Page 1: Body of Work2

Network setup for your company

Page 2: Body of Work2

Final ObjectivesHigh Speed ConnectionsFast Network Capability SecurityPotential for GrowthE-mail Sever

Page 3: Body of Work2

Management WorkstationsDesktops LaptopsManufacturer: Dell DellModel: Vostro 330 Vostro

3555Processor: Intel Pentium Dual Core SameHard Drive: 500 GB 500 GBMemory: 4 GB 6 GBOS: Windows 7 Professional 64 bit Same

Page 4: Body of Work2

Security, Marketing, & Sales OfficeWorkstationsManufacturer: DellModel: Vostro 460 Processor: Intel Core i7Hard Drive: 1500 GBMemory: 16 GBOS: Windows 7 Professional 64 bit

Page 5: Body of Work2

Human Resources, Accounting, Administration Staff, & Training Room Workstations

Manufacturer: DellModel: OptiPlex 390Processor: Intel Core i5Hard Drive: 1000 GBMemory: 8 GBOS: Windows 7 Professional 64 bit

Page 6: Body of Work2

ServerManufacturer: DellModel: PowerEdge M910Processor: Two, Eight core Intel XeonHard Drive: 2 TBMemory: 512 GB up to 1066MHzOS: Windows Sever 08 R2 SP1

Page 7: Body of Work2

Color Printers Manufacturer: DellModel: 2150cn Color Laser PrinterPages/minute: 25Capable of Printing: 8 ½ x 11 Pages

Page 8: Body of Work2

Black and White PrintersManufacturer: Dell Model: 2350dn Mono Laser PrinterPages/Minute:40Capable of Printing: 8 ½ x 11 Pages

Page 9: Body of Work2

Switches and Routers

Page 10: Body of Work2

Network InformationIP Address 10.10.0.0CIDR 18Mask 255.255.192.0Subnets 1024Host 16,382

Subnets First Host Last Host BroadcastNetwork A

10.10.0.0 10.10.0.1 10.10.63.254 10.10.63.255

Network B10.10.8.0 10.10.8.1 10.10.8.254 10.10.8.255

Network C10.10.16.0 10.10.16.1 10.10.16.254 10.10.16.255

Network D10.10.24.0 10.10.24.1 10.10.24.254 10.10.24.255

Network F10.10.32.0 10.10.32.1 10.10.32.254 10.10.32.255

Page 11: Body of Work2

Network Expansion for VOIPIP Addres 172.192.0.0CIDR 24Mask 255.255.255.0Subnets 2Host 254

Subnets First Host Last Host BroadcastIP Range

172.192.0.0 172.192.0.1 172.192.0.254 172.192.0.255

Page 12: Body of Work2

Security

Page 13: Body of Work2

Service Contract

Page 14: Body of Work2

Cost Analysis Breakdown

Item Price Per Unit # of Units TotalRouter 129.99$ 1 129.99$ Firewall 449.99$ 1 449.99$ Access Point 178.99$ 3 536.97$ Patch Panel 62.99$ 6 377.94$ Cables 134.29$ 30(Rolls) 4,028.70$ Patch Cable 1.64$ 225 369.00$ Cable End Pieces 35.99$ 3 107.97$ Wall Panels 3.69$ 225 830.25$

0.99$ 225 222.75$ Switches 2,999.00$ 3 8,997.00$

Server 3,554.00$ 1 3,554.00$ Workstations 1,030.00$ 90 92,700.00$ Laptops 1,125.00$ 5 5,625.00$ Printers 259.99$ 4 1,024.00$

239.99$ 2 478.00$ Network Rack 238.99$ 1 238.99$

Labor 2.00$ 30,000 ' 60,000.00$ Markup 5% Necessary Hardware 6,942.89$

Service Contract 1,000.00$ /Month

Grand Total186,613.44$

Required Equipment

Notes: These prices are subject to change.

Page 15: Body of Work2

Item Price Per Unit # of Units TotalRouter 129.99$ 1 129.99$ Firewall 449.99$ 1 449.99$ Access Point 178.99$ 3 536.97$ Patch Panel 62.99$ 6 377.94$ Cables 134.29$ 30(Rolls) 4,028.70$ Patch Cable 1.64$ 225 369.00$ Cable End Pieces 35.99$ 3 107.97$ Wall Panels 3.69$ 225 830.25$

0.99$ 225 222.75$ Switches 2,999.00$ 3 8,997.00$

Server 3,554.00$ 1 3,554.00$ Workstations 1,030.00$ 90 92,700.00$ Laptops 1,125.00$ 5 5,625.00$ Printers 259.99$ 4 1,024.00$

239.99$ 2 478.00$ Network Rack 238.99$ 1 238.99$

Labor 2.00$ 30,000 ' 60,000.00$ Markup 5% Necessary Hardware 6,942.89$

Service Contract 1,000.00$ /Month

Grand Total186,613.44$

Required Equipment

Notes: These prices are subject to change.

Page 16: Body of Work2

# of Cables Length in Inches Patch Panel to Ceiling Ceiling to Workstation WAO RunTrunk Runs

20 1118 12040 815 12040 575 12040 348 12020 234 12020 107620 99

Workstation Runs4 810 120 484 630 120 484 450 120 484 270 120 484 90 120 48

12 156 120 4812 336 120 4812 517 120 4812 696 120 4812 876 120 4812 1157 120 4812 1338 120 4812 1518 120 4812 1699 120 4812 1878 120 48

2 1836 1201 1740 120

Second Floor Cabling Needs

Second Floor CableNeeds

# of CablesLength in InchesPatch Panel to CeilingCeiling to WorkstationWAO RunTotal Run in InchesTotal Run in Feet

Page 17: Body of Work2

Length of Cable # of Rolls Needed Cost per Thousand FeetBasement 1305First Floor 2023Second Floor 26363Total Cable 29691 30 134.29 4028.7

# CostPatch Cables 225 1.64 369

Total Cost 4397.7

Total Cable and Cost

Total Cable and Cost

Page 18: Body of Work2

Deliverables:

Analyze of needs, ordering all receiving equipment

Installation of devices (Hardware/Drops) training

Training all configuration of devicesTesting all training methods, guidelines.Evaluation of completed work.

Page 19: Body of Work2

Timeline:We will analyze the needs of your company,

defining the needs of hardware & software. The amount of cabling required, we will order the hardware & receive it within 1-2 days.

Once all hardware is received, we will start installing & training on-site techs. Our outside contractor will provide installing Drop(s).

We will then continue training your tech & start configuring the hardware.

Testing the network with on-site techs.On-site techs will be train on how to utilized

network.

Page 20: Body of Work2

Project Time Line

ID Task Name Duration Start Finish

1 install drops 3 days Sat 8/6/11 Tue 8/9/11

2 receive devices 2 days Mon 8/8/11 Tue 8/9/11

3 start installing devices 8 days Mon 8/8/11 Wed 8/17/11

4 train it admin on network 14 days Tue 8/9/11 Fri 8/26/11

5 configure devices 12 days? Tue 8/9/11 Wed 8/24/11

6 test 5 days? Fri 8/19/11 Thu 8/25/11

7 hand over network 1 day? Fri 8/26/11 Fri 8/26/11

F S S M T W T FJul 31, '11 Aug 7, '11