bill no. 1 preliminaries - mintek … · additions and alterations level 7 & 8 asd - mintek...
TRANSCRIPT
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 1
PRELIMINARIES
PREAMBLES FOR TRADES
The Model Preambles for Trades (2008 edition) as publishedby the Association of South African Quantity Surveyors shall bedeemed to be incorporated in these bills of quantities and noclaims arising from brevity of description of items fullydescribed in the said Model Preambles will be entertained
Supplementary preambles are incorporated in these bills ofquantities to satisfy the requirements of this project suchsupplementary preambles shall take precedence over theprovisions of the said Model Preambles
The contractor's prices for all items throughout these bills ofquantities must take account of and include for all of theobligations, requirements and specifications given in the saidModel Preambles and in any supplementary preambles
PRELIMINARIES
Where explanations or comments are reflected in thesePreliminaries, same are to be read as supplementing asopposed to varying the provisions of the relevant clauses
SECTION A: PRINCIPAL BUILDING AGREEMENT - JBCCSeries 2000
NOTES
The JBCC Series 2000 Principal Building Agreement (July 2007edition) prepared by the Joint Building Contract Committeeshall be the applicable building agreement, amended ashereinafter described
The ASAQS Preliminaries (November 2007 edition) publishedby the Association of South African Quantity Surveyors for usewith the said JBCC Principal Building Agreement shall bedeemed to be incorporated in these bills of quantities
Contractor's are referred to the abovementioned documents forthe full intent and meaning of each clause thereof
Carried Forward R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
These clauses are hereinafter reffered to by clause number andheading only Where standard clauses or alternatives are notentirely applicable to this contract, such modifications,corrections or supplements as will apply are given under eachrelevant clause heading and such modifications, corrections orsupplements shall take precedence notwithstanding anythingcontrary contained in the abovementioned documents
Where any item is not relevant to this specific contract suchitem is marked N/A, signifying "not applicable"
Definitions
1/1/1 Definitions and Interpretation (Clause 1) Item
Objective and preparations
1/1/2 Offer, Acceptance and Performance obligations (Clause 2) Item
1/1/3 Documents (Clause 3) Item
1/1/4 Design Responsibility (Clause 4) Item
1/1/5 Employer's Agents (Clause 5) Item
1/1/6 Contractor's site Representative (Clause 6) Item
1/1/7 Compliance with Laws and Regulations (Clause 7) Item
1/1/8 Works Risk (Clause 8) Item
1/1/9 Indemnities (Clause 9) Item
1/1/10 General Insurances (Clause 10) Item
1/1/11 Special Insurances (Clause 11) Item
1/1/12 Effecting Insurances (Clause 12) Item
1/1/13 Assignment (Clause 13) Item
1/1/14 Security (Clause 14) Item
Carried Forward R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Execution
1/1/15 Preparation For and Execution of The Works (Clause 15) Item
1/1/16 Site and Access (Clause 16) Item
1/1/17 Contract Instructions (Clause 17) Item
1/1/18 Setting Out Of The Works (Clause 18) Item
1/1/19 Temporary works and plant (Clause 19) Item
1/1/20 Nominated Subcontractors (Clause 20) Item
1/1/21 Selected Subcontractors (Clause 21) Item
1/1/22 Employer's Direct Contractors (Clause 22) Item
1/1/23 Contractor's Domestic Subcontractors (Clause 23) Item
Completion
1/1/24 Practical Completion (Clause 24) Item
1/1/25 Works Completion (Clause 25) Item
1/1/26 Final Completion (Clause 26) Item
1/1/27 Latent Defects Liability Period (Clause 27) Item
1/1/28 Sectional Completion (Clause 28) Item
1/1/29 Revision of Date for Practical Completion (Clause 29) Item
1/1/30 Penalty for Late or Non-Completion (Clause 30) Item
Payment
1/1/31 Interim Payment to the Contractor (Clause 31) Item
1/1/32 Adjustment to the Contract Value (Clause 32) Item
1/1/33 Recovery of Expense and Loss (Clause 33) Item
1/1/34 Final Account and Final Payment (Clause 34) Item
Carried Forward R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 3 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
1/1/35 Payment to Other Parties (Clause 35) Item
Termination
1/1/36 Termination by Employer - Contractor's Default (Clause 36) Item
1/1/37 Termination by Employer - Loss and Damage (Clause 37) Item
1/1/38 Termination by Contractor - Employer's Default (Clause 38) Item
1/1/39 Termination - Cessation of the Works (Clause 39) Item
Dispute
1/1/40 Dispute Settlement (Clause 40) Item
Contract Agreement
1/1/41 Post tender provisions (Clause 41)
The required post tender information shall be inserted in thepost tender provisions after consultation with the contractor Item
1/1/42 Contractual agreement (Clause 42)
The required information of the contracting parties and theamount of the accepted contract sum shall be inserted in thecontractual agreement for signature of the agreement by thecontracting parties Item
SECTION B: PRELIMINARIES
Definitions and Interpretation
1/1/43 Definitions and Interpretation (Clause 1.0) Item
Documents
1/1/44 Checking of Documents (Clause 2.1) Item
1/1/45 Provisional Bills of Quantities (Clause 2.2) Item
1/1/46 Availability of Construction Documentation (Clause 2.3) Item
Carried Forward R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 4 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Previous work and adjoining properties
1/1/47 Previous Work - Dimensional Accuracy (Clause 3.1) Item
1/1/48 Previous Work - Defects ( Clause 3.2) Item
1/1/49 Inspection of Adjoining Properties (Clause 3.3) Item
Samples, Shop Drawings and Manufacturer's Instructions
1/1/50 Samples of Materials (Clause 4.1) Item
1/1/51 Workmanship Samples (Clause 4.2) Item
1/1/52 Shop Drawings (Clause 4.3) Item
1/1/53 Compliance with Manufacturer's Instructions (Clause 4.4) Item
Deposits and Fees
1/1/54 Deposits and Fees (Clause 5.1) Item
Temporary Services
1/1/55 Water (Clause 6.1) Item
1/1/56 Electricity (Clause 6.2) Item
1/1/57 Telecommunication Equipment (Clause 6.3) Item
1/1/58 Ablution Facilities (Clause 6.4) Item
Prime cost Amounts
1/1/59 Responsibility for Prime Cost Amounts (Clause 7.1) Item
Special Attendance on N/S Subcontractors
1/1/60 Special Attendance (Clause 8.1) Item
GENERAL
1/1/61 Protection of the Works (Clause 9.1) Item
Carried Forward R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 5 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
1/1/62 Protection / Isolation of Existing / Sectionally Occupied Works(Clause 9.2) Item
1/1/63 Security of the Works (Clause 9.3) Item
1/1/64 Notice Before Covering Work (Clause 9.4) Item
1/1/65 Disturbance (Clause 9.5) Item
1/1/66 Environmental Disturbance (Clause 9.6) Item
1/1/67 Works Cleaning and Clearing (Clause 9.7) Item
1/1/68 Vermin (Clause 9.8) Item
1/1/69 Overhand Work (Clause 9.9) Item
SECTION C: SPECIFIC PRELIMINARIES
1/1/70 Standard Conditions of Tender Item
1/1/71 Special Conditions of Tender Item
1/1/72 Tender Data Schedule Item
1/1/73 General Conditions of Contract Item
1/1/74 Special Conditions of Contract Item
Carried to Final Summary R Section No. 1PRELIMINARIESBill No. 1PRELIMINARIES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 6 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 1
ALTERATIONS
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008Edition).
REMOVAL OF EXISTING WORK
Breaking down and removing brickwork, etc.
2/1/1 One brick wall m2 657
Taking out and removing doors, windows, etc frombrickwork to be demolished
2/1/2 Timber single door and frame not exceeding 2,5m2 No 28
2/1/3 Timber double door and frame exceeding 2,5m² and notexceeding 5m² No 7
Taking out and removing doors, windows, etc includingthresholds, sills, etc (building up openings elsewhere)
2/1/4 Timber single door and frame 813 x 2032mm high overall fromone brick wall No 12
2/1/5 Timber double door and frame 1626 x 2032mm high overallfrom one brick wall No 7
Taking out and removing ironmongery and setting asidefor re-use including protecting same with bubble wrap
2/1/6 Pinning board 2200mm x 1300mm high plugged No 17
Taking up and removing vinyl floor coverings, carpeting,etc
2/1/7 Vinyl tile floor covering including preparing screed for new floorcovering (elsewhere measured) m2 360
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 1ALTERATIONS
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 7 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Hacking up/off and removing ceramic tile floor and wallfinishes including removing mortar bed or backing andpreparing concrete or brick surfaces for new screed,plaster or tile finishes
2/1/8 Ceramic tiles to floors m2 50
Taking out and removing piping, sanitary fittings, etcincluding disconnecting piping from fittings and makinggood floor and wall finishes
2/1/9 Stainless steel sink and drainer on timber cupboard 760 x 465 x1200mm high No 20
2/1/10 Vitreous china wash hand basin No 10
2/1/11 Vitreous china WC pan with cistern No 6
2/1/12 Vitreous china wall hung urinal with flush valve No 4
Taking off and removing sanitary accessories andpreparing concrete or brick surfaces for new plaster or tilefinishes
2/1/13 Soap dispensor No 4
2/1/14 Paper towel dispensor No 4
2/1/15 Toilet roll holder No 6
Taking out and removing glass and mirrors
2/1/16 Mirror 650 x 650mm high from wall No 4
Sundries
2/1/17 Cutting toothings and bonding new brickwork to existing m2 145
MAKING GOOD OF FINISHES, ETC
2/1/18 Making good brickwork to face of wall where half brick crosswall removed m 90
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 1ALTERATIONS
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 8 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 2
MASONRY
SUPPLEMENTARY PREAMBLES
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008Edition).
NOTE
Brickwork rates are to include, where applicable for returnbricks at window and door reveals, lintels, etc., galvanized 'Z'ties every third course at 900mm centres and shall whereapplicable include for forming preformed openings to receivealuminium windows, doors, etc.
Unless otherwise stated, all brickwork is to be built in stretcherbond.
Wire ties will be as described in the Model Preambles.
Sizes in descriptions
Where sizes in descriptions are given in brick units, 'one brick'shall represent the length and 'half brick' the width of a brick.
Hollow walls etc
Descriptions of hollow walls shall be deemed to include leavingevery fifth perpend of the bottom course of the external skinopen as a weep hole.
Walls in two skins described as 'bagged and sealed' shall bedeemed to include having the outer face of the inner skinbagged with 1:6 cement and sand mixture and sealed with twocoats 'Brixeal' bitumen emulsion waterproofing coating.
Face bricks
Bricks shall be ordered timeously to obtain uniformity in sizeand colour.
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 2MASONRY
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 9 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Pointing
Descriptions of recessed pointing to fair face brickwork andface brickwork shall be deemed to include square recessed,hollow recessed, weathered pointing, etc.
BRICKWORK IN SUPERSTRUCTURE
Brickwork of NFP bricks in class II mortar
2/2/1 Half brick wall m2 8
2/2/2 One brick wall m2 70
BRICKWORK SUNDRIES
Brickwork reinforcement
2/2/3 75mm Wide reinforcement built in horizontally m 31
2/2/4 150mm Wide reinforcement built in horizontally m 210
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 2MASONRY
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 0 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 3
CARPENTRY AND JOINERY
SUPPLEMENTARY PREAMBLES
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008 Edition)
Fixing
Items described as "nailed" shall be deemed to be fixed withhardened steel nails or shot pins to brickwork or concrete
Items described as "plugged" shall be deemed to includescrewing to fibre, plastic or metal plugs at not exceeding500mm centres, and where described as "bolted", the boltshave been given elsewhere
Joinery
Descriptions of frames shall be deemed to include frames,transoms, mullions, rails, etc.
Descriptions of hardwood joinery shall be deemed to includepelleting of bolt holes
Decorative thermosetting plastic laminate finish
Laminate covering shall be glued under pressure and edgestrips of same shall be butt jointed at junctions with adjacentsimilar finish
SKIRTINGS
Wrought Meranti
2/3/1 75 x 19mm Skirting plugged m 3,014
DOORS, ETC
44mm Thick solid core door with Maple veneer hung totimber frame
2/3/2 Door 813mm x 2032mm high as per Architect's door schedule No 22
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 3CARPENTRY AND JOINERY
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 1 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
2/3/3 Door 900mm x 2032mm x 40mm Thick 2 HR Fire rated doubledoor as per Architect's door schedule No 6
2/3/4 Door 1700mm x 2032mm x 40mm Thick 2 HR Fire rateddouble door as per Architect's door schedule No 4
FRAMED FRAMES, ETC
Wrought meranti
2/3/5 90 x 55mm Rebated frames plugged m 124
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 3CARPENTRY AND JOINERY
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 2 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 4
CEILINGS, PARTITIONS AND ACCESS FLOORING
SUPPLEMENTARY PREAMBLES
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008Edition).
Descriptions
Items described as "nailed" shall be deemed to be fixed withhardened steel nails or pins or shot pinned to brickwork orconcrete
Items described as "plugged" shall be deemed to includescrewing to fibre, plastic or metal plugs at not exceeding600mm centres, and where described as "bolted" the boltshave been given elsewhere
INSULATION
Insulation
2/4/1 50mm Thick flexible non-combustible light weight insulationmaterial over brandering in a completed roof & ceiling system.Installation strictly in accordance with the manufacturers detail& specification.
m2 1,600
SUSPENDED CEILINGS
Suspended ceilings
Note:
Electrical light fittings, diffusers, panels, etc generally are "layin" units of the same dimensions as the suspension griddescribed and allowance must be made accordingly fortheir support inclusive of any flexibility insetting out that maybe required (ceiling panels have not been deducted and pricingis to take cognisance thereof)
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 4CEILINGS, PARTITIONS AND ACCESS FLOORING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 3 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
600 x 600 x 15mm Thick AMF thermatex aquatec ceilingtile, on pre-painted dove grey exposed tee suspensionsystem including main and cross tees, necessaryhangers, grids, etc to make provision for electrical andventilation grille/air conditioning diffuser openings
2/4/2 Ceilings suspended not exceeding 1m below concrete soffits m2 1,579
CORNICES,ETC
'Donn' cornices to suspended ceilings
2/4/3 47 x 35mm 'SM25' recessed shadowline cornice plugged m 156
PARTITIONS, ETC
Partitions
Single skin, half hour fire rated drywall partitioning system withoverall thickness of 89mm, comprising internal framing formedof 63.5mm galvanised steel studs fixed at 600mm centres to63.5mm steel top and bottom track including any additionalsteel studding necessary at door openings, glazed or otherapertures, abutments, ends, corners, etc. and clad both sideswith one layer 12.5mm thick Taper Edge Gypsum Boards insingle lengths to suit height, butt jointed and secured tostudding with 25mm drywall screws at maximum 220mmcentres, the joints taped over and joined in accordance with themanufacturers specifications. All external corners to receive0.6mm galvanised steel corner beads. Drywall to be skimmed,sanded and finished sufficiently for painting (elsewheremeasured). All aluminium door frames, glazing sections,corners, transomes, cornices, skirtings, etc. shall be formed ofnatural anodised aluminium sections. (Intersections andabutments are measured separately and descriptions shall bedeemed to include any additional studs, corner beads, jointingcompound, tape, etc.)
Steel stud partitioning with 12.5mm gypsum plasterboardon both sides
2/4/4 Partitioning 3000mm high with bottom and top tracks plugged m 110
2/4/5 Extra over partition 2685mm high for vertical abutment No 36
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 4CEILINGS, PARTITIONS AND ACCESS FLOORING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 4 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
2/4/6 Extra over partition 2685mm high for corner No 1
2/4/7 Extra over partition 2685m high for T-intersection No 2
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 4CEILINGS, PARTITIONS AND ACCESS FLOORING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 5 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 5
FLOOR COVERINGS, PLASTIC LININGS, ETC
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008Edition).
FLOOR COVERINGS
Flowcrete as specified in Architect's drawings
Flowcoate SF41
2/5/1 On floors; including epoxy as per manufacturer's specificationsand as per manufacturer's installation instructions:
m2 66
Flowshield 2000 including CR Sealer Coat
2/5/2 On floors; including epoxy as per manufacturer's specificationsand as per manufacturer's installation instructions:
m2 574
Peran STB
2/5/3 On floors; including epoxy as per manufacturer's specificationsand as per manufacturer's installation instructions:
m2 694
Anti static vynil tile, Van Dyck cpec, neon code orangefixed with adhesive to plaster (plaster elsewheremeasured) as per manufacturer's specifications and flushpointed with white waterproof jointing compound as permanufacturer's installation instructions
2/5/4 On floors and landings; (Allow PC Amount of R200.00/m2 forsupply of the tile) including epoxy as per manufacturer'sspecifications and as per manufacturer's installationinstructions:
m2 235
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 5FLOOR COVERINGS
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 6 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 6
PLASTERING
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008 Edition)
INTERNAL PLASTER
Cement plaster on brickwork or concrete
2/6/1 On walls m2 250
2/6/2 On narrow widths m2 55
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 6PLASTERING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 7 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 7
TILING
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008 Edition)
SUPPLEMENTARY PREAMBLES
Descriptions
Unless described as "fixed with adhesive to plaster (plasterelsewhere measured)" descriptions of tiling on brick or concretewalls, columns, etc shall be deemed to include 1:4 cementplaster backing and descriptions of tiling on concrete floors, etc.shall be deemed to include cement screed bedding
WALL TILING
300 x 600m x 12mm Thick ceramic tile (Allow PC Amount ofR150.00/m2 for supply of the tile) fixed with adhesive toplaster (plaster elsewhere measured) as permanufacturer's specifications and flush pointed with whitewaterproof jointing compound as per manufacturer'sinstallation instructions:
2/7/1 On walls m2 203
FLOOR TILING
600 x 600 x 12mm Thick porcelain tile (Allow PC Amount ofR200.00/m2 for supply of the tile) fixed to screed; fromMaharani specification; Europa Amsterdam glazed codeAT1005 and flush pointed with white waterproof jointingcompound as per manufacturer's installation instructions:
2/7/2 On floors and landings m2 125
SUNDRIES
"Tal" White PVC tile edge trim fixed simultaneously withtiling including mitres, ends, etc:
2/7/3 6mm Edge trim to walls. m 423
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 7TILING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 8 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 8
METALWORK
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (September2008 Edition) and to the Supplementary Preambles which areincorporated in this Bill.
The Tenderer is also referred to foregoing sections forpreambles and full descriptions of items and materials notdescribed in this section which will apply equally to the work inthis section, unless otherwise described.
SUPPLEMENTARY PREAMBLES
Tenderers are to refer to the Drawings, Finishes Schedules,etc. appended to these bill of quantities, which indicate both thelocation and unit types of various fittings together with sizes,details, etc. prior to pricing this section.
Tenderers are to note that should there be any doubt orobscurity as to the meaning and intent regarding the drawings,finishing schedules, etc. the tenderer must have the samerectified with the Principal Agent and allow for accordingly in thetender. The tenderer is to include in the rates for all that he /she considers necessary for the design, construction andinstallation of the works
Rates are to include for supply and installation of AluminiumShopfronts complete as detailed on the drawings, finishingschedules, etc. including glazing, ironmongery as describedand as necessary, metalwork, finishes, silicone sealing to bothedges (internally and externally), making good finishesdisturbed, fixing in position, etc.
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 8GLAZING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 1 9 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Tenderers are referred to the following drawings attached tothis tender document:
(1) Drawing 11015TP5002 Shopfront ScheduleRevision 01
Tenderers are advised to carefully study the drawings referredto above and to allow for the cost of all notes and requirementsindicated thereon, which is deemed to include the full extent ofthe works. Should there be any doubt or obscurity as to themeaning and the intent thereof, the Tenderer shall have thesame verified with the Architect and to accordingly makeallowance for same in the tender amount. No claims whatsoverwill be entertained due to the tenderer having failed to complywith any of these conditions.
ALUMINIUM SHOPFRONTS
Natural anodised aluminium glazed shopfronts includingdoors, ironmongery, glazing, frames, etc. executedcomplete
2/8/1 8382mm Wide x 2800mm high glazed aluminium shopfront(SF01) including doors. Refer to Drawing Number: 14058-5000. No 1
2/8/2 4850mm Wide x 1600mm high glazed aluminium shopfront(SF02). Refer to Drawing Number: 14058-5000.
No 5
2/8/3 4130mm Wide x 2800mm high glazed aluminium shopfront(SF03) including doors. Refer to Drawing Number: 14058-5000.
No 2
2/8/4 4130mm Wide x 2800mm high glazed aluminium shopfront(SF04) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/5 10505mm Wide x 2800mm high glazed aluminium shopfront(SF05) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/6 6940mm Wide x 2800mm high glazed aluminium shopfront(SF06) including doors. Refer to Drawing Number: 14058-5000.
No 1
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 8GLAZING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 0 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
2/8/7 900mm Wide x 2800mm high glazed aluminium shopfront(SF07). Refer to Drawing Number: 14058-5000.
No 3
2/8/8 1800mm Wide x 1000mm high glazed aluminium shopfront(SF08). Refer to Drawing Number: 14058-5000.
No 1
2/8/9 1800mm Wide x 2800mm high glazed aluminium shopfront(SF09) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/10 6810mm Wide x 2800mm high glazed aluminium shopfront(SF10) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/11 4001mm Wide x 2800mm high glazed aluminium shopfront(SF11) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/12 6205mm Wide x 2800mm high glazed aluminium shopfront(SF12). Refer to Drawing Number: 14058-5000.
No 1
2/8/13 7563mm Wide x 2800mm high glazed aluminium shopfront(SF13). Refer to Drawing Number: 14058-5000.
No 2
2/8/14 1215mm Wide x 2800mm high glazed aluminium shopfront(SF14) including door. Refer to Drawing Number: 14058-5000.
No 1
2/8/15 2695mm Wide x 2800mm high glazed aluminium shopfront(SF15) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/16 2635mm Wide x 2800mm high glazed aluminium shopfront(SF16) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/17 1275mm Wide x 2800mm high glazed aluminium shopfront(SF17). Refer to Drawing Number: 14058-5000.
No 1
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 8GLAZING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 1 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
2/8/18 4101mm Wide x 2100mm high glazed aluminium shopfront(SF18) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/19 12684mm Wide x 2800mm high glazed aluminium shopfront(SF19) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/20 10460mm Wide x 2800mm high glazed aluminium shopfront(SF20) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/21 4911mm Wide x 2800mm high glazed aluminium shopfront(SF21) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/22 1199mm Wide x 2800mm high glazed aluminium shopfront(SF22) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/23 5305mm Wide x 1600mm high glazed aluminium shopfront(SF23). Refer to Drawing Number: 14058-5000.
No 1
2/8/24 2711mm Wide x 2800mm high glazed aluminium shopfront(SF24) including doors. Refer to Drawing Number: 14058-5000.
No 1
2/8/25 4000mm Wide x 2800mm high glazed aluminium shopfront(SF25). Refer to Drawing Number: 14058-5000.
No 1
2/8/26 4000mm Wide x 2800mm high glazed aluminium shopfront(SF26) including doors. Refer to Drawing Number: 14058-5000.
No 1
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 8GLAZING
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 2 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 9
PAINTWORK
SUPPLEMENTARY PREAMBLES
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008 Edition)
PAINTWORK ETC TO NEW WORK
FLOATED PLASTER SURFACES WITH
Prepare new surface, apply two coats undercoat and twocoats acryllic PVA paint on
2/9/1 On walls m2 305
ON PLASTERBOARD
ON WOOD
Prepare new surface and apply two coats wood primer on:
2/9/2 On backs of frames, linings, etc. not exceeding 300mm wide m2 30
Prepare new surface, apply two coats undercoat and twocoats non drip enamel paint on
2/9/3 On doors m2 64
Prepare new surface and apply two coats varnish on
2/9/4 On wooden floors, skirtings, rails, etc not exceeding 300 mmgirth m 3,014
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 9PAINTWORK
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 3 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Item Quantity Rate AmountNo
BILL NO. 10
PROVISIONAL SUMS AND BUDGETARYALLOWANCES
The Tenderer is referred to the relevant Clauses in theseparate document Model Preambles for Trades (2008Edition)
The following sub-contract amounts are for work to becarried out by nominated sub-contractors in terms ofclause 20, clause 21 selected sub-contractors and clause22 work by others of the Principal Building Agreement
Note: Tenderers are to note that the allowances listed hereunder are for work to be executed by the appointedprincipal contractor. Tenderers are to allow in their overallPremilinaries costs for this scope of work as no additionalPreliminaries will be entertained once this scope of work isrealised. The Employer reserves the right to execute thiswork in part or in whole or omit the entire scope
SUPPLEMENTARY PREAMBLES
General
Work for which budgetary allowances are provided will bemeasured and valued in accordance with clause 5 of the NEC 3Engineering and Construction contract June 2005 anddeducted in whole or in part if not required without anycompensation for loss or profit on the said allowances
Prime cost amounts and provisional sums are NET. Prime costamounts include for delivery to site of all articles concerned
Provisional sums are for material and equipment supplied andinstalled complete by firms of specialists
Profit
Where stated, the contractor may allow for profit if required
General attendance on subcontractors
The item "Attendance" which follows each provisional sum forsubcontractors' work, shall be deemed tocover all the contractor's costs incurred in providing free ofcharge to the subcontractors, the following:
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 10PROVISIONAL SUMS AND BUDGETARY ALLOWANCES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 4 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
1 The services as set out in clause 26 of the Preliminaries
2 Making good in all trades and cleaning down and removal of rubbish on completion
PROVISIONAL SUMS
PLUMBING AND DRAINAGE INCLUDING SANITARY WAREAND SANITARY ACCESSORIES
Plumbing and Drainage Including Sanitaryware and SanitaryAccessories
2/10/1 Provide the sum of R1,500,000.00 (One Million Five HundredThousand Rand) for Plumbing and Drainage IncludingSanitaryware and Sanitary Accessories Item 1,500,000 00
2/10/2 Profit Item
2/10/3 Attendance Item
HEATING VENTILATION AND AIRCONDITIONING
Heating, Ventilation and Airconditioning
2/10/4 Provide the sum of R 2, 500,000.00 (Two Million Five HundredThousand Rand) for Heating, Ventilation and Airconditioning Item 2,500,000 00
2/10/5 Profit Item
2/10/6 Attendance Item
GAS INSTALLATION
Gas Installation
2/10/7 Provide the sum of R 920,000.00 (Five Hundred and FiftyThousand Rand) for Gas Installation Item 920,000 00
2/10/8 Profit Item
2/10/9 Attendance Item
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 10PROVISIONAL SUMS AND BUDGETARY ALLOWANCES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 5 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
ELECTRICAL AND ELECTRONICS INSTALLATION
Electrical and Electronics Installation
2/10/10 Provide the sum of R 1, 320, 000.00 (One Million ThreeHundred and Twenty Thousand Rand) for Electrical andElectronics Installation Item 1,320,000 00
2/10/11 Profit Item
2/10/12 Attendance Item
FIRE SERVICES
Fire Services
2/10/13 Provide the sum of R 55,000.00 (Fifty Five Thousand Rand) forFire Services Item 55,000 00
2/10/14 Profit Item
2/10/15 Attendance Item
SIGNAGE
Signage
2/10/16 Provide the sum of R75,000.00 (Seventy Five Thousand Rand)for Signage Item 75,000 00
2/10/17 Profit Item
2/10/18 Attendance Item
BUDGETARY ALLOWANCES
Carried Forward R Section No. 2SUPERSTRUCTUREBill No. 10PROVISIONAL SUMS AND BUDGETARY ALLOWANCES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 6 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Brought Forward R
Note: Tenderers are to note that the provisionalallowances listed here under are for work to be executedby the appointed principal contractor. Tenderers are toallow in their overall P & G allowances for this scope ofwork as no additional P & G's will be entertained once thisscope of work is realised. The Employer reserves the rightto execute this work in part or in whole or omit the entirescope
2/10/19 Provide the sum of R 120,000.00 (One Hundred and TwentyThousand Rand) for the Removal and Relocation and Storageof Existing Loose Furniture Item 120,000 00
2/10/20 Provide the sum of R 500,000.00 (Five Hundred ThousandRand) for Contingencies Item 500,000 00
2/10/21 Provide the sum of R 50,000.00 (Fifty Thousand Rand) for theSundry Alterations and Demolitions Item 50,000 00
2/10/22 Provide the sum of R 100,000.00 (One Hundred ThousandRand) for hoarding, dust screens, etc., executed complete. Item 100,000 00
2/10/23 Provide the sum of R 50,000.00 (Fifty Thousand Rand) forMunicipal Plans Submission., executed complete. Item 50,000 00
2/10/24 Provide the sum of R 200,000.00 (Two Hundred Thousand) forSundry Builder's work to Specialist Installations, etc., executedcomplete Item 200,000 00
2/10/25 Provide the sum of R 420,000.00 (Four Hundred and TwentyThousand) for Escalation Item 420,000 00
Carried Forward to Summary of Section No. 2 R Section No. 2SUPERSTRUCTUREBill No. 10PROVISIONAL SUMS AND BUDGETARY ALLOWANCES
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 7 -
ADDITIONS AND ALTERATIONS LEVEL 7 & 8 ASD - MINTEK
Section No. 2
SUPERSTRUCTURE
SECTION SUMMARY - SUPERSTRUCTURE
Bill Page AmountNo No
2/1 -8-ALTERATIONS
2/2 -10-MASONRY
2/3 -12-CARPENTRY AND JOINERY
2/4 -15-CEILINGS, PARTITIONS AND ACCESS FLOORING
2/5 -16-FLOOR COVERINGS
2/6 -17-PLASTERING
2/7 -18-TILING
2/8 -22-GLAZING
2/9 -23-PAINTWORK
2/10 -27-PROVISIONAL SUMS AND BUDGETARY ALLOWANCES
Carried to Final Summary R Section No. 2SUPERSTRUCTURE
Annexure A - Bills of QuantitiesPricing Data: Builder's Work
- 2 8 -