)

1.install cooling lines and compressed air lines

2.connect cooling and compressed air lines (manifold - modules)

Test2:

1.test module cooling, circulation, readjust valves for flow equalization

2.check for frost & leaks on modules => if success, finalize insulation

in red : prepare in advancein blue: mostly in RA43in black: mostly in UA43

in red : prepare in advancein blue: mostly in RA43in black: mostly in UA43

inde

pend

ent o

f det

ecto

r m

odul

es

Page 5: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 5

prepare in advanceprepare in advance

manifold: – connect the four supply lines to the 4 returns lines

– PT100 installed inside, connector outside.

– fixation bolts ? who ? cables from chiller to detector:

– PT100 external (4-wire shielded cable, could be a cat6 network cable)

– interlock from air flow (what cable ?) cable from chiller to racks:

– network cable other stuff:

– enough spare C6F14 (20 liters ?)

– spare insulation material (tape, armaflex, etc)

– velcroz strips

Page 6: BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel

BGV 05-may-2015 CERN Massimiliano Ferro-Luzzi 6

Who ? When ? Who ? When ?

Who:mostly Valdir and Massi, but contributions by others are welcomemaybe some help from EN-CV ?

When:cables should/could be prepared beforehand (short access ?)Install1 & Test1 is probably an 8h day of workInstall2 & Test2 is another 8h day of workLong-term leak/frost tests would of course require more time