Construction QC/QA Representative Samples 1
Quality Control / Quality Assurance
Obtaining a representative sample
Senior/GraduateHMA Course
Construction QC/QA Representative Samples 2
Sample Size
• Mixture Component Variability
• Confidence Level
• Error or Bias From True Value
• Effect on Performance
Construction QC/QA Representative Samples 3
Frequency of Sampling/Testing
• Mixture Production Variability
• Effect on Performance
• Previous History
• Compliance With Specifications
Construction QC/QA Representative Samples 4
SAMPLING
• Preliminary Investigation of the Potential
Source
• Control of Product at the Source of Supply
• Control of Operations at the Site of Use
• Acceptance or Rejection of Material
Construction QC/QA Representative Samples 5
SIZE AND NUMBER OFSAMPLES
D 3665 Random Sampling of Construction Materials
E 105 Probability Sampling of Materials
E 122 Choice of Sample Size to Estimate the Average Quality of a Lot or Process
E 141 Acceptance of Evidence Based on the Result of Probability of Sampling
Construction QC/QA Representative Samples 6
SAMPLE SIZE
Nominal
Maximum Size Minimum Mass, lbs.
No. 8 4
No. 4 4
3/8 8
1/2 12
3/4 16
1 20
Construction QC/QA Representative Samples 7
Types of samples to be taken
• Aggregate
• Asphalt binder
• HMA mixture
Construction QC/QA Representative Samples 8
Sampling at Point of Shipment Delivery
• By bleeder valve or tap in transfer line or at back of truck
– During unloading, center 1/3 of load
Safety equipment is a must
Construction QC/QA Representative Samples 9
• Draw and discard at least a gallon of binder to clear line
Sampling Truck
Construction QC/QA Representative Samples 10
• Immediately take at least a quart sample
Sampling Truck
Construction QC/QA Representative Samples 11
Protection and Preservation• Take care not to contaminate containers• Fill and immediately seal
– Don’t immerse in solvent
Construction QC/QA Representative Samples 12
Protection and Preservation
• Store so that emulsions are protected from freezing
• Avoid transferring from one container to another
• Retain samples not tested (point of delivery)
• Take precautions to avoid contamination during
sampling, handling, shipping and storage
Construction QC/QA Representative Samples 13
Sampling at Plant Tank
• Same sampling directions apply to sampling the plant tank
Construction QC/QA Representative Samples 14
Sampling Bituminous Paving Mixtures
• Accurate test results depend upon a uniform, representative sample being collected.
Construction QC/QA Representative Samples 15
Sample Location
• At the plant– From the truck – most common– From plant discharge– From cold feed (gradation only)
• At the roadway– Behind the paver (11 states)– From the windrow
Construction QC/QA Representative Samples 16
Which is the best location?
WHY?
Construction QC/QA Representative Samples 17
Truck sampling
Construction QC/QA Representative Samples 18
Loose HMA
RTSD
Construction QC/QA Representative Samples 19
Construction QC/QA Representative Samples 20
Sampling – Roadway
• Approximately equal increments• Make vertical face with shovel
750 mm (30 in.) parallel to centerline• Pull material back 300 mm (12 in.)
Construction QC/QA Representative Samples 21
Sampling – Roadway (continued)
• Place scoop on pavement next to vertical face and fill scoop
Obtain material to full depth• Close lid and remove scoop when full• Repeat to obtain required sample size
Construction QC/QA Representative Samples 22
Sampling from the roadway
Construction QC/QA Representative Samples 23
Sampling – Paver
• Obtain samples at end of auger using square shovel
• Place shovel in front of auger extension with blade flat on surface
• Allow front face of auger stream to cover shovel
Construction QC/QA Representative Samples 24
Sampling – Paver (continued)
• Remove shovel before auger reaches it Lift shovel vertically
• Repeat until sample size reached
Construction QC/QA Representative Samples 25
Sampling from Paver
WHAT ARE THE PROBLEMS WITH
THIS?
Construction QC/QA Representative Samples 26
“Sampling The Windrow”
Solution
Construction QC/QA Representative Samples 27
Sampling Loose HMA?
See any problems with this?
Construction QC/QA Representative Samples 28
Effect of Sampling Location on Gradation Variability
0
1
2
3
4
5
6
3/4"
1/2"
3/8" #4 #8 #16
#30
#50
#100
#200
Sieve Size
Sta
nd
ard
Dev
iati
on
s
Coldfeeds (n=45)
Loose HMA (n=45)
Cores (n=46)
Construction QC/QA Representative Samples 29
Sample Splitting
Construction QC/QA Representative Samples 30
Sample Splitting
Construction QC/QA Representative Samples 31
Segregated Samples from the Same Mix
Coarse Portion
3.79% Asphalt Binder
Fine Portion
5.21% Asphalt Binder
Construction QC/QA Representative Samples 32