bids and awards committee for dictbac supplemental bid...
TRANSCRIPT
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 1 of 87
BIDS AND AWARDS COMMITTEE FOR DICTBAC
Supplemental Bid Bulletin No. 6
SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING,
OPERATION AND MAINTENANCE SUPPORT OF IP MICROWAVE RADIO
COMMUNICATION SYSTEM FOR DICT-PAGASA “ALL WEATHER COMMUNICATION
SYSTEM PROGRAM”
Item No.
Reference Query End Users Response
1
Bid Data Sheet ITB Clauses 21 and 24.1,
Page 50
The Deadline for
Submission Of Bids is 15 July 2019, 12:00PM
the date and time of Bid
Opening is on 15 July
2019, 1:30PM
We request to extend the Bid Submission and Opening from 15
July 2019 to 15 August 2019 so that
we can thoroughly prepare the documentation relative thereto,
among which is the JVA documentation
The Bid Opening has been scheduled on October 1, 2019
2
Schedule of
Requirements Number2,Page80
Hauling, delivery, supply and installation of towers
and facilities materials
Within one hundred twenty (120) days after
the approval of detailed
design, tests, plan, etc
We request to extend the delivery
lead time of towers from 120 days to 18 months upon approval due to
the fabrication and hauling process
of towers
Denied.
3
Bid Data Sheet ITB
Clause 12, Page46
the Bidder must hold a
minimum of 20 years PCAB license in General
Engineering on or before the date of the bid
opening, with an AAA
Category.
We request to waive the partially the
requirement of the holding of a minimum of 20 years PCAB license
in General Engineering on or before
the date of the Bid opening, with an AAA Category from the bidder, and
in lieu thereof;
1. We request to allow 3 years of
holding of such a license should be
Change to:
The bidder must hold a PCAB License with Category AAA in
General Engineering for a
minimum of two (2) years on or before the date of the bid
opening. For joint venture, at
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 2 of 87
considered as sufficient for both
General engineering and Communication Facilities
2. We request to allow A or B
category for General Engineering
and Communication Facilities should be considered as well
3.Such PCAB in General Engineering
license BE REQUIRED FROM THE
FABRICATOR partner of the bidder and NOT from the bidder (not from
the Bidder itself) since this is primarily a bid for Microwave Radio.
Most companies who will join are either supplier of equipment BUT
NOT a tower fabricator at the same.
SO it is almost impossible to be both a supplier of both microwave radio
and fabricator of towers at the same time.
The principal equipment to be delivered under this Project is MW
Radio, only with Antenna Towers, that is 3- legged/Monopole_ self-
supporting Tower or 4-legged self- supporting tower, which
requirement as to towers can be put
up by a PCAB Licensee not necessarily under AAA Category.
Hence, the AAA PCAB License requirement is too high of a
category. In relation thereto, too
long possession of such a license for a period of at least 20 years appears
to be restrictive.
The waiver will allow more
participants and make the bidding more competitive
least one of the JV should
comply to this requirement.
.
4
Bid Data Sheet ITB Clause 5.4, Page
The Bidder must have
completed, within past
five years from the date
We request to allow any ICT or other Telecommunication 40 Solution
Projects from a major telecom company within 6 years. the amount
of project (Microwave radio) is quite
huge so the chances of having the
Denied.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 3 of 87
of submission and
receipt of at least one (1) single contract of similar
in nature amounting to at least fifty percent
(50%) of the ABC
same size or amount (50% ABC) as
similar in project name is a bit restrictive.
5
Bid Data Sheet ITB Clause 12, Page41
Any of the following
documents must be
submitted corresponding to listed contracts per
submitted Annex I-A1.
1.Copy of End user’s acceptance;
2. Official receipt; or
3.Sales Invoice
Due to the NDA signed by the manufacturer, can the bidder submit
documents where some of the Information were blocked or
redacted in order to uphold the
previously signed NDA?
Denied.
6
Bid Data Sheet ITB
Clause 12, Page41
Any of the following
documents must be submitted corresponding
to listed contracts per submitted Annex I-A1.
1.Copy of End user’s
acceptance;
2. Official receipt; or 3.Sales Invoice
We request to extend the delivery
lead time of towers from 120 days to 18 months upon approval due to the
fabrication and hauling process of
towers
Denied.
7
Bid Data Sheet ITB Clause 12, Page41
Any of the following documents must be
submitted corresponding to listed contracts per
submitted Annex I-A1.
1.Copy of End user’s
acceptance; 2. Official receipt; or
3.Sales Invoice
Please accept Goods Acceptance Certificate or acknowledgement of
equipment receipt in lieu of FAC as
attachment for the SLCC
Denied.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 4 of 87
8
Bid Data Sheet ITB
Clause 12, Page46
Certification from National Telecommunications
Commission (NTC) that
the proposed Microwave IP Radio equipment is
duly-type approved
may we request that the NTC type
approval certificate be submitted during post qualification as this
process usually takes 2-3 months to be approved by NTC
May we submit an NTC type approval certificate of our brand applied by
another company? as per NTC practice, they allow the use of NTC
type approval certificate acquired by
another company.
Denied
9
Schedule of Requirements
Item 1,Page80
Note: DICT shall take charge of Site Acquisition
Please confirm if the repeater sites
are already acquired by DICT?
if not, the timeline provided should be adjusted and shall not include the
period of site acquisition
please confirm
-if the repeater site is not feasible,
DICT shall provide new repeater site,
otherwise, the delivered equipment shall be deemed final accepted once
it is available for delivery to DICT.
-if in the event that DICT failed to acquire the site, all delivered
equipment that were not installed
due to this lack of site shall be deemed final accepted.
-DICT shall be responsible for new
site at no cost to bidder and should
not affect the timeline of the bidder.
-timeline of acquiring the new site should not be taken against the
bidder
Yes. DICT took charge of the
site acquisition.
Equipment shall be inspected
and accepted by DICT first, in
accordance with payment procedure and milestones
based on the TOR. Further, Bidder shall be allowed to
perform site inspection/survey before
start of manufacturing of
equipment to confirm the feasibility of the equipment to
the areas. A final BOM and link design will be submitted
before proceeding to
manufacturing of equipment.
Yes.Running of period for
delivery of project may be
suspended, subject to approval by DICT for
meritorious reasons under the law.
10 Schedule of requirements item 2,Page80
May we suggest, in order to ensure timely permitting, that the
government take charge of securing
DICT will only help on securing the permits.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 5 of 87
Acquisition of permits and
clearances from the local government units for the
installation of tower
government permits since it will be
faster if transaction is between government agencies
Winning Bidder is in charge
in securing permits
11
Schedule of requirement
item 7, page81
Two (2) years Operation
and maintenance support (inclusive of two (2)- year
warranty parts and labor,
free of charge)
Please consider the operation and
maintenance support of 8 hours x 5
days, Monday to Friday.
Denied.
12
Technical Specifications
Item 1.1.5, Page 84
Shall support the following modulations
schemes without any
hardware change, or additional boards: QPSK,
16QAM, 32QAM, 64QAM, 128QAM, 256QAM,
512QAM, 1024QAM up to
4096QAM whichever is applicable per site
Since this is a bid that includes
DETAILED DESIGN, kindly allow modulation scheme up to 2048QAM.
4096QAM is not usually used for backbone or long haul transmission
and the capacity increase of this
modulation is negligible if we compare it to 2048QAM.
Denied. The modulation
scheme of 4096QAM may not be required in the hops
in this project, however, it still have to be at least
supported, in case we need
higher capacity or reallocation with higher
capacity requirement. There should be about 8~10%
capacity increase per RF
which is not negligible and further mutiplying that
increased capacity with the no. of MODEMS or Channels
your MW Radio System can accommodate, which in this
RFP, we prefer up to 12
MODEMS or 12-Way, would definitely provide a better
scalability for the MW Radio System if you can comply.
13
Technical Specifications
1.1.6, Page84
Frequency: the equipment shall support
all licensed bands L6 to
42 GHz.
Since this is a bid that includes
DETAILED DESIGN, kindly allow “the equipment shall support ANY of the
licensed bands between l6 to 42 GHz as what may be required depending
on the bidders design".
high frequencies are not usually used
for backbone or long haul transmission design.
Denied. This RFP does not
require the bidder to design all hops using all frequency
bands. The bidder is given the liberty to propose its own
recommended frequency
based on the link budget design requirement using the
KPIs provided in the RFP (Avail=99.99%, 35dBm).
However, the bidder is still compelled to comply that it
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 6 of 87
can support L6GHz uo to
42GHz for flexibility.
14
Technical Specification
Item 1.1.6,Page84
ODU that is tunable to
the whole frequency (sub-band free.) Vendors
shall state what kind of free tunable ODU can be
provided. Self Frequency
scan is required.
Since this is a bid that includes
DETAILED DESIGN, the mentioned reference statements are not
applicable for long haul
transmissions.
sub-band free radios are usually used for access radios and not for
long haul radios which filters are
needed.
if DICT needs to have removable diplexers on the ODU, the IP66
compliance (waterproof and dustproof) will be affected.
self frequency scanning is used in PTP UNlicensed radios. this is not
needed with licensed radios since the frequency is dedicated to one (1)
user only.
Please note that preferred
equipment to be supplied in this proposal is
Outdoor/Split-Type System.
If you are proposing a Long Haul Transmission Radio
System which uses indoor filters and connected to
antenna via waveguide, then
this is not this RFP's preferred radio type to be
supplied. However, if you are referring to the
"outdoor" filters which you intend to supply which
probably includes the
duplexer units, these all have to be for outdoor use.
ODUs to be used should be sub-band free, provide such
information in your proposal
to identify which frequency bands are supported.
ODU's IP66 compliance is non-negotiable. Removable
items, such as diplexers, are not preferred. ODUs should
have wide-band filters.
Self-freqeuncy scanning can also be defined as being able
to check for the suitable point frequency to be used
using the installed ODUs and
having the opposite station in mute mode for
transmitting, then checking at local station if
interferences are observed.
15
Technical Specifications Item 1.1.10,Page84
Receive Signal threshold
Sensitivity: the radio equipment must have
Since this is a bid that includes DETAILED DESIGN, please allow the
bidder to state their own Receive Signal Threshold Sensitivity. (same
as the transmit power) in reference to the equipment configuration per
site.
Denied. The Bidder is required to provide their
equipment's Receive Signal Threshold. It is understood
that Receive Signal Threshold shall be based on
modulation, bandwidth and
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 7 of 87
signal sensitivity of BER
10-6 of -60dBm or better.
Please not that the Receive Signal Threshold Sensitivity (same as the
transmit Power) depends on the modulation and frequency used
which is based on the bidders
design.
frequency band which shall
be in accordance to bidder's link budget calculation,
however, it should still be -60dBm or better at BER10E-
6. Better Transmit Power
and Receive Signal Threshold translates to better system
gain, and DICT will also evaluate proposed radio
systems in this regard.
16
Technical Specifications Item 1.1.11 to .14, Page
84-85
1.1.11 the vendor shall propose Layer 3 routing
function and multiplexing,
and shall support L3VPN, L2VPN, native IP and
MPLS
1.1.12 the proposed
equipment shall support OSPF, 8GP route protocol.
1.1.13 the proposed
equipment shall have built-in MADM and ETH
switching platform to
cross connect service among different
directions.
1.1.14 the proposed
equipment shall support layer 2 and layer 3 frame
header compression functions.
kindly confirm that the bidder can propose a separate equipment that
can do layer 3 function and multiplex function
to require the radio its own layer 3
and multiplex functionality is a bit
restrictive to certain brands only.
Denied. It is required that L3 functions can be supported
by the same MW Radio System. Less footprint is an
advantage and adding a separate box corresponds to
Higher Opex (Spares, Power
consumption, Footprint, Maintenance)
17
Technical Specifications
Item 1.1.17,Page85
Ethernet Linear Protection Switching (G.8031)
Ethernet Ring Protection (G.8032v2)
Kindly confirm that the bidder can
propose a separate equipment that can do layer 3 function and
multiplexer function
to require the radio to have its own layer 3 and multiplexer functionality
Denied. It is required that L3
functions can be supported by the same MW Radio
System. Less footprint is an advantage and adding a
separate box corresponds to Higher Opex (Spares, Power
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 8 of 87
is a bit restrictive to certain brands
only.
consumption, Footprint,
Maintenance)
18
Technical Specifications
item 1.1.17,Page85
Ethernet OAM (IEEE
802.3ah, IEEE 802.1ag, ITU-T Y.1731)
Kindly allow ANY of the listed
standards
Changed to:
● 10/100/1000 base - T/X
(IEEE 802.3) ● Ethernet VLANs (IEEE
802.3ac) ● Virtual LAN (IEEE
802.1Q) ● Class of Service (IEEE
802.1q/p) ● Provider Bridges (QinQ-
IEEE 802.1ad) ● Link Aggregation Group
(LAG) ● Ethernet Ring Protection
(G.8032v2) ● Ethernet OAM (IEEE
802.3ah, IEEE 802.1ag,
ITU-T Y.1731)
19
Technical Specifications
Item 1.1.20,Page85
Priority Management, the scheduling scheme should
support SP, WRR, DWRR, WFQ, SP+WRR,
SP+DWRR, SP+WFQ
Kindly allow ANY of the listed
standards
Offered MW Radio System
should be able to support the listed QoS functions.
Please comply to at least four (4) of the QoS
functions.
20
Technical Specifications Item 1.1.21,Page85
Congestion Management
Shall support Tail drop,
RED (Random early Detection) and WRED
(Weighted Random early detection)
Kindly allow ANY of the listed standards
Denied. Offered MW Radio System should be able to
support the listed QoS functions.
21
Technical Specifications
Item 1.1.22,Page85
the proposed equipment shall support port
blocking and mirroring
Kindly confirm that the bidder can
propose a separate equipment that can do layer 3 function and
multiplexer function
to require the radio to have its own layer 3 and multiplexer functionality
Denied. It is required that L3
functions can be supported by the same MW Radio
System. Less footprint is an advantage and adding a
separate box corresponds to Higher Opex (Spares, Power
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 9 of 87
- Port blocking feature is
possible to prevent forwarding of frames
from a given ingress port to one or more egress
ports. with port blocking,
flows of leaves can be isolated to each other in a
tree topology
- Supports port based
mirror function; the messages from input,
output or both directions of observed interface are
copied intact to the observing interface. this
is to be used for testing
and maintenance of the traffic without traffic
interruption.
is a bit restrictive to certain brands
only.
consumption, Footprint,
Maintenance)
22
Technical Specifications
Item 1.3,Page86
Synchronization
the system shall manage synchronous Ethernet
(according to ITU-UG.8261, 8262,8264) on
both FE and GE interface
kindly allow ANY of the listed
standards
Denied. Offered MW Radio
System should be able to
support the stated Synchronization standards.
23
Technical Specifications Item 1.6,Page86
Scalability
the equipment shall
support multinodal ODUs on one IDU with
minimum of 4 ODUs up to 12 ODUs or above
without cascade and shall
support 1+0 2+0, 1+1 HSB/SD/FD, XPIC
Configuration
Please confirm that this is applicable for split type systems only (for IDU
only)
this portion on "scalability" were
entered twice
Denied. This RFP requires Bidder to propose
Outdoor/Split-Type Radio Systems only. The scalability
should be applicable to
whole system offered.
Noted on the duplicated entry. Reply to the
compliance twice, as well.
24
Technical Specifications
Item 1.10.1,Page87
the prefered equipment
Please confirm that NMS (server
software/hardware) shall be installed at one (1) central site only
To be determined during
project implementation.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 10 of 87
should be managed with
unified NMS with Optical transmission equipment.
where will be this central site?
25
Technical Specifications Item 1.11,Page87
Scalability the proposed equipment
shall support twelve (12) Radio Directions or above
without cascade, and
shall support 1+0, 2+0., 1+1 HSB/SD/FC, (CE)
Certificate.
Please confirm that this is applicable for split type systems only (for IDU
only)
this portion on "scalability" were
entered twice
This RFP requires Bidder to propose Outdoor/Split-Type
Radio Systems only. The
scalability should be applicable to whole system
offered.
Noted on the duplicated
entry. Reply to the compliance twice, as well.
26
Technical Specifications
Item 1.12.1,Page87
the offered equipment
shall comply with the chartered engineer (CE)
Certificate
Please double check this requirement
since this section refers to the CE certificate of the equipment.
Therefore, MEF CE is more
appropriate. Carrier Ethernet Certificate and not Chartered
Certificate.
Chartered Certificate refers personnel
credential for all types of engineering discipline.
CE Markings should be
clearly visible in the offered MW Radio System. The CE
Certification certifies that
your equipment is compliant to the requirements of
Health & Safety, Electromangetic
Compatibility and Effective &
Efficient Use of Radio Spectrum. Provide any CE
Certification.
27
Technical Specifications
Item 1.14.1.1,Page88
4 channel Network DVR
please confirm that the bidder shall
propose CCTV for the repeater sites only
this item should be NVR to accommodate IP cameras (DVR is for
analog cameras)
Changed to: 4 channel
Network NVR
28
Technical Specifications
Item 1.14,Page91
Access Road
this involves installation of route between main
road to site location. the
access road shall accommodate vehicles
that deliver materials to site area. the road
surface and base course is made of compacted
the timeline given is not enough to
include this scope given also the fact
that there are no specific details provided (e.g distance from main
road to site, right of way, etc.)
during the implementation, the
contractor shall be able to haul all the necessary equipment, tools etc.
to the site without having to construct access road using tramline
or other appropriate means
Changed to: This involves
installation of route between
main road to site location. The access road shall
accommodate vehicles that deliver materials to site area.
The road surface and base
course is made of compacted aggregates. The total width
of the road is 3.2m with sloping grade of 2-3% at
each end. The canal has an incline slope of 5%. If not
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 11 of 87
aggregates. the total
width of the road is 3.2m with sloping grade of 2-
3% at each end. the canal has an incline slope
of 5%
feasible the winning bidder
can suggest other alternatives with
coordination and approval of DICT.
29
Technical Specifications Item 1.16.3, Page 92
All towers shall have
design wind velocity of
300kph
please allow the bidder to propose the required wind velocity based on
the area of the site.
Denied.
30
Technical Specifications
Item 1.17,Page92
Assumption of 100kpa for allowable soil bearing
capacity, capacity may
change depending on environment and soil
classification of different site locations
if in the event that the site provided
by DICT did not pass the soil test results, DICT shall be amenable for
variation for redoing the soil investigation, survey, testing, etc. on
another site
Denied.
31
Technical Specifications,
Page 92-93
Payment Terms Advance payment subject
to submission of an irrevocable letter of credit
or bank guarantee issued
by a universal or commercial bank
pursuant to Section 4.5 of Annex D of the Revised
IRR of RA 9184-15%
Upon Completion of site
survey-15%
Upon onsite delivery of IP
Microwave Radio System Hardware- 40%
Upon Completion of
Agreed testing- 15%
Upon Completion of
Please confirm
- that progress billing (except for the
advance payment) is on a per site/link basis.
-if in the event that DICT failed to
acquire the site, all delivered
equipment that were not installed due to this lack of site shall be
deemed final accepted and bidder are allow to bill/collet 100% due to
the said sites/link.
-if the repeater site is not feasible,
DICT shall provide new repeater site, otherwise, the delivered equipment
shall be deemed final accepted and
bidder are allow to bill/ collect 100% due to the said sites/link
- DICT accept Progress
billing per site/link basis
- Denied. After the
completion of site
acquisition and the confirmation of access
road's and repeater site’s feasibility by DICT,
bidder should cause the
manufacturing of equipment. Upon
delivery of IP Microwave Radio System hardware
to bidder’s centralized
warehouse, DICT should pay 40% of contract
amount as written in payment milestone.
- Denied. Bidder shall be
allowed to perform site
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 12 of 87
training -5%
Upon Project Acceptance
- 10%
inspection before start of
manufacturing of equipment to confirm
the feasibility of the equipment to the areas.
A final BOM and link
design will be submitted before proceeding to
manufacturing of equipment.
32
fuel to be provided for the generator
sets shall be for testing purposes only. Upon acceptance of the site,
fuel shall be DICT's responsibility
Yes.
33 Technical Bid form, Page
116
Please confirm that there is no
"tower" entry in the technical Bid form
Yes. Technical Bid form will
be revised.
34
Technical Bid form item
6, Page119
Delivery period
two hundred Seventy (270) calendar days from
receipt of notice to
proceed
Please allow the delivery lead time to
commence counting upon receipt of
[purchase order and not from NTP date.
Please allow extension of delivery
lead time to 18 months. it is
impossible to deliver goods like microwave radio and tower ina
matter of 270 days since manufacturer of radio can commence
only after survey, approval of tssr, approval of design application of NTC
and approval of frequency, acquiring
final frequency, soil testing, awaiting soil test results (month at least),
fabrication of tower, hauling, access road, installation. etc.
“DICT would keep delivery
period as 270 days on
condition that the completion of site acquisition and the
confirmation of access road's feasibility is finished by DICT
without any delay.
If completion of site acquisition and the
confirmation of access road's feasibility is not performed
by DICT on timely manner, the delivery lead time should
be extended accordingly.
The starting of point of counting delivery lead time
for Milestone #2 & #4 described in Page80 should
be after the completion of
site acquisition, confirmation of access road's feasibility by
DICT.”
35
Detailed Financial
Breakdown, Page 124
Engineering services
(site survey, design and technical documents,
radio license permit and structural integrity test)-
please confirm the final total
number of links. there are several
entries that have discrepancy.
Change to: Detailed
Financial Breakdown, Page
124
Engineering services (site survey, design and
technical documents, radio license permit and
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 13 of 87
19links
installation, testing
commissioning and acceptance of the
systems-31 links
structural integrity test – 33
links
installation, testing commissioning and
acceptance of the systems
– 33 links
36
Please confirm
Dict shall provide access pass for ALL existing sites (including
PAGASA, DICT, NGCP, LGU, co-
location sites etc.) AND repeater sites
YES.
37
Please confirm Space/radio room for the
equipment and AC power supply (commercial Electricity) for all the
existing sites shall be DICT's
responsibility
To be determined during site survey.
38
Please confirm
Structural integrity and stability of all existing towers shall be the
responsibility of DICT
in the event that after the survey, the vendor concluded that the tower
is not structurally safe. DICT shall be responsible for the retrofitting, and
other tower works and ensure that
the tower is ready for installation after the retrofitting activity.
dict shall provide "certificate if
tower's readiness for the installation
"prior to the vendor mobilization and installation of MW radio.
Yes. DICT will be responsible
for the structural integrity and integrity of all existing
towers.
Yes. DICT will be responsible
for the all the work to be done.
Yes.
39
please confirm DICT shall ensure sufficient tower
height for all existing towers.
Otherwise, DICT shall conduct retrofitting of these existing towers
Please refer to site details for LOS Study. Bidder shall be
allowed to perform site
inspection before start of manufacturing of equipment
to confirm the feasibility of the equipment to the areas.
A final BOM and link design will be submitted before
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 14 of 87
proceeding to manufacturing
of equipment.
40
please confirm
warehousing of delivered equipment
bidder to deliver the equipment to
DICT's warehouse
Winning Bidder shall provide
a warehouse or staging area for the project
41
Please confirm
safety and security of delivered
equipment
DICT shall be responsible for the
safety and security of all delivered equipment to their warehouse and
on site. in the event that there is a pilferage incident after the accepting
the delivered equipment, vendor
shall bear no additional cost due to the incident.
Winning Bidder shall provide
a warehouse or staging area for the project.
42
Please confirm DICT shall be responsible for
securing RIGHT OF WAY for the
repeater stations or whatever is applicable.
Yes.
43 Please confirm that "Commercial
Electricity" shall be DICT's
responsibility
Yes.
44
Kindly provide list and info of existing
and repeater sites include
coordinates, tower info (tower height, tower type), property
acquisition status, availability of commercial power, etc.
Please refer to side
coordinates
45
kindly provide conceptual design
(placement of tower generator, shelter, etc) for the repeater sites.
Bidder shall provide
conceptual design during site survey
46
We request to remove the requirement for "affidavit of site
inspection prior awarding of the
bidas this will delay the timeline and will incur additional cost apart from
the site survey required in the Schedule of Requirements.
Affidavit of site inspection shall be submitted after site
survey
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 15 of 87
47
the list of tower heights and quantity
for sites that need tower and facilities were mentioned during the pre-bid
conference. Please provide FINAL list of tower heights and quantity through
SBB for everybody's reference
Please refer to site
coordinates
48
Bid Data Sheet ITB Clause 5.4, Page 40
The bidder must have
completed , within past
five (5) years from the date of submission and
receipt of at least one (1) single contract of similar
nature amounting to at least fifty percent (50%
of the ABC.
We request to allow similar contract within the past ten (10) years from
the date of submission.
Denied
49
The bidder must hold a minimum of 20 years
PCAB License in General Engineering on or before
the date of the bid
opening, with a AAA Category. (In case of
renewal, the bidder shall submit official receipt on
the filling of the application for renewal of
PCAB License). The
bidder must also hold a PCAB License in
Communication Facilities with a least Medium A
Category for the last five
years before the date of opening
Will it be possible to waive this qualification considering the
restriction or challenge of some bidders for the issuance of a PCAB
license particularly major bidders
who has done nationwide IP Microwave radio deployment at
telecom (telco) companies but were not required such certification
Change to:
The bidder must hold a PCAB
License with Category AAA in General Engineering for a
minimum of two (2) years on
or before the date of the bid opening. For joint venture, at
least one of the JV should comply to this requirement.
50
Link Requirements and Equipment Characteristics
1.1.1. IP Microwave
radio should either be Outdoor/Split system,
must adopt modular design, the service boards
can be plugged/ unplugged.
a. Does outdoor system mean full outdoor? If yes, what is the
requirement for full outdoor system
since the document specifies split system?
B. Full outdoor system does not have service board, is it acceptable?
C. Control unit required to be 1+1 Hot standby, does it mean there is
no need to have the whole split
A. The Outdoor/Split-Type System pertains to MW
Radio Systems that are Split-
Type with Outdoor Unit. MODEM Part is indoor while
TX/RX (RF) Part is outdoor. B.Full Outdoor is not
preferred in this RFP. MODEM and INTERFACE part
should be easily accessed for
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 16 of 87
In case of a Split System,
1.1.1.1. IDU shall
support cascading; 1.1.1.2. IDU must have
an attached cooling
system. 1.1.1.3. The distance
between IDU and ODU can support at least 100
meters
1.1.1.4. Control unit is required to be
configurable to 1+1 Hot standby.
mount system (IDU+ODUS) in 1+1
Hot standby?
ease in O&M.
C. The Control Unit should be redundant. Traffic shall
be protected through RTA for more than 1 RF
canannels. However, the
offered system should be able to support 1+0, 2+0,
1+1 HSB/SD/FD, XPIC Configuration. Where SD
configuration shall be used
for overwater propagation, when necessary, to counter
fading due to reflection.
51
1.1.2. Capacity: The desired microwave IP
radio should have a
guaranteed link capacity of at least 200Mbps (Full
Duplex) upgradeable to 2Gbps. The vendor shall
propose any suitable
configurations to meet the desired requirements
by the DICT, all subject to review and approval of
DICT.
What does upgradeable to 2Gbps entails? Is it via large
bandwidth/channel spacing like 112
MHz or via adding more RF Channels/carriers?
The requirement of the MW Radio to be able to support
upgraeability up to 2Gbps
can be a combination of increased modulation,
increased bandwidth and additional RF channels.
52
1.1.4. Reliability Methods:
ITU-R P.530-7/8 with
Fade Margin of at least 35dB (minimum).
35dB Fade Margin will entails the use
of larger antenna size to cater to the
short period of average path condition is there a limit to the size
of the antenna?
There is no limit to the size
of the antenna, however, if
other vendors can propose smaller size antennas it
means that their radio system is more superior in
terms of sytem gain and in
consideration of other losses.
53
1.1.5. Modulation: The
equipment shall support modulation schemes with
full range of hitless and
errorless Adaptive Coding Modulation (ACM). ATPC
and ACM can work together at same time,
increasing TX power of ATPC function should be
made prior to dropping
35dB Fade Margin will entails the use
of larger antenna size to cater to the short period of average path
condition is there a limit to the size
of the antenna?
There is no limit to the size
of the antenna, however, if other vendors can propose
smaller size antennas it
means that their radio system is more superior in
terms of sytem gain and in consideration of other losses.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 17 of 87
modulation mode of ACM.
When the modulation is adjusted to lower level
modulation scheme, the max TX power of the
radio should be adjusted
to the corresponding level in real time.
• Shall support the
following modulation
schemes without any hardware change or
additional boards: QPSK, 16QAM, 32QAM, 64QAM,
128QAM, 256QAM, 512 QAM, 1024QAM
whichever is applicable
per site.
54
1.1.5. Modulation: The
equipment shall support modulation schemes with
full range of hitless and
errorless Adaptive Coding Modulation (ACM). ATPC
and ACM can work together at same time,
increasing TX power of ATPC function should be
made prior to dropping
modulation mode of ACM. When the modulation is
adjusted to lower level modulation scheme, the
max TX power of the
radio should be adjusted to the corresponding level
in real time.
• Shall support the
following modulation schemes without any
hardware change or additional boards: QPSK,
16QAM, 32QAM, 64QAM, 128QAM, 256QAM, 512
QAM, 1024QAM
Is 409QAM mandatory since such a
high modulation can only caters to very short distance depending on the
frequency band?
The modulation scheme of
4096QAM may not be required in the hops in this
project, however, it still have
to be at least supported, in case we need higher
capacity or reallocation with higher capacity requirement.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 18 of 87
whichever is applicable
per site.
55
1.1.6. Frequency: The
equipment shall support all licensed bands L6 to
42 GHz. ODU that is tunable to the whole
frequency is preferred.
Vendors shall state what kind of free tunable ODU
can be provided. Self-frequency scan is
required.
Is tunable frequency refers to the
whole band within the diplexer range? Is self-frequency scar can
refer to build-into the licensed band microwave transmission system? All
frequency pair spots have to apply to
NTC and need to scan first at site before the installation of microwave
transmission system and such RFI has to be performed at site.
ODUs to be used should be
sub-band free, provide such information in your proposal
to identify which frequency bands are supported.
Self-freqeuncy scanning can
also be defined as being able to check for the suitable
point frequency to be used using the installed ODUs and
having the opposite station
in mute mode for transmitting, then checking
at local station if interferences are observed.
56
1.1.10. Receive Signal Threshold Sensitivity: The
radio equipment must
have signal sensitivity of BER 10-6 of -60dBm or
better.
What is the bandwidth and modulation for a receiver threshold
of 60dBm @BER 10 -6.
The Receiver Threshold Level shall be based on Bidder's
Link Budget Calculation.
Clearly state the Receive Threshold Level according to
the modulation, bandwidth and freqeuncy band used,
but should be -60dBm or
better at BER10E-6.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 19 of 87
57
1.1.13. The proposed
equipment shall have built-in MADM and ETH
switching platform to cross-connect service
among different
directions.
Since the desired microwave system
is all IP, is it necessary to have built-in MADM?
Yes, it is. The switching
capacity should be easily be stated in Vendor's MW Radio
System Catalogue.
58
1.1.17. Ethernet feature.
The proposed equipment shall support, but not
limited to, the following
services and standards: ● 10/100/1000 base -
T/X (IEEE 802.3) ● Ethernet VLANs (IEEE
802.3ac) ● Virtual LAN (IEEE
802.1Q)
● Class of Service (IEEE 802.1q/p)
● Provider Bridges (QinQ-IEEE 802.1ad)
● Link Aggregation
Group (LAG) ● Ethernet Linear
Protection Switching (G.8031)
● Ethernet Ring Protection (G.8032v2)
● Ethernet OAM (IEEE
802.3ah, IEEE 802.1ag, ITU-T Y.1731)
● RFC 1349: IPv4 TOS ● RFC 2460: IPv6 Traffic
Classes
● RFC 2474: IPv4 DSCP
Ethernet OAM - is compliance to ITU-
Y-1731 good enough since it is an ITU standard applicable for the
world.
Denied.
59
1.1.20. Priority
Management, the scheduling scheme should
support SP, WRR, DWRR,
WFQ, SP+WRR, SP+DWRR, SP+WFQ
Priority Management - Is compliance
to a few scheduling schemes good enough?
Offered MW Radio System
should be able to support the listed QoS functions.
Please comply to at least
four (4) of the QoS functions.
60
1.1.21. Congestion Management shall
support Tail drop, RED (Random Early Detection)
Congestion Management - Is compliance good enough/
Denied. Offered MW Radio System should be able to
support the listed QoS functions.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 20 of 87
and WRED (Weighted
Random Early Detection)
61
The equipment shall
support multi-nodal ODUs on one IDU with
minimum of 4 ODUs up to
12 ODUs or above without cascade and shall
support 1+0, 2+0, 1+1 HSB/SD/FD, XPIC
Configuration
Do the minimum of 4 ODUs up tp 12
ODUs or above refers to the RF carriers?
Yes, it refers to the no. of
RFs as well. It can also mean the no. of directions it can
support in nodal
configuration.
62
1.8.1. The antenna should be a dual
polarized-high performance with
radome. Vendor shall provide single and dual
polarized antennas
covering 6 to 42GHz frequency. The antenna
system should withstand a wind loading of at least
300kph. Must be
adaptable to the NTC allowed frequencies to be
used.
Which antenna type, single or dual polarized should the vendor provide
as there is a conflict with the earlier statement?
The Bidder shall propose either Single or Dual
Polarized antenna depending on the design and
configuration of the link. Bidder shall provide the most
cost effective solution for
this requirement.
63
1.11. Scalability
The proposed equipment shall support twelve (12)
Radio Directions or above
without cascade, and shall support 1+0, 2+0,
1+1 HSB/SD/FC, XPIC Configuration.
Does the cascade refer to IDUs only? Yes, it refers to IDU only.
64
1.1.6 Frequency: The
equipment shall support all licensed bands
L6 to 42 GHz. ODU that is tunable to the whole
frequency (subband
free). Vendors shall state what kind of free tunable
ODU can be provided. Self-frequency scan is
required.
Is this a mandatory item for vendors
to comply? Tunable ODU is not a common practice and does not
comply with your IP66 requirement.
ODUs to be used should be
sub-band free, provide such information in your proposal
to identify which frequency bands are supported.
ODU's IP66 compliance is
non-negotiable.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 21 of 87
65
1.11 The proposed
equipment shall support twelve (12) Radio
Directions or above without
cascade, and shall
support 1+0, 2+0, 1+1 HSB/SD/FC, XPIC
Configuration.
Is (12) Radio Directions needed at
day 1? What is the minimum radio directions based on actual project
requirement?
The 12 Radio Directions will
not be applied on Day-1, however, it should be
supported on Day-1 by the offered MW Radio
equipment. The actual
project requirement for no. radio directions will be based
on Bidder's design.
66
1.1.11 The vendor shall
propose Layer 3 routing
function and multiplexing, and shall
support L3VPN, L2VPN, Native IP and
MPLS.
Can vendor propose SDN which can
manage the L3 VPN instead of
relying on L3 Equipment Router? This will simplify the operation and
maintenance of the network and will not increase the cost of equipment.
Denied.
67
1.8.3.3 Ingress
Protection: IEC 60529
IP66
Having Tunable ODU does not
comply with IP66. Please confirm
item 1.
Denied. ODUs to be used
should be sub-band free,
provide such information in your proposal to identify
which frequency bands are supported.
ODU's IP66 compliance is
non-negotiable.
68
1.1.4. Reliability Methods:
ITU-R P.530-7/8 with Fade Margin of at least
35dB (minimum).
Faded margin reduced to 25db
instead of 35db. Most Microwave vendors does not support 35db fade
margin.
Denied. Please comply to the
Fade Margin (35dB) and Availability (99.99%)
requirement.
69
1.1.7. Channel Spacing:
Shall support between 7
to 112 MHz
The TOS is old version developed in
1992, it was replaced and adapted
by almost all Microwave manufacturers with RFC2474:IPv4
DSCP. We highly suggest to adapt the latest RFC2474:IPv4 DSCP
instead of the old RFC1349:IPv4
TOS.
DICT cannot see the relation
of the inquiry to the clause.
Reference: Please comply to the stated Channel Spacing
range.
70
1.1.17. Ethernet feature.
The proposed equipment shall support, but not
limited to, the following
services and standards: ● RFC 2460: IPv6 Traffic
Classes
We respectfully suggest to delete
this requirement since all Microwave vendors support VLAN to classify
IPv6 traffic.
IPv6 DSCP compliance is also
acceptable.
71 1.1.20. Priority
Management, the
We respectfully suggest to delete
this requirement, based on our study
Offered MW Radio System
should be able to support
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 22 of 87
scheduling scheme should
support SP, WRR, DWRR, WFQ, SP+WRR,
SP+DWRR, SP+WFQ
there are only very few microwave
manufacturers who can comply on this requirement.
the listed QoS functions.
Please comply to at least four (4) of the QoS
functions.
72
1.8.1. The antenna
should be a dual
polarized-high performance with
radome. Vendor shall provide single and dual
polarized antennas
covering 6 to 42GHz frequency. The antenna
system should withstand a wind loading of at least
300kph. Must be adaptable to the NTC
allowed frequencies to be
used.
No tower will survive a 300Kph wind
speed, it doesn't make sense to keep
the equipment in the tower if there is an incoming typhoon that packs a
wind speed of 300kph. We respectfully suggest to reduce the
wind speed requirement from
300Kph to 200Kph.
Denied. Comply to the
300kph wind survival rating
for antenna.
73
1.8.2.5. Dustproof and
waterproof and must be IP66 Compliant
The antenna is passive component, it
is not a practice in the industry or among microwave manufacturers to
have water Ingress protection specs
on the antenna. We respectfully suggest that this requirement be
deleted.
This item is meant for the
ODUs of your MW Radio Systems. However, the
antenna are already built for
outdoor use and should not be an issue.
74
Eligibility Documents: On
the eligibility requirement. The bidder must have
completed within the past
five (5) years from the date of submission and
receipt of at least one (1) single contract of similar
nature amounting to at
least fifty percent (50%) of the ABC "similar in
contracts" shall mean completed projects
related to Supply,
Installation, Detailed Design, Testing and
Commissioning, or Operation and
Maintenance Support of IP Microwave Radio
Communications System.
In order to accommodate more
eligible bidders, we respectfully suggest that the SLC eligibility
requirement be amended to the ff:
The bidder must have completed within the past ten (10) years from
the date of submission and receipt of at least two (2)completed contract of
similar nature amounting to at least
fifty percent (25%) of the ABC "similar in contracts" shall mean
completed projects related to Supply, delivery and installation of wired and
wireless systems, or ICT project with
Wired and Wireless Network Infra that is nationwide in scope, or any IP
Microwave Radio Communications System.
Denied.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 23 of 87
75
1.1.12. The proposed
equipment shall support OSPF, BGP route
protocol.
The proposed equipment shall
support OSPF, BGP route protocol. The equipment should support
hardware-based BFD, the minimum interval for sending probe packets
should be 3.3ms.
The 802.1ag standard defines the
minimum interval for sending OAM detection packets at 3.3ms in order
to realize fast switching when
detects failure. Is fast switching (during failure detection) standard
important to DICT?
Denied. Please comply to the
listed standard, as well as to 802.1ag.
76
On the UPS requirement, do you
have required Battery Backup Time for the Microwave Radio IDU and
ODU.
15 Mins
77
On the General requirements please advise the required fuel running
capacity in hours of Genset fuel tanks.
To be determined during project implementation.
78
Will dry contracts from Electrical
Power Systems be sufficient for the monitoring of alarms via the NMS?
Yes.
79 Are we going to apply for a separate
KwHr meter from the local Electric
Utility for each facility?
To be determined during site survey.
80
Please advise the approximate land
area that will be provided for the
side development of each site.
To be determined during site
survey.
81
Will there be no Environmental
Alarms required within the Equipment Shelter?
Equipment must support
environmental alarms using dry contacts
82 For the CCTV camera, please advise
the required camera resolution.
2688 x 1520
83
The bidder must hold a
minimum of 20 years PCAB License in General
Engineering on or before
the date of the bid opening, with an AAA
Category. (In case of renewal, the bidder shall
Is this a mandatory requirement?
What if we have a lower PCAB license with corresponding lower
year of holding requirement – can
we use the said license and still be eligible to bid?
Change to:
The bidder must hold a PCAB License with Category AAA in
General Engineering for a
minimum of two (2) years on or before the date of the bid
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 24 of 87
submit official receipt on
the filling of the application for renewal of
PCAB License.). The bidder must also hold a
PCAB License in
Communication Facilities with a least Medium A
Category for the last five years before the date of
the opening.
opening. For joint venture, at
least one of the JV should comply to this requirement.
84
1.1.6. Frequency: The equipment shall support
all licensed bands L6 to 42 GHz. ODU that is
tunable to the whole frequency (sub- band
free). Vendors shall state
what kind of free tunable ODU can be provided.
Self-frequency scan is required.
Is this a mandatory requirement? Usually Sub‐band free equipment
would mean that diplexers of the ODU’s are field replaceable which
would mean they need to be weatherproofed properly and may
risk water ingress on site. The
requirement being an all‐weather system should take into
consideration this disadvantage. Also, usually these types of
equipment would cost more and
would not prove beneficial to the project’s objective.
ODUs to be used should be sub-band free, provide such
information in your proposal to identify which frequency
bands are supported. ODU's IP66 compliance is non-
negotiable. Removable
items, such as diplexers, are not preferred. ODUs should
have wide-band filters.
85
1.1.23. The proposed equipment shall support
bandwidth notification based on ITU Standard.
Is this a mandatory requirement? The equipment to be proposed would
support Layer 3 services which can be used to interface to any external
third‐party router. The
abovementioned feature would not really be needed and would only eat
up equipment resources if enabled.
The offered MW Radio System should be able to
support such requirement.
86
1.4. Security The
proposed equipment
should support SSL/SSH/SNMPV3 to
guarantee the securityof management.
SSL is a networking protocol used for
web clients and web servers which
does not apply to radio backhaul equipment, is this a mandatory
requirement? Because that would mean a firewall or another router
would be supplied together with the
equipment?
This is a security
management for the
communication between your MW Radio network
element and your NMS. Please comply to this
requirement.
87
1.12. Certifications
1.12.1. The offered equipment shall comply
with the Chartered Engineer (CE) Certificate.
Kindly elaborate please on the
Chartered Engineering certificate? And what particular equipment would
be certified?
CE Markings should be
clearly visible in the offered MW Radio System, usually in
your Transmitter/Receiver Units (or ODUs). The CE
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 25 of 87
Certification certifies that
your equipment is compliant to the requirements of
Health & Safety, Electromangetic
Compatibility and Effective &
Efficient Use of Radio Spectrum. Provide any CE
Certification.
88
1.8. Antenna 1.8.1. The
antenna should be a dual
polarized-high performance with
radome. Vendor shall provide single and dual
polarized antennas covering 6 to 42GHz
frequency. The antenna
system should withstand a wind loading of at least
300kph. Must be adaptable to the NTC
allowed frequencies to
beused.
Most if not all antenna
manufacturers only sell 250KPH
rated antennas, I feel it better that this requirement be lowered down to
250KPH.
All antenna suppliers have
300kph capability. Please
comply to this requirement.
89 Kindly provide site coordinates in
order to check the design.
See site coordinates.
90
Please provide preliminary details of
existing towers and their structural plan for our review. Also, for the new
sites details of the lot should be
supplied.
See site coordinates.
91
Given that there are a lot of
requirements pertaining to tower retrofitting, access roads, civil works
and MW link design. Will there be a
preliminary survey to be conducted by the bidder in order to provide a
good proposal?
Bidder will be allowed to visit
the sites. Please see supplemental bid bulletin for
site coordinates.
92
If there would be initial surveys done
will DICT be accompanying the
bidders on the sites?
No.
93 Are all new sites complete acquired
by the Government?
No.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 26 of 87
94
ON the requirement of NMS – how
many servers are needed? And on the DCN plan what are the details of
the network in which the sites are to be connected on?
One Server and One Client.
DCN Plan to be dicuss by the winning bidder.
95
Need to relax requirement of PCAB. Change to:
The bidder must hold a PCAB License with Category AAA in
General Engineering for a minimum of two (2) years on
or before the date of the bid
opening. For joint venture, at least one of the JV should
comply to this requirement.
96
Is this a mandatory requirement? Usually Sub-band free equipment
would mean that diplexers of the
ODU’s are field replaceable which would mean they need to be
weather-proofed properly and may risk water ingress on site. The
requirement being an all-weather
system should take into consideration this disadvantage.
Also, usually these types of equipment would cost more and
would not prove beneficial to the project’s objective.
Yes, it is a mandatory requirement. ODUs to be
used should be sub-band
free, provide such information in your proposal
to identify which frequency bands are supported. ODU's
IP66 compliance is non-
negotiable. Removable items, such as diplexers, are
not preferred. ODUs should have wide-band filters.
97
Is this a mandatory requirement?
The equipment to be proposed would support Layer 3 services which can
be used to interface to any external third-party router. The above-
mentioned feature would not really
be needed and would only eat up equipment resources if enabled.
The offered MW Radio
System should be able to support such requirement.
98
1.4. Security The proposed equipment
should support
SSL/SSH/SNMPV3 to guarantee the securityof
management.
SSL is a networking protocol used for web clients and web servers which
does not apply to radio backhaul
equipment, is this a mandatory requirement? Because that would
mean a firewall or another router
This is a security management for the
communication between
your MW Radio network element and your NMS.
Please comply to this requirement.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 27 of 87
would be supplied together with the
equipment?
99
1.12. Certifications
1.12.1. The offered equipment shall comply
with the Chartered
Engineer (CE) Certificate.
Kindly elaborate please on the
Chartered Engineering certificate? And what particular equipment would
be certified?
CE Markings should be
clearly visible in the offered MW Radio System, usually in
your Transmitter/Receiver
Units (or ODUs). The CE Certification certifies that
your equipment is compliant to the requirements of
Health & Safety,
Electromangetic Compatibility and Effective &
Efficient Use of Radio Spectrum. Provide any CE
Certification.
100
1.8. Antenna 1.8.1. The
antenna should be a dual
polarized-high performance with
radome. Vendor shall provide single and dual
polarized antennas
covering 6 to 42GHz frequency. The antenna
system should withstand a wind loading of at least
300kph. Must be adaptable to the NTC
allowed frequencies to be
used.
Most if not all antenna
manufacturers only sell 250KPH
rated antennas, I feel it better that this requirement be lowered down to
250KPH.
All antenna suppliers have
300kph capability. Please
comply to this requirement.
101
Given that there are a lot of
requirements pertaining to tower retrofitting, access roads, civil works
and MW link design. Will there be a
preliminary survey to be conducted by the bidder in order to provide a
good proposal?
Bidder will be allowed to visit
the sites. Please see supplemental bid bulletin for
site coordinates.
102
If there would be initial surveys done
will DICT be accompanying the
bidders on the sites?
No.
103 Are all new sites complete acquired
by the Government?
No.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 28 of 87
104
ON the requirement of NMS – how
many servers are needed? And on the DCN plan what are the details of
the network in which the sites are to be connected on?
One Server and One Client.
DCN Plan to be discuss by the winning bidder.
105
We also would like to ask for the
Network Diagram for us to be able to address any issue on interoperability.
These are all new links, there
is no interoperability issue.
106
Clarification 1. - Can we provide single polarized if it will suffice the
link requirement?
-NMS was not in the specifications
but requires to provide in the proposal
Clarification 2 - Kindly provide details
on NMS requirement such as HW
Servers etc.
Clarification1: The Bidder shall propose either Single or
Dual Polarized antenna
depending on the design and configuration of the
link. Bidder shall provide the most cost effective solution
for this requirement.
Clarification 2: Provide 1
Main Server and 1 Client Server.
107
SBB No. 5
Deadline for Submission of Bids is 1 October 2019
12:00PM
The Date and time of Bid Opening is on 1 October
2019 1:30PM
We Request to extend the Bid
Submission and Opening from1
October 2019 to 31 October 2019 so that we can thoroughly prepare the
documentation relative thereto, among which is the JVA
documentation.
Denied
108
Schedule of Requirement Number 2, Page 80
Hauling delivery, supply
and installation of tower
and facilities materials
Within one hundred twenty (120) calendar
days after the approval of
detailed design, tests, plans, etc.
We request to extend the delivery lead time of towers from 120 days to
18 months upon approval due to the fabrication and hauling process of
towers
Denied
109
May we request another pre-bid conference to be conducted to
include the clarification from last pre-bid
Denied
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 29 of 87
110
May we ask for an extension of the
bid deadline to October 18 instead of October 1 in the last bid supplement
Denied
111
Bid Data Sheet ITB Clause 5.4, Page 40
The Bidder must have completed within past
five (5) years from the date of submission and
receipt of at least one (1)
single contract of similar in nature amounting to at
least fifty percent (50%) of the ABC.
We request to allow any ICT or other Telecommunication Solution Projects
from a major telecom company
within ten (10) years.
This amount of project (microwave radio) is quite huge so the chances
of having the same size or amount
(50% ABC) as similar project name is a bit restrictive.
Denied
112
Kindly provide list for info for exisiting sites and repeater sites:
-Coordinates -Tower info (tower height, tower
type), -Property acquisition status,
-availability of commercial power
and/or genset, -Other pertinent info needed.
Please refer to site coordinates.
113 For the sites that need tower and
facilities, please provide FINAL list of
tower heights.
To be determined during Implementation.
ORIGINAL PROVISION AMENDED PROVISION
Section I. Invitation to Bid
Atty. Jiezl Gabrielle G. Reotutar OIC – Head, BAC Secretariat Department of Information and Communications Technology C.P. Garcia Avenue, Diliman, Quezon City Telephone No.: 920-0101 local 1101 Email Address: [email protected] Website: www.dict.gov.ph
Manuel Anthony S. Tan OIC Director, Procurement Service Department of Information and Communications Technology C.P Garcia Avenue, Diliman, Quezon Telephone No.: 920-0101 local 1101 Email Address: [email protected] Website: www.dict.gov.ph
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 30 of 87
Section II. Instruction to Bidders
12. Documents Comprising the Bid: Eligibility and Technical Components
1.1 Unless otherwise indicated in the BDS, the first envelope shall contain the following eligibility and technical documents:
1. Eligibility Documents –
Class “A” Documents:
(i) PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
(ii) Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid; and
Statement of the Bidder’s SLCC similar to the contract to be bid, in accordance with ITB Clause 5.4, within the relevant period as provided in the BDS.
The two statements required shall indicate for each contract the following:
(ii.1) name of the contract;
(ii.2) date of the contract;
12. Documents Comprising the Bid: Eligibility and Technical Components
1.1. Unless otherwise indicated in the
BDS, the first envelope shall
contain the following eligibility
and technical documents:
1. Eligibility Documents –
Class “A” Documents:
(i) Registration Certificate from the
Securities and Exchange
Commission (SEC) for
corporations, Department of
Trade and Industry (DTI) for sole
proprietorship, or from
Cooperative Development
Authority CDA) for cooperatives.
(ii) Valid and Current
Business/Mayor’s Permit issued by
the city or municipality where the
principal place of business of the
prospective bidder is located OR the
equivalent document for Exclusive
Economic Zones or Areas.
(iii) Valid and Current Tax Clearance
issued by Philippines’ Bureau of
Internal Revenue (BIR) Accounts
Receivable Monitoring Division per
Executive Order 398, Series of 2005.
(iv) Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative format or separate reports):
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 31 of 87
(ii.3) contract duration;
(ii.4) owner’s name and address;
(ii.5) kinds of Goods;
(ii.6) For Statement of Ongoing Contracts - amount of contract and value of outstanding contracts;
(ii.7) For Statement of SLCC - amount of completed contracts, adjusted by the Bidder to current prices using PSA’s consumer price index, if necessary for the purpose of meeting the SLCC requirement;
(ii.8) date of delivery; and
(ii.9) end user’s acceptance or official receipt(s) or sales invoice issued for the contract, if completed, which shall be attached to the statements.
(iii) NFCC computation in accordance with ITB Clause 5.5 or a committed Line of Credit from a universal or commercial bank.
(iv.1) Independent Auditor’s Report;
(iv.2) Balance Sheet (Statement of Financial Position); and
(iv.3) Income Statement (Statement of Comprehensive Income)
(v) PhilGEPS Certificate of
Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
(vi) Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid; and
Statement of the Bidder’s SLCC similar to the contract to be bid, in accordance with ITB Clause 5.4, within the relevant period as provided in the BDS.
The two statements required shall indicate for each contract the following: (ii.1) name of the contract; (ii.2) date of the contract; (ii.3) contract duration; (ii.4) owner’s name and address; (ii.5) kinds of Goods;
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 32 of 87
(ii.6) For Statement of
Ongoing Contracts - amount of
contract and value of outstanding
contracts;
(ii.7) For Statement of SLCC -
amount of completed contracts,
adjusted by the Bidder to current
prices using PSA’s consumer price
index, if necessary for the
purpose of meeting the SLCC
requirement;
(ii.8) date of delivery; and
(ii.9) end user’s acceptance or official receipt(s) or sales invoice issued for the contract, if completed, which shall be attached to the statements.
(vii) Statement of Completed Single Largest Contract within the past five (5) years from the date of submission and receipt of bids equivalent to at least fifty percent (50%) of the ABC (Annex I-A)
(viii) NFCC computation in accordance with ITB Clause 5.5 or a committed Line of Credit from a universal or commercial bank.
SECTION III. BID DATA SHEET
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 33 of 87
xii. Other technical documents which will be required for the project
i. The bidder must hold a minimum of 20 years PCAB License in General Engineering on or before the date of the bid opening, with an AAA Category. (In case of renewal, the bidder shall submit official receipt on the filling of the application for renewal of PCAB License.). The bidder must also hold a PCAB License in Communication Facilities with a least Medium A Category for the last five years before the date of the opening.
xii. Other technical documents which will be required for the project
i.The bidder must hold a PCAB License with Category AAA in General Engineering for a minimum of two (2) years on or before the date of the bid opening. For joint venture, at least one of the JV should comply to this requirement.
xii. Other technical documents which will be required for the project i.xxx ii.xxx
iii. Contractor shall submit resume of key personnel to be assigned to the project upon bid opening. These key personnel are the Professional Electronics Engineer (PECE), Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel; Structural Engineer.
xii. Other technical documents which will be required for the project
i.xxx ii. xxx
iii.Contractor shall submit resume of key personnel to be assigned to the project upon bid opening. These key personnel are the Professional Electronics & Communication Engineer (PECE) with minimum Seven (7) years experience in Communication Facilities, Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel.
(a) ELIGIBILITY DOCUMENTS –
Class “A” Documents:
(a) ELIGIBILITY DOCUMENTS –
Class “A” Documents:
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 34 of 87
i. PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
ii. Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid (Annex I).
iii.
a. Statement of Completed Single Largest Contract within the past five (5) years from the date of submission and receipt of bids equivalent to at least fifty percent (50%) of the ABC (Annex I-A)
Any of the following documents must be submitted corresponding to listed contracts per submitted Annex I-A: ● Copy of End user’s acceptance; ● Official receipt/s; or ● Sales Invoice
iv. Duly signed Net Financial Contracting Capacity Computation (NFCC)* per Annex II, in accordance with ITB Clause 5.5 or a committed Line of Credit equivalent to at least ten percent (10%) of the ABC from a universal or commercial bank.
*NFCC = [(Current Assets minus Current Liabilities) (15)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including
i. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations, Department of Trade and Industry (DTI) for sole proprietorship, or from Cooperative Development Authority CDA) for cooperatives;
ii. Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent document for Exclusive Economic Zones or Areas;
In cases of recently expired Mayor’s / Business Permits, said permit shall be submitted together with the official receipt as proof that the bidder has applied for renewal with the period prescribed by the concerned local government units, provided that the renewed permit shall be submitted as a post-qualification requirement.
iii. Valid and Current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005;
iv. Copy of each of the following Audited Financial Statements for 2018 and 2017 (in comparative format or separate reports):
a. Independent Auditor’s Report; b. Balance Sheet (Statement of Financial Position); and
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 35 of 87
awarded contracts yet to be started coinciding with the contract to be bid. Notes: A. The values of the bidder’s current assets and current liabilities shall be based on the data submitted to BIR through its Electronic Filing and Payment System. B. Value of all outstanding or uncompleted contracts refers those listed in Annex-I. C. The detailed computation using the required formula must be shown as provided above. D. The NFCC computation must at least be equal to the total ABC of the project.
c. Income Statement (Statement of Comprehensive Income)
OR
Submission of valid and current PHILGEPS Certificate of Registration and Membership (Platinum Registration) together with Annex A in lieu of (Items i., ii., iii., iv.) Eligibility Documents. Note: Bidder must ensure that all Class “A” Eligibility Documents are valid and current at the time of submission of PHILGEPS Certificate of Registration and Membership (Platinum Registration). In case any of the submitted Eligibility Documents are not valid and current at the time of submission of Platinum Registration, bidders are required to submit the valid and current documents together with the Platinum Registration.
In case the bidder opt to submit their Class “A” Documents, the Certificate of PhilGEPS Registration (Platinum Membership) shall remain as post-qualification requirement to be submitted in accordance with Section 34.2 of the 2016 Revised IRR of RA9184. “GPPB Circular 07-2017 dated 31 July 2017”.
v. PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 36 of 87
their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
vi. Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid (Annex I).
vii. Statement of Completed Single Largest Contract within the past five (5) years from the date of submission and receipt of bids equivalent to at least fifty percent (50%) of the ABC (Annex I-A)
Any of the following documents must be submitted corresponding to listed contracts per submitted Annex I-A:
∙ Copy of End user’s acceptance; ∙ Official receipt/s; or ∙ Sales Invoice
viii. Duly signed Net Financial Contracting Capacity Computation (NFCC)* per Annex II, in accordance with ITB Clause 5.5 or a committed Line of Credit equivalent to at least ten percent (10%) of the ABC from a universal or commercial bank.
a. Should the bidder opt to submit NFCC, computation must at least be equal to the ABC of the project. Provided, however, for joint ventures, the partner
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 37 of 87
responsible to submit the NFCC shall likewise submit the Statement of all its ongoing contracts and Audited Financial Statements. *NFCC = [(Current Assets minus Current Liabilities) (15)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract to be bid.
Notes:
A. The values of the bidder’s current assets and current liabilities shall be based on the data submitted to BIR through its Electronic Filing and Payment System.
B. Value of all outstanding or uncompleted contracts refers those listed in Annex-I.
C. The detailed computation using the required formula must be shown as provided above.
D. The NFCC computation must at least be equal to the total ABC of the project.
OR
b. Should the bidder opt to submit a Committed Line of Credit, it must be at least equal to ten percent (10%) of the ABC issued by a Local Universal or Local Commercial Bank.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 38 of 87
Class “B” Documents: (For Joint Venture)
v.For Joint Ventures, Bidder to submit either:
1. Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint venture is already in existence; or
2. Copy of Protocol / Undertaking of Agreement to Enter into Joint Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture.
For Joint Venture, the following documents must likewise be submitted by each partner:
● PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
For item (ii) to (iv) of the required eligibility documents, submission by any
CLASS “B” DOCUMENTS (FOR JOINT VENTURE)
v. For Joint Ventures, Bidder to submit either:
1.Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint venture is already in existence, or
2.Copy of Protocol / Undertaking of Agreement to Enter into Joint Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture.
For Joint Venture, the following documents must likewise be submitted by each partner:
1. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations or from Department of Trade and Industry (DTI) for sole proprietorship, or from Cooperative Development Authority (CDA) for cooperatives;
2. Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 39 of 87
of the Joint Venture partner constitutes compliance.
document for Exclusive Economic Zones or Areas;
In cases of recently expired Mayor’s / Business Permits, said permit shall be submitted together with the official receipt as proof that the bidder has applied for renewal with the period prescribed by the concerned local government units, provided that the renewed permit shall be submitted as a post-qualification requirement;
3. Valid and current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005;
4. Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative form or separate reports):
a. Independent Auditor’s Report;
b. Balance Sheet (Statement of Financial Position); and
c. Income Statement (Statement of Comprehensive Income)
Each of the above statements must have stamped “received” by the Bureau of Internal Revenue (BIR) or its duly accredited and authorized institutions.
OR
5. Submission of valid and current PHILGEPS Certificate of Registration and Membership (Platinum
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 40 of 87
Registration) together with Annex A in lieu of the eligibility documents.
Note: Bidder must ensure that all Class “A” Eligibility Documents are valid and current at the time of submission of PHILGEPS Certificate of Registration and Membership (Platinum Registration). In case any of the submitted Eligibility are not valid and current at the time of submission of Platinum Registration, bidders are required to submit the valid and current documents.
● In case the JV Partners opt to submit their Class “A” Documents, the Certificate of PhilGEPS Registration (Platinum Membership) shall remain as post-qualification requirement to be submitted in accordance with Section 34.2 of the 2016 Revised IRR of RA9184. “GPPB Circular 07-2017 dated 31 July 2017”
For item (ii) to (iv) of the required eligibility documents, submission by any of the Joint Venture partner constitutes compliance.
10.1 The Procuring Entity’s address is:
Department of Information and Communications Technology DICT Building, C.P. Garcia Avenue, Diliman, Quezon City Atty. Jiezl Gabrielle G. Reotutar Head, BAC Secretariat Department of Information and Communications Technology C.P. Garcia Avenue, Diliman, Quezon City
10.1 The Procuring Entity’s address is:
Department of Information and Communications Technology DICT Building, C.P. Garcia Avenue, Diliman, Quezon City Atty. Manuel Anthony S. Tan OIC Director, Procurement Service Department of Information and Communications Technology C.P. Garcia Avenue, Diliman, Quezon City
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 41 of 87
Telephone No.: 920-0101 local 3021 Email Address: [email protected] Website: www.dict.gov.ph
Telephone No.: 920-0101 local 3020 Email Address: [email protected] Website: www.dict.gov.ph
ix. Valid and Current Certificate of Distributorship / Dealership/ Resellership of the following product being offered, issued by the principal or manufacturer of the product (if Bidder is not the manufacturer). If not issued by manufacturer, must also submit certification / document linking bidder to the manufacturer. *Note: If in foreign language other than English, it must be accompanied by a translation of the documents in English. The documents shall be translated by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country, and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.
x. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer by an Independent Certifying body;
*Note: If in foreign language other than English, it must be accompanied by a translation of the documents in English. The documents shall be translated by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country, and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines;
xi.List of authorized Service Centers/Support Centers in the Philippines (with available spare parts, indicating address, telephone & fax number/s, e-mail address & contact person). In the event of closure of business, termination of franchise / service center, the supplier shall
ix. Valid and Current Certificate of Distributorship / Dealership/ Resellership of the main products being offered (IP Microwave Radio), issued by the principal or manufacturer of the product (if Bidder is not the manufacturer). If not issued by manufacturer, must also submit certification / document linking bidder to the manufacturer. *Note: If in foreign language other than English, it must be accompanied by a translation of the documents in English. The documents shall be translated by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country, and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines.
x.Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer (IP Microwave Radio) by an Independent Certifying body; *Note: If in foreign language other than English, it must be accompanied by a translation of the documents in English. The documents shall be translated by the relevant foreign government agency, the foreign government agency authorized to translate documents, or a registered translator in the foreign bidder’s country, and shall be authenticated by the appropriate Philippine foreign service establishment/post or the equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines;
xi. Provision is deleted.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 42 of 87
notify the DICT accordingly of the new service centers with telephone numbers and address who can provide the needed parts, supplies and service;
xii. Other technical documents which will be required for the project
i. Written Statement of the contractor signed by their authorized representative that they have at least five (5) years of direct experience on engineering, supply and delivery, installation, testing, and commissioning and experience in operations and maintenance of communications facilities network.
ii. Contractor shall submit resume of key personnel to be assigned to the project upon
bid opening. These key personnel are the Professional Electronics & Communication
Engineer (PECE) with minimum Seven (7)
years experience in Communication Facilities, Project Manager, Project Engineer and Outside
Plant Supervisor and six (6) support personnel.
iii. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer of radio equipment by an Independent Certifying body.
iv. Written Statement of the equipment manufacturer signed by their authorized representative that all features offered and complied to must be available from the time of award.
v. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved.
Written Certification from the equipment manufacturer signed by their authorized representative that they are in in good standing and reputation both in the Local and US, European, and ASIAN Market.
xii. Other technical documents which will be required for the project
i. Written Statement of the contractor signed by their authorized representative that they have at least five (5) years of direct experience on engineering, supply and delivery, installation, testing, and commissioning and experience in operations and maintenance of communications facilities network.
ii. Contractor shall submit resume of key
personnel to be assigned to the project upon bid opening. These key personnel are the
Professional Electronics & Communication
Engineer (PECE) with minimum Seven (7) years experience in Communication Facilities,
Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel.
iii. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer of radio equipment by an Independent Certifying body.
iv. Written Statement of the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that all features offered and complied to must be available from the time of award.
v. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved.
Written Certification from the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that they are in in good standing and reputation both in the Local and US, European, and ASIAN Market.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 43 of 87
Section V. Special Conditions of the Contract
5.1 The Procuring Entity’s addressee, address and contact person for Notices is:
ELISEO M. RIO, JR. Officer-In-Charge, Secretary Department of Information and Communications Technology DICT Building, C.P. Garcia Avenue, Diliman, Quezon City Telephone No.: +63-02-9200101 Contact Person JIEZL GABRIELLE G. REOTUTAR OIC - Head, BAC Secretariat Department of Information and Communications Technology C.P. Garcia Avenue, Diliman, Quezon City Tel. No. +63-2-9200101 local 3021 Email Address: [email protected] Website: www.dict.gov.ph
5.1 The Procuring Entity’s addressee, address and contact person for Notices is:
ELISEO M. RIO, JR. Undersecretary for Operations Department of Information and Communications Technology DICT Building, C.P. Garcia Avenue, Diliman, Quezon City Telephone No.: +63-02-9200101 Contact Person Atty. Manuel Anthony S. Tan OIC Director, Procurement Service Department of Information and Communications Technology C.P. Garcia Avenue, Diliman, Quezon City Tel. No. +63-2-9200101 local 3020 Email Address: [email protected] Website: www.dict.gov.ph
SECTION VI. SCHEDULE OF REQUIREMENTS
# DESCRIPTION
DURATION
(calendar days) DESCRIPTION
DURATION
(calendar days)
2 Hauling, delivery, supply and installation of tower and facilities materials
Within one hundred twenty (120) days after the approval of detailed design, tests, plans, etc.
Hauling, delivery, supply and installation of tower and facilities materials
Within one hundred twenty (120) days after the completion of site acquisition, confirmation of access road's feasibility by DICT, and approval of
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 44 of 87
detailed design, tests, plan, etc.
4 Hauling, Delivery, Supply, Installation and Configuration of IP radio system, power system, NMS and other relevant works
Within one hundred and fifty (150) days after the approval of detailed design drawing, test, plans, etc., and upon receipt of Notice to Install/Approval Sheet of submitted requirements
Hauling, Delivery, Supply, Installation and Configuration of IP radio system, power system, NMS and other relevant works
Within one hundred fifty (150) days after the completion of site acquisition, confirmation of access road's feasibility by DICT, and approval of detailed design drawing, test, plans,
SECTION VII TECHNICAL SPECIFICATIONS
1.1 Link Requirements and Equipment Characteristics
1.1.6. Frequency: The equipment shall support all licensed bands L6 to 42 GHz. ODU that is tunable to the whole frequency (sub-band free). Vendors shall state what kind of free tunable ODU can be provided. Self-frequency scan is required.
1.1.6. Frequency: The equipment shall support all licensed bands L6 to 42 GHz. ODU that is tunable to the whole frequency (sub-band free). Vendors shall state what kind of free tunable ODU can be provided.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 45 of 87
1.1.17. Ethernet feature. The proposed equipment shall support, but not limited to, the following services and standards:
● 10/100/1000 base - T/X (IEEE 802.3) ● Ethernet VLANs (IEEE 802.3ac) ● Virtual LAN (IEEE 802.1Q) ● Class of Service (IEEE 802.1q/p) ● Provider Bridges (QinQ-IEEE 802.1ad) ● Link Aggregation Group (LAG) ● Ethernet Linear Protection Switching
(G.8031)Ethernet Ring Protection (G.8032v2)
● Ethernet OAM (IEEE 802.3ah, IEEE 802.1ag, ITU-T Y.1731)
● RFC 1349: IPv4 TOS ● RFC 2460: IPv6 Traffic Classes RFC
2474: IPv4 DSCP
1.1.17. Ethernet feature. The proposed equipment shall support, but not limited to, the following services and standards:
● 10/100/1000 base - T/X (IEEE 802.3)
● Ethernet VLANs (IEEE 802.3ac)
● Virtual LAN (IEEE 802.1Q) ● Class of Service (IEEE
802.1q/p) ● Provider Bridges (QinQ-
IEEE 802.1ad) ● Link Aggregation Group (LAG) ● Ethernet Ring Protection
(G.8032v2) ● Ethernet OAM (IEEE
802.3ah, IEEE 802.1ag, ITU-T Y.1731)
1.1.20. Priority Management, the scheduling scheme should support SP, WRR, DWRR, WFQ, SP+WRR, SP+DWRR, SP+WFQ
1.1.20 Priority Management, the scheduling scheme should support SP, WRR, DWRR, WFQ, SP+WRR, SP+DWRR, SP+WFQ. Winning bidder should at least comply to four (4) QOS functions.
1.14.1.1. 4-channel Network DVR 1.14.1.1 channel Network NVR
ANTENNA TOWERS
Towers to be assembled and installed shall be 3-legged/ Monopole Self-Supporting Tower or 4-legged self-supporting tower (as applicable, depending on the design)
Towers to be assembled and installed shall be Guyed Tower/ 3-legged/ Monopole Self-Supporting Tower or 4-legged self-supporting tower (as applicable, depending on the design)
1.11. SHELTER WORKS
This involves the installation of telecommunications equipment facilities with dimension of 4x4x3 (LxWxH) in meters, continous footing for CHB wall 6” thick, concrete slab roof with sloping grade provided with a concrete
OEM approved shelter, bidder to submit that proposed shelter is certified by the OEM. Shelter shall be made of pre fabricated polyurethane insulated parts with aluminium frame construction and design for marine environment are able to widthstand
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 46 of 87
column as support. 1m wide and 2.7m height of steel door as entry to facility as per approved plan and specification
Philippine Wind & Seismic Zone Structural requirements. Protected against insect, radio frequency interference (RFI), insemsitive to salt water fungus and termites. This involves the installation of telecommunications equipment facilities with dimension of 4x4x3 (LxWxH) in meters, or continous footing for CHB wall 6” thick, concrete slab roof with sloping grade provided with a concrete column as support. 1m wide and 2.7m height of steel door as entry to facility as per approved plan and specification
1.14. ACCESS ROAD This involves installation of route between
main Road. To site location. The access road shall Accommodate vehicles that deliver materials
to site area. The road surface and base course is made of compacted aggregates. The total
width of the road is 3.2m with sloping grade of 2-
3% at each end. The canal has an incline slope of
5%.
1.14. ACCESS ROAD This involves installation of route between main road. To site location. The access road shall accommodate vehicles that deliver materials to site area. The road surface and base course is made of compacted aggregates. The total width of the road is 3.2m with sloping grade of 2-3% at each end. The canal has an incline slope of 5%. If not feasible the winning bidder can suggest other alternatives with coordination and approval of DICT.
No original provision. BIDDER’S QUALIFICATION The bidder must be ISO 9001: 2015 certified (Quality Management System), for joint venture agreement, at least one of the JV should be ISO 9001: 2015 certified.
Payment Terms: Payment Terms:
Payment Milestones Progress
Payment Milestones Progress
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 47 of 87
Advance Payment subject to submission of an irrevocable letter of credit or bank guarantee issued by a universal or commercial bank pursuant to Section 4.5 of Annex D of the Revised IRR of RA 9184
15% Advance Payment subject to submission of an irrevocable letter of credit or bank guarantee issued by a universal or commercial bank pursuant to Section 4.5 of Annex D of the Revised IRR of RA 9184
15%
Upon Completion of Site Survey 15% Provision Deleted
Upon onsite delivery of IP Microwave Radio System Hardware
40% Upon delivery of IP Microwave Radio/antenna System Hardware to supplier’s centralized warehouse
40%
Upon completion of Agreed Testing
15% Upon delivery, hauling, installation of towers and accessories and completion of Agreed Testing Per Link, and upon installation of IP Radio, Antenna, power system, NMS and its accessories Payment is per completed site/link: *number of links pro rated at 30% for this milestone
30%
After completion of Training 5% After completion of Training 5%
Upon Project Acceptance 10% Upon Project Acceptance 10%
No original provision. OTHER TECHNICAL DOCUMENTS Other technical documents which will be required for the project
i. The bidder must hold a PCAB License with Category AAA in General Engineering for a minimum of two (2) years on or before the date of the bid opening. For joint venture, at least one of the JV should comply to this requirement.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 48 of 87
ii. Written Statement of the contractor
signed by their authorized representative that they have at least five (5) years of direct experience on engineering, supply and delivery, installation, testing, and commissioning and experience in operations and maintenance of communications facilities network.
ii. Contractor shall submit resume of key personnel to be assigned to the project upon bid opening. These key personnel are the Professional Electronics & Communication Engineer (PECE) with minimum Seven (7) years experience in Communication Facilities, Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel.
iv. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer of radio equipment by an Independent Certifying body.
v. Written Statement of the equipment manufacturer signed by their authorized representative that all features offered and complied to must be available from the time of award. vi. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 49 of 87
vii. Written Certification from the equipment manufacturer (IP MICROWAVE RADIO) signed by their authorized representative that they are in good standing and reputation both in the Local and US, European, and ASIAN Market.
SECTION XIII. TECHNICAL BID FORM
a. IP Microwave Radio b. Battery c. Rectifier d. Generator Set e. Antenna f. CCTV Camera
a. IP Microwave Radio b. UPS/Battery c. Rectifier d. Generator Set e. Antenna f. CCTV Camera g. Antenna Tower
Delivery Place and Distribution 1. Tagum-Libuganon River Basin (NGCP
Maco) 2. Virac PAGASA Complex (Legaspi
GovNetPoP) 3. Abra River Basin (NGCP Bantay) 4. Aparri PAGASA Radar (NGCP
Tuguegarao) 5. Baler PAGASA Station (Baler CLS) 6. Guiuan Radar Station (Tacloban
GovNet POP) 7. Subic Radar Station (NGCP Subic) 8. Tagaytay PAGASA Station (NGCP
Dasmarinas) 9. Virac Radar Station (Legaspi GovNet
POP) 10. Tampakan PAGASA Station (NGCP
Tacurong) 11. Hinatuan PAGASA Station (NGCP
Bislig) 12. Quezon, Palawan (Puerto Princesa Wi-
Fi POP) 13. Agusan River Basin (NGCP San
Francisco) 14. Tagum USEP (NGCP Maco)
Delivery Place and Distribution 1. Tagum-Libuganon River Basin
(NGCP Maco) 2. Virac PAGASA Complex
(Legaspi GovNetPoP) 3. Abra River Basin (NGCP Bantay) 4. Aparri PAGASA Radar (NGCP
Tuguegarao) 5. Baler PAGASA Station (Baler CLS) 6. Guiuan Radar Station (Tacloban
GovNet POP) 7. Subic Radar Station (NGCP Subic) 8. Tagaytay PAGASA Station (NGCP
Dasmarinas) 9. Virac Radar Station (Legaspi
GovNet POP) 10. Tampakan PAGASA Station (NGCP
Tacurong) 11. Hinatuan PAGASA Station (NGCP
Bislig) 12. Quezon, Palawan (Puerto
Princesa Wi-Fi POP) 13. Agusan River Basin (NGCP San
Francisco) 14. Tagum USEP (NGCP Maco)
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 50 of 87
15. General Santos Synoptic Station (NGCP General Santos)
16. Tanay Radar and Synoptic Station (NGCP Lumban)
17. Dagupan Weather Complex Station (Dagupan GovNetPoP)
18. Tacloban Airport Synoptic Station (Tacloban GovNetPoP)
19. Daet Station (P. Daet RS)
15. General Santos Synoptic Station (NGCP General Santos)
16. Tanay Radar and Synoptic Station (NGCP Lumban)
17. Dagupan Weather Complex Station (Dagupan GovNetPoP)
18. Tacloban Airport Synoptic Station (Tacloban GovNetPoP)
19. Daet Station (P. Daet RS) 20. Agno River Basin
ANNEX X. DETAILED FINANCIAL BREAKDOWN
ITEM Qty ITEM Qty
Engineering services (site survey, design and technical documents, Radio license permit and structural integrity test)
19 links Engineering services (site survey, design and technical documents, Radio license permit and structural integrity test)
33 links
Supply and deliver of IP Microwave radio including spares and antenna system, Power system (Rectifier, Battery and Genset)
19 links Supply and deliver of IP Microwave radio including spares and antenna system, Power system (Rectifier, UPS/Battery and Genset)
33 links
Installation, testing, commissioning and acceptance of the systems
31 links Installation, testing, commissioning and acceptance of the systems
33 links
Section X. Checklist of Requirements
ENVELOPE 1: ELIGIBILITY AND TECHNICAL DOCUMENTS
ELIGIBILITY DOCUMENTS
CLASS “A” DOCUMENTS
12.1 (a.1.) ELIGIBILITY DOCUMENTS
i. PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign
ENVELOPE 1: ELIGIBILITY AND TECHNICAL DOCUMENTS
ELIGIBILITY DOCUMENTS
CLASS “A” DOCUMENTS
12.1 (a) ELIGIBILITY DOCUMENTS
i. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations, Department of Trade and Industry (DTI) for sole proprietorship, or
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 51 of 87
Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
ii. Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid (Annex I)
iii. Statement of Completed Single Largest Contract within the past five (5) years from the date of submission and receipt of bids equivalent to at least fifty percent (50%) of the ABC (Annex I-A). or
1. Duly signed Net Financial Contracting Capacity Computation (NFCC)* per Annex II, in accordance with ITB Clause 5.5 or a committed Line of Credit equivalent to at least ten percent (10%) of the ABC from a universal or commercial bank
*NFCC = [(Current Assets minus Current Liabilities) (15)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract to be bid.
Notes:
a) The values of the bidder’s current assets and current liabilities shall be based on the data submitted
from Cooperative Development Authority CDA) for cooperatives.
ii. Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent document for Exclusive Economic Zones or Areas.
iii. Valid and Current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005.
iv. Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative format or separate reports):
a. Independent Auditor’s Report;
b. Balance Sheet (Statement of Financial Position); and
c. Income Statement (Statement of Comprehensive Income)
v. PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 52 of 87
to BIR through its Electronic Filing and Payment System.
b) Value of all outstanding or uncompleted contracts refers those listed in Annex-I.
c) The detailed computation using the required formula must be shown as provided above.
d) The NFCC computation must at least be equal to the total ABC of the project.
the PhilGEPS in accordance with section 37.1.4 of the IRR.
vi. Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid (Annex I)
vii.Statement of Completed Single Largest Contract within the [insert relevant period] from the date of submission and receipt of bids equivalent to at least fifty percent (50%) of the ABC (Annex I-A).
viii.Duly signed Net Financial Contracting Capacity Computation (NFCC)* per Annex II, in accordance with ITB Clause 5.5 or a committed Line of Credit equivalent to at least ten percent (10%) of the ABC from a universal or commercial bank
*NFCC = [(Current Assets minus Current Liabilities) (15)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract to be bid.
Notes:
a) The values of the bidder’s current assets and current liabilities shall be based on the
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 53 of 87
data submitted to BIR through its Electronic Filing and Payment System.
b) Value of all outstanding or uncompleted contracts refers those listed in Annex-I.
c)The detailed computation using the required formula must be shown as provided above.
d) The NFCC computation must at least be equal to the total ABC of the project.
CLASS “B” DOCUMENTS (FOR JOINT VENTURE)
i. For Joint Ventures, Bidder to submit either:
1. Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint venture is already in existence, or
2. Copy of Protocol / Undertaking of Agreement to Enter into Joint Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture.
For Joint Venture, the following documents must likewise be submitted by each partner:
CLASS “B” DOCUMENTS (FOR JOINT VENTURE)
i.For Joint Ventures, Bidder to submit either:
1.Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint venture is already in existence, or
2.Copy of Protocol / Undertaking of Agreement to Enter into Joint Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 54 of 87
● PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
For Joint Venture, the following documents must likewise be submitted by each partner:
1. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations or from Department of Trade and Industry (DTI) for sole proprietorship, or from Cooperative Development Authority (CDA) for cooperatives;
2. Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent document for Exclusive Economic Zones or Areas;
In cases of recently expired Mayor’s / Business Permits, said permit shall be submitted together with the official receipt as proof that the bidder has applied for renewal with the period prescribed by the concerned local government units, provided that the renewed permit shall be submitted as a post-qualification requirement;
3. Valid and current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005;
4. Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative form or separate reports):
a. Independent Auditor’s Report;
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 55 of 87
b. Balance Sheet (Statement of Financial Position); and
c. Income Statement (Statement of Comprehensive Income)
Each of the above statements must have stamped “received” by the Bureau of Internal Revenue (BIR) or its duly accredited and authorized institutions.
OR
5. Submission of valid and current PHILGEPS Certificate of Registration and Membership (Platinum Registration) together with Annex A in lieu of the eligibility documents.
Note: Bidder must ensure that all Class “A” Eligibility Documents are valid and current at the time of submission of PHILGEPS Certificate of Registration and Membership (Platinum Registration). In case any of the submitted Eligibility are not valid and current at the time of submission of Platinum Registration, bidders are required to submit the valid and current documents.
● In case the JV Partners opt to submit their Class “A” Documents, the Certificate of PhilGEPS Registration (Platinum Membership) shall remain as post-qualification requirement to be submitted in accordance with Section 34.2 of the 2016 Revised IRR of RA9184. “GPPB Circular 07-2017 dated 31 July 2017”
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 56 of 87
No original provision.
12.1(b)(xi) Other technical documents which will be required for the project
i. The bidder must hold a PCAB License with Category AAA in General Engineering for a minimum of two (2) years on or before the date of the bid opening. For joint venture, at least one of the JV should comply to this requirement.
ii. Written Statement of the contractor signed by their authorized representative that they have at least five (5) years of direct experience on engineering, supply and delivery, installation, testing, and commissioning and experience in operations and maintenance of communications facilities network. iii. Contractor shall submit resume of key personnel to be assigned to the project upon bid opening. These key personnel are the Professional Electronics & Communication Engineer (PECE) with minimum Seven (7) years experience in Communication Facilities, Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel. iv. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer of radio equipment by an Independent Certifying body. v. Written Statement of the equipment manufacturer (IP
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 57 of 87
Microwave Radio) signed by their authorized representative that all features offered and complied to must be available from the time of award. vi. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved.
vii. Written Certification from the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that they are in in good standing and reputation both in the Local and US, European, and ASIAN Market.
All terms, conditions and instructions to bidders specified in the Bidding Documents inconsistent with this Bid Bulletin are hereby superseded and modified accordingly.
Please use the following forms attached in this Supplemental Bid Bulletin: ● Revised Technical Specifications as of 24 September 2019 ● Revised Schedule of Requirements as of 24 September 2019 ● Revised Technical Bid Form as of 24 September 2019 ● Revised Detailed Financial Breakdown as of 24 September 2019
For information and guidance of all concerned.
Issued this 24th day of September 2019.
IVIN RONALD D.M. ALZONA
Chairperson, DICTBAC
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 58 of 87
SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING,
OPERATION AND MAINTENANCE SUPPORT OF IP MICROWAVE RADIO
COMMUNICATION SYSTEM FOR DICT-PAGASA "ALL WEATHER COMMUNICATION
SYSTEM PROGRAM"
[DICTBAC-2019-017]
REVISED SCHEDULE OF REQUIREMENTS AS OF 24 SEPTEMBER 2019
The delivery schedule expressed as weeks/months stipulates hereafter a delivery date which is
the date of delivery to the project site
# DESCRIPTION MILESTONE DURATION
(calendar days) DELIVERABLES
1
Site validation, detailed
design and technical
documents, structural
integrity test, test and
training plans)
NOTE: DICT shall take
charge of Site Acquisition
Conduct of detailed
survey and design
Provision of
technical documents
(including revision)
Within forty-five (45) days
upon receipt of NTP
Within forty-five (45) days
upon completion of detailed
survey
Validation and
Detailed Design,
Documentation
Conducted
Document
submitted/approved
2
Hauling, delivery, supply
and installation of tower
and facilities materials
Acquisition of
permits and
clearances from the
Local Government
Units for the
installation of tower
Within one hundred twenty
(120) days after the
completion of site acquisition,
confirmation of access road's
feasibility by DICT, and
approval of detailed design,
tests, plan, etc.
Tower installation
and facilities
completed;
Test reports and
as-built map
submitted
3
Acquisition of NTC Radio
Station License/
Spectrum User
Frequency permit and
other related
permits/clearance
Submission of plan
Acquisition of permit
Within ninety (90) days upon
receipt of NTP
Within ninety (90) days upon
receipt of NTP
Approved permit plan
NTC permit,
clearance
secured/acquired
4
Hauling, Delivery, Supply,
Installation and
Configuration of IP radio
system, power system,
NMS and other relevant
works
Implementation
activities
Within one hundred fifty (150)
days after the completion of
site acquisition, confirmation
of access road's feasibility by
DICT, and approval of
detailed design drawing, test,
plans, etc. and upon receipt
of Notice to Install/Approval
Sheet of submitted
requirements.
Installed and
Configured System
Test reports and as-
built plan submitted
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 59 of 87
5
Testing, commissioning
and acceptance of the
system and components
Testing, commissioning
and acceptance of the
system and components
Submission and
Approval of Test
plan
Factory Testing and
Acceptance
Submission of
Acceptance
documents / Actual
Work Done
Testing,
commission, and
acceptance
Within forty-five (45) days
after the approval of detailed
design, test, plans, etc.
Within forty-five (45) days
after approval of Factory test
plan
Within seven (7) days prior to
acceptance
Within thirty (30) days upon
completion of all
works/activities
Approved Test Plan
Testing,
commissioning and
Acceptance report
Actual Detailed
Design drawing, As-
Built Plan, BOQ,
Diagrams, maps, etc.
Testing,
Commissioning,
Acceptance
Conducted
6
Comprehensive technical
training services with
certification (thirty (30)
pax - local)
Submission and
Approval of Training
plan
Conduct of Training
Within forty-five (45) cd after
the approval of detailed
design, test, plans, etc.
Within ten (10) calendar days
prior to the date of
acceptance
Approved Training
Plan
Training Conducted
7
Two (2) years Operation
and Maintenance support
(inclusive of two (2)–year
warranty parts & labor,
free of charge)
Two (2) years
contracted
maintenance
support
Will commence after issuance
of the Final Acceptance
Maintenance support
activities conducted,
and required
documents submitted
I hereby commit to comply and deliver all the above requirements in accordance with the above-stated schedule
_________________ ____________________________ ________________
Name of Company Signature over printed name of Date Authorized Representative
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 60 of 87
SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING,
OPERATION AND MAINTENANCE SUPPORT OF IP MICROWAVE RADIO
COMMUNICATION SYSTEM FOR DICT-PAGASA "ALL WEATHER COMMUNICATION
SYSTEM PROGRAM"
[DICTBAC-2019-017]
REVISED TECHNICAL SPECIFICATIONS AS OF 24 SEPTEMBER 2019
Bidders must state here either “Comply” or “Not Comply” against each of the individual parameters of each Specification stating the corresponding performance parameter of the equipment offered. Statements of “Comply” or “Not Comply” must be supported by evidence in a Bidders Bid and cross-referenced to that evidence. Evidence shall be in the form of manufacturer’s un-amended sales literature, unconditional statements of specification and compliance issued by the manufacturer, samples, independent test data etc., as appropriate. A statement that is not supported by evidence or is subsequently found to be contradicted by the evidence presented will render the Bid under evaluation liable for rejection. A statement either in the Bidders statement of compliance or the supporting evidence that is found to be false either during Bid evaluation, post-qualification or the execution of the Contract may be regarded as fraudulent and render the Bidder or supplier liable for prosecution subject to the provisions of ITB Clause 3.1.(a)(ii) and/or GCC Clause 2.1(a)(ii).
ITEM MINIMUM SPECIFICATIONS STATEMENT
OF COMPLIANCE
1 IP MICROWAVE RADIO SYSTEM
1.1. Link Requirements and Equipment Characteristics
1.1.1. IP Microwave radio should either be Outdoor/Split system, must adopt modular design, the service boards can be plugged/ unplugged.
In case of a Split System, 1.1.1.1. IDU shall support cascading; 1.1.1.2. IDU must have an attached cooling system. 1.1.1.3. The distance between IDU and ODU can support at least 100 meters 1.1.1.4. Control unit is required to be configurable to 1+1 Hot standby.
1.1.2. Capacity: The desired microwave IP radio should have a guaranteed link capacity of at least 200Mbps (Full Duplex) upgradeable to 2Gbps. The vendor shall propose any suitable configurations to meet the desired requirements by the DICT, all subject to review and approval of DICT.
1.1.3. Availability: with at least 99.99% performance
1.1.4. Reliability Methods: ITU-R P.530-7/8 with Fade Margin of at least 35dB (minimum).
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 61 of 87
1.1.5. Modulation: The equipment shall support modulation schemes with full range of hitless and errorless Adaptive Coding Modulation (ACM). ATPC and ACM can work together at same time, increasing TX power of ATPC function should be made prior to dropping modulation mode of ACM. When the modulation is adjusted to lower level modulation scheme, the max TX power of the radio should be adjusted to the corresponding level in real time. ● Shall support the following modulation schemes without any
hardware change or additional boards: QPSK, 16QAM, 32QAM, 64QAM, 128QAM, 256QAM, 512QAM, 1024QAM up to 4096QAM whichever is applicable per site.
1.1.6. Frequency: The equipment shall support all licensed bands L6 to 42 GHz. ODU that is tunable to the whole frequency (sub-band free). Vendors shall state what kind of free tunable ODU can be provided.
1.1.7. Channel Spacing: Shall support between 7 to 112 MHz
1.1.8. Polarization Technology: Shall support CCDP and XPIC
1.1.9. Transmit Power: Vendors shall state Transmit Power of all kinds of ODUs in different frequency and modulation in reference to the equipment configuration per site.
1.1.10. Receive Signal Threshold Sensitivity: The radio equipment must have signal sensitivity of BER 10-6 of -60dBm or better.
1.1.11. The vendor shall propose Layer 3 routing function and multiplexing, and shall support L3VPN, L2VPN, Native IP and MPLS.
1.1.12. The proposed equipment shall support OSPF, BGP route protocol.
1.1.13. The proposed equipment shall have built-in MADM and ETH switching platform to cross-connect service among different directions.
1.1.14. The proposed equipment shall support layer 2 and layer 3 frame header compression functions.
1.1.15. The proposed equipment shall support local configuration via CLI or Web GUI for network management.
1.1.16. User Interface. The proposed equipment shall support the following: ● FE electrical interface: 10/100 BASE-T [RJ-45] ● GE optical interface: 1000 BASE-X [SFP], LX (1310 nm), SX (850 nm)
& 1550 nm ● GE electrical interface. 10/100/1000 BASE-T [RJ-45)
1.1.17. Ethernet feature. The proposed equipment shall support, but not limited to, the following services and standards:
● 10/100/1000 base - T/X (IEEE 802.3) ● Ethernet VLANs (IEEE 802.3ac) ● Virtual LAN (IEEE 802.1Q) ● Class of Service (IEEE 802.1q/p) ● Provider Bridges (QinQ-IEEE 802.1ad) ● Link Aggregation Group (LAG)
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 62 of 87
● Ethernet Ring Protection (G.8032v2) ● Ethernet OAM (IEEE 802.3ah, IEEE 802.1ag, ITU-T Y.1731)
1.1.18. The proposed equipment shall be based on the IEEE 802.1p/802.1Q/802.1ad standard.
1.1.19. Load balance should be possible based on flow classification parameters.
1.1.20. Priority Management, the scheduling scheme should support SP, WRR, DWRR, WFQ, SP+WRR, SP+DWRR, SP+WFQ. Winning bidder should at least comply to four (4) QOS functions.
1.1.21. Congestion Management shall support Tail drop, RED (Random Early Detection) and WRED (Weighted Random Early Detection)
1.1.22. The proposed equipment shall support port blocking and mirroring ● Port blocking feature is possible to prevent forwarding of frames from
a given ingress port to one or more egress ports. With port blocking, flows of leaves can be isolated to each other in a tree topology.
● Supports port-based mirror function: the messages from input, output or both directions of observed interface are copied intact to the observing interface. This is to be used for testing and maintenance of the traffic without traffic interruption.
1.1.23. The proposed equipment shall support bandwidth notification based on ITU Standard. 1.1.24. All features offered and complied to must be available from the time of award.
1.2. Test Plan. Network Performance Tests compliant to RFC 2544 or Y.1564 standards.
1.3. Synchronization
1.3.1 The system shall manage Synchronous Ethernet (according to ITU-UG.8261, 8262, 8264) on both FE and GE interfaces.
1.3.2. The system shall support IEEE 1588V2 Synchronization
1.4. Security. The proposed equipment should support SSL/SSH/SNMPV3 to guarantee the security of management.
1.5. MTBF. ODU/IDU MTBF - MTBF both for ODU/IDU shall be minimum of 100,000 hours.
1.6. Scalability. The equipment shall support multi-nodal ODUs on one IDU with minimum of 4 ODUs up to 12 ODUs or above without cascade and shall support 1+0, 2+0, 1+1 HSB/SD/FD, XPIC Configuration
1.7. Supervisory Performance Monitoring. The offered equipment shall be fully managed remotely, allowing downloading of system configuration, equipment software or system operation firmware changes. In addition, the offered equipment shall also be able to collect performance monitoring data on each Ethernet port of the equipment, means, on all Ethernet ports (external) used for traffic
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 63 of 87
collection as well on all internal ports (i.e. from Ethernet switch towards radio controller).
2 Antenna
1.8.1. The antenna should be a dual polarized-high performance with radome. Vendor shall provide single and dual polarized antennas covering 6 to 42GHz frequency. The antenna system should withstand a wind loading of at least 300kph. Must be adaptable to the NTC allowed frequencies to be used.
1.8.2. Environmental requirements of units: Minimum for Indoor:
1.8.2.1. Ambient temperature range: Long
term: 0°C - 55°C 1.8.2.2. Relative humidity: 5% - 95%
Minimum for Outdoor:
1.8.2.3. Ambient temperature range: 0°C -
55°C 1.8.2.4. Relative humidity: 5% - 100% 1.8.2.5. Dustproof and waterproof and must be IP66 Compliant
1.8.3. The proposed equipment shall comply with the following standards:
1.8.3.1. EMC: EN 301 489-4, EN 301 489-1, FCC 47 CFR, part 15, class B
1.8.3.2. Safety: EN 60950, IEC 60950-1, UL 60950-1, CSA-C22.2 No. 60950-1, EN 60950-22, UL 60950-22, CSA, C22.2.60950-22
1.8.3.3. Ingress Protection: IEC 60529 IP66 1.8.3.4. Storage: ETSI EN 300 019-1-1 Class 1.2 1.8.3.5. Transportation: ETSI EN 300 019-1-2 Class 2.3
Vendor may propose any other standards, other than mentioned above, subject to the review and approval of DICT.
1.9. Link Calculation Bidder shall provide software-based path profile and link budget calculation, preferably PL4 or PL5 software. User’s training must be included to ensure proper cascading of information and operation.
1.10. Interoperability
1.10.1. The preferred equipment should be managed with the unified NMS with optical transmission equipment.
1.10.2. The preferred equipment should support open and standard interfaces like SNMP for easy integration.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 64 of 87
1.10.3. Provide integrated monitoring system through internet for power system status (Generator Set, battery, etc.)
1.11. Scalability. The proposed equipment shall support twelve (12) Radio Directions or above without cascade, and shall support 1+0, 2+0, 1+1 HSB/SD/FC, XPIC Configuration.
1.12. Certifications
1.12.1. The offered equipment shall comply with the Chartered Engineer (CE) Certificate.
1.12.2. The bidder shall provide Electromagnetic Compatibility (EMC) Test Report, Safety Test Report and Environment report.
1.13. Frequency Considerations
The existing frequencies in the Technical Details will be considered in the upgrade but changes will be done depending on the actual survey and conduct of Radio Frequency Investigation (RFI).
1.14 Other System Components
1.14.1. CCTV requirements 1.14.1.1. 4 channel Network NVR 1.14.1.2. Color outdoor IP camera (360 degrees) with PTZ
function and night vision 1.14.5.3. 1TB surveillance storage 1.14.5.4. Provision of required cabling
1.14.2. Environmental, Power and Mechanical 1.14.2.1. Environmental requirements of indoor unit: Vendor may propose suitable working temperature depending on the location.
Subject to approval of DICT. 1.14.2.2. Environmental requirements of outdoor unit: Vendor
may propose suitable working temperature depending on the location.
Subject to approval of DICT. Must be dustproof and waterproof. 1.14.2.3. Bidder shall propose suitable electrical power supply,
Battery System, housing cabinets and Rectifier system including
installation materials, mounting brackets, racks with uninterruptible power
supply (UPS) to sustain at least 1.5kVA for fifteen (15) minutes, and
accessories for their proposed equipment. Subject to approval of DICT.
1.14.3. Bidder shall ensure that all electrical power systems can be monitored remotely through the Network Management System (NMS).
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 65 of 87
ANTENNA TOWERS
Towers to be assembled and installed shall be Guyed Tower/ 3-legged/ Monopole Self-Supporting Tower or 4-legged self-supporting tower (as
applicable, depending on the design)
1.1. Design Criteria and Specification
1.1.1. Structural design is based on the minimum design criteria and should be administered/approved by a competent Structural Engineer. The design of members and connections shall be consistent with intended behavior of structure system. In addition, monopole self-supporting tower will be utilized as necessary.
1.1.2. Standards and References 1.1.2.1. National Structural Code of the
Philippines 2015 (NSCP 2015) 1.1.2.2. American Institute of Steel
Construction latest edition (AISC) 1.1.2.3. American Society of Testing and
Materials latest edition (ASTM) 1.1.2.4. American Concrete Institute (ACI318-
11M) 1.1.2.5. American Society of Civil Engineer
(ASCE) 1.1.2.6. American Welding Society latest
edition (AWS) 1.1.2.7. British, European and International
Standards (BS EN ISO)
1.2. Materials Specification
1.2.1 The materials and installation requirement shall conform to the specification of standard and reference.
1.2.2. Concrete shall have a minimum compressive strength of not less than 35mpa at 28 days. All grout shall be non-ferrous and non-shrink with a minimum comprehensive strength of 35mpa at 28 days. Concrete cover shall have a minimum thickness of 50mm.
1.2.3. Reinforcing steel bars shall have a minimum yielding strength of 415mpa.
1.2.4. Connection of all bolts shall be pre-tensioned high strength and meet the minimum requirements of ASTM A325 or A490.
1.2.5. Welding shall meet the minimum requirement of AWS.
1.2.6. Structural materials steel shall meet the minimum requirement of ASTM and AISC.
1.2.7. Hot dip galvanized coating on fabricated iron and steel materials, with a minimum thickness 86 microns for all members shall be in accordance of BS EN ISO 1461.
1.3. Materials Quality Control
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 66 of 87
1.3.1. The following documents shall be available for review by the engineer-of-record prior to fabrication or installation, as applicable.
1.3.1.1 Materials test reports for structural steel, bolts, shear, connectors and welding materials.
1.3.1.2 Inspection procedure 1.3.1.3 Installation procedure 1.3.1.4 Nonconformance procedure 1.3.1.5 Material control procedure 1.3.1.6 Bolt installation procedure 1.3.1.7 Welder performance qualification record (WPQR),
including any supplemental testing requirements
1.4. EARTH WORKS
This includes the excavation of the design grade line, width, length and depth for the solid concrete foundation of tower in reinforcing bars as per approved plan and specification.
1.5. CONCRETE WORKS
This include the installation of reinforced concrete solid foundation, with a minimum mix of 1:2:3 mixing of concrete as per approved plan and specification.
1.6. RSB WORKS
This includes the required setting/installation of standard reinforcing steel bar for solid concrete foundation of the tower as per approved plan and specification.
1.7. FORM WORKS.
This involves the setting/formation of good quality of form for the required concrete foundation design and as per approved plan and specification.
1.8. FABRICATION/ METAL WORKS.
This involves the fabrication part of design steel tower, column, flat form, ladder and other accessories, pre-assemble/erection/installation of the structure; should be done by the supplier in the fabrication yard/site, before hauling at the actual site for final erection as per approved plan and specification. Fabrication and up to proper erection is subject for inspection and monitoring.
1.8.1. Pre-arrange schedule inspection to the winning bidder is required during fabrication and pre-installation/ assemble and other activity, as painting and galvanization process of application, for checking and monitoring purposes.
1.8.2. Pre-installation and its needed inspection is required prior to the delivery transport of materials to the site, at the contractor fabrication yard.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 67 of 87
1.8.3. Affected structure, plants, crops, trees during tower installation, if any, shall be borne by the contractor.
1.9. GALVANIZATION/ PAINTING WORKS
This involves the application of primer paint, paint and adequate micron of hot dip coated of galvanize at tower part, such as for steel column, tower base, platform, vertical, horizontal and diagonal member and ladder/cage including nuts and bolts or the whole part of the tower at the fabrication yard of the contractor/ supplier, as per approved plan and specification. After fabrication of part, application of adequate micron of hot dip galvanize, a metal primer paint should be applied prior for delivery at the site and the final erection and final coating of paint should be applied and completed.
1.10. SECURITY FENCING WORKS
This involves the installation of perimeter fence along the property line of both existing and new repeaters, with 2x2 cyclone wire and 2-inch diameter pipe mounted on CHB wall (refer to approved plan and specification).
1.11. SHELTER WORKS
OEM approved shelter, bidder to submit that proposed shelter is certified by the OEM. Shelter shall be made of pre-fabricated
polyurethane insulated parts with aluminum frame construction
and design for marine environment are able to withstand Philippine Wind & Seismic Zone Structural requirements.
Protected against insect, radio frequency interference (RFI), insensitive to salt water fungus and termites. This involves the
installation of telecommunications equipment facilities with dimension of 4x4x3 (LxWxH) in meters, or continuous footing for
CHB wall 6” thick, concrete slab roof with sloping grade provided
with a concrete column as support. 1m wide and 2.7m height of steel door as entry to facility as per approved plan and
specification
1.12. BACKFILLING AND COMPACTION WORKS
Backfill shall be placed in thin lifts (maximum 200mm) and compacted to a minimum 95% of standard proctor maximum dry density. In the event that excavated materials are not suitable for backfill, it shall be responsibility of the contractor to supply and compact suitable clean materials to meet that requirement. Any organic or deleterious material shall be removed and will not be permitted in fills. Except as permitted by the geotechnical engineer, no rock or similar irreducible material with a maximum dimension greater than 200 mm shall be buried or placed in fills. Gravel bedding shall have a minimum thickness of 200mm and ¾’’ coarse aggregates shall be use.
1.13. EARTHING SYSTEM WORKS
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 68 of 87
This involves underground wire installation, providing a protective conductor for fault current to flow to earth.
1.14. ACCESS ROAD
This involves installation of route between main road to site location. The access road shall accommodate vehicles that deliver materials to site area. The road surface and base course is made of compacted aggregates. The total width of the road is 3.2m with sloping grade of 2-3% at each end. The canal has an incline slope of 5%. If not feasible the winning bidder can suggest other alternatives with coordination and approval of DICT.
1.15. LIGHTING WORKS
This involves installation of obstruction light on top of the tower. Specification of Aviation Obstruction light is flashing signal Light, as per approved specification.
1.16. LOADINGS
1.16.1. Dead load – consist of self-weight of tower structure including ladder and appurtenances.
1.16.2. Live load – Antenna and antenna accessories
1.16.3. Wind Load – varies on location of towers and calculated accordance to NSCP 2015; all towers shall have design wind velocity of 300kph.
1.17. FOUNDATION
Assumption of 100kpa for allowable soil bearing capacity, capacity may change depending on environment and soil classification of different site locations.
1.18. QUALITY CONTROL WORK
This includes testing of materials and factory testing to control the quality of materials and workmanship used in the structures. Quality Assurance officers shall be provided to verify, audit and evaluate quality of work.
1.18.1. The winning bidder shall undertake hauling activities of tower parts, in any manner as deemed appropriate, to the location of repeater sites. It shall be responsible in securing access to the repeater sites and provision of temporary facilities of its materials and equipment for tower installation.
1.18.2. The winning bidder shall supply all needed labor, materials, equipment, tools and tower parts and accessories including materials tests in accordance with the specified technical requirements and standards.
1.18.3. The winning bidder shall be responsible for the restoration of the site after the installation of tower. It shall be answerable to any and all expenses, damages and liabilities that shall incur during hauling activities, foundation works and tower installation.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 69 of 87
BIDDERS QUALIFICATION
The bidder must be ISO 9001: 2015 certified (Quality Management System), for joint venture agreement, at least one of the JV should be ISO 9001: 2015 certified.
PAYMENT TERMS
Payment Milestones Progress
Advance Payment subject to submission of an irrevocable letter of credit or bank guarantee issued by a universal or commercial bank pursuant to Section 4.5 of Annex D of the Revised IRR of RA 9184
15%
Upon delivery of IP Microwave Radio/Antenna System Hardware to suppliers centralized warehouse
40%
Upon delivery, hauling, installation of towers and accessories and completion of Agreed Testing Per
Link, and upon installation of IP Radio, Antenna, power system, NMS and its accessories
Payment is per completed site/link: *number of links pro rated at 30% for this milestone
30%
After completion of Training 5%
Upon Project Acceptance 10%
OTHER TECHNICAL DOCUMENTS
Other technical documents which will be required for the project
i. The bidder must hold a PCAB License with Category AAA in General Engineering for a minimum of two (2) years on or before the date of
the bid opening. For joint venture, at least one of the JV should
comply to this requirement.
ii. Written Statement of the contractor signed by their authorized representative that they have at least five (5) years of direct experience
on engineering, supply and delivery, installation, testing, and
commissioning and experience in operations and maintenance of communications facilities network.
iii. Contractor shall submit resume of key personnel to be assigned to
the project upon bid opening. These key personnel are the Professional Electronics & Communication Engineer (PECE) with minimum Seven (7)
years experience in Communication Facilities, Project Manager, Project
Engineer and Outside Plant Supervisor and six (6) support personnel.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 70 of 87
iv. Valid and current ISO 9001 Quality Management System Certificate
issued to the manufacturer of radio equipment by an Independent Certifying body.
v. Written Statement of the equipment manufacturer (IP Microwave
Radio) signed by their authorized representative that all features offered
and complied to must be available from the time of award.
vi. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved.
vii. Written Certification from the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that they
are in good standing and reputation both in the Local and US, European, and ASIAN Market.
_______________________ ___________________________ __________
Name of Company Signature over printed name of Date Authorized Representative
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 71 of 87
Annex VIII (page 1 of 3)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
DEPARTMENT OF INFORMATION AND COMMUNICATIONS TECHNOLOGY SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING, OPERATION AND
MAINTENANCE SUPPORT OF IP MICROWAVE RADIO COMMUNICATION SYSTEM FOR DICT-PAGASA
"ALL WEATHER COMMUNICATION SYSTEM PROGRAM"
[DICTBAC-2019-017]
REVISED TECHNICAL BID FORM AS OF 24 SEPTEMBER 2019
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”.
Line No.:
Project Requirements Bidder’s Statement of
Compliance
1 DICT’s Section VII Technical Specifications For the SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING
AND COMMISSIONING, OPERATION AND MAINTENANCE
SUPPORT OF IP MICROWAVE RADIO COMMUNICATION SYSTEM
FOR DICT-PAGASA "ALL WEATHER COMMUNICATION SYSTEM
PROGRAM" (1LOT)
2
ITEM BRAND MODEL
a. IP Microwave Radio
b. UPS/Battery
c. Rectifier
d. Generator Set
e. Antenna
f. CCTV Camera
g. Antenna Tower
BIDDER’S UNDERTAKING I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable
hereby OFFER to (supply/deliver/perform) the above described items. I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions contained
in the bid documents, including the posting of the required performance security within ten (10) calendar days from
receipt of the Notice of Award. Until a formal contract/order confirmation is prepared and signed, this Bid is binding on us.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 72 of 87
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 73 of 87
Annex VIII (page 2 of 3)
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
DEPARTMENT OF INFORMATION AND COMMUNICATIONS TECHNOLOGY SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING, OPERATION AND
MAINTENANCE SUPPORT OF IP MICROWAVE RADIO COMMUNICATION SYSTEM FOR DICT-PAGASA "ALL WEATHER COMMUNICATION SYSTEM PROGRAM"
[DICTBAC-2019-017] REVISED TECHNICAL BID FORM AS OF 24 SEPTEMBER 2019
INSTRUCTION TO THE SUPPLIER: Indicate “COMPLY” (per line number) under Bidder’s Statement of Compliance
if Bidder can meet the technical specifications and project requirements. DO NOT LEAVE ANY BLANK. A “YES” or “NO” ENTRY WILL NOT BE ACCEPTED. FAILURE TO CONFORM WILL RESULT IN A RATING OF “FAILED”.
Line No.:
Other Requirements Bidder’s Statement of
Compliance
3 Bidder did not participate as consultant in the preparation of the design or technical specifications of the GOODS as subject of the bid
4
Delivery Place and Distribution 1. Tagum-Libuganon River Basin (NGCP Maco) 2. Virac PAGASA Complex (Legaspi GovNetPoP) 3. Abra River Basin (NGCP Bantay) 4. Aparri PAGASA Radar (NGCP Tuguegarao) 5. Baler PAGASA Station (Baler CLS) 6. Guiuan Radar Station (Tacloban GovNet POP) 7. Subic Radar Station (NGCP Subic) 8. Tagaytay PAGASA Station (NGCP Dasmarinas) 9. Virac Radar Station (Legaspi GovNet POP) 10. Tampakan PAGASA Station (NGCP Tacurong) 11. Hinatuan PAGASA Station (NGCP Bislig) 12. Quezon, Palawan (Puerto Princesa Wi-Fi POP) 13. Agusan River Basin (NGCP San Francisco) 14. Tagum USEP (NGCP Maco) 15. General Santos Synoptic Station (NGCP General
Santos) 16. Tanay Radar and Synoptic Station (NGCP Lumban) 17. Dagupan Weather Complex Station (Dagupan
GovNetPoP) 18. Tacloban Airport Synoptic Station (Tacloban
GovNetPoP) 19. Daet Station (P. Daet RS) 20. Agno River Basin
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 74 of 87
Annex VIII
(page 3 of 3)
5 Delivery Period Two hundred Seventy (270) calendar days from receipt of Notice to Proceed
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the Bidding Documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and conditions
contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract/order confirmation is prepared and signed, this Bid is binding on us.
Name of Company (in print)
Signature of Company Authorized Representative
Name and Designation (in print)
Date
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 75 of 87
Annex X
PLEASE USE THIS BID FORM. DO NOT RETYPE OR ALTER.
DEPARTMENT OF INFORMATION AND COMMUNICATIONS TECHNOLOGY
REVISED DETAILED FINANCIAL BREAKDOWN AS OF 24 SEPTEMBER 2019 (QUOTED PRICE MUST BE INCLUSIVE OF VAT AND DELIVERED DUTIES PAID)
SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING, OPERATION
AND MAINTENANCE SUPPORT OF IP MICROWAVE RADIO COMMUNICATION SYSTEM FOR
DICT-PAGASA "ALL WEATHER COMMUNICATION SYSTEM PROGRAM" [DICTBAC-2019-017]
INSTRUCTION: -The Sum of the Detailed Financial Breakdown must be equal to the Financial Bid per Annex IX. -Do not leave any blanks. Indicate “0” if the item is being offered for free.
ITEM Qty Unit Cost Total Cost per Item
Engineering services (site survey, design and technical documents, Radio license permit and structural integrity test)
33 links
Supply and deliver of IP Microwave radio including spares and antenna system, Power system (Rectifier, UPS/Battery and Genset)
33 links
Tower Foundations and Development Works (Materials Cost for structural foundation/ tower installation)
1 lot
Tower Foundation and Development Works (Labor Cost/Miscellaneous for tower installation)
1 lot
Installation, testing, commissioning and acceptance of the systems
33 links
Network management system
1 lot
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 76 of 87
Comprehensive technical training services with certification (20 pax - local)
1 lot
Two (2) yrs Operations and Maintenance, Support, and two (2) years Warranty
1 lot
Contingencies (5%) 1 lot
TOTAL
TOTAL BID PRICE FIVE HUNDRED FORTY-ONE MILLION NINE HUNDRED NINETY NINE THOUSAND NINE HUNDRED NINE PESOS AND EIGHTY TWO CENTAVOS. (PHP 541,990,909.82)
BIDDER’S UNDERTAKING
I/We, the undersigned bidder, having examined the bidding documents including Bid Bulletins, as applicable hereby OFFER to (supply/deliver/perform) the above described items.
I/We undertake, if our bid is accepted, to deliver the items in accordance with the terms and
conditions contained in the bid documents, including the posting of the required performance security within ten (10) calendar days from receipt of the Notice of Award.
Until a formal contract/order confirmation is prepared and signed, this Bid is binding on us.
___________________________________ Name of Company (in print)
___________________________________ Signature of Company Authorized Representative
___________________________________ Name and Designation (in print)
___________________________________ Date
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 77 of 87
SITE COORDINATES
Radar Station (FROM) DICT POP/NGCP Station (TO) ADDITIO
NAL
INFO OF
END
POINT
SITE
(NGCP,
GOVNET,
WIFIPOP)
Available and Proposed Relay Station
STATION NAME
LATITUDE
LONGITUDE
Power Remarks
Exis
t
i
n
g
Tow
e
r
H
e
i
g
h
t
Propo
s
e
d
Towe
r
H
e
i
g
h
t
SITE NAME
LATITUDE
LONGITUDE
Power Remarks
Exis
t
i
n
g
Tow
e
r
H
e
i
g
h
t
Propo
s
e
d
Tower
H
e
i
g
h
t
REPEAT
ER
STATION
LATITUDE
LONGITUDE
POWE
R
REQUI
REME
NT
RS TYPE
LAN
D
PRO
PER
TY
LAND ACQUISITION
Exit
ing
To
wer
Hei
ght
P
r
o
p
o
s
e
d
T
o
w
e
r
H
e
i
g
h
t
1 Tagum-
Libuga
non
River
Basin
7.45214
125.7796 (1)
Commercial
Electri
city (2)
Gener
ator
For improvement
15m
NGCP Maco
7.403331
125.853056
(1)
Commerci
al
Elect
ricity
(2)
Gene
rator
For Improvem
ent
40m
USE
P
Tagu
m
Agro
met
7.446217
125.806389
(1
)
C
o
m
m
er
ci
al
El
e
ct
ri
cit
y
(2)
Generator
Existing
PAGASA
owned Government-owned
10m
2 US
EP
Ta
gu
m
Ag
ro
m
et
7.4462
17 125.806389 (1) Commercial
Electri
city (2)
Gener
ator
For
improvement
1
0m
3
Virac
PAGA
SA
Synop
tic
Statio
n
13.576
389 124.2094 (1)
Commercial
Electri
city (2)
Gener
ator
For
improvement
1
2m
DICT
Legasp
i
GovNet
PoP
13.146309
123.753119
(1) Commercial
Elect
ricity
(2)
Gene
rator
Wit
h
exis
ting
mon
opol
e at
the
roof
top
of
the
buil
ding
.
20m
Improveme
nt for
existing or
can use
compound
for new
tower
Bariw RS
13.11603
123.7268
(1) Sol
ar Power
(2) Gen
erator
N
ew
LGU
Lease/Rent 5
0m
Sto. Nino RS
13.607
124.2307
(1) Sol
ar Power
(2) Generator
New
Private
Lease/Rent 30m
4
Virac
PAGASA
Radar
Station
13.629061
124.333951
(1)
Commercial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
45m
Igang RS
13.
529752
124.
208315
(1) Sol
ar Power
(2) Gen
erat
or
New
Private
Lease/Rent 30m
5 Abra River
Basin. 17.563
811 120.371611 (1) Commercial
Electri
city (2)
Gener
ator
For
Improve
ment 2
5m
NGCP
Bantay 17.
594634
120.
391684
(1) Commerci
al
Elect
ricity
(2)
Gene
rator
For
Improvem
ent 4
0m
6 Aparri
PAGASA
Radar
18.359
722 121.630139 (1)
Commercial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
3
0m DICT
Tugueg
arao
GovNet
PoP
17.
62163
121.
7219 (1) Commerci
al
Elect
ricity
(2)
Gene
rator
For
Improvem
ent
4
0m DICT
Nassiping RS
17.
98158
121.
6433 (1) Sol
ar Po
wer (2) Generator
E
xi
sting
DICT Government
-owned 4
5m
DICT Allacapan
RS 18.265
61 121.529
(1) Commercial
(2) Generator
Ex
is
tin
g
DICT Government-owned 4
5
m
7
Baler
PAGASA Radar
15.748
972 121.632117 (1)
Commercial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
1
5m Baler
CLS 15.
75723
121.
5378 (1) Commerci
al
Elect
ricity
(2)
Gene
rator
New
Tower
2
5m
New
tower
and
equipme
nt room
Baler
CLS
Baler RS.
15.
756503
121.
604167
(1) Solar Power
(2) Gen
erator
New
Private
Lease/Rent
25m
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 78 of 87
buil
ding
8
Guiuan
Radar Station.
11.045
58 125.755495 (1)
Commer
cial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
1
5m
Tacloba
n
GovNet
PoP
11.24506
125.004744
(1)
Commercial
Elect
ricity
(2)
Gene
rator
New Tower
30m
Improvement of facilities
DICT
Naparan 11.
158445
125.
633521
(1) C
o
m
m
er
cia
l
El
ec
tri
cit
y (2) Gen
erator
Exi
sti
ng
DICT
Government-owned
45m
9 Tacloban
Synoptic
Station. 11.229783 125.025311 (1)
Commer
cial
Electri
city (2)
Gener
ator
N
e
w
T
o
w
er
a
n
d
fa
cil
iti
e
s
15
m DICT
San
Roque
RS 11.000
456 125.0337
64 (1) C
o
m
m
er
cia
l
El
ec
tri
cit
y (2) Generator
E
xisti
ng
DICT Government
-owned 4
5m
1
0 Subic Radar
Station 14.822
067 120.3638 (1)
Commercial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
3
0m NGCP
Hermosa
14.
817611
120.
300906
(1) Commercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
4
0m
11
Taga
ytay
Rada
r
Stati
on
14.142139 121.022278 (1)
Commer
cial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
30m
NGCP
Dasmarinas
14.312329
120.949691
(1) Com
mercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
30m
12
Tamp
akan
Radar
Statio
n.
6.417578 125.03
0841 (1) Commer
cial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
12
m NGCP
Tacurong
6.6692
22 124.6864
73 (1) Com
mercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
35
m
13
Hina
tuan
Rad
ar
Stati
on
8.367325 126.338536 (1)
Commer
cial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
25
m NGCP
Bislig 8.1469
42 126.3594
08 (1) Com
mercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
35
m Bislig RS 8.2
970
2 126.3238
2 (1) C
o
m
m
er
cia
l
El
ec
tri
cit
y (2) Generator
New
LGU Government-owned 3
0m
1
4
Quezo
n,
Palaw
an
Radar
station
9.2305
83
118.005806
(1) Commer
cial
Electri
city (2)
Gener
ator
Inst
allat
ion
of
ant
enn
a
on
exis
ting
buil
ding
2
5m
Puerto
Princes
a WiFi
PoP
9.7
39736
118.
735146
(1) Com
mercial
Elect
ricity
(2)
Gene
rator
D
I
C
T
t
o
w
e
r
e
n
c
r
o
a
c
h
e
d
.
N
e
g
o
ti
a
ti
o
n
t
1
2m
Option
to
erect
new
tower
Mt. Hilipad RS
9.632576
118.3533
(1) Sol
ar Power
(2) Generator
Ne
w Private
Lease/Rent
35
m
WesCom RS
9.7155
09 118.5400
41
(1) Sol
ar
Power
(2) Generat
or
New
AFP
Government-owned
25m
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 79 of 87
o
a
ll
o
w
u
s
t
o
r
e
h
a
b
il
it
a
t
e
t
h
e
t
o
w
e
r
i
s
i
n
p
r
o
g
r
e
s
s
.
15
Agusan River Basin
8.545069
125.942558 (1)
Commercial
Electri
city (2)
Gener
ator
Faci
lities
und
er
con
stru
ctio
n.
New
Tow
er
Nee
ded
15m
NGCP San
Francisco
8.501142
125.9933
(1)
Commercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
35m
16
Gen. Santos Synoptic
6.057439
125.103015 (1)
Commercial
Electri
city (2)
Gener
ator
For Improvement
12m NGCP
Gen.
Santos 6.2029
81 125.1480
56 (1) Commercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
35
m
17 Tan
ay
Syn
optic
Stati
on
14.581711
121.369444 (1)
Commercial
Electri
city (2)
Gener
ator
For Improvement
12
m NGCP
Lumban 14.307861
121.485556
(1)
Commerci
al
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
40m
1
8 Agno River
Basin 15.888
33 120.6089 (1)
Commercial
Electri
city (2)
Gener
ator
For Improvement
25m
DICT
Pacd
al
Bagui
o
16.
41735
120.
6136
(1) Commercial
Elect
ricity
(2)
Gene
rator
New Tower
15m
Tower or
monopole
can be
placed on
DICT
compound
at the back
of Govnet
Equipment
Room
Sto. Tomas
RS 16.
33627
120.
5601
(1) C
o
m
m
er
cia
l
El
ec
tri
cit
y (2) Gen
erat
or
F
o
r
I
m
p
r
o
v
e
m
e
n
t
DICT
Government
-owned 1
0m
19
Dagup
an
Weath
er
Compl
ex
16.08688 120.3522 (1)
Commercial
Electri
city (2)
Gener
ator
For Improvement
12m
20 Daet
Synoptic
Station 14.128694 122.982972 (1)
Commer
cial
Electri
city (2)
Gener
ator
For Improvement
1
2m NGCP
Labo 14.191
636 122.7843
91 (1) Com
mercial
Elect
ricity
(2)
Gene
rator
Tow
er
impr
ove
men
t
25
m Tower
improvemen
t Masalong RS 14.
172
557 122.8091
54 (1) Comm
ercial
Ele
ctri
city
(2)
Ge
ner
ator
N
ew
LGU Government
-owned 3
0m
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 80 of 87
DICT BIDS AND AWARDS COMMITTEE
REVISED CHECKLIST OF REQUIREMENTS FOR BIDDERS AS OF 24 SEPTEMBER 2019
Name of Company : _______________________________
SUPPLY, INSTALLATION, DETAILED DESIGN, TESTING AND COMMISSIONING, OPERATION AND MAINTENANCE SUPPORT OF IP MICROWAVE RADIO
COMMUNICATION SYSTEM FOR DICT-PAGASA "ALL WEATHER
COMMUNICATION SYSTEM PROGRAM"
[DICTBAC-2019-017] PhP541,999,909.82
Ref. No.
Particulars
ENVELOPE 1: ELIGIBILITY AND TECHNICAL DOCUMENTS
ELIGIBILITY DOCUMENTS
CLASS “A” DOCUMENTS
12.1 (a.1.) ELIGIBILITY DOCUMENTS
i. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations, Department of Trade and Industry (DTI) for sole proprietorship, or from Cooperative Development Authority CDA) for cooperatives.
ii.Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent document for Exclusive Economic Zones or Areas.
iii.Valid and Current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005.
iv. Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative format or separate reports):
a. Independent Auditor’s Report; b. Balance Sheet (Statement of Financial Position); and c. Income Statement (Statement of Comprehensive Income)
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 81 of 87
v. PhilGEPS Certificate of Registration and Membership in accordance with Section 8.5.2 of the IRR, except for foreign bidders participating in the procurement by a Philippine Foreign Service Office or Post, which shall submit their eligibility documents under Section 23.1 of the IRR, provided, that the winning bidder shall register with the PhilGEPS in accordance with section 37.1.4 of the IRR.
vi. Statement of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid (Annex I)
vii. Statement of Completed Single Largest Contract within the 5 years from the date of submission and receipt of bids equivalent to at least fifty percent (50%)
viii. Duly signed Net Financial Contracting Capacity Computation (NFCC)* per Annex II, in accordance with ITB Clause 5.5 or a committed Line of Credit equivalent to at least ten percent (10%) of the ABC from a universal or commercial bank
*NFCC = [(Current Assets minus Current Liabilities) (15)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract to be bid.
Notes: a) The values of the bidder’s current assets and current liabilities
shall be based on the data submitted to BIR through its Electronic Filing and Payment System.
b) Value of all outstanding or uncompleted contracts refers those listed in Annex-I.
c) The detailed computation using the required formula must be shown as provided above.
The NFCC computation must at least be equal to the total ABC of the project.
CLASS “B” DOCUMENTS (FOR JOINT VENTURE)
i.For Joint Ventures, Bidder to submit either: 1. Copy of the JOINT VENTURE AGREEMENT (JVA) in case the joint venture is already in existence, or 2. Copy of Protocol / Undertaking of Agreement to Enter into Joint Venture signed by all the potential join venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful. (Annex III)
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 82 of 87
The JVA or the Protocol/Undertaking of Agreement to Enter into Joint Venture (Annex III) must include/specify the company/partner and the name of the office designated as authorized representative of the Joint Venture. For Joint Venture, the following documents must likewise be submitted by each partner: 1. Registration Certificate from the Securities and Exchange Commission (SEC) for corporations or from Department of Trade and Industry (DTI) for sole proprietorship, or from Cooperative Development Authority (CDA) for cooperatives; 2. Valid and Current Business/Mayor’s Permit issued by the city or municipality where the principal place of business of the prospective bidder is located OR the equivalent document for Exclusive Economic Zones or Areas; In cases of recently expired Mayor’s / Business Permits, said permit shall be submitted together with the official receipt as proof that the bidder has applied for renewal with the period prescribed by the concerned local government units, provided that the renewed permit shall be submitted as a post-qualification requirement; 3. Valid and current Tax Clearance issued by Philippines’ Bureau of Internal Revenue (BIR) Accounts Receivable Monitoring Division per Executive Order 398, Series of 2005; 4. Copy of each of the following Audited Financial Statements for 2017 and 2016 (in comparative form or separate reports): a. Independent Auditor’s Report; b. Balance Sheet (Statement of Financial Position); and c. Income Statement (Statement of Comprehensive Income) Each of the above statements must have stamped “received” by the Bureau of Internal Revenue (BIR) or its duly accredited and authorized institutions. OR 5. Submission of valid and current PHILGEPS Certificate of Registration and Membership (Platinum Registration) together with Annex A in lieu of the eligibility documents. Note: Bidder must ensure that all Class “A” Eligibility Documents are valid and current at the time of submission of PHILGEPS Certificate of Registration and Membership (Platinum Registration). In case any of the submitted Eligibility are not valid and current at the time of submission of Platinum Registration, bidders are required to submit the valid and current documents.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 83 of 87
● In case the JV Partners opt to submit their Class “A” Documents, the Certificate of PhilGEPS Registration (Platinum Membership) shall remain as post-qualification requirement to be submitted in accordance with Section 34.2 of the 2016 Revised IRR of RA9184. “GPPB Circular 07-2017 dated 31 July 2017”.
For item (ii) to (iv) of the required eligibility documents, submission by any of the Joint Venture partner constitutes compliance.
TECHNICAL DOCUMENTS
12.1 (b)(i)
Bid security shall be issued in favor of the DEPARTMENT OF INFORMATION AND COMMUNICATIONS TECHNOLOGY (DICT) valid at least one hundred twenty (120) days after date of bid opening in any of the following forms: a) BID SECURING DECLARATION per Annex IV; or b) Cashier’s / Manager’s Check equivalent to at least 2% of ABC issued by an Universal or Commercial Bank. c) Bank Draft / Guarantee or Irrevocable Letter of Credit issued by a Universal or Commercial Bank equivalent to at least 2% of the ABC: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank d) Surety Bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security equivalent to at least 5% of the ABC
Description SUPPLY, INSTALLATION,
DETAILED DESIGN, TESTING AND
COMMISSIONING, OPERATION AND
MAINTENANCE
SUPPORT OF IP
MICROWAVE
RADIO
COMMUNICATION
SYSTEM FOR DICT-PAGASA "ALL
WEATHER
COMMUNICATION
SYSTEM
PROGRAM"
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 84 of 87
Qty 1 lot
Total ABC (PhP) (VAT Inclusive)
541,999,909.82
BID SECUR
ITY
Cashier’s / Manager’s Check equivalent to at least 2% of the
ABC (PhP)
10,839,998.20
Bank Draft / Guarantee or Irrevocable Letter of Credit
equivalent to at least 2 % of the ABC (PhP)
Surety Bond equivalent to at least 5% of the ABC (PhP)
27,099,995.49
Bid Securing Declaration No required percentage
12.1 (b)(ii)
Proof of Authority of the Bidder’s authorized representative/s: a) FOR SOLE PROPRIETORSHIP (IF OWNER OPTS TO APPOINT A REPRESENTATIVE): Duly notarized Special Power of Attorney b) FOR CORPORATIONS, COOPERATIVE OR THE MEMBERS OF THE JOINT VENTURE: Duly notarized Secretary’s Certificate evidencing the authority of the designated representative/s. c) IN THE CASE OF UNINCORPORATED JOINT VENTURE: Each member shall submit a separate Special Power of Attorney and/or Secretary’s Certificate evidencing the authority of the designated representative/s.
12.1 (b)(iii)
Omnibus Sworn Statements using the form prescribed. (Annex V)
a) Authority of the designated representative
b) Non-inclusion of blacklist or under suspension status
c) Authenticity of Submitted Documents
d) Authority to validate Submitted Documents
e) Disclosure of Relations
f) Compliance with existing labor laws and standards
g) Bidder’s Responsibility
h) Did not pay any form of consideration
i) Company Official Contact Reference
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 85 of 87
12.1 (b)(iv)
Company Profile (Annex VI). Company printed brochure may be included
12.1 (b)(v)
Vicinity / Location of Bidder’s principal place of business
12.1 (b)(vi)
Certificate of Performance Evaluation (Annex VII) showing a rating at least Satisfactory issued by the Bidder’s Single Largest Completed Contract Client stated in the submitted Annex I-A;
12.1 (b)(vii
)
Completed and signed Revised Technical Bid Form (Annex VIII) as of 24 September 2019
12.1 (b)(vii
i)
Brochure (original or internet download) / Technical Data Sheet or equivalent document
12.1 (b)(ix)
Valid and Current Certificate of Distributorship / Dealership/ Resellership of the following product being offered, issued by the principal or manufacturer of the product (if Bidder is not the manufacturer). If not issued by manufacturer, must also submit certification / document linking bidder to the manufacturer
12.1 (b)(x)
Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer be an Independent Certifying body;
12.1 (b)(xi)
Other technical documents which will be required for the project
viii. The bidder must hold a PCAB License with Category AAA in General Engineering for a minimum of two (2) years on or before the date of the bid opening. For joint venture, at least one of the JV should comply to this requirement.
ix. Written Statement of the contractor signed by their authorized representative that they have at least five (5) years of direct experience on engineering, supply and delivery, installation, testing, and commissioning and experience in operations and maintenance of communications facilities network. x. Contractor shall submit resume of key personnel to be assigned to the project upon bid opening. These key personnel are the Professional Electronics & Communication Engineer (PECE) with minimum Seven (7) years experience in Communication Facilities, Project Manager, Project Engineer and Outside Plant Supervisor and six (6) support personnel. xi. Valid and current ISO 9001 Quality Management System Certificate issued to the manufacturer of radio equipment by an Independent Certifying body.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 86 of 87
xii. Written Statement of the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that all features offered and complied to must be available from the time of award. xiii. Certification from National Telecommunications Commission (NTC) that the proposed Microwave IP Radio equipment is duly-type approved. xiv. Written Certification from the equipment manufacturer (IP Microwave Radio) signed by their authorized representative that they are in in good standing and reputation both in the Local and US, European, and ASIAN Market.
12.1 (b)(xii
)
Compliance with the Revised Schedule of Requirements as per Section VI as of 24 September 2019
12.1 (b)(xii
i)
Compliance with the Revised Technical Specifications as per Section VII as of 24 September 2019
ENVELOPE 2: FINANCIAL DOCUMENTS
13.1 (a)
Completed and signed Financial Bid Form. Bidder must use, accomplish and submit Financial Bid Form hereto attached Annex IX.
Description Qty
ABC P (VAT Inclusive)
Total
SUPPLY, INSTALLATION, DETAILED
DESIGN, TESTING AND
COMMISSIONING, OPERATION AND
MAINTENANCE SUPPORT OF IP
MICROWAVE RADIO
COMMUNICATION SYSTEM FOR DICT-PAGASA "ALL WEATHER
COMMUNICATION SYSTEM
PROGRAM"
1 Lot
541,999,909.82
The ABC is inclusive of VAT. Any proposal with a financial component exceeding the ABC shall not be accepted. Further, the sum of bid for each item indicated in the Detailed Financial Breakdown per Annex X must be equal to the signed and submitted Financial Bid Form per Annex VII.
Supplemental Bid Bulletin No. 6
Supply, Installation, Detailed Design, Testing and Commissioning, Operation and Maintenance Support of IP Microwave Radio Communication System for DICT-PAGASA “All Weather Communication System Program”
Bid Reference No.: [DICTBAC-2019-017]
Page 87 of 87
13.1 (a)
Revised Detailed Financial Breakdown per Annex X as of 24 September 2019
15.4(a)(i) & 15.4(b)(ii)
Completed “For Goods Offered from Abroad” and/or “For Goods Offered From Within the Philippine” Forms per Annex XI-A and Annex XI-B, whichever is applicable.
13.1 (b)
If the Bidder claims preference as a Domestic Bidder or Domestic Entity, a Certification from the DTI, SEC or CDA to be enclosed pursuant to the Revised IRR of R.A. 9184.
NOTE:
In case of inconsistency between the Checklist of Requirements for Bidders and the provisions in the Instruction to Bidders/Bid Data Sheet, the Instruction to Bidders/Bid Data Sheet shall prevail