Installed capacity – 2 x 544 perkins genset
Back-up for pb108, (7.2MW)
Peak demand - 2.6 MW (grid total)
![Page 2: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/2.jpg)
Manuk Mangkaw DPPManuk Mangkaw DPPTawi-tawiTawi-tawi
Installed capacity – 1 x 163 kw perkins
Peak demand – 80 kw
6 hours operation
![Page 3: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/3.jpg)
Sacol DPPSacol DPPSacol Island, Zamboanga CitySacol Island, Zamboanga City
Installed capacity – 1 x 163 kw perkins
Peak demand – 155kw
6 hours operation
Plant turn over to NPC SPUG from city government of Zamboanga City
![Page 4: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/4.jpg)
Sibutu DppSibutu DppTawi-tawi ProvinceTawi-tawi Province
Installed capacity – 2 x 163 kw perkins
Peak demand – 240 kw
6 hours operation
![Page 5: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/5.jpg)
West Simunul DPPWest Simunul DPPTawi-tawi ProvinceTawi-tawi Province
Installed capacity – 2 x 54 kw visa, 1 x 260 kw perkins
Peak demand – 220 kw
6 hours operation
![Page 6: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/6.jpg)
TANDUBANAK DPPTaunguh, Sibutu Island
Unit no. 1, 1 x 280 kw Cummins GensetsUnit no. 2, 1 x 160 kw Cummins Gensets
6 hours operation, peak load 80 kw
![Page 7: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/7.jpg)
Sitangkay DPPSitangkay DPPTawi-tawi ProvinceTawi-tawi Province
Installed capacity – 2 x 280 kw cummins
Started commercial operation – August 22, 2009
![Page 8: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/8.jpg)
Basilan DPPBasilan DPPIsabela City, Basilan ProvinceIsabela City, Basilan Province
Installed capacity – 1 x 1224 kw CKD, 1 x 448 kw CKD
Back up units for PB 119, 7.2 MW
Rented units 2 x 1000kw, 1 x 600 kw caterpillar units are stationed here.
Peak system demand – 6.200 MW
![Page 9: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/9.jpg)
Siasi DppSiasi DppSiasi, SuluSiasi, Sulu
Installed capacity – 2 x 500 kw MAN, 2 x 560kw perkins, 2 x 260 kw perkins
Peak demand – 680 kw
20 hours operation
![Page 10: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/10.jpg)
Luuk DPPLuuk DPPCamp Andres, Luuk, SuluCamp Andres, Luuk, Sulu
Installed capacity – 1 x 175 kw cat, 1 x 54 kw visa
Peak demand – 225 kw
6 hours operation
![Page 11: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/11.jpg)
Manuk Mangkaw DPPManuk Mangkaw DPPEast Simunul, Tawi-tawiEast Simunul, Tawi-tawi
Installed capacity – 1 x 163 kw perkins
Peak demand – 80 kw
6 hours operation
![Page 12: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/12.jpg)
Jolo DPPJolo DPPJolo, SuluJolo, Sulu
Installed capacity – 3 x 1.8 MW daihatsu
Peak demand – 4.622 MW
24 hours operation
Rented back up 1 x 1000kw, 1 x 1,500kw caterpillar
![Page 13: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/13.jpg)
Mapun DPPMapun DPPCagayan de Tawi-tawiCagayan de Tawi-tawi
Installed capacity – 2 x 260 kw perkins, 1 x 500 kw MAN
Peak demand – 350 kw
10 hours operation
![Page 14: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/14.jpg)
Sibutu DPPSibutu DPPSibutu island, Tawi-tawiSibutu island, Tawi-tawi
Installed capacity – 2 x 163 kw perkins
Peak demand – 240 kw
6 hours operation
![Page 15: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/15.jpg)
Balimbing DPPPanglima Sugala, Bato-bato, Tawi-tawi
Installed capacity : 2 x 163 kw Perkins, 2 x 150 kw Cummins
8 hours operation, 5:00pm to 1:00am
![Page 16: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/16.jpg)
Power Barge 108Power Barge 108Bongao, Tawi-tawiBongao, Tawi-tawi
Installed capacity – 4 x 1.8 MW daihatsu (7.2MW)
Peak demand – 2.600 kw
24 hours operation
Backed up by land based plant
![Page 17: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/17.jpg)
Power Barge 119Power Barge 119Isabela City, BasilanIsabela City, Basilan
Installed capacity – 4 x 1.8 MW daihatsu (7.2MW)
Peak demand – 6.200 MW
24 hours operation
Backed up by land based plant and rented units
![Page 18: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/18.jpg)
TANDUBAS DPPTANDUBAS DPP
![Page 19: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/19.jpg)
SPUG MINDANAOSPUG MINDANAO
• Eastern Mindanao Area
Total system capacity – 9. 690 KW
![Page 20: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/20.jpg)
Palimbang DPPPalimbang DPPsultan kudaratsultan kudarat
•Installed capacity – 1 x 54 kw visa
Peak demand – 48 kw
6 hours operation
![Page 21: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/21.jpg)
Dinagat DPP (new PH)Dinagat DPP (new PH)San Jose, Dinagat IslandSan Jose, Dinagat Island
Installed capacity – 5 x 275kw cumper, 2 x 260kw perkins, 1 x 364kw
1 x 163kw perkins
Peak demand – 1.220kw
18 hours operation
![Page 22: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/22.jpg)
Loreto DPPLoreto DPPDinagat IslandDinagat Island
Installed capacity – 2 x 220 kw ckd, 1 x 500 kw MAN
Peak demand – 290 kw
8 hours operation
![Page 23: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/23.jpg)
Talicud DppTalicud DppDavao del NorteDavao del Norte
Installed capacity – 2 x 163 kw perkins
Peak demand – 160 kw
10 hours operation
![Page 24: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/24.jpg)
Kalamansig DPPKalamansig DPPSultan KudaratSultan Kudarat
Installed capacity – 5 x 260 kw perkins, 1 x 220 kw ckd,
Peak demand – 1.800 kw
24 hours operation, backed up by PB 111
![Page 25: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/25.jpg)
Abad Santos DPPAbad Santos DPPCaburan, Davao del SurCaburan, Davao del Sur
Installed capacity – 1 x 163kw perkins, 1 x 260 kw perkins
Peak demand – 210 kw
10 hours operation
![Page 26: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/26.jpg)
Balut DPPBalut DPPSarangani, Davao del SurSarangani, Davao del Sur
Installed capacity – 2 x 163 kw perkins
Peak demand – 120 kw
8 hours operation
![Page 27: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/27.jpg)
Hikdop DPPHikdop DPPHikdop, Surigao del NorteHikdop, Surigao del Norte
Installed capacity – 2 x 163 kw perkins
Peak demand -95 kw
7 hours operation
![Page 28: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/28.jpg)
Power Barge 111Power Barge 111Lebak, Sultan KudaratLebak, Sultan Kudarat
Installed capacity – 4 x 560 kw perkins
Peak demand – grid total 1.800 kw
24 hours operation
Back up power of land based plant.
![Page 29: Bongao DPP Bongao, Tawi-tawi Installed capacity – 2 x 544 perkins genset Back-up for pb108, (7.2MW) Peak demand - 2.6 MW (grid total)](https://reader035.vdocuments.net/reader035/viewer/2022062321/56649f1c5503460f94c31d09/html5/thumbnails/29.jpg)
Ninoy Aquino DPPNinoy Aquino DPPSultan KudaratSultan Kudarat
Installed capacity – 2 x 163 kw perkins
Peak demand – 230 kw
12 hours operation