biosng demonstration plant -...

45
gogreengas.com BioSNG Demonstration Plant Project Close-Down Report

Upload: duongthu

Post on 26-Mar-2018

222 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

gogreengas.com

BioSNG Demonstration Plant Project Close-Down Report

Page 2: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 1

Table of Contents

1.0 Project Background ................................................................................................ 2

2.0 Executive Summary ................................................................................................ 3

2.1 Scope and Objectives ............................................................................................... 3

2.2 Project Outcomes ...................................................................................................... 3

2.3 Successful Delivery Reward Criteria ......................................................................... 5

2.4 Learning .................................................................................................................... 5

3.0 Project Description and Outcomes ....................................................................... 6

3.1 BioSNG ..................................................................................................................... 6

3.2 Demonstration Plant Construction and Commissioning .......................................... 10

3.3 Testing and Optimisation ........................................................................................ 13

3.4 Commercial Plant Engineering ................................................................................ 17

3.5 Commercial Plant Financial Performance ............................................................... 19

3.6 Environmental Performance .................................................................................... 22

3.7 Commercial Plant Development .............................................................................. 24

4.0 Performance .......................................................................................................... 26

4.1 Overall Performance ............................................................................................... 26

4.2 Performance against SDRCs .................................................................................. 27

5.0 Modifications to the Planned Approach to the Project ...................................... 33

6.0 Financial Performance .......................................................................................... 34

7.0 Business Case....................................................................................................... 35

7.1 The Vision for 2050 ................................................................................................. 35

7.2 Achieving the Vision ................................................................................................ 36

7.3 Changes since the Full Submission ........................................................................ 37

8.0 Lessons Learnt for Future Innovation Projects .................................................. 39

9.0 Project Replication ................................................................................................ 39

10.0 Planned Implementation ....................................................................................... 40

11.0 Dissemination........................................................................................................ 40

12.0 Key Documents ..................................................................................................... 44

13.0 Contact Details ...................................................................................................... 44

Page 3: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 2

1.0 Project Background

BioSNG addresses the issue of decarbonising heat and transport, which together account for more than

70% of final energy use in the UK. It offers an affordable, low carbon alternative to fossil gas which could

help provide a greener and more secure energy future. The widespread deployment of BioSNG will use the

UK’s extensive gas network to help reduce carbon emissions from heat and transport with no disruption to

consumers.

The BioSNG technology converts household waste into a grid compliant gas through the combination of

gasification and catalytic conversion. Producing BioSNG would greatly expand the supply of renewable gas

over and above existing solutions such as anaerobic digestion (AD). In total, AD and BioSNG have the

potential to produce 100TWh of low carbon gas per annum, enough to meet one third of domestic heat

demand.

The funding and strategic backing for the project comes from Ofgem’s Network Innovation Competition

and the European BioEnergy Securing the Future ERANET programme.

Cadent (formerly known as National Grid Gas Distribution) has worked with Advanced Plasma Power,

Progressive Energy and Carbotech to demonstrate the technical and commercial feasibility of BioSNG

production. The partners have constructed and operated a demonstration plant facility that has

successfully shown BioSNG production. The results from this facility have validated the technical and

commercial models of the process and enabled the development of the first commercial BioSNG plant,

which will deliver gas to grid in 2018.

The results from the project will lead to the construction of larger scale commercial BioSNG facilities to

serve regional needs across the country. These plants could make a telling contribution to the future

reliability of gas supplies at an affordable cost and with significant reductions in greenhouse gas emissions.

The approach could help solve a major issue facing governments, energy suppliers, policy makers and

consumer groups across the world: how to decarbonise heat and heavy goods transport in a sustainable

way through the development of technology that is commercially viable, affordable, and acceptable to

consumers. It highlights Cadent’s commitment to seeking economic and innovative ways to decarbonise

energy, while making the best use of the existing UK gas network.

The benefits include contributing to the acceleration of a low carbon economy, the decarbonisation of heat

and transport, and a marked reduction of waste volumes going to landfill. The economic benefits include

new investment opportunities which will provide affordable energy for consumers, and the possibility of

increased local control over waste processing linked to green energy production.

This document is supported by more detailed reports that have been published on the project website.

These cover the detailed technical results of the project1, the design of commercial BioSNG facilities2 and

the economic performance of those facilities3.

1 http://gogreengas.com/wp-content/uploads/2015/11/P167-BioSNG-Results.pdf 2 http://gogreengas.com/wp-content/uploads/2017/03/P167-BioSNG-Design.pdf 3 http://gogreengas.com/wp-content/uploads/2017/03/P167-BioSNG-Commercial.pdf

Page 4: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 3

2.0 Executive Summary

2.1 Scope and Objectives

In the introduction to the UK Government strategy on decarbonising heat4 Ed Davey, the former Secretary

of State for Energy and Climate Change, states that “there has been a historic failure to get to grips with

one enormous part of the energy jigsaw; the supply of low carbon heat.” In response to this failure, the

Government is using schemes such as the Renewable Heat Incentive to encourage a range of possible

solutions including electrification, heat networks, biomass boilers and green gas production.

For transport, in the recent consultation on renewable fuels5 John Hayes, the Transport Minister, says: “As

we transition to electric cars, we will continue to need low carbon liquid and gaseous fuels for decades to

come, particularly to decarbonise transport sectors that are not as easy to electrify, such as planes and

lorries.” The consultation then identifies renewable gas as strategically important for the heavy goods

sector.

This shows the importance of low carbon substitutes for fossil natural gas in decarbonising both heat and

transport. Renewable gas produced by anaerobic digestion (AD) of crops, agricultural residues and waste

has grown strongly over the last five years. However, the potential of conventional AD is limited by the

availability of suitable feedstocks. New technologies that can process a wider range of materials are

required for renewable gases to make a meaningful contribution.

The potential to generate large quantities of low carbon gas is essential for the future of the gas grid. As

the UK continues to reduce greenhouse gas emissions in line with the Climate Change Act, the use of fossil

gas for heating or transport will need to fall significantly. Unless low carbon gases can replace the fossil gas

then volumes will eventually fall below the level where it is economic to operate a gas network.

The objectives of the BioSNG Demonstration Project were to prove the technical and economic feasibility of

thermal gasification of waste and biomass feedstock to produce renewable gas, through the construction of

a demonstration plant. The construction and operation of the facility and test programme has

demonstrated BioSNG production and validated technical and commercial models to enable the

construction of large scale commercial plants.

BioSNG has the potential to generate more than 100TWh of renewable gas, enough to make a significant

contribution to heating and transport, to secure the long-term future of the gas grid, and to allow

consumers to reduce carbon emissions without any changes in how they heat their homes.

2.2 Project Outcomes

The project has directly led to the construction of a commercial BioSNG facility that will convert 10,000

tonnes of waste into 22GWh of low carbon BioSNG that will be injected into the local grid. This will start

operation in the first half of 2018 and provide a reference facility that will catalyse the construction of

larger scale commercial plants.

The successful delivery of the commercial facility is reliant on the outcomes of the demonstration project

4https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/190149/16_04-DECC-The_Future_of_Heating_Accessible-10.pdf 5https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/572971/rtfo-consultation-document-2016.pdf

Page 5: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 4

such as:

The results from experiments on the kinetics of the water gas shift and methanation reactions

carried out in the demonstration plant which validated the process engineering models used to

underpin the commercial design.

The procedures and controls developed to operate the demonstration plant safely.

The solutions to design issues identified in the demonstration plant project.

The confidence in the performance of BioSNG technology given by the demonstration plant such as

the successful demonstration of sensitive methanation catalysts on waste-derived syngas.

Another important outcome is the increase in BioSNG’s profile as a result of the demonstration plant. The

facility has been visited by representatives of more than fifty organisations including ministers, civil

servants, gas distribution companies, regulators, academics, industry and financiers. It has frequently

featured in print, television and radio news stories and project partners have presented the project results

at a large number of commercial and academic conferences. The work has also led to a number of

academic papers for submission to well respected energy journals, the first of which is in press.

The results of the project are influencing the strategies of Government and industry. DEFRA, BEIS and the

DfT are all considering the role of BioSNG in future heat, transport and waste policy. The Labour Party has

worked with the Energy Networks Association to produce the Green Gas Book6 which makes extensive

references to BioSNG. KPMG has carried out a detailed analysis7 of the economics of the decarbonisation

of heat using BioSNG. Cadent’s Future of Gas publications8 set out the strategic importance of BioSNG

production.

The project has produced outline design and financial models for a number of commercial plants. The key

outputs from those models for two scenarios are presented in the following table:

315GWh/a

(1st of a kind)

665GWh/a

(nth of a kind)

RDF energy input 66MWth 132MWth

RDF mass input 136tkpa 289ktpa

Footprint 3.14ha 4.95ha

Capital cost £108m £151m

Operating cost £10.2m/a £16.5m/a

Real pre-tax project return 12% 10%

Levelised cost of BioSNG £50/MWh £21/MWh

The 315GWh model represents the performance of a first generation facility. It offers the level of returns

that funders would expect for a new technology and the model includes large capital and operating cost

risk contingencies. This means that it has a levelised cost for its gas that is above the current fossil price

and, like any other new low carbon technology, would require Government support to secure funding.

6 https://alansenergyblog.files.wordpress.com/2016/07/13973-the-green-gas-book_96pp_v5.pdf 7http://www.energynetworks.org/assets/files/gas/futures/KPMG%20Future%20of%20Gas%20Main%20report%20plus%20appendices%20FINAL.pdf 8 http://cadentgas.com/About-us/The-future-role-of-gas

Page 6: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 5

The 665GWh model represents the performance of a mature facility built in the middle of the next decade.

Returns and risk contingencies that are lower than earlier plants and its larger size offer significant

economies of scale. This means that the levelised cost of its gas is in line with expected fossil gas prices.

Overall, the project has helped move BioSNG from the fringes of discussions on decarbonisation of heat

and transport to a central place and has put in place the foundations for the construction of large scale

BioSNG plants.

2.3 Successful Delivery Reward Criteria

The project met all of its Successful Delivery Reward Criteria (SDRC).

The dissemination SDRCs (9.1 and 9.9) were met ahead of schedule through the setting up and promotion

of the web portal for the project, presentation at a large number of conferences, construction of a visitor

centre, and hosting visits and workshops on BioSNG. The highlight was an event in November 2016 with

more than 100 attendees including senior representatives from Government and industry. This event

secured very positive coverage in the national press.

The design, delivery, commissioning and operation SDRCs (9.2, 9.3, 9.4 and 9.5) were all successfully

completed. Testing included a programme of extensive process optimisation trials and concluded with a

run demonstrating end to end operation of the facility in December 2016. A value engineering exercise was

carried out after the initial design was completed to bring the project back within budget and this caused a

delay of around three months. However, there was sufficient contingency to ensure that all of the project

objectives could still be met.

The SDRCs relating to the design and commercial modelling of a full-scale plant (9.6, 9.7 and 9.8) were met

ahead of schedule. The results of the full-scale plant engineering and levelised cost of gas calculations were

used to produce a detailed submission for DECC in response to their consultation on the future of the

Renewable Heat Incentive. All the work relating to these SDRCs has been very useful in the design and

construction of the first commercial BioSNG plant.

Overall, the results of the project have exceeded the expectations of the project partners. The project has

delivered far more than was expected.

2.4 Learning

The project has increased understanding of the technical, commercial and environmental importance of

BioSNG.

At high level, the project has confirmed the technical assumptions for BioSNG production. It has

demonstrated that it is possible to produce BioSNG at small scales using a once-through process and there

are simple, cost effective methods of reducing the contaminants in waste-derived syngas to the low levels

required by the methanation catalysts.

At a project level the key learning for the partners has been:

The original programme did not allow sufficient time for value engineering. This led to delays at

the start of the project. However, there was sufficient contingency to ensure all the work could be

completed on time.

It became clear that the demonstration facility was too large to allow all of the optimisation work

Page 7: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 6

set out in in the test plan to be undertaken in the time available. The partners built a smaller test

rig that provided more flexibility and greatly increased the range of experiments that could be

completed under the project.

The project has been a positive experience for the partners, and Cadent, Advanced Plasma Power and

Progressive Energy continue to collaborate on the project to build a commercial BioSNG plant.

A key insight from the project is the synergies between BioSNG and hydrogen. Work by Northern Gas

Networks9 has shown how the replacement of fossil natural gas with hydrogen, produced using steam

methane reforming (SMR), in conjunction with carbon capture and storage provides an efficient pathway to

decarbonising heat using gas networks. BioSNG facilities can produce gas with the low levels of hydrogen

required to meet the current grid specification but are able to increase hydrogen levels if this is considered

desirable and shift to very high levels of hydrogen if networks move to hydrogen use. This flexibility means

that BioSNG can play an important part in the conversion of gas networks to hydrogen.

The commercial modelling from the project has shown that a mature, full scale BioSNG plant using waste as

a feedstock will be able to produce gas with a similar cost to fossil natural gas. However, Government

support for the technology will be required while it is maturing. The modelling has shown what levels of

support are required and this has been discussed with BEIS and the DfT; these Government departments

are currently considering the long term incentive structures for low carbon heat and transport. It will be

important to continue to engage with Government on this.

Environmental modelling has shown that a full scale BioSNG plant will produce gas with carbon emissions

80% lower than fossil natural gas, which exceeds expectations from the start of the project. The BioSNG

process produces a high-purity stream of carbon dioxide which could be sequestered in carbon storage

infrastructure to increase carbon savings to 190%. The combination of bioenergy with carbon capture and

storage can provide the negative greenhouse gas emissions that are essential to offset emissions that are

difficult to reduce from sectors such as agriculture and aviation.

The results of the project clearly show that BioSNG will play an important role in delivering sustainable,

affordable and low carbon heat and transport.

3.0 Project Description and Outcomes

3.1 BioSNG

BioSNG production is a five-stage process as shown in the following diagram:

9 http://www.northerngasnetworks.co.uk/wp-content/uploads/2016/07/H21-Executive-Summary-Interactive-PDF-July-2016-V2.pdf

Fuel

Preparation

Thermal

Treatment

Cooling and

Cleaning

Gas

Conversion

Purification

Page 8: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 7

The stages are:

Fuel Preparation: Drying, shredding and removal of recyclates from feedstocks to produce a fuel

that is compatible with the thermal treatment.

Thermal Treatment: Gasification or pyrolysis of the prepared feedstock to produce a synthesis gas

that can be converted into biomethane.

Cool and Cleaning: The synthesis gas will contain contaminants such as tars, sulphur and chlorine

compounds and heavy metals that would hinder the next stage. Techniques such as wet scrubbing,

activated carbon filtration and other polishing media are used to remove these.

Gas Conversion: A combination of catalysed reactions is used to convert the syngas to natural gas.

Purification: Carbon dioxide, hydrogen and other unwanted gases will be removed from the

product gas to give a natural gas that meets grid or transport specifications.

All of these stages are established technologies with a large number of reference facilities but the

combination is relatively novel. However, the challenges of decarbonising heat and transport have led to

increased interest in the technology. The GoBiGas facility in Sweden, which started operations in

December 2015, and the commercial plant being built by the project partners, which will produce gas in

2018, are the first commercial facilities.

Thermal technologies have demonstrated that they can utilise a wide range of feedstocks. Outotec, the

gasifier supplier for the BioSNG commercial plant, has over 100 reference plants treating manure, paper

sludge, wood waste, refuse derived fuel, sewage sludge, and agricultural residues. This flexibility is a key

strength of the technology.

Biomass feedstocks are limited, and demand for them is expected to grow as worldwide demand for low

carbon fuels increases. Finding the right balance between growing crops for food and energy is very

important as diversion of land from food production in one country can lead to land use changes in another

country that result in deforestation, release of carbon locked in land, and loss of biodiversity. The potential

capacity and sustainability of fuels from biomass is a complex and contentious area.

The Committee on Climate Change (CCC) recently reviewed the availability of biomass for energy10 in the

UK. They produced an estimate of the potential of different feedstocks which is shown in the following

graph:

10 https://www.theccc.org.uk/archive/aws2/Bioenergy/1463%20CCC_Bioenergy%20review_interactive.pdf

Page 9: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 8

0

50

100

150

200

250

300

350

400

2011 2015 2020 2025 2030 2035 2040 2045 2050

Bio

en

erg

y p

rim

ary

en

erg

y (T

Wh

/ye

ar)

Imported forest biomass

Imported agriculturalresidues (dry)

Imported feed and foddercrops

Imported dedicated energycrops

Domestic forest biomass

Domestic agriculturalresidues (dry)

Domestic feed and foddercrops

Domestic dedicated energycrops

Domestic wastes

Total domestic supply

This shows that biofuels can make a significant contribution to the UK energy mix and emphasises the

importance of domestic wastes, the UK’s largest source of biomass, which are particularly well suited to

thermal treatment. If all of the sustainable UK wastes identified by the CCC were used for BioSNG

production they would generate over 100TWh of renewable gas.

Thermal biomethane has a significantly lower carbon footprint than fossil natural gas but the production

and distribution of renewable gas results in some greenhouse gas (GHG) emissions. The key factors in the

calculation of GHG impact of thermal biomethane are shown in the following diagram:

The greenhouse gas emissions from a first of a kind BioSNG plant have been calculated under the project

and are set out in the following table:

Thermal

Biomethane

Facility

Gas to grid

Feedstock

Electricity and fossil fuel use

Consumables and construction

Page 10: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 9

Emissions

(kgCO2eq/MWh)

Electricity consumption 29.7

Gas consumption 2.5

Construction & maintenance 15.9

Avoided landfill (151.0)

CO2 capture (267.4)

(370.3)

GHG emissions without landfill credit (219.3)

GHG emissions without CO2 capture or landfill credit 48.1

Overall emissions from fossil natural gas are 243kgCO2eq/MWh so BioSNG gives an overall saving of 80%

compared to fossil gas. This increases to a saving of 142% if the benefit of diverting waste from landfill is

taken into account and to 252% if carbon dioxide from the process is sequestered.

This means 100TWh of BioSNG production would result in GHG savings of at least 19.4m tonnes per annum

which would increase to 34.4m tonnes per annum if the impact of diverting waste from landfill was taken

into account and 61.1m tonnes per annum if the carbon dioxide produced by the process was sequestered.

BioSNG has the following advantages over other routes for decarbonising heat:

It does not require any changes to heating appliances or consumer behaviour. Gas customers are

very satisfied with the performance of their heating systems. Work undertaken by Wales and West

Utilities11 shows that it is very challenging to persuade them to move to new solutions based on

electric heating or heat networks.

BioSNG is naturally stored within the gas network in order to smooth out the peaks and troughs in

demand for heating. The large variation in demand for heat, shown in the graph below, is

challenging for electric solutions.

The overall cost of using BioSNG to decarbonise heat is lower than other approaches. This is

supported by work by KPMG12.

11http://www.smarternetworks.org/Files/Bridgend_Future_Modelling_%E2%80%93_Phase_2_150910144351.pdf 12http://www.energynetworks.org/assets/files/gas/futures/KPMG%20Future%20of%20Gas%20Main%20report%20plus%20appendices%20FINAL.pdf

Page 11: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 10

For transport BioSNG offers the following benefits:

Heavy goods vehicles and buses that can use gas as a fuel are available now. Scania, Iveco,

Mercedes and Volvo all sell vehicles that can use BioSNG. Electrification of heavy goods vehicles

will require major advances in battery technology.

Currently the conversion of syngas to BioSNG is simpler and less expensive than the conversion to

liquid fuels such as diesel.

The gas grid provides a cost-effective network for delivery of BioSNG to transport users.

BioSNG offers a low-cost route to decarbonising heat and transport that can address sectors that other

solutions find challenging. It will play an important role in the UK’s future energy mix.

3.2 Demonstration Plant Construction and Commissioning

The primary route to establishing the technical feasibility of BioSNG production was the construction of a

demonstration plant to accept syngas produced by the gasification of waste using an existing plant owned

by Advanced Plasma Power, one of the project partners. In the new demonstration plant the syngas is

compressed and stored and then converted into methane using a series of catalysed reactors. The resulting

mix of methane and carbon dioxide is refined using a pressure swing adsorption system.

The preliminary design of the pilot plant was carried out under Innovation Funding Incentive project IFI79.

The present project developed a detailed design based on this preliminary work and then engaged with

suppliers to deliver the facility.

Initial quotations obtained for the core of the plant significantly exceeded the capital spend budget and this

necessitated a detailed value engineering exercise being undertaken with the preferred supplier. The

outcome of this work was a significant reduction in cost, to bring it in line with the budget, without causing

a reduction either in the performance or functionality of the system. A schematic of the final design,

including the gasification pilot plant, is shown below:

Page 12: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 11

The delay associated with finalising the design and cost of the equipment packages put some pressure on

the project schedule. The project partners worked closely with the suppliers to improve their delivery

timescales or arrange for them to conduct more off-site functional testing of equipment in order to reduce

downstream risk of malfunction and to expedite subsequent commissioning of the facility. Site preparation

was carried out in parallel with equipment manufacture to ensure that any equipment delivered to site was

rapidly and easily installed.

Despite these mitigating activities, the value engineering led to a delay in the construction and

commissioning of the plant and this used up the contingency in the programme for any further project

delay.

Installation of all of the equipment was completed by June 2015, fifteen months after the start of the

project. The primary components of the installed facility are shown in the following photographs:

The completed facility showing gas storage vessels

Page 13: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 12

Gas Compressor

Reaction Vessels (before and after insulation)

Pressure Swing Adsorption System

Page 14: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 13

Commissioning of the facility was completed in December 2015 without any major issues and in line with

the project programme. The facility was then handed over to the operations teamto carry out testing and

optimisation.

3.3 Testing and Optimisation

Following the successful commissioning of the demonstration plant, work focussed on testing and

optimisation of integrated methanation and refining. Data from this testing was used to develop designs of

commercial facilities.

Fundamentally, the testing and optimisation work confirmed that it is possible to produce methane from a

mixed waste feedstock. The combination of an oxy-steam fluidised bed gasifier directly coupled to a tar-

cracking plasma unit delivers a high quality, raw syngas with very low levels of tars and organo-sulphur

compounds. The downstream gas processing and polishing techniques provide syngas of sufficient quality

for catalyst operation, with no evidence of sulphur-induced catalyst degradation or any other

contamination or deactivation.

The fundamentals of a once-through methanation process train have been established on the

demonstration facility. For the commercial plant, Amec Foster Wheeler is providing its Vesta process,

which relies on similar principles and can be supplied with appropriate process guarantees.

A foundational element to this project has been the development of validated process models to enable

confident prediction of plant performance. These models were based on data from lab-scale experiments.

The first stage of the methanation process is the water gas shift reaction. Experimental work was

performed to provide data which, when combined with data available in the literature, enabled a rate

equation to be established. The predictions of the model were validated against experimental data as in

the following graph, showing that the model performs well.

Control Room and Visitor Centre

Page 15: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 14

The remaining methanation process comprises a complex system of reactions as shown below:

C CO CO2

CH4

CH3OHCnH2n CnH2n+2CnH2nOH

CO2 reduction

(+2H2O)

DH = -90.1 kJ/mol

Inversed CH4 reforming

(+2H2)

DH = -247.3 kJ/mol

Methane cracking

(-2H2)

DH = +74.8 kJ/mol

CO2 methanation

(Sabatier)

(+4H2)

DH = -165.0 kJ/mol

CO methanation

(+3H2)

DH = -206.1 kJ/mol

Water gas shift

(+H2O)

DH = -41.2 kJ/mol

Boudouard

(+H2O)

DH = 172.5 kJ/mol

Alkenation

(+2n+1 H2)

Alkanation

(+2n H2)

CO2 hydrogenation

(+ 3H2)

DH = -49.3 kJ/mol

CO hydrogenation

(+ 2H2)

DH = -90.5 kJ/mol

Hydrolysis

(+H2O)

Steam reforming

(+H2O)

DH = 131.3 kJ/mol

Kinetic modelling of the methanation reaction system focussed on the water gas shift, the reverse water

gas shift, CO methanation, and steam methane reforming. Further experimental data was used to produce

a model for the reaction network that was based on empirical power law relationships; the output of the

model is compared to experimental data in the graph below, showing good correlation:

Page 16: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 15

The models enabled the gas compositions throughout a commercial plant to be predicted as shown in the

following graph:

A key tool in evaluating and optimising catalyst operation was an offline testing rig, which was built and

operated in parallel to the demonstration plant and which enabled the partners to quickly and efficiently

analyse catalyst performance across a range of tightly controlled variables. Using the rig, the effects of

operating temperature, pressure, reactant concentrations, and diluents could be assessed. An early

success of the offline rig was showing the important role of steam in process control and in reducing carbon

deposition. The offline test rig is shown in the following picture:

Following the successful construction and commissioning of the demonstration plant, the plant

components were first tested individually, then integrated operation and testing of methanation and

refining was demonstrated, both on bottled gases and on waste-derived syngas.

A series of operational runs were undertaken on the demonstration plant to explore its operating envelope

Page 17: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 16

and to verify results from the offline work. Methane production from waste-derived syngas in the first

stage methanator (below) shows the achievement of stable operation; the demonstration plant

experimental work consistently confirmed the predictions of offline testing.

The high degree of correlation between model predictions, laboratory scale tests, and demonstration plant

results gives confidence in the thermodynamic and kinetic modelling and, therefore, the ability to predict

performance of the commercial plant. This allows rapid assessments of different scales, configurations and

feedstock types.

Heat loss on the demonstration plant was a significant issue. This was a result of scale, uncertainties over

catalyst performance at the plant design stage, and the impact of designing for experimental flexibility.

Heat losses will be addressed in commercial plant design, with assurances secured from Amec Foster

Wheeler. Because of the heat loss issues, flows in the plant were increased, resulting in methane

production that far exceeded the 51kWth design rate.

A key element in delivering grid quality gas is the refining stage downstream of methanation. The facility

provided demonstration of the efficacy of a single stage pressure swing adsorption (PSA) system for

separation of carbon dioxide, as well as the potential to remove a proportion of residual hydrogen,

nitrogen and carbon monoxide, although removal of these gases was associated with appreciable loss of

methane to the tail gas stream. During testing, the PSA was optimised for three bottled gas compositions

(Base 1, 2 and 3 in the graph below) and also tested on transient conditions (“B1T1” etc.). It showed

Page 18: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 17

consistent performance across these varied gas compositions, as well as methanated syngas from the

demonstration plant (“Waste”).

Whilst a PSA is feasible for this application, alternative separation techniques such as chemical solvents use

heat to effect separation, which offers the prospect of integration with the waste heat available from the

methanation proces, and produces a high-quality carbon dioxide stream that is suitable for industrial sales

or storage.

A further result of the work was demonstration of the possibility of in-situ low-level production of ethane

and propane, giving an alternative to fossil propane enrichment that offers environmental and economic

benefits.

Based on the work undertaken in this programme, a commercial plant, including the appropriate grid entry

unit, will be able to meet the gas requirements of both the Gas Safety (Management) Regulations and

Network Entry Agreement.

Operation of the demonstration plant has required development of a range of competencies within the

operations team which are directly transferable to a commercial plant. In particular, this has required

development of detailed safety assessments and provided extensive operational experience with regard to

handling combustible gases at high temperatures and pressures, as well as safe catalyst handling. This

invaluable experience will form the basis for safe operation in commercial facilities.

3.4 Commercial Plant Engineering

The project partners developed designs for plants producing 315GWhper annum and 665GWh per annum

of BioSNG. These were based on the demonstration plant design and were informed by the results of

experimental testing, an assessment of scale up risk and engagement with suppliers.

The designs were reviewed by the project team to ensure that they addressed the risks of scaling up the

various process steps. All of the individual steps in the BioSNG are already operating at large scale in a

large number of reference facilities which means that the chief scale up risks relate to the integration of the

process. Where it was appropriate, computerised fluid dynamic modelling was carried out to reduce the

Page 19: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 18

uncertainties introduced by the increase in scale.

The key design choices made were:

The use of an oxy-steam fluidised bed gasifier rather than an indirect gasifier, because fluidised bed

systems produce far lower levels of tars and volatile organic compounds (VOCs) which are difficult

to remove from the syngas.

Plasma treatment of the syngas to:

o remove tars and VOCs, rather than water or oil-based scrubbing systems which would

result in lower process efficiencies.

o remove organo-sulphur compounds which cannot be addressed by conventional scrubbing

techniques.

Compression of the syngas to 10 bar(g) prior to methanation, because this represents a good

compromise between compression duty and vessel and pipework scale.

Methanation using the VESTA process developed by Amec Foster Wheeler, because, like the

approach taken in the demonstration project, this is a once-through solution operating at low

temperatures but has the prospect of commercial guarantees.

A chemical solvent system for gas refining rather than a PSA system, because chemical systems

maximise yield of BioSNG and use waste heat arising from the plant rather than electricity to

remove the carbon dioxide.

The team produced process flow diagrams for each scale of plant and then produced computer simulations

of the process using the Aspen modelling software, building on the experimental validation work developed

in this project. The software was used to produce mass and energy balances and the information from

these was used to engage with equipment suppliers to select equipment for each process step. A Sankey

diagram summarising the energy balance for 315GWh per annum is given below as an example of the

output from the design.

Page 20: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 19

Equipment information was used to produce a layout for the commercial facilities using a CAD package.

The energy balances for commercial facilities are summarised in the following table:

315GWh/a 665GWh/a

Energy input

RDF 66MWth 132MWth

Net power input 4MWe 7MWe

Energy output

BioSNG 42MWth 84MWth

Thermal losses 28MWth 55MWth

The table below summarises the mass balances for commercial plants:

315GWh/a 665GWh/a

Mass input (tph)

Wet RDF 18.3 36.7

Oxygen and other chemicals 5.8 11.7

Water 5.4 7.0

Mass output (tph)

Carbon dioxide 12.8 25.5

Product BioSNG 3.0 6.0

Effluent 7.1 10.7

Solid residues 1.8 3.6 Exhaust 4.8 9.6

The results of the engineering design work were used to prepare financial models of large scale facilities.

3.5 Commercial Plant Financial Performance

The assessment of commercial plant financial performance is based on modelling of the technical

performance of large scale facilities and estimates of their capital and operating costs.

The designs of the large scale facilities were analysed and the process was broken down into the following

discrete packages:

Fuel preparation and storage.

Gasification and tar removal.

Gas cooling.

Gas cleaning.

Gas compression.

Oxygen production.

Gas compression and methanation

Carbon dioxide removal.

Page 21: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 20

Power and controls.

Mechanical integration.

Building and civils.

Design and construction management.

The cost of each package was estimated through discussion with suppliers.

The contracting structure for delivery of the facilities has a significant impact on costs. The project partners

assume that commercial facilities would be delivered under fixed price, turnkey contract with a large EPC

contractor. This increases the cost of delivery but reduces the cost of finance because the contractor is

accepting more risk.

The cost models for each scale of plant are shown in the following table:

315GWh/a 665GWh/a

First of a kind

Nth of a kind

£m £m

Fuel receipt and drying 4.9 7.4

Gasification 28.3 42.7

Oxygen production 7.2 10.9

Methanation 14.8 22.6

Building and civils 8.7 13.2

Install, power, controls 12.0 18.2

Grid connection 1.6 3.1

Construction management 16.8 21.2

EPC risk, overhead and profit 11.4 9.2

Other 2.2 2.2

107.9 150.7

£ per expected MWh of annual production 348 229

In general, the lower costs per MWh of the 665GWh per annum plant are due to economies of scale. In

addition, the larger plant is expected to be delivered after the technology is mature and this is reflected in a

smaller risk allowance and higher operating hours. A first of a kind facility is expected to operate for 7,446

hours per annum (85% availability) increasing to 7,884 hours (90% availability) for an nth of a kind facility.

These costs can be benchmarked against advanced conversion technology waste to power facilities which

have a similar cost base. The Arup review of renewable energy costs13 suggests a cost of £5.5m per MW of

power produced. A facility producing 315GWh per annum of BioSNG is equivalent to a power plant

producing around 20MW of power using gas engines, which would cost £111m using the Arup figure

compared to the £108m calculated above.

13https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/66176/Renewables_Obligation_consultation_-_review_of_generation_costs_and_deployment_potential.pdf

Page 22: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 21

The key operating costs of a BioSNG facility are set out in the following table:

Type Description

Parasitic load The cost of power used for plant equipment, mainly plasma converter and

oxygen plant power.

Waste disposal The cost of disposing of APC-R waste generated from gas cleaning.

Consumables Consumables derived from the mass and energy balance.

Catalysts The cost of catalyst replacement.

Maintenance Annual and lifecycle costs of maintaining equipment.

Staff costs Salaries, benefit, social security costs, IT and other costs associated with

employees.

Other consumables Consumables not derived from the mass and energy balance such as lubricants,

personal protection equipment or electrodes.

Other Permit compliance, royalties and rent.

These have been estimated by the project partners using the mass and energy balance and current market

rates. The results are shown in the following table:

315GWh/a 665GWH/a

First of a kind

Nth of a kind

£m £m

Labour 1.6 1.8

Power 3.0 5.3

Consumables 1.5 3.1

Maintenance 1.9 2.9

Other 2.2 3.5

10.2 16.5

£ per expected MWh of annual production 33 25

The capital and operating costs can be used to calculate the levelised costs of gas produced by the BioSNG

facilities. The levelised cost calculations require an estimate of the hurdle rates required by funders of the

plant. For the 315GWh per annum facility it is assumed that funders will require a 12% return. This falls to

10% for the large plants that will be built after the BioSNG technology is mature.

The levelised costs calculated in the project are shown in the following table:

Page 23: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 22

315GWh/a 665GWh/a

First of a kind Nth of a kind

£/MWh £/MWh

Capex 50 29

Opex 33 25

Gate fee (33) (33)

Levelised cost 50 21

These compare to current natural gas prices of around £16/MWh. It is expected that the cost of gas

produced by large scale nth of kind facilities will match the future market price of natural gas and that they

will be able to operate without any subsidy. The smaller, first of a kind facilities will require support from

Government through schemes such as the Renewable Heat Incentive and Renewable Transport Fuel

Obligation. The project partners have engaged with Government to explain the need for support and the

benefits of BioSNG.

3.6 Environmental Performance

The commercial plant engineering set out in Section 3.4 can be used to calculate the greenhouse gas

impact of BioSNG.

Use of waste to produce BioSNG results in significant carbon savings over fossil natural gas; plants will

produce BioSNG with a GHG emissions 80% lower than fossil gas in the absence of carbon capture. If

carbon capture is used and the impact of diverting waste from landfill are taken into account the saving

could be as high as 264%, resulting in a GHG credit that can be used to offset GHG emissions from other

activities.

The basis for these figures is laid out in the emissions analysis below where the main areas of the plant

process are considered and associated emissions highlighted. Waste contains a mix of fossil and biogenic

carbon but the standard approach, as set out in the Renewable Energy Directive and other methodologies

for GHG analysis, is to only consider the renewable component.

The waste used in these plants will be collected locally, typically from sites within a 10km radius of the

refuse derived fuel processing plant, which will in turn be a short distance from the BioSNG facility. Due to

the short distances involved analysis has shown the impact of this feedstock transport to be negligible,

constituting less than 1% of emissions from the process.

The facilities under consideration are fuelled by RDF. Figures from existing RDF plants indicate electricity

consumption of 0.42MWh/tonne wet RDF, resulting in 0.018MWh electricity used per MWh BioSNG (all

figures stated using gross calorific value).

The counterfactual used for the waste handled in BioSNG plants is landfill. Landfilled biomass decomposes

and emits methane; figures from Defra estimate that each tonne of organic waste sent to landfill would

release 350kgCO2eq14. Using this figure we find that the BioSNG process saves 151kgCO2eq/MWh BioSNG

produced.

14 Consultation Stage IA: The Renewable Heat Incentive: A reformed and refocused scheme p97. 320g is the most conservative figure given.

Page 24: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 23

Emissions associated with construction and maintenance of BioSNG facilities need to be accounted for.

Figures from a model produced by the NNFCC15 suggest that the lifetime contribution of these emissions

equates to 15.9kg/MWh BioSNG.

The BioSNG plant will generate some electricity from process heat but will require additional electricity

input of 0.127MWh for each MWh of BioSNG produced. In addition, 0.011MWh of natural gas is used in

production of each MWh of BioSNG for the preheating of equipment.

The BioSNG process captures carbon dioxide at sufficient quality for sale to industry. If this is to be done,

the CO2 must be liquefied for temporary storage and transport. In production of each MWh of BioSNG,

290kg CO2 could be captured, with 0.078MWh electricity used for liquefaction. Transporting the CO2 to the

end user would emit 6.8kgCO2, assuming a distance of 250km.

The product is then injected into the local gas grid, with negligible power required for this step.

Because biomethane in use comprises biogenic carbon, emissions at the point of use are taken to be zero.

The overall emissions of the process depend strongly on the carbon intensity of the electricity used in the

process. The National Grid Future Energy Scenario gives a forecast of the grid intensity of power under four

different scenarios as shown in the chart below. Even under the least aggressive assumptions, the intensity

of electricity is expected to fall to 204.5kgCO2eq/MWhe by 2025, and this figure has been used to find a

worst-case emissions figure for BioSNG. The Gone Green scenario predicts carbon intensity of

121.45kgCO2eq/MWhe by 2025 and 79.85kgCO2eq/MWhe by 2030, which has been used to provide less

conservative estimates.

15 10-06-21 NNFCC Solid Gasifier SNG v23

Page 25: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 24

The table below summarises the emissions from the process under these various assumptions. All figures

are given on a per MWh of BioSNG basis and the gas loads have been converted into CO2eq emissions

using the EU grid mix value of 243kgCO2eq/MWh16. The results of the greenhouse gas analysis are shown

in the following table:

Emissions (kgCO2eq) at kgCO2eq/MWh electricity

Electricity/gas consumption

204.5 121.4 79.8

MWh kgCO2eq/MWh BioSNG

Electricity

RDF production 0.018 3.7 2.2 1.5

SNG plant 0.127 26.0 15.4 10.2

CO2 capture 0.078 15.8 9.4 6.2

Gas

SNG plant 0.011 2.5 2.5 2.5

Other

Construction & maintenance 15.9 15.9 15.9

Avoided landfill (151) (151) (151)

CO2 capture (290) (290) (290)

CO2 transport 6.8 6.8 6.8

Absolute performance

With CO2 capture and landfill credit (370) (389) (398)

Without CO2 capture, with landfill credit (103) (115) (121)

Without CO2 capture or landfill credit 48 36 30

Comparison to fossil natural gas

With CO2 capture and landfill credit 252% 260% 264%

Without CO2 capture, with landfill credit 142% 147% 150%

Without CO2 capture or landfill credit 80% 85% 88%

This calculation shows that even at the worst expected GHG intensity of UK electricity, and ignoring the

impact of diverting waste from landfill for carbon capture, BioSNG has a GHG intensity of 48kg/MWh which

is 80% lower than fossil gas. Even larger savings are achieved if the waste used for BioSNG production is

diverted from landfill or if the carbon dioxide produced in the process is sequestered.

3.7 Commercial Plant Development

While the project was being delivered an opportunity arose to secure grant funding for a commercial

BioSNG plant from the Department for Transport’s Advanced Biofuels Demonstration Competition. The

project partners won £11m of funding from the Department for Transport and this, combined with £5.4m

of NIC funding (project NGGDGN02), enabled construction to start on a commercial BioSNG plant in

16 JEC Well-to-Wheel study, WTT Appendix 1, available at http://iet.jrc.ec.europa.eu/about-jec/

Page 26: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 25

November 2016.

A key objective of this project was to enable the construction of a commercial BioSNG facility and to

achieve this objective before the conclusion of the project represents a very positive outcome.

The commercial facility will process 10,000 tonnes per annum of waste from local households to produce

22GWh of gas, enough to heat more than 1,500 homes. The plant is being built at Advanced Plasma

Power’s premises in Swindon. Detailed design is complete and all permits are in place. It is expected that

construction of the facility will be completed by the end of 2017 and the first gas should be injected to grid

in the first half of 2018.

The commercial plant will provide a reference facility for the BioSNG process that operates on a full time

basis in a fully commercial environment. It will give organisations the confidence to develop larger scale

commercial facilities and lead to the wide scale deployment of BioSNG technology.

The development of the commercial plant would not have been possible without the learning from the

demonstration plant project. The following learning from the demonstration plant played a key role in

enabling the development of the commercial facility:

The conceptual designs developed for the demonstration plant project were used for the

commercial plant.

The relationships developed with suppliers of equipment for the demonstration plant were very

helpful in the design and development of the commercial plant.

The computer simulations used in the design of the commercial plant were validated through

experimental work on the demonstration plant.

The demonstration plant showed the effectiveness of both carbon dioxide and steam as diluents to

control the methanation reaction. The VESTA methanation solution developed by Amec Foster

Wheeler selected for the commercial plant relies on steam to control reactions.

The catalysts that will be used in the commercial plant for syngas polishing, the water gas shift and

methanation have all been tested by the project partners to ensure their performance matches

their specifications.

The processes developed for operating the demonstration plant safely are being refined and reused

Page 27: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 26

in the commercial plant.

The commercial models developed in the demonstration plant project were used to model the

commercial plant and give funders confidence it will generate sufficient revenue to cover its costs.

The demonstration plant has provided the DfT, Ofgem and Cadent with sufficient confidence in BioSNG

technology to allow them to agree to invest significant funds in the commercial plant. Without the

demonstration plant it is unlikely that the commercial plant would have secured this funding.

4.0 Performance

4.1 Overall Performance

The project sought to prove the technical and economic feasibility of the production of BioSNG. This has

been clearly demonstrated by the agreement to build the commercial facility described in Section 3.7.

Starting the development of a commercial facility before the completion of the demonstration plant project

far exceeds the expectations of the project partners when they started the project.

The work in the demonstration facility described in Section 3.3 has clearly demonstrated that it is feasible

to convert waste-derived syngas to pipeline quality gas. The contaminants in the syngas can be reduced to

levels that allow normal catalyst operation. The combination of the water gas shift and methanation

reactions can convert the carbon monoxide and hydrogen in the syngas to methane with very high

conversion efficiencies. The PSA system can remove sufficient carbon dioxide to enable the gas to meet

calorific value and Wobbe requirements if it is propanated. These results show that the technical

objectives of the project have been met.

The commercial designs and simulations developed during the project, as described in Section 3.4, show

the technical feasibility of large scale plants and the commercial models, as described in Section 3.5, show

that once the technology has matured a large scale BioSNG plant will be able produce gas for a cost that

matches fossil gas prices. Earlier plants will require Government support in order to achieve the hurdle

rates of return required by investors. However, both the Department for Business, Energy and Industrial

Strategy and the Department for Transport are working on schemes that are likely to include significant

support for BioSNG.

The results of the environmental analysis of BioSNG are set out in Section 3.6. This project has clearly

demonstrated that BioSNG offers significant greenhouse gas savings in comparison to fossil gas and that

even higher savings can be achieved if the process uses waste diverted from landfill or if it is combined with

carbon dioxide storage. The environmental performance of BioSNG is better than the initial calculation set

out in the full submission for the project.

By establishing the technical, economic and environmental feasibility of BioSNG production, the project has

significantly increased the potential for deployment of low carbon green gas. This increases the likelihood

that the gas grid will continue to operate as the UK reduces greenhouse gas emissions in accordance with

the Climate Change Act. This will contribute to the decarbonisation of heat whilst allowing consumers to

continue to use existing appliances. It will also provide a pathway for the decarbonisation of heavy goods

transport.

Page 28: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 27

4.2 Performance against SDRCs

The performance of the project partners against each of the Successful Delivery Reward Criteria are set out

in the following table:

SDRC Description Target

Date

Performance

9.1 Dissemination Portal

The consortium will create a

National Grid BioSNG

Website dedicated to the

project, and through this

portal provide public

visibility of the objectives

and aspirations of the

project, as well as progress

through the project life.

Details of this web portal

will be sent to all GB

network licensees, as well as

promoted at wider industry

conferences. Already the

project has received

publicity in this way through

a number of industry

related conferences that

promote waste to energy

and fuels. We would expect

this to continue and

increase during the project.

A key element of

dissemination is also the

‘showcase’ Visitors’ Centre –

which is considered as a

separate criteria, see Item

9.9

02/06/2014 First website17 set up on 30/05/2014 and a refreshed website18

launched on 18/12/2015. Website publicised at more than 12

exhibitions including Low Carbon Networks and Innovation,

World Energy to Waste Summit, and European Biomass

Conference. All GB Network Licensees given details of website

at BioSNG Day event.

The websites communicates:

The environmental, economic and social benefits of

BioSNG.

The business case for BioSNG.

Details of project partners.

Demonstration plant details.

News and project updates including Project Progress

Reports.

In addition, the website provides a form for people to ask

questions about the technology. Total traffic to the website in

the last 12 months is 5,176 sessions. On average, visitors

visited 2.31 pages per visit.

The Go Green Gas website continues to be updated with news

and information on the project.

Conferences and exhibitions have provided valuable channels

for communicating project goals and achievements to

business, Government and academia. Each of the project

partners has presented the project at a large number of

conferences and communicated project results through stands

at industry exhibitions.

For more information, see Section 11 below.

17 http://cadentgas.com/About-us/Innovation/ 18 http://gogreengas.com/

Page 29: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 28

9.2 Final Design and Safety

Review

The work of the project will

include completing the final

designs and drawings prior

to fabrication and assembly

along with the completion

of the safety review of the

plant in accordance with the

APP site safety procedures

and regulations. This work

will be completed as part of

task one.

01/08/2014 A detailed Hazardous Operations (Hazop) Review of the design

and drawings was completed in July 2014. This was facilitated

by Rowan House, a respected engineering consultancy.

A further Hazop review was carried out to review the changes

resulting from the value engineering work carried out to bring

the project cost back within budget. This review was

completed in March 2015. This was facilitated by 6

Engineering.

A final, “as built”, Hazop was completed by 6 Engineering in

October 2015 as final check on the safe operation of the

facility.

The designs were successfully used to construct the

demonstration plant and the results of the Hazops helped

ensure that the facility operated safely throughout the project.

All Hazop reports are available to Ofgem for review.

9.3 Construction and

Installation

This is a clear criterion that

will require the delivery to

the site of completed

equipment packages and

the integration of these to

make a complete BioSNG

plant as set out in the final

design document. Tasks two

and three will show

evidence of the completion

of the tasks whilst the start

of commissioning will be

further confirmation that

the required equipment has

been procured and brought

to site

10/04/2015 All of the packages were delivered to site and integrated in

accordance with the project programme. This is evidenced

through photographs of the plant and supplier documents.

Installation was completed in July 2015 and commissioning

commenced in August 2015.

The installation was completed three months later than set

out in the SDRCs. This is because of the delay caused by the

value engineering exercise carried out in 2014 to bring

planned project cost back within budget. This used most of

the delay contingency in the project programme but still left

sufficient time for the testing and optimisation objectives of

the project to be met on time before the project concluded in

March 2017.

Page 30: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 29

9.4 Commissioning of plant

a. Storage of syngas

b. Purity level of syngas

c. Water gas shift success =

purity and levels of CO and

H2

d. Methanator operation

and production of substitute

natural gas

The major success delivery

criterion will be seen once

the plant has been

commissioned and produces

natural gas which will be

fired in a household boiler in

the exhibition area of the

plant. There will be a

number of different stages

of the commissioning as

each new piece of

equipment is commissioned

in sequence.

06/07/2015 The commissioning of the plant was completed in December

2015 and the plant was handed over to the operational team

for detailed testing. This is evidenced by the commissioning

test documentation.

All of the equipment used in the facility and the control

systems passed commissioning tests successfully. The

commissioning SDRC was achieved four months later than

originally envisaged. This was partly due to the knock-on effect

of the delay in the completion of construction and installation

outlined above, and partly due to the commissioning activities

taking longer than initially envisaged.

As noted in respect of the previous SDRC, this still left

sufficient time for the testing and optimisation objectives of

the project to be met on time before the project concluded in

March 2017.

The inclusion in this SDRC of a requirement to demonstrate

production of grid quality gas was not consistent with the

project plan included in the Full Submission to Ofgem.

Therefore, Cadent believes that it was included in error.

Production of BioSNG was undertaken later in the project, but

it could not possibly have been achieved during the

commissioning phase.

Page 31: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 30

9.5 Test & Optimisation

Programme

The testing phase of the

project will be completed

during task 5 in the

2015/2016 year. The

successful delivery of this

criterion will be measured

by the details as shown in

the task 5 work package and

reported in the milestone 5

report.

01/04/2016 As it was framed in the Project Direction of December 2013,

this SDRC incorrectly referred only to the “testing phase of the

project”. It did not include the detailed investigation and

optimisation of the methanation equipment and the PSA

equipment, and so did not cover the full range of experimental

work associated with the project. Cadent believes that this

SDRC should have included all of those activities with a target

date for completion of February 2017, as set out in the

programme for Tasks 5, 6 and 7 in Appendix 7 of the Project

Full Submission.

Testing of the plant commenced in January 2016 with a

number of runs using bottled gas to ensure safe operation and

provide baseline results to compare with later operation on

syngas. The plant performed in line with expectation and the

results of testing the water gas shift and methanation

reactions agreed with theory. The PSA was able to remove

carbon dioxide from the methane / carbon dioxide stream.

Further testing with waste derived syngas also produced good

results. The syngas polishing package worked as expected and

there was no measureable damage to the catalysts from

contaminants in the syngas.

Thermal losses in the demonstration plant were higher than

expected and this initially prevented end to end operation.

This was addressed by the use of thermal blankets to maintain

the operating temperature of the system. By this means,

successful end to end operation of the facility was achieved

and assessed for grid quality.

It was originally envisaged that the demonstration plant would

be used for all of the optimisation tests. However, the scale of

the plant meant that it took a long time to reconfigure it

between tests – it took more than 24 hours for the plant to

cool down after running. The project partners invested in a

smaller off-line test rig to perform optimisation tests, as this

provided far more flexibility while still producing useful results.

The results from the test rig were validated against the

demonstration plant to check that they were valid at larger

scales.

The test and optimisation programme was completed in

February 2017.

All of the work in the test and optimisation programme are

evidenced in run reports which are summarised in Section 3.3

of this report and on the project website.

Page 32: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 31

9.6 Assessment of scale up risks

Once the project testing

programmes have been

completed the scale up risks

to a commercial plant will

be assessed during the

report stage incorporating

all of the learning that has

been achieved during the

project. A separate part of

the final report will include

scale up risks, their effect

and the route to mitigation.

2/2/2017 This activity was accelerated following the agreement to

design and construct a commercial facility. A detailed risk

register covering scale up risks was prepared for the

commercial plant project using learning from this project.

The assessment of scale up risks concluded that there was

minimal risk in the scale up of individual packages because the

design is based on equipment that is already operating at scale

in a large number of facilities. The results from the

demonstration plant combined with computer modelling

mitigated the integration risks to an acceptable level.

This work is evidenced by a detailed report and summarised in

Section 3.4 of the report and on the project website.

9.7 Engineering scheme for a

full scale plant.

The basic design of a full

scale plant will be included

in task 8 and will submitted

within the final report

incorporating the learning

that has been achieved

during the project as

milestone 10 report. The

basic design will include

high level process flow

diagrams, mass and energy

balance, functional

specifications and generic

layout drawings.

31/03/2017 The basic design of a commercial BioSNG plant was carried out

earlier in the project in connection with the submission of the

NIC project proposal for a Commercial Demonstration Plant in

July 2015. Detailed engineering for the first commercial plant

was completed in November 2016 to a much greater level of

detail than was required to meet this SDRC.

In parallel to the design of the commercial plant the project

partners have completed high level designs for BioSNG

facilities producing 315GWh per annum and 665GWh per

annum.

This work is evidenced by a detailed report which is

summarised in Section 3.4 of this report and on the project

website.

Page 33: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 32

9.8 Levelised Cost of Gas for a

full scale plant in the UK

As part of the project we

will be developing the

levelised cost of gas for a

full scale plant which would

be integrated with a

170,000 tonnes per annum

waste capacity Gasplasma®

plant taking the syngas

output and then producing

BioSNG. The objective is to

show that the commercial

scale plant will deliver value

to the gas consumer and will

demonstrate the

commercial viability of the

technical approach of the

project. Furthermore this

information will be used in

the dissemination of the

project information leading

to the development of

follow on commercial scale

projects utilising the

knowledge learned in this

project.

27/2/2017 The levelised cost of gas for a full scale plant was initially

calculated in April 2016, in connection with APP’s submission

to DECC in response to DECC’s consultation on the Renewable

Heat incentive.

A first of a kind 315GWh per annum facility will produce gas

with a levelised cost of £50/MWh, which should be achievable

with Government support for low carbon heat and transport

fuels. An nth of a kind 665MWh per annum plant will produce

gas with a levelised cost of £21/MWh, which is in line with the

expected market value of green gas.

This work is evidenced by a detailed report which is

summarised in Section 3.5 of this report and on the project

website.

Page 34: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 33

9.9 Operation showcase –

dissemination

Part of the project design

will be a visitor’s centre with

a household boiler, a set of

radiators and a showroom

exhibiting the technology of

the project whilst also

showing the potential future

opportunities for the

technology. The plant will

be operated on a regular

basis to demonstrate the

technology to gas network

licensees as well as to

potential owners,

developers and municipal

authorities considering

developing projects utilising

the technology. This will

allow the consortium to

share both the vision of the

opportunity created by

BioSNG from waste, but also

how projects can be

deployed on the network.

This will be accompanied by

a programme of workshops

planned onsite to explain

the features and benefits of

the BioSNG process for

interested stakeholders

including other network

licensees.

03/08/2015 The visitor centre was completed ahead of schedule in

February 2015 and has been visited by over fifty organisations

including all of the gas network licensees, politicians,

Government, academia, industrials, engineering contractors,

waste companies and consumers.

Visitors can physically see the BioSNG plant and monitor the

internal plant functionality via a webcam and display screens.

Feedback on visits has been collected and used to improve the

experience of subsequent tours.

A major stakeholder event was held in November 2016 with

over 100 key individuals from government, regulatory bodies,

industry and the media visiting the demonstration plant. This

event secured very positive media coverage

The success of the dissemination activities is evidenced by

feedback from visitors and the positive media coverage.

Overall the project partners have delivered all of the projects SDRCs. The results from the project have

exceeded the expectations set out in the Full Submission for the project.

5.0 Modifications to the Planned Approach to the Project

Over the three years of the project there have been several modification to the planned approach to the

project in response to external events, new information, and results from testing.

Early in the project it became clear that the cost of the methanation equipment was significantly greater

than budgeted. The results of a competitive tender for this equipment showed that it would cost around

£0.5m more than the budget. The partners selected the supplier offering the best price for this package and

then spent around three months working with them to find ways to reduce costs without compromising

Page 35: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 34

functionality or safety. This led to several changes in the design of the system which successfully brought

the cost back within budget.

In December 2014, the Department for Transport (DfT) launched a competition to provide significant

funding for plants producing fuels, such as BioSNG, from wastes and residues. The project partners entered

the competition and won £11m of grant funding from the DfT for the construction of a commercial BioSNG

plant. Additional funds were then secured from NIC, NIA, and the project partners to allow construction of

the plant to commence. This led to an acceleration of work on assessment of scale up risk and the design

and financial modelling of a commercial plant, meaning these tasks were completed ahead of schedule. In

addition, the test programme was revised to allow testing of the catalysts and operating conditions of the

commercial facility. The development of a commercial facility earlier than expected provided the project

with a fresh focus and increased relevance.

The results of testing in the demonstration facility showed that thermal losses were higher than expected.

Initially this prevented end to end operation of the plant because the outlet temperatures from the first

reactors were insufficient to achieve operational temperatures in in subsequent reactors. An investigation

into the issue showed that this was primarily due to catalysts operating at higher temperatures than

expected, resulting in higher thermal losses, and higher than expected heat losses through the base of the

reactors. The issues were compounded by the small gas flows and large amounts of interconnected

pipework inherent to a demonstration facility. The issue was solved through the use of thermal blankets to

maintain system temperatures which allowed end to end operation to be successfully demonstrated.

These types of modification to the project plan are to be expected in a three year research and

development programme. However, the results of the testing have validated the predictions of the

theoretical models, and the designs and expected financial performance of large scale plants are in line

with those set out at the start of the project. Overall, very few modifications to the planned approach have

been required.

6.0 Financial Performance

The project costs are broadly in line with the budget. The final costs are presented in the following table:

Total

Actual Budget Variance

£ £ £

Labour

1,510,787 1,353,724 (157,063)

Equipment/Consumables

2,387,790 2,273,480 (114,310)

Contractors

249,723 240,677 (9,046)

IT

52,282 59,900 7,618

IPR Costs

0 32,000 32,000

Travel and Expenses

51,557 88,400 36,843

Contingency

202,409 202,409

4,252,139 4,250,590 (1,549)

Page 36: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 35

Expenditure on labour was £157k higher than budget and the cost of contractors was £9k higher primarily

because of the work on the value engineering exercise required to bring the project cost back within

budget. Expenditure on equipment / consumables was £114k higher than expected which was a result of

all equipment costing slightly more than budget.

IT costs were slightly less than budgets. As expected, the project did not produce any registerable

intellectual property and so no IPR costs were incurred. Most meetings with suppliers and stakeholders

took place at the demonstration plant which meant that travel costs were £37k lower than expected.

The contingency of £202k was used to meet the over-expenditure on labour and equipment resulting in the

total cost of the project exceeding the budget by £1k, less than 0.1% of total project budget.

7.0 Business Case

7.1 The Vision for 2050

BioSNG offers lower costs to consumers than other forms of low carbon heat while allowing them to

continue to heat their homes using existing boilers and radiators. For transport, BioSNG is one of the few

cost effective pathways for decarbonising heavy goods transport because battery technologies struggle to

handle heavy loads and production of biodiesel from most biomass is currently very expensive. The

business case for BioSNG is based on an assessment of the overall energy system savings in 2050 resulting

from replacing other forms of low carbon energy by BioSNG.

The financial modelling of a full scale nth of a kind BioSNG plant set out in Section 3.5 shows that it can

produce gas with a cost of £21/MWh, which is slightly lower than the BEIS fossil gas price forecast19 for

2030 onwards. This shows that once the technology is mature it should be commercially attractive and be

deployed widely. In general, other pathways to renewable heat such as heat pumps or heat networks have

levelised costs of heat significantly higher than fossil gas, giving BioSNG a cost advantage.

The overall potential for BioSNG deployment is limited by the availability of sustainable feedstocks. A

review of bioenergy20 by the Climate Change Committee forecasts that the UK will produce 139TWh per

annum of sustainable feedstocks by 2050 and the results from the demonstration project show that this

could produce 100TWh per annum of BioSNG. This could be increased through the use of imported

feedstocks, but there is likely to be significant global demand for these in 2050, which makes availability

hard to forecast. Overall, 100TWh per annum is seen as a realistic target for BioSNG production by 2050.

By 2050 it is possible that a large part of the gas network may have partially or wholly converted to

hydrogen produced by steam methane reforming (SMR) of natural gas combined with carbon capture and

sequestration. The potential of this technology is clearly set out in Northern Gas Network’s H21 report21.

Similarly, hydrogen may become the primary fuel for heavy goods vehicles by 2050 if fuel cell and hydrogen

storage technology develop in line with industry expectations. It is important to understand how BioSNG

fits with the possible conversion of the gas network to hydrogen. One of the insights gained from the

BioSNG demonstration project is the flexibility of BioSNG technology to convert between BioSNG and

19 https://www.gov.uk/government/publications/fossil-fuel-price-assumptions-2016 20https://www.theccc.org.uk/publication/bioenergy-review/ 21http://www.northerngasnetworks.co.uk/wp-content/uploads/2016/07/H21-Report-Interactive-PDF-July-2016.pdf

Page 37: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 36

Biohydrogen production. Biohydrogen can be produced for lower costs than BioSNG and the costs of

converting a BioSNG plant to Biohydrogen production or the production of a BioSNG/Biohydrogen blend

are relatively low. A BioSNG plant can produce a fuel that matches the requirements of the network it is

connected to.

The BioSNG vision for 2050 is a network of BioSNG facilities around the UK injecting 100TWh per annum of

BioSNG or Biohydrogen into the gas grid. This gas will be used for low carbon heat and transport. Its cost

will be similar to fossil gas and significantly cheaper than hydrogen produced by SMR or other low carbon

alternatives.

KPMG have recently produced a report22 comparing the costs of decarbonising heat and transport using a

combination of BioSNG and hydrogen produced by SMR and electrification. This showed that the use of

low carbon gas would be at least £152 billion less expensive than electrification.

To support the NIC bid for the commercial BioSNG facility, National Grid’s independent Energy Strategy and

Policy Group analysed23 the impact of a gradual growth in BioSNG production to 100TWh per annum by

2050 on the Gone Green scenario set out in their Future Energy Scenarios24. This showed that the use of

BioSNG would reduce energy system costs by £3.9 billion per annum and £46.3 billion in total by 2050.

An important benefit of BioSNG or Biohydrogen is the production of a high purity stream of carbon dioxide

that is simple to sequester. As shown in Section 3.6, the combination of BioSNG production with carbon

capture and storage (CCS) provides negative greenhouse gas emissions. These can be used to offset the

residual emissions from sectors that are difficult to decarbonise, such as agriculture and aviation, to ensure

the Climate Change Act targets are met. Combining Biohydrogen production with CCS leads to even higher

GHG savings. The Energy Technologies Institute sets out the benefits of combining bioenergy production

with CCS in a recent report25.

In summary, BioSNG can provide low carbon heat and transport for a similar cost to fossil fuels. This gives

it a significant cost advantage over other solutions resulting in reductions in overall energy system costs

when it is deployed. The overall potential for BioSNG is limited by the availability of sustainable feedstocks

but the UK has sufficient resources for BioSNG to make a significant contribution. Investment in BioSNG

now will be more than paid back by the economic benefits in the future.

7.2 Achieving the Vision

The key barrier to development of BioSNG technology was overcome when funding was secured to

construct the first commercial plant. When the facility starts injecting gas to the grid in 2018 it will provide

a reference facility operating on a full time basis in normal commercial conditions for stakeholders,

developers and funders.

However, there are significant challenges to the development of full scale BioSNG facilities to follow on

from the first commercial plant. The financial models set out in Section 3.5 show that the gas produced by

a first of a kind plant producing 315GWh per annum of BioSNG will have a levelised cost of £50/MWh,

22http://www.energynetworks.org/assets/files/gas/futures/KPMG%20Future%20of%20Gas%20Main%20report%20plus%20appendices%20FINAL.pdf 23 http://www.smarternetworks.org/Files/Commercial_BioSNG_Demonstration_Plant_151208133939.pdf 24 http://fes.nationalgrid.com/fes-document/ 25 http://www.eti.co.uk/insights/the-evidence-for-deploying-bioenergy-with-ccs-beccs-in-the-uk

Page 38: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 37

considerably higher than the current market price of £16MWh. The levelised cost will reduce as the

technology matures but some form of Government support will be required to enable the first full scale

commercial plants to secure funding.

Support for low carbon heat is managed by the Department for Business, Energy and Industrial strategy

(BEIS) and support for low carbon transport fuels is managed by the Department for Transport. The project

partners have engaged with both organisations to explain the benefits of BioSNG and the levels of support

required to commercialise the technology.

BEIS has committed to continue to operate the Renewable Heat Incentive (RHI) until March 2021 and set

out its views on the scheme in a recent consultation response26. The RHI does support BioSNG at present

but the level of support drops significantly for gas production above 40GWh per annum. The proposed

level of support for the first 40GWh is £53.5/MWh, falling to £31.4/MWh for the next 40GWh and

£24.2/MWh thereafter. The project partners had argued no tiering should apply for BioSNG and that

support should be paid at £53.5/MWh for a plant’s entire renewable output. However, BEIS rejected this

argument because in their view there was not currently enough cost evidence to set an appropriate tariff.

The project partners continue to engage with BEIS. The RHI will either be extended beyond 2021 or

replaced with another scheme during the course of this parliament, and this will offer Government the

opportunity to set appropriate levels of support for the use of BioSNG for heat.

Support for low carbon transport fuels is provided under the Renewable Transport Fuel Obligation (RTFO).

The scheme currently supports BioSNG that is used in transport. However, the value of the RTFO is set by

the market which means that its value is volatile and difficult to use to secure funds. The DfT is consulting27

on whether to include BioSNG in a new scheme, referred to as the Development RTFO (DRTFO), which will

give higher levels and more certainty of support. If the DRTFO is introduced as set out in the consultation it

should provide sufficient support for BioSNG plants to secure funding providing the BioSNG is used for

transport. The DfT’s response to the consultation is expected in September 2017.

The key challenge to using the DRTFO to secure funding for the plant is finding sufficient transport off-

takers for BioSNG. Natural gas use in vehicles is growing but as the size of the market is currently quite

small, agreeing long term off-take contracts for transport may be difficult. The project partners are

engaging with transport companies and natural gas filling station operators in order to find off-takers.

The commercialisation of BioSNG technology is dependent on Government policy. If either BEIS or the DfT

decide to put appropriate incentives in place then it should be possible to secure financing for large scale

plants and start the journey to the time when BioSNG is a mature technology and no longer requires

support.

7.3 Changes since the Full Submission

The project has not discovered any significant problems with the approach and technique being trialled.

The results from the tests and experiments carried out in the demonstration plant have shown that it is

technically, commercially, and environmentally feasible to produce BioSNG from waste, and results of the

technical and economic modelling of BioSNG facilities are broadly in line with the models set out in the full

26https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/577024/RHI_Reform_Government_response_FINAL.pdf 27https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/572971/rtfo-consultation-document-2016.pdf

Page 39: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 38

submission.

However, there have been a number of developments that have affected the business case for BioSNG

production. These are:

• The work on the commercial plant has shown the benefits of using BioSNG in heavy goods

transport through delivery of gas to compressed natural gas filling stations via the grid. This

increases the size of the market for BioSNG.

• The project has increased the understanding of the flexibility of BioSNG plants in producing

Biohydrogen and the benefits this may bring if the gas network converts wholly or partially to

hydrogen.

• There is a growing consensus that electrification cannot be the sole solution for the

decarbonisation of heat and that low carbon gases must form part of the solution. This is

supported through publications by Cadent28 and by the Labour Party29.

• As the carbon intensity of the UK’s electricity falls, the GHG benefits of BioSNG improve. This

means that the environmental benefits set out in Section 3.6 of this report are greater than those

set out in the Full Submission. The carbon intensity of UK electricity has fallen from 449kg/MWh in

2013 to 332kg/MWh in 2015 according to Government figures30.

• Changes in the underlying assumptions in the Gone Green Future Energy Scenario (FES) has led to a

reduction in the benefits of adding 100TWh per annum to the models. This has reduced the 2050

benefit calculated by the model from £8.5 billion in 2050 to £3.9 billion. This value is likely to vary

as the FES models are refined but it is clear that BioSNG will always offer a significant benefit over

other routes to decarbonising heat and transport.

• Commercial models now focus on production of BioSNG rather than a combination of BioSNG and

power production. Changes to the support regime for power production make it less attractive

than BioSNG.

• The forecast operating costs for full scale facilities are lower than those set out in the Full

Submission, particularly for large scale plants. This is predominantly due to lower consumable

costs. However, learning from the project and the first commercial plant has led to an increase in

the forecast capital costs for full scale plants. The increase is primarily due to higher design and

mechanical and electrical installation costs than set out in the Full Submission.

• The expected hurdle rates of return for investors are lower than set out in the Full Submission. The

evidence from the first commercial plant will reduce investors’ expected rate of return on

subsequent plants.

• Overall, the expected levelised cost of BioSNG has increased for a first of a kind plant and reduced

for an nth of a kind plant.

• The overall levels of support available under the Renewable Heat Incentive have been reduced and

tiering has been introduced to limit support for plants producing more than 40GWh per annum. In

general, the levels of Government incentives for renewable heat have been reduced significantly.

• Support for renewable transport fuels under the RTFO and the proposed DRTFO has improved

significantly. This offers a new route to securing finance for first of a kind plants.

These have resulted in the new case set out in Sections 7.1 and 7.2.

28 http://cadentgas.com/About-us/The-future-role-of-gas 29 https://alansenergyblog.files.wordpress.com/2016/07/final-the-green-gas-book_96pp_v5.pdf 30https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/577712/DUKES_2016_FINAL.pdf

Page 40: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 39

8.0 Lessons Learnt for Future Innovation Projects

Overall, the project has delivered its objectives on time and within budget without any significant

difficulties. There are a number of lessons to be learnt from the success of the project and from the few

minor problems that were encountered. In general, the project underlined the importance of following

best practice in project management, risk management, communication between partners, and

maintaining good budgetary control. Some lessons specific to the project are set out below.

The success of the project was partially due to good preparatory work. A detailed design for the

demonstration facility was produced by Innovation Funding Incentive project IFI79. This gave the project

partners the opportunity and resources to develop the right solution and make the major strategic

decisions before commencing the NIC project. In addition, the design project established good

relationships and clear lines of communication between the project partners. Splitting some of the

development work into a separate project allowed the NIC demonstration project to be more focused and

reduced the risk of significant delays.

However, the cost of the detailed design produced in the IFI project exceeded the available budget and the

value engineering exercise required to solve this issue resulted in a three month delay. In future projects it

will be important to allow sufficient time in the programme to revisit the design after the initial results from

procurement have been collated.

Throughout the project the partners focussed on delivering the Successful Delivery Reward Criteria (SDRCs)

and measured project performance against them. However, some of the SDRCs were not aligned with the

project plan or set targets that were not appropriate. For future projects the SDRCs will be reviewed

carefully to ensure they set out the key objectives of the project and provide a good benchmark for

performance.

These principles have been applied to subsequent NIC projects in which the project partners have

participated.

9.0 Project Replication

The outcomes from the project are the outline designs for BioSNG facilities producing 315GWh per annum

and 665GWh per annum of gas. The demonstration plant has validated the technical feasibility of these

designs and the technical and commercial modelling has validated their environmental and financial

viability.

The facilities would inject low carbon gas into the grid, providing a cost effective route to decarbonising

heat and transport. Details on the performance of the facilities are set out in Sections 3.4, 3.5 and 3.6.

Section 3.5 sets out the costs of building and operating a BioSNG facility in detail.

The key documents listed in Section 11 provide sufficient information to start the development of a BioSNG

facility and provide detailed evidence of the viability of the technology. They cover all of the intellectual

property arising from the project and are available, on request, to other GB DNOs.

The project partners would welcome any discussions on the commercialisation of the BioSNG technology.

Page 41: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 40

10.0 Planned Implementation

The project has moved the technology readiness level (TRL) of BioSNG to 6 – technology demonstrated in a

relevant environment. The first commercial BioSNG plant is under construction and will enter operation in

2018 – moving the TRL to 7. More details of the first commercial facility are provided in Section 3.7.

A feature of the BioSNG technology is that it contributes to the decarbonisation of the gas network with no

requirement for modifications to the network. The processes and equipment developed for the injection of

gas from anaerobic digestion can be used for BioSNG facilities. The gas produced by BioSNG facilities will

comply with current network entry agreements. The key challenge is meeting the GS(M)R 0.1% limit for

hydrogen : in the future a relaxation of this limit to around 0.5% may be sought. The typical outputs from

BioSNG plants will be suitable for injection into the high and medium pressure networks.

Following the successful operation of the first commercial plant it is likely that large scale plants will be

developed. As explained in Section 7.2, the key challenge to deploying the technology is the availability of

suitable Government incentives. However, as more plants are deployed and the perceived risk of the

technology reduces, the required level of support will reduce and eventually the technology will be viable

without any incentives. After this point it is likely that widespread deployment will follow.

The project partners will continue to lobby Government to introduce appropriate incentives for BioSNG

production.

The production of Biohydrogen uses very similar equipment to BioSNG and it is possible for BioSNG plants

to be converted to Biohydrogen production or designed with the flexibility to produce either BioSNG or

Biohydrogen. The results from this project have increased the understanding of Biohydrogen production

but more work is required to develop Biohydrogen.

11.0 Dissemination

Dissemination of the results and learning from the project and sharing information with other distribution

network operators is essential to realise the objective of accelerating the development of commercial

BioSNG facilities.

The project partners carried out the following dissemination activities:

• Establishing a BioSNG brand and communication plan.

• Creating a web portal to communicate the benefits of BioSNG and the project learning.

• Attending and speaking at technical and commercial conferences.

• Publishing articles and press releases in mainstream and social media.

• Setting up a visitor showcase at the pilot plant and hosting visits.

• Holding workshops to discuss the BioSNG technologies.

Dissemination activities have continued throughout the project, from conclusion of the design and plant

construction to communication of results. There have been successes with key stakeholders in the

technology, such as the visit by a minister from the Department for Transport, and in communication with

the general public, such as the article describing the project in the Guardian newspaper.

Early in the development of the project a workshop was held to determine the branding that would be used

for communications. This identified the key groups with an interest in the project, the target geographical

Page 42: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 41

regions, and the channels that would be used to reach those groups. It was agreed that it was important to

develop an independent brand for the project to allow results to be disseminated without being influenced

by any preconceptions associated with individual project partners.

The Go Green Gas brand was adopted for the project, and logos and graphics were developed to support

the brand. Go Green Gas was seen as striking the right balance between accessibility for the general public

and giving a succinct summary of the BioSNG technology for Government and businesses.

The website fulfils the following functions:

• Communication of the environmental, economic and social benefits of BioSNG.

• Explanation of the BioSNG technology.

• News from the project such as results of experiments, attendance at events and visits to the plant.

• Providing access to project documentation such as Project Progress Reports.

• Providing a route for people to ask questions about the project or register interest in the plant.

Feedback on the website has been very positive and it has been extremely useful in providing detailed

information on the project. Total traffic to the website in the last 12 months is 5,176 sessions. On average,

visitors visited 2.31 pages per visit.

Conferences and exhibitions provide a valuable channel for communicating project goals and achievements

to business, Government, and academia. Each of the project partners has presented the project at a large

number of conferences and communicated project results through stands at industry exhibitions.

Page 43: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 42

The partners have presented at more than fifteen events including:

• Utility Week Live

• Biomethane Day

• World Energy to Waste Summit

• World Gas Conference

• Low Carbon Networks and Innovation Conference

• Supergen Bioenergy Hub

• London Energy from Waste Conference

Feedback from the conferences was positive and resulted in a large number of enquiries about BioSNG

which resulted in a number of visits to the plant.

The mainstream media presents an opportunity to communicate the key messages about the technology.

The trade press provides a good channel for communication to industry and the general press, such as

newspapers and television, are used to tell the BioSNG story to the general public. Social media is used to

create discussions on the technology within networks with an interest in low carbon technology.

Articles and news stories on BioSNG have been published or broadcast through a large number of outlets including:

Page 44: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 43

• BBC Radio and TV and ITV, • Daily Mail, Daily Telegraph and the Guardian, • CIWM Journal, • Gas International • Resource, Lets Recycle, Materials Recovery Weekly, and Recycling and Waste World,

All of these reports have been positive, focusing on the environmental benefits of the technology. A visitor centre has been built within the facility to provide an opportunity for visitors to gain an insight into the BioSNG process and to communicate BioSNG benefits. Organised, pre-arranged visits are offered, with presentations on the process, a tour of the facility, and literature. Visitors can physically see the BioSNG plant and monitor the internal plant functionality via a webcam and display screens. Feedback on visits is collected and used to improve the experience of future tours.

A large number of organisations and individuals have visited the plant including:

• Partners: Cadent, including David Parkin, Safety & Network Strategy Director, and Chris

Train, Chief Executive Officer

• Gas industry: Northern Gas Networks, Wales & West, SGN, ENA, Calor Gas, EUA

• Government agencies: Ofgem, DECC, BEIS, Innovation UK, Environment Agency,

Department for Transport

• Politicians, including Ed Miliband, then Leader of the Opposition, and Andrew Jones, the

Transport Minister

• Academia: University College London, Imperial College London

• Potential suppliers and industrials: BOC, Air Liquide, Air Products, Green Biologics

• Consultants: Arthur D Little, Enzygo, WRC, FWA, Ricardo, E4Tech

• Contractors: Amec Foster Wheeler, Clariant, Thyssen Krupp, Metso

• Waste companies: Veolia, Hills, Public Power Solutions, Viridor

• End users: Howard Tenens, British Airways, Peel Environmental, Waste2Tricity

More detailed workshops were held with the distribution network operators to give them the opportunity

to learn more about the BioSNG technology and ask any questions.

A major stakeholder event was held in November 2016 with over a hundred key individuals from

government, regulatory bodies, industry, and the media. The event provided an opportunity to

disseminate the key findings from this programme. It also featured the start of practical work on the

commercial plant and an announcement from Cadent regarding their investment to complete the funding

package for that project. In addition to hearing presentations from senior personnel from Cadent and the

Page 45: BioSNG Demonstration Plant - gogreengasgogreengas.com/.../11/BioSNG-170223-1-Project-Close-Out-Report.pdf · Page 2 1.0 Project Background BioSNG addresses the issue of decarbonising

Page 44

Department for Transport, most attendees also took the opportunity to take a tour of the pilot facility. The

media follow up was very positive, including a very favourable piece in the Daily Telegraph.

The project partners continue to welcome visitors to visit the demonstration plant and the commercial

plant while it is under construction.

12.0 Key Documents

The following project documents are publicly available.

Document Date of Publication Description

Full Submission 3rd December 2013 Final Network Innovation Competition full

submission to Ofgem.

First Project Progress Report 19th June 2014 First project progress report.

Second Project Progress Report 11th February 2015 Second project progress report.

Third Project Progress Report 5th June 2015 Third project progress report.

Fourth Project Progress Report 5th November 2015 Fourth project progress report.

Fifth Project Progress Report 11th June 2016 Fifth project progress report.

Sixth Project Progress Report 11th December 2016 Sixth project progress report.

Summary of Commercial Results 31st March 2017 Summary of commercial models of full scale

plants.

Summary of Plant Design 31st March 2017 Summary of full scale BioSNG plant design and

assessment of scale up risks.

Summary of Technical Results 31st March 2017 Summary of results of test and experiments on the

demonstration plant.

13.0 Contact Details

If you have any questions on the project or would like access to any project documents please contact:

David Pickering

BioSNG Project Manager

Cadent

07867 537360

[email protected]