Page 1: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

April 19-21, 2016

Blaine Pritchett, P.E.PCGP Project DirectorWilliams Company

Page 2: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

2© 2012 The Williams Companies, Inc. All rights reserved.

Page 3: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

3© 2012 The Williams Companies, Inc. All rights reserved.

Presentation Topics

Project ScopePipeline Precedent AgreementsLand Classification and Acquisition ProgressPermitsTheoretical Project TimelineEPC TenderProject OppositionProject Support

Page 4: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

4© 2012 The Williams Companies, Inc. All rights reserved.

Williams Northwest Pipeline in Oregon1956/1963 year built750 miles of pipe12”-30” pipeline size7 compressor stations50 MLV’s

Page 5: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

5© 2012 The Williams Companies, Inc. All rights reserved.

PCGP Fact Sheet

$1.74B+ private investment232-mile 36-inch diameter pipelineProvides up to 1,060,000 Dth/d of firm transportation1,480 psig Maximum Allowable Operating Pressure223 miles of Class 1 location; rural population density1 compressor station with 61,500 of installed HP2 receipt and 2 delivery meter stations

17 mainline valves; 3 intermediate launcher/receivers50-foot wide permanent easement + 45-foot

construction easement

Page 6: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

6© 2012 The Williams Companies, Inc. All rights reserved.

Pipeline Precedent Agreements Executed

817,354 Dth/d of firm service contracted77% of pipeline capacity subscribedMacquarie Energy LLC agreement for 215,000 Dth/d firm serviceAvista Corp. agreement for 10,000 Dth/d firm serviceJordan Cover Energy Project agreement for 592,354 Dth/d firm serviceReserves capacity for JERA, ITOCHU, and JCEP

sales

Open Season2016Opportunity to subscribe to the remaining capacity

Page 7: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

7© 2012 The Williams Companies, Inc. All rights reserved.

Land Ownership Classification

Land ClassificationDescription Miles % of RoutePublic Lands 75 32%

Private Lands 96 41%

Timber Company Lands 61 27%

TOTAL 232 100%

Page 8: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

8© 2012 The Williams Companies, Inc. All rights reserved.

Timberlands Classification

Timber ClassificationDescription MilesOld Growth(100+ yr old timber stands)

41

Mid-Seral(40-100 yr old stands)

44

Reproduction and Clear Cut(0-40 yr olds stands)

61

TOTAL 146

47% of the remaining land classified as agricultural, range land, and off shore

Page 9: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

9© 2012 The Williams Companies, Inc. All rights reserved.

Land Rights Acquisition Progress

Land Rights AcquisitionDescription Landowners1 Land Rights AcquiredPublic Lands 3 0

Private Lands 264 66

Timber Company Lands 23 2

TOTAL 290 68

Limited land acquisition program pre FID

90% of route landowners granted survey permission

Limited condemnation proceedings

1. Permanent right of way, construction right of way, and temporary extra work areas

Page 10: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

10© 2012 The Williams Companies, Inc. All rights reserved.

PermitsEnvironmental Permits

7 Federal Permit Agencies8 State Permit Agencies4 County Permit Agencies

Non-Environmental Permits183 crossing permits: roads, railroads, transmission lines, etc.

Critical Path Environmental PermitsFERC CertificateBureau of Land Management Record of Decision and Land Grant

Permits Received to DateFederal and State - 0County - 4 (Conditional Use Permits)

Page 11: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

11© 2012 The Williams Companies, Inc. All rights reserved.

Potential Pipeline Project Timeline

PermitsLand RightsFinal Investment DecisionEngineeringProcurementConstructionCommissioningFirst Gas

Months MonthsTaskYear 1 Year 2Months Months

Year 3Months

Year 5Year 4

Page 12: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

12© 2012 The Williams Companies, Inc. All rights reserved.

Solicit Tender from 5 EPC Contractors April 20164 months for EPC Contractors to prepare and submit TenderAward EPC Contract by the end of 2016

2016 EPC Construction Strategy

Page 13: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

13© 2012 The Williams Companies, Inc. All rights reserved.

Current OppositionProtest• Pacific Connector land office, Medford, Oregon on 8/7/2015 and 9/30/2015• Will not impede on any citizens constitutional right of freedom of speech or to peaceably

assemble.

Page 14: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

ture Oppositionmples of Direct ons:ree Sittingripodsleeping Dragons

Page 15: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

David Ludlum, Executive Director, West Slope Colorado Oil and Gas AssociationPat McCown, Williams Parachute Plant Manager of OperationsRockies Producers who submitted support letters to FERCPublic Officials and Organizations who submitted support letters to FERCAll project proponents are encouraged to submit their expression of Project support on the FERC web siteFERC Docket Number CP13-492-000

and CP13-483-000

ANK YOU

Page 16: Blaine Pritchett, P.E. PCGP Project Director Williams … · Jordan Cover Energy Project agreement for 592,354 Dth/d firm service Reserves capacity for JERA, ITOCHU, and JCEP sales

Questions