bored piling method statement
DESCRIPTION
MSTRANSCRIPT
BORED PILING METHOD STATEMENTRED PILING METHOD
BORED PILING METHOD STATEMENT.
WORK PROCEDURE
PROJECT:Ref No. FOUN/04
PAGE 1 OF 2
SECTION:
FOUNDATIONSDATE OF ISSUE
Dec 2012
SUBJECT:
BORED PILING
BY:
QA/QC ENGINEER
APPROVED BY:
QEHS MANAGER
ACTIONVERIFY
1.SCOPE
The scope of this procedure covers the control of installation of Bored Cast-in-Situ Concrete piles executed by a sub-contractor.
2.PROCEDURE
.1Method Statement:
A method statement shall be submitted by the piling Sub-contractor for approval which shall include:
i)Construction procedure.
ii)Pile design with calculations.
iii)Testing procedure.
iv)Documentation to be maintained during the execution of work.
v)Mix design for concrete.
vi)Specification for reinforcement steel and bentonite clay.
vii)Any other information required by the specification.
.2Construction Programme:
The sub-contractor shall submit a programme for approval based on the Contract Programme. The subcontractor shall also indicate the mobilisation time of plant, equipment, materials and work force.
.3Piling Sequence:
Approval of piling sequence will be given prior to commencement of piling by the Subcontractor.
.4Setting-Out:
HEE will execute pre-piling setting out and offer for cross-checking by Subcontractors Surveyor and Consultants Representative.Project
Manager
Sub-contractor
Project
Manager
Subcon/
FCC SurveyorMethod
Statement
Approved
Construction Programme
Approval
Field Book
WORK PROCEDURE
PROJECT:Ref No. FOUN/04
PAGE 2 OF 2
SECTION:
FOUNDATIONSDATE OF ISSUE
Dec 2012
SUBJECT:
BY:
QA/QC ENGINEER
BORED PILING
APPROVED BY:
QHSE MANAGER
ACTIONVERIFY
.5Source Certificates:
Reinforcement steel and Bentonite test certificates if required shall be obtained from the Subcontractor and, submitted for approval by the Consultant.
.6Concrete Cube Testing:
Cube results will be assessed and retained. The cube test reports shall be clearly identified with the location of pour by reference to the checksheet.
.7Testing of Piles:
The Subcontractor shall carry out a load test and integrity test as specified in the Contract.
.8Inspection of Work/Checksheet:
The work shall be inspected using the attached checksheet as Appendix FOUN/04/A which shall be completed as verification and record of compliance.
.9Non-Conformity:
Non-conforming workmanship shall be notified to the Subcontractor as Appendix 7/3/6/A and corrective action taken in accordance with good working practice and Consultants approval.
Project Engineer
Project Engineer/
Labtech.
Subcon.
QA/QC
QA/QC
Source certificate
Test result, FOUN/04/A
Pile testing record
Checksheet
Non-
Conformity Report
PROJECT:SITE NO.:
CHECK SHEET FOR BORED PILINGSheet No.
SUBCONTRACTOR: FATAYERJI
SECTION OF WORK ____________________________LOCATION _________________
STAGEITEMChecked
byDATE
PREPARATION1. Subcontractors method statement approved.PE
2. Materials approved by the consultant.PE
3. Cross-check location of Pile.SU
APPROVAL TO PROCEEDQA/QC
INSTALLATION4. Check borehole to be filled with Bentonite
slurry at all times.GF
5. Check cleaning of bottom of borehole.GF
6. Check reinforcement cage.SE
7. Check minimum cover while lowering cage into the borehole.GF
8. Check slump of concrete.Lab
9. Check cut-off level + location.SU
APPROVAL TO PROCEED WITH PILE CAP.CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer, GF General Foreman, SU Surveyor, Lab Laboratory Technician