![Page 1: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/1.jpg)
FEASIBILITY STUDY South Montgomery Community School Corporation
January 11, 2016
Board Work Session
![Page 2: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/2.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Outline
Alignment with 2015-2016 Board
Goals- discussion
Initial Facility Review Findings
Process Schedule
![Page 3: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/3.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Student Achievement
Programming & Facilities
Communication
Governance & Fiscal Stability
![Page 4: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/4.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Student Achievement
Improve Test Scores and
Graduation Rates
Culture of use/integration of
technology
Plan for the use of personal
technology devices
![Page 5: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/5.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Programming & Facilities
Junior/Senior High School
Site Master Plan
CTE Programs
Infrastructure improvements
Technology needs
![Page 6: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/6.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Programming & Facilities
Elementary Schools
Site Master Plan
Infrastructure improvements
Technology needs
![Page 7: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/7.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Programming & Facilities
Grade Reconfiguration
![Page 8: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/8.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Communication
Maintain communications that
is timely and informative to
stakeholders and promotes
the school corporation
Use [electronic media] in this
effort
![Page 9: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/9.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Alignment with 2015-2016 Board Goals- discussion
Governance & Fiscal Stability
Explore cost savings strategies
within the current corporation
footprint
Ensure the long-term viability
of the corporation through
sound, strategic and
responsible financial panning
![Page 10: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/10.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
Ladoga Elementary School
Grades K-6
224 Enrollment
42,978 Square Feet
Construction Plans
1976
Renovations/Additions
1996
Renovations
![Page 11: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/11.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Site
Vehicular congestion
Playground access
Drainage
![Page 12: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/12.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Building
Roof needs replaced
Secure entrance with curb appeal
Interior finishes need replaced
HVAC system needs replaced
Improve electrical power and
technology access/reliability
![Page 13: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/13.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
Walnut Elementary School
Grades K-6
181 Enrollment
51,033 Square Feet
Construction Plans
1989
Renovation/Addition
2008
Renovation/Addition
![Page 14: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/14.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Site
Replace on-site sewage
treatment plant or provide
connection to nearby
municipal facility
![Page 15: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/15.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Building
Roof repairs needed
Secure entrance with curb appeal
Interior finishes need updated
HVAC system needs replaced
Improve technology
access/reliability
![Page 16: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/16.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
New Market Elementary School
Grades K-6
500 Enrollment
80,577 Square Feet
Construction Plans
1989
Additions/Renovation
![Page 17: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/17.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Site
Vehicular congestion
Remove portable
![Page 18: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/18.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Building
Roof needs replaced
Improve entrance security
Interior finishes need
replaced
Consider additional rest
room facilities
HVAC system needs
replaced
Improve electrical power and
technology
access/reliability
![Page 19: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/19.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
Waveland School Facility
Estimate $258,000 for total
demolition
Partial demolition, with
gym/support spaces
remaining will cost more
![Page 20: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/20.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
Junior/Senior High School
Grades 7-8/9-12
277/519 Enrollment
282,184 Square Feet
Construction Plans
1969
Renovation/Addition 1989
Renovation/Addition 2004
![Page 21: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/21.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Junior/Senior High School
Site
Master Plan
Expanded athletic facilities
Soccer
Baseball
Softball
Football-practice
Parking
Support facilities
Future district support facilities
![Page 22: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/22.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Junior/Senior High School
Building
Security/zoning
CTE entrance and facilities
Collaborative learning spaces
Specific infrastructure improvements
Roof repairs/replacement
Plumbing
Elevator(s)
JH bleachers
Doors/hardware
![Page 23: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/23.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Initial Facility Review Findings
District Support Facilities
District-wide needs
WAN fiber improvements
New transportation
support building
Additional areas for
evaluation will be
identified in this process
![Page 24: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/24.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Process going forward
Develop conceptual plans to illustrate proposed renovations/new
construction:
Junior/Senior High School
Campus Master Plan
Floor plans
Elementary School
Floor plans
![Page 25: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/25.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Process
Community Outreach
Presentation at each School site
![Page 26: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/26.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Process going forward
Document proposed
improvements that may become
part of a District-wide facilities
initiative
Correlate improvements to
available funding
Prioritize project improvements
over a phased timeline
![Page 27: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/27.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Process going forward
Final Report
Executive Summary
Documented findings as
noted above
Recommended Option(s):
Timeline
Cost
Funding
![Page 28: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/28.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Schedule/Major Milestones
2015 November Kick-off Meeting
Data Collection begins
Building Visitations
Board Meeting- Study Overview
2016 January Board Work Session
February Board Review- initial concepts
March Community Meetings
April Draft Study Review
May Board Meeting- Final Study Presentation
![Page 29: Board Work Session FEASIBILITY STUDY...SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Schedule/Major Milestones 2015 November Kick-off Meeting Data Collection begins Building Visitations](https://reader031.vdocuments.net/reader031/viewer/2022011914/5fbd820936c04f24bf63d807/html5/thumbnails/29.jpg)
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Feasibility Study