Page 1: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

Board of Directors MeetingFebruary 26, 2013

Standards, Registration and Certification Report

Page 2: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

2

STANDARDS

Board of Directors Meeting February 26, 2013

Page 3: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

3

Approve Reliability Standards Committee 2013 Officers (VOTE)

● Chair – Brenda Hampton, EFH Luminant Brenda was Vice Chair/Acting Chair of RSC in 2012. Brenda is currently Senior Project Manager,

Regulatory Policy for Energy Future Holdings (EFH), where she is involved in a variety of regulatory activities for Luminant and other EFH entities.

● Vice Chair – Andrew Gallo, Austin Energy Andrew was Chair of NSRS in 2012. He currently serves as Director, Reliability

Compliance for Austin Energy, where he oversees compliance efforts for FERC, NERC and ERCOT reliability requirements.

Board of Directors Meeting February 26, 2013

Page 4: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

4

NERC Standards Review Subcommittee Officers for 2012

● Chair – Lisa Martin, Austin Energy Lisa is the Transmission Service Compliance

Program Manager for Austin Energy. She works to ensure compliance with non-CIP NERC Standards relating to transmission operations.

● Vice Chair – Daniela Hammons, CenterPoint Energy Daniela is the Manager of Policy and Compliance for

CenterPoint Energy Houston Electric, LLC., where she oversees implementation of the company’s internal compliance program and other activities related to regulatory policy and compliance.

Board of Directors Meeting February 26, 2013

Page 5: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

5

Regional Standard – Status and Path Forward

● Ballot conducted February 1-15 – PASSED Ballot passed with 80% segment-weighted

affirmative vote (67% required to pass) 22 Entities Voted (plus 12 abstentions)

• Abstentions were from generation companies and their affiliated registered entities

● RSC will Approve Ballot Results

● Texas RE Board Approval (April 2013)

● Submit to NERC/FERC (~May 2013)

Board of Directors Meeting February 26, 2013

Page 6: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

6

Regional Standard BAL-001-TRE-1

● Primary Frequency Response in the ERCOT Region Requires ERCOT to maintain the Interconnection

Frequency Response at an acceptable level Requires Generator Owners to apply specified

Governor settings and to provide Frequency Response from individual units

Provides objective performance metrics to assess compliance by individual generators

● A Field Trial was conducted to demonstrate and test the individual unit Frequency Response requirements and measures

Board of Directors Meeting February 26, 2013

Page 7: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

7

Other Standards Activities

● The Texas RE NERC Standards Review Subcommittee (NSRS) continues to meet every few weeks to discuss issues of interest to our Region.

● Texas RE regularly votes in NERC standards ballots, based on evaluation of posted drafts by Texas RE experts. We file comments as needed to explain negative votes and

to provide our perspective.

● Texas RE staff actively participates in NERC Standards Committee and related activities. NERC Standard Quality Review teams Paragraph 81 Working Group Cold Weather Event Working Group

Board of Directors Meeting February 26, 2013

Page 8: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

8

Current NERC Standards Activities

● There are currently a number of high-profile NERC projects: Major Revision of NERC’s Standards Development

Procedures and Practices Addressing recommendations from the 2011 Cold

Weather Event Report Bulk Electric System Definition – Phase 2

● Major Projects Completed in 2012 Paragraph 81 – retire requirements that do not

support reliability BES Definition CIP Version 5

Board of Directors Meeting February 26, 2013

Page 9: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

9

REGISTRATION & CERTIFICATION

Board of Directors Meeting February 26, 2013

Page 10: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

10

Work Completed in 2012

● Completed TOP Entity Certifications Denton Municipal Electric TMPA Reviewed Several Control Center Moves

● 54 Registration Actions Registrations, Retirements, Revisions Also processed annual CFR addendums and

revisions

Board of Directors Meeting February 26, 2013

Page 11: Board of Directors Meeting February 26, 2013 Standards, Registration and Certification Report

11

2013 Projects

● CREZ TOP Entity Certifications Wind Energy Transmission Texas (WETT) Sharyland Utilities

● “Bulk Electric System” (BES) Definition Implementation Administer Exception Process Registration issues

● Monitor Proposed CFR Revisions