borough of mountain lakes department of public …lakes... · 2016. 12. 19. · 2002, the building...
TRANSCRIPT
BOROUGH OF MOUNTAIN LAKES DEPARTMENT OF PUBLIC WORKS GARAGE
ENERGY ASSESSMENT
for
NEW JERSEY BUREAU OF PUBLIC UTILITIES
BOROUGH OF MOUNTAIN LAKES DEPARTMENT OF PUBLIC WORKS GARAGE
ENERGY ASSESSMENT
for
NEW JERSEY BUREAU OF PUBLIC UTILITIES
CHA PROJECT NO. 21795
OCTOBER 2010
Prepared by:
CLOUGH HARBOUR & ASSOCIATES LLP
6 Campus Drive Parsippany, NJ 07054
(973) 538-2120
TABLE OF CONTENTS Page
1.0 INTRODUCTION & BACKGROUND....……………….……...…...…............1
2.0 EXECUTIVE SUMMARY………………....…………..…………..…………...2
3.0 EXISTING CONDITIONS……………………….…………....……………..…4
3.1 Building General 3.2 Utility Usage 3.3 HVAC Systems 3.4 Lighting/Electrical Systems 3.5 Control Systems 3.6 Plumbing Systems
4.0 ENERGY CONSERVATION MEASURES……………….…………………..8 4.1 ECM-1 Lighting Fixture Modifications 4.2 ECM-2 Lighting Control Modifications 4.3 ECM-3 Replace Heating Unit Serving Garage Area 4.4 ECM-4 Provide Radiant Heating in Garage and Setpoint Modification 4.5 ECM-5 Replace Single Pane Windows with Double Pane Windows 4.6 ECM-6 Insulate Hot Water Piping
5.0 PROJECT INCENTIVES……………………………………...………………13 5.1 Incentives Overview 5.2 Building Incentives 6.0 ALTERNATIVE ENERGY SCREENING EVALUATION………..………16
6.1 Geothermal 6.2 Solar 6.3 Wind 6.4 Combined Heat and Power Generation (CHP) 6.5 Biomass Power Generation 6.6 Demand Response Curtailment
7.0 EPA PORTFOLIO MANAGER………………………………………………22 8.0 CONCLUSIONS & RECOMMENDATIONS.…………………….…..…..23
APPENDICES A Utility Usage Analysis
B HVAC Equipment List C ECM-1 Lighting Fixture Modifications D ECM-2 Lighting Control Modifications E ECM-3 Replace Heating Unit Serving Garage Area F ECM-4 Provide Radiant Heating in Garage and Setpoint Modification G ECM-5 Replace Single Pane Windows with Double Pane Windows H ECM-6 Insulate Hot Water Piping I Photovoltaic (PV) Rooftop Solar Power Generation J Solar Thermal Domestic Hot Water Plant K Wind L EPA Portfolio Manager M Carrier Hourly Analysis Program Base Building Data N Site Aerial Image
New Jersey BPU - Energy Audits
Page 1 of 23
1.0 INTRODUCTION & BACKGROUND This report summarizes the energy audit performed at the Borough of Mountain Lakes Department of Public Works Garage, located on Pocono Road in Mountain Lakes, NJ. Originally built in 1955 and expanded in 2002, the building is a 10,300 square feet, single story, high bay structure. The building houses the Department of Public Works garage and maintenance facility. New Jersey’s Clean Energy Program, funded by the New Jersey Board of Public Utilities, supports energy efficiency and sustainability for Municipal and Local Government Energy Audits. Through the support of a utility trust fund, New Jersey is able to assist state and local authorities in reducing energy consumption while increasing comfort. This report covers the energy audit for the Borough of Mountain Lakes Department of Public Works Garage.
New Jersey BPU - Energy Audits
Page 2 of 23
2.0 EXECUTIVE SUMMARY This report details the results of the energy audit performed at the Borough of Mountain Lakes Department of Public Works Garage, located on Pocono Road in Mountain Lakes, NJ. The 10,300 square foot, single story, high bay structure houses garage space, offices, lunchroom/conference room, locker room, restroom, and auxiliary spaces. The following areas were evaluated for energy conservation measures:
! Lighting upgrades with occupancy sensors ! Office area HVAC upgrades ! Replacing existing air handling unit in garage ! Provide radiant heating in garage to lower average maintained temperature throughout space ! Replace single pane windows with double pane windows ! Insulation of domestic hot water piping
Various potential Energy Conservation Measures (ECMs) were identified for the above categories. Measures which are recommended for implementation have a payback of 10 years or less. This threshold is considered a viable return on investment. Potential annual savings of $3,530 for the recommended ECMs may be realized with a payback of 7.1 years. These savings represent approximately 16% reduction in the resent electric and natural gas costs. The ECMs identified in this report will allow for the building to reduce its energy usage and if pursued has the opportunity to qualify for the New Jersey SmartStart Buildings Program. A summary of the costs, savings, and paybacks for the recommended ECMs follows:
ECM-1 Lighting Fixture Modifications
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
5,300 - 5,000 0 1,000 1.8 870 5.3 4.4 * There is a $30 per fixture incentive for replacing T12 fixtures with T8 fixtures available through the New Jersey Smart Start program’s Prescriptive Lighting Application for this ECM.
ECM-2 Lighting Control Modifications (Proposed Fixtures)
Budgetary Annual Utility Savings ROI Potential Payback Payback
Cost (with Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total Incentive)
$ kW kWh Therms $ $ Years Years
550 0 1,900 0 110 3.0 140 5.0 3.7 * Incentive shown is per the New Jersey Smart Start Program, 2010 Lighting Controls Application. Incentive is based on the use of seven wall-mounted occupancy sensors.
New Jersey BPU - Energy Audits
Page 3 of 23
ECM-4 Provide Radiant Heating in Garage and Setpoint Modification (92% efficient H&V Unit)
Budgetary Annual Utility Savings Potential Payback Payback
Cost* Incentive** (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
19,200 - 900 900 1,300 0 NA 14.8 NA * Budgetary Cost includes cost to replace existing Garage H&V unit with 92% efficient unit. ** There is no incentive available through the New Jersey Smart Start program for this ECM.
ECM-6 Insulate Hot Water Piping
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Natural Gas Electricity Total ROI
$ Therms kWh $ $ Years Years
40 14 0 20 6.5 NA 2 NA * There is no incentive available through the New Jersey Smart Start program for this ECM.
New Jersey BPU - Energy Audits
Page 4 of 23
3.0 EXISTING CONDITIONS 3.1 Building General The Borough of Mountain Lakes Department of Public Works Garage, constructed in 1955 and expanded in 2002, is a 10,300 square foot, single story, high bay structure. The building houses garage space, offices, lunchroom/conference room, locker room, restroom, and auxiliary spaces. The Mountain Lakes Department of Public Works is a sector of the Borough of Mountain Lakes government that operates 50 hours per week throughout the year. Operating hours are 7:00 a.m. to 4:00 p.m. Monday through Friday and 7:00 a.m. through 2:00 p.m. on Saturday. The garage facility is primarily used for vehicle storage and maintenance, as well as miscellaneous equipment storage. The original building was constructed in 1955, the expansion was constructed in 2002, and the building’s exterior shell is in good condition. The exterior walls of the original building are 12” CMU with poured insulation within the block cores. In 2002 a 1,000 ft2 office addition was constructed that adjoins the existing structure. At the time of the office addition a 700 ft2 woodshop was also constructed. The exterior walls of the office addition have the same construction as the original building’s walls, but with a stone veneer on the exterior. The exterior walls of the woodshop have the same construction as the original building’s walls. The attic is composed of “A” frame wood trusses and joists with 6” batt insulation at the lower cord of the truss and gypsum board for the ceiling attached to the bottom cord of the joists. The roof is made up of asphalt shingles on 5/8” plywood sheathing. The floor slab is on grade. Windows are located around the building. Window types include single pane, single pane with storm windows, and double pane windows. There are two entries to the building. One is the single pane, glass entry door and the other is an insulated metal door. The garage doors are insulated metal with vision glass, approximately 12’ high by 11’ wide. All doors appear to have good weather stripping. In addition to the main building, the site also has an open salt shed and a 4 bay storage garage (pole barn), half of which is heated. These out buildings appear to be in good shape. 3.2 Utility Usage Utilities include electricity and natural gas. Electricity is purchased from Jersey Central Power & Light Company (JCP&L). Natural gas is purchased from New Jersey Natural Gas. Potable water and sewer utilities are provided by the Borough of Mountain Lakes. As a result, the Department of Public Works does not receive a bill for these utilities. During the period of June 2009 to May 2010, electric usage was approximately 72,700 kWh at a total cost of about $12,500. Review of electricity bills during this period determined the building was charged a supply unit cost of $0.16 per kWh, demand unit cost of $3.67 per kW, and blended unit cost of $0.1719 per kWh. Electricity usage was highest in the winter months when the supplemental electric heat is energized in the office space. The electrical consumption actually decreases in the summer when cooling is in operation because the building personnel are diligent in manually setting back the temperature during unoccupied times. During the same 2009 timeframe, the building heat and domestic hot water (DHW) produced by natural gas-fired equipment required approximately 7,224 therms. Based on the annual cost of $9,684, the blended price for natural gas was $1.34 per therm. Natural gas consumption is highest in the winter months to produce building heat. Utility data can be found in Appendix A. Electricity supply and delivery is presently purchased from JCP&L. Natural gas supply and delivery is presently purchased from New Jersey Natural Gas. The delivery component will always be the
New Jersey BPU - Energy Audits
Page 5 of 23
responsibility of the utility that connects the facility to the power grid or gas line; however, the supply can be purchased from a third party. The electricity or natural gas commodity supply entity will require submission of one to three years of past energy bills. Contract terms can vary among suppliers. A list of approved electrical and natural gas energy commodity suppliers can be found in Appendix A. 3.3 HVAC Systems Heating and air conditioning is provided to various areas of the facility as follows: A large, gas-fired, Flexaire furnace heats the original building’s garage area. The furnace is rated at 80% efficiency. The supply ductwork is located below the floor and supplies air in floor registers at the exterior garage doors. The unit appears to be original to the building, approximately 55 years old. The unit supplies the entire 7,800-ft2 garage space. As a result if there is only one employee working in the garage, the entire space must be heated. An air-handling unit manufactured by Heil, with cooling and electric heat, conditions the original offices, locker room, and bathroom. The furnace is a high efficiency unit (90%) and is located in the attic space. The unit is approximately 18 years old, according to the serial number. The condensing unit is located on grade. Nameplate data on unit is partially concealed and EER value could not be determined. An American Standard furnace, cooling coil, and condensing unit conditions the office addition which includes the conference/lunchroom and the front office. The furnace fuel is natural gas. The unit was installed at the time that the addition was constructed and is approximately 8 years old, high efficiency (90%), and is located in the attic space. The condensing unit is located on grade. Nameplate data on unit is partially concealed and EER value could not be determined. A gas-fired furnace, with split system cooling, conditions the woodworking shop. The furnace has a rated efficiency of 80%. The unit is approximately 13 years old. The gas fired furnace and coil are suspended from the structure. The condensing unit is located on grade. Nameplate data on unit is partially concealed and EER value could not be determined. The following is a summary of this equipment and areas served:
Equipment Cooling Tons
Heating MBH Input/Output Area Served
AHU-1 N/A 750 / 600 Original Garage AHU-2 2 15 kW Original Offices, Locker Room, and Bathroom
AHU-3 2 60 / 54 New Addition Conference/Lunchroom and Front Office
AHU-4 3 60 / 48 Woodworking Shop UH-1 N/A 125 / 100 Pole Barn (2 Units)
Exhaust in the office toilet room is through a combination light/fan. Exhaust in the locker/toilet area is by a stand-alone exhaust fan operated by a wall switch. In addition, two summer ventilation exhaust fans of undetermined size exhaust the garage space. A single vehicle truck exhaust system is also located in the garage service bay. General ventilation in the garage area is achieved through the use of operable garage doors.
New Jersey BPU - Energy Audits
Page 6 of 23
The salt shed out building is not heated or cooled. The four bay storage out building (pole barn) is heated. The building is divided into two sections. One half of the building is unconditioned. The other half is heated by two gas fired unit heaters with an efficiency of 80% and a gas input of 125 MBH each. The equipment appears to be in good condition. A list of HVAC equipment can be found in Appendix B. 3.4 Lighting/Electrical Systems The majority of lighting fixtures throughout the facility utilize energy efficient T-8 fluorescent lamps or incandescent A-lamps. Although most of the fluorescent lamps have been changed from T-12 to T-8, there are a few fixtures in the garage area that have not been replaced yet. Exit signs within the building are not lit and do not use lamps. A comprehensive list of existing lighting fixtures is included in Appendix C. Exterior building lighting, located around the entire building, is a mix of 50W high pressure sodium lamps and 400W metal halide lamps. Site lighting consists of pole mounted metal halide lamps. A 60 kW, natural gas fired, Onan generator, provides emergency power. The unit powers heat and emergency lighting. The unit is located outside of the facility on the side of the building. 3.5 Control Systems 3.5.1 HVAC Controls Four wall-mounted thermostats, located in the garage, woodworking shop, and two in the office areas control the four HVAC units in the building. The thermostat located in the woodworking shop is the programmable type. The other thermostats are manual. Following are the existing occupied and unoccupied heating and cooling setpoints for each piece of HVAC equipment:
Equipment Heating Occ/Unocc
Cooling Occ/Unocc
Yearly Occupied
Hours
AHU-1 68°F / 60°F N/A 2080 hrs/yr AHU-2 70°F / 68°F 75°F / 75°F 2080 hrs/yr AHU-3 70°F / 68°F 75°F / 75°F 2080 hrs/yr AHU-4 68°F / 60°F 75°F / 75°F 2080 hrs/yr UH-1 62°F / 62°F N/A 520 hrs/yr
A manual switch controls the toilet room exhaust fans. A manual switch controls the summer ventilation fan.
3.5.2 Lighting Controls Manual wall switches control lighting in the public works garage. Exterior lighting is controlled by time clocks.
New Jersey BPU - Energy Audits
Page 7 of 23
3.6 Plumbing Systems Domestic hot water for the facility is produced by a 40 gallon, 40 MBH, gas-fired, A.O. Smith water heater. The heater is located in the garage mechanical room, near the garage heater, and vented through the roof. In the woodworking shop a 20 gallon , 2kW, electric, Rheem water heater is installed on a shelf above a service sink. Approximately 40’ of hot water piping is not insulated. Plumbing fixtures include 1.6 gallon per flush tank type water closets; vanity type restroom sinks; urinal with 1.0 gallon per flush valve; shower with 2.5 gallon per minute shower head; kitchen sink; service sink; clothes washer, and exterior non-freeze wall hydrants. All flush valves and faucets meet the maximum water flow requirements of the adopted plumbing codes.
New Jersey BPU - Energy Audits
Page 8 of 23
4.0 ENERGY CONSERVATION MEASURES 4.1 ECM-1 Lighting Fixture Modifications The facility utilizes a great deal of energy efficient fixtures. The majority of fixtures are T-8 fixtures, although some inefficient T-12 fixtures remain. In addition, there are areas that use incandescent A-Lamps where compact fluorescent lamps can cut energy consumption by 75%. There are 29 T-12 fixtures and 18 A-Lamps that can be replaced. The fixtures and lamps that are suggested to be replaced are highlighted in Appendix C. Energy savings for this measure were calculated by applying the existing and proposed fixture wattages to the estimated time of operation. The difference resulted in an annual savings of 6,000 kWh per year, or $1,000 per year. Supporting calculations, including all assumptions for lighting hours, and the annual energy usage for each fixture can be found in Appendix C. Lighting has an expected life of 15 years, according to the manufacturer, and total energy savings over the life of the project are estimated at 90,000 kWh and $15,000. The implementation cost and savings related to this ECM are presented in Appendix C and summarized as follows:
ECM-1 Lighting Fixture Modifications Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
5,300 - 5,000 0 1,000 1.8 870 5.3 4.4 * There is a $30 per fixture incentive for replacing T12 fixtures with T8 fixtures available through the New Jersey Smart Start program’s Prescriptive Lighting Application for this ECM. This measure is recommended. 4.2 ECM-2 Lighting Control Modifications Manual wall switches and panel switching currently control lighting throughout the facility. By equipping the offices, lunchroom, locker room, and restroom areas with motion sensors, unoccupied energy use can be greatly reduced. This ECM proposes the addition of six wall-mounted occupancy sensors. The weekly occupied times for each space was determined by taking into account typical traffic patterns for the building as provided through interviews with the end user. Applying the existing and proposed operating times to the combined wattage requirements for each room’s lighting fixtures, the energy reduction in kWh per year and operational savings per year were determined. The occupancy sensor controls are being applied to lighting that were proposed to be revised in ECM-1. It was determined that approximately 1,900 kWh per year, or $110 per year, can be saved through implementation of this ECM. Occupancy sensors have an expected life of 15 years, according to the manufacturer, and total energy savings over the life of the project are estimated at 28,500 kWh and $1,650. Supporting calculations, including the proposed rooms to install occupancy sensors; assumptions for lighting hours in each space; annual energy usage for each fixture; and the type of occupancy sensor
New Jersey BPU - Energy Audits
Page 9 of 23
recommended is included in Appendix D. The implementation cost and savings related to this ECM are summarized below:
ECM-2 Lighting Control Modifications (Proposed Fixtures)
Budgetary Annual Utility Savings ROI Potential Payback Payback
Cost (with Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total Incentive)
$ kW kWh Therms $ $ Years Years
550 0 1,900 0 110 3.0 140 5.0 3.7 * Incentive shown is per the New Jersey Smart Start Program, 2010 Lighting Controls Application. Incentive is based on the use of seven wall-mounted occupancy sensors. This measure is recommended. When applied to the reduced wattages of the proposed fixtures, the occupancy sensors still provide a short payback period on the initial cost. If the existing fixtures remain and are not replaced as proposed in ECM-1, the savings for ECM-2 increase. It is recommended to implement both ECM-1 and ECM-2 to maximize energy savings. 4.3 ECM-3 Replace Heating Unit Serving Garage Area A large, gas-fired, Flexaire furnace heats the original building’s garage area. The furnace is rated at 80% efficiency. The supply ductwork is located below the floor and supplies air in floor registers at the exterior garage doors. The unit appears to be original to the building, approximately 55 years old. Because of the old age of the unit, the efficiency of the unit is derated from its stated value. The unit supplies the entire 7,800-ft2 garage space. As a result if there is only one employee working in the garage, the entire space must be heated. By replacing the unit with a high efficiency model and lowering the maintained set-point in the large garage space, overall energy consumption can be greatly reduced. To maintain worker comfort with the lower set point temperature of the space, radiant heating is proposed to be installed in ECM-4. ECM-3 will only analyze increasing the efficiency of the garage heating unit. The reduction in set point temperature will be analyzed in conjunction with the radiant heaters in ECM-4. The annual energy consumed in the garage area for heating can be reduced, yielding an annual savings of approximately 800 therms or $1,100. Implementation of this measure requires demolition of the existing indirect-fired natural gas furnace and installation of a new, high efficiency (92% efficient), direct-fired unit in its place. This ECM was analyzed by modeling both the building and the hours of operation in the Carrier Hourly Analysis Program (HAP). Using this model, the energy use of replacement equipment can be compared to the existing equipment under equal conditions. HAP data for this ECM is located in Appendix E. Base building data is located in Appendix M. The furnace has an expected life of 15 years, according to ASHRAE, and total energy savings over the life of the project are estimated at 12,000 therms, and $16,500. The implementation cost and savings related to this ECM are presented in Appendix E and summarized on the following page:
New Jersey BPU - Energy Audits
Page 10 of 23
ECM-3 Replace Heating Unit Serving Garage Area
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
16,800 - - 800 1,100 1.0 NA 15.3 NA * There is no incentive available through the New Jersey Smart Start program for this ECM. Although the payback for this ECM falls outside the payback range of 10 years, this measure is recommended because of the age of the existing unit. The existing unit is likely to fail in the near future and replacing it prior to failure is the lowest cost solution. The existing unit also demonstrates that when equipment is taken care of, the ASHRAE life expectancy guidelines can often be exceeded, increasing the return on investment. Because ECM-4 combines this measure with additional energy conservation methods, ECM-4 analysis is utilized for the summation of energy reduction to prevent double counting of savings. 4.4 ECM-4 Provide Radiant Heating in Garage and Setpoint Modification The 7,800 square foot garage space is currently heated by a single heating and ventilating unit. When a single employee is working in the garage, more than 93,600 cubic feet of space must be heated for the comfort of a single individual. By providing radiant heaters in the working area of the garage, a minimum temperature can be maintained by the heating and ventilating unit for the entire space while a comfortable working temperature is projected directly onto the work area of the individual employee. This setup allows employee comfort with minimal modification to the existing layout and systems in the garage, as well as the lowest installation cost for a comfort system. Utilizing natural gas-fired radiant heaters in garage work areas allows a minimum temperature to be maintained throughout the space, but provide a comfortable work environment for a single employee without heating the entire space. By lowering the occupied and unoccupied space temperature to 55 deg F, The annual energy consumed in the garage area for heating can be reduced, yielding an annual savings of approximately 900 kWh and 900 therms, or a total of $1,300. Implementation of this measure requires installation of gas-fired radiant heaters and the associated modifications to the natural gas piping in the space. This ECM was analyzed by modeling, in the Carrier Hourly Analysis Program (HAP), both the air handling unit as proposed in ECM-3, but with the unit having a 55 deg F temperature set point, and natural gas-fired radiant heaters in the garage work areas. Using these models, the energy use of reducing the air handling unit load and adding a radiant heat load can be compared to the existing equipment under equal conditions. HAP data for this ECM is located in Appendix F. Data for the high efficiency heating and ventilating unit proposed in ECM-3 can be found in Appendix E. The installation of radiant heating and a setpoint modification for the existing unit is also shown below so that the savings associated with each scenario can be compared. Because the garage heating and ventilation unit is recommended to be replaced in ECM-3 due to the age and condition of the unit, the energy savings of radiant heating with the installation of a 92% efficient unit are used for this report’s analysis. The radiant heaters have an expected life of 15 years, according to ASHRAE, and total energy savings over the life of the project are estimated at 13,500 kWh, 13,500 therms, and $19,500.
New Jersey BPU - Energy Audits
Page 11 of 23
The implementation cost and savings related to this ECM are presented in Appendix F and summarized below:
ECM-4 Provide Radiant Heating in Garage and Setpoint Modification (80% Efficient H&V Unit)
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
2,400 - 900 300 500 2.1 NA 4.8 NA * There is no incentive available through the New Jersey Smart Start program for this ECM.
ECM-4 Provide Radiant Heating in Garage and Setpoint Modification (92% efficient H&V Unit)
Budgetary Annual Utility Savings Potential Payback Payback
Cost* Incentive** (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
19,200 - 900 900 1,300 0 NA 14.8 NA * Budgetary Cost includes cost to replace existing Garage H&V unit with 92% efficient unit. ** There is no incentive available through the New Jersey Smart Start program for this ECM. This measure is recommended whether or not the existing garage heating and ventilation unit is replaced. 4.5 ECM-5 Replace Single Pane Windows with Double Pane Windows The currently installed exterior windows are a combination of single and double pane. Double pane windows have better insulating properties that reduce the rate of heat loss or gain. Single pane windows have poorer insulating properties than double pane windows and allow a greater amount of air infiltration or exfiltration, depending on the pressure of the building. When single pane windows are used in conjunction with storm windows, the air gap between the single pane window and the storm window improves the insulating properties of the whole window system and reduces air movement through the windows. Four of the buildings seven single pane windows also have storm windows installed. This ECM proposes the replacement of the single pane windows with double pane windows. This will improve the insulating properties of the windows and add convenience to the building maintenance program. Single pane windows with permanently installed storm windows account for 123 square feet of window are on the west elevation. Approximately 43 square feet of windows on the south elevation are single pane windows that have storm windows installed each heating season. By replacing these windows with double pane windows, annual energy consumed for heating and cooling the spaces can be reduced, yielding an annual savings of approximately 190 kWh or $30 and 30 therms or $40, for a total of $70. Implementation of this measure requires removal of the existing single pane windows and installation of the new double pane windows. This ECM was analyzed by modeling both the existing building and the building with replacement windows in the Carrier Hourly Analysis Program (HAP). Using this model, the energy use of heating and cooling equipment can be compared to the current energy consumption under equal conditions. HAP data for this ECM is located in Appendix G. Base building data is located in Appendix M.
New Jersey BPU - Energy Audits
Page 12 of 23
The double pane windows have an expected life of 15 years and total energy savings over the life of the project are estimated at 2,850 kWh, 450 therms, and $1,050. The implementation cost and savings related to this ECM are presented in Appendix G and summarized below:
ECM-5 Replace Single Pane Windows with Double Pane Windows
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
8,500 - 190 30 70 (0.9) NA >25 NA * There is no incentive available through the New Jersey Smart Start program for this ECM. This measure is not recommended. It is recommended to continue using storm windows on the single pane windows to achieve insulating values close to double pane windows, without the significant cost of replacing the windows.
4.6 ECM-6 Insulate Hot Water Piping Sections of hot water supply piping in the facility are currently not insulated. Increased heat losses through the walls of the pipe require the water heater to use additional energy to make up for these losses. The addition of 1” fiberglass insulation with all service jacket on one foot of one inch pipe, with a pipe surface temperature of 130 deg F will reduce heat loss by approximately 4 BTUh/ft. This reduction in heat loss translates to approximately $0.46/foot of insulated pipe per year. The analysis temperature of 130 deg F was utilized as an average temperature between the water heater supply temperature and the point of use temperature at fixtures. The facility has approximately forty feet of uninsulated hot water pipe resulting in 1,400 MBH/year of energy losses, or about $20 per year. To achieve these reductions, as much piping as possible should be insulated including valve bodies, check valves, etc. The ease of installing the insulation is such that it can be installed as part of an in-house maintenance program. The raw cost is approximately $1.04/foot, or about $40 for this facility. Insulation has an expected life of 15 years, according to the manufacturer, and the total energy saving over the life of the project are estimated at 200 therms and $275. The implementation and savings related to this ECM are presented in Appendix H and summarized on the following page:
ECM-6 Insulate Hot Water Piping
Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Natural Gas Electricity Total ROI
$ Therms kWh $ $ Years Years
40 14 0 20 6.5 NA 2 NA * There is no incentive available through the New Jersey Smart Start program for this ECM.
This measure is recommended.
New Jersey BPU - Energy Audits
Page 13 of 23
5.0 PROJECT INCENTIVES 5.1 Incentives Overview 5.1.1 New Jersey Pay For Performance Program The building will be eligible for incentives from the New Jersey Office of Clean Energy. The most significant incentives will be from the New Jersey Pay for Performance (P4P) Program. The P4P program is designed for qualified energy conservation projects in facilities whose demand in any of the preceding 12 months exceeds 200 kW. However, the 200 kW/month average minimum has been waived for buildings owned by local governments or municipalities and non-profit organizations. Facilities that meet this criterion must also achieve a minimum performance target of 15% energy reduction by using the EPA Portfolio Manager benchmarking tool before and after implementation of the measure(s). If the participant is a municipal electric company customer, and a customer of a regulated gas New Jersey Utility, only gas measures will be eligible under the Program. American Recovery and Reinvestment Act (ARRA) funding, when available, may allow oil, propane and municipal electric customers to be eligible for the P4P Program. Available incentives are as follows: Incentive #1: Energy Reduction Plan – This incentive is designed to offset the cost of services associated with the development of the Energy Reduction Plan (ERP). The standard incentive pays $0.10 per square foot, up to a maximum of $50,000, not to exceed 50% of facility annual energy cost, paid after approval of application. For building audits funded by the New Jersey Board of Public Utilities, which receive an initial 75% incentive toward performance of the energy audit, facilities are only eligible for an additional $0.05 per square foot, up to a maximum of $25,000, rather than the standard incentive noted above. Incentive #2: Installation of Recommended Measures – This incentive is based on projected energy saving and designed to pay approximately 60% of the total performance-based incentive. Base incentives deliver $0.11/kWh and $1.10/therm not to exceed 30% of total project cost. Incentive #3: Post-Construction Benchmarking Report – This incentive is paid after acceptance of a report proving energy savings over one year utilizing the Environmental Protection Agency (EPA) Portfolio Manager benchmarking tool. Incentive #3 base incentives deliver $0.07/kWh and $0.70/therm not to exceed 20% of total project cost. Combining incentives #2 and #3 will provide a total of $0.18/ kWh and $1.8/therm not to exceed 50% of total project cost. Additional incentives for #2 and #3 are increased by $0.005/kWh and $0.05/therm for each percentage increase above the 15% minimum target to 20%, calculated with the EPA Portfolio Manager benchmarking tool, not to exceed 50% of total project cost. 5.1.2 New Jersey Smart Start Program
For this program, specific incentives for energy conservation measures are calculated on an individual basis utilizing the 2010 New Jersey Smart Start incentive program. This program provides incentives dependent upon mechanical and electrical equipment. If applicable, incentives from this program are reflected in the ECM summaries and attached appendices. If the building qualifies and enters into the New Jersey Pay for Performance Program, all energy savings will be included in the total building energy reduction, and savings will be applied towards the Pay for Performance incentive. A project is not applicable for both New Jersey incentive programs.
New Jersey BPU - Energy Audits
Page 14 of 23
5.1.3 Energy Efficient and Conservation Block Grant Following is a brief summary of the Energy Efficient and Conservation Block Grant (EECBG) program. The Energy Efficiency and Conservation Block Grant Complete Program Application Package should be consulted for rules and regulations. Additional funding is available to local government entities through the EECBG, a part of New Jersey’s Clean Energy program (NJCEP). The grant is for local government entities only, and can offset the cost of energy reduction implementation to a maximum of $20,000 per building. This program is provided in conjunction with NJCEP funding and any utility incentive programs; the total amount of the three incentives combined cannot exceed 100% of project cost. Funds shall first be provided by NJCEP, followed by the EECBG and any utility incentives available to the customer. The total amount of the incentive shall be determined TRC Solutions, a third party technical consulting firm for the NJCEP. In order to receive EECBG incentives, local governments must not have received a Direct Block Grant from the US Department of Energy. A list of the 512 qualifying municipalities and counties is provided on the NJCEP website. Qualifying municipalities must participate in at least one eligible Commercial & Industrial component of the NJCEP, utility incentive programs, or install building shell measures recommended by the Local Government Energy Audit Program. Eligible conservation programs through NJCEP include:
• Direct Install • Pay for Performance • NJ SmartStart Buildings for measures recommended by a Local Government Energy
Audit (LGEA) or an equivalent audit completed within the last 12 months • Applicants may propose to independently install building shell measures recommended
by a LGEA or an equivalent audit. The audit must have been completed within the past 12 months.
• Any eligible utility energy efficiency incentive program Most facilities owned or leased by an eligible local government within the State of New Jersey are eligible for this grant. Ineligible facilities include casinos or other gambling establishments, aquariums, zoos, golf courses, swimming pools, and any building owned or leased by the United States Federal Government. New construction is also ineligible. 5.1.4 ARRA Initiative “Energy Efficiency Programs through the Clean Energy Program” The American Recovery and Reinvestment Act (ARRA) Initiative is available to New Jersey oil, propane, cooperative and municipal electric customers who do not pay the Societal Benefits Charge. This charge can be seen on any electric bill as the line item “SBC Charge.” Applicants can participate in this program in conjunction with other New Jersey Clean Energy Program initiatives including Pay for Performance, Local Government Energy Audits, and Direct Install programs. Funding for this program is dispersed on a first come, first serve basis until all funds are exhausted. The program does not limit the municipality to a minimum or maximum incentive, and the availability of funding cannot be determined prior to application. If the municipality meets all qualifications, the application must be submitted to TRC Energy Solutions for review. TRC will then determine the amount
New Jersey BPU - Energy Audits
Page 15 of 23
of the incentive based on projected energy savings of the project. It is important to note that all applications for this incentive must be submitted before implementation of energy conservation measures. Additional information is available on New Jersey’s Clean Energy Program website. 5.2 Building Incentives 5.2.1 New Jersey Pay For Performance Program The building is eligible for all three incentives available from the New Jersey P4P program. Incentive #1 is for the development of an energy reduction plan and will pay $.05/ square foot of the building footprint, which equates to about $515. Implementation of the energy conservation measures discussed in this report is expected to reduce the building’s energy usage by over 15%, which qualifies it for both incentives #2 and #3. Combining incentives #2 and #3 will provide maximum savings of $0.18/ kWh and $1.80/ therm not to exceed 50% of the total project cost. The building is projected to save about 7,800 kWh, which amounts to about $1,400 in incentives. The building is also projected to save about 1,700 therms of natural gas. With New Jersey’s current incentive structure, this would qualify for about $3,000 in incentive money. Combining all incentives in the P4P program would amount to approximately $4,400, reducing the overall payback of the project from 7.1 years to 5.9 years. 5.2.2 New Jersey Smart Start Program The Borough of Mountain Lakes Department of Public Works Garage is eligible for incentives from the New Jersey Smart Start Program. The lighting replacement measure is eligible for $870 in savings if all fixtures are replaced. The lighting controls measure is eligible for $140 in savings if seven motion sensors are added for lighting control. 5.2.3 Energy Efficient and Conservation Block Grant The Borough of Mountain Lakes Department of Public Works Garage is owned by local government, which makes it eligible for this incentive. The incentive amount is determined by TRC Solutions and is not calculable at this time. Further information about this incentive, including the application, can be found at: http://www.njcleanenergy.com/commercial-industrial/programs/energy-efficiency-and-conservation-block-grants 5.2.4 ARRA Initiative “Energy Efficiency Programs through the Clean Energy Program” Based on the utility information that was provided by the borough for the Department of Public Works garage, the building pays for the societal benefits charge. The garage building is not eligible for additional funding through this program.
New Jersey BPU - Energy Audits
Page 16 of 23
6.0 ALTERNATIVE ENERGY SCREENING EVALUATION 6.1 Geothermal
Geothermal heat pumps (GHP) transfer heat between the constant temperature of the earth and the building to maintain the building’s interior space conditions. Below the surface of the earth throughout New Jersey the temperature remains in the low 50°F range throughout the year. This stable temperature provides a source for heat in the winter and a means to reject excess heat in the summer. With GHP systems, water is circulated between the building and the piping buried in the ground. The ground heat exchanger in a GHP system is made up of a closed or open loop pipe system. Most common is the closed loop in which high density polyethylene pipe is buried horizontally at 4-6 feet deep or vertically at 100 to 400 feet deep. These pipes are filled with an environmentally friendly antifreeze/water solution that acts as a heat exchanger. In the summer, the water picks up heat from the building and moves it to the ground. In the winter the system reverses and fluid picks up heat from the ground and moves it to the building. Heat pumps make collection and transfer of this heat to and from the building possible.
Due to the use of this building, the best heating system available for the garage area is an infrared system. Such a system heats materials and the people, not the air surrounding these. A geothermal system requires the use of heat pumps, which are systems that heat air and not surfaces. Such systems are not compatible with the use of this building. Within the areas that an air system works well, the office, lunchroom, locker/toilet room, and mezzanine, there is little cooling required. This imbalance between the large swing in cooling and heating requirements is not conducive to a geothermal system. The benefits associated with a geothermal system are not realized in this type of facility.
6.2 Solar 6.2.1 Photovoltaic Rooftop Solar Power Generation The facility was evaluated for the potential to install rooftop photovoltaic (PV) solar panels for power generation. Present technology incorporates the use of solar cell arrays that produce direct current (DC) electricity. This DC current is converted to alternating current (AC) with the use of an electrical device known as an inverter. The building’s roof has sufficient room to install a large solar cell array. A structural analysis would be required to determine if the roof framing could support a cell array. The PVWATTS solar power generation model was utilized to calculate PV power generation. The New Jersey Clean Energy Program recommends the use of the PVWATTS program to determine solar grid tied system production. Version 2 of the program was used, allowing the zip code of the Department of Public Works garage to be analyzed. A fixed tilt array type was utilized to calculate energy production. The PVWATTS solar power generation model is provided in Appendix I. Additionally, further financial analysis was provided by www.solar-estimate.org. The result of this analysis is also located in Appendix I. The State of New Jersey incentives for non-residential PV applications is $1.00/watt up to 50 kW of installed PV array. Federal tax credits are also available for renewable energy projects up to 30% of installation cost. Municipalities do not pay federal taxes; therefore, would not be able to utilize the federal tax credit incentive. Installation of (PV) arrays in the State of New Jersey will allow the owner to participate in the New Jersey solar renewable energy certificates program (SREC). This is a program that has been set up to allow entities with large amounts of environmentally unfriendly emissions to purchase credits from zero
New Jersey BPU - Energy Audits
Page 17 of 23
emission (PV) solar-producers. An alternative compliance penalty (ACP) is paid for by the high emission producers and is set each year on a declining scale of 3% per year. One SREC credit is equivalent to 1000 kilowatt hours of PV electrical production; these credits can be traded for period of 15 years from the date of installation. The cost of the ACP penalty for 2009 is $689; this is the amount that must be paid per SERC by the high emission producers. The expected dollar amount that will be paid to the PV producer for 2009 is expected to be $600/SREC credit. Payments that will be received from the PV producer will change from year to year dependent upon supply and demand. Renewable Energy Consultants is a third party SREC broker that has been approved by the New Jersey Clean Energy Program. As stated above there is no definitive way to calculate an exact price that will be received by the PV producer per SREC over the next 15 years. Renewable Energy Consultants estimated an average of $487/ SERC per year and this number was utilized in the cash flow for this report. The building had a maximum kW demand of 30.1 kW and a minimum of 16.1 kW over the previous 12 months. The monthly average over the observed 12-month period was 25.18 kW. Because the most frequent monthly demand is approximately 25 kW, a 25 kW system size was selected for the calculations. The system costs for PV installations were derived from average installation costs for this area. It should be noted that the cost of installation is currently $8 per watt or $8,000 per kW of installed system. This has increased in the past few years due to the rise in national demand for PV power generator systems. Other cost considerations will also need to be considered. PV panels have an approximate 20 year life span; however, the inverter device that converts DC electricity to AC has a life span of 10 to 12 years and will need to be replaced multiple times during the useful life of the PV system. The implementation cost and savings related to this ECM are presented in Appendix I and summarized below:
Photovoltaic (PV) Rooftop Solar Power Generation – 25 kW System
Budgetary Annual Utility Savings Total
New Jersey
Renewable
New Jersey
Renewable Payback Payback
Cost Savings Energy
Incentive* SREC** (without
incentive) (with
incentives)
Electricity Natural Gas Total
$ kW kWh Therms $ $ $ $/yr Years Years
200,000 0 31,300 0 5,400 5,400 25,000 15,200 >25 ~5 *Incentive based on New Jersey Renewable Energy Program for non-residential applications of $1.00 per Watt of installed capacity ** Estimated Solar Renewable Energy Certificate Program (SREC) for 15 years at $487/1000 kWh Based on the above, it is recommended that a third party power purchase agreement (PPA) be considered to take advantage of the ITC, reduce the cost of the system to the township, and provide a guaranteed reduced cost of power. 6.2.2 Solar Thermal Hot Water Plant Active solar water-heating systems for buildings use solar collectors to absorb the sun’s energy to heat a fluid, either a liquid or air. The collector would then circulate the heated liquid to the normal system. If the liquid is water it may be circulated to the domestic water heater to increase the temperature further prior to entering the hot water supply system. There are also collectors that heat air which is then passed through an air to liquid heat exchanger to increase the temperature of another fluid. Applications for active solar thermal energy include providing hot water, heating swimming pools, space heating, and preheating air in residential and commercial buildings.
New Jersey BPU - Energy Audits
Page 18 of 23
A standard solar hot water system is typically composed of solar collectors, heat storage vessel, piping, circulators, and controls. Systems are typically integrated to work alongside a conventional heating system that provides heat when solar resources are not sufficient. The solar collectors are usually placed on the roof of the building, oriented south, and tilted around the site’s latitude, to maximize the amount of radiation collected on a yearly basis. Several options exist for using active solar thermal systems for space heating. The most common method involves using glazed collectors to heat a liquid held in a storage tank (similar to an active solar hot water system). The most practical system for the garage would utilize a solar circulation, domestic hot water system that pre-heats incoming water prior to entering the domestic water heater. Although this system is the both the simplest and least expensive to implement, the small amount of hot water used at the facility on an annual basis results in a payback period that greatly exceeds the useful life of the system itself. DHW is presently produced by a natural gas fired water heater and, therefore, this measure would not save site electricity. Currently, an incentive is not available for installation of thermal solar systems. A Federal tax credit of 30% of installation cost for the thermal applications is available; however, the Borough of Mountain Lakes does not pay Federal taxes and, therefore, would not benefit from this program. The implementation cost and savings related to this ECM are presented in Appendix J and summarized as follows:
Solar Thermal Domestic Hot Water Plant
Budgetary Annual Utility Savings Total New Jersey Renewable Payback Payback
Cost
Savings Energy
Incentive (without
incentive) (with incentive)
Electricity Natural Gas Total
$ kW kWh Therms $ $ $ Years Years
9,300 0 0 170 230 230 NA >25 NA * No incentive is available in New Jersey at this time. This measure is not recommended. 6.3 Wind Wind turbines are part of a renewable energy system that converts the kinetic energy of wind into usable mechanical and electrical energy. Small wind turbines comprise the group of turbines utilized for residential and small business applications. The most common design for small wind turbines utilize a horizontal axis propeller, which converts kinetic energy of the wind into rotary motion to drive a generator, which usually is designed specifically for the wind turbine. The rotor consists of two or three blades, usually made from wood or fiberglass. These materials give the turbine the needed strength and flexibility, and have the added advantage of not interfering with television signals. The structural backbone of the wind turbine is the mainframe, and includes the slip-rings that connect the wind turbine, which rotates as it points into changing wind directions, and the fixed tower wiring. The tail aligns the rotor into the wind. To avoid turbulence and capture greater wind energy, turbines are mounted on towers. Turbines should be mounted at least 30 feet above any structure or natural feature within 300 feet of the installation. Smaller turbines can utilize shorter towers. For example, a 250-watt turbine may be mounted on a 30-50 foot
New Jersey BPU - Energy Audits
Page 19 of 23
tower, while a 10 kW turbine will usually need a tower of 80-120 feet. Tower designs include tubular or latticed, guyed or self-supporting. Wind turbine manufacturers also provide towers. The New Jersey Clean Energy Program for small wind installations has designated numerous pre-approved wind turbines for installation in the State of New Jersey. Incentives for wind turbine installations are based on kilowatt hours saved in the first year. Systems sized under 16,000 kWh per year of production will receive a $3.20 per kWh incentive. Systems producing over 16,000 kWh will receive $51,200 for the first 16,000 kWh of production with an additional $0.50 per kWh up to a maximum cap of 750,000 kWh per year. Federal tax credits are also available for renewable energy projects up to 30% of installation cost for systems less than 100 kW. However, as noted previously, municipalities do not pay federal taxes and is, therefore, not eligible for the tax credit incentive. The most important part of any small wind generation project is the mean annual wind speed at the height of which the turbine will be installed. In the Mountain Lakes area, the map indicates a mean annual wind speed of less than 4.5 meters per second, approximately 14 miles per hour. Most small wind turbines are not financially viable at such wind speeds. Therefore, the model indicates that a wind turbine installation may not be applicable at this location. The model was designed to provide a good indication of wind speeds at applicable locations throughout the state. Before moving forward with a small wind production project at the facility’s location, a wind test tower will need to be installed at the 30 meter tower height and monitored for a year. Consideration must also be given to the effects of the turbine location on the neighbors and local ordinances. A wind speed map is included in Appendix K. This measure is not recommended due to the low mean annual wind speed at the proposed location. 6.4 Combined Heat and Power Generation (CHP)
Combined heat and power, cogeneration, is self-production of electricity on-site with beneficial recovery of the heat byproduct from the electrical generator. Common CHP equipment includes reciprocating engine-driven, micro turbines, steam turbines, and fuel cells. Typical CHP customers include industrial, commercial, institutional, educational institutions, and multifamily residential facilities. CHP systems that are commercially viable at the present time are sized approximately 50 kW and above, with numerous options in blocks grouped around 300 kW, 800 kW, 1,200 kW and larger. Typically, CHP systems are used to produce a portion of the electricity needed by a facility some or all of the time, with the balance of electric needs satisfied by purchase from the grid.
Any proposed CHP project will need to consider many factors, such as existing system load, use of thermal energy produced, system size, natural gas fuel availability, and proposed plant location. The facility does not have sufficient need for electrical generation or the ability to use most of the thermal byproduct during the winter or summer months. Thermal energy produced by the CHP plant in the warmer months will be wasted. An absorption chiller could be installed to utilize the heat to produce chilled water; however, there is no chilled water distribution system in the building. The most viable selection for a CHP plant at this location would be a reciprocating engine natural gas-fired unit. Purchasing this system and performing modifications to the existing HVAC and electrical systems would greatly outweigh the savings over the life of the equipment. This measure is not recommended.
New Jersey BPU - Energy Audits
Page 20 of 23
6.5 Biomass Power Generation
Biomass power generation is a process in which waste organic materials are used to produce electricity or thermal energy. These materials would otherwise be sent to the landfill or expelled to the atmosphere. To participate in NJCEP's Customer On-Site Renewable Energy program, participants must install an on-site sustainable biomass or fuel cell energy generation system. Incentives for bio-power installations are available to support up to 1MW-dc of rated capacity.
*Class I organic residues are eligible for funding through the NJCEP CORE program. Class I wastes include the following renewable supply of organic material:
! Wood wastes not adulterated with chemicals, glues or adhesives ! Agricultural residues (corn stover, rice hulls or nut shells, manures, poultry litter, horse manure,
etc) and/or methane gases from landfills ! Food wastes ! Municipal tree trimming and grass clipping wastes ! Paper and cardboard wastes ! Non adulterated construction wood wastes, pallets
The NJDEP evaluates biomass resources not identified in the RPS.
Examples of eligible facilities for a CORE incentive include:
! Digestion of sewage sludge ! Landfill gas facilities ! Combustion of wood wastes to steam turbine ! Gasification of wood wastes to reciprocating engine ! Gasification or pyrolysis of bio-solid wastes to generation equipment
* from NJOCE Website This measure is not recommended because of noise issues, potential zoning issues, and the lack of a reliable waste stream that can be utilized.
6.6 Demand Response Curtailment
Presently, electricity is delivered by JCP&L, which receives the electricity from regional power grid RFC. PJM is the regional transmission organization (RTO) that coordinates the movement of wholesale electricity in all or parts of 13 states and the District of Columbia including the State of New Jersey. Utility Curtailment, also known as Economic Load Response, is an agreement with the PJM regional transmission organization and an approved Curtailment Service Provider (CSP) to reduce electrical demand by either turning major equipment off or energizing all or part of a facility utilizing an emergency generator; therefore, reducing the electrical demand on the utility grid. This program is to benefit the utility company during high demand periods and PJM offers incentives to the CSP to participate in this program. Enrolling in the program will require program participants to drop electrical load or turn on emergency generators during high electrical demand conditions or during emergencies. Part of the program also will require that program participants reduce their required load or run emergency generators with notice to test the system.
New Jersey BPU - Energy Audits
Page 21 of 23
A PJM pre-approved CSP will require a minimum of 100 kW of load reduction to participate in any curtailment program. The garage had a monthly average kW demand of 25.2 kW and a maximum demand of 30.1 kW over the previous 12 months. This measure is not recommended because the facility does not have adequate load to meet the required minimum load reduction.
New Jersey BPU - Energy Audits
Page 22 of 23
7.0 EPA PORTFOLIO MANAGER The United State Energy Protection Agency (EPA) is a federal agency in charge of regulating environment waste and policy in the United States. The EPA has released the EPA Portfolio Manager for public use. The program is designed to allow property owners and managers to share, compare and improve upon their facility’s energy consumption. Inputting such parameters as electricity, heating fuel, building characteristics and location into the website based program generates a naturalized energy rating score out of 100. Once an account is registered, monthly utility data can be entered to track the savings progress and retrieve an updated energy rating score on a monthly basis. The Department of Public Works garage is considered a moderate to high energy consumer per the Portfolio Manager with a Site Energy Usage Index (EUI) of 95 kBTU/ft2/year. In comparison, a similarly sized site with an energy performance rating of 75 (the minimum to be eligible for ENERGY STAR) has a site EUI of 42 kBTU/ft2/year and the national average site EUI is 77 kBTU/ft2/year. The building’s EUI is higher than the national average because the national average includes a large variety of buildings that are classified as “Other.” Because of the aged equipment heating the garage area, coupled with the opening of garage doors in the heating season, the building uses more energy than other more tightly sealed buildings. If the recommended measures are implemented, ECM-1, ECM-2, ECM-3, ECM-4, and ECM-6, the facility’s EUI will be reduced from 95 kBTU/ft2/year to 76 kBTU/ft2/year. The EPA Portfolio Manager was not able to calculate an energy performance rating for this building because more than 50% of the floor area is defined as “Other” within the program. Although the Portfolio Manager does not calculate a rating for this building, we are still able to compare the building’s performance with the national average for all buildings designated “Other” as follows: Energy Performance Comparison Evaluation Period Comparisons Performance Metrics Baseline (Ending date 11/30/2009) Rating of 75 National Average Energy Intensity Site (kBtu/ft2) 95 42 77 Source (kBtu/ft2) 154 68 150 Energy Cost $/year $21,819.79 9,581.49 $17,696.69 $/ft2/year $2.10 $0.92 $1.70 Greenhouse Gas Emissions MtCO2e/year 77 34 62 kgCO2e/ft2/year 7 3 6 A full EPA Energy Star Portfolio Manager Report is located in Appendix L. The user name and password for the facility’s EPA Portfolio Manager Account has been provided to Barry R. Lewis, Borough Manager for Mountain Lakes.
New Jersey BPU - Energy Audits
Page 23 of 23
8.0 CONCLUSIONS & RECOMMENDATIONS The energy audit conducted by CHA at the Borough of Mountain Lakes Department of Public Works Garage in Mountain Lakes, New Jersey identified potential ECMs for lighting fixture upgrades, new lighting occupancy sensors, HVAC system upgrades, and pipe insulation. Potential annual savings of $3,530 may be realized for the recommended ECMs, with a summary of the costs, savings, and paybacks as follows:
ECM-1 Lighting Fixture Modifications Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
5,300 - 5,000 0 1,000 1.8 870 5.3 4.4 * There is a $30 per fixture incentive for replacing T12 fixtures with T8 fixtures available through the New Jersey Smart Start program’s Prescriptive Lighting Application for this ECM.
ECM-2 Lighting Control Modifications (Proposed Fixtures) Budgetary Annual Utility Savings ROI Potential Payback Payback
Cost (with Incentive* (without incentive) (with incentive)
Electricity Natural Gas Total Incentive)
$ kW kWh Therms $ $ Years Years
550 0 1,900 0 110 3.0 140 5.0 3.7 * Incentive shown is per the New Jersey Smart Start Program, 2010 Lighting Controls Application. Incentive is based on the use of seven wall-mounted occupancy sensors.
ECM-4 Provide Radiant Heating in Garage and Setpoint Modification (92% efficient H&V Unit) Budgetary Annual Utility Savings Potential Payback Payback
Cost* Incentive** (without incentive) (with incentive)
Electricity Natural Gas Total ROI
$ kW kWh Therms $ $ Years Years
19,200 - 900 900 1,300 0 NA 14.8 NA * Budgetary Cost includes cost to replace existing Garage H&V unit with 92% efficient unit. ** There is no incentive available through the New Jersey Smart Start program for this ECM.
ECM-6 Insulate Hot Water Piping Budgetary Annual Utility Savings Potential Payback Payback
Cost Incentive* (without incentive) (with incentive)
Natural Gas Electricity Total ROI
$ Therms kWh $ $ Years Years
40 14 0 20 6.5 NA 2 NA * There is no incentive available through the New Jersey Smart Start program for this ECM.
APPENDIX A
Utility Usage Analysis
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
PeriodC
oustomer
Charge
Delivery
RG
GI R
ecovery C
hargeD
eliverySocietal B
enefitsSystem
Control
Charge
Delivery Total
Basic
Generation
Non-U
tility G
eneration Supply Total
Total
kWkW
hkW
hkW
hkW
hkW
hkW
h
5/16-6/17/0911.65
$ 65.93
$ 0.38
$ 103.47
$ 37.94
$ 0.47
$ 219.84
$ 747.71
$ 99.84
$ 847.55
$ 1,067.39
$ 6/18-7/20/09
11.65$
53.40$
0.39$
105.63$
39.70$
0.49$
211.26$
774.17$
104.49$
878.66$
1,089.92$
7/21-8/19/0911.65
$ 83.28
$ 0.38
$ 103.93
$ 38.31
$ 0.47
$ 238.02
$ 747.04
$ 100.83
$ 847.87
$ 1,085.89
$ 8/20-9/18/09
11.65$
53.40$
0.28$
91.41$
28.08$
0.34$
185.16$
533.71$
73.91$
607.62$
792.78$
9/19-10/20/0911.65
$ 53.40
$ 0.12
$ 91.40
$ 31.69
$ 0.39
$ 188.65
$ 538.84
$ 83.85
$ 622.69
$ 811.34
$ 10/21-11/19/09
11.65$
86.05$
-$
103.39$
40.87$
0.51$
242.47$
704.49$
109.63$
814.12$
1,056.59$
11/20-12/21/0911.65
$ 67.94
$ -
$ 114.19
$ 49.53
$ 0.62
$ 243.93
$ 884.61
$ 132.86
$ 1,017.47
$ 1,261.40
$ 12/22-1/20/10
11.65$
130.05$
0.50$
111.89$
47.68$
0.60$
302.37$
860.52$
127.91$
988.43$
1,290.80$
1/21-2/18/1011.65
$ 109.34
$ 0.84
$ 118.34
$ 52.85
$ 0.66
$ 293.68
$ 955.78
$ 141.77
$ 1,097.55
$ 1,391.23
$ 2/19-3/19/10
11.65$
108.70$
0.52$
93.57$
32.99$
0.41$
247.84$
591.58$
88.51$
680.09$
927.93$
3/20-4/20/1011.65
$ 78.93
$ 0.53
$ 94.08
$ 33.40
$ 0.42
$ 219.01
$ 594.93
$ 89.60
$ 684.53
$ 903.54
$ 4/21-5/19/10
11.65$
63.52$
0.47$
89.32$
29.59$
0.37$
194.92$
536.63$
79.37$
616.00$
810.92$
Totals139.80
$ 953.94
$ 4.41
$ 1,220.62
$ 462.63
$ 5.75
$ 2,787.15
$ 8,470.01
$ 1,232.57
$ 9,702.58
$ 12,489.73
$
JCP&
L Rate Schedule "G
S Secondary"
Electricity Cost Sum
mary: M
eter #S36396766
BPU ENERGY AUDIT PROGRAMBorough of Mountain Lakes Department of Public Works Garage
CHA Project #21795
Period Billed Use Billed Demand Total Cost Demand Unit Cost
Suppy Unit Cost
Blended Cost
kWh kW $ $/kW $/kWh $/kWh
6/17/09 5,887 19.50 1,067.39$ 3.38$ 0.17$ 0.1813$ 7/20/09 6,161 16.10 1,089.92$ 3.32$ 0.17$ 0.1769$ 8/19/09 5,945 22.00 1,085.89$ 3.79$ 0.17$ 0.1827$ 9/18/09 4,358 15.20 792.78$ 3.51$ 0.17$ 0.1819$ 10/20/09 4,944 14.40 811.34$ 3.71$ 0.15$ 0.1641$ 11/19/09 6,464 23.30 1,056.59$ 3.69$ 0.15$ 0.1635$ 12/21/09 7,834 20.50 1,261.40$ 3.31$ 0.15$ 0.1610$ 1/20/10 7,542 30.10 1,290.80$ 4.32$ 0.15$ 0.1711$ 2/18/10 8,359 26.90 1,391.23$ 4.06$ 0.15$ 0.1664$ 3/19/10 5,219 26.80 927.93$ 4.06$ 0.15$ 0.1778$ 4/20/10 5,283 22.20 903.54$ 3.56$ 0.15$ 0.1710$ 5/19/10 4,680 19.40 810.92$ 3.27$ 0.16$ 0.1733$
Totals 72,676 256.40 12,489.73$ 0.1719$ Monthly Ave. 6,056 21.37 1,040.81$ 3.67$ 0.16$ Max. Demand 30.10
Account Number: 10 00 06 6568 52Meter Number: G28570790Rate Schedule: General Service Secondary 3 PhaseUtility Company: JCP&L
Notes: Total Billed Use kWh is the sum of each month's use in kWh.Total Billed Billed Demand is the highest month's demand. Total Cost is sum of each month's total billing including all charges.
(See Chart 2 "Total Column".) Demand Unit Cost per month is kW charges from Chart 2 divided by kW used.
Does not incled Service Charge from Chart 2.Supply Unit Cost per month is kWh charges from Chart 2 divided by kWh used.
Does not include Service Charge from Chart 2Total Demand Unit Cost is total kW charges from chart 2 divided by total kW used. Total Supply Unit Cost per year total kWh charges from chart 2 divided by total kWh.Blended Rate per month is the Cost divided by the kWh used for that month.Total Blended Rate is the Total Cost divided by the Total Use for the year.
Electricity Cost Summary: Meter # - Various
0.00
10.00
20.00
30.00
40.00
50.00
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
6/13/09
7/13/09
8/12/09
9/11/09
10/11/09
11/10/09
12/10/09
1/9/10
2/8/10
3/10/10
4/9/10
5/9/10
DEMAND (kW)
USAGE (kWh)
DA
TE
Borough of M
ountain Lakes DP
W G
arage
Billed U
se kWh
Billed D
emand kW
Supplier Name Phone No.
BOC Energy Services 800-247-2644
Champion Energy Services, Inc. 281-653-5090
Commerce Energy, Inc. 800-556-8457
Con Edison Solutions, Inc. 888-686-1383
Constellation NewEnergy, Inc. 888-635-0827
Direct Energy, LLC 800-260-0300
Dominion Retail, Inc. 800-264-4754
FirstEnergy Solutions Corp. 800-977-0500
Gateway Energy Services Corp. 800-313-8333
Glacial Energy 877-569-2841
Hess Corp 800-437-7872
Integrys Energy Services, Inc. 877-763-9977
Liberty Power Holdings, LLC 866-POWER-99
Palmco Power NJ, LLC 877-726-5862
Pepco Energy Services, Inc. 800-ENERGY-9
PP&L EnergyPlus, LLC 800-281-2000
Sempra Energy Solutions 877-2SEMPRA
South Jersey Energy 800-756-3749
GDF Suez Energy Resources NA 888-644-1014
UGI Energy Services 800-427-8545
Licensed Electric Generation Suppliers(May 2010)
To sell electric generation service in New Jersey, electric power suppliers must be licensed by the New Jersey Board of Public Utilities (NJ BPU). They must also be registered with the local public utility to sell electric generation service in that utility's service area. Below is a list of suppliers who are licensed with
the NJ BPU and are registered to sell electric generation service in the Jersey Central Power & Light Company service territory.
Contact the supplier directly to verify whether or not new customers are being accepted.
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
PeriodService C
harge Therm
sD
istribution (Therm
s)D
emand
Basic
Charge
CA
CTotal Supply
Gas C
ost R
efundTotal C
ostB
lended Cost
$/Therm
6/10-7/9/0940.00
$ 24.09
9.98$
108.78$
12.73$
62.71$
171.49$
5.46$
7/9-8/5/0940.00
$ 6.28
2.62$
108.78$
3.44$
46.06$
154.84$
18.29$
8/5-9/4/0940.00
$ 8.37
3.57$
108.78$
4.12$
47.69$
156.47$
13.92$
9/4-10/7/0940.00
$ 33.44
13.92$
108.78$
15.27$
69.19$
177.97$
4.13$
10/7-11/10/0940.00
$ 714.81
288.43$
108.78$
399.25$
727.68$
836.46$
1.11$
11/10-12/10/0940.00
$ 866.61
349.68$
108.78$
529.33$
919.01$
1,027.79$
1.14$
12/10-1/11/1040.00
$ 1780.85
718.57$
108.78$
1,229.21$
1,987.78$
2,096.56$
1.15$
1/11-2/9/1040.00
$ 1505.91
607.64$
108.78$
1,147.51$
1,795.15$
1,903.93$
1.24$
2/9-3/12/1040.00
$ 1321.48
533.22$
108.69$
916.31$
1,489.53$
1,598.22$
1.18$
3/12-4/13/1040.00
$ 593.48
239.47$
108.69$
369.13$
648.60$
757.29$
1.21$
4/13-5/13/1040.00
$ 316.09
128.58$
108.69$
304.58$
473.16$
581.85$
1.71$
5/13-6/11/1040.00
$ 52.96
21.80$
108.69$
51.03$
112.83$
221.52$
3.43$
Totals480.00
$ 7224.37
2,917.48$
1,305.00$
4,981.91$
-$
8,379.39$
-$
9,684.39$
1.34$
Billing Type: M
onthly 007M
Notes:
Chart 4
Gas C
ost Summ
aryThis chart provides gas cost breakdow
ns and sums totals. Sum
totals are "Total Supply", 1st, 3rd, and 5th columns and Total C
ost = Total Supply + Dem
and. B
lended Cost = Total divided by Therm
s. A
ll numbers are in $ except Therm
s.
Gas C
ost Summ
ary: Meter #00718689
Account: 12-1256-4620-19
0
200
400
600
800
1000
1200
1400
1600
1800
2000
6/10-7/9/09
7/9-8/5/09
8/5-9/4/09
9/4-10/7/09
10/7-11/10/09
11/10-12/10/09
12/10-1/11/10
1/11-2/9/10
2/9-3/12/10
3/12-4/13/10
4/13-5/13/10
5/13-6/11/10
NATURAL GAS USAGE (Therms)
MO
NTH
S
Borough of M
ountain Lakes DPW
Garage
Therms P
er Month
The natural gas suppliers listed below have been licensed by the New Jersey Board of PublicUtilities (BPU) to operate in the state of New Jersey. The last column indicates the type ofcustomers being served by the suppliers in the specified utility's service territory: residential (R),commercial (C) or both (R/C). A blank indicates the supplier is not currently operating in therespective utility's area.
Suppliers listed may not always have offers available.
Eligible Natural Gas Supplier List for Residential Customers and Commercial Customerswithin the NJNG Service Territory
NATURAL GAS SUPPLIER TELEPHONE NJNG
Core Energy 877-329-3495 R/C
Dominion Retail, Inc. 866-275-4240 R/C
GASMARK 856-273-9995 C
Gateway Energy Services Corp. 800-805-8586 R/C
Great Eastern Energy 888-651-4121 C
Hess Corporation 800-437-7872 C
Hudson Energy Services LLC 877-HUDSON9 R/C
Infinite Energy d/b/a Intelligent Energy 877-483-4684 R/C
Metro Media Energy 732-542-7575 C
MXenergy 800-785-4373 R/C
NATGASCO (Mitchell Supreme) 800-840-4GAS C
Palmco Energy NJ, LLC 877-726-5862 R/C
Pepco Energy Services 800-363-7499 C
PPL EnergyPlus, LLC 866-505-8825 C
South Jersey Energy Company 609-561-8385 C
Sprague Energy 603-431-1000 C
Systrum Energy 877-797-8786 R/C
U.S. Gas & Electric Inc. d/b/a New Jersey Gas & Electric 866-568-0290 R/C
Woodruff Energy 800-557-1121 R/C
View residential supplier offers.
Updated June 21, 2010
My Account :: Energy Choice :: Supplier List
Copyright © 2010 New Jersey Resources. All rights reserved.
APPENDIX B
HVAC Equipment List
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
HVA
C E
quipment L
istItem
Quanity
Manufacturer
Model N
umber
Serial number
Cooling C
apacity M
BH
Condition
FuelH
eating Input M
BH
Heating
Output M
BH
Refrigerant
Com
ments
Flexaire Furnace1
Flexaire - Jackson & C
hurchSD
F60-GFI
--
PoorN
atural Gas
750600
-G
arage - Unit approxim
ately 55 years oldA
ir Handling and C
ondensing Unit
1A
merican Standard
AU
D060C
924K1
-24
Good
Natural G
as60
54H
CFC
-22Front O
ffice / Meeting R
oomA
ir Handling and C
ondensing Unit
1H
eilN
BC
M024X
KB
2L921076687
24G
oodElectricity
15 kW15 kW
HC
FC-22
Original O
fficesA
ir Handling and C
ondensing Unit
1A
merican Standard
AU
DC
60 / 7A0036A
100A0
-36
Good
Natural G
as60
48R
-22W
ood Working Shop
Unit H
eaters2
TraneG
HN
D012A
E-MF05H
39223 / F05H39222
-G
oodN
atural Gas
125100
-Pole B
arnG
arage Exhaust Fans2
Not Available
--
-G
ood-
--
-M
anufacturer and model num
ber unavailable.
APPENDIX C
ECM-1 Lighting Fixture Modifications
BP
U E
NER
GY
AU
DIT
PR
OG
RA
MB
oro
ug
h o
f Mo
un
tain
Lakes D
ep
artm
en
t of P
ub
lic Wo
rks G
ara
ge
CH
A P
roje
ct #2
17
95
EC
M-1
Ligh
ting
Fixtu
re M
od
ificatio
ns
Electricity
Natural G
asTotal
$K
WH
Therms
$$
YearsYears
A-Lam
p to CFLs
90$
1400-
$ 250
$ -
$ 0.4
0.4T12 Fixtures to T8 Fixtures
5,200$
4670-
$ 802
$ 870
$ 6.5
5.4
Com
bined5,290
$ 6070
1,052$
870$
5.04.2
ItemPayback
(With Incentive)
Budgetary C
osts A
nnual Utility Savings
Potential Incentive
Payback (W
ithout Incentive)
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-1
Ligh
ting
Fixtu
re M
od
ificatio
ns
LocationFixture D
escriptionN
o. of Fixture
Lamp Type &
No.
Ballast Type &
N
o.Fixture W
attsTotal W
attsH
ours of O
perationC
ontrolkw
h/YearO
perational C
ost/YearEntrance H
all4' Fluorescent Surface M
ounted3
(2) T-8, 34W(1) Electronic
62186
2600Sw
itch484
$83.13Front O
ffice4'x1' Fluorescent Surface M
ounted4
(2) T-8, 34W(1) Electronic
62248
2250Sw
itch558
$95.92Front O
ffice Restroom
Nutone Light/Exhaust Fan C
ombination Fixture
1(1) A
-Lamp, 60W
-60
60260
Switch
16$2.68
IT Closet
4'x1' Fluorescent Surface Mounted
1(2) T-8, 34W
(1) Electronic62
62260
Switch
16$2.77
Meeting R
oomIncandescent H
igh Hat
6(1) A
-Lamp, 60W
-60
360104
Switch
37$6.44
Meeting R
oom4'x1' Fluorescent Surface M
ounted4
(2) T-8, 34W(1) Electronic
62248
2250Sw
itch558
$95.92C
orridor4'x1' Fluorescent Surface M
ounted2
(2) T-8, 34W(1) Electronic
62124
2600Sw
itch322
$55.42O
ffice4'x2' Fluorescent Surface M
ounted2
(4) T-8, 34W(1) Electronic
114228
2250Sw
itch513
$88.18O
fficeIncandescent H
igh Hat
12(1) A
-Lamp, 65W
-65
7802250
Switch
1755$301.68
Locker Room
4'x1' Fluorescent Surface Mounted
2(2) T-8, 34W
(1) Electronic62
1242250
Switch
279$47.96
Men's R
oom/Locker
4'x1' Fluorescent Surface Mounted
2(2) T-8, 34W
(1) Electronic62
1242250
Switch
279$47.96
Mechanical R
oom4'x2' Fluorescent Surface M
ounted2
(2) T-8, 34W(1) Electronic
62124
260Sw
itch32
$5.54G
arage Office/Storage
4'x2' Fluorescent Surface Mounted
3(4) T-8, 34W
(1) Electronic114
3422250
Switch
770$132.28
Garage
4' Fluorescent Utility Fixture
20(2) T-8, 34W
(1) Electronic62
12402250
Switch
2790$479.60
Garage
4' Fluorescent Utility Fixture
16(2) T-8, 34W
(1) Electronic62
992570
Switch
565$97.20
Garage
8' Fluorescent Utility Fixture
3(2) T-12, 110 W
(1) Magnetic
252756
2080Sw
itch1572
$270.31G
arage8' Fluorescent U
tility Fixture8
(2) T-12, 110 W(1) M
agnetic252
20162080
Switch
4193$720.82
Garage
8' Fluorescent Utility Fixture
8(2) T-12, 110 W
(1) Magnetic
2522016
2080Sw
itch4193
$720.82G
arage4' Fluorescent Strip
2(2) T-8, 34W
(1) Electronic62
124570
Switch
71$12.15
Garage
Fire Extinguisher Lights5
LED-
1.26
8760B
reaker53
Wood Shop
8' Fluorescent Strip10
(2) T-12, 110 W (1) M
agnetic252
25201125
Switch
2835$487.34
ExteriorB
uilding Mounted Flood Light
5-
04380
Photocell0
$0.00Exterior
Building M
ounted High Pressure Sodium
Fixture6
(1) HPS, 50W
(1) Magnetic
61366
4380Photocell
1603$275.57
ExteriorB
uilding Mounted M
etal Halide Fixture
1(1) M
H, 400W
(1) Magnetic
461461
4380Photocell
2019$347.10
ExteriorPole M
ounted Metal H
alide Fixture4
(1) MH
, 400W(1) M
agnetic461
18444380
Photocell8077
$1,388.39
Salt ShedM
etal Halide Fixture
2(1) M
H, 500W
(1) Magnetic
561-
4380Photocell
--
Pole Barn
Metal H
alide1
MH
, 400W-
461461
1125Sw
itch519
$0.00Pole B
arnM
etal Halide
1M
H, 400W
-461
4611125
Switch
519$89.15
Pole Barn
4'x2' Fluorescent Fixture10
(4) T-8, 34W(1) Electronic
1141140
1125Sw
itch1283
$220.46Pole B
arn4'x2' Fluorescent Fixture
10(4) T-8, 34W
(1) Electronic114
11401125
Switch
1283$220.46
TOTA
L
Energy Cost:
$0.1719
Notes:
Existing L
ighting Fixture ScheduleTotal W
atts = No. of Fixture x Fixture W
attskw
h/Year = Total Watts/1000 x H
ours of Operation
Operational C
ost/Year = kwh/Year x Energy C
ost
EX
ISTIN
G L
IGH
TIN
G FIX
TU
RE
S AN
D C
ON
TR
OL
S
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
LocationFixture D
escription with System
Watts
Controls
kwh/Year
Operational
Cost/Year
Fixture Description
No. of
FixturesFixture W
attsTotal W
attsH
ours of O
perationkw
h/YearO
perational C
ostsInstalled C
ost Per Fixture
Total Installed C
ostkw
h/YearYearly $ Savings
Payback in Years
Entrance Hall
4' Fluorescent Surface Mounted
Switch
484$83.20
3Front O
ffice4'x1' Fluorescent Surface M
ountedSw
itch558
$95.924
Front Office R
estroomN
utone Light/Exhaust Fan Com
bination FixtureSw
itch16
$2.751
IT Closet
4'x1' Fluorescent Surface Mounted
Switch
16$2.75
1M
eeting Room
Incandescent High H
atSw
itch37
$6.36C
ompact Fluorescent Lam
p, 15W6
1590
1049
$1.61$5.00
$30.0028
$4.756.3
Meeting R
oom4'x1' Fluorescent Surface M
ountedSw
itch558
$95.924
Corridor
4'x1' Fluorescent Surface Mounted
Switch
322$55.35
2O
ffice4'x2' Fluorescent Surface M
ountedSw
itch513
$88.182
Office
Incandescent High H
atSw
itch1755
$301.68C
ompact Fluorescent Lam
p, 15W12
15180
2250405
$69.62$5.00
$60.001350
$232.070.3
Locker Room
4'x1' Fluorescent Surface Mounted
Switch
279$47.96
2M
en's Room
/Locker4'x1' Fluorescent Surface M
ountedSw
itch279
$47.962
Mechanical R
oom4'x2' Fluorescent Surface M
ountedSw
itch32
$5.502
Garage O
ffice/Storage4'x2' Fluorescent Surface M
ountedSw
itch770
$132.363
Garage
4' Fluorescent Utility Fixture
Switch
2790$479.60
20G
arage4' Fluorescent U
tility FixtureSw
itch565
$97.1216
Garage
8' Fluorescent Utility Fixture
Switch
1572$270.23
8' Fluorscent Utility Fixture, (2) T-8, 86 W
3160
4802080
998$171.62
$150.00$450.00
574$98.60
4.6G
arage8' Fluorescent U
tility FixtureSw
itch4193
$720.788' Fluorscent U
tility Fixture, (2) T-8, 86 W8
1601280
20802662
$457.67$150.00
$1,200.001531
$263.114.6
Garage
8' Fluorescent Utility Fixture
Switch
4193$720.78
8' Fluorscent Utility Fixture, (2) T-8, 86 W
8160
12802080
2662$457.67
$150.00$1,200.00
1531$263.11
4.6G
arage4' Fluorescent Strip
Switch
71$12.20
2G
arageFire Extinguisher Lights
Breaker
53$9.11
5W
ood Shop8' Fluorescent Strip
Switch
2835$487.34
8' Fluorscent Utility Fixture, (2) T-8, 86 W
10160
16001125
1800$309.42
$150.00$1,500.00
1035$177.92
8.4Exterior
Building M
ounted Flood LightPhotocell
0$0.00
5Exterior
Building M
ounted High Pressure Sodium
FixturePhotocell
1603$275.56
6Exterior
Building M
ounted Metal H
alide FixturePhotocell
2019$347.07
1Exterior
Pole Mounted M
etal Halide Fixture
Photocell8077
$1,388.444
Salt ShedM
etal Halide Fixture
Photocell0
$0.002
Pole Barn
Switch
0$0.00
1Pole B
arnSw
itch0
$0.001
Pole Barn
4'x2' Fluorescent FixtureSw
itch1233
$211.9510
Pole Barn
4'x2' Fluorescent FixtureSw
itch1233
$211.9510
$0.00
Total$4,440.00
60471040
4.3Energy C
ost:$0.1719
* Installed cost per fixture includes $30 per fixture incentive when converting from
T-12 to T-8
Notes:
Lighting Fixture R
eplacement Savings
Total Watts = N
o. of Fixture x Fixture Watts
kwh/Year = Total W
atts/1000 x Hours of O
perationO
perational Cost/Year = kw
h/Year x Energy Cost
Total Installed Cost = N
umber of Fixtures x Installed C
ost Per FixtureYearly $ Savings = Savings kw
h/Year x Energy Cost
Payback in Years = Total Installed Cost/Yearly $ Savings
Lighting Fixture Replacem
ent SavingsExisting Fixtures
SavingsProposed R
eplacement Fixture
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-1 L
ighting Fixture Modifications
T-12 to T-8 FixturesMaterial
1Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
8', 2 Lamp, T-12 to T-8 Fixture
29ea
$81$49
$0$2,349
$1,719$0
$4,068$870
$4,068$407$407$407
$5,289
$870Total C
ost with Incentive
$4,419
Multipliers
Subtotal
Installation Costs
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ost w/o
IncentiveR
emarks
10% O
H
Incentive Available
Incentive
Total
10% Profit
10% C
ontingency
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-1 L
ighting Fixture Modifications
A-L
amp to C
FLMaterial
1Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
Com
pact Fluorescent Lamp
18ea
$6$0
$0$107
$0$0
$107$0
$107
Multipliers
Installation Costs
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ost w/o
IncentiveR
emarks
Incentive Available
Subtotal
APPENDIX D
ECM-2 Lighting Control Modifications
BP
U E
NER
GY
AU
DIT
PR
OG
RA
MB
oro
ug
h o
f Mo
un
tain
Lakes D
ep
artm
en
t of P
ub
lic Wo
rks G
ara
ge
CH
A P
roje
ct #2
17
95
EC
M-2
Ligh
ting
Co
ntro
l Mo
difica
tion
s
Electricity
Natural G
asTotal
$K
WH
Therms
$$
YearsYears
Motion S
ensor Control
Areas Indicated
550$
19,4000
110$
2.0140
$ 5.0
3.7
ItemPayback
(With Incentive)
Budgetary C
osts A
nnual Utility Savings
RO
IPotential Incentive
Payback (W
ithout Incentive)
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-2
Ligh
ting
Co
ntro
l Mo
difica
tion
s
LocationFixture D
escriptionN
o. of Fixture
Lamp Type &
No.
Ballast Type &
N
o.Fixture W
attsTotal W
attsH
ours of O
perationC
ontrolkw
h/YearO
perational C
ost/YearEntrance H
all4' Fluorescent Surface M
ounted3
(2) T-8, 34W(1) Electronic
62186
2600Sw
itch484
$0.00Front O
ffice4'x1' Fluorescent Surface M
ounted4
(2) T-8, 34W(1) Electronic
62248
2250Sw
itch558
$0.00Front O
ffice Restroom
Nutone Light/Exhaust Fan C
ombination Fixture
1(1) A
-Lamp, 60W
-60
60260
Switch
16$0.00
IT Closet
4'x1' Fluorescent Surface Mounted
1(2) T-8, 34W
(1) Electronic62
62260
Switch
16$0.00
Meeting R
oomH
igh Hat
6(1) C
FL, 15W-
1590
104Sw
itch9
$0.00M
eeting Room
4'x1' Fluorescent Surface Mounted
4(2) T-8, 34W
(1) Electronic62
2482250
Switch
558$0.00
Corridor
4'x1' Fluorescent Surface Mounted
2(2) T-8, 34W
(1) Electronic62
1242600
Switch
322$0.00
Office
4'x2' Fluorescent Surface Mounted
2(4) T-8, 34W
(1) Electronic114
2282250
Switch
513$0.00
Office
High H
at12
(1) CFL, 15W
-15
1802250
Switch
405$0.00
Locker Room
4'x1' Fluorescent Surface Mounted
2(2) T-8, 34W
(1) Electronic62
1242250
Switch
279$0.00
Men's R
oom/Locker
4'x1' Fluorescent Surface Mounted
2(2) T-8, 34W
(1) Electronic62
1242250
Switch
279$0.00
Mechanical R
oom4'x2' Fluorescent Surface M
ounted2
(2) T-8, 34W(1) Electronic
62124
260Sw
itch32
$0.00G
arage Office/Storage
4'x2' Fluorescent Surface Mounted
3(4) T-8, 34W
(1) Electronic114
3422250
Switch
770$0.00
Garage
4' Fluorescent Utility Fixture
20(2) T-8, 34W
(1) Electronic62
12402250
Switch
2790$0.00
Garage
4' Fluorescent Utility Fixture
16(2) T-8, 34W
(1) Electronic62
992570
Switch
565$0.00
Garage
8' Fluorescent Utility Fixture
3(2) T-8, 86 W
(1) Magnetic
160480
2080Sw
itch998
$0.00G
arage8' Fluorescent U
tility Fixture8
(2) T-8, 86 W(1) M
agnetic160
12802080
Switch
2662$0.00
Garage
8' Fluorescent Utility Fixture
8(2) T-8, 86 W
(1) Magnetic
1601280
2080Sw
itch2662
$0.00G
arage4' Fluorescent Strip
2(2) T-8, 34W
(1) Electronic62
124570
Switch
71$0.00
Garage
Fire Extinguisher Lights5
LED-
1.26
8760B
reaker53
Wood Shop
8' Fluorescent Strip10
(2) T-8, 86 W (1) M
agnetic160
16001125
Switch
1800$0.00
ExteriorB
uilding Mounted Flood Light
5-
04380
Photocell0
$0.00Exterior
Building M
ounted High Pressure Sodium
Fixture6
(1) HPS, 50W
(1) Magnetic
61366
4380Photocell
1603$0.00
ExteriorB
uilding Mounted M
etal Halide Fixture
1(1) M
H, 400W
(1) Magnetic
461461
4380Photocell
2019$0.00
ExteriorPole M
ounted Metal H
alide Fixture4
(1) MH
, 400W(1) M
agnetic461
18444380
Photocell8077
$0.00
Salt ShedM
etal Halide Fixture
2(1) M
H, 500W
(1) Magnetic
561-
4380Photocell
--
Pole Barn
Metal H
alide1
MH
, 400W-
461461
1125Sw
itch519
$89.15Pole B
arnM
etal Halide
1M
H, 400W
-461
4611125
Switch
519$0.00
Pole Barn
4'x2' Fluorescent Fixture10
(4) T-8, 34W(1) Electronic
1141140
1125Sw
itch1283
$0.00Pole B
arn4'x2' Fluorescent Fixture
10(4) T-8, 34W
(1) Electronic114
11401125
Switch
1283$0.00
TOTA
L
Energy Cost:
$0.1719
Notes:
Existing L
ighting Fixture ScheduleTotal W
atts = No. of Fixture x Fixture W
attskw
h/Year = Total Watts/1000 x H
ours of Operation
Operational C
ost/Year = kwh/Year x Energy C
ost
LIG
HT
ING
FIXT
UR
ES A
ND
CO
NT
RO
LS A
S PRO
POSE
D IN
EC
M-1
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-2
Ligh
ting
Co
ntro
l Mo
difica
tion
sMaterial
0.98Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
Motion Sensor (W
all Mounted)
6ea
25$
50$
147$
363$
-$
510$
120$
510$ 51$ 56$ 62$ 679$ 120$
Total Cost w
ith Incentive559
$
10% O
H
Incentive Available
Incentive
Total
10% Profit
10% C
ontingency
Multipliers
Subtotal
Insta
llatio
n C
osts
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ost w/o
IncentiveR
emarks
BPU ENERGY AUDIT PROGRAMBorough of Mountain Lakes Department of Public Works Garage
CHA Project #21795
Location Fixture Description No. of Fixtures
Lamp Type & No. Total Watts Hours of Operation
Control kwh/Year Operational Cost/Year
Modified Control
New Hours of
Operation
kwh/Year Operational Cost/Year
Installation Cost*
Cost Savings/Year Payback in Years
Entrance Hall 4' Fluorescent Surface Mounted 3 (2) T-8, 34W 186 2600 Switch 484 83 -Front Office 4'x1' Fluorescent Surface Mounted 4 (2) T-8, 34W 248 2250 Switch 558 96 Motion Sensor 1,688 419 $71.94 $93.14 $23.98 3.9
Front Office Restroom Nutone Light/Exhaust Fan Combination Fixture 1 (1) A-Lamp, 60W 60 260 Switch 16 3 -IT Closet 4'x1' Fluorescent Surface Mounted 1 (2) T-8, 34W 62 260 Switch 16 3 -
Meeting Room High Hat 6 (1) CFL, 15W 90 104 Switch 9 2 -Meeting Room 4'x1' Fluorescent Surface Mounted 4 (2) T-8, 34W 248 2250 Switch 558 96 Motion Sensor 1,688 419 $71.94 $93.14 $23.98 3.9
Corridor 4'x1' Fluorescent Surface Mounted 2 (2) T-8, 34W 124 2600 Switch 322 55 -Office 4'x2' Fluorescent Surface Mounted 2 (4) T-8, 34W 228 2250 Switch 513 88 Motion Sensor 1,688 385 $66.14 $93.14 $22.05 4.2Office High Hat 12 (1) CFL, 15W 180 2250 Switch 405 70 Motion Sensor 1,688 304 $52.21 $93.14 $17.40 5.4
Locker Room 4'x1' Fluorescent Surface Mounted 2 (2) T-8, 34W 124 2250 Switch 279 48 Motion Sensor 1,688 209 $35.97 $93.14 $11.99 7.8Men's Room/Locker 4'x1' Fluorescent Surface Mounted 2 (2) T-8, 34W 124 2250 Switch 279 48 Motion Sensor 1,688 209 $35.97 $93.14 $11.99 7.8Mechanical Room 4'x2' Fluorescent Surface Mounted 2 (2) T-8, 34W 124 260 Switch 32 6 -
Garage Office/Storage 4'x2' Fluorescent Surface Mounted 3 (4) T-8, 34W 342 2250 Switch 770 132 -Garage 4' Fluorescent Utility Fixture 20 (2) T-8, 34W 1240 2250 Switch 2790 480 -Garage 4' Fluorescent Utility Fixture 16 (2) T-8, 34W 992 570 Switch 565 97 -Garage 8' Fluorescent Utility Fixture 3 (2) T-8, 86 W 480 2080 Switch 998 172 -Garage 8' Fluorescent Utility Fixture 8 (2) T-8, 86 W 1280 2080 Switch 2662 458 -Garage 8' Fluorescent Utility Fixture 8 (2) T-8, 86 W 1280 2080 Switch 2662 458 -Garage 4' Fluorescent Strip 2 (2) T-8, 34W 124 570 Switch 71 12 -Garage Fire Extinguisher Lights 5 LED 6 8760 Breaker 53 9 -
Wood Shop 8' Fluorescent Strip 10 (2) T-8, 86 W 1600 1125 Switch 1800 309 -Exterior Building Mounted Flood Light 5 0 4380 Photocell 0 0 -Exterior Building Mounted High Pressure Sodium Fixture 6 (1) HPS, 50W 366 4380 Photocell 1603 276 -Exterior Building Mounted Metal Halide Fixture 1 (1) MH, 400W 461 4380 Photocell 2019 347 -Exterior Pole Mounted Metal Halide Fixture 4 (1) MH, 400W 1844 4380 Photocell 8077 1388 -
Salt Shed Metal Halide Fixture 2 (1) MH, 500W .001 4380 Photocell 0 0 -
Pole Barn Metal Halide 1 MH, 400W 461 1125 Switch 519 89 -Pole Barn Metal Halide 1 MH, 400W 461 1125 Switch 519 89 -Pole Barn 4'x2' Fluorescent Fixture 10 (4) T-8, 34W 1140 1125 Switch 1283 220 -Pole Barn 4'x2' Fluorescent Fixture 10 (4) T-8, 34W 1140 1125 Switch 1283 220 -
Energy Cost: $0.1719
*Installation costs do not include potential incentive.kwh
Savings/YearInstallation
CostCost
Savings/Year Payback in Years1944 $558.84 $111.39 5.0
Notes: Lighting Control ModificationsTotal Watts = No. of Fixture x Fixture Wattskwh/Year = Total Watts/1000 x Hours of OperationOperational Cost/Year = kwh/Year x Energy Cost
Motions Sensors with 10 Years or Less Payback
Existing Lighting Fixture Controls Prooposed Lighting Fixture Controls Savings After Retrofit
APPENDIX E
ECM-3 Replace Heating Unit Serving Garage Area
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-3
Rep
lace
Heatin
g U
nit S
ervin
g G
ara
ge A
rea
Material
0.98Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
Rem
oval of Existing Garage H
&V
Unit
1ea
$0$300
Installation of New
, 92% Efficient, D
irect Fired Unit*
1ea
$13,800$385
$13,524$466
$0$13,990
*Includes electrical and ductwork m
odifications$13,990
10% O
H, 10%
Profit$1,399
10% C
ontingency$1,399
$16,788Total
Multipliers
Subtotal
Insta
llatio
n C
osts
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ostR
emarks
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-3
Rep
lace
Heatin
g U
nit S
ervin
g G
ara
ge A
rea
Electricity
Natural G
asC
ostkW
htherm
s$
Building w
ith Existing Garage H
eating Unit
72,4677,176
22,100.00$
Building w
ith Higher Efficiency G
arage Heating U
nit72,467
6,40021,000.00
$
Difference
0776
1,100.00$
An
nu
al E
nerg
y Use
Co
mp
ariso
n
ECM-3 AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
1. General Details: Air System Name ECM-3 AHU-2 - Original Offices Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Electric Resistance Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-3 Original Offices x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-3 AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1300.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1300.2 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 22.3 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 SEER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Hourly Analysis Program v4.50 Page 2 of 2
ECM-3 AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
1. General Details: Air System Name ECM-3 AHU-1 - Garage Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-3 Garage x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 85.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Garage Schedule Unoccupied Cooling is Not Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Supply Fan Airflow 10580.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hourly Analysis Program v4.50 Page 1 of 2
ECM-3 AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 10580.2 - -
5. Equipment DataCentral Heating Unit - Combustion Estimated Maximum Load 295.9 MBH Equipment Sizing User-Defined Gross Heating Capacity 600.0 MBH Average Efficiency 92.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
ECM-3 AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
1. General Details: Air System Name ECM-3 AHU-3 - Office Addition Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-3 Office Addition x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-3 AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:38PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1445.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1445.2 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 24.5 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 37.5 MBH Equipment Sizing User-Defined Gross Heating Capacity 54.0 MBH Average Efficiency 90.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
ECM-3 AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:39PM
1. General Details: Air System Name ECM-3 AHU-4 - Woodworking Shop Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-3 Wood Shop x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Woodworking Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-3 AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:39PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1418.6 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1418.6 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 26.1 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 36.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 32.0 MBH Equipment Sizing User-Defined Gross Heating Capacity 48.0 MBH Average Efficiency 80.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
Billing Details - Electric - ECM-3 Replace Garage Heating UnitMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
1. Component Charges
BillingPeriod
Energy Charges($)
Demand Charges($)
CustomerCharges
($)Taxes
($)Total Charge
($)Jan 1,510 0 0 0 1,510
Feb 1,297 0 0 0 1,297
Mar 1,235 0 0 0 1,235
Apr 981 0 0 0 981
May 714 0 0 0 714
Jun 812 0 0 0 812
Jul 912 0 0 0 912
Aug 900 0 0 0 900
Sep 756 0 0 0 756
Oct 810 0 0 0 810
Nov 1,114 0 0 0 1,114
Dec 1,415 0 0 0 1,415
Totals 12,457 0 0 0 12,457
2. Totals
BillingPeriod
Total Charges($)
Total Consumption
(kWh)Avg Price
($/kWh)Jan 1,510 8,786 0.1719
Feb 1,297 7,544 0.1719
Mar 1,235 7,183 0.1719
Apr 981 5,708 0.1719
May 714 4,153 0.1719
Jun 812 4,722 0.1719
Jul 912 5,306 0.1719
Aug 900 5,238 0.1719
Sep 756 4,400 0.1719
Oct 810 4,713 0.1719
Nov 1,114 6,481 0.1719
Dec 1,415 8,233 0.1719
Totals 12,457 72,468 0.1719
3. Consumption TotalsBillingPeriod
Peak(kWh)
Mid-Peak(kWh)
Normal Peak(kWh)
Off-Peak(kWh)
Overall(kWh)
Jan 0 0 0 0 8,786
Feb 0 0 0 0 7,544
Mar 0 0 0 0 7,183
Apr 0 0 0 0 5,708
May 0 0 0 0 4,153
Jun 0 0 0 0 4,722
Jul 0 0 0 0 5,306
Aug 0 0 0 0 5,238
Sep 0 0 0 0 4,400
Oct 0 0 0 0 4,713
Nov 0 0 0 0 6,481
Dec 0 0 0 0 8,233
Totals 0 0 0 0 72,468
Hourly Analysis Program v4.50 Page 1 of 2
Billing Details - Electric - ECM-3 Replace Garage Heating UnitMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
4. Billing DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.8
Jun 0.0 0.0 0.0 0.0 25.2
Jul 0.0 0.0 0.0 0.0 26.5
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 24.1
Oct 0.0 0.0 0.0 0.0 23.0
Nov 0.0 0.0 0.0 0.0 25.6
Dec 0.0 0.0 0.0 0.0 27.1
5. Maximum DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.8
Jun 0.0 0.0 0.0 0.0 25.2
Jul 0.0 0.0 0.0 0.0 26.5
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 24.1
Oct 0.0 0.0 0.0 0.0 23.0
Nov 0.0 0.0 0.0 0.0 25.6
Dec 0.0 0.0 0.0 0.0 27.1
6. Time Of Maximum DemandsBillingPeriod
Peak(m/d/h)
Mid-Peak(m/d/h)
Normal Peak(m/d/h)
Off-Peak(m/d/h)
Overall(m/d/h)
Jan n/a n/a n/a n/a 1/25/0900
Feb n/a n/a n/a n/a 2/1/0900
Mar n/a n/a n/a n/a 3/18/0900
Apr n/a n/a n/a n/a 4/8/0900
May n/a n/a n/a n/a 5/17/1400
Jun n/a n/a n/a n/a 6/11/1400
Jul n/a n/a n/a n/a 7/1/1400
Aug n/a n/a n/a n/a 8/4/1400
Sep n/a n/a n/a n/a 9/10/1400
Oct n/a n/a n/a n/a 10/1/1400
Nov n/a n/a n/a n/a 11/22/0900
Dec n/a n/a n/a n/a 12/8/0900
Hourly Analysis Program v4.50 Page 2 of 2
Monthly Component Costs - ECM-3 Replace Garage Heating UnitMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
0
500
1000
1500
2000
2500
3000
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Air System Fans Cooling Heating Lights Electric Equipment
1. HVAC Component Costs
MonthAir System Fans
($)Cooling
($)Heating
($)Pumps
($)Cooling Towers
($)HVAC Total
($)January 101 0 2,952 0 0 3,053
February 84 0 2,303 0 0 2,387
March 74 0 1,695 0 0 1,769
April 55 3 866 0 0 924
May 39 44 0 0 0 83
June 43 116 0 0 0 159
July 48 206 0 0 0 254
August 47 199 0 0 0 246
September 41 63 0 0 0 104
October 41 12 314 0 0 367
November 66 0 1,361 0 0 1,427
December 90 0 2,394 0 0 2,484
Total 729 643 11,886 0 0 13,258
2. Non-HVAC Component Costs
MonthLights
($)
Electric Equipment
($)Misc. Electric
($)Misc. Fuel Use
($)Non-HVAC Total
($)Grand Total
($)January 465 167 0 0 631 3,684
February 438 158 0 0 596 2,983
March 500 182 0 0 681 2,450
April 479 174 0 0 653 1,577
May 465 167 0 0 631 714
June 479 174 0 0 653 812
July 484 174 0 0 658 912
August 481 174 0 0 655 901
September 479 174 0 0 653 757
October 465 167 0 0 631 998
November 479 174 0 0 653 2,080
December 500 182 0 0 681 3,165
Total 5,711 2,065 0 0 7,776 21,034
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Costs - ECM-3 Replace Garage Heating UnitMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
0200400600800
1000120014001600180020002200
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
HVAC Electric HVAC Natural Gas Non-HVAC Electric
1. HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)
Remote Chilled Water
($)January 879 2,175 0 0 0 0 0
February 701 1,687 0 0 0 0 0
March 554 1,215 0 0 0 0 0
April 328 595 0 0 0 0 0
May 83 0 0 0 0 0 0
June 159 0 0 0 0 0 0
July 254 0 0 0 0 0 0
August 246 0 0 0 0 0 0
September 104 0 0 0 0 0 0
October 179 189 0 0 0 0 0
November 461 966 0 0 0 0 0
December 734 1,750 0 0 0 0 0
Total 4,682 8,576 0 0 0 0 0
2. Non-HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)January 631 0 0 0 0 0
February 596 0 0 0 0 0
March 681 0 0 0 0 0
April 653 0 0 0 0 0
May 631 0 0 0 0 0
June 653 0 0 0 0 0
July 658 0 0 0 0 0
August 655 0 0 0 0 0
September 653 0 0 0 0 0
October 631 0 0 0 0 0
November 653 0 0 0 0 0
December 681 0 0 0 0 0
Total 7,776 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Use by Energy Type - ECM-3 Replace Garage Heating UnitMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
1. HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Remote CW
(na)Jan 5,113 1,623 0 0 0 0 0
Feb 4,077 1,259 0 0 0 0 0
Mar 3,221 907 0 0 0 0 0
Apr 1,911 444 0 0 0 0 0
May 481 0 0 0 0 0 0
Jun 925 0 0 0 0 0 0
Jul 1,478 0 0 0 0 0 0
Aug 1,431 0 0 0 0 0 0
Sep 603 0 0 0 0 0 0
Oct 1,041 141 0 0 0 0 0
Nov 2,683 721 0 0 0 0 0
Dec 4,270 1,306 0 0 0 0 0
Totals 27,234 6,400 0 0 0 0 0
2. Non-HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Jan 3,672 0 0 0 0 0
Feb 3,467 0 0 0 0 0
Mar 3,962 0 0 0 0 0
Apr 3,797 0 0 0 0 0
May 3,672 0 0 0 0 0
Jun 3,797 0 0 0 0 0
Jul 3,827 0 0 0 0 0
Aug 3,808 0 0 0 0 0
Sep 3,797 0 0 0 0 0
Oct 3,672 0 0 0 0 0
Nov 3,797 0 0 0 0 0
Dec 3,962 0 0 0 0 0
Totals 45,233 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Mon
thly
Ene
rgy
Use
by
Com
pone
nt -
ECM
-3 R
epla
ce G
arag
e H
eatin
g U
nit
Mou
ntai
n La
kes
- DP
W08
/09/
2010
K
itche
n an
d A
ssoc
iate
s02
:35P
M
1. M
onth
ly E
nerg
y U
se b
y Sy
stem
Com
pone
ntC
ompo
nent
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Air
Sys
tem
Fan
s (k
Wh)
589
491
429
320
224
250
277
275
237
241
383
523
C
oolin
g
E
lect
ric (k
Wh)
00
115
256
675
1201
1156
366
702
0
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
R
emot
e C
W (n
a)0
00
00
00
00
00
0
Hea
ting
E
lect
ric (k
Wh)
4524
3587
2791
1576
00
00
073
022
9937
47
N
atur
al G
as (T
herm
)16
2312
5990
744
40
00
00
141
721
1306
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
P
umps
(kW
h)0
00
00
00
00
00
0
Clg
. Tow
er F
ans
(kW
h)0
00
00
00
00
00
0
Ligh
ting
(kW
h)27
0325
4629
0627
8627
0327
8628
1427
9627
8627
0327
8629
06
Ele
ctric
Eqp
t. (k
Wh)
970
920
1056
1011
970
1011
1014
1012
1011
970
1011
1056
Mis
c. E
lect
ric (k
Wh)
00
00
00
00
00
00
M
isc.
Fue
l
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
Hou
rly A
naly
sis
Pro
gram
v4.
50P
age
1 of
1
Annual Cost SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 1. Annual Costs
Component
ECM-3 Replace Garage Heating
Unit($)
Air System Fans 729
Cooling 643
Heating 11,886
Pumps 0
Cooling Tower Fans 0
HVAC Sub-Total 13,258
Lights 5,711
Electric Equipment 2,065
Misc. Electric 0
Misc. Fuel Use 0
Non-HVAC Sub-Total 7,776
Grand Total 21,034
Table 2. Annual Cost per Unit Floor Area
Component
ECM-3 Replace Garage Heating
Unit($/ft!)
Air System Fans 0.071
Cooling 0.063
Heating 1.154
Pumps 0.000
Cooling Tower Fans 0.000
HVAC Sub-Total 1.287
Lights 0.555
Electric Equipment 0.200
Misc. Electric 0.000
Misc. Fuel Use 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.042
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 1 of 2
Annual Cost SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 3. Component Cost as a Percentage of Total Cost
Component
ECM-3 Replace Garage Heating
Unit( % )
Air System Fans 3.5
Cooling 3.1
Heating 56.5
Pumps 0.0
Cooling Tower Fans 0.0
HVAC Sub-Total 63.0
Lights 27.2
Electric Equipment 9.8
Misc. Electric 0.0
Misc. Fuel Use 0.0
Non-HVAC Sub-Total 37.0
Grand Total 100.0
Hourly Analysis Program v4.50 Page 2 of 2
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 1. Annual Costs
Component
ECM-3 Replace Garage Heating
Unit($)
HVAC Components
Electric 4,682
Natural Gas 8,576
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Remote CW 0
HVAC Sub-Total 13,258
Non-HVAC Components
Electric 7,776
Natural Gas 0
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Non-HVAC Sub-Total 7,776
Grand Total 21,034
Table 2. Annual Energy Consumption
Component
ECM-3 Replace Garage Heating
Unit
HVAC Components
Electric (kWh) 27,234
Natural Gas (Therm) 6,400
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Non-HVAC Components
Electric (kWh) 45,233
Natural Gas (Therm) 0
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Totals
Electric (kWh) 72,467
Natural Gas (Therm) 6,400
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Hourly Analysis Program v4.50 Page 1 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 3. Annual Emissions
Component
ECM-3 Replace Garage Heating
UnitCO2 Equivalent (lb) 0
Table 4. Annual Cost per Unit Floor Area
Component
ECM-3 Replace Garage Heating
Unit($/ft!)
HVAC Components
Electric 0.455
Natural Gas 0.833
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Remote CW 0.000
HVAC Sub-Total 1.287
Non-HVAC Components
Electric 0.755
Natural Gas 0.000
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.042
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 2 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 5. Component Cost as a Percentage of Total Cost
Component
ECM-3 Replace Garage Heating
Unit( % )
HVAC Components
Electric 22.3
Natural Gas 40.8
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Remote CW 0.0
HVAC Sub-Total 63.0
Non-HVAC Components
Electric 37.0
Natural Gas 0.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Non-HVAC Sub-Total 37.0
Grand Total 100.0
Hourly Analysis Program v4.50 Page 3 of 3
APPENDIX F
ECM-4 Provide Radiant Heating in Garage and Setpoint Modification
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-4
Pro
vide R
ad
ian
t Heatin
g in
Gara
ge a
nd
Setp
oin
t Mo
difica
tion
Material
0.98Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
3/4" Natural G
as Piping Modifications
50LF
$4$7
$210$414
$0$624
40 MB
H R
adiant Heating U
nit*2
ea$515
$166$1,009
$402$0
$1,411
*Installation costs include electrical modifications.
$2,035*U
nits are only located around lift area where w
ork occurs. Rest of garage space used for truck and equipm
ent storage.10%
OH
, 10% Profit
$204*A
dditional combustion air is not required based on International Fuel G
as Code requirem
ents. 10%
Contingency
$204
$2,442Total
Multipliers
Subtotal
Insta
llatio
n C
osts
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ostR
emarks
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-4
Pro
vide R
ad
ian
t Heatin
g in
Gara
ge a
nd
Setp
oin
t Mo
difica
tion
Qty
Radiant H
eater Dem
andR
un Time*
Radiant H
eaterRadiant H
eaterB
uilding Natural G
as Use
Building N
atural Gas U
seTotal G
as Use
(MB
H)
(hrs)(M
BT
Us)
(Therm
s)80%
Efficient H
&V
Unit (T
herms)
92% E
fficint H&
V U
nit Per EC
M-3 (T
herms)
(Therm
s)
40 MB
H R
adiant Heater w
/ 80% Efficient H
&V
Unit
280
61048800
4885,617
06,105
40 MB
H R
adiant Heater w
/ 92% Efficient H
&V
Unit
280
61048800
4880
5,0455,533
*Assum
es 4 hours per day, 5 days a week, over 7 heating m
onths.A
ctual run time m
ay be less during the transitional months
Rad
ian
t Heate
rs An
nu
al E
nerg
y Use
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-4
Pro
vide R
ad
ian
t Heatin
g in
Gara
ge a
nd
Setp
oin
t Mo
difica
tion
Electricity
Natural G
asC
ostkW
htherm
s$
Existing Garage H
eating Unit
72,4676,400
21,000.00$
Radiant H
eating with Existing U
nit Setback71,572
6,10520,500.00
$
Difference
895295
500.00$
Electricity
Natural G
asC
ostkW
htherm
s$
Existing Garage H
eating Unit
72,4676,400
21,000.00$
Radiant H
eating with 92%
Efficient Unit Setback
71,5725,533
19,700.00$
Difference
895867
1,300.00$
An
nu
al E
nerg
y Use
Co
mp
ariso
n (8
0%
Efficie
nt H
&V
Un
it)
An
nu
al E
nerg
y Use
Co
mp
ariso
n (9
2%
Efficie
nt H
&V
Un
it)
Billing Details - Electric - ECM-4b Spot Heating in Garage 80% UnitMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
1. Component Charges
BillingPeriod
Energy Charges($)
Demand Charges($)
CustomerCharges
($)Taxes
($)Total Charge
($)Jan 1,491 0 0 0 1,491
Feb 1,280 0 0 0 1,280
Mar 1,218 0 0 0 1,218
Apr 968 0 0 0 968
May 706 0 0 0 706
Jun 803 0 0 0 803
Jul 903 0 0 0 903
Aug 892 0 0 0 892
Sep 748 0 0 0 748
Oct 800 0 0 0 800
Nov 1,098 0 0 0 1,098
Dec 1,397 0 0 0 1,397
Totals 12,303 0 0 0 12,303
2. Totals
BillingPeriod
Total Charges($)
Total Consumption
(kWh)Avg Price
($/kWh)Jan 1,491 8,674 0.1719
Feb 1,280 7,446 0.1719
Mar 1,218 7,086 0.1719
Apr 968 5,629 0.1719
May 706 4,105 0.1719
Jun 803 4,671 0.1719
Jul 903 5,255 0.1719
Aug 892 5,187 0.1719
Sep 748 4,349 0.1719
Oct 800 4,654 0.1719
Nov 1,098 6,390 0.1719
Dec 1,397 8,126 0.1719
Totals 12,303 71,572 0.1719
3. Consumption TotalsBillingPeriod
Peak(kWh)
Mid-Peak(kWh)
Normal Peak(kWh)
Off-Peak(kWh)
Overall(kWh)
Jan 0 0 0 0 8,674
Feb 0 0 0 0 7,446
Mar 0 0 0 0 7,086
Apr 0 0 0 0 5,629
May 0 0 0 0 4,105
Jun 0 0 0 0 4,671
Jul 0 0 0 0 5,255
Aug 0 0 0 0 5,187
Sep 0 0 0 0 4,349
Oct 0 0 0 0 4,654
Nov 0 0 0 0 6,390
Dec 0 0 0 0 8,126
Totals 0 0 0 0 71,572
Hourly Analysis Program v4.50 Page 1 of 2
Billing Details - Electric - ECM-4b Spot Heating in Garage 80% UnitMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
4. Billing DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 28.9
Feb 0.0 0.0 0.0 0.0 26.9
Mar 0.0 0.0 0.0 0.0 26.3
Apr 0.0 0.0 0.0 0.0 25.3
May 0.0 0.0 0.0 0.0 25.4
Jun 0.0 0.0 0.0 0.0 24.9
Jul 0.0 0.0 0.0 0.0 26.1
Aug 0.0 0.0 0.0 0.0 25.0
Sep 0.0 0.0 0.0 0.0 23.7
Oct 0.0 0.0 0.0 0.0 22.6
Nov 0.0 0.0 0.0 0.0 25.2
Dec 0.0 0.0 0.0 0.0 26.8
5. Maximum DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 28.9
Feb 0.0 0.0 0.0 0.0 26.9
Mar 0.0 0.0 0.0 0.0 26.3
Apr 0.0 0.0 0.0 0.0 25.3
May 0.0 0.0 0.0 0.0 25.4
Jun 0.0 0.0 0.0 0.0 24.9
Jul 0.0 0.0 0.0 0.0 26.1
Aug 0.0 0.0 0.0 0.0 25.0
Sep 0.0 0.0 0.0 0.0 23.7
Oct 0.0 0.0 0.0 0.0 22.6
Nov 0.0 0.0 0.0 0.0 25.2
Dec 0.0 0.0 0.0 0.0 26.8
6. Time Of Maximum DemandsBillingPeriod
Peak(m/d/h)
Mid-Peak(m/d/h)
Normal Peak(m/d/h)
Off-Peak(m/d/h)
Overall(m/d/h)
Jan n/a n/a n/a n/a 1/25/0900
Feb n/a n/a n/a n/a 2/1/0900
Mar n/a n/a n/a n/a 3/18/0900
Apr n/a n/a n/a n/a 4/8/0900
May n/a n/a n/a n/a 5/17/1400
Jun n/a n/a n/a n/a 6/11/1400
Jul n/a n/a n/a n/a 7/1/1400
Aug n/a n/a n/a n/a 8/4/1400
Sep n/a n/a n/a n/a 9/10/1400
Oct n/a n/a n/a n/a 10/1/1400
Nov n/a n/a n/a n/a 11/22/0900
Dec n/a n/a n/a n/a 12/8/0900
Hourly Analysis Program v4.50 Page 2 of 2
ECM-4b Spot Heating in Garage 80% Unit Input DataMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:15AM
1. General Details: Building Name ECM-4b Spot Heating in Garage 80% Unit
2. Plants Included in this Building: None
3. Air Systems Included in this Building:
System Name Mult.ECM-4b AHU-1 - Garage 1ECM-4b AHU-2 - Original Of 1ECM-4b AHU-3 - Office Addi 1ECM-4b AHU-4 - Woodworking 1
4: Miscellaneous Energy (no items defined)
5: Meters Electric Electric Rate Natural Gas Natural Gas Rates
6: Miscellaneous Data Average Building Power Factor 100.00 % Source Electric Generating Efficiency 28.00 % Additional Floor Area 0.0 ft!
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Component Costs - ECM-4b Spot Heating in Garage 80% UnitMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
0
500
1000
1500
2000
2500
3000
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Air System Fans Cooling Heating Lights Electric Equipment
1. HVAC Component Costs
MonthAir System Fans
($)Cooling
($)Heating
($)Pumps
($)Cooling Towers
($)HVAC Total
($)January 82 0 2,868 0 0 2,950
February 67 0 2,193 0 0 2,260
March 57 0 1,503 0 0 1,560
April 41 3 676 0 0 720
May 30 44 0 0 0 74
June 34 116 0 0 0 150
July 39 206 0 0 0 245
August 39 199 0 0 0 238
September 32 63 0 0 0 95
October 31 12 181 0 0 224
November 50 0 1,155 0 0 1,205
December 72 0 2,260 0 0 2,332
Total 575 643 10,836 0 0 12,054
2. Non-HVAC Component Costs
MonthLights
($)
Electric Equipment
($)Misc. Electric
($)Misc. Fuel Use
($)Non-HVAC Total
($)Grand Total
($)January 465 167 0 0 631 3,581
February 438 158 0 0 596 2,856
March 500 182 0 0 681 2,241
April 479 174 0 0 653 1,373
May 465 167 0 0 631 705
June 479 174 0 0 653 803
July 484 174 0 0 658 903
August 481 174 0 0 655 893
September 479 174 0 0 653 748
October 465 167 0 0 631 855
November 479 174 0 0 653 1,858
December 500 182 0 0 681 3,013
Total 5,711 2,065 0 0 7,776 19,830
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Costs - ECM-4b Spot Heating in Garage 80% UnitMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
0200400600800
100012001400160018002000
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
HVAC Electric HVAC Natural Gas Non-HVAC Electric
1. HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)
Remote Chilled Water
($)January 860 2,091 0 0 0 0 0
February 684 1,576 0 0 0 0 0
March 537 1,024 0 0 0 0 0
April 315 405 0 0 0 0 0
May 74 0 0 0 0 0 0
June 150 0 0 0 0 0 0
July 245 0 0 0 0 0 0
August 237 0 0 0 0 0 0
September 95 0 0 0 0 0 0
October 169 55 0 0 0 0 0
November 446 759 0 0 0 0 0
December 716 1,616 0 0 0 0 0
Total 4,528 7,526 0 0 0 0 0
2. Non-HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)January 631 0 0 0 0 0
February 596 0 0 0 0 0
March 681 0 0 0 0 0
April 653 0 0 0 0 0
May 631 0 0 0 0 0
June 653 0 0 0 0 0
July 658 0 0 0 0 0
August 655 0 0 0 0 0
September 653 0 0 0 0 0
October 631 0 0 0 0 0
November 653 0 0 0 0 0
December 681 0 0 0 0 0
Total 7,776 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Use by Energy Type - ECM-4b Spot Heating in Garage 80% UnitMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
1. HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Remote CW
(na)Jan 5,001 1,560 0 0 0 0 0
Feb 3,979 1,176 0 0 0 0 0
Mar 3,124 764 0 0 0 0 0
Apr 1,832 303 0 0 0 0 0
May 432 0 0 0 0 0 0
Jun 874 0 0 0 0 0 0
Jul 1,427 0 0 0 0 0 0
Aug 1,380 0 0 0 0 0 0
Sep 552 0 0 0 0 0 0
Oct 981 41 0 0 0 0 0
Nov 2,593 567 0 0 0 0 0
Dec 4,163 1,206 0 0 0 0 0
Totals 26,339 5,617 0 0 0 0 0
2. Non-HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Jan 3,672 0 0 0 0 0
Feb 3,467 0 0 0 0 0
Mar 3,962 0 0 0 0 0
Apr 3,797 0 0 0 0 0
May 3,672 0 0 0 0 0
Jun 3,797 0 0 0 0 0
Jul 3,827 0 0 0 0 0
Aug 3,808 0 0 0 0 0
Sep 3,797 0 0 0 0 0
Oct 3,672 0 0 0 0 0
Nov 3,797 0 0 0 0 0
Dec 3,962 0 0 0 0 0
Totals 45,233 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Mon
thly
Ene
rgy
Use
by
Com
pone
nt -
ECM
-4b
Spot
Hea
ting
in G
arag
e 80
% U
nit
Mou
ntai
n La
kes
- DP
W09
/17/
2010
K
itche
n an
d A
ssoc
iate
s09
:16A
M
1. M
onth
ly E
nerg
y U
se b
y Sy
stem
Com
pone
ntC
ompo
nent
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Air
Sys
tem
Fan
s (k
Wh)
477
393
332
241
176
199
226
224
186
181
292
416
C
oolin
g
E
lect
ric (k
Wh)
00
115
256
675
1201
1156
366
702
0
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
R
emot
e C
W (n
a)0
00
00
00
00
00
0
Hea
ting
E
lect
ric (k
Wh)
4524
3587
2791
1576
00
00
073
022
9937
47
N
atur
al G
as (T
herm
)15
6011
7676
430
30
00
00
4156
712
06
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
P
umps
(kW
h)0
00
00
00
00
00
0
Clg
. Tow
er F
ans
(kW
h)0
00
00
00
00
00
0
Ligh
ting
(kW
h)27
0325
4629
0627
8627
0327
8628
1427
9627
8627
0327
8629
06
Ele
ctric
Eqp
t. (k
Wh)
970
920
1056
1011
970
1011
1014
1012
1011
970
1011
1056
Mis
c. E
lect
ric (k
Wh)
00
00
00
00
00
00
M
isc.
Fue
l
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
Hou
rly A
naly
sis
Pro
gram
v4.
50P
age
1 of
1
Annual Cost SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
Table 1. Annual Costs
Component
ECM-4b Spot Heating in Garage
80% Unit($)
Air System Fans 575
Cooling 643
Heating 10,836
Pumps 0
Cooling Tower Fans 0
HVAC Sub-Total 12,054
Lights 5,711
Electric Equipment 2,065
Misc. Electric 0
Misc. Fuel Use 0
Non-HVAC Sub-Total 7,776
Grand Total 19,830
Table 2. Annual Cost per Unit Floor Area
Component
ECM-4b Spot Heating in Garage
80% Unit($/ft!)
Air System Fans 0.056
Cooling 0.063
Heating 1.052
Pumps 0.000
Cooling Tower Fans 0.000
HVAC Sub-Total 1.170
Lights 0.555
Electric Equipment 0.200
Misc. Electric 0.000
Misc. Fuel Use 0.000
Non-HVAC Sub-Total 0.755
Grand Total 1.925
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 1 of 2
Annual Cost SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
Table 3. Component Cost as a Percentage of Total Cost
Component
ECM-4b Spot Heating in Garage
80% Unit( % )
Air System Fans 2.9
Cooling 3.2
Heating 54.6
Pumps 0.0
Cooling Tower Fans 0.0
HVAC Sub-Total 60.8
Lights 28.8
Electric Equipment 10.4
Misc. Electric 0.0
Misc. Fuel Use 0.0
Non-HVAC Sub-Total 39.2
Grand Total 100.0
Hourly Analysis Program v4.50 Page 2 of 2
Annual Energy and Emissions SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
Table 1. Annual Costs
Component
ECM-4b Spot Heating in Garage
80% Unit($)
HVAC Components
Electric 4,528
Natural Gas 7,526
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Remote CW 0
HVAC Sub-Total 12,054
Non-HVAC Components
Electric 7,776
Natural Gas 0
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Non-HVAC Sub-Total 7,776
Grand Total 19,830
Table 2. Annual Energy Consumption
Component
ECM-4b Spot Heating in Garage
80% Unit
HVAC Components
Electric (kWh) 26,339
Natural Gas (Therm) 5,617
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Non-HVAC Components
Electric (kWh) 45,233
Natural Gas (Therm) 0
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Totals
Electric (kWh) 71,572
Natural Gas (Therm) 5,617
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Hourly Analysis Program v4.50 Page 1 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
Table 3. Annual Emissions
Component
ECM-4b Spot Heating in Garage
80% UnitCO2 Equivalent (lb) 0
Table 4. Annual Cost per Unit Floor Area
Component
ECM-4b Spot Heating in Garage
80% Unit($/ft!)
HVAC Components
Electric 0.440
Natural Gas 0.731
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Remote CW 0.000
HVAC Sub-Total 1.170
Non-HVAC Components
Electric 0.755
Natural Gas 0.000
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Non-HVAC Sub-Total 0.755
Grand Total 1.925
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 2 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:16AM
Table 5. Component Cost as a Percentage of Total Cost
Component
ECM-4b Spot Heating in Garage
80% Unit( % )
HVAC Components
Electric 22.8
Natural Gas 38.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Remote CW 0.0
HVAC Sub-Total 60.8
Non-HVAC Components
Electric 39.2
Natural Gas 0.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Non-HVAC Sub-Total 39.2
Grand Total 100.0
Hourly Analysis Program v4.50 Page 3 of 3
Billing Details - Electric - ECM-4 Spot Heating in GarageMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
1. Component Charges
BillingPeriod
Energy Charges($)
Demand Charges($)
CustomerCharges
($)Taxes
($)Total Charge
($)Jan 1,491 0 0 0 1,491
Feb 1,280 0 0 0 1,280
Mar 1,218 0 0 0 1,218
Apr 968 0 0 0 968
May 706 0 0 0 706
Jun 803 0 0 0 803
Jul 903 0 0 0 903
Aug 892 0 0 0 892
Sep 748 0 0 0 748
Oct 800 0 0 0 800
Nov 1,098 0 0 0 1,098
Dec 1,397 0 0 0 1,397
Totals 12,303 0 0 0 12,303
2. Totals
BillingPeriod
Total Charges($)
Total Consumption
(kWh)Avg Price
($/kWh)Jan 1,491 8,674 0.1719
Feb 1,280 7,446 0.1719
Mar 1,218 7,086 0.1719
Apr 968 5,629 0.1719
May 706 4,105 0.1719
Jun 803 4,671 0.1719
Jul 903 5,255 0.1719
Aug 892 5,187 0.1719
Sep 748 4,349 0.1719
Oct 800 4,654 0.1719
Nov 1,098 6,390 0.1719
Dec 1,397 8,126 0.1719
Totals 12,303 71,572 0.1719
3. Consumption TotalsBillingPeriod
Peak(kWh)
Mid-Peak(kWh)
Normal Peak(kWh)
Off-Peak(kWh)
Overall(kWh)
Jan 0 0 0 0 8,674
Feb 0 0 0 0 7,446
Mar 0 0 0 0 7,086
Apr 0 0 0 0 5,629
May 0 0 0 0 4,105
Jun 0 0 0 0 4,671
Jul 0 0 0 0 5,255
Aug 0 0 0 0 5,187
Sep 0 0 0 0 4,349
Oct 0 0 0 0 4,654
Nov 0 0 0 0 6,390
Dec 0 0 0 0 8,126
Totals 0 0 0 0 71,572
Hourly Analysis Program v4.50 Page 1 of 2
Billing Details - Electric - ECM-4 Spot Heating in GarageMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
4. Billing DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 28.9
Feb 0.0 0.0 0.0 0.0 26.9
Mar 0.0 0.0 0.0 0.0 26.3
Apr 0.0 0.0 0.0 0.0 25.3
May 0.0 0.0 0.0 0.0 25.4
Jun 0.0 0.0 0.0 0.0 24.9
Jul 0.0 0.0 0.0 0.0 26.1
Aug 0.0 0.0 0.0 0.0 25.0
Sep 0.0 0.0 0.0 0.0 23.7
Oct 0.0 0.0 0.0 0.0 22.6
Nov 0.0 0.0 0.0 0.0 25.2
Dec 0.0 0.0 0.0 0.0 26.8
5. Maximum DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 28.9
Feb 0.0 0.0 0.0 0.0 26.9
Mar 0.0 0.0 0.0 0.0 26.3
Apr 0.0 0.0 0.0 0.0 25.3
May 0.0 0.0 0.0 0.0 25.4
Jun 0.0 0.0 0.0 0.0 24.9
Jul 0.0 0.0 0.0 0.0 26.1
Aug 0.0 0.0 0.0 0.0 25.0
Sep 0.0 0.0 0.0 0.0 23.7
Oct 0.0 0.0 0.0 0.0 22.6
Nov 0.0 0.0 0.0 0.0 25.2
Dec 0.0 0.0 0.0 0.0 26.8
6. Time Of Maximum DemandsBillingPeriod
Peak(m/d/h)
Mid-Peak(m/d/h)
Normal Peak(m/d/h)
Off-Peak(m/d/h)
Overall(m/d/h)
Jan n/a n/a n/a n/a 1/25/0900
Feb n/a n/a n/a n/a 2/1/0900
Mar n/a n/a n/a n/a 3/18/0900
Apr n/a n/a n/a n/a 4/8/0900
May n/a n/a n/a n/a 5/17/1400
Jun n/a n/a n/a n/a 6/11/1400
Jul n/a n/a n/a n/a 7/1/1400
Aug n/a n/a n/a n/a 8/4/1400
Sep n/a n/a n/a n/a 9/10/1400
Oct n/a n/a n/a n/a 10/1/1400
Nov n/a n/a n/a n/a 11/22/0900
Dec n/a n/a n/a n/a 12/8/0900
Hourly Analysis Program v4.50 Page 2 of 2
ECM-4 Spot Heating in Garage Input DataMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:15AM
1. General Details: Building Name ECM-4 Spot Heating in Garage
2. Plants Included in this Building: None
3. Air Systems Included in this Building:
System Name Mult.ECM-4 AHU-1 - Garage 1ECM-4 AHU-2 - Original Offices 1ECM-4 AHU-3 - Office Addition 1ECM-4 AHU-4 - Woodworking Shop 1
4: Miscellaneous Energy (no items defined)
5: Meters Electric Electric Rate Natural Gas Natural Gas Rates
6: Miscellaneous Data Average Building Power Factor 100.00 % Source Electric Generating Efficiency 28.00 % Additional Floor Area 0.0 ft!
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Component Costs - ECM-4 Spot Heating in GarageMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
0
500
1000
1500
2000
2500
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Air System Fans Cooling Heating Lights Electric Equipment
1. HVAC Component Costs
MonthAir System Fans
($)Cooling
($)Heating
($)Pumps
($)Cooling Towers
($)HVAC Total
($)January 82 0 2,651 0 0 2,733
February 67 0 2,030 0 0 2,097
March 57 0 1,400 0 0 1,457
April 41 3 639 0 0 683
May 30 44 0 0 0 74
June 34 116 0 0 0 150
July 39 206 0 0 0 245
August 39 199 0 0 0 238
September 32 63 0 0 0 95
October 31 12 179 0 0 222
November 50 0 1,079 0 0 1,129
December 72 0 2,093 0 0 2,165
Total 575 643 10,070 0 0 11,287
2. Non-HVAC Component Costs
MonthLights
($)
Electric Equipment
($)Misc. Electric
($)Misc. Fuel Use
($)Non-HVAC Total
($)Grand Total
($)January 465 167 0 0 631 3,364
February 438 158 0 0 596 2,693
March 500 182 0 0 681 2,138
April 479 174 0 0 653 1,336
May 465 167 0 0 631 705
June 479 174 0 0 653 803
July 484 174 0 0 658 903
August 481 174 0 0 655 893
September 479 174 0 0 653 748
October 465 167 0 0 631 853
November 479 174 0 0 653 1,782
December 500 182 0 0 681 2,846
Total 5,711 2,065 0 0 7,776 19,063
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Costs - ECM-4 Spot Heating in GarageMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
0
200
400
600
800
1000
1200
1400
1600
1800
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
HVAC Electric HVAC Natural Gas Non-HVAC Electric
1. HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)
Remote Chilled Water
($)January 860 1,873 0 0 0 0 0
February 684 1,413 0 0 0 0 0
March 537 920 0 0 0 0 0
April 315 368 0 0 0 0 0
May 74 0 0 0 0 0 0
June 150 0 0 0 0 0 0
July 245 0 0 0 0 0 0
August 237 0 0 0 0 0 0
September 95 0 0 0 0 0 0
October 169 53 0 0 0 0 0
November 446 684 0 0 0 0 0
December 716 1,449 0 0 0 0 0
Total 4,528 6,760 0 0 0 0 0
2. Non-HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)January 631 0 0 0 0 0
February 596 0 0 0 0 0
March 681 0 0 0 0 0
April 653 0 0 0 0 0
May 631 0 0 0 0 0
June 653 0 0 0 0 0
July 658 0 0 0 0 0
August 655 0 0 0 0 0
September 653 0 0 0 0 0
October 631 0 0 0 0 0
November 653 0 0 0 0 0
December 681 0 0 0 0 0
Total 7,776 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Use by Energy Type - ECM-4 Spot Heating in GarageMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
1. HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Remote CW
(na)Jan 5,001 1,398 0 0 0 0 0
Feb 3,979 1,054 0 0 0 0 0
Mar 3,124 687 0 0 0 0 0
Apr 1,832 274 0 0 0 0 0
May 432 0 0 0 0 0 0
Jun 874 0 0 0 0 0 0
Jul 1,427 0 0 0 0 0 0
Aug 1,380 0 0 0 0 0 0
Sep 552 0 0 0 0 0 0
Oct 981 40 0 0 0 0 0
Nov 2,593 510 0 0 0 0 0
Dec 4,163 1,081 0 0 0 0 0
Totals 26,339 5,045 0 0 0 0 0
2. Non-HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Jan 3,672 0 0 0 0 0
Feb 3,467 0 0 0 0 0
Mar 3,962 0 0 0 0 0
Apr 3,797 0 0 0 0 0
May 3,672 0 0 0 0 0
Jun 3,797 0 0 0 0 0
Jul 3,827 0 0 0 0 0
Aug 3,808 0 0 0 0 0
Sep 3,797 0 0 0 0 0
Oct 3,672 0 0 0 0 0
Nov 3,797 0 0 0 0 0
Dec 3,962 0 0 0 0 0
Totals 45,233 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Mon
thly
Ene
rgy
Use
by
Com
pone
nt -
ECM
-4 S
pot H
eatin
g in
Gar
age
Mou
ntai
n La
kes
- DP
W09
/17/
2010
K
itche
n an
d A
ssoc
iate
s09
:14A
M
1. M
onth
ly E
nerg
y U
se b
y Sy
stem
Com
pone
ntC
ompo
nent
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Air
Sys
tem
Fan
s (k
Wh)
477
393
332
241
176
199
226
224
186
181
292
416
C
oolin
g
E
lect
ric (k
Wh)
00
115
256
675
1201
1156
366
702
0
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
R
emot
e C
W (n
a)0
00
00
00
00
00
0
Hea
ting
E
lect
ric (k
Wh)
4524
3587
2791
1576
00
00
073
022
9937
47
N
atur
al G
as (T
herm
)13
9810
5468
727
40
00
00
4051
010
81
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
P
umps
(kW
h)0
00
00
00
00
00
0
Clg
. Tow
er F
ans
(kW
h)0
00
00
00
00
00
0
Ligh
ting
(kW
h)27
0325
4629
0627
8627
0327
8628
1427
9627
8627
0327
8629
06
Ele
ctric
Eqp
t. (k
Wh)
970
920
1056
1011
970
1011
1014
1012
1011
970
1011
1056
Mis
c. E
lect
ric (k
Wh)
00
00
00
00
00
00
M
isc.
Fue
l
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
Hou
rly A
naly
sis
Pro
gram
v4.
50P
age
1 of
1
Annual Cost SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
Table 1. Annual Costs
Component
ECM-4 Spot Heating in Garage
($)Air System Fans 575
Cooling 643
Heating 10,070
Pumps 0
Cooling Tower Fans 0
HVAC Sub-Total 11,287
Lights 5,711
Electric Equipment 2,065
Misc. Electric 0
Misc. Fuel Use 0
Non-HVAC Sub-Total 7,776
Grand Total 19,063
Table 2. Annual Cost per Unit Floor Area
Component
ECM-4 Spot Heating in Garage
($/ft!)Air System Fans 0.056
Cooling 0.063
Heating 0.978
Pumps 0.000
Cooling Tower Fans 0.000
HVAC Sub-Total 1.096
Lights 0.555
Electric Equipment 0.200
Misc. Electric 0.000
Misc. Fuel Use 0.000
Non-HVAC Sub-Total 0.755
Grand Total 1.851
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Table 3. Component Cost as a Percentage of Total Cost
Component
ECM-4 Spot Heating in Garage
( % )Air System Fans 3.0
Cooling 3.4
Heating 52.8
Pumps 0.0
Cooling Tower Fans 0.0
HVAC Sub-Total 59.2
Lights 30.0
Electric Equipment 10.8
Misc. Electric 0.0
Misc. Fuel Use 0.0
Non-HVAC Sub-Total 40.8
Grand Total 100.0
Hourly Analysis Program v4.50 Page 1 of 1
Annual Energy and Emissions SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
Table 1. Annual Costs
Component
ECM-4 Spot Heating in Garage
($)
HVAC Components
Electric 4,528
Natural Gas 6,760
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Remote CW 0
HVAC Sub-Total 11,287
Non-HVAC Components
Electric 7,776
Natural Gas 0
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Non-HVAC Sub-Total 7,776
Grand Total 19,063
Table 2. Annual Energy Consumption
ComponentECM-4 Spot
Heating in Garage
HVAC Components
Electric (kWh) 26,339
Natural Gas (Therm) 5,045
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Non-HVAC Components
Electric (kWh) 45,233
Natural Gas (Therm) 0
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Totals
Electric (kWh) 71,572
Natural Gas (Therm) 5,045
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Hourly Analysis Program v4.50 Page 1 of 2
Annual Energy and Emissions SummaryMountain Lakes - DPW 09/17/2010 Kitchen and Associates 09:14AM
Table 3. Annual Emissions
ComponentECM-4 Spot
Heating in GarageCO2 Equivalent (lb) 0
Table 4. Annual Cost per Unit Floor Area
Component
ECM-4 Spot Heating in Garage
($/ft!)HVAC Components
Electric 0.440
Natural Gas 0.656
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Remote CW 0.000
HVAC Sub-Total 1.096
Non-HVAC Components
Electric 0.755
Natural Gas 0.000
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Non-HVAC Sub-Total 0.755
Grand Total 1.851
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Table 5. Component Cost as a Percentage of Total Cost
Component
ECM-4 Spot Heating in Garage
( % )
HVAC Components
Electric 23.8
Natural Gas 35.5
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Remote CW 0.0
HVAC Sub-Total 59.2
Non-HVAC Components
Electric 40.8
Natural Gas 0.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Non-HVAC Sub-Total 40.8
Grand Total 100.0
Hourly Analysis Program v4.50 Page 2 of 2
APPENDIX G
ECM-5 Replace Single Pane Windows with Double Pane Windows
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-5
Rep
lace
Sin
gle
Pan
e W
ind
ow
s with
Do
ub
le P
an
e W
ind
ow
sMaterial
0.98Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
Existing Window
Rem
oval - Up to 25 Sq. Ft.
125 s.f.
$0$24
$0$29
$0$29
Existing Window
Rem
oval - Up to 50 Sq. Ft.
350 s.f.
$0$53
$0$192
$0$192
New
Window
Installation14
ea$370
$37$5,076
$627$0
$5,703Trim
work, C
asing, Finishing14
ea$41
$33$563
$559$0
$1,122
*Quantity of w
indows determ
ined by available sizes in RSM
eans Building C
onstruction Cost D
ata. $7,046
Actual quantity of w
indows m
ay vary slightly.10%
OH
, 10% Profit
$70510%
Contingency
$705
$8,455Total
Multipliers
Subtotal
Insta
llatio
n C
osts
Unit C
ostsSubtotal C
ostsQ
tyU
nitTotal C
ostR
emarks
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-5
Rep
lace
Sin
gle
Pan
e W
ind
ow
s with
Do
ub
le P
an
e W
ind
ow
s
Electricity
Natural G
asC
ostkW
htherm
s$
Existing Building Energy U
se72,467
7,176$22,100
Building Energy U
se with N
ew D
ouble Pane Window
s72,276
7,143$22,000
Difference
19133
$100
An
nu
al E
nerg
y Use
Co
mp
ariso
n
ECM-5 AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
1. General Details: Air System Name ECM-5 AHU-2 - Original Offices Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Electric Resistance Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-5 Original Offices x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-5 AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1300.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1300.2 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 22.3 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 SEER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Hourly Analysis Program v4.50 Page 2 of 2
ECM-5 AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
1. General Details: Air System Name ECM-5 AHU-1 - Garage Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-5 Garage x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 85.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Garage Schedule Unoccupied Cooling is Not Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Supply Fan Airflow 10537.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hourly Analysis Program v4.50 Page 1 of 2
ECM-5 AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 10537.2 - -
5. Equipment DataCentral Heating Unit - Combustion Estimated Maximum Load 294.7 MBH Equipment Sizing User-Defined Gross Heating Capacity 600.0 MBH Average Efficiency 80.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
ECM-5 AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
1. General Details: Air System Name ECM-5 AHU-3 - Office Addition Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-5 Office Addition x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-5 AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1383.1 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1383.1 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 23.0 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 35.8 MBH Equipment Sizing User-Defined Gross Heating Capacity 54.0 MBH Average Efficiency 90.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
ECM-5 AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
1. General Details: Air System Name ECM-5 AHU-4 - Woodworking Shop Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 ECM-5 Wood Shop x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Woodworking Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
ECM-5 AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:40PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1363.6 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1363.6 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 25.1 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 36.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 30.3 MBH Equipment Sizing User-Defined Gross Heating Capacity 48.0 MBH Average Efficiency 80.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
Billing Details - Electric - ECM-5 Replace Single Pane WindowsMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
1. Component Charges
BillingPeriod
Energy Charges($)
Demand Charges($)
CustomerCharges
($)Taxes
($)Total Charge
($)Jan 1,509 0 0 0 1,509
Feb 1,296 0 0 0 1,296
Mar 1,234 0 0 0 1,234
Apr 980 0 0 0 980
May 711 0 0 0 711
Jun 807 0 0 0 807
Jul 905 0 0 0 905
Aug 892 0 0 0 892
Sep 752 0 0 0 752
Oct 809 0 0 0 809
Nov 1,113 0 0 0 1,113
Dec 1,414 0 0 0 1,414
Totals 12,424 0 0 0 12,424
2. Totals
BillingPeriod
Total Charges($)
Total Consumption
(kWh)Avg Price
($/kWh)Jan 1,509 8,781 0.1719
Feb 1,296 7,541 0.1719
Mar 1,234 7,180 0.1719
Apr 980 5,704 0.1719
May 711 4,138 0.1719
Jun 807 4,695 0.1719
Jul 905 5,264 0.1719
Aug 892 5,191 0.1719
Sep 752 4,373 0.1719
Oct 809 4,705 0.1719
Nov 1,113 6,478 0.1719
Dec 1,414 8,228 0.1719
Totals 12,424 72,276 0.1719
3. Consumption TotalsBillingPeriod
Peak(kWh)
Mid-Peak(kWh)
Normal Peak(kWh)
Off-Peak(kWh)
Overall(kWh)
Jan 0 0 0 0 8,781
Feb 0 0 0 0 7,541
Mar 0 0 0 0 7,180
Apr 0 0 0 0 5,704
May 0 0 0 0 4,138
Jun 0 0 0 0 4,695
Jul 0 0 0 0 5,264
Aug 0 0 0 0 5,191
Sep 0 0 0 0 4,373
Oct 0 0 0 0 4,705
Nov 0 0 0 0 6,478
Dec 0 0 0 0 8,228
Totals 0 0 0 0 72,276
Hourly Analysis Program v4.50 Page 1 of 2
Billing Details - Electric - ECM-5 Replace Single Pane WindowsMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
4. Billing DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.6
Jun 0.0 0.0 0.0 0.0 25.1
Jul 0.0 0.0 0.0 0.0 26.3
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 23.9
Oct 0.0 0.0 0.0 0.0 22.8
Nov 0.0 0.0 0.0 0.0 25.5
Dec 0.0 0.0 0.0 0.0 27.1
5. Maximum DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.6
Jun 0.0 0.0 0.0 0.0 25.1
Jul 0.0 0.0 0.0 0.0 26.3
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 23.9
Oct 0.0 0.0 0.0 0.0 22.8
Nov 0.0 0.0 0.0 0.0 25.5
Dec 0.0 0.0 0.0 0.0 27.1
6. Time Of Maximum DemandsBillingPeriod
Peak(m/d/h)
Mid-Peak(m/d/h)
Normal Peak(m/d/h)
Off-Peak(m/d/h)
Overall(m/d/h)
Jan n/a n/a n/a n/a 1/25/0900
Feb n/a n/a n/a n/a 2/1/0900
Mar n/a n/a n/a n/a 3/18/0900
Apr n/a n/a n/a n/a 4/8/0900
May n/a n/a n/a n/a 5/17/1400
Jun n/a n/a n/a n/a 6/11/1400
Jul n/a n/a n/a n/a 7/1/1400
Aug n/a n/a n/a n/a 8/4/1400
Sep n/a n/a n/a n/a 9/10/1400
Oct n/a n/a n/a n/a 10/19/0900
Nov n/a n/a n/a n/a 11/22/0900
Dec n/a n/a n/a n/a 12/8/0900
Hourly Analysis Program v4.50 Page 2 of 2
Monthly Component Costs - ECM-5 Replace Single Pane WindowsMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
0
500
1000
1500
2000
2500
3000
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Air System Fans Cooling Heating Lights Electric Equipment
1. HVAC Component Costs
MonthAir System Fans
($)Cooling
($)Heating
($)Pumps
($)Cooling Towers
($)HVAC Total
($)January 100 0 3,199 0 0 3,299
February 84 0 2,497 0 0 2,581
March 73 0 1,839 0 0 1,912
April 55 2 938 0 0 995
May 38 42 0 0 0 80
June 42 112 0 0 0 154
July 47 200 0 0 0 247
August 46 191 0 0 0 237
September 40 59 0 0 0 99
October 41 11 340 0 0 392
November 65 0 1,475 0 0 1,540
December 89 0 2,594 0 0 2,683
Total 721 618 12,882 0 0 14,221
2. Non-HVAC Component Costs
MonthLights
($)
Electric Equipment
($)Misc. Electric
($)Misc. Fuel Use
($)Non-HVAC Total
($)Grand Total
($)January 465 167 0 0 631 3,930
February 438 158 0 0 596 3,177
March 500 182 0 0 681 2,593
April 479 174 0 0 653 1,648
May 465 167 0 0 631 711
June 479 174 0 0 653 807
July 484 174 0 0 658 905
August 481 174 0 0 655 892
September 479 174 0 0 653 752
October 465 167 0 0 631 1,023
November 479 174 0 0 653 2,193
December 500 182 0 0 681 3,364
Total 5,711 2,065 0 0 7,776 21,996
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Costs - ECM-5 Replace Single Pane WindowsMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
0
500
1000
1500
2000
2500
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
HVAC Electric HVAC Natural Gas Non-HVAC Electric
1. HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)
Remote Chilled Water
($)January 878 2,421 0 0 0 0 0
February 700 1,881 0 0 0 0 0
March 553 1,359 0 0 0 0 0
April 328 667 0 0 0 0 0
May 80 0 0 0 0 0 0
June 154 0 0 0 0 0 0
July 247 0 0 0 0 0 0
August 238 0 0 0 0 0 0
September 99 0 0 0 0 0 0
October 178 214 0 0 0 0 0
November 461 1,080 0 0 0 0 0
December 733 1,949 0 0 0 0 0
Total 4,649 9,572 0 0 0 0 0
2. Non-HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)January 631 0 0 0 0 0
February 596 0 0 0 0 0
March 681 0 0 0 0 0
April 653 0 0 0 0 0
May 631 0 0 0 0 0
June 653 0 0 0 0 0
July 658 0 0 0 0 0
August 655 0 0 0 0 0
September 653 0 0 0 0 0
October 631 0 0 0 0 0
November 653 0 0 0 0 0
December 681 0 0 0 0 0
Total 7,776 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Use by Energy Type - ECM-5 Replace Single Pane WindowsMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
1. HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Remote CW
(na)Jan 5,108 1,807 0 0 0 0 0
Feb 4,074 1,404 0 0 0 0 0
Mar 3,218 1,014 0 0 0 0 0
Apr 1,907 498 0 0 0 0 0
May 465 0 0 0 0 0 0
Jun 898 0 0 0 0 0 0
Jul 1,436 0 0 0 0 0 0
Aug 1,383 0 0 0 0 0 0
Sep 576 0 0 0 0 0 0
Oct 1,033 160 0 0 0 0 0
Nov 2,680 806 0 0 0 0 0
Dec 4,265 1,455 0 0 0 0 0
Totals 27,043 7,143 0 0 0 0 0
2. Non-HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Jan 3,672 0 0 0 0 0
Feb 3,467 0 0 0 0 0
Mar 3,962 0 0 0 0 0
Apr 3,797 0 0 0 0 0
May 3,672 0 0 0 0 0
Jun 3,797 0 0 0 0 0
Jul 3,827 0 0 0 0 0
Aug 3,808 0 0 0 0 0
Sep 3,797 0 0 0 0 0
Oct 3,672 0 0 0 0 0
Nov 3,797 0 0 0 0 0
Dec 3,962 0 0 0 0 0
Totals 45,233 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Mon
thly
Ene
rgy
Use
by
Com
pone
nt -
ECM
-5 R
epla
ce S
ingl
e Pa
ne W
indo
ws
Mou
ntai
n La
kes
- DP
W08
/09/
2010
K
itche
n an
d A
ssoc
iate
s02
:35P
M
1. M
onth
ly E
nerg
y U
se b
y Sy
stem
Com
pone
ntC
ompo
nent
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Air
Sys
tem
Fan
s (k
Wh)
584
487
426
317
221
246
272
270
233
239
379
518
C
oolin
g
E
lect
ric (k
Wh)
00
113
244
651
1164
1113
343
642
0
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
R
emot
e C
W (n
a)0
00
00
00
00
00
0
Hea
ting
E
lect
ric (k
Wh)
4524
3587
2791
1576
00
00
073
022
9937
47
N
atur
al G
as (T
herm
)18
0714
0410
1449
80
00
00
160
806
1455
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
P
umps
(kW
h)0
00
00
00
00
00
0
Clg
. Tow
er F
ans
(kW
h)0
00
00
00
00
00
0
Ligh
ting
(kW
h)27
0325
4629
0627
8627
0327
8628
1427
9627
8627
0327
8629
06
Ele
ctric
Eqp
t. (k
Wh)
970
920
1056
1011
970
1011
1014
1012
1011
970
1011
1056
Mis
c. E
lect
ric (k
Wh)
00
00
00
00
00
00
M
isc.
Fue
l
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
Hou
rly A
naly
sis
Pro
gram
v4.
50P
age
1 of
1
Annual Cost SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 1. Annual Costs
Component
ECM-5 Replace Single Pane
Windows($)
Air System Fans 721
Cooling 618
Heating 12,882
Pumps 0
Cooling Tower Fans 0
HVAC Sub-Total 14,221
Lights 5,711
Electric Equipment 2,065
Misc. Electric 0
Misc. Fuel Use 0
Non-HVAC Sub-Total 7,776
Grand Total 21,996
Table 2. Annual Cost per Unit Floor Area
Component
ECM-5 Replace Single Pane
Windows($/ft!)
Air System Fans 0.070
Cooling 0.060
Heating 1.251
Pumps 0.000
Cooling Tower Fans 0.000
HVAC Sub-Total 1.381
Lights 0.555
Electric Equipment 0.200
Misc. Electric 0.000
Misc. Fuel Use 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.136
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 1 of 2
Annual Cost SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 3. Component Cost as a Percentage of Total Cost
Component
ECM-5 Replace Single Pane
Windows( % )
Air System Fans 3.3
Cooling 2.8
Heating 58.6
Pumps 0.0
Cooling Tower Fans 0.0
HVAC Sub-Total 64.7
Lights 26.0
Electric Equipment 9.4
Misc. Electric 0.0
Misc. Fuel Use 0.0
Non-HVAC Sub-Total 35.3
Grand Total 100.0
Hourly Analysis Program v4.50 Page 2 of 2
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 1. Annual Costs
Component
ECM-5 Replace Single Pane
Windows($)
HVAC Components
Electric 4,649
Natural Gas 9,572
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Remote CW 0
HVAC Sub-Total 14,221
Non-HVAC Components
Electric 7,776
Natural Gas 0
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Non-HVAC Sub-Total 7,776
Grand Total 21,996
Table 2. Annual Energy Consumption
Component
ECM-5 Replace Single Pane
Windows
HVAC Components
Electric (kWh) 27,043
Natural Gas (Therm) 7,143
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Non-HVAC Components
Electric (kWh) 45,233
Natural Gas (Therm) 0
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Totals
Electric (kWh) 72,276
Natural Gas (Therm) 7,143
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Hourly Analysis Program v4.50 Page 1 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 3. Annual Emissions
Component
ECM-5 Replace Single Pane
WindowsCO2 Equivalent (lb) 0
Table 4. Annual Cost per Unit Floor Area
Component
ECM-5 Replace Single Pane
Windows($/ft!)
HVAC Components
Electric 0.451
Natural Gas 0.929
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Remote CW 0.000
HVAC Sub-Total 1.381
Non-HVAC Components
Electric 0.755
Natural Gas 0.000
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.136
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Hourly Analysis Program v4.50 Page 2 of 3
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:35PM
Table 5. Component Cost as a Percentage of Total Cost
Component
ECM-5 Replace Single Pane
Windows( % )
HVAC Components
Electric 21.1
Natural Gas 43.5
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Remote CW 0.0
HVAC Sub-Total 64.7
Non-HVAC Components
Electric 35.3
Natural Gas 0.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Non-HVAC Sub-Total 35.3
Grand Total 100.0
Hourly Analysis Program v4.50 Page 3 of 3
APPENDIX H
ECM-6 Insulate Hot Water Piping
BP
U E
NER
GY
AU
DIT
PR
OG
RA
MB
oro
ug
h o
f Mo
un
tain
Lakes D
ep
artm
en
t of P
ub
lic Wo
rks G
ara
ge
CH
A P
roje
ct #2
17
95
EC
M-6
Insu
late
Ho
t Wate
r Pip
ing
Water
Natural G
asTotal
$$
$$
$Years
Years
40.00$
-$
20.00$
20.00$
6.50
2.0N/A
Payback (W
ith Incentive)B
udgetary C
osts A
nnual Utility Savings
RO
IPotential Incentive
Payback (W
ithout Incentive)
BP
U E
NER
GY
AU
DIT
PR
OG
RA
MB
oro
ug
h o
f Mo
un
tain
Lakes D
ep
artm
en
t of P
ub
lic Wo
rks G
ara
ge
CH
A P
roje
ct #2
17
95
Sim
ple
Payb
ack
An
alysis
Cost
$42.00
Incentive$0.00
Adjusted C
ost$42.00
Savings/yr
$18.31
Payback in years2.29
EC
M-6
Insu
late
Ho
t Wate
r Pip
ing
Len
gth
of
Un
insu
late
d P
ipe (ft)
Un
insu
late
d
En
erg
y Loss
per Fo
ot
(BTU
h/
ft)
Un
insu
late
d
En
erg
y Loss P
er
Year
(BTU
h/
ft/ye
ar)
Un
insu
late
d
En
erg
y Loss P
er
Year
(therm
s/ft/
year)
Un
insu
late
d
En
erg
y Loss
per Y
ear
(therm
s/ye
ar)
Gas C
ost
($/
therm
)
Co
st of
En
erg
y Loss
($/
year)
Inta
llatio
n
Co
st ($/
ft)In
stalla
tion
C
ost ($
)
40' of 1" Copper Pipe
3.934164
0.3416413.6656
$1.34$18.31
$1.05$42.00
BPU
EN
ER
GY
AU
DIT PR
OG
RA
MB
orough of Mountain L
akes Departm
ent of Public Works G
arageC
HA
Project #21795
EC
M-6
Insu
late
Ho
t Wate
r Pip
ing
Material
1Labor
1.21Equipm
ent1.07
Material
Labor
Equipm
entM
aterialL
aborE
quipment
1" Fiberglass Insulation40
LF1.05
$ -
42.00$
--
$ 42.00
$ -
$
** Intallation by Ow
ner42.00
$ 42.00$
Total
Multipliers
Subtotal
Insta
llatio
n C
osts
Unit C
ostsSubtotal C
ostsItem
Qty
Unit
Total Cost
Rem
arks
APPENDIX I
Photovoltaic (PV) Rooftop Solar Power Generation
* * * * *AC Energy
&Cost Savings
* * * * *
(Type comments here to appear on printout; maximum 1 row of 90 characters.)
Station IdentificationCell ID: 0267370State: New Jersey Latitude: 40.9 ° NLongitude: 74.7 ° W
PV System SpecificationsDC Rating: 25.0 kWDC to AC Derate Factor: 0.770AC Rating: 19.2 kWArray Type: Fixed Tilt Array Tilt: 40.9 °Array Azimuth: 180.0 °
Energy SpecificationsCost of Electricity: 17.2 ¢/kWh
Results
Month
SolarRadiation
(kWh/m2/day)
ACEnergy
(kWh)
EnergyValue
($)
1 3.13 1942 333.83 2 3.93 2191 376.63 3 5.04 2976 511.57 4 5.30 2915 501.09 5 5.57 3095 532.03 6 5.80 3040 522.58 7 5.48 2906 499.54 8 5.46 2923 502.46 9 5.29 2810 483.04
10 4.74 2702 464.47 11 3.43 1944 334.17 12 2.98 1812 311.48
Year 4.68 31256 5372.91
Output Results as Text
Saving Text from a Browser
Run PVWATTS v.2 for another location Run PVWATTS v.1
Please send questions and comments to WebmasterDisclaimer and copyright notice.
RReDC home page (http://rredc.nrel.gov )
Your Solar Electric Estimate YOUR SOLAR RATING
O K G O O D G R E A T E X C E L L E N T
The solar rating of your area is Great for adopting a solar system. (4.68 kWh/m^2 per day). You may want to change some of the information to better match your situation.
Customize Your Assumptions Price Installed $ 8 per watt DC.
This is a user-entered cost. Enter 0 to return to default. Provide 43 % of my electricity, on average, over the course of a year.
Electric Rate: $ 0.1719/kWh
Monthly Electric Usage: 6,058 kWh/Month Utility Annual Inflation Rate: 3.78%
Utility Savings Method: !Net Metering (common) Federal ITC Based Upon: !Gross Cost Federal Income Tax Rate: !28%
State Income Tax Rate: 7.8% (Low: 1.40% - High: 8.97%) help Loan Modeling: Borrow 0% of $118,896 estimated cost
at % interest (apr) re-paid over years
If you agree this is a smart investment, we encourage you to work with a Professional to help you install your very own system.
http://www.solar-estimate.org/index.php?page=solar-installer&subpage=show&wantsolar=1&zipcode=07046
Click on the buttons to learn about our assumptions and other important information used to generate your estimate. Also, please review the notes below. Help us improve. We rely on feedback from our users to help keep our service accurate and useful: » Send us your Feedback
Your Solar Electric Estimate by the Numbers Building Type: Commercial/Business
State & County: NJ - Morris
Utility: Jersey Central Power & Lt Co
Utility Type: Investor-Owned Utility
Your Average Monthly Electricity Bill: (Assumed rate x average monthly useage) $ 1,041 / Month
Tiered Rates Apply: No
kw No
Net-Metering Available: Yes - See Notes, below!
ESTIMATED SYSTEM SIZE
The system size best for your situation will vary based upon product, building, geographic and other variables. We encourage you to work with a Solar Pro who can better estimate the system size best for your situation. We estimate your building will need a system sized between 19.82 kW and 29.72 kW of peak power. This estimate assumes the mid-point of this range.
Solar Rating: Good 4.68 kWh/sq-m/day
Solar System Capacity Required: 24.77 kW of peak power (DC watts)
Roof Area Needed: 2,477 sq-ft
Equivalent Annual Production: 31,260 kWh electricity
ESTIMATED SYSTEM COST
This is only an estimate based upon many assumptions. Installation costs can vary considerably. We encourage you to work with a Solar Pro who can provide you with a more detailed cost estimate. We estimate that a 25 kW peak DC power system will cost between $158,528 and $237,792. This estimate assumes the mid-point of this cost range.
Assumed Installation Gross Cost: "Gross Cost" is the cost before any rebates, incentives, tax credits, etc. are applied. See the Cost Notes, below!
$198,160
assuming $8 per watt DC
FINANCIAL INCENTIVES
Financial incentives shown are totals across all years. So, if an incentive spans multiple years then the value shown is the total of all years. For details, please refer to the table below "Cash Flow by Year and Cumulative Across Years"
NJ Solar Electric (PV) Incentive (Non-residential $ 0.80 per watt to 50 kW) » link $ 19,816
NJ: Solar Renewable Energy Certificates (SREC) » link $ 240,766
Federal Tax Credit (30% of Gross Cost at Installation) » link $ 59,448
Modified Accelerated Cost Recovery System (MACRS) Depreciation (5 yr) » link YES
ESTIMATED NET COST: $ -121,870
ESTIMATED NET COST AT INSTALLATION: $ 118,896
Cash & Loan Amounts: $ 118,896 Cash $ 0 Borrowed
Loan Monthly Payment (6.5% apr, 30 years): $ 0
CASH FLOW
Cash Flow Breakeven is where the chart crosses the $0 point - this is when your investment has paid itself back in cash. The chart above is a summary of the net cash flow you can expect over time. Net Cash Flow is the total cash after all costs (out-flows of cash) are reduced by financial incentives, annual utility savings and tax effects (in-flows of cash). Average values are used together with your assumed income tax rate (36%). Any property appreciation has not been included, as this is generally not a cash flow (it's an investment). The loan modeled, if any, is included. Because this is a business, we have assumed utility savings result in loss of some expense write offs against income, but Modified Accelerated Cost Recovery System (MACRS) Depreciation applies (an income tax benefit). Because individual tax situations vary, we have not included Federal income tax liabilities that may result from having received non-federal incentives, if any (e.g. state rebate programs) as they are usually not taxed as earned income.
SAVINGS & BENEFITS
First-year Utility Savings: $5,373
Average Monthly Utility Savings: over 25-year expected life of system $752
Average Annual Utility Savings: over 25-year expected life of system $9,019
25-year Utility Savings: $225,471
Return on Investment (ROI): 250%
Internal Rate of Return (IRR): 23.9%
Net Present Value (NPV): $162,471
Profitability Index: 2.4
Greenhouse Gas (CO2) Saved: over 25-year system life
641 tons 1,282,000 auto miles
Cash Flow by Year and Cumulative Across Years This cash flow table includes tax effects applied to utility savings and loan interest payments (if any). For commercial (business) situations we assume utility savings result in loss of some expense write offs against income: Utility Savings = ($'s saved on utility bill) x (1 - Income Tax Rate). "Tax Savings from MACRS depreciation" (below) is the
net cash saved on income taxes after the depreciation expense is written off. So the amount that was depreciated would be the cash value shown divided by the Income Tax Rate (more info.). Because individual tax situations vary, we have not included Federal income tax liabilities that may result from having received non-federal incentives, if any (e.g. state rebate programs) as they are usually not taxed as earned income. Any income from your system (e.g. performance-based incentives and "SREC's") may be taxed as income (also not shown).
Year of Operation: at Install 1 2 3 4 5 Gross Cost ($198,160)
NJ Solar Electric (PV) Incentive (Non-
residential $ 0.80 per watt to 50 kW)
$19,816 $0 $0 $0 $0 $0
NJ: Solar Renewable Energy Certificates
(SREC) $0 $19,707 $19,114 $18,539 $17,981 $17,440
Federal Tax Credit (30% of Gross Cost at
Installation) $59,448 $0 $0 $0 $0 $0
Tax savings from MACRS Depreciation $0 $10,641 $17,026 $10,216 $6,129 $6,129
Utility Savings $0 $3,580 $3,715 $3,856 $4,002 $4,153 ANNUAL CASH
FLOW $-118,896 $33,928 $39,855 $32,610 $28,112 $27,722
Cumulative Cash Flow $-118,896 $-84,968
$-45,113
$-12,503
$15,609 Breakeven
$43,331
Year of Operation: 6 7 8 9 10 11
Gross Cost NJ Solar Electric (PV)
Incentive (Non-residential $ 0.80 per
watt to 50 kW)
$0 $0 $0 $0 $0 $0
NJ: Solar Renewable Energy Certificates
(SREC) $16,915 $16,406 $15,912 $15,433 $14,969 $14,518
Federal Tax Credit (30% of Gross Cost at
Installation) $0 $0 $0 $0 $0 $0
Tax savings from MACRS Depreciation $3,065 $0 $0 $0 $0 $0
Utility Savings $4,310 $4,473 $4,642 $4,817 $4,999 $5,188 ANNUAL CASH
FLOW $24,289 $20,879 $20,554 $20,250 $19,968 $19,706
Cumulative Cash Flow $67,620 $88,499 $109,053 $129,303 $149,271 $168,977
Year of Operation: 12 13 14 15 16 17
Gross Cost ($22,293)
Inverter Replaced
NJ Solar Electric (PV) Incentive (Non-residential $ 0.80 per
watt to 50 kW)
$0 $0 $0 $0 $0 $0
NJ: Solar Renewable Energy Certificates
(SREC) $14,081 $13,657 $13,246 $12,848 $0 $0
Federal Tax Credit (30% of Gross Cost at
Installation) $0 $0 $0 $0 $0 $0
Tax savings from MACRS
Depreciation $0 $0 $0 $0 $0 $0
Utility Savings $5,384 $5,588 $5,799 $6,018 $6,246 $6,482 ANNUAL CASH
FLOW $19,465 $19,245 $19,045 $-3,427 $6,246 $6,482
Cumulative Cash Flow
$188,442 $207,687 $226,732 $223,305 $229,551 $236,033
Year of
Operation: 18 19 20 21 22 23 24 25
Gross Cost NJ Solar Electric
(PV) Incentive
(Non-residential $ 0.80 per watt to 50
kW)
$0 $0 $0 $0 $0 $0 $0 $0
NJ: Solar $0 $0 $0 $0 $0 $0 $0 $0
Renewable Energy
Certificates (SREC)
Federal Tax Credit
(30% of Gross Cost
at Installation)
$0 $0 $0 $0 $0 $0 $0 $0
Tax savings from
MACRS Depreciatio
n
$0 $0 $0 $0 $0 $0 $0 $0
Utility Savings $6,727 $6,981 $7,245 $7,519 $7,803 $8,098 $8,404 $8,722
ANNUAL CASH FLOW
$6,727 $6,981 $7,245 $7,519 $7,803 $8,098 $8,404 $8,722
Cumulative Cash Flow
$242,760
$249,741
$256,986
$264,505
$272,308
$280,406
$288,810
$297,532
FAQ's: Frequently Asked Questions for NJ:
• Are renewable energy systems exempt from sales tax in New Jersey? • Can I sell Solar Renewable Energy Certificates (SREC) in New Jersey? • Where can I find more information about New Jersey Renewable energy
programs and incentives? Notes & Assumptions: Solar Electric (PV) Systems * HOW TO REDUCE THE SYSTEM SIZE NEEDED & INCREASE SAVINGS The estimate provided above assumes "base" electric rates apply. Other taxes and surcharges may be applied to your utility bill. We suggest you review a recent utility bill and change the "Assumed Electric Rate", above, as needed to better match your situation. You may have other metered-rate options with your utility. Options such as Tiered billing rates, Time-Of-Use (TOU) metering, and Net-Metering, if available, can help reduce the system size you need to provide a "net-zero" energy bill. Sometimes people also reduce the size of their solar system to accommodate planned improvements in their building's energy efficiency, or to match a budget and/or the available space for installing a solar system. Energy production from a solar electric (PV) system is a function of several factors, including the following. Our assumptions are:
Factor Assumption
Solar resources Assumed solar availability: As per Solar Radiance chart
Soiling or contamination of the PV panels
Clean, washed frequently: 100% design sunlight transmission
Temperature 25C, calm wind
System configuration (battery or non-battery) Non-battery
Orientation to the sun tilted at your latitude, full sun
Shading None
PV Energy delivered as % of manufacturer's rating 95%
Soiling, wiring & power point tracking losses 9% (91% delivered)
Inverter Efficiency 90%
Total Energy Delivered 95% x 91% x 90% = 78% Energy Efficiency: Improving your building's energy efficiency will reduce the system size you need to attain a "net-zero" energy bill. Tiered Rates: Often people are paying a "Tiered" rate for their electricity. This is a higher rate (higher than the "Base" rate) for electricity charged when a home or building uses more that a "Base" amount allocated for the building. Installing a solar system will reduce your electrical demand from the utility. This can result in a lower utility rate because you stay within the "Base" rate level. In this case, the more expensive "Tiered" rate electricity is eliminated, reducing your average electricity rate. TOU Metering: Many utilities offer Time-of-Use (TOU) meters. This allows the price of electricity to vary by time of day (called "Peak" or "Off-Peak" periods) and by season (usually "Winter" versus "Summer" rates). If TOU metering is offered by your utility, a solar system may result in additional savings. This is because peak (more expensive electricity) rates often occur during the daytime. This is usually when a solar system is producing the most output, thus reducing your demand for peak-rate electricity from the utility. Most utilities do charge for the purchase and installation of a time-of-use meter (normally a few hundred dollars). We have assumed the cost for this is part of the "Estimated Installation cost" shown above. Net-Metering: With Net-Metering, surplus electricity generated by your renewable energy system will be credited back to your utility account. So if your solar system makes more electricity than you are using, the "meter spins backwards". You are not actually "selling" electricity, since in most states the utility will not reimburse you for excess electricity. But, if your utility offers "Net-Metering" you may be able to get credit for electricity provided back to the grid during peak periods. Combined with TOU metering, Net-Metering can result in multiplied savings since your electricity account may be gaining electricity credits during the time of peak utility rates -- Think of a hot, sunny summer day ... your solar system is producing power, spinning your electric meter backwards, and supplying the grid with electricity to run other people's air conditioners -- you're "spinning back" cost at peak rates! That's the savings power of Net-metering, combined with TOU rates. Solar Power "Fixes" Energy Costs: The cost of sunshine is free. While the sun rises every morning, the cost of sunshine does not. Utility rates, on the other hand, tend to rise steadily in cost. So, the value of your savings from a solar system are likely to increase as time goes on. If you are on a fixed income (e.g. nearing or in retirement) this may be of particular interest to you.
THE COST TO GO SOLAR This is only an estimate based upon many assumptions and limited data entered by you: Installation costs can vary considerably. The cost to purchase and install a complete grid-tied solar photovoltaic (PV) system on a residential home is typically as further defined in the table, below. This includes the PV array, inverter and associated balance of system costs. It does not include the cost of options you may select, such as battery backup power storage, or the costs of building preparation work, like new shingles. Costs can also be higher if you add other features or have special installation needs (such as application over tile roofing) or you choose to use special mounting systems (such as sun tracking systems). Other factors may also affect price, including, but not limited to, your location, the building condition, type and location, its wiring, and warrantees offered.
Assumed Cost, per Watt DC
Item System Size < 2kW System Size > 2kW
Assumed Total $10 per watt DC (+/- 20%)
$9 per watt DC (+/- 20%)
About 60% of the cost to install a solar-electric (PV) system goes to the solar photovoltaic (PV) panels, 10% to an inverter, 15% to direct labor, and 15% to the "balance of system" (BOS) costs.
OTHER ASSUMPTIONS This summary is based upon many assumptions and the limited data you entered. An actual site assessment by a qualified solar system retailer or contractor will be needed to determine the actual costs and benefits of installing a solar electric system.
HELPFUL PDF's & Links
Report on Solar-Estimate.org Estimator: Comparisons, Methods & Assumptions
Payback & Other Financial Test for Solar on Your Home
The Dept. of Energy's: PVWatts Online PV Calculator
Natural Resources Canada's: RETScreen Renewable Energy Calculators
A Free Public Service of the Solar & Wind Communities since 2000
Contractor verification assisted by »
ContractorCheck.com Pre-screened, Customer-recommended Solar Pros
See: » How it Works
Your privacy is important. We will not release or disclose your personal information to others without your permission. Privacy Policy
SOLAR-ESTIMATE.ORG is a free, public service. We believe the efficient use of energy and renewable energy systems makes for comfortable living and a more secure future. So we want to help you reduce your energy demands, increase your energy efficiency and help you utilize more energy from renewable energy systems and sources -- like solar electric (PV - photovoltaics), solar space (air), water & pool heating, wind turbines, biomass furnaces and ground-source heat pumps. Our mission is to serve as a convenient, user-friendly means for home and small commercial building owners to make preliminary evaluations of renewable and solar energy options for their location, run financial analysis and help find and verify the experience, quality and business status of certified solar contractors, and other professionals who can design, install and service renewable and solar energy and energy efficient power systems. (See How It Works). As a business verification service, we maintain the largest directory of current local solar installer and solar contractor profiles including extensive customer reviews and ratings of these professionals. Profiles are not limited to solar energy professionals, but include many other renewable energy, design, engineering and support professional services. We also serve as a consolidator of national and region-specific solar and energy efficiency programs, and utility information about renewable energy, solar energy and energy efficient measures. Our software tools and content include: Online solar estimator (solar calculator, analysis) to help you determine the costs and benefits of a renewable or solar energy system for your particular location and building needs, including financial analysis tools. We also provide a trusted means by which you, as a consumer, can review and access solar panel installers, solar contractors, solar pros and other solar, renewable energy and energy efficiency professional services. And we offer answers to frequently asked questions about renewable and solar power, links and resources to current information about solar power, solar energy, renewable energy, energy bill savings, energy efficiency data, solar incentives, tax credits, rebates and other programs and helpful information so you can learn about solar energy, help us promote renewable and solar power adoption and, hopefully, install a solar system for your home, building, company or community and/or improve your energy efficiency and use. Site Map © 2000 - 2010 Energy Matters LLC. This is copyrighted content and includes company trademarks. Use of content or trademarks without prior written consent is strictly prohibited. U.S. and International patents pending. Terms & Conditions of Use
A solar-powered site and service of Energy Matters LLC.
APPENDIX J
Solar Thermal Domestic Hot Water Plant
Home
What Can I Do?
Electric Choice
Home Energy
FAQs
LEARNFact SheetsLesson Plans
PLAYCalculators
NETWORKOrganizationsBusinessesEvents Calendar
BROWSEResources Solar Wind Biomass Geothermal Water
Projects
TX Energy -Past and Present
Financial Help
About Us
About SECO
RARE
Interactive Energy Calculators
Our calculators help you understand energy production and consumption in a whole new way. Use them todevelop a personal profile of your own energy use.
Carbon Pollution CalculatorElectric Power Pollution CalculatorPV System EconomicsSolar Water HeatingWhat's a Watt?
Solar Water Heating CalculatorWater heating is a major energy consumer. Although the energy consumed daily is often less than for airconditioning or heating, it is required year round, making it a good application of solar energy. Use thiscalculator to explore the energy usage of your water heater, and to estimate whether a solar water heatercould save you money.
Water Heater Characteristics
Physical Thermal
? Diameter (feet) 1.7 ? Water Inlet Temperature(Degrees F)
58
? Capacity (gallons) 40 ? Ambient Temperature (DegreesF)
70
? Surface Area (calculated -sq ft)
17.12 ? Hot Water Temperature (DegreesF)
135
? Effective R-value 5.04 ? Hot Water Usage (Gallons perDay)
64.3
Energy Use
1694 ? Heat Delivered in Hot Water (BTU/hr)
220.8 ? Heat loss through insulation (BTU/hr)
Gas vs. Electric Water Heating
Gas Electric
0.61 ? Overall Efficiency 0.867
0.6895 ? Conversion Efficiency 0.98
2777 BTU/hr ? Power Into Water Heater 1954 BTU/hr
Cost
$ 1.34 /Therm ? Utility Rates $ 0 /kWh
$ 325.97536800000006 ? Yearly Water Heating Cost $ 0
How Does Solar Compare?
? Solar Water Heater Cost: $ 9300? Percentage Solar:
70
40.75680431692705 years forgas
? Payback Time for Solar System Infinity years forelectric
More information on solar water heating:
Fact sheet - Solar Water HeatersFact sheet - Solar Water Heaters for Swimming PoolsKids fact sheet - Heat from the Sun
Return to Top of Page
Send comments, questions, and suggestions to website manager.
Window on State Government | Privacy and Security Policy | Accessibility Policy
State Energy Conservation Office (SECO)
APPENDIX K
Wind
APPENDIX L
EPA Portfolio Manager
APPENDIX M
Carrier Hourly Analysis Program Base Building Data
AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:33PM
1. General Details: Air System Name AHU-2 - Original Offices Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Electric Resistance Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 Original Offices x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
AHU-2 - Original Offices Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:33PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1300.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1300.2 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 22.3 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 SEER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Hourly Analysis Program v4.50 Page 2 of 2
AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:33PM
1. General Details: Air System Name AHU-1 - Garage Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 Garage x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 85.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Garage Schedule Unoccupied Cooling is Not Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Supply Fan Airflow 10580.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hourly Analysis Program v4.50 Page 1 of 2
AHU-1 - Garage Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:33PM
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 10580.2 - -
5. Equipment DataCentral Heating Unit - Combustion Estimated Maximum Load 295.9 MBH Equipment Sizing User-Defined Gross Heating Capacity 600.0 MBH Average Efficiency 80.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:34PM
1. General Details: Air System Name AHU-3 - Office Addition Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 Office Addition x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 70.0 °F Heating T-stat: Unocc. 68.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Occupied/Unoccupied Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
AHU-3 - Office Addition Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:34PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1445.2 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1445.2 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 24.5 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 24.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 37.5 MBH Equipment Sizing User-Defined Gross Heating Capacity 54.0 MBH Average Efficiency 90.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:34PM
1. General Details: Air System Name AHU-4 - Woodworking Shop Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1
2. System Components:Ventilation Air Data: Airflow Control Constant Ventilation Airflow Ventilation Sizing Method Sum of Space OA Airflows Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm
Central Cooling Data: Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling Source Air-Cooled DX Schedule JFMAMJJASOND Capacity Control Cycled or Staged Capacity - Fan On
Central Heating Data: Supply Temperature 95.0 °F Heating Source Combustion - Natural Gas Schedule JFMA* * * * * OND Capacity Control Cycled or Staged Capacity - Fan On
Supply Fan Data: Fan Type Forward Curved Configuration Draw-thru Fan Performance 0.50 in wg Overall Efficiency 54 %
Duct System Data:Supply Duct Data: Duct Heat Gain 0 % Duct Leakage 0 %
Return Duct or Plenum Data: Return Air Via Ducted Return
3. Zone Components:Space Assignments:
Zone 1: Zone 1 Wood Shop x1
Thermostats and Zone Data: Zone All Cooling T-stat: Occ. 75.0 °F Cooling T-stat: Unocc. 75.0 °F Heating T-stat: Occ. 68.0 °F Heating T-stat: Unocc. 60.0 °F T-stat Throttling Range 1.50 °F Diversity Factor 100 % Direct Exhaust Airflow 0.0 CFM Direct Exhaust Fan kW 0.0 kW
Thermostat Schedule Woodworking Unoccupied Cooling is Available
Supply Terminals Data: Zone All Terminal Type Diffuser Minimum Airflow 0.00 CFM/person
Zone Heating Units: Zone All Zone Heating Unit Type None
Zone Unit Heat Source Electric Resistance
Hourly Analysis Program v4.50 Page 1 of 2
AHU-4 - Woodworking Shop Input DataProject Name: Mountain Lakes - DPW 08/09/2010 Prepared by: Kitchen and Associates 02:34PM
Zone Heating Unit Schedule JFMAMJJASOND
4. Sizing Data (Computer-Generated):System Sizing Data: Cooling Supply Temperature 58.0 °F Supply Fan Airflow 1418.6 CFM Ventilation Airflow 0.0 CFM Heating Supply Temperature 95.0 °F
Hydronic Sizing Specifications: Chilled Water Delta-T 10.0 °F Hot Water Delta-T 20.0 °F
Safety Factors: Cooling Sensible 0 % Cooling Latent 0 % Heating 0 %
Zone Sizing Data: Zone Airflow Sizing Method Sum of space airflow rates Space Airflow Sizing Method Individual peak space loads
Zone Supply Airflow Zone Htg Unit Reheat Coil - (CFM) (MBH) (MBH) (CFM)
1 1418.6 - -
5. Equipment DataCentral Cooling Unit - Air-Cooled DX Estimated Maximum Load 26.1 MBH Design OAT 95.0 °F Equipment Sizing User-Defined Gross Cooling Capacity 36.0 MBH ARI Performance Rating 11.00 EER Conventional Cutoff OAT 55.0 °F Low Temperature Operation Used Low Temperature Cutoff OAT 0.0 °F
Central Heating Unit - Combustion Estimated Maximum Load 32.0 MBH Equipment Sizing User-Defined Gross Heating Capacity 48.0 MBH Average Efficiency 80.0 % Misc. Electric 0.000 kW
Hourly Analysis Program v4.50 Page 2 of 2
Billing Details - Electric - Base BuildingMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
1. Component Charges
BillingPeriod
Energy Charges($)
Demand Charges($)
CustomerCharges
($)Taxes
($)Total Charge
($)Jan 1,510 0 0 0 1,510
Feb 1,297 0 0 0 1,297
Mar 1,235 0 0 0 1,235
Apr 981 0 0 0 981
May 714 0 0 0 714
Jun 812 0 0 0 812
Jul 912 0 0 0 912
Aug 900 0 0 0 900
Sep 756 0 0 0 756
Oct 810 0 0 0 810
Nov 1,114 0 0 0 1,114
Dec 1,415 0 0 0 1,415
Totals 12,457 0 0 0 12,457
2. Totals
BillingPeriod
Total Charges($)
Total Consumption
(kWh)Avg Price
($/kWh)Jan 1,510 8,786 0.1719
Feb 1,297 7,544 0.1719
Mar 1,235 7,183 0.1719
Apr 981 5,708 0.1719
May 714 4,153 0.1719
Jun 812 4,722 0.1719
Jul 912 5,306 0.1719
Aug 900 5,238 0.1719
Sep 756 4,400 0.1719
Oct 810 4,713 0.1719
Nov 1,114 6,481 0.1719
Dec 1,415 8,233 0.1719
Totals 12,457 72,468 0.1719
3. Consumption TotalsBillingPeriod
Peak(kWh)
Mid-Peak(kWh)
Normal Peak(kWh)
Off-Peak(kWh)
Overall(kWh)
Jan 0 0 0 0 8,786
Feb 0 0 0 0 7,544
Mar 0 0 0 0 7,183
Apr 0 0 0 0 5,708
May 0 0 0 0 4,153
Jun 0 0 0 0 4,722
Jul 0 0 0 0 5,306
Aug 0 0 0 0 5,238
Sep 0 0 0 0 4,400
Oct 0 0 0 0 4,713
Nov 0 0 0 0 6,481
Dec 0 0 0 0 8,233
Totals 0 0 0 0 72,468
Hourly Analysis Program v4.50 Page 1 of 2
Billing Details - Electric - Base BuildingMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
4. Billing DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.8
Jun 0.0 0.0 0.0 0.0 25.2
Jul 0.0 0.0 0.0 0.0 26.5
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 24.1
Oct 0.0 0.0 0.0 0.0 23.0
Nov 0.0 0.0 0.0 0.0 25.6
Dec 0.0 0.0 0.0 0.0 27.1
5. Maximum DemandsBillingPeriod
Peak(kW)
Mid-Peak(kW)
Normal Peak(kW)
Off-Peak(kW)
Overall(kW)
Jan 0.0 0.0 0.0 0.0 29.3
Feb 0.0 0.0 0.0 0.0 27.3
Mar 0.0 0.0 0.0 0.0 26.7
Apr 0.0 0.0 0.0 0.0 25.7
May 0.0 0.0 0.0 0.0 25.8
Jun 0.0 0.0 0.0 0.0 25.2
Jul 0.0 0.0 0.0 0.0 26.5
Aug 0.0 0.0 0.0 0.0 25.3
Sep 0.0 0.0 0.0 0.0 24.1
Oct 0.0 0.0 0.0 0.0 23.0
Nov 0.0 0.0 0.0 0.0 25.6
Dec 0.0 0.0 0.0 0.0 27.1
6. Time Of Maximum DemandsBillingPeriod
Peak(m/d/h)
Mid-Peak(m/d/h)
Normal Peak(m/d/h)
Off-Peak(m/d/h)
Overall(m/d/h)
Jan n/a n/a n/a n/a 1/25/0900
Feb n/a n/a n/a n/a 2/1/0900
Mar n/a n/a n/a n/a 3/18/0900
Apr n/a n/a n/a n/a 4/8/0900
May n/a n/a n/a n/a 5/17/1400
Jun n/a n/a n/a n/a 6/11/1400
Jul n/a n/a n/a n/a 7/1/1400
Aug n/a n/a n/a n/a 8/4/1400
Sep n/a n/a n/a n/a 9/10/1400
Oct n/a n/a n/a n/a 10/1/1400
Nov n/a n/a n/a n/a 11/22/0900
Dec n/a n/a n/a n/a 12/8/0900
Hourly Analysis Program v4.50 Page 2 of 2
Monthly Component Costs - Base BuildingMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
0
500
1000
1500
2000
2500
3000
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Air System Fans Cooling Heating Lights Electric Equipment
1. HVAC Component Costs
MonthAir System Fans
($)Cooling
($)Heating
($)Pumps
($)Cooling Towers
($)HVAC Total
($)January 101 0 3,215 0 0 3,316
February 84 0 2,508 0 0 2,592
March 74 0 1,843 0 0 1,917
April 55 3 937 0 0 995
May 39 44 0 0 0 83
June 43 116 0 0 0 159
July 48 206 0 0 0 254
August 47 199 0 0 0 246
September 41 63 0 0 0 104
October 41 12 337 0 0 390
November 66 0 1,479 0 0 1,545
December 90 0 2,606 0 0 2,696
Total 729 643 12,925 0 0 14,297
2. Non-HVAC Component Costs
MonthLights
($)
Electric Equipment
($)Misc. Electric
($)Misc. Fuel Use
($)Non-HVAC Total
($)Grand Total
($)January 465 167 0 0 631 3,947
February 438 158 0 0 596 3,188
March 500 182 0 0 681 2,598
April 479 174 0 0 653 1,648
May 465 167 0 0 631 714
June 479 174 0 0 653 812
July 484 174 0 0 658 912
August 481 174 0 0 655 901
September 479 174 0 0 653 757
October 465 167 0 0 631 1,021
November 479 174 0 0 653 2,198
December 500 182 0 0 681 3,377
Total 5,711 2,065 0 0 7,776 22,073
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Costs - Base BuildingMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
0
500
1000
1500
2000
2500
Cos
t ($)
MonthJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
HVAC Electric HVAC Natural Gas Non-HVAC Electric
1. HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)
Remote Chilled Water
($)January 879 2,438 0 0 0 0 0
February 701 1,891 0 0 0 0 0
March 554 1,363 0 0 0 0 0
April 328 666 0 0 0 0 0
May 83 0 0 0 0 0 0
June 159 0 0 0 0 0 0
July 254 0 0 0 0 0 0
August 246 0 0 0 0 0 0
September 104 0 0 0 0 0 0
October 179 211 0 0 0 0 0
November 461 1,084 0 0 0 0 0
December 734 1,962 0 0 0 0 0
Total 4,682 9,616 0 0 0 0 0
2. Non-HVAC Costs
MonthElectric
($)Natural Gas
($)Fuel Oil
($)Propane
($)
Remote Hot Water
($)Remote Steam
($)January 631 0 0 0 0 0
February 596 0 0 0 0 0
March 681 0 0 0 0 0
April 653 0 0 0 0 0
May 631 0 0 0 0 0
June 653 0 0 0 0 0
July 658 0 0 0 0 0
August 655 0 0 0 0 0
September 653 0 0 0 0 0
October 631 0 0 0 0 0
November 653 0 0 0 0 0
December 681 0 0 0 0 0
Total 7,776 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Monthly Energy Use by Energy Type - Base BuildingMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
1. HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Remote CW
(na)Jan 5,113 1,819 0 0 0 0 0
Feb 4,077 1,411 0 0 0 0 0
Mar 3,221 1,017 0 0 0 0 0
Apr 1,911 497 0 0 0 0 0
May 481 0 0 0 0 0 0
Jun 925 0 0 0 0 0 0
Jul 1,478 0 0 0 0 0 0
Aug 1,431 0 0 0 0 0 0
Sep 603 0 0 0 0 0 0
Oct 1,041 158 0 0 0 0 0
Nov 2,683 809 0 0 0 0 0
Dec 4,270 1,464 0 0 0 0 0
Totals 27,234 7,176 0 0 0 0 0
2. Non-HVAC Energy Use
MonthElectric
(kWh)Natural Gas
(Therm)Fuel Oil
(na)Propane
(na)Remote HW
(na)Remote Steam
(na)Jan 3,672 0 0 0 0 0
Feb 3,467 0 0 0 0 0
Mar 3,962 0 0 0 0 0
Apr 3,797 0 0 0 0 0
May 3,672 0 0 0 0 0
Jun 3,797 0 0 0 0 0
Jul 3,827 0 0 0 0 0
Aug 3,808 0 0 0 0 0
Sep 3,797 0 0 0 0 0
Oct 3,672 0 0 0 0 0
Nov 3,797 0 0 0 0 0
Dec 3,962 0 0 0 0 0
Totals 45,233 0 0 0 0 0
Hourly Analysis Program v4.50 Page 1 of 1
Mon
thly
Ene
rgy
Use
by
Com
pone
nt -
Bas
e B
uild
ing
Mou
ntai
n La
kes
- DP
W08
/09/
2010
K
itche
n an
d A
ssoc
iate
s02
:29P
M
1. M
onth
ly E
nerg
y U
se b
y Sy
stem
Com
pone
ntC
ompo
nent
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Air
Sys
tem
Fan
s (k
Wh)
589
491
429
320
224
250
277
275
237
241
383
523
C
oolin
g
E
lect
ric (k
Wh)
00
115
256
675
1201
1156
366
702
0
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
R
emot
e C
W (n
a)0
00
00
00
00
00
0
Hea
ting
E
lect
ric (k
Wh)
4524
3587
2791
1576
00
00
073
022
9937
47
N
atur
al G
as (T
herm
)18
1914
1110
1749
70
00
00
158
809
1464
F
uel O
il (n
a)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
P
umps
(kW
h)0
00
00
00
00
00
0
Clg
. Tow
er F
ans
(kW
h)0
00
00
00
00
00
0
Ligh
ting
(kW
h)27
0325
4629
0627
8627
0327
8628
1427
9627
8627
0327
8629
06
Ele
ctric
Eqp
t. (k
Wh)
970
920
1056
1011
970
1011
1014
1012
1011
970
1011
1056
Mis
c. E
lect
ric (k
Wh)
00
00
00
00
00
00
M
isc.
Fue
l
N
atur
al G
as (T
herm
)0
00
00
00
00
00
0
P
ropa
ne (n
a)0
00
00
00
00
00
0
R
emot
e H
W (n
a)0
00
00
00
00
00
0
R
emot
e S
team
(na)
00
00
00
00
00
00
Hou
rly A
naly
sis
Pro
gram
v4.
50P
age
1 of
1
Annual Cost SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
Table 1. Annual Costs
ComponentBase Building
($)Air System Fans 729
Cooling 643
Heating 12,925
Pumps 0
Cooling Tower Fans 0
HVAC Sub-Total 14,297
Lights 5,711
Electric Equipment 2,065
Misc. Electric 0
Misc. Fuel Use 0
Non-HVAC Sub-Total 7,776
Grand Total 22,073
Table 2. Annual Cost per Unit Floor Area
ComponentBase Building
($/ft!)Air System Fans 0.071
Cooling 0.063
Heating 1.255
Pumps 0.000
Cooling Tower Fans 0.000
HVAC Sub-Total 1.388
Lights 0.555
Electric Equipment 0.200
Misc. Electric 0.000
Misc. Fuel Use 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.143
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Table 3. Component Cost as a Percentage of Total Cost
ComponentBase Building
( % )Air System Fans 3.3
Cooling 2.9
Heating 58.6
Pumps 0.0
Cooling Tower Fans 0.0
HVAC Sub-Total 64.8
Lights 25.9
Electric Equipment 9.4
Misc. Electric 0.0
Misc. Fuel Use 0.0
Non-HVAC Sub-Total 35.2
Grand Total 100.0
Hourly Analysis Program v4.50 Page 1 of 1
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
Table 1. Annual Costs
ComponentBase Building
($)
HVAC Components
Electric 4,682
Natural Gas 9,616
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Remote CW 0
HVAC Sub-Total 14,297
Non-HVAC Components
Electric 7,776
Natural Gas 0
Fuel Oil 0
Propane 0
Remote HW 0
Remote Steam 0
Non-HVAC Sub-Total 7,776
Grand Total 22,073
Table 2. Annual Energy ConsumptionComponent Base Building
HVAC Components
Electric (kWh) 27,234
Natural Gas (Therm) 7,176
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Non-HVAC Components
Electric (kWh) 45,233
Natural Gas (Therm) 0
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Totals
Electric (kWh) 72,467
Natural Gas (Therm) 7,176
Fuel Oil (na) 0
Propane (na) 0
Remote HW (na) 0
Remote Steam (na) 0
Remote CW (na) 0
Hourly Analysis Program v4.50 Page 1 of 2
Annual Energy and Emissions SummaryMountain Lakes - DPW 08/09/2010 Kitchen and Associates 02:29PM
Table 3. Annual EmissionsComponent Base BuildingCO2 Equivalent (lb) 0
Table 4. Annual Cost per Unit Floor Area
ComponentBase Building
($/ft!)HVAC Components
Electric 0.455
Natural Gas 0.934
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Remote CW 0.000
HVAC Sub-Total 1.388
Non-HVAC Components
Electric 0.755
Natural Gas 0.000
Fuel Oil 0.000
Propane 0.000
Remote HW 0.000
Remote Steam 0.000
Non-HVAC Sub-Total 0.755
Grand Total 2.143
Gross Floor Area (ft!) 10300.0
Conditioned Floor Area (ft!) 10300.0Note: Values in this table are calculated using the Gross Floor Area.
Table 5. Component Cost as a Percentage of Total Cost
ComponentBase Building
( % )
HVAC Components
Electric 21.2
Natural Gas 43.6
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Remote CW 0.0
HVAC Sub-Total 64.8
Non-HVAC Components
Electric 35.2
Natural Gas 0.0
Fuel Oil 0.0
Propane 0.0
Remote HW 0.0
Remote Steam 0.0
Non-HVAC Sub-Total 35.2
Grand Total 100.0
Hourly Analysis Program v4.50 Page 2 of 2
APPENDIX N
Site Aerial Image
Annual General Meeting of the Mississippi Lakes Association 6 June, 2009 Beckwith Municipal Building
Annual General Meeting of the Mississippi Lakes Association May 29, 2010 Beckwith Municipal Building