Construction QC/QA Representative Samp les 1 Quality Control / Quality Assurance Obtaining a representative sample Senior/Graduate HMA Course

Upload: chris-yarnell

Post on 27-Jun-2015

150 views

Category:

Technology


3 download

TRANSCRIPT

Page 1: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 1

Quality Control / Quality Assurance

Obtaining a representative sample

Senior/GraduateHMA Course

Page 2: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 2

Sample Size

• Mixture Component Variability

• Confidence Level

• Error or Bias From True Value

• Effect on Performance

Page 3: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 3

Frequency of Sampling/Testing

• Mixture Production Variability

• Effect on Performance

• Previous History

• Compliance With Specifications

Page 4: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 4

SAMPLING

• Preliminary Investigation of the Potential

Source

• Control of Product at the Source of Supply

• Control of Operations at the Site of Use

• Acceptance or Rejection of Material

Page 5: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 5

SIZE AND NUMBER OFSAMPLES

D 3665 Random Sampling of Construction Materials

E 105 Probability Sampling of Materials

E 122 Choice of Sample Size to Estimate the Average Quality of a Lot or Process

E 141 Acceptance of Evidence Based on the Result of Probability of Sampling

Page 6: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 6

SAMPLE SIZE

Nominal

Maximum Size Minimum Mass, lbs.

No. 8 4

No. 4 4

3/8 8

1/2 12

3/4 16

1 20

Page 7: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 7

Types of samples to be taken

• Aggregate

• Asphalt binder

• HMA mixture

Page 8: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 8

Sampling at Point of Shipment Delivery

• By bleeder valve or tap in transfer line or at back of truck

– During unloading, center 1/3 of load

Safety equipment is a must

Page 9: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 9

• Draw and discard at least a gallon of binder to clear line

Sampling Truck

Page 10: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 10

• Immediately take at least a quart sample

Sampling Truck

Page 11: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 11

Protection and Preservation• Take care not to contaminate containers• Fill and immediately seal

– Don’t immerse in solvent

Page 12: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 12

Protection and Preservation

• Store so that emulsions are protected from freezing

• Avoid transferring from one container to another

• Retain samples not tested (point of delivery)

• Take precautions to avoid contamination during

sampling, handling, shipping and storage

Page 13: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 13

Sampling at Plant Tank

• Same sampling directions apply to sampling the plant tank

Page 14: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 14

Sampling Bituminous Paving Mixtures

• Accurate test results depend upon a uniform, representative sample being collected.

Page 15: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 15

Sample Location

• At the plant– From the truck – most common– From plant discharge– From cold feed (gradation only)

• At the roadway– Behind the paver (11 states)– From the windrow

Page 16: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 16

Which is the best location?

WHY?

Page 17: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 17

Truck sampling

Page 18: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 18

Loose HMA

RTSD

Page 19: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 19

Page 20: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 20

Sampling – Roadway

• Approximately equal increments• Make vertical face with shovel

750 mm (30 in.) parallel to centerline• Pull material back 300 mm (12 in.)

Page 21: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 21

Sampling – Roadway (continued)

• Place scoop on pavement next to vertical face and fill scoop

Obtain material to full depth• Close lid and remove scoop when full• Repeat to obtain required sample size

Page 22: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 22

Sampling from the roadway

Page 23: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 23

Sampling – Paver

• Obtain samples at end of auger using square shovel

• Place shovel in front of auger extension with blade flat on surface

• Allow front face of auger stream to cover shovel

Page 24: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 24

Sampling – Paver (continued)

• Remove shovel before auger reaches it Lift shovel vertically

• Repeat until sample size reached

Page 25: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 25

Sampling from Paver

WHAT ARE THE PROBLEMS WITH

THIS?

Page 26: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 26

“Sampling The Windrow”

Solution

Page 27: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 27

Sampling Loose HMA?

See any problems with this?

Page 28: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 28

Effect of Sampling Location on Gradation Variability

0

1

2

3

4

5

6

3/4"

1/2"

3/8" #4 #8 #16

#30

#50

#100

#200

Sieve Size

Sta

nd

ard

Dev

iati

on

s

Coldfeeds (n=45)

Loose HMA (n=45)

Cores (n=46)

Page 29: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 29

Sample Splitting

Page 30: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 30

Sample Splitting

Page 31: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 31

Segregated Samples from the Same Mix

Coarse Portion

3.79% Asphalt Binder

Fine Portion

5.21% Asphalt Binder

Page 32: Block 24   Obtaining Samples 13

Construction QC/QA Representative Samples 32

Questions?