bhogat

58
Activity ID Activity Name Start Finish Original Duration PROCUREMENT,CONSTRUCTION AND PRE-COMMISSIONING SERVICES- ... 01-Sep-10 A 19-Mar-14 916 MILESTONES 01-Sep-1... 11-Mar-14 916 INT0100 Award of Contract (LOA) 01-Sep-1... 0 INT0110 Kick of meeting 15-Sep-1... 0 INT0120 Site Enabling works ( Site office,Warehouse) 07-Oct-1... 02-Apr-11 A 100 INT0130 Completion of Residual Basic Engg. for Packages 04-Oct-12 A 0 INT0140 Ordering of Steam Generation Package 25-Oct-10 A 0 INT0150 Ordering of Air Compressor Package 16-Mar-11 A 0 INT0170 Ordering of Oily Water Treatment Package (OWS) 28-Oct-10 A 0 INT0180 Ordering of Gate/Ball Valves 16-Mar-11 A 0 INT0190 Ordering of Control Valves 11-Feb-11 A 0 INT0191 Ordering of Emergency Shut Down Valves 11-Feb-11 A 0 INT0200 Ordering of Nitrogen Package 01-Dec-10 A 0 INT0210 Ordering of Panel / Switchgear 01-Dec-10 A 0 INT0220 Ordering of Power Transformer 31-Dec-10 A 0 INT0230 Ordering of FF Pumps 09-Jun-11 A 0 INT0240 Ordering of DG set 14-Jan-11 A 0 INT0250 Receipt of Steam Generation Package 16-May-12 A 0 INT0260 Receipt of Air Compressor Package 10-May-12 A 0 INT0280 Receipt of Oily Water Treatment Package (OWS) 20-Nov-13 A 0 INT0290 Receipt of Gate/Ball Valves 24-Jul-13 A 0 INT0300 Receipt of Control Valves 05-Aug-13 A 0 INT0301 Receipt of Emergency Shut Down Valves 16-Jul-13 A 0 INT0310 Receipt of Nitrogen Package 04-Jun-12 A 0 INT0320 Receipt of Panel / Switchgear 11-Oct-12 A 0 INT0330 Receipt of Power Transformer 15-Jul-12 A 0 INT0340 Receipt of Fire Water System 16-Jul-13 A 0 INT0350 Receipt of DG set 21-Apr-12 A 0 INT0360 All Building's Construction Completion 22-Oct-13 A 0 INT0380 Hydrotesting Completion 08-Jan-14 A 0 INT0390 Erection of Equipments completion 15-Jul-13 A 0 INT0400 Electrical works completion 12-Feb-13 A 0 INT0410 Instrument works completion 11-Mar-14 A 0 INT0420 Fire Fighting Work Completion 18-Nov-13 0 INT0430 Mechanical Completion 13-Jan-14 0 INT440 Receipt of FIM-GT 06-Apr-12 A 0 INT450 Receipt of FIM-Export Booster Pumps 11-Apr-12 A 0 INT460 Receipt of Heat Tracing System 21-Oct-13 A 0 INT470 Receipt of Foam Concentrate Tank 27-Mar-12 A 0 INT480 Receipt of Deludge Valve 15-May-13 A 0 INT490 Receipt of Electronic Flow Meter 04-Jun-13 A 0 INT500 Mobilization of Mechanical Contractor 07-Nov-11 A 0 INT510 Mobilization of Electrical Contractor 10-Apr-12 A 0 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2011 2012 PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 58 © Primavera Systems, Inc.

Upload: dreamboy87

Post on 20-Jul-2016

11 views

Category:

Documents


1 download

DESCRIPTION

schedule

TRANSCRIPT

Activity ID Activity Name Start Finish Original

DurationPROCUREMENT,CONSTRUCTION AND PRE-COMMISSIONING SERVICES- CAIRN BHOGATPROCUREMENT,CONSTRUCTION AND PRE-COMMISSIONING SERVICES- ... 01-Sep-10

A19-Mar-14 916

MILESTONESMILESTONES 01-Sep-1... 11-Mar-14 916

INT0100 Award of Contract (LOA) 01-Sep-1... 0INT0110 Kick of meeting 15-Sep-1... 0INT0120 Site Enabling works ( Site office,Warehouse) 07-Oct-1... 02-Apr-11 A 100INT0130 Completion of Residual Basic Engg. for Packages 04-Oct-12 A 0INT0140 Ordering of Steam Generation Package 25-Oct-10 A 0INT0150 Ordering of Air Compressor Package 16-Mar-11 A 0INT0170 Ordering of Oily Water Treatment Package (OWS) 28-Oct-10 A 0INT0180 Ordering of Gate/Ball Valves 16-Mar-11 A 0INT0190 Ordering of Control Valves 11-Feb-11 A 0INT0191 Ordering of Emergency Shut Down Valves 11-Feb-11 A 0INT0200 Ordering of Nitrogen Package 01-Dec-10 A 0INT0210 Ordering of Panel / Switchgear 01-Dec-10 A 0INT0220 Ordering of Power Transformer 31-Dec-10 A 0INT0230 Ordering of FF Pumps 09-Jun-11 A 0INT0240 Ordering of DG set 14-Jan-11 A 0INT0250 Receipt of Steam Generation Package 16-May-12 A 0INT0260 Receipt of Air Compressor Package 10-May-12 A 0INT0280 Receipt of Oily Water Treatment Package (OWS) 20-Nov-13 A 0INT0290 Receipt of Gate/Ball Valves 24-Jul-13 A 0INT0300 Receipt of Control Valves 05-Aug-13 A 0INT0301 Receipt of Emergency Shut Down Valves 16-Jul-13 A 0INT0310 Receipt of Nitrogen Package 04-Jun-12 A 0INT0320 Receipt of Panel / Switchgear 11-Oct-12 A 0INT0330 Receipt of Power Transformer 15-Jul-12 A 0INT0340 Receipt of Fire Water System 16-Jul-13 A 0INT0350 Receipt of DG set 21-Apr-12 A 0INT0360 All Building's Construction Completion 22-Oct-13 A 0INT0380 Hydrotesting Completion 08-Jan-14 A 0INT0390 Erection of Equipments completion 15-Jul-13 A 0INT0400 Electrical works completion 12-Feb-13 A 0INT0410 Instrument works completion 11-Mar-14 A 0INT0420 Fire Fighting Work Completion 18-Nov-13 0INT0430 Mechanical Completion 13-Jan-14 0INT440 Receipt of FIM-GT 06-Apr-12 A 0INT450 Receipt of FIM-Export Booster Pumps 11-Apr-12 A 0INT460 Receipt of Heat Tracing System 21-Oct-13 A 0INT470 Receipt of Foam Concentrate Tank 27-Mar-12 A 0INT480 Receipt of Deludge Valve 15-May-13 A 0INT490 Receipt of Electronic Flow Meter 04-Jun-13 A 0INT500 Mobilization of Mechanical Contractor 07-Nov-11 A 0INT510 Mobilization of Electrical Contractor 10-Apr-12 A 0

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 1 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 2 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationINT520 Mobilization of Instrumentation Contractor 10-Apr-12 A 0INT530 Receipt of Intrusion Detection System 13-Apr-12 A 0INT540 Mobilization of Insulation Contractor 05-Jun-12 A 0INT550 Completion of Piping Erection 14-Dec-13 A 0INT560 Installation of Jockey Pump 22-Nov-12 A 0INT570 Delivery of Gate Valves 15-Jul-13 A 0INT580 RCC Completion of Dyke Wall 18-Sep-13 A 0INT590 Installation of Booster Pump 31-May-12 A 0

CONTRACTUAL MILESTONES- FINISH MILESTONESCONTRACTUAL MILESTONES- FINISH MILESTONES 07-Dec-1... 19-Mar-14 526

COMIM4.11 UNPRICED PO COPIES OF FIRE PROTECTION SYSTEM 16-Aug-12 A 0COMIM4.15 UNPRICED PO COPIES OF E & I WORKS SUB-CONTRACT 15-Mar-12 A 0COMIM4.16 UNPRICED PO COPIES OF HVAC WORKS SUB-CONTRACT 12-Dec-11 A 0COMIM4.9 UNPRICED PO COPIES OF HEAT TRACING 29-Dec-11 A 0COMIM5.1.1 COMPLETION OF CIVIL FDN. FOR FIRE WATER STORAGE TANKS 15-Mar-12 A 0COMIM5.1.10 COMPLETION OF CIVIL FDN. FOR DIESEL GENERATOR 24-Feb-12 A 0COMIM5.1.11 COMPLETION OF CIVIL FDN. FOR VENT STACK 15-May-12 A 0COMIM5.1.13 COMPLETION OF CIVIL FDN. FOR DIESEL STORAGE TANK 24-Feb-12 A 0COMIM5.1.2 COMPLETION OF CIVIL FDN. FOR RAW WATER STORAGE TANKS 13-Sep-12 A 0COMIM5.1.3 COMPLETION OF CIVIL FDN. FOR CLOSED DRAIN TANKS 13-Sep-12 A 0COMIM5.1.4 COMPLETION OF CIVIL WORKS FOR TANK DYKE WALLS AND PAVING 20-Nov-13 A 0COMIM5.1.5 COMPLETION OF CIVIL FDN. FOR EXPORT PUMPS 07-Dec-11 A 0COMIM5.1.6 COMPLETION OF CIVIL FDN. FOR GAS TURBINES 15-Jan-12 A 0COMIM5.1.7 COMPLETION OF CIVIL FDN. FOR CUSTODY TRANSFER METERING SKID 17-Jan-12 A 0COMIM5.1.8 COMPLETION OF CIVIL FDN. FOR FIRE WATER & JOCKEY PUMPS 28-Apr-12 A 0COMIM5.1.9 COMPLETION OF CIVIL FDN. FOR STEAM GENERATION PACKAGE 26-Mar-12 A 0COMIM5.2.1 RECEIPT AT SITE OF STEAM GENERATION PACKAGE 14-Nov-12 A 0COMIM5.2.10 RECEIPT AT SITE OF FIRE WATER AND JOCKEY PUMPS 16-Oct-12 A 0COMIM5.2.12 RECEIPT AT SITE OF HT & LT CABLES 13-Nov-12 A 0COMIM5.2.13 RECEIPT AT SITE OF PIPING BULKS – PIPE, FLANGES, FITTINGS, GASKETS 18-Sep-13 A 0COMIM5.2.15 RECEIPT AT SITE OF ELECTRICAL BULKS 18-Jul-13 A 0COMIM5.2.2 RECEIPT AT SITE OF DIESEL GENERATOR PACKAGE 21-Apr-12 A 0COMIM5.2.3 RECEIPT AT SITE OF RAW WATER TREATMENT PACKAGE 15-Nov-12 A 0COMIM5.2.4 RECEIPT AT SITE OF INSTRUMENT AIR PACKAGE 24-Oct-12 A 0COMIM5.2.5 RECEIPT AT SITE OF OWS PACKAGE 20-Nov-13 A 0COMIM5.2.6 RECEIPT AT SITE OF SEWAGE/EFFLUENT TREATMENT PACKAGES 21-Oct-13 A 0COMIM5.2.7 RECEIPT AT SITE OF POWER & DISTRIBUTION TRANSFORMERS 20-Dec-12 A 0COMIM5.2.8 RECEIPT AT SITE OF HEAT TRACING 21-Nov-13 A 0COMIM5.2.9 RECEIPT AT SITE OF HV / LV SWITCHGEAR 23-Jan-13 A 0COMIM5.3.1 COMP. INSTAL. OF STEAM GENERATION PACKAGE 15-Nov-12 A 0COMIM5.3.10 COMP. INSTAL. OF HV / LV SWITCHGEAR 18-Sep-13 A 0COMIM5.3.11 COMP. INSTAL. OF FIRE WATER AND JOCKEY PUMPS 22-Jul-13 A 0COMIM5.3.13 COMP. INSTAL. OF FREE-ISSUE ITEMS 15-May-13 0COMIM5.3.14 COMP. INSTAL. OF ALL EXPORT PUMPS 31-May-12 A 0COMIM5.3.15 COMP. INSTAL. OF GAS TURBINES 25-Jan-12 A 0

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 3 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 4 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCOMIM5.3.16 COMP. INSTAL. OF SEHMS HARDWARE / EQUIPMENT 15-May-13 0COMIM5.3.17 COMP. INSTAL. OF CUSTODY TRANSFER METERING PACKAGE 20-Mar-12 A 0COMIM5.3.2 COMP. INSTAL. OF INSTRUMENT AIR PACKAGE 16-Nov-12 A 0COMIM5.3.3 COMP. INSTAL. OF RAW WATER TREATMENT PACKAGE 17-Jan-13 A 0COMIM5.3.4 COMP. INSTAL. OF TREATED WATER PACKAGE 20-Nov-13 A 0COMIM5.3.5 COMP. INSTAL. OF DIESEL GENERATOR PACKAGE 30-Apr-12 A 0COMIM5.3.6 COMP. INSTAL. OF OWS PACKAGE 19-Mar-14 A 0COMIM5.3.7 COMP. INSTAL. OF SEWAGE/EFFLUENT TREATMENT PACKAGES 13-Jun-13 A 0COMIM5.3.8 COMP. INSTAL. OF POWER & DISTRIBUTION TRANSFORMERS 23-Jul-13 0COMIM5.3.9 COMP. INSTAL. OF HEAT TRACING 30-Dec-13 0COMIM5.4.1 COMPLETION OF SUPER-STRUCTURE FOR ADMIN BUILDING 01-Nov-12 A 0COMIM5.4.2 COMPLETION OF SUB-STRUCTURE FOR ADMIN BUILDING 15-May-13 0COMIM5.4.3 COMPLETION OF INTERNAL FIT-OUT FOR CONTROL BUILDINGS 15-May-13 0COMIM5.5.1 COMPLETION OF WORKSHOP/WAREHOUSE/LABORATORY 15-May-13 0COMIM5.5.2 COMPLETION OF ADMINISTRATION BDLG 15-May-13 0COMIM5.5.3 COMPLETION OF SECURITY BUILDINGS & CABINS 15-May-13 0COMIM5.5.4 COMPLETION OF FIRE STATION & MEDICAL CENTRE 15-May-13 0COMIM5.5.5 COMPLETION OF MAIN PLANT SUBSTATION 15-May-13 0COMIM5.5.6 COMPLETION OF 11KV SUBSTATION 15-May-13 0COMIM5.5.7 COMPLETION OF SEHMS SUBSTATION 15-May-13 0COMIM5.5.8 COMPLETION OF MAIN DG ROOM 15-May-13 0COMIM5.5.9 COMPLETION OF VARIOUS MCC ROOMS 03-Jul-13 0COMIM5.6.1 COMPLETION OF WALLS, FENCING INCL. SECURITY GATES, CABINS, TOWERS 15-May-13 0COMIM5.6.10 COMPLETION OF ALL OTHER CIVIL, MECHANICAL, ELECTRICAL & INSTRUMENT... 06-Jan-14 0COMIM5.6.12 TEST. & COMMI. OF STEAM GENERATION PACKAGE 17-Aug-13 0COMIM5.6.13 TEST. & COMMI. OF DIESEL GENERATOR PACKAGE 15-May-13 0COMIM5.6.14 TEST. & COMMI. OF RAW WATER TREATMENT PACKAGE 02-Oct-13 0COMIM5.6.15 TEST. & COMMI. OF TREATED WATER PACKAGE 29-Oct-13 0COMIM5.6.16 TEST. & COMMI. OF INSTRUMENT AIR PACKAGE 15-May-13 0COMIM5.6.17 TEST. & COMMI. OF OWS PACKAGE 03-Jul-13 0COMIM5.6.18 TEST. & COMMI. OF SEWAGE/EFFLUENT TREATMENT PACKAGES 29-Oct-13 0COMIM5.6.19 TEST. & COMMI. OF POWER & DISTRIBUTION TRANSFORMERS 23-Jul-13 0COMIM5.6.2 COMPLETION OF TERMINAL ROADS AND DRAINS 09-Sep-13 0COMIM5.6.20 TEST. & COMMI. OF HEAT TRACING 30-Dec-13 0COMIM5.6.21 TEST. & COMMI. OF HV / LV SWITCHGEAR 15-May-13 0COMIM5.6.22 TEST. & COMMI. OF FIRE WATER AND FOAM SYSTEM 09-Aug-13 0COMIM5.6.24 TEST. & COMMI. OF TERMINAL PIPING 06-Jan-14 0COMIM5.6.25 TEST. & COMMI. OF TERMINAL TANKS – FIRE WATER, CLOSED DRAIN, FOAM C... 09-Aug-13 0COMIM5.6.26 TEST. & COMMI. OF DIESEL STORAGE AND DISTRIBUTION SYSTEM 15-May-13 0COMIM5.6.3 COMPLETION OF DRILLING OF 5 BORE WELLS AND ASSOCIATED PUMP & ITS P... 01-Jun-13 0COMIM5.6.4 COMPLETION OF TERMINAL PIPING, VALVES (INCL FREE-ISSUE), PIPING RACK... 14-Dec-13 0COMIM5.6.5 COMPLETION OF POWER AND CONTROL CABLING 30-Nov-13 0COMIM5.6.7 COMPLETION OF DIESEL STORAGE AND DISTRIBUTION SYSTEM 15-May-13 0COMIM5.6.8 COMPLETION OF ALL TANKS & VESSELS – FIRE WATER, CLOSED DRAIN, FOA... 15-May-13 0

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 5 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 6 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationDETAIL ENGINEERINGDETAIL ENGINEERING 02-Sep-1... 09-Jan-13 A 611

Equipment / System PackagesEquipment / System Packages 15-Sep-1... 24-Aug-11 A 277EPR100 Receive of Package Scheme, Flow Diagrams, system data sheets, equipment layout ... 15-Sep-1... 16-Sep-10 A 1EPR110 Review of Package Scheme, Flow Diagrams, system data sheets, equipment layout ... 18-Sep-1... 26-Nov-10 A 25EPR140 Release of P&ID for package items by IOT 19-Jan-1... 08-Aug-11 A 30EPR150 Release of Final Equipment Layout drawings, GADs by IOT 17-Jan-1... 04-Jul-11 A 15EPR160 Participation of Hazop study for package equipments 04-Aug-1... 24-Aug-11 A 7EPR170 Incorporatiion of recommendations as per Hazop Review 12-Jun-1... 24-Jun-11 A 10

CivilCivil 10-Sep-1... 27-Apr-12 A 467ECV050 Receipt of AFC Architectural Drawing from TCEL / CEIL 12-Oct-1... 15-Oct-10 A 5ECV100 Receipt of AFC Drawing of Admin Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2ECV110 Receipt AFC Drawing for Control Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2ECV120 Receipt of AFC Drawing of canopy at entrance from TCEL / CEIL 15-Oct-1... 18-Oct-10 A 2ECV130 Receipt of AFC Drawing of laboratory Building from TCEL / CEIL 20-Sep-1... 21-Sep-10 A 2ECV140 Receipt of AFC Drawing of Warehouse/ Workshop Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2ECV150 Receipt of AFC Drawing of Electrical substation from TCEL / CEIL 21-Sep-1... 25-Sep-10 A 5ECV160 Receipt AFC Drawing for Fire station Building from TCEL / CEIL 18-Sep-1... 23-Sep-10 A 5ECV170 Receipt of AFC Drawing of Medical Centre from TCEL / CEIL 18-Sep-1... 20-Sep-10 A 2ECV180 Receipt of AFC Drawing for Fire Water Pump House from TCEL / CEIL 20-Oct-1... 29-Oct-10 A 10ECV190 Receipt of AFC Drawing for Pump/Package Foundation from TCEL / CEIL 19-Oct-1... 27-Oct-10 A 10ECV200 Release of Pipe Sleepers Drgs for Fire Water Network 13-Jul-11 A 24-Jul-11 A 1ECV210 Receipt of AFC Drawing of Roads,Culverts, walkways, etc from TCEL / CEIL 17-Sep-1... 20-Sep-10 A 3ECV220 Receipt of AFC Drawing of Dyke wall and Paving in the Tank Farm from TCEL / CEIL 23-Sep-1... 24-Sep-10 A 2ECV240 Receipt AFC Drawing of MCC & Substation from TCEL / CEIL 20-Sep-1... 21-Sep-10 A 2ECV250 Receipt of AFC Drawing for Drains system from TCEL / CEIL 17-Sep-1... 18-Sep-10 A 2ECV260 Detail Engineeing for Foundations of Package items 10-Sep-1... 22-Sep-10 A 15Equipment FoundationEquipment Foundation 05-Sep-1... 27-Apr-12 A 241

ECV270 Fdn Drgs for Air Compressor 10-Jan-1... 10-Feb-12 A 25ECV280 Fdn Drgs for STP Package 12-Dec-1... 30-Dec-11 A 25ECV290 Fdn Drgs for Water Treatment Package 16-Jan-1... 27-Feb-12 A 25ECV300 Fdn Drgs for OWS Treatment Package 23-Apr-1... 27-Apr-12 A 15ECV310 Fdn Drgs for Nitrogen Package 02-Jan-1... 10-Feb-12 A 25ECV320 Fdn Drgs for Steam Generation Package / Boiler 01-Feb-1... 10-Feb-12 A 25ECV330 Fdn Drgs for Pumps 21-Apr-1... 25-Apr-12 A 25ECV340 Fdn Drgs for Fuel & Gas System (KO Drum,Cartridge Filter, Electric Heater) 28-Mar-1... 09-Apr-12 A 25ECV350 Fdn Drgs for NGR 26-Mar-1... 20-Apr-12 A 25ECV360 Fdn Drgs for Transformer 06-Dec-1... 23-Dec-11 A 25ECV370 Fdn Drgs for SHEMS Transformer 05-Dec-1... 30-Dec-11 A 25ECV380 Fdn Drgs for Vent Stack 05-Sep-1... 23-Feb-12 A 25ECV390 Fdn Drgs for DG Set 05-Dec-1... 29-Dec-11 A 25ECV400 Fdn Drgs for Foam Pump Skid 16-Jan-1... 22-Feb-12 A 25ECV410 Fdn Drgs for Foam Concentrate Tank 27-Feb-1... 03-Apr-12 A 25ECV420 Fdn Drgs for Fire Water Tank (New) 01-Feb-1... 26-Mar-12 A 25ECV430 Fdn Drgs for Fire Water Pump 01-Mar-1... 11-Apr-12 A 25

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 7 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 8 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationPipingPiping 08-Sep-1... 12-Jul-12 A 437

EPIP090 Incorporate Vendor datas and Finalisation of Plot Plan 22-Feb-1... 08-May-12 A 30EPIP100 Receipt of P&ID Piping Layout, GAD, Sectional Drawings from TCEL/CEIL 08-Sep-1... 09-Sep-10 A 2EPIP110 Receipt of Updated PMS and VMS from TCEL / CEIL 08-Sep-1... 09-Sep-10 A 2EPIP120 Layout & Isometric drgs for U/G Services like OWS / CBD / Sewage 13-Apr-1... 29-Apr-11 A 1EPIP130 Layout & Isometric for Fire Water Network 21-Apr-1... 21-Apr-11 A 1EPIP140 Issue of Piping/ Fitting MTO-1 by IOT 21-Sep-1... 10-Nov-10 A 10EPIP150 Issue of Piping / Fitting MTO-2 15-Feb-1... 15-Feb-11 A 10EPIP160 Issue of Isometric from CEIL/Vendor 22-Feb-1... 12-Jul-12 A 60EPIP170 Detail Engineeing for Package items 18-Jan-1... 08-Apr-11 A 15

MechanicalMechanical 16-Sep-1... 01-Jun-12 A 46EME120 Issue of MR for Oily water/ Sewage water treatment package 16-Sep-1... 18-Sep-10 A 2EME140 Issue of MR for Plant and Treated water package 16-Sep-1... 21-Sep-10 A 2EME150 Issue of MR for Plant and Instrument Air Package 16-Sep-1... 21-Sep-10 A 2EME160 Issue of MR for Raw Water Treatment Package 16-Sep-1... 21-Sep-10 A 1EME170 Issue of MR for Steam generation system package 16-Sep-1... 21-Sep-10 A 2EME175 Issue of MR for Nitrogen Generation System 16-Sep-1... 21-Sep-10 A 5EME180 Issue of MR for Fuel Gas System 29-Sep-1... 03-Dec-10 A 20EME220 Issue of MR for Pipes Bulks 21-Sep-1... 23-Sep-10 A 2EME250 Issue of MR for Fire water pump package 16-Sep-1... 21-Sep-10 A 2EME260 Issue of MR for Closed Drain Pump 16-Sep-1... 21-Sep-10 A 2EME270 Issue of MR for Diesel Unloading pump 16-Sep-1... 21-Sep-10 A 2EME280 Issue of MR for Reinforecement Steel / Structural Steel Bulk items 21-Sep-1... 26-Oct-10 A 40EME290 Issue of MR for Air conditioning and Ventiliation system 16-Sep-1... 20-Nov-10 A 2EME300 Issue of MR for EOT Crane or Material Handling system 16-Sep-1... 21-Sep-10 A 6EME310 Detail Engineering for Tanks (Fabrication Drawings.) 28-Oct-1... 01-Jun-12 A 25

ElectricalElectrical 02-Sep-1... 11-Apr-12 A 91EEL100 Receipt of SLDs from TCEL / CEIL 27-Sep-1... 28-Sep-10 A 1EEL120 Receipt of Approved Area classification Drawing from TCEL / CEIL 29-Oct-1... 06-Nov-10 A 10EEL130 Receipt of Approvevd Load List from TCEL / CEIL 27-Sep-1... 28-Sep-10 A 1EEL140 Issue of MR for Transformer 28-Sep-1... 30-Sep-10 A 2EEL150 Issue of MR for UPS 28-Sep-1... 30-Sep-10 A 2EEL160 Issue of MR for Switchgear/Panel 28-Sep-1... 30-Sep-10 A 2EEL170 Receipt of Approvevd data sheet & Cable Schedule from TCEL / CEIL 02-Sep-1... 21-Sep-10 A 5EEL180 Issue of MR C.P. System 30-Sep-1... 08-Oct-10 A 10EEL190 Issue of MR for DG 30-Sep-1... 01-Oct-10 A 2EEL200 Issue of MR for Battery and Battery Charger 30-Sep-1... 01-Oct-10 A 2EEL210 Issue of MR for NGR 30-Sep-1... 01-Oct-10 A 2EEL220 Detail Engineeing for Package items 01-Dec-1... 11-Apr-12 A 15

InstrumentationInstrumentation 25-Sep-1... 09-May-12 A 82EIN100 Receipt of Approvevd instrument index from TCEL / CEIL 11-Oct-1... 15-Oct-10 A 5EIN110 Receipt of Approvevd I/O list from TCEL / CEIL 28-Sep-1... 02-Oct-10 A 5EIN120 Receipt of Approvevd Instrument data sheet from TCEL /CEIL 25-Sep-1... 30-Sep-10 A 5EIN130 Receipt of Approvevd Instrument Hook up drawing from TCEL / CEIL 31-Dec-1... 03-Jan-11 A 7

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 9 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 10 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationEIN140 Issue of MR for Bulk Items (MOV / PCV / Transmitters / Gauges etc.) 16-Oct-1... 12-Nov-10 A 30EIN150 Detail Engineeing for Package items 20-Dec-1... 09-May-12 A 15

Addition Engineering-Fire Fighting ChangesAddition Engineering-Fire Fighting Changes 25-Apr-1... 05-Sep-11 A 74MDPP-FPSC-0001 RECEIPT OF CONSOLIDATED CHANGE LIST ON FPS FROM CEIL AND CHANGE ... 15-Jul-11 A 0MDPP-FPSC-E-00001RECEIPT OF REVISED PLOT PLAN 02-Sep-1... 05-Sep-11 A 1MDPP-FPSC-E-0002MR FOR FIRE WATER MAIN & JOCKEY PUMP 25-Apr-1... 25-Apr-11 A 1MDPP-FPSC-E-0003MR FOR FOAM CONCENTRATE TANK 25-Apr-1... 25-Apr-11 A 1MDPP-FPSC-E-0004MR FOR FOAM CONCENTRATE 25-Apr-1... 25-Apr-11 A 1MDPP-FPSC-E-0005MR FOR FOAM SYSTEM ACCESSORIES 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0006MR FOR DELUGE VALVES 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0007MR FOR STRAINERS 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0008MR FOR GATE VALVES 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0009MR FOR CHECK VALVES 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0010MR FOR ELECTROMAGNETIC FLOW METER 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0011MR FOR PLC FOR PUMPS 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0012MR FOR RUBBER EXPANSION BELLOW 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0022MR FOR CP SYSTEM 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0032MR FOR FPS-PIPES 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0042MR FOR FPS-FITTINGS 24-May-1... 24-May-11 A 1MDPP-FPSC-E-0052MR FOR FPS-FLANGES & MISCELLENOUS 24-May-1... 24-May-11 A 1

ENGINEERING-FREE ISSUE MATERIALENGINEERING-FREE ISSUE MATERIAL 20-Sep-1... 09-Jan-13 A 601EFI010 Receipt of Input of free issue material from CEIL 20-Sep-1... 28-Sep-10 A 10EFI030 Receipt of Electrical Input for GT / MAIN LINE PUMP / BOOSTER PUMPS/ CTM Pkg 20-Oct-1... 28-Feb-11 A 10EFI040 Receipt of Civil Foundation drawing of free issue material from CEIL 31-Jan-1... 01-May-12 A 10EFI050 Detail Engineering for Clean agent system, location of Fire Extinguisher by Vendor 20-Mar-1... 30-Mar-12 A 10EFI051 Receipt of Hydrant Layout form CEIL/TCE 11-Dec-1... 09-Jan-13 A 10

AS BUILT DRAWINGAS BUILT DRAWING 18-Nov-13 10-Jan-14 39

EBD100 As Built drawing & Final Documentation 18-Nov-13 10-Jan-14 60

PROCUREMENTPROCUREMENT 17-Sep-1... 20-Sep-13 777

SUBCONTRACTINGSUBCONTRACTING 30-Sep-1... 14-Feb-12 A 129CIVIL/STRUCTURALCIVIL/STRUCTURAL 30-Sep-1... 08-Jan-11 A 40

SC120 Prep. of Tender & award of contract for all Civil Package (Road, Dyke wall, drain etc.) 30-Sep-1... 25-Oct-10 A 25SC130 Finalisation of Civil Contractor for all packages (Equipment foundations etc.) 02-Oct-1... 03-Jan-11 A 60SC140 Prep. of Tender & award of contract for Building Contractor 04-Oct-1... 08-Jan-11 A 25

MECHANICAL/PIPINGMECHANICAL/PIPING 03-Jan-1... 06-Jul-11 A 22SC160 Prep. of Tender Mechanical ( Piping & Fire Fighting) 03-Jan-1... 04-Feb-11 A 20SC170 Finalisation of Mechanical Contractor 12-Feb-1... 06-Jul-11 A 5

ELECTRICALELECTRICAL 30-Dec-1... 14-Feb-12 A 16SC260 Preparation and Issue Tender for Electrical 30-Dec-1... 07-Feb-11 A 22SC270 Finalisation of Tender for Electrical Contractor 11-Feb-1... 14-Feb-12 A 25

INSTRUMENTINSTRUMENT 29-Dec-1... 14-Feb-12 A 29SC180 Preparation and Issue Instrumentation Tender 29-Dec-1... 01-Feb-11 A 22SC190 Finalisation of Instrumentation Contractor 09-Feb-1... 14-Feb-12 A 5

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 11 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 12 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationINSULATIONINSULATION 29-Dec-1... 21-Dec-11 A 9

SC200 Preparation and Issue Tender for piping Insulation 29-Dec-1... 02-Feb-11 A 15SC210 Finalisation of Tender for Insulation contractor 08-Feb-1... 21-Dec-11 A 7

PAINTINGPAINTING 30-Dec-1... 01-Jun-11 A 22SC220 Preparation and Issue Tender for Painting 30-Dec-1... 07-Feb-11 A 15SC230 Finalisation of Tender for Painting Contractor 15-Feb-1... 01-Jun-11 A 5

MECHANICAL/ EQUIPMENTMECHANICAL/ EQUIPMENT 17-Sep-1... 17-Sep-13 587

OWS PackageOWS Package 20-Sep-1... 13-Aug-13 127PRE120 Issue Enquiry 20-Sep-1... 20-Sep-10 A 1PRE122 Bids received 20-Sep-1... 01-Oct-10 A 10PRE123 TBA / CBA 29-Sep-1... 25-Oct-10 A 20PRE124 Ordering for Oily water treatment package 25-Oct-1... 28-Oct-10 A 8PRE130 Mfg and Del at site-Oily water treatment package 28-Oct-1... 13-Aug-13 160

Water Treatment PackageWater Treatment Package 17-Sep-1... 14-Sep-13 163PRE191 Issue Enquiry 17-Sep-1... 21-Sep-10 A 1PRE192 Bids received 18-Sep-1... 05-Oct-10 A 10PRE193 TBA / CBA 27-Sep-1... 25-Oct-10 A 15PRE194 Ordering of Raw Water Treatment Package 25-Oct-1... 28-Oct-10 A 8PRE195 Mfg and Del at site-Water Treatment Package 28-Oct-1... 14-Sep-13 200

STP PackageSTP Package 18-Sep-1... 08-Jun-13 133PRE160 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1PRE162 Bids received 20-Sep-1... 05-Oct-10 A 10PRE163 TBA / CBA 05-Oct-1... 25-Oct-10 A 12PRE164 Ordering for Sewage water treatment package 25-Oct-1... 28-Oct-10 A 8PRE170 Mfg and Del at site- Sewage water treatment package 28-Oct-1... 08-Jun-13 160

Closed Drain PumpClosed Drain Pump 18-Sep-1... 23-Jul-12 A 207PRE100 Issue Enquiry 18-Sep-1... 20-Sep-10 A 1PRE102 Bids received 20-Sep-1... 30-Oct-10 A 8PRE103 TBA / CBA 31-Oct-1... 28-Jan-11 A 14PRE104 Ordering for Closed Drain Pump 28-Jan-1... 07-Feb-11 A 7PRE110 Mfg and Del at site-Closed Drain pump 28-Feb-1... 23-Jul-12 A 150

Diesel Unloading PumpDiesel Unloading Pump 18-Sep-1... 30-May-12 A 172PRE260 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1PRE262 Bids received 25-Sep-1... 28-Oct-10 A 8PRE263 TBA / CBA 28-Oct-1... 23-Nov-10 A 15PRE264 Ordering for Diesel unloading pump 27-Nov-1... 17-Dec-10 A 8PRE270 Mfg and Del at site-Diesel unloading pump 17-Dec-1... 30-May-12 A 150

Interface Transfer PumpInterface Transfer Pump 18-Sep-1... 20-Dec-12 A 172PRE272 Bids received 25-Sep-1... 28-Oct-10 A 8PRE273 TBA / CBA 28-Oct-1... 23-Nov-10 A 15PRE274 Ordering for Interface Transfer Pump 27-Nov-1... 17-Dec-10 A 8PRE280 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1PRE290 Mfg and Del at site-Interface Transfer Pump 17-Dec-1... 20-Dec-12 A 150

Structural Steel / Reinforcement Steel/ PlatesStructural Steel / Reinforcement Steel/ Plates 23-Sep-1... 12-Dec-12 A 80

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 13 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 14 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationPRE300 Issue Enquiry 23-Sep-1... 24-Sep-10 A 1PRE302 Bids received 24-Sep-1... 20-Oct-10 A 10PRE303 TBA / CBA 20-Oct-1... 02-Nov-10 A 15PRE304 Ordering of Structural Steel / Reinforcement Steel 05-Nov-1... 01-Jun-11 A 25PRE310 Mfg and Del at site-Structural steel and Plate 06-Nov-1... 12-Dec-12 A 80

Treated Water PackageTreated Water Package 0Air CompressorAir Compressor 18-Sep-1... 28-Nov-12 A 292

PRE180 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1PRE182 Bids received 20-Sep-1... 19-Oct-10 A 10PRE183 TBA / CBA 20-Oct-1... 16-Feb-11 A 15PRE184 Ordering of Air Compressor 16-Feb-1... 16-Mar-11 A 8PRE190 Mfg and Del at site-Air Compressor-(Dryer & receiver pending) 23-May-1... 28-Nov-12 A 160

Nitrogen PackageNitrogen Package 21-Sep-1... 22-Nov-12 A 240PRE201 Issue Enquiry 21-Sep-1... 22-Sep-10 A 1PRE202 Bids received 22-Sep-1... 29-Oct-10 A 12PRE203 TBA / CBA 29-Oct-1... 24-Nov-10 A 20PRE204 Ordering for Nitrogen Generation System 24-Nov-1... 01-Dec-10 A 10PRE210 Mfg and Del at site-Nitrogen Generation System 02-Dec-1... 22-Nov-12 A 230

HVAC SystemHVAC System 18-Sep-1... 25-Dec-12 A 256PRE340 Issue Enquiry 18-Sep-1... 04-Nov-10 A 1PRE342 Bids received 04-Nov-1... 14-Dec-10 A 10PRE343 TBA / CBA 15-Dec-1... 17-Jan-11 A 25PRE345 Ordering of Air conditioning and Ventiliation system 19-Jan-1... 03-Feb-11 A 7PRE350 Mfg and Del at site-Air conditioning and Ventiliation system 28-Feb-1... 25-Dec-12 A 200

EOT CraneEOT Crane 27-Sep-1... 17-Jan-13 A 233PRE360 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1PRE362 Bids received 28-Sep-1... 16-Oct-10 A 8PRE363 TBA / CBA 16-Oct-1... 10-Feb-11 A 15PRE364 Ordering of -EOT Crane or Material Handling system 10-Feb-1... 15-Mar-11 A 8PRE370 Mfg and Del at site-EOT Crane 17-Mar-1... 17-Jan-13 A 160

Fuel & Gas SystemFuel & Gas System 30-Sep-1... 27-Dec-12 A 238PRE400 Issue Enquiry 30-Sep-1... 03-Dec-10 A 1PRE402 Bids received 15-Dec-1... 20-Dec-10 A 10PRE403 TBA / CBA 23-Dec-1... 24-Jan-11 A 15PRE405 Ordering of Fuel & Gas System 25-Jan-1... 10-Feb-11 A 8PRE410 Mfg and Del at site-Fuel & Gas System 15-Feb-1... 27-Dec-12 A 200

Steam Generation System / BoilerSteam Generation System / Boiler 18-Sep-1... 16-Oct-12 A 232PRE420 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1PRE422 Bids received 20-Sep-1... 04-Oct-10 A 10PRE423 TBA / CBA 04-Oct-1... 21-Oct-10 A 22PRE424 Ordering of Steam generation system 21-Oct-1... 25-Oct-10 A 8PRE430 Mfg and Del at site-Steam generation system 26-Oct-1... 16-Oct-12 A 240

SMC Panel TankSMC Panel Tank 01-Jun-1... 28-Jun-13 135PRE434 Ordering of SMC Panel Tank 01-Jun-1... 09-Jun-11 A 8

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 15 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 16 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationPRE470 Mfg and Del at site-SMC Panel Tank 13-Jun-1... 28-Jun-13 180

Fire Fighting SystemFire Fighting System 18-Sep-1... 17-Sep-13 587PRE440 Issue Enquiry 18-Sep-1... 18-Sep-10 A 1PRE442 Bids received 20-Sep-1... 10-Dec-10 A 8PRE443 TBA / CBA 11-Dec-1... 20-Jan-11 A 20PRE444 Ordering of Fire Fighting System 31-Jan-1... 12-Apr-11 A 20PRE450 Mfg and Del at site of Fire Fighting System 07-Jun-1... 17-Sep-13 140

PIPINGPIPING 27-Sep-1... 22-Jul-13 301Pipes - 1st MTOPipes - 1st MTO 27-Sep-1... 15-Dec-11 A 131

PPIP100 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1PPIP102 Bids received 28-Sep-1... 07-Oct-10 A 10PPIP103 TBA / CBA 07-Oct-1... 30-Oct-10 A 5PPIP104 Ordering for Pipes -1st MTO (in Lots) 30-Oct-1... 16-Nov-10 A 60PPIP110 Mfg and Del at site-Pipe 1st MTO-A1 18-Nov-1... 15-Dec-11 A 150

Pipes - 2nd MTOPipes - 2nd MTO 15-Feb-1... 14-Nov-12 A 79PPIP120 Issue Enquiry 15-Feb-1... 15-Feb-11 A 1PPIP122 Bids received 15-Feb-1... 31-Oct-11 A 1PPIP123 TBA / CBA 15-Feb-1... 15-Feb-11 A 5PPIP124 Ordering for Pipes -2nd MTO 15-Feb-1... 15-Feb-11 A 30PPIP130 Mfg and Delivery at site- 2nd MTO-A3 15-Feb-1... 14-Nov-12 A 70

Fittings / FlangesFittings / Flanges 12-Oct-1... 04-Jul-13 193PPIP140 Issue Enquiry 12-Oct-1... 13-Oct-10 A 1PPIP142 Bids received 13-Oct-1... 30-Oct-10 A 10PPIP143 TBA / CBA 03-Nov-1... 06-Nov-10 A 5PPIP144 Ordering for Fitting / Flanges 09-Nov-1... 11-Apr-11 A 25PPIP150 Mfg and Del at site- Fittings / Flanges 15-Apr-1... 04-Jul-13 90

Gate / Ball ValveGate / Ball Valve 27-Sep-1... 22-Jul-13 301PRE320 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1PRE322 Bids received 28-Sep-1... 16-Oct-10 A 8PRE323 TBA / CBA 16-Oct-1... 23-Oct-10 A 8PRE324 Ordering of Ball / Gate Valve 15-Nov-1... 16-Mar-11 A 14PRE330 Mfg and Del at site- Ball and Gate Valve 25-May-1... 22-Jul-13 180

ELECTRICALELECTRICAL 21-Sep-1... 20-Sep-13 438

6.6KV Switchgear6.6KV Switchgear 23-Sep-1... 08-May-12 A 177PELE131 Issue Enquiry for 6.6KV Switchgear 23-Sep-1... 24-Sep-10 A 1PELE132 Bids received 30-Sep-1... 15-Oct-10 A 7PELE133 TBA / CBA 15-Oct-1... 24-Nov-10 A 15PELE134 Ordering of Switchgear 24-Nov-1... 01-Dec-10 A 12PELE135 Mfg and Del at site- 6.6KV Switchgear 02-Dec-1... 08-May-12 A 220

11KV Switchgear11KV Switchgear 22-Sep-1... 13-Jul-12 A 184PELE120 Issue Enquiry 22-Sep-1... 23-Sep-10 A 1PELE122 Bids received 30-Sep-1... 15-Oct-10 A 10PELE124 TBA / CBA 15-Oct-1... 24-Nov-10 A 12PELE125 Ordering of Switchgear 25-Nov-1... 01-Dec-10 A 22

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 17 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 18 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationPELE130 Mfg and Del at site-11KV Switchgear 02-Dec-1... 13-Jul-12 A 220

Distribution TransformerDistribution Transformer 21-Sep-1... 12-Mar-12 A 192EPR130 Preparation of Detail specifications, data sheets, standard drawings and documents f... 28-Oct-1... 03-Feb-11 A 30PELE151 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1PELE152 Bids received 05-Oct-1... 15-Oct-10 A 8PELE153 TBA / CBA 19-Oct-1... 24-Nov-10 A 20PELE154 Ordering of Transformer 24-Nov-1... 01-Dec-10 A 8PELE155 Mfg and Del at site-Distribution Transformer 02-Dec-1... 12-Mar-12 A 240

415 V Panel415 V Panel 22-Sep-1... 13-Nov-12 A 177PELE100 Issue Enquiry 22-Sep-1... 23-Sep-10 A 1PELE102 Bids received 04-Oct-1... 15-Oct-10 A 7PELE104 TBA / CBA 15-Oct-1... 24-Nov-10 A 18PELE105 Ordering of Panel 25-Nov-1... 01-Dec-10 A 8PELE110 Mfg and Del at site- Panel 02-Dec-1... 13-Nov-12 A 220

Power TransformerPower Transformer 21-Sep-1... 12-Nov-12 A 201PELE140 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1PELE141 Bids received 04-Oct-1... 13-Nov-10 A 10PELE142 TBA / CBA 13-Nov-1... 24-Nov-10 A 20PELE143 Ordering of Power Transformer 24-Nov-1... 31-Dec-10 A 8PELE150 Mfg and Del at site-Power transformer 31-Dec-1... 12-Nov-12 A 210

DG SetsDG Sets 21-Sep-1... 21-Apr-12 A 248PELE160 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1PELE162 Bids received 04-Oct-1... 12-Nov-10 A 8PELE163 TBA / CBA 13-Nov-1... 15-Dec-10 A 20PELE164 Ordering of DG sets 16-Dec-1... 14-Jan-11 A 10PELE170 Mfg and Del at site-DG sets 14-Jan-1... 21-Apr-12 A 180

CablesCables 21-Sep-1... 03-Dec-12 A 152PELE180 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1PELE182 Bids received 09-Oct-1... 15-Oct-10 A 7PELE183 TBA / CBA 15-Oct-1... 22-Nov-10 A 12PELE184 Ordering of Cables 29-Nov-1... 30-Dec-10 A 25PELE190 Mfg and Del at site-Cable 30-Dec-1... 03-Dec-12 A 150

UPS / Battery ChargerUPS / Battery Charger 04-Oct-1... 05-Nov-11 A 227PELE200 Issue Enquiry 04-Oct-1... 04-Oct-10 A 1PELE202 Bids received 04-Oct-1... 11-Oct-10 A 7PELE203 TBA / CBA 11-Oct-1... 23-Dec-10 A 20PELE204 Ordering of UPS and battery charger 23-Dec-1... 11-Feb-11 A 8PELE210 Mfg and Del at site-UPS and Battery charger 28-Feb-1... 05-Nov-11 A 175

Heat Tracing SystemHeat Tracing System 25-Nov-1... 20-Sep-13 433PELE220 Issue Enquiry 25-Nov-1... 25-Nov-10 A 1PELE222 Bids received 26-Nov-1... 30-Nov-10 A 8PELE223 TBA / CBA 01-Dec-1... 13-May-11 A 18PELE224 Ordering of Heat Tracing System 13-May-1... 21-Dec-11 A 10PELE230 Mfg and Del at site-Heat tracing 15-Nov-1... 20-Sep-13 145

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 19 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 20 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCP SystemCP System 04-Nov-1... 30-Jan-12 A 196

PELE240 Issue Enquiry 04-Nov-1... 04-Nov-10 A 1PELE242 Bids received 05-Nov-1... 25-Nov-10 A 8PELE243 TBA / CBA 25-Nov-1... 03-Jan-11 A 20PELE244 Ordering of CP System 03-Jan-1... 04-Feb-11 A 10PELE250 Mfg and Del at site-CP System 15-Feb-1... 30-Jan-12 A 150

Electrical Bulk MaterialElectrical Bulk Material 04-Oct-1... 01-Jul-13 187PELE260 Issue Enquiry 04-Oct-1... 06-Oct-10 A 2PELE262 Bids received 30-Oct-1... 06-Nov-10 A 8PELE263 TBA / CBA 06-Nov-1... 04-Feb-11 A 15PELE264 Ordering of Electrical Bulk material (Cable Tray, Switches, DB etc.) 17-Jan-1... 14-Feb-11 A 20PELE270 Mfg and Del at site-Electrical Bulk material 17-Feb-1... 01-Jul-13 120

NGRNGR 01-Oct-1... 31-Dec-10 A 149PELE280 Issue Enquiry 01-Oct-1... 02-Oct-10 A 1PELE282 Bids received 02-Oct-1... 11-Oct-10 A 8PELE283 TBA / CBA 11-Oct-1... 25-Nov-10 A 20PELE284 Ordering of NGR 26-Nov-1... 17-Dec-10 A 10PELE290 Mfg and Del at site-NGR 18-Dec-1... 31-Dec-10 A 130

INSTRUMENTATIONINSTRUMENTATION 21-Sep-1... 05-Aug-13 452

Tank Farm Management System (TFMS)Tank Farm Management System (TFMS) 22-Sep-1... 30-Nov-12 A 145PINS100 Issue Enquiry 22-Sep-1... 22-Sep-10 A 1PINS102 Bids received 01-Oct-1... 15-Nov-10 A 10PINS103 TBA / CBA 15-Nov-1... 24-Nov-10 A 10PINS104 Ordering of TFMS 26-Nov-1... 03-Jan-11 A 15PINS110 Mfg and Del at site-TFMS 03-Jan-1... 30-Nov-12 A 150

Control Valve / MOV/On-Off /ESVControl Valve / MOV/On-Off /ESV 23-Sep-1... 05-Aug-13 249PINS120 Issue Enquiry 23-Sep-1... 23-Sep-10 A 1PINS122 Bids received 14-Oct-1... 18-Nov-10 A 8PINS123 TBA / CBA 18-Nov-1... 28-Dec-10 A 8PINS124 Ordering of Control valve/On Off Valve/ESV/MOV's 28-Dec-1... 10-Feb-11 A 20PINS130 Mfg and Del at site-Control Valve/MOV's /On off valves/ESV 15-Feb-1... 05-Aug-13 230

Instrumentation Bulk itemsInstrumentation Bulk items 02-Oct-1... 15-Jul-13 186PINS140 Issue Enquiry 02-Oct-1... 02-Oct-10 A 1PINS142 Bids received 08-Oct-1... 10-Nov-10 A 10PINS143 TBA / CBA 12-Nov-1... 07-Feb-11 A 8PINS144 Ordering of Instruments Bulk item 29-Dec-1... 01-Mar-11 A 25PINS150 Mfg and Del at site-Instrumentation Bulk items 15-Mar-1... 15-Jul-13 150

Instrument CablesInstrument Cables 21-Sep-1... 21-Jul-13 237PINS160 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1PINS162 Bids received 09-Oct-1... 19-Oct-10 A 10PINS163 TBA / CBA 19-Oct-1... 16-Dec-10 A 8PINS164 Ordering for Instrument Cable 25-Nov-1... 26-Feb-11 A 25PINS170 Mfg and Del at site-Instrument Cable 11-Apr-1... 21-Jul-13 150

Instrustion Detection SystemInstrustion Detection System 16-Jan-1... 13-Apr-12 A 156

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 21 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 22 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationPINS172 Bids received 13-Feb-1... 13-Feb-11 A 10PINS173 TBA / CBA 25-Mar-1... 25-Mar-11 A 8PINS174 Ordering for Instrusion Detection System 04-Apr-1... 04-Apr-11 A 25PINS180 Issue Enquiry 16-Jan-1... 16-Jan-11 A 1PINS190 Mfg and Del at site-Instrusion Detection System 05-Apr-1... 13-Apr-12 A 180

Fire & Gas Detection SystemFire & Gas Detection System 12-Oct-1... 20-Jul-13 236PINS182 Bids received 17-Dec-1... 20-Dec-10 A 10PINS183 TBA / CBA 19-Oct-1... 16-Dec-10 A 8PINS184 Ordering for Fire & Gas Detection System 25-Nov-1... 26-Feb-11 A 25PINS200 Issue Enquiry 12-Oct-1... 13-Oct-10 A 1PINS210 Mfg and Del at site-Fire & Gas Detection System 11-Apr-1... 20-Jul-13 155

Nitrogen Blanketing ValvesNitrogen Blanketing Valves 19-Nov-1... 01-May-12 A 157PINS192 Bids received 17-Jan-1... 27-Jan-11 A 10PINS193 TBA / CBA 27-Jan-1... 16-Mar-11 A 8PINS194 Ordering for Nitrogen Blanketing Valves 17-Mar-1... 09-Jun-11 A 25PINS220 Issue Enquiry 19-Nov-1... 19-Nov-10 A 1PINS230 Mfg and Del at site-Nitrogen Blanketing Valves 20-Jun-1... 01-May-12 A 180

Instruments Cable Trays / ConduitsInstruments Cable Trays / Conduits 02-Jan-1... 10-Jun-13 93PINS202 Bids received 25-Jan-1... 31-Jan-12 A 10PINS203 TBA / CBA 02-Feb-1... 15-Feb-12 A 8PINS204 Ordering for Instrument Cable Trays / Conduits 16-Mar-1... 17-Apr-12 A 25PINS240 Issue Enquiry 02-Jan-1... 02-Jan-12 A 1PINS250 Mfg and Del at site-Instrument Cable Trays / Conduits 23-Apr-1... 10-Jun-13 69

In-Line InstrumentsIn-Line Instruments 16-Nov-1... 23-Sep-11 A 170PINS212 Bids received 19-Nov-1... 29-Nov-10 A 30PINS213 TBA / CBA 30-Nov-1... 31-Dec-10 A 8PINS214 Ordering for In-line Instruments 03-Jan-1... 25-Jan-11 A 25PINS260 Issue Enquiry 16-Nov-1... 17-Nov-10 A 1PINS270 Mfg and Del at site-In-line Instruments 01-Feb-1... 23-Sep-11 A 180

Additional / Procurement- Fire Fighting ChangesAdditional / Procurement- Fire Fighting Changes 10-Nov-1... 27-Aug-13 599FIRE WATER PUMPS (3 NOS)FIRE WATER PUMPS (3 NOS) 31-May-1... 14-Aug-12 A 216

MDPP-FPSC-P-0001ISSUE ENQUIRY 31-May-1... 31-May-11 A 1MDPP-FPSC-P-0011RECEIPT BIDS 01-Jun-1... 01-Jun-11 A 1MDPP-FPSC-P-0021TECHNICAL BID ANALYSIS 02-Jun-1... 06-Jun-11 A 1MDPP-FPSC-P-0031COMMERCIAL BID ANALYSIS 06-Jun-1... 07-Jun-11 A 1MDPP-FPSC-P-0041ISSUE LOI 07-Jun-1... 08-Jun-11 A 1MDPP-FPSC-P-0051MANUFACTURING & DELIVERY AT SITE 01-Jul-11 A 14-Aug-12 A 250MDPP-FPSC-P-0061ISSUE PO / PR TO VENDOR 08-Jun-1... 09-Jun-11 A 1MDPP-FPSC-P-0071RECEIPT OF VENDOR DRAWINGS 07-Jul-11 A 10-Feb-12 A 15MDPP-FPSC-P-0081APPROVAL OF VENDOR DRAWINGS 05-Dec-1... 19-Mar-12 A 15

JOCKEY PUMP (2 NOS)JOCKEY PUMP (2 NOS) 31-May-1... 20-Mar-12 A 217MDPP-FPSC-P-0251ISSUE ENQUIRY 31-May-1... 31-May-11 A 1MDPP-FPSC-P-0261RECEIPT BIDS 01-Jun-1... 03-Jun-11 A 1MDPP-FPSC-P-1321TECHNICAL BID ANALYSIS 03-Jun-1... 06-Jun-11 A 1

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 23 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 24 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationMDPP-FPSC-P-1331COMMERCIAL BID ANALYSIS 06-Jun-1... 06-Jun-11 A 1MDPP-FPSC-P-1341ISSUE LOI 06-Jun-1... 07-Jun-11 A 1MDPP-FPSC-P-1351MANUFACTURING & DELIVERY AT SITE 20-Jul-11 A 04-Oct-11 A 230MDPP-FPSC-P-1361ISSUE PO / PR TO VENDOR 08-Jun-1... 09-Jun-11 A 1MDPP-FPSC-P-1371RECEIPT OF VENDOR DRAWINGS 07-Jul-11 A 05-Jan-12 A 15MDPP-FPSC-P-1381APPROVAL OF VENDOR DRAWINGS 05-Dec-1... 20-Mar-12 A 15

FOAM CONCENTRATE TANKFOAM CONCENTRATE TANK 03-Jan-1... 26-Mar-12 A 260MDPP-FPSC-P-0091ISSUE ENQUIRY 03-Jan-1... 03-Jan-11 A 1MDPP-FPSC-P-0101RECEIPT BIDS 28-Feb-1... 28-Feb-11 A 26MDPP-FPSC-P-0111TECHNICAL BID ANALYSIS 14-Mar-1... 06-Jun-11 A 1MDPP-FPSC-P-0121COMMERCIAL BID ANALYSIS 06-Jun-1... 10-Jun-11 A 1MDPP-FPSC-P-0131ISSUE LOI 10-Jun-1... 13-Jun-11 A 1MDPP-FPSC-P-0141MANUFACTURING & DELIVERY AT SITE 15-Feb-1... 26-Mar-12 A 75MDPP-FPSC-P-0151ISSUE PO / PR TO VENDOR 13-Jun-1... 13-Jun-11 A 1MDPP-FPSC-P-0161RECEIPT OF VENDOR DRAWINGS 30-Jun-1... 27-Dec-11 A 18MDPP-FPSC-P-0171APPROVAL OF VENDOR DRAWINGS 26-Dec-1... 13-Feb-12 A 15

FIRE WATER TANK- PLATE'SFIRE WATER TANK- PLATE'S 15-Dec-1... 31-May-12 A 140MDPP-FPSC-P-1081ISSUE ENQUIRY 15-Dec-1... 15-Dec-11 A 1MDPP-FPSC-P-1091RECEIPT BIDS 16-Dec-1... 30-Dec-11 A 18MDPP-FPSC-P-1101TECHNICAL BID ANALYSIS 02-Jan-1... 03-Jan-12 A 1MDPP-FPSC-P-1111COMMERCIAL BID ANALYSIS 04-Jan-1... 04-Jan-12 A 1MDPP-FPSC-P-1121ISSUE LOI 16-Jan-1... 16-Jan-12 A 1MDPP-FPSC-P-1131MANUFACTURING & DELIVERY AT SITE 28-Mar-1... 31-May-12 A 90

FIRE PROTECTION SYSTEM-PIPESFIRE PROTECTION SYSTEM-PIPES 02-Aug-1... 23-Nov-11 A 156MDPP-FPSC-P-1141ISSUE ENQUIRY 02-Aug-1... 02-Aug-11 A 1MDPP-FPSC-P-1151RECEIPT BIDS 03-Aug-1... 05-Aug-11 A 18MDPP-FPSC-P-1161TECHNICAL BID ANALYSIS 05-Aug-1... 05-Aug-11 A 1MDPP-FPSC-P-1171COMMERCIAL BID ANALYSIS 08-Aug-1... 08-Aug-11 A 1MDPP-FPSC-P-1181ISSUE LOI 09-Aug-1... 09-Aug-11 A 1MDPP-FPSC-P-1191MANUFACTURING & DELIVERY AT SITE 11-Aug-1... 23-Nov-11 A 120

FIRE PROTECTION SYSTEM-FITTINGSFIRE PROTECTION SYSTEM-FITTINGS 28-Jul-11 A 08-May-12 A 187MDPP-FPSC-P-1201ISSUE ENQUIRY 28-Jul-11 A 28-Jul-11 A 1MDPP-FPSC-P-1211RECEIPT BIDS 29-Jul-11 A 05-Aug-11 A 18MDPP-FPSC-P-1221TECHNICAL BID ANALYSIS 05-Aug-1... 09-Aug-11 A 1MDPP-FPSC-P-1231COMMERCIAL BID ANALYSIS 09-Aug-1... 12-Aug-11 A 1MDPP-FPSC-P-1241ISSUE LOI 09-Sep-1... 12-Sep-11 A 1MDPP-FPSC-P-1251MANUFACTURING & DELIVERY AT SITE 15-Mar-1... 08-May-12 A 30

FIRE PROTECTION SYSTEM-FLANGES & MISC.FIRE PROTECTION SYSTEM-FLANGES & MISC. 29-Jul-11 A 05-Jun-12 A 214MDPP-FPSC-P-1261ISSUE ENQUIRY 29-Jul-11 A 29-Jul-11 A 1MDPP-FPSC-P-1271RECEIPT BIDS 29-Jul-11 A 05-Aug-11 A 18MDPP-FPSC-P-1281TECHNICAL BID ANALYSIS 05-Aug-1... 09-Aug-11 A 1MDPP-FPSC-P-1291COMMERCIAL BID ANALYSIS 09-Aug-1... 12-Aug-11 A 1MDPP-FPSC-P-1301ISSUE LOI 09-Sep-1... 15-Sep-11 A 1MDPP-FPSC-P-1311MANUFACTURING & DELIVERY AT SITE 19-Apr-1... 05-Jun-12 A 40

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 25 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 26 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationFOAM CONCENTRATEFOAM CONCENTRATE 24-Jan-1... 15-May-13 195

MDPP-FPSC-P-0181ISSUE ENQUIRY 24-Jan-1... 24-Jan-11 A 1MDPP-FPSC-P-0191RECEIPT BIDS 26-Jan-1... 28-Jan-11 A 26MDPP-FPSC-P-0201TECHNICAL BID ANALYSIS 31-Jan-1... 31-Jan-11 A 1MDPP-FPSC-P-0211COMMERCIAL BID ANALYSIS 02-Feb-1... 02-Feb-11 A 1MDPP-FPSC-P-0221ISSUE LOI 03-Feb-1... 24-Feb-11 A 1MDPP-FPSC-P-0231PRODUCTION & DELIVERY AT SITE 30-May-1... 15-May-13 90MDPP-FPSC-P-0241ISSUE PO / PR TO VENDOR 25-Feb-1... 28-Feb-11 A 1

FOAM SYSTEM ACCESSORIESFOAM SYSTEM ACCESSORIES 10-Nov-1... 27-Aug-13 379MDPP-FPSC-P-0271ISSUE ENQUIRY 14-Nov-1... 21-Nov-11 A 1MDPP-FPSC-P-0281RECEIPT BIDS 16-Nov-1... 25-Nov-11 A 20MDPP-FPSC-P-0291TECHNICAL BID ANALYSIS 30-Nov-1... 30-Nov-11 A 1MDPP-FPSC-P-0301COMMERCIAL BID ANALYSIS 01-Dec-1... 01-Dec-11 A 1MDPP-FPSC-P-0311ISSUE LOI 05-Dec-1... 06-Dec-11 A 1MDPP-FPSC-P-0321MANUFACTURING & DELIVERY AT SITE 14-Dec-1... 27-Aug-13 105MDPP-FPSC-P-0331ISSUE PO / PR TO VENDOR 07-Dec-1... 07-Dec-11 A 1MDPP-FPSC-P-0341RECEIPT OF VENDOR DRAWINGS 10-Nov-1... 21-Nov-11 A 18MDPP-FPSC-P-0351APPROVAL OF VENDOR DRAWINGS 30-Nov-1... 30-Nov-11 A 15

DELUGE VALVESDELUGE VALVES 19-Jan-1... 06-Nov-12 A 433MDPP-FPSC-P-0361ISSUE ENQUIRY 12-Dec-1... 12-Dec-11 A 1MDPP-FPSC-P-0371RECEIPT BIDS 13-Dec-1... 13-Jan-12 A 26MDPP-FPSC-P-0381TECHNICAL BID ANALYSIS 14-Jan-1... 17-Jan-12 A 1MDPP-FPSC-P-0391COMMERCIAL BID ANALYSIS 19-Jan-1... 02-Feb-11 A 1MDPP-FPSC-P-0401ISSUE LOI 08-Mar-1... 07-Jun-12 A 1MDPP-FPSC-P-0411MANUFACTURING & DELIVERY AT SITE 11-Jul-12 A 06-Nov-12 A 120MDPP-FPSC-P-0421ISSUE PO / PR TO VENDOR 02-Mar-1... 02-Mar-11 A 1MDPP-FPSC-P-0431RECEIPT OF VENDOR DRAWINGS 04-Feb-1... 08-Feb-11 A 18MDPP-FPSC-P-0441APPROVAL OF VENDOR DRAWINGS 13-Feb-1... 15-Feb-11 A 12

STRAINERSSTRAINERS 02-Mar-1... 12-Aug-13 358MDPP-FPSC-P-0451ISSUE ENQUIRY 02-Mar-1... 02-Mar-11 A 1MDPP-FPSC-P-0461RECEIPT BIDS 04-Mar-1... 10-Mar-11 A 15MDPP-FPSC-P-0471TECHNICAL BID ANALYSIS 11-Mar-1... 12-Mar-11 A 1MDPP-FPSC-P-0481COMMERCIAL BID ANALYSIS 13-Mar-1... 14-Mar-11 A 1MDPP-FPSC-P-0491ISSUE LOI 15-Mar-1... 15-Mar-11 A 1MDPP-FPSC-P-0501MANUFACTURING & DELIVERY AT SITE 12-Apr-1... 12-Aug-13 90MDPP-FPSC-P-0511ISSUE PO / PR TO VENDOR 15-Mar-1... 15-Mar-11 A 1MDPP-FPSC-P-0521RECEIPT OF VENDOR DRAWINGS 03-Mar-1... 07-Mar-11 A 18MDPP-FPSC-P-0531APPROVAL OF VENDOR DRAWINGS 04-Mar-1... 04-Mar-11 A 15

GATE VALVESGATE VALVES 02-Aug-1... 15-Jul-13 222MDPP-FPSC-P-0541ISSUE ENQUIRY 02-Aug-1... 02-Aug-11 A 1MDPP-FPSC-P-0551RECEIPT BIDS 03-Aug-1... 05-Aug-11 A 20MDPP-FPSC-P-0561TECHNICAL BID ANALYSIS 15-Aug-1... 22-Aug-11 A 1MDPP-FPSC-P-0571COMMERCIAL BID ANALYSIS 24-Aug-1... 25-Aug-11 A 1MDPP-FPSC-P-0581ISSUE LOI 02-Sep-1... 05-Sep-11 A 1

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 27 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 28 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationMDPP-FPSC-P-0591MANUFACTURING & DELIVERY AT SITE 31-Oct-1... 15-Jul-13 220MDPP-FPSC-P-0601ISSUE PO / PR TO VENDOR 03-Aug-1... 09-Aug-11 A 1MDPP-FPSC-P-0611RECEIPT OF VENDOR DRAWINGS 04-Aug-1... 11-Aug-11 A 18MDPP-FPSC-P-0621APPROVAL OF VENDOR DRAWINGS 19-Aug-1... 19-Aug-11 A 15

CHECK VALVESCHECK VALVES 03-Aug-1... 27-Jun-13 203MDPP-FPSC-P-0631ISSUE ENQUIRY 03-Aug-1... 03-Aug-11 A 1MDPP-FPSC-P-0641RECEIPT BIDS 04-Aug-1... 08-Aug-11 A 26MDPP-FPSC-P-0651TECHNICAL BID ANALYSIS 10-Aug-1... 16-Aug-11 A 1MDPP-FPSC-P-0661COMMERCIAL BID ANALYSIS 17-Aug-1... 18-Aug-11 A 1MDPP-FPSC-P-0671ISSUE LOI 05-Sep-1... 05-Sep-11 A 1MDPP-FPSC-P-0681MANUFACTURING & DELIVERY AT SITE 13-Sep-1... 27-Jun-13 72MDPP-FPSC-P-0691ISSUE PO / PR TO VENDOR 16-Aug-1... 04-Sep-11 A 1MDPP-FPSC-P-0701RECEIPT OF VENDOR DRAWINGS 23-Aug-1... 25-Aug-11 A 18MDPP-FPSC-P-0711APPROVAL OF VENDOR DRAWINGS 29-Aug-1... 29-Aug-11 A 15

ELECTROMAGNETIC FLOW METERELECTROMAGNETIC FLOW METER 03-Jan-1... 22-May-13 239MDPP-FPSC-P-0721ISSUE ENQUIRY 03-Jan-1... 03-Jan-11 A 1MDPP-FPSC-P-0731RECEIPT BIDS 04-Jan-1... 17-Jan-11 A 26MDPP-FPSC-P-0741TECHNICAL BID ANALYSIS 17-Jan-1... 28-Jan-11 A 1MDPP-FPSC-P-0751COMMERCIAL BID ANALYSIS 31-Jan-1... 08-Feb-11 A 1MDPP-FPSC-P-0761ISSUE LOI 28-Jan-1... 29-Jan-11 A 1MDPP-FPSC-P-0771MANUFACTURING & DELIVERY AT SITE 06-Mar-1... 22-May-13 150MDPP-FPSC-P-0781ISSUE PO / PR TO VENDOR 24-Feb-1... 24-Feb-11 A 1MDPP-FPSC-P-0791RECEIPT OF VENDOR DRAWINGS 16-Jan-1... 24-Jan-11 A 18MDPP-FPSC-P-0801APPROVAL OF VENDOR DRAWINGS 26-Jan-1... 31-Jan-11 A 15

PLC FOR PUMPSPLC FOR PUMPS 11-Jan-1... 17-Aug-11 A 482MDPP-FPSC-P-0811ISSUE ENQUIRY 11-Jan-1... 11-Jan-11 A 1MDPP-FPSC-P-0821RECEIPT BIDS 14-Jan-1... 19-Jan-11 A 26MDPP-FPSC-P-0831TECHNICAL BID ANALYSIS 25-Jan-1... 25-Jan-11 A 1MDPP-FPSC-P-0841COMMERCIAL BID ANALYSIS 02-Feb-1... 04-Feb-11 A 1MDPP-FPSC-P-0851ISSUE LOI 07-Feb-1... 10-Feb-11 A 1MDPP-FPSC-P-0861MANUFACTURING & DELIVERY AT SITE 09-Feb-1... 17-Aug-11 A 137MDPP-FPSC-P-0871ISSUE PO / PR TO VENDOR 25-Jan-1... 26-Jan-11 A 1MDPP-FPSC-P-0881RECEIPT OF VENDOR DRAWINGS 21-Jan-1... 30-Jan-11 A 18MDPP-FPSC-P-0891APPROVAL OF VENDOR DRAWINGS 28-Jan-1... 01-Feb-11 A 12

RUBBER EXPANSION BELLOWRUBBER EXPANSION BELLOW 09-Mar-1... 13-Oct-12 A 114MDPP-FPSC-P-0901ISSUE ENQUIRY 09-Mar-1... 09-Mar-11 A 1MDPP-FPSC-P-0911RECEIPT BIDS 10-Mar-1... 21-Mar-11 A 26MDPP-FPSC-P-0921TECHNICAL BID ANALYSIS 29-Mar-1... 04-Apr-11 A 1MDPP-FPSC-P-0931COMMERCIAL BID ANALYSIS 06-Apr-1... 08-Apr-11 A 1MDPP-FPSC-P-0941ISSUE LOI 15-Apr-1... 15-Apr-11 A 1MDPP-FPSC-P-0951MANUFACTURING & DELIVERY AT SITE 31-May-1... 13-Oct-12 A 120MDPP-FPSC-P-0961ISSUE PO / PR TO VENDOR 15-Apr-1... 15-Apr-11 A 1MDPP-FPSC-P-0971RECEIPT OF VENDOR DRAWINGS 17-Apr-1... 30-Apr-11 A 18MDPP-FPSC-P-0981APPROVAL OF VENDOR DRAWINGS 01-May-1... 11-May-11 A 15

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 29 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 30 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCP SYSTEMCP SYSTEM 10-Mar-1... 20-Jul-11 A 157

MDPP-FPSC-P-0991ISSUE ENQUIRY 10-Mar-1... 10-Mar-11 A 1MDPP-FPSC-P-1001RECEIPT BIDS 14-Mar-1... 14-Mar-11 A 1MDPP-FPSC-P-1011TECHNICAL BID ANALYSIS 15-Mar-1... 17-Mar-11 A 1MDPP-FPSC-P-1021COMMERCIAL BID ANALYSIS 19-Mar-1... 22-Mar-11 A 1MDPP-FPSC-P-1031ISSUE LOI / AMMENDMENT 23-Mar-1... 23-Mar-11 A 1MDPP-FPSC-P-1041MANUFACTURING & DELIVERY AT SITE 21-Apr-1... 20-Jul-11 A 100MDPP-FPSC-P-1051ISSUE PO / PR TO VENDOR 23-Mar-1... 23-Mar-11 A 1MDPP-FPSC-P-1061RECEIPT OF VENDOR DRAWINGS 31-Mar-1... 07-Apr-11 A 18MDPP-FPSC-P-1071APPROVAL OF VENDOR DRAWINGS 09-Apr-1... 12-Apr-11 A 13

PROCUREMENT- FREE ISSUE MATERIALPROCUREMENT- FREE ISSUE MATERIAL 06-Jun-1... 01-Jun-13 679PRFI001 Delivery at Site of GT 06-Jun-1... 29-Jun-11 A 20PRFI011 Delivery at Site of Export Booster Pumps 12-Jul-11 A 31-Jul-11 A 20PRFI021 Delivery at Site of Custody Transfer Metering system 05-Jul-11 A 20-Jul-11 A 20PRFI031 Delivery at Site of Butterfly/Ball Valves above 24" size 15-May-13* 01-Jun-13 20

CONSTRUCTIONCONSTRUCTION 07-Oct-1... 06-Jan-14 891

CNCM001 Site Mobilization 07-Oct-1... 28-Oct-10 A 20CNCM011 Camp Establishment 28-Oct-1... 03-Dec-10 A 30

MOBILISATIONMOBILISATION 28-Oct-1... 22-Nov-11 A 407CNM100 Mobilise Civil Contractor - For Roads, Dyke Wall 30-Oct-1... 18-Nov-10 A 22CNM105 Mobilise Civil Contractor - For Packages (foundations etc.) 16-Dec-1... 28-Dec-10 A 22CNM110 Mobilise Building Contractor 12-Nov-1... 27-Dec-10 A 12CNM130 Mobilise Mechanical / Piping Contractor 07-Apr-1... 30-Apr-11 A 15CNM140 Mobilization of Batching Plant-II 28-Oct-1... 03-Dec-10 A 45CNM150 Mobilise Contractor- Instrumentation Contractor 24-May-1... 13-Jun-11 A 20CNM160 Mobilise Electrical Contractor 03-May-1... 25-May-11 A 12CNM180 Mobilise Insulation & C.P. Contractor 02-Nov-1... 22-Nov-11 A 15CNM190 Mobilise Plant and Machinery at site 31-Dec-1... 02-Mar-11 A 90

PHASE-1PHASE-1 23-Nov-1... 06-Jan-14 846

THREE OIL TANKS (TAG NO.-2,3,4)THREE OIL TANKS (TAG NO.-2,3,4) 11-Feb-1... 04-May-13 A 357Construction of Vertical Dyke Wall V-2Construction of Vertical Dyke Wall V-2 11-Feb-1... 07-Jun-11 A 183

CNCV550 Release of Front 11-Feb-11 A 0CNCV592 RCC 17-Mar-1... 07-Jun-11 A 72CNCV610 Excavation 22-Feb-1... 28-Feb-11 A 15CNCV651 PCC 02-Mar-1... 09-Mar-11 A 15

Construction of Horizontal Dyke Wall H-1Construction of Horizontal Dyke Wall H-1 18-Apr-1... 06-Nov-12 A 273CNCV270 Release of Front 15-Feb-12 A 0CNCV331 PCC 11-Mar-1... 03-Sep-12 A 101CNCV332 RCC 18-Apr-1... 06-Nov-12 A 150CNCV390 Excavation 22-Feb-1... 18-Jul-12 A 97

Construction of Vertical Dyke Wall V-4Construction of Vertical Dyke Wall V-4 15-Jul-12 A 03-Nov-12 A 68CNCV612 RCC 10-Sep-1... 03-Nov-12 A 79CNCV640 Release of Front 15-Jul-12 A 0CNCV650 Excavation 30-Jul-12 A 08-Aug-12 A 15

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 31 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 32 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV671 PCC 13-Aug-1... 29-Aug-12 A 15

Construction of Vertical Dyke Wall V-3Construction of Vertical Dyke Wall V-3 15-Feb-1... 11-Jun-12 A 317CNCV602 RCC 23-Mar-1... 11-Jun-12 A 79CNCV620 Release of Front 15-Feb-12 A 0CNCV630 Excavation 22-Feb-1... 28-Feb-12 A 15CNCV661 PCC 02-Mar-1... 15-Mar-12 A 15

Construction of Vertical Dyke Wall V-5Construction of Vertical Dyke Wall V-5 17-Feb-1... 25-Jun-12 A 320CNCV622 RCC 21-Mar-1... 25-Jun-12 A 80CNCV660 Release of Front 17-Feb-12 A 0CNCV670 Excavation 20-Feb-1... 29-Feb-12 A 15CNCV681 PCC 06-Mar-1... 16-Mar-12 A 15

Construction of Horizontal Dyke Wall H-2Construction of Horizontal Dyke Wall H-2 15-Feb-1... 18-Aug-12 A 274CNCV280 Release of Front 15-Feb-12 A 0CNCV352 RCC 06-Mar-1... 18-Aug-12 A 152CNCV400 Excavation 21-Feb-1... 27-Mar-12 A 97CNCV401 PCC 01-Mar-1... 03-Jul-12 A 101

Construction of Horizontal Dyke Wall H-3Construction of Horizontal Dyke Wall H-3 15-Feb-1... 04-Dec-12 A 200CNCV310 Release of Front 15-Feb-12 A 0CNCV362 RCC 31-Jul-12 A 04-Dec-12 A 84CNCV410 Excavation 15-Feb-1... 11-Apr-12 A 35CNCV411 PCC 31-May-1... 20-Jun-12 A 65

Construction of Vertical Dyke Wall V-8Construction of Vertical Dyke Wall V-8 07-Feb-1... 04-Aug-12 A 247CNCV382 RCC 30-May-1... 04-Aug-12 A 90CNCV431 PCC 30-Mar-1... 05-Jun-12 A 75CNCV440 Release of Front 07-Feb-12 A 0CNCV450 Excavation 10-Feb-1... 22-Mar-12 A 45

Construction of Vertical Dyke Wall V-7Construction of Vertical Dyke Wall V-7 09-Feb-1... 03-Apr-13 A 103CNCV372 RCC 02-May-1... 21-Aug-12 A 90CNCV420 Release of Front 09-Feb-12 A 0CNCV421 PCC 11-Apr-1... 11-Jul-12 A 75CNCV430 Excavation 15-Feb-1... 03-Apr-13 A 45

Construction of Vertical Dyke Wall V-6Construction of Vertical Dyke Wall V-6 16-Feb-1... 04-Sep-12 A 355CNCV402 RCC 12-Apr-1... 04-Sep-12 A 90CNCV451 PCC 30-Mar-1... 10-Jul-12 A 75CNCV480 Release of Front 16-Feb-12 A 0CNCV490 Excavation 22-Feb-1... 22-Mar-12 A 35

Construction of Vertical Dyke Wall V-1Construction of Vertical Dyke Wall V-1 26-Dec-1... 13-Jun-12 A 266CNCV392 RCC 14-Mar-1... 13-Jun-12 A 60CNCV441 PCC 24-Jan-1... 17-Apr-12 A 45CNCV460 Release of Front 26-Dec-11 A 0CNCV470 Excavation 02-Jan-1... 31-Jan-12 A 35

Construction of Vertical Dyke Wall V-9Construction of Vertical Dyke Wall V-9 18-Jan-1... 04-May-13 A 98CNCV412 RCC 02-Mar-1... 04-May-13 A 58CNCV461 PCC 29-Feb-1... 20-Mar-13 A 47

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 33 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 34 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV500 Release of Front 18-Jan-12 A 0CNCV510 Excavation 08-Feb-1... 04-Mar-12 A 35

EXPORT MANIFOLD,BOOSTER AND EXPORT PUMPS ETC (TAG-22,25 & 70)EXPORT MANIFOLD,BOOSTER AND EXPORT PUMPS ETC (TAG-22,25 & 70) 15-Jun-1... 25-Jun-13 482

Export Booster PumpsExport Booster Pumps 14-Nov-1... 31-May-12 A 182CNCV380 Excavation 14-Nov-1... 16-Nov-11 A 6CNCV385 Foundation 15-Nov-1... 07-Dec-11 A 21INT150 Installation of Export and Booster Pump 21-Apr-1... 31-May-12 A 31

Export & Booster Pump House (SHED)Export & Booster Pump House (SHED) 03-Oct-1... 25-Jun-13 334CNCV224 Brick works -deleted 31-May-1... 31-May-12 A 45CNCV232 Superstructure -deleted 31-May-1... 31-May-12 A 75CNCV233 Structural Fab.,Shot Blasting & primer Painting 29-May-1... 25-Jun-13 60CNCV234 Structural Erection & Final painting 12-Sep-1... 26-Oct-12 A 45CNCV251 Substructure 03-Oct-1... 10-Jan-12 A 60CNCV324 Sheet Fixing 08-Aug-1... 20-Sep-12 A 45CNCV445 Finishing (Paving,Elect. Inst.,Doors & Window fixing,Painting) 12-Jun-1... 15-Oct-12 A 80

Custody Transfer Metering (CTM)Custody Transfer Metering (CTM) 16-Nov-1... 15-Mar-12 A 68CNCV370 Excavation 16-Nov-1... 22-Nov-11 A 15CNCV375 Foundation 26-Dec-1... 17-Jan-12 A 31INT140 Installation of Custody Transfer Metering 15-Feb-1... 15-Mar-12 A 21

Panel Room for CTMPanel Room for CTM 19-Dec-1... 14-Nov-12 A 270CNCV242 Superstructure 01-Mar-1... 26-Mar-12 A 65CNCV253 Structural Fab.,Shot Blasting & primer Painting 01-May-1... 25-Jul-12 A 60CNCV474 Brick works 10-Apr-1... 13-Jun-12 A 45CNCV475 Finishing (Paving,Elect. Inst.,Doors & Window fixing,Painting) 25-Jun-1... 08-Aug-12 A 70CNCV484 Structural Erection & Final painting 12-Sep-1... 14-Nov-12 A 60CNCV494 Sheet Fixing 23-Oct-1... 07-Nov-12 A 30CNCV761 Substructure 19-Dec-1... 25-Feb-12 A 45

CTM Package ShedCTM Package Shed 15-Jun-1... 29-Nov-12 A 482CNCV181 Substructure 15-Jun-1... 25-Jan-12 A 60CNCV184 Sheet Fixing 01-Jun-1... 04-Aug-12 A 45CNCV192 Superstructure 26-Jan-1... 02-May-12 A 75CNCV193 Masonary 17-May-1... 19-Jun-12 A 45CNCV255 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 02-Jul-12 A 29-Nov-12 A 110CNCV691 Structural Fab.,Shot Blasting & primer Painting 26-Jan-1... 10-May-12 A 75CNCV701 Structural Erection. & final Painting 07-Aug-1... 23-Aug-12 A 110

LFO TANKS (TAG NO-44,45 & 46)LFO TANKS (TAG NO-44,45 & 46) 0LFO MANIFOLD,EXPORT PUMP (TAG NO-65,66 & 67)LFO MANIFOLD,EXPORT PUMP (TAG NO-65,66 & 67) 03-Oct-1... 19-Dec-12 A 357

Interface Storage tanksInterface Storage tanks 03-Oct-1... 31-May-12 A 80CNCV132 Excavation 03-Oct-1... 25-Nov-11 A 15CNCV134 Barbending 28-Oct-1... 22-Nov-11 A 25CNCV136 Form Work 28-Oct-1... 22-Nov-11 A 25CNCV138 RCC 29-Dec-1... 05-Feb-12 A 35CNCV140 Backfilling & Compaction 02-Apr-1... 31-May-12 A 8

Interface Transfer Pump BayInterface Transfer Pump Bay 06-Jul-12 A 30-Aug-12 A 222

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 35 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 36 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV158 RCC 14-Jul-12 A 14-Jul-12 A 35CNCV210 Backfilling & Compaction 19-Jul-12 A 28-Jul-12 A 10CNCV244 Barbending 09-Jul-12 A 11-Jul-12 A 3CNCV246 Form Work 11-Jul-12 A 13-Jul-12 A 25CNCV262 Excavation 06-Jul-12 A 11-Jul-12 A 15CNEQ180 Installation of Interface Transfer pump 08-Aug-1... 30-Aug-12 A 15

INTERFACE HOLDUP TANKINTERFACE HOLDUP TANK 01-Mar-1... 19-Dec-12 A 204CNME460 Fabtication of Tank 01-Mar-1... 02-Jul-12 A 90CNME470 Erection of Tank 15-Jun-1... 05-Nov-12 A 65CNME480 Hydrotesting of Tank 20-Nov-1... 30-Nov-12 A 10CNME490 Painting of Tank 01-Dec-1... 19-Dec-12 A 21

INTERFACE STORAGE TANK-DYKE WALLINTERFACE STORAGE TANK-DYKE WALL 10-Jul-12 A 29-Aug-12 A 53CNCV520 Excavation 10-Jul-12 A 14-Jul-12 A 11CNCV632 RCC & RELATED FACILITIES 02-Aug-1... 29-Aug-12 A 75CNCV711 PCC 13-Jul-12 A 31-Jul-12 A 21

INTERFACE HOLD UP TANK-DYKE WALLINTERFACE HOLD UP TANK-DYKE WALL 08-Aug-1... 22-Nov-12 A 111CNCV530 Excavation 08-Aug-1... 15-Aug-12 A 90CNCV642 RCC & RELATED FACILITIES 25-Oct-1... 14-Nov-12 A 120CNCV721 PCC 06-Sep-1... 22-Nov-12 A 90

DYKE WALL AROUND TANK -9,10,11DYKE WALL AROUND TANK -9,10,11 25-May-1... 07-Nov-12 A 131CNCV662 RCC & RELATED FACILITIES 16-Aug-1... 07-Nov-12 A 120CNCV680 Excavation 25-May-1... 14-Jul-12 A 90CNCV741 PCC 28-May-1... 28-Aug-12 A 90

AIR COMPRESSOR & PSA NITROGEN SYSTEM (TAG NO-12)AIR COMPRESSOR & PSA NITROGEN SYSTEM (TAG NO-12) 22-Jan-1... 20-Dec-12 A 380Air CompressorAir Compressor 22-Jan-1... 23-Aug-12 A 119

CNCV273 Earth Work 22-Jan-1... 24-Mar-12 A 26CNCV283 PCC 26-Mar-1... 26-Mar-12 A 36CNCV313 Barbending 26-Mar-1... 30-Mar-12 A 31CNCV323 Form Work 26-Mar-1... 30-Mar-12 A 31CNCV333 RCC 31-Mar-1... 31-Mar-12 A 46CNCV442 Back filling & Compaction 16-Apr-1... 23-Apr-12 A 11CNEQ120 Installation of Air Compressor 15-May-1... 23-Aug-12 A 61

Nitrogen PackageNitrogen Package 20-Mar-1... 17-Sep-12 A 295CNCV276 Earth Work 20-Mar-1... 24-Mar-12 A 26CNCV286 PCC 26-Mar-1... 26-Mar-12 A 31CNCV296 Barbending 26-Mar-1... 30-Mar-12 A 31CNCV306 Form Work 26-Mar-1... 30-Mar-12 A 31CNCV316 RCC 31-Mar-1... 16-May-12 A 46CNCV472 Back filling & Compaction 30-May-1... 05-Jun-12 A 11CNEQ130 Installation of Nitrogen Generation Package 21-Aug-1... 17-Sep-12 A 46

Air Compressor ShedAir Compressor Shed 22-Jan-1... 20-Dec-12 A 380CNCV343 Earth Work 22-Jan-1... 25-Mar-12 A 15CNCV353 PCC 26-Mar-1... 26-Mar-12 A 1CNCV363 Barbending 28-Mar-1... 02-Jul-12 A 30

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 37 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 38 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV373 Form Work 30-Mar-1... 13-Jul-12 A 30CNCV383 RCC 20-Feb-1... 19-Apr-12 A 40CNCV393 Structural Fab. Shot Blasting & Primer painting 15-Jun-1... 04-Sep-12 A 60CNCV403 Structural Erection & Final painting 26-Jul-12 A 04-Sep-12 A 40CNCV413 Metal Sheet Fixing & Side Cladding 17-Sep-1... 10-Oct-12 A 60CNCV423 Internal & External Painting 15-Nov-1... 20-Dec-12 A 50

FUEL GAS HANDLING (TAG NO-38)FUEL GAS HANDLING (TAG NO-38) 15-May-1... 02-Oct-12 A 298

Fuel Gas system foundation (KO Drum,Cartridge Filter, Electric Heater)Fuel Gas system foundation (KO Drum,Cartridge Filter, Electric Heater) 15-May-1... 02-Oct-12 A 298CNCV349 Earth Work 15-May-1... 30-May-12 A 26CNCV359 PCC 04-Jun-1... 14-Jun-12 A 6CNCV369 Form Work 20-Jun-1... 04-Jul-12 A 15CNCV379 RCC 10-Jul-12 A 18-Jul-12 A 16CNCV512 Back filling & Compaction 24-Jul-12 A 09-Aug-12 A 10CNEQ250 Installation of Fuel & Gas system 03-Sep-1... 02-Oct-12 A 45

RAW WATER SYSTEM (TAG NO-34)RAW WATER SYSTEM (TAG NO-34) 14-Jun-1... 02-Oct-13 307CNCV414 Earth Work 15-Jun-1... 09-Jul-12 A 25CNCV424 PCC 25-Jun-1... 18-Jul-12 A 60CNCV434 Barbending 20-Jul-12 A 22-Aug-12 A 60CNCV444 Form Work 08-Aug-1... 04-Sep-12 A 60CNCV454 RCC 23-Aug-1... 16-Oct-12 A 90CNCV464 Handover of Area 14-Jun-12 A 0CNCV502 Back filling & Compaction 14-Nov-1... 23-Nov-12 A 11CNEQ185 Installation of Raw Water Package(Water Treatment Package 22-Nov-1... 02-Oct-13 55

WATER TREATMENT SYSTEM (TAG NO-35,36,37,51,56 & 72)WATER TREATMENT SYSTEM (TAG NO-35,36,37,51,56 & 72) 10-May-1... 29-Oct-13 369Water Treatment Package (WTP)Water Treatment Package (WTP) 10-May-1... 29-Oct-13 363

CNCV274 Earth Work 10-May-1... 25-May-12 A 26CNCV284 PCC 25-May-1... 30-May-12 A 31CNCV294 Barbending 01-Jun-1... 02-Jul-12 A 31CNCV304 Form Work 06-Jun-1... 03-Jul-12 A 21CNCV314 RCC 06-Jun-1... 18-Jul-12 A 46CNCV452 Back filling & Compaction 01-Aug-1... 13-Aug-12 A 11CNEQ195 Installation Testing & Commissioning of Water Treatment Package 16-Oct-1... 29-Oct-13 60

Treated Water Storage Tank (1263-TK-21)Treated Water Storage Tank (1263-TK-21) 15-Jun-1... 14-Nov-12 A 273CNME660 Pre-Fabtication of Plates 15-Jun-1... 26-Jun-12 A 90CNME710 Hydrotesting of Tank 04-Sep-1... 14-Nov-12 A 10CNME720 Erection & Painting of Tank 11-Jul-12 A 04-Oct-12 A 90

Treated Water Overhead Storage Tank-(1263-TK-22)Treated Water Overhead Storage Tank-(1263-TK-22) 15-Jun-1... 11-Sep-13 107CNEQ200 FDN & Fabrication & Erection of SMC Panel Tank 15-Jun-1... 11-Sep-13 150

DM Water TankDM Water Tank 15-May-1... 09-Nov-12 A 114CNME730 Pre-Fabtication of Plates 17-May-1... 18-Jul-12 A 90CNME740 Erection & Painting of Tank 15-May-1... 10-Sep-12 A 90CNME750 Hydrotesting of Tank 10-Oct-1... 09-Nov-12 A 10

Filter Water Storage TankFilter Water Storage Tank 11-May-1... 12-Nov-12 A 223CNME760 Pre-Fabtication of Plates 11-May-1... 25-May-12 A 90

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 39 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 40 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNME770 Erection & Painting of Tank 25-May-1... 12-Sep-12 A 90CNME780 Hydrotesting of Tank 04-Nov-1... 12-Nov-12 A 10

DUG BOREWELLDUG BOREWELL 18-May-1... 29-Oct-13 369CNCV334 DRILLING 18-May-1... 01-Jun-13 45CNCV354 INSTALLATION OF PIPES 18-May-1... 16-Jul-13 60CNCV364 FDN / FIXING OF PUMPS 17-Jul-13 14-Sep-13 60CNCV374 CONNECTION OF PUMPS 31-Aug-13 29-Oct-13 60

STEAM GENERATION PLANT (TAG NO-21)STEAM GENERATION PLANT (TAG NO-21) 02-Jan-1... 17-Aug-13 404Steam Generation System / Boiler FoundationSteam Generation System / Boiler Foundation 25-Jan-1... 17-Aug-13 169

CNCV277 Earth Work 25-Jan-1... 15-Feb-12 A 31CNCV287 PCC 31-Jan-1... 09-Mar-12 A 46CNCV297 Barbending 31-Jan-1... 12-Mar-12 A 36CNCV307 Form Work 02-Feb-1... 15-Mar-12 A 36CNCV317 RCC 15-Feb-1... 24-Mar-12 A 76CNCV482 Back filling & Compaction 29-Mar-1... 04-Apr-12 A 11CNEQ260 Installation Testing & Commissioning of Steam Generation system 04-Sep-1... 17-Aug-13 95

Boiler House Shed (32MX24MX9H)Boiler House Shed (32MX24MX9H) 02-Jan-1... 26-Dec-12 A 355CNCV523 Earth Work 02-Jan-1... 06-Jan-12 A 15CNCV533 PCC 09-Jan-1... 20-Jan-12 A 30CNCV543 Barbending 02-Apr-1... 04-Jun-12 A 30CNCV553 Form Work 05-Apr-1... 12-Jun-12 A 30CNCV563 Structural Fab. Shot Blasting & Primer painting 17-May-1... 24-Aug-12 A 60CNCV573 RCC 04-Jun-1... 27-Jun-12 A 40CNCV583 Structural Erection & Final painting 20-Jul-12 A 23-Oct-12 A 40CNCV593 Sheet Fixing 05-Sep-1... 03-Dec-12 A 80CNCV603 Final Painting 14-Nov-1... 26-Dec-12 A 40

CLOSED DRAIN SYSTEM (TAG NO-10 & 59)CLOSED DRAIN SYSTEM (TAG NO-10 & 59) 06-Jun-1... 14-Dec-12 A 380CNEQ100 Installation of Closed drain Pump 14-Nov-1... 14-Dec-12 A 30CLOSED DRAIN TANK PIT (CRUDE & LIGHT FLUSING OIL -1 NOS)CLOSED DRAIN TANK PIT (CRUDE & LIGHT FLUSING OIL -1 NOS) 22-Dec-1... 31-May-12 A 380

CNCV090 Excavation 22-Dec-1... 22-Feb-12 A 20CNCV100 Barbending 27-Feb-1... 08-May-12 A 40CNCV110 Form Work 28-Feb-1... 10-May-12 A 10CNCV120 RCC 10-Mar-1... 16-May-12 A 60CNCV125 Backfilling & Compaction 23-May-1... 31-May-12 A 16

CLOSED DRAIN TANK-FABRICATION (CRUDE & LIGHT FLUSING OIL -1 NOS)CLOSED DRAIN TANK-FABRICATION (CRUDE & LIGHT FLUSING OIL -1 NOS) 15-May-1... 13-Dec-12 A 237CNME630 Pre-Fabtication & Transportation of Dish End & Fabrication 15-May-1... 04-Sep-12 A 120CNME640 Erection & Painting of Tank 18-Jul-12 A 22-Nov-12 A 60CNME650 Hydrotesting of Tank 04-Dec-1... 13-Dec-12 A 20

CLOSED DRAIN TANK-DYKE WALL ( LIGHT & FLUSHING OIL)CLOSED DRAIN TANK-DYKE WALL ( LIGHT & FLUSHING OIL) 06-Jun-1... 08-Aug-12 A 122CNCV540 Excavation 06-Jun-1... 09-Jul-12 A 90CNCV652 RCC & RELATED FACILITIES 26-Jun-1... 08-Aug-12 A 120CNCV731 PCC 06-Jun-1... 16-Jul-12 A 90

DG SET ( TAG NO-52 & 23)DG SET ( TAG NO-52 & 23) 02-Aug-1... 05-Dec-12 A 552CNEL190 Installation of DG set outside of substation bldg 23-Apr-1... 12-Sep-12 A 31

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 41 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 42 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationDG Set FoundationDG Set Foundation 13-Jan-1... 28-Feb-12 A 64

CNCV561 Earth Work 13-Jan-1... 14-Jan-12 A 9CNCV562 Back filling & Compaction 17-Feb-1... 28-Feb-12 A 11CNCV571 PCC 16-Jan-1... 30-Jan-12 A 11CNCV581 RCC 24-Jan-1... 15-Feb-12 A 21

Diesel Storage tanks-FoundationDiesel Storage tanks-Foundation 02-Aug-1... 13-Apr-12 A 167CNCV122 Excavation 08-Aug-1... 12-Aug-11 A 20CNCV124 Barbending 13-Aug-1... 18-Feb-12 A 30CNCV126 Form Work 02-Aug-1... 23-Feb-12 A 45CNCV128 RCC 19-Aug-1... 24-Feb-12 A 60CNCV130 Backfilling & Compaction 02-Apr-1... 13-Apr-12 A 20

DIESEL STORAGE TANK-FabricationDIESEL STORAGE TANK-Fabrication 15-Nov-1... 05-Dec-12 A 356CNEQ170 Installation of Diesel Unloading pump 26-May-1... 09-Aug-12 A 15CNME670 Fabtication of Tank 15-Nov-1... 15-Feb-12 A 45CNME680 Erection of Tank 22-May-1... 30-May-12 A 40CNME690 Hydrotesting of Tank 13-Nov-1... 20-Nov-12 A 14CNME700 Painting of Tank 22-Nov-1... 05-Dec-12 A 23

DIESEL STORAGE TANK-DYKE WALLDIESEL STORAGE TANK-DYKE WALL 21-Mar-1... 06-Jul-12 A 129CNCV672 RCC & RELATED FACILITIES 21-May-1... 06-Jul-12 A 120CNCV690 Excavation 21-Mar-1... 02-Apr-12 A 45CNCV751 PCC 08-Apr-1... 22-May-12 A 90

FIRE PROTECTION SYSTEM (TAG NO-18,19,47 & 53)FIRE PROTECTION SYSTEM (TAG NO-18,19,47 & 53) 24-Jan-1... 25-Aug-13 715FW PUMP HOUSEFW PUMP HOUSE 09-Feb-1... 09-Aug-12 A 603

CNCV215 Substructure 09-Feb-1... 20-Mar-12 A 45CNCV216 Superstructure 26-Mar-1... 14-Jun-12 A 75CNCV218 Flooring 03-Jul-12 A 09-Aug-12 A 35

FIRE STATION BUILDING ( Drill Yard)FIRE STATION BUILDING ( Drill Yard) 02-Jan-1... 23-Aug-13 A 567CNCV204 Flooring 10-Jul-12 A 28-Jul-12 A 30CNCV212 Superstructure 07-Feb-1... 03-Apr-12 A 95CNCV213 Masonary 21-Mar-1... 13-Jun-12 A 60CNCV221 Substructure 02-Jan-1... 04-Feb-12 A 60CNCV350 Installation of Split Air Conditioner 29-Aug-1... 04-Sep-12 A 10CNCV425 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 08-Aug-1... 23-Aug-13 A 90

FIRE WATER TANK FOUNDATION - 2 NOSFIRE WATER TANK FOUNDATION - 2 NOS 24-Jan-1... 05-Jul-11 A 304CNCV050 Excavation 24-Jan-1... 04-Feb-11 A 8CNCV060 Barbending 31-Jan-1... 31-Mar-11 A 12CNCV070 Form Work 16-Mar-1... 13-Apr-11 A 15CNCV080 RCC 19-Apr-1... 30-May-11 A 90CNCV085 Backfilling & Compaction 15-Jun-1... 05-Jul-11 A 30

FIRE WATER TANK FABRICATION - 2 NOSFIRE WATER TANK FABRICATION - 2 NOS 28-Oct-1... 28-Dec-12 A 423CNME590 Fabtication of Tank 28-Oct-1... 06-Jan-12 A 105CNME600 Erection of Tank 04-Dec-1... 05-Mar-12 A 120CNME610 Hydrotesting of Tank 20-Nov-1... 04-Dec-12 A 90CNME620 Painting of Tank 11-Dec-1... 28-Dec-12 A 90

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 43 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 44 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationFIRE WATER PUMP HOUSE -SHEDFIRE WATER PUMP HOUSE -SHED 15-Nov-1... 22-Jan-13 A 403

CNCV433 Earth Work 15-Nov-1... 09-Jan-12 A 15CNCV443 PCC 09-Feb-1... 20-Mar-12 A 30CNCV453 Barbending 09-Feb-1... 20-Mar-12 A 30CNCV463 Form Work 09-Feb-1... 20-Mar-12 A 30CNCV473 Structural Fab. Shot Blasting & Primer painting 15-Aug-1... 29-Nov-12 A 60CNCV483 RCC 26-Mar-1... 16-May-12 A 40CNCV493 Structural Erection & Final painting 27-Sep-1... 13-Nov-12 A 40CNCV503 Metal Sheet Fixing & Side Cladding 05-Nov-1... 14-Jan-13 A 80CNCV513 Internal & External Painting 18-Dec-1... 22-Jan-13 A 60CNCV613 Installation of Monorail 16-Nov-1... 13-Dec-12 A 78

Impact Fire Fighting Changes- ConstructionImpact Fire Fighting Changes- Construction 15-Feb-1... 25-Aug-13 390CIVILCIVIL 15-Feb-1... 13-Jul-12 A 108

MDPP-FPSC-CC-0001FDN. FOR FIRE WATER PUMP 24-Feb-1... 30-Apr-12 A 45MDPP-FPSC-CC-0011FDN. FOR JOCKEY PUMP 07-Mar-1... 30-Apr-12 A 45MDPP-FPSC-CC-0021FDN. FOR FOAM CONCENTRATE TANK 15-Jun-1... 13-Jul-12 A 60MDPP-FPSC-CC-0031FDN. FOR FIRE WATER TANK (NEW TANK) 15-Feb-1... 16-Mar-12 A 60

MECHANICAL & PIPINGMECHANICAL & PIPING 05-Mar-1... 09-Aug-13 348FIRE WATER TANK FABRICATIONFIRE WATER TANK FABRICATION 05-Mar-1... 12-Dec-12 A 312

MDPP-FPSC-CC-0051CATHODIC PROTECTION FOR FIRE WATER TANK (NEW TANK) 08-May-1... 28-May-12 A 60MDPP-FPSC-CMP-0051FABRICATION OF PLATES 05-Mar-1... 15-May-12 A 50MDPP-FPSC-CMP-0121ALIGNMENT & ERECTION OF ROLLED SEGMENTS 16-Apr-1... 03-Oct-12 A 120MDPP-FPSC-CMP-0131NDT 27-Nov-1... 12-Dec-12 A 30MDPP-FPSC-CMP-0141PIPING CONNECTION 05-Jun-1... 10-Oct-12 A 30

FIRE WATER PUMPFIRE WATER PUMP 07-Aug-1... 28-May-13 31MDPP-FPSC-CMP-0021ASSEMBLY,INSTALLATION OF FIRE WATER PUMP 07-Aug-1... 09-Oct-12 A 30MDPP-FPSC-CMP-0061PIPING CONNECTION 17-Oct-1... 24-May-13 10MDPP-FPSC-CMP-0071NDT & HYDROTESTING 12-Mar-1... 28-May-13 10

JOCKEY PUMPJOCKEY PUMP 03-Oct-1... 08-Jun-13 63MDPP-FPSC-CMP-0031INSTALLATION OF JOCKEY PUMP 03-Oct-1... 23-Oct-12 A 12MDPP-FPSC-CMP-0081PIPING CONNECTION 04-Dec-1... 08-Jun-13 25

FOAM CONCENTRATE TANKFOAM CONCENTRATE TANK 12-Sep-1... 09-Aug-13 35MDPP-FPSC-CMP-0041ERECTION AND ALLIGNMENT 12-Sep-1... 04-Oct-12 A 12MDPP-FPSC-CMP-0101PIPING CONNECTION 12-Nov-1... 09-Aug-13 20

ELECTRICALELECTRICAL 21-Aug-1... 13-Jun-13 21MDPP-FPSC-CE-0001INSTALLATION & TERMINATION OF CABLES 21-Aug-1... 13-Jun-13 30

INSTRUMENTATIONINSTRUMENTATION 04-Oct-1... 25-Aug-13 65MDPP-FPSC-CI-0001INSTALLATION OF INSTRUMENTATION ITEMS 04-Oct-1... 25-Aug-13 90

SEWAGE TREATMENT SYSTEM (TAG NO-32)SEWAGE TREATMENT SYSTEM (TAG NO-32) 22-Jan-1... 13-Jun-13 339

Sewage Treatment Package (STP)Sewage Treatment Package (STP) 22-Jan-1... 13-Jun-13 339CNCV272 Earth Work 22-Jan-1... 26-Apr-12 A 30CNCV282 PCC 28-Jan-1... 29-Mar-12 A 35CNCV302 Barbending 30-Jan-1... 11-May-12 A 30CNCV312 Form Work 30-Jan-1... 15-May-12 A 30

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 45 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 46 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV322 RCC 20-Apr-1... 26-May-12 A 45CNCV432 Back filling & Compaction 28-May-1... 29-Jun-12 A 10CNEQ150 Installation of Sewage water treatment plant 11-Sep-1... 13-Jun-13 30

OILY WATE TREATMENT SYSTEM(TAG NO-11 & 71)OILY WATE TREATMENT SYSTEM(TAG NO-11 & 71) 13-Jun-1... 03-Jul-13 304Oily Water Package (OWP)Oily Water Package (OWP) 13-Jun-1... 03-Jul-13 304

CNCV271 Earth Work 13-Jun-1... 18-Jul-12 A 25CNCV281 PCC 08-Aug-1... 12-Aug-12 A 12CNCV301 Barbending 16-Aug-1... 04-Sep-12 A 45CNCV311 Form Work 21-Aug-1... 10-Sep-12 A 30CNCV321 RCC 14-Sep-1... 09-Oct-12 A 60CNCV462 Back filling & Compaction 09-Oct-1... 18-Oct-12 A 10CNEQ140 Installation of Oily water treatment plant 11-Feb-1... 03-Jul-13 50

SUB STATION ( TAG NO-27)SUB STATION ( TAG NO-27) 15-Mar-1... 23-Jul-13 664

Main Substation BuildingMain Substation Building 15-Mar-1... 20-Mar-13 A 664CNCV185 Substructure 15-Mar-1... 30-Oct-11 A 75CNCV186 Superstructure 20-Oct-1... 30-Dec-11 A 110CNCV187 Masonary 15-Feb-1... 10-May-12 A 60CNCV188 Flooring 08-May-1... 17-Aug-12 A 60CNCV190 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 29-Aug-1... 04-Nov-12 A 95CNCV191 HVAC ducting work 12-Nov-1... 12-Dec-12 A 30CNEL175 Installation of Switchgear & Panel 29-Nov-1... 10-Jan-13 A 50CNEL185 Installation of Substation Equipment incl. testing 10-Jan-1... 12-Mar-13 A 90CNEL200 Installation of Substation Automation System 10-Jan-1... 20-Mar-13 A 90

TransformerTransformer 14-Jan-1... 23-Jul-13 328CNCV471 Earth Work 14-Jan-1... 16-Jan-12 A 8CNCV481 PCC 18-Jan-1... 18-Jan-12 A 10CNCV491 RCC 22-Jan-1... 08-Feb-12 A 20CNCV532 Back filling & Compaction 20-Feb-1... 28-Feb-12 A 10CNEL177 Installation of Transformers 28-Nov-1... 23-Jul-13 70

NGRNGR 08-May-1... 05-Dec-12 A 55CNCV371 Earth Work 08-May-1... 24-May-12 A 8CNCV381 PCC 28-May-1... 06-Jun-12 A 10CNCV391 RCC 11-Jun-1... 28-Jun-12 A 20CNCV522 Back filling & Compaction 11-Jul-12 A 30-Jul-12 A 10CNEQ190 Installation of NGR 13-Nov-1... 05-Dec-12 A 45

Gas TurbineGas Turbine 11-Nov-1... 25-Jan-12 A 90CNCV342 Excavation 11-Nov-1... 30-Nov-11 A 12CNCV344 Foundation 20-Nov-1... 15-Jan-12 A 60INT160 Installation of Gas turbine Generator 21-Jan-1... 25-Jan-12 A 60

11-KV Kiosk11-KV Kiosk 31-Jul-12 A 03-Oct-12 A 40CNCV700 Excavation & Foundation 31-Jul-12 A 20-Aug-12 A 21CNCV720 Installation of kiosk 29-Aug-1... 03-Oct-12 A 40

2 Pole Structure for incoming Grid Structure2 Pole Structure for incoming Grid Structure 10-Sep-1... 06-Dec-12 A 54CNCV730 Excavation & Foundation 10-Sep-1... 04-Oct-12 A 21

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 47 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 48 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV740 Erection of Structure 08-Nov-1... 06-Dec-12 A 60

CONTROL ROOM BUILDING (TAG NO-30)CONTROL ROOM BUILDING (TAG NO-30) 23-Nov-1... 21-May-13 486Control Room BuildingControl Room Building 23-Nov-1... 21-May-13 486

CNCV150 Substructure 23-Nov-1... 15-Feb-12 A 75CNCV151 Superstructure 08-Dec-1... 27-Apr-12 A 120CNCV152 Masonary 14-Feb-1... 01-May-12 A 60CNCV153 Flooring 03-May-1... 11-Jul-12 A 40CNCV155 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 14-Mar-1... 12-Jun-12 A 120CNCV156 HVAC ducting work 18-Jul-12 A 10-Oct-12 A 75CNEL140 Installation of UPS in Control Room 07-May-1... 21-May-13 25

BUILDING AND INFRASTRUCTUREBUILDING AND INFRASTRUCTURE 28-Jan-1... 21-Nov-13 759

BUILDING WORKSBUILDING WORKS 28-Jan-1... 21-Nov-13 739Administration BuildingAdministration Building 04-Apr-1... 10-Apr-13 A 706

CNCV141 Substructure 04-Apr-1... 05-Jun-12 A 75CNCV142 Superstructure 11-Jun-1... 11-Sep-12 A 66CNCV143 Masonary 24-Aug-1... 04-Oct-12 A 60CNCV144 Flooring 04-Mar-1... 10-Apr-13 A 40CNCV145 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 09-Oct-1... 13-Feb-13 A 120CNCV146 HVAC ducting work 18-Dec-1... 09-Apr-13 A 40

Medical Centre BuildingMedical Centre Building 28-Jan-1... 15-Oct-13 A 672CNCV235 Substructure 28-Jan-1... 15-Feb-12 A 75CNCV236 Superstructure 01-Feb-1... 13-Apr-12 A 90CNCV237 Masonary 15-Mar-1... 06-Jun-12 A 60CNCV238 Flooring 02-Oct-1... 01-Nov-12 A 30CNCV240 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 17-May-1... 15-Oct-13 A 120CNCV250 Installation of Split Air Conditioner 04-Apr-1... 24-Apr-13 A 10

Security BuildingSecurity Building 12-Oct-1... 08-May-13 A 567CNCV195 Substructure 12-Oct-1... 10-Jan-12 A 75CNCV196 Superstructure 13-Jan-1... 13-Mar-12 A 90CNCV197 Masonary 05-Mar-1... 24-Apr-12 A 60CNCV198 Flooring 14-Nov-1... 04-Dec-12 A 50CNCV200 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 23-May-1... 12-Sep-12 A 120CNCV201 HVAC ducting work 27-Mar-1... 08-May-13 A 40

Admin MCC SubstationAdmin MCC Substation 28-Nov-1... 13-Jun-13 237CNCV225 Substructure 28-Nov-1... 22-Feb-12 A 30CNCV226 Superstructure 12-Mar-1... 16-May-12 A 70CNCV227 Masonary 09-May-1... 13-Jun-12 A 55CNCV228 Flooring 07-Aug-1... 12-Dec-12 A 55CNCV230 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 13-Aug-1... 12-Dec-12 A 120CNCV231 HVAC ducting work 08-Jan-1... 13-Jun-13 30

Workshop / Warehouse Building / LaboratoryWorkshop / Warehouse Building / Laboratory 04-Feb-1... 23-May-13 609CNCV165 Substructure 04-Feb-1... 02-Jul-12 A 75CNCV166 Superstructure 15-Feb-1... 05-Jun-12 A 90CNCV167 Masonary 01-May-1... 13-Jun-12 A 45

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 49 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 50 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV168 Flooring 03-Dec-1... 10-Jan-13 A 60CNCV170 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 26-Sep-1... 13-Feb-13 A 80CNCV176 Fab. & Erection of Structural Steel Works 07-May-1... 15-Nov-12 A 120CNCV180 Sheet Fixing 06-Nov-1... 28-Nov-12 A 90CNCV320 Installation of Split Air Conditioner 15-May-13 23-May-13 10CNEQ220 Erection of EOT crane 24-Oct-1... 10-Jan-13 A 60

Canopy at Entrance -DELETEDCanopy at Entrance -DELETED 15-Feb-1... 25-Nov-12 A 440CNCV112 Substructure 15-Feb-1... 19-May-12 A 30CNCV113 Superstructure 20-May-1... 08-Jul-12 A 50CNCV116 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 10-May-1... 18-Jul-12 A 70CNCV123 Sheet Fixing 26-Sep-1... 25-Nov-12 A 60CNCV133 Fabrication & Erection of Structural Steel 09-Jul-12 A 26-Sep-12 A 90

Security Cabin /Sheds (2 Nos)Security Cabin /Sheds (2 Nos) 21-Sep-1... 05-Feb-13 A 159CNCV243 Masonary 07-Feb-1... 06-Jun-12 A 45CNCV261 Substructure 21-Sep-1... 04-Nov-11 A 40CNCV264 Flooring 29-Nov-1... 05-Feb-13 A 40CNCV422 Superstructure 14-Dec-1... 25-Apr-12 A 45CNCV455 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 03-Jul-12 A 02-Nov-12 A 75

SEHMS Sub StationSEHMS Sub Station 15-Apr-1... 08-Jan-13 A 143CNCV154 Flooring 11-Dec-1... 08-Jan-13 A 30CNCV160 Release of Front 15-Apr-12 A 0CNCV161 Substructure 09-May-1... 04-Jul-12 A 45CNCV162 Superstructure 19-Jul-12 A 03-Sep-12 A 55CNCV163 Masonary 02-Aug-1... 20-Sep-12 A 45CNCV205 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 12-Sep-1... 03-Dec-12 A 60

Hazardous Waste Area ShedHazardous Waste Area Shed 08-Jun-1... 18-Jul-13 267CNCV164 Flooring 24-Jan-1... 13-Jun-13 30CNCV169 Release of Front 08-Jun-12 A 0CNCV171 Substructure 31-Jul-12 A 15-Aug-12 A 14CNCV182 Superstructure 31-Aug-1... 11-Oct-12 A 20CNCV183 Masonary 19-Sep-1... 14-Nov-12 A 35CNCV245 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 21-Nov-1... 18-Jul-13 45

Raw Water MCC RoomRaw Water MCC Room 06-Mar-1... 08-Jul-13 321CNCV194 Flooring 23-Jan-1... 23-Jun-13 40CNCV202 Superstructure 24-Apr-1... 13-Jun-12 A 70CNCV203 Masonary 14-Jun-1... 16-Jul-12 A 45CNCV209 Release of Front 30-Mar-12 A 0CNCV211 Substructure 06-Mar-1... 12-Apr-12 A 60CNCV260 Installation of Split Air Conditioner 29-Jun-13 08-Jul-13 10CNCV265 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 13-Aug-1... 03-Jul-13 50

Chemical HouseChemical House 15-Jun-1... 22-Aug-13 290CNCV214 Flooring 12-Dec-1... 05-Feb-13 A 30CNCV222 Superstructure 30-Jul-12 A 30-Oct-12 A 75CNCV223 Masonary 25-Sep-1... 18-Oct-12 A 45

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 51 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 52 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNCV241 Substructure 15-Jun-1... 18-Jul-12 A 45CNCV435 Finishing ( Elect. Inst.,Doors & Window fixing,Painting) 12-Dec-1... 22-Aug-13 100

Car parkingCar parking 04-Sep-1... 21-Nov-13 A 83CNCV570 Excavation 04-Sep-1... 18-Sep-12 A 30CNCV580 PCC & Foundation 17-Sep-1... 21-Nov-13 A 45CNCV590 Erection of Purlin 04-Dec-1... 09-Jan-13 A 40CNCV600 Erection of Roof Sheet 06-Feb-1... 16-Apr-13 A 60

HVAC System (AC Screw Chillers,Water Pumps Etc)HVAC System (AC Screw Chillers,Water Pumps Etc) 17-Feb-1... 02-Aug-13 433CNCV384 Foundation 22-Feb-1... 28-Feb-12 A 45CNCV394 Installation of Chillers, Pumps & Connention of Air handling Unit-AHU) 23-Jul-12 A 14-Nov-12 A 180CNCV404 Installation of Ventilation System in Buildings 07-Jan-1... 02-Aug-13 60CNCV682 Excavation 17-Feb-1... 20-Feb-12 A 20

INFRASTRUCTURE WORKSINFRASTRUCTURE WORKS 07-Nov-1... 10-Nov-13 725

Civil Work- Foundation of EquipmentsCivil Work- Foundation of Equipments 28-Apr-1... 12-Dec-12 A 283Pump's FoundationPump's Foundation 02-Aug-1... 12-Dec-12 A 94

CNCV318Earth Work 08-Aug-1... 29-Aug-12 A 20CNCV328PCC 02-Aug-1... 11-Oct-12 A 65CNCV338Form Work 29-Aug-1... 17-Oct-12 A 50CNCV348RCC 13-Sep-1... 01-Dec-12 A 80CNCV492Back filling & Compaction 03-Dec-1... 12-Dec-12 A 10

SHEMS Transformer FoundationSHEMS Transformer Foundation 28-Apr-1... 27-Aug-12 A 162CNCV501Earth Work 28-Apr-1... 07-May-12 A 8CNCV511PCC 03-May-1... 25-Jun-12 A 10CNCV521RCC 25-May-1... 04-Jul-12 A 20CNCV542Back filling & Compaction 07-Aug-1... 27-Aug-12 A 10

Vent StackVent Stack 14-May-1... 14-Nov-12 A 283CNCV531Earth Work 14-May-1... 14-May-12 A 8CNCV541PCC 15-May-1... 15-May-12 A 10CNCV551RCC 30-May-1... 31-May-12 A 20CNCV552Back filling & Compaction 15-Jun-1... 29-Jun-12 A 10CNEQ270Installation of Vent Stack 16-Aug-1... 14-Nov-12 A 45

Foam Pump Skid FoundationFoam Pump Skid Foundation 15-Jun-1... 21-Aug-12 A 164CNCV572Back filling & Compaction 06-Aug-1... 21-Aug-12 A 10CNCV591Earth Work 15-Jun-1... 22-Jun-12 A 8CNCV601PCC 18-Jun-1... 28-Jun-12 A 10CNCV611RCC 05-Jul-12 A 31-Jul-12 A 20

Foam Concentrate Tank FoundationFoam Concentrate Tank Foundation 15-Jun-1... 16-Aug-12 A 35CNCV582Back filling & Compaction 09-Aug-1... 16-Aug-12 A 10CNCV621Earth Work 15-Jun-1... 29-Jun-12 A 15CNCV631PCC 18-Jun-1... 02-Jul-12 A 30CNCV641RCC 03-Jul-12 A 13-Jul-12 A 30

Construction of RoadsConstruction of Roads 07-Nov-1... 12-Aug-13 125CNCV252 WBM (63-40) 07-Nov-1... 15-May-13 90CNCV254 WBM (50-20) 28-Nov-1... 12-Aug-13 100

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 53 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 54 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCivil Works - DrainsCivil Works - Drains 11-Sep-1... 10-Nov-13 665

CNCV290 Excavation 11-Sep-1... 15-May-13 140CNCV291 PCC 18-Sep-1... 25-Sep-13 140CNCV292 Bar Bending 24-Sep-1... 05-Oct-13 140CNCV293 Form Work 27-Sep-1... 08-Aug-13 90CNCV298 RCC 03-Oct-1... 09-Sep-13 120CNCV303 Plastering 15-May-13 10-Nov-13 180

Construction of Cable Trenches around BuildingConstruction of Cable Trenches around Building 18-Jun-1... 26-Aug-13 115CNCV300 Excavation 18-Jun-1... 01-Aug-12 A 60CNCV340 PCC 11-Sep-1... 15-May-13 60CNCV341 Bar Bending 17-Sep-1... 28-Jul-13 75CNCV351 Form Work 19-Sep-1... 07-Aug-13 70CNCV361 RCC 10-Oct-1... 26-Aug-13 90

Civil works- Pipe SleepersCivil works- Pipe Sleepers 07-Nov-1... 08-Jun-13 70Contruction of Pipe Sleepers ( Pre-Cast)Contruction of Pipe Sleepers ( Pre-Cast) 0

Contruction of Pipe Sleepers ( Cast-In-Citu)Contruction of Pipe Sleepers ( Cast-In-Citu) 07-Nov-1... 08-Jun-13 70CNCV560Excavation & Pedestal Casting 12-Nov-1... 15-May-13 100CNCV710Release of Front 07-Nov-1... 08-Jun-13 70

Civil works- PavingCivil works- Paving 22-Aug-1... 11-Sep-13 86CNCV330 Civil works - Paving in Tank Farm area 22-Aug-1... 11-Sep-13 120

Construction of Watch Towers InstallationConstruction of Watch Towers Installation 10-Nov-1... 26-Oct-13 474CNCV335 Excavation 03-Jan-1... 25-Jan-12 A 32CNCV345 PCC 10-Nov-1... 14-Mar-12 A 32CNCV355 RCC 01-Dec-1... 18-May-13 46CNCV365 Backing Filling & Compaction 24-Feb-1... 14-Aug-13 A 48CNCV395 Fabrication 21-Nov-1... 17-Jun-13 152CNCV405 Blasting & Painting 30-Nov-1... 20-Jul-13 93CNCV415 Installation & Start up of Watch Towers (11 Nos.) 29-Feb-1... 30-Aug-13 110CNCV465 Final Painting & Touch up 03-Sep-13 26-Oct-13 61

PathwaysPathways 02-Aug-1... 08-Nov-13 127CNCV505 Construction of Pathways around Terminal 02-Aug-1... 08-Nov-13 200

COMMON AREASCOMMON AREAS 15-Feb-1... 06-Jan-14 696PIPING WORKSPIPING WORKS 06-Jun-1... 06-Jan-14 646

U/G PIPINGU/G PIPING 04-Sep-1... 05-Nov-13 124CNME501 Excavation & Lowering of Pipes 04-Sep-1... 02-Aug-13 90CNME502 Piping Laying & Erection & Connection 07-Nov-1... 07-Oct-13 120CNME512 NDT & Hydrotesting 20-Nov-1... 05-Nov-13 60

CS PIPING/AG PIPINGCS PIPING/AG PIPING 05-Dec-1... 06-Jan-14 646CNME500 Pipe Fabrication 10-Jul-12 A 15-May-13 240CNME510 Pipe Laying, Erection & Connections 05-Dec-1... 14-Dec-13 200CNME515 NDT Works 12-Dec-1... 18-Dec-13 240CNME520 Hydrotesting 10-Nov-1... 20-Dec-13 120CNME530 Insulation 15-Sep-13 03-Jan-14 110CNME540 Painting 14-Aug-1... 30-Dec-13 220

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 55 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 56 of 58 © Primavera Systems, Inc.

Activity ID Activity Name Start Finish Original

DurationCNME550 Flushing and Handing over 12-Nov-13 06-Jan-14 55

FIRE FIGHTING SYSTEMFIRE FIGHTING SYSTEM 06-Jun-1... 15-Nov-13 550CNME560 Fabrication of Fire water Networks 06-Jun-1... 01-Oct-13 100CNME570 Erection of Fire water Networks 14-Feb-1... 05-Nov-13 175CNME580 Flushing 27-Sep-13 15-Nov-13 50

EQUIPMENT ERECTIONEQUIPMENT ERECTION 15-May-13 10-Nov-13 128CNEQ210 Installation of Fire alarm system 15-May-13 22-Aug-13 100CNEQ261 Installation completion of HVAC 15-May-13 10-Nov-13 180

EQUIPMENT ERECTION OF FREE ISSUE MATERIALEQUIPMENT ERECTION OF FREE ISSUE MATERIAL 29-Nov-13 29-Dec-13 20INT170 Installation of Valves (above 24" size) 29-Nov-13 29-Dec-13 30

ELECTRICALELECTRICAL 02-Aug-1... 29-Dec-13 290CNEL100 Laying and termination Cable (HT/LT) in Cable trench 24-Oct-1... 10-Sep-13 90CNEL110 Laying and termination Cable (HT/LT) on Pipe Sleepers 02-Aug-1... 30-Nov-13 200CNEL130 Installation of Cable trays and Cables in Buildings 29-Nov-1... 02-Aug-13 70CNEL150 Installation of Area Lightning 17-Oct-1... 09-Dec-13 125CNEL160 Installation of Earthing System 09-Aug-1... 10-Nov-13 180CNEL170 Installation of Electrical Heat tracing system 02-Apr-1... 29-Dec-13 140CNEL180 Installation of Electrical items (Switches,JB's,Cable Tray, DB ) 15-May-13 11-Sep-13 120

INSTRUMENTATIONINSTRUMENTATION 15-Feb-1... 05-Jan-14 696CNINS100 Installation of Tank Farm Management system 13-May-1... 12-Nov-13 A 120CNINS110 Cable laying and Termination 15-Feb-1... 23-Dec-13 A 150CNINS120 Installation of Field Instrument ( Radar Guage, PRV, Level Guage) 20-Sep-1... 17-Nov-13 A 790CNINS130 Installation of Cable Trays 15-Feb-1... 16-Sep-13 A 160CNINS135 Installation of Valves (On-off, Control Valves) 23-Aug-1... 17-Jul-13 A 90CNINS140 Instrumentation Works inside Control room 20-Jul-11 A 25-Nov-13 120CNINS145 Installation of In-Line Instruments 15-May-13 10-Dec-13 210CNINS150 Instrumentation Loop Testing 06-Nov-13 05-Jan-14 60CNINS155 Installation of Intrusion Detection System 15-May-13 22-Aug-13 100

STATUATORY APPROVALSSTATUATORY APPROVALS 15-May-1... 26-Nov-13 2CNSA100 CEA Approval (GEB Approval) for Electricity 16-May-1... 26-Nov-13 A 1CNSA110 Final Lincence from PESO / CCOE 15-May-13 15-May-13 1

MECHANICAL COMPLETIONMECHANICAL COMPLETION 07-Feb-1... 13-Jan-14 174

COM110 Energisation of Substation 06-Mar-1... 28-Jun-13 A 20COM120 Rectification of Check list point 07-Feb-1... 11-Jan-14 18COM130 Mechanical Completion & Pre-Commissioning 16-Dec-13* 13-Jan-14 28COM140 No load run 15-May-13 13-Jun-13 30COM150 Equipment trial run 27-Aug-13 25-Sep-13 30

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32011 2012

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 57 of 58 © Primavera Systems, Inc.

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q12013 2014 2015 2016 2017

PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 58 of 58 © Primavera Systems, Inc.