bidp standard forms & jbcc minor works · pdf file · 2017-11-17commentary...
TRANSCRIPT
BIDP Standard FORMS & JBCC Minor WORKS –
Commentary ARCPE SEMINAR
compiled BY FRED PHIRI Arch.BW 01160007
04th NOVEMBER 2017
Types of Contract
• Fixed Price ContractsFor Specified work for a sum not adjustable in the price of goods or labour. Ideal for minor building works or Maintenance
Example: BIDP Minor Building Works Contract
• Remeasurement ContractsIn remeasurement contracts the price is based on quantities and there is an express right for the works to be remeasured after completion
Example: BIDP Standard Form (With Quantities); JBCC Minor Works; JBCC Principal Building Agreement; FIDIC
• Lump sum ContractsThis is a contract where a specific Total Figure is quoted but it should be Noted that the total price is adjustable on account of :
• Variations
• Fluctuations in Price of goods and Services
• Re-valuation of provisional sums
• Loss and/or expense
Example: BIDP Standard Form of Contract Without Quantities; JBCC Minor Works
JBCC Minor Works Agreement 5.1 © March 2014
• This agreement is intended for use where:
• The works are not complex
• The employer appoints:
• A principal agent to administer the agreement
• Other agents for specific aspects of the works
• Direct contractors for specialised work or installation not undertaken by the contractor
• This agreement is suitable but not limited for use where:
• The contractor is a small to medium enterprise
• The employer carries the major liabilities related to the works
• The employer is responsible for the primary insurances related to the works
JBCC Minor Works Agreement 5.1 © March 2014
• This agreement is not suitable where the works requires:
• The appointment of nominated or selected subcontractors
• Contract price adjustment (escalation) provisions
and is not considered suitable where:
• the works is of a complex nature
• The anticipated construction period is longer than nine months
• The necessary contract documentation is not complete and available at tender stage
• Sectional completions are required
BIDP Standard Form of Building Contract Private Edition (With Quantities. 1985 Edition 2006 Revision)
• Based on Detailed drawing And Bills of Quantities
• Has its Genesis in the RIBA / JCT Forms of Contract.
• Is the oldest Form of Contract in use in Private Sector in Botswana today.
BIDP Standard Form of Building Contract Private Edition (Without Quantities. 1985 Edition 2006 Revision)
• Based on detailed Drawings and Specifications
• Design Intent must be properly communicated to contractor through preparation of very detailed drawings and specification.
• The onus is on the contractor to do his own take off (measurements) from the detailed drawings
• Has provision for employment of Quantity Surveyor
BIDP Agreement For Minor Building Works
Contract Administration
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract
BIDP
• Administered by Architect
• Contract can be under Seal or Under Hand – Prescription Period different depending on how contract is executed (6Years or 12Years)
• Custody of contract Documents: Original kept by Architect or QS
JBCC
• Administered by Principal Agent
• Contract is under hand with a 5year Prescription Period from Issue of Final Completion Certificate (Botswana Law has a 6Year Prescription Period)
• Custody of contract Documents: Principal Agent originals and parties are issued with copies.
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Insurance
i) Clauses 19 (workmen’s compensation, Injury to persons and property – Contractor Insures
ii) Clause 20(A) New Work –Contractor Insures
iii) Clause 20(B) New Work –Employer Insures
iv) Clause 20(C) Alterations and Extensions – Employer Insures
JBCC
• Insurance : Clause 8 – Employers Responsibility save for Clauses 8.2 and 8.5 and 8.6 (contractor’s Employees, construction equipment and vehicles and Insurance Deductible
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Clauses 30.4 / 36 – Security• This comes in the Form of Retention which is
normally set at 10% of the certified value to a limit of 5% of the contract amount
• Clause 36 has an optional provisional for a Surety Bond which is set at 10% of the contract sum. This Clause can be deleted if not required
JBCC
• Clause 9 – Security• Both Parties to the contract are required to
provide the requisite security
• The contractor can opt for Retention at 8% of the Certified Value to a limit of 4% or can submit JBCC Guarantee for Construction
• Employer is obliged to submit a Guarantee for payment. Submission of which will relieve the contractor right to lien on the works
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Clause 2 – Architect’s Instructions
• Instructions must be in writing
• Contractor must execute instructions within 7 days, failure of which employer can engage others to carry out the instruction
• Oral Instructions should be confirmed back in writing within 7 days for them to have effect
• Contractor may request written confirmation from architect regarding which clause the architect is empowered to issue the instruction
JBCC
• Clause 14 – Contract Instructions• Contractor obliged to comply and Duly execute
contract instructions
• Oral Instructions have no force or effect
• There is no obligation on a contractor to carry out a contract instruction for additional work after practical completion has been certified
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Extension of Time Provisions –Clause 23
• Force Majeure
• Exceptionally Inclement Weather
• By reason of Loss or Damage From Perils specified under Clause 23
• Civil Commotion, workmen strikes
• AI’s to cover discrepancies in contract documents; variations; postponement of work
• Late information (request for information to have been specified in writing in reasonable time IRO date of practical completion)
• Nominated Subcontractors
• Artists and Tradesmen and others engaged by the employer doing work not forming part of the contract
• Opening up of covered work for inspection.
JBCC
• Extension of Time Provisions – Clause 17• Adverse Weather conditions
• Inability to obtain materials and goods
• Making good physical loss and damage to the works
• Exercise of Statutory Powers
• Force Majeure
• Delayed possession of site
• Making Good of Physical loss & Repairing of damage where the contractor is not at risk
• Opening up of work which is found to be in accordance with the contract
• Late Issue of construction Information
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Extension of Time Provisions –Clause 23
• Inability to secure labour, goods , materials etc. beyond the contractor’s control (This is optional and can be deleted)
EOT Notices
Contractor required to forthwith, give written notice of delay to architect. The Architect is required, as soon as he is able to, to estimate the length of delay beyond the date or time aforesaid, make in time a fair and reasonable extension of time
JBCC
• Extension of Time Provisions –Clause 17
• Late supply of free issue materials where the employer is responsible
• Default by Principal agent or employer
• Act or omission by Direct Subcontractor
• Utilities connection not available
• Suspension of the works
EOT Notices
Contractor must report at the next site meeting, cause and days claimed. The Principal shall determine claim and revise date for practical completion within 10 working days. Record of details of delay & adjustments to be recorded in site meeting minutes
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
Clause 29 – Artists , Tradesmen or others engaged by the Employer• Contractor to permit direct contractor’s to install works
as part of the works.
• No obligation on contractor to program the works
• Claim Expense and/or loss due to direct contractor’s default
• Payment is the responsibility of the employer outside the agreement
• No privity of contract between Contractor and Artists, tradesmen
JBCC
• Clause 13 – Direct contractors• Contractor to permit direct contractor’s to install works
as part of the works.
• Works to be programmed
• Claim Expense and/or loss due to direct contractor’s default
• Payment of the Direct contractor is the responsibility of the employer outside the agreement
• No privity of contract between Contractor and Direct contractor
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Clause 22 – Liquidated & Ascertained Damages
Clause 22 requires architect to certify in writing that that the works ought to have been reasonably completed before LAD’s can be effected
Liquidated and Ascertained Damages: These are a reasonable pre-estimate of the losses the employer is likely to incur if work is completed late. Such sum is enforceable if due to his own default the contractor completes work late
JBCC
• Clause 18.2 – Penalty for non-completion
18.2 Where the employer elects to levy such penalty, on notice thereof, to the contractor, the principal agent shall determine the amount due…
A penalty of non-completion is a sum included in the contract which is intended to penalise the contractor for late completion and can sometimes be far greater than the employer’s estimated loss
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Clause 25 – Grounds For Termination by Employer
• Suspension of the works without reasonable cause
• Contractor’s failure to proceed with regularity and diligence
• Contractors refusal to comply with architect’s written notice to remove defective work or improper materials
• Contractor’s failure to comply with Clause 17 (assignment or subletting)
• Bankruptcy (Forthwith determination)
JBCC
• Clause 21 – Grounds For Termination by Employer
• Contractor’s Failure to provide JBCC Guarantee for Construction
• Contractor’s failure to proceed with the works
• Contractor’s failure to timeously comply with contract Instructions.
• Employer’s right to terminate cannot be exercised where the employer is in material breach
Comparisons & Contrasts – JBCC Minor Works & BIDP Standard Forms of Contract (contd.)
BIDP
• Clause 26 – Grounds For Suspension /Termination by Contractor
• Employer’s Failure to honour certificates within the stipulated period – Termination can be forth with after 7-Days Notice
• Employer’s Interference or obstruction of any certificate due to the contractor
• Suspension of works for a period stated in the appendix due to force majeure; loss or damage from Clause 20 risks; AI to cover discrepancy or divergence in contract documentation; architect’s failure to issue necessary instructions, drawings, details or levels etc. in due time; delay on the part of artists, tradesmen; opening up of work
• Employer’s Bankruptcy
JBCC
• Clause 21 – Grounds For Suspension /Termination by Contractor
• Employer’s Failure to provide JBCC Guarantee for Payment
• Employer’s failure to give possession of the site
• Employer’s failure to pay certified amount
• Employers failure to appoint Principal Agent or other Agents
• Employer’s interference with Principal Agents independent judgement
• Principal Agents failure to issue payment Certificate
• Employer’s failure to effect insurance