Page 1: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

Booster Main Bending Magnet Test in SM18

Page 2: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

Why• The energy upgrade of the PS

Booster main bending magnet requires endurance tests at high current (≈12 kA) and high ramp rates

• High currents and high ramp rates require powerful converters

• The cluster A of the SM18 test benches is actually equipped with a 14kA/61V capacity power converter that fulfills the requirements

Page 3: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

How

• The magnet will be installed in-between the A1 and A2 benches, close to the platform (action: TE/MSC-TF)

• The main water-cooled current leads will be disconnected from A1 CFB leads (action: TE/MSC-TF)

Page 4: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

How (2)• Extra cables will be used to

connect those leads to the magnet lying beneath (action: TE/MSC-MNC)

• Cooling water for the magnet will be drawn from the main water supply distribution of the test facility and connected to a pressure booster in order to reached the required ΔP (action: CERN water support team under request of TE/MSC-MNC)

IN OUT

Page 5: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

Powering

• RM.A converter will be switched to 18kV mode, in order to get the required 61V/14kA capacity (action: CERN electrical support under request of TE/EPC-MPC)

• The usual interlocks from test benches will be removed from the converter (action: TE/EPC-MPC)

• The only left interlocks will be the magnet water flow and the coils temperature, connected in series and brought directly to the converter (action: TE/MSC-MNC)

• The regulation loop parameters will be adapted to the magnet and cables impedance (action: TE/EPC-MPC)

Page 6: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

Current cycles control

• The usual power application, running on Sunmta32, will be used through the gateway (action: TE/MSC-TF)

• Possibility of creating any required current cycle within the limits of the PC range (action: TE/MSC-TF following TE/MSC-MNC specifications )

• Usual cold benches interlocks will be shorted in order to use the software (action: TE/MSC-TF)

Page 7: Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)

Some pictures of the « beast »