FEASIBILITY STUDY South Montgomery Community School Corporation
June 13, 2016
Board Meeting Presentation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Schedule/Major Milestones
2015
November Data Collection
December Board Meeting- Update
2016
January Elementary School visitations
February JH/HS and other facility visitations
March Board Meeting- Update
April 12 New Market ES Community Meeting
20 Ladoga ES Community Meeting
26 Walnut ES Community Meeting
May Finance review
June 13 Board Meeting- Summary Presentation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Feasibility Study Content
Evaluate School Facilities for the following:
* Site/Circulation
* Safety/Security
* Building Envelope
* Building Environment
* Building Interior/Systems
***Consider 6th Grade Location
Consider District-wide needs
Identify Associated Costs
Review Project Options
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
All Elementary Schools
Building Interior/Systems
1. Replace HVAC system
2. Selective technology
improvements
3. Finishes improvements
4. Replace chalkboards
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Site/Circulation
1. Dual stripe for bus
or for handicap
parking (not
simultaneous)
2. Improve security
camera coverage
3. Selective playground
equipment
replacement to
improve accessibility
4. Replace sewage
treatment plant
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Building Envelope
1. Replace exterior doors
and windows
2. Replace main 1995 roof
3. Create larger, enclosed
entry vestibule for
security and wind
screen for students that
are transferring between
buses
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Building Interior/Systems
1. Expanded secure entry
vestibule
2. Improve office visibility/
function
3. Renovate main restrooms
4. Repurpose music room
5. Combine music/ band
6. Would gain four classrooms
with 6th grade relocation
7. Consider potential for life
skills classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Site/Circulation
1. Improve control/flow at
drop-off/pick-up
2. Resolve basement
flooding that occurs
during large rainfall
events
3. Expand sidewalk for bus
loading
4. Selective playground
equipment replacement/
to improve accessibility
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Building Envelope
1. Replace exterior doors
and windows
2. Replace 1998 shingle
and 2009 gym roofs
3. Add vestibule to main
entry
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Building Interior/Systems 1. Provide new secure entry
vestibule
2. Relocate administrative offices to
larger/more functional location
3. Repurpose existing office for small
group/other
4. Improve restroom ADA
compliance
5. Improve flexibility for team
collaboration
6. Selective kitchen equipment
replacement
7. Replace seating handrails/stage
curtain
8. Would gain one classroom with
6th grade relocation
* Generally improve acoustics in all
classrooms
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Site/Circulation
1. Create new bus loading
lot
2. Change existing bus
loading to parking
3. Improve turn radii for
drop-off/pick-up
4. Selective playground
equipment replacement/
improve accessibility
5. Remove portable unit
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Building Envelope
1. Replace 1995 metal
roof and 1999
shingle roof
2. Resolve fascia/leak
problems
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Building Interior/Systems
1. Expanded secure
vestibule
2. Expanded secure office
waiting
3. Replace bleachers
4. Add second set of
restrooms
5. Improve serving line
flow/ replace seating
6. Renovate staff lounge
7. Add story areas
8. Would gain three
classrooms with 6th
grade relocation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont Junior High
Building Interior/Systems
1. Secure corridor near cafeteria
2. Repurpose Corp. Admin. Space
to accommodate 6th Grade
3. Repurpose lower level storage
for JH wrestling
4. Add time-out room at SE
classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
Building Interior/Systems
1. Replace door hardware as
needed/incorporate
electronic access
2. New digital cameras
3. Replace 1996 HS and 1990
JH gym roofs
4. Remodel and possibly add
to, Career and Technical
Education 1. Advanced manufacturing
2. Engineering and Technology
3. Fire Science
4. Law Enforcement
5. Culinary Arts
5. Remodel Woods Lab,
Ag./Hort. , and associated
spaces
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
District Needs
Administrative Offices
1. New freestanding facility
at JH/HS Campus
Transportation Center
1. New facility located at
JH/HS Campus
Administrative Offices
1. Provide fiber optic
connections from three
elementary schools
JH/HS Campus
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Cost- updated
Site/Circ. Safety/Sec. Building Env. Building Int. Building Sys. Total
High School 5,696,500 95,000 487,200 $2,679,500 $8,958,200
Junior High School 45,000 281,350 326,350
Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826
Ladoga ES $350,000 520,956 673,692 860,736 1,292,306 3,697,690
New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673
Administrative Offices 1,476,000
Transportation Center 3,731,250
District-wide Needs 926,640
Construction Costs 6,554,000 1,076,176 3,524,097 5,952,351 4,688,115 $27,928,629
Soft Costs $6,982,157
Total Project Costs $34,910,787
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to current and
future improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options- New Market Elementary School
Building Envelope
1. Replace 1995 metal
roof and 1999
shingle roof
2. Resolve fascia/leak
problems
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either schedule work to be completed over summer break, or provide an
alternative program location while work is being completed
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options- Ladoga Elementary School
Building Interior/Systems 1. Provide new secure entry
vestibule
2. Relocate administrative offices to
larger/more functional location
3. Repurpose existing office for small
group/other
4. Improve restroom ADA
compliance
5. Improve flexibility for team
collaboration
6. Selective kitchen equipment
replacement
7. Replace seating handrails/stage
curtain
8. Would gain one classroom with
6th grade relocation
* Generally improve acoustics in all
classrooms
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options- Southmont High School
Building Interior/Systems
1. Replace door hardware as
needed/incorporate
electronic access
2. New digital cameras
3. Replace 1996 HS and 1990
JH gym roofs
4. Remodel and possibly add
to, Career and Technical
Education 1. Advanced manufacturing
2. Engineering and Technology
3. Fire Science
4. Law Enforcement
5. Culinary Arts
5. Remodel Woods Lab,
Ag./Hort. , and associated
spaces
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location while work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
Group similar kinds of work
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options
Phasing Considerations
Protect future improvements
Reroof work will eliminate leaks and the accompanying damage to building
interiors
Consider timing of work to avoid conflicts with school functions
Either plan work to be completed over summer break, or provide an
alternative location wile work is being completed
Avoid re-doing work following completion
Include all work in a room or rooms to avoid returning and potentially
damaging improvements
Group similar kinds of work
A poor grouping would be HVAC replacement and pavement repair
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options- New Market Elementary School
Site/Circulation
1. Create new bus loading
lot
2. Change existing bus
loading to parking
3. Selective playground
equipment replacement
to improve accessibility
4. Remove portable unit
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Options- Schedule
Much of the work must take advantage of summer months
Summer is the busiest construction period
The most favorable pricing (bids) is received in January-March in
advance of the following summer
That will require design work to commence no later than
September-October
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Cost
Site/ Circulation
Safety/ Security
Building Envelop
Building Interior
Building Systems
Total
High School 5,696,500 95,000 487,200 $2,679,500 $8,958,200
Junior High School 45,000 281,350 326,350
Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826
Ladoga ES $350,000 520,956 673,692 860,736 1,292,306 3,697,690
New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673
Administrative Offices 1,476,000
Transportation Center 3,731,250
District-wide Needs 926,640
Construction Costs 6,554,000 1,076,176 3,524,097 5,952,351 4,688,115 $27,928,629
Soft Costs $6,982,157
Total Project Costs $34,910,787
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
High School - Project Cost Breakdown
Site/Circulation
PE/Athletics
Baseball complex $ 925,000
Softball complex $ 625,000
BB/SB Support Building $ 756,250
Soccer complex $ 210,000
Practice Football complex $ 180,000
Stadium synthetic turf $ 850,000
Stadium team building $ 1,375,000
Parking
Soccer parking $ 240,000
Football parking $ 187,500
BB/SB parking $ 123,750
Drive
New North Drive $ 224,000
SUBTOTAL $ 5,696,500
Safety/Security
Replace hardware as needed $ 70,000
New digital cameras $ 25,000
SUBTOTAL $ 95,000
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
High School - Project Cost Breakdown
Building Envelope
Reroof Main Gym $ 268,800
Reroof Junior High Gym $ 218,400
SUBTOTAL $ 487,200
Building Interior Spaces Career/Tech Ed. Improvements
Remodeling $ 795,000
New Construction $ 1,269,000
Woods Lab Improvement $ 80,500
Ag/Horticulture Improvements
Lab/classrooms $ 280,000
Greenhouses $ 150,000
Culinary Arts Lab Finishes Remodeling
$ 105,000
SUBTOTAL $ 2,679,500
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Junior High - Project Cost Breakdown
Safety/Security
Install new doors/gates to secure corridor Near cafeteria $ 30,000
Digital cameras $ 15,000
SUBTOTAL $ 45,000
Building Interior Spaces Repurpose Corp. Admin. for 6th grade wing
$ 130,000
Repurpose lower level storage for JH wrestling
$ 150,000
Add Time-Out Room at SE classroom $ 1,350
SUBTOTAL $ 281,350
Site/Circulation
Included with High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School- Project Cost Breakdown
Site/Circulation New sewage treatment plant $ 250,000
Playground equipment Improvements
$ 50,000
SUBTOTAL $ 300,000
Safety/Security New digital camera system $ 102,066
SUBTOTAL $ 102,066
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School- Project Cost Breakdown
Building Envelope Reroof entire building $ 612,396
Replace exterior windows/doors $ 153,000
Provide new entry vestibule $ 228,000
SUBTOTAL $ 993,396
Building Interior Spaces
Remodel office $ 180,000
Repurpose music room $ 58,500
Remodel finishes $ 765,495
Install new marker boards $ 20,000
Renovate restrooms (north group) $ 40,000
SUBTOTAL $ 1,063,995
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School- Project Cost Breakdown
Building Systems HVAC systems replacement $ 1,224,792
Replace PA system $ 41,626
Add phones in all rooms $ 46,950
SUBTOTAL $ 1,313,369
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School- Project Cost Breakdown
Site/Circulation
Taylor Street Improvements $ 200,000
Drainage Improvements $ 75,000
Playground equip. Improvements $ 50,000
Increase west sidewalk width $ 25,000
SUBTOTAL $ 350,000
Safety/Security
New secure main entrance/admin. $ 435,000
New Digital camera system $ 85,956
SUBTOTAL $ 520,956
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School- Project Cost Breakdown
Building Envelope
Reroof entire building $ 601,692
Replace exterior windows/doors $ 72,000
SUBTOTAL $ 673,692
Building Interior Spaces
Repurpose existing office area $ 90,000
Improve classroom acoustics $ 20,000
Repurpose music room $ 20,000
Remodel finishes $ 515,736
Install new marker boards $ 20,000
Remodel group restrooms $ 60,000
Selective kitchen equip. replacement $ 75,000
Gym railings/curtain replacement $ 60,000
SUBTOTAL $ 860,736
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School- Project Cost Breakdown
Building Systems HVAC systems replacement $ 1,031,472
Provide new sprinkler system $ 171,912
Replace PA system $ 34,382
Add phones in all rooms $ 39,540
Improve wireless coverage $ 15,000
SUBTOTAL $ 1,292,306
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School- Project Cost Breakdown
Site/Circulation
New bus drop-off/pick-up lot $ 112,500
Repurpose existing drop-off pick-up lot $ 20,000 Playground equip. improvements $ 50,000 Provide additional walks at playgrounds $ 25,000
SUBTOTAL $ 207,500
Safety/Security Expand secure vestibule and office entrance $ 152,000
New digital camera system $ 161,154
SUBTOTAL $ 313,154
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School- Project Cost Breakdown
Building Envelope
Reroof entire building $ 1,208,655
Resolve soffit/venting issues $ 161,154
SUBTOTAL $ 1,369,809
Building Interior Spaces
Add second set of group restrooms $ 135,000
Update staff lounge $ 20,000
Replace gym bleachers $ 75,000
Remodel finishes $ 805,770
Install new marker boards $ 20,000
Add stepped story areas in 2 Kindergarten rooms
$ 11,000
SUBTOTAL $ 1,066,770
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School- Project Cost Breakdown
Building Systems
HVAC systems replacement $ 1,933,848
Replace PA system $ 64,462
Add phones in all rooms $ 74,131
Replace gym sound system $ 10,000
HVAC
SUBTOTAL $ 2,082,440