    E-Z-GO Shingo Prize Case Study

    Westy BowenVice President of Quality and Six Sigma

    October 15, 2009

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    2/27

    E-Z-GOs Beginning State

    A plaque outside the E-Z-GO weld shop shows the transformation of the facility andcommemorates the shops embarking on a journey of continuous improvement.

    It reads, In 2007 the weld-shop team began a journey of continuous improvement.

    This ongoing journey will transform the shop into a benchmark of premier fabrication

    performance. This spot has intentionally been left unimproved, not as a look

    backward, but as a constant reminder of the importance of moving forward.

    History of AutocraticLeadership

    Top down - do as you are told

    Firefighting Heroes

    2001 Strategy to Outsource

    Dungeon Facilities

    Aging Equipment

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    3/27

    State of the Business

    E-Z-GO was Losing Market Share and Less Profitablethan Main Competitor in an Oligopoly Market

    1999 2000 2001 2002 2003 2004 2005 2006 2007F

    Brand X Sales E-Z-GO Sales

    1999 2000 2001 2002 2003 2004 2005 2006 2007F

    Brand X NOP E-Z-GO NOP

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    4/27

    Textron VisionTo be the premier multi-industry company recognized forour network of powerful brands, world-class enterprise

    processes and talented people

    E-Z-GO MissionTo be the premier provider of light transportation vehicles

    achieving global recognition as the benchmark forcustomer satisfaction and financial results

    E-Z-GO Values StatementTo fulfill these goals, E-Z-GO will exemplify

    Textrons values of integrity, trust, respect and the pursuitof excellence which will enable us to become the employer

    of choice in the industry

    Strategic Direction: Premier

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    5/27

    What is the Enterprise Shingo Prize?

    Shingo Prize for Operational Excellence:

    Established 1988;

    Enterprise Level Prize Established 2008

    Shingo Prize for Operational Excellence is named forJapanese industrial engineer Shigeo Shingo

    Business Week stated that the Shingo Prize is theNobel prize of manufacturing

    The Shingo Model Provides Engine for LeanTransformation

    E-Z-GO Shingo Prize Video

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    6/27

    Textron Business System Assessment

    Section 1:CulturalEnablers(20%)

    Section 2:BusinessOperating

    System(45%)

    Section 3:EnterpriseThinking(10%)

    Section 4: BusinessResults(25%)

    1.1Leadershipand Ethics

    1.2PeopleDevelopment

    1.3Empowerment

    and Involvement1.4 Environmental,Health & Safety

    2.1BusinessManagement and LeanPrinciples

    2.2 CustomerManagement

    2.3Product/ServiceDevelopment

    2.4 Operations

    2.5SupplyManagement

    3.1 LeanEnterprise Culture

    3.2 PolicyDeployment

    4.1 PeopleDevelopment

    4.2Quality

    4.3Delivery

    4.4Cost

    4.5Financial Impact

    4.6CompetitiveImpact

    TBSA Aligned with Shingo Prize Criteria

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    7/27

    Goal set in 2004: Shingo Gold in 08

    Leadership Right People in Right Place

    100% Turnover in Sr. Leadership Team (2002-2004)

    Vision Established for Operational Excellence

    Textron Challenge to Go for Gold

    Textron Business System Assessment

    Accelerator Pilot

    Developed Roadmap

    Lean Maturity Roadmap

    Action Plans for Manufacturing and Functional Areas

    Key is to Just Get Started and Include Everyone

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    8/27

    Implementation Evolution

    2004-2005: Cell Improvement

    Single Point Kaizen Events

    Big Impact Kaizen Events

    2005-2007: Value Stream Improvement

    Material Flow; Process Flow

    Information Flow; Communication

    Cultures, Mindsets and Behaviors (CMB)

    2007-2008: Business Level Improvements

    Goal Deployment (GDP/Hoshin)

    Performance Management

    Pro ject Leader Name Maintenance

    Manufacturing

    Engineering

    Operations

    Quality

    Purchasing

    ProductionControl

    DesignEngineering

    Sales/Marketing

    Finance

    Warehouse

    OperatorMixedModel

    Line

    FleetPowertrain

    Operator(OtherShops)

    GB-NGGCTeam(Former

    Back-shopexpertise)

    OperationServices

    Project 1 Hegel

    Eliminate schedule dispersion and

    create pull process from Pedal Box

    (accelerator only) Back Shops

    John

    Thomann

    Debbie

    Burton,

    Tommy

    G arne r A nn T ate

    Barry

    Lenart Lori Daly

    Mary

    Hampton,

    Barry

    Austin

    Rick

    Schieberl,

    ( 1) TBD TBD

    Project 2 Stern Powertrain Rebalance/ Layout/5S TBD

    Ricky

    Criss

    James

    Gonella

    Raju

    Janardhan

    Kim

    Schleiff

    Spanky,

    Marvin

    (Lee)

    Sims

    John

    Whitehea

    d

    Donna

    Glascock,

    Shane

    Holley,

    Reco Grant

    Project 3 Corradino

    Feasibilitystudyof moving line

    over to Bldg 3

    Gary

    Toole

    Don

    Bingham Janie Burnsed

    Russell

    Watts

    Herbert

    Fryer

    TBD

    (Backshop)

    (Least 2)

    Steve

    Franks;

    David

    Jones

    Pr oj ect 4 Ke ndi nger De vel op Mat er ial Pl an for MP T l ine

    Jeff

    Wall

    Krystal

    Mottel

    John

    Schmidt

    Jason

    Muterspaugh

    Orlando

    Mays

    Mike

    Smith

    TBD(Backshop)

    (Least 2)

    Safety/Maintenance/Operation

    Svcs/ Forklift Operator as Floaterwith exception of Powertrain

    changes. Will need dedicated

    Maintenance person involved.

    Shingijutsu Led Kaizen Event

    Cross Functional Teams

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    9/27

    Initial TBSA February 2005

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    10/27

    2006 High Level Lean Maturity Road Map

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    11/27

    What is an Accelerator ?

    How to build:

    A lean Operating SystemSupporting InfrastructureAligned mindset and capabilities

    Skilled practitionersTeam of ~ 20 full-time; 10 part-time

    Proven in multiple environmentsStandard, but tailored to a specificsituation

    On what matters most, asidentified by the TBSA

    Relevantknowledge

    Skilledpeople

    Provenprocess

    Focus

    Reach outcontinuous

    improvementmindset

    2-5x faster

    A proven process to achieve customer satisfaction, operational andfinancial improvement in a significantly accelerated sustainable way

    A capability engine that builds the skills of management, supervisors andfront line workers so they will be able to drive continuous improvement

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    12/27

    Accelerator Composed of 4 Teams

    Process Flow

    Physical Layout; Line Balancing

    Material Flow

    Line Side Inventory; Warehouse Mgt.

    Right Part at Right Place at Right Time

    Information Flow

    Systems (MIS); MRP; Production Control

    Cultures/Mindsets/Behaviors

    Operator Involvement; Training

    Order of Physical Activity and ChangesReverse Order of Impact to Sustain Improvements

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    13/27

    Meeting Cadence

    Workingteamsupdate

    Content of meeting

    Impactreview withALT

    Staffupdates

    Required

    participation Frequency Duration

    Accomplishments of dayProgress Value Stream. planmilestones

    All Team LeadersFull time teammembers & ProcessOwners (as often

    as possible)

    Daily at4:30

    30 min

    Impact and ProgressFuture milestonesCountermeasures

    Weekly 4-Blocker Review

    ALT membersProject ManagerAll Process Owners

    Weekly onThursdaysat 1PM

    60 min

    Impact to dateBarriers/roadblocksRoll-out plan to other value streams

    ELTProject Manager

    Monthly onspecific Staff

    meetings

    15 min

    Impact to date

    Lessons learnedLearn from Cessna and Bell

    Project Managers Weekly 30 min

    Workingteamsupdate

    Content of meeting

    Impactreview withALT

    Staffupdates

    Required

    participation Frequency Duration

    Accomplishments of dayProgress Value Stream. planmilestones

    All Team LeadersFull time teammembers & ProcessOwners (as often

    as possible)

    Daily at4:30

    30 min

    Impact and ProgressFuture milestonesCountermeasures

    Weekly 4-Blocker Review

    ALT membersProject ManagerAll Process Owners

    Weekly onThursdaysat 1PM

    60 min

    Impact to dateBarriers/roadblocksRoll-out plan to other value streams

    ELTProject Manager

    Monthly onspecific Staff

    meetings

    15 min

    Impact to date

    Lessons learnedLearn from Cessna and Bell

    Project Managers Weekly 30 min

    Daily, weekly, monthly touch points Established

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    14/27

    Current State Value Stream Map

    30% productivity lossDue to imbalanced line

    70% of FTQ issues areFrom material shortage issues

    50% of parts have a lead timeGreater than the order visibility; parts

    are ordered from forecast

    Excess inventoryin the yard

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    15/27

    Future State Value Stream Map

    Customer

    Ship

    Assembly

    (Paced)

    Custom CarsSMRs

    Include Reconfigs

    OE withTFC Tie

    SIOP

    SchedulingMPS, Traffic,

    Sales, Load Seq

    MRP

    Suppliers

    Receiving

    InternalFabrication

    Cars

    Accy

    Internal& Purchased

    Internal

    CommonParts

    Drop-off

    Warehouse

    E-Z-GO3PL

    RBW

    Trailers

    Raw Materials

    FIFO

    ECR/ECN

    FIFO

    Crate Cars

    Line balanced acrossmodels

    Order and forecastingClosely linked

    Standard workFor incomingMaterial flow

    Match orders withFG inventory

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    16/27

    Themes

    Impact

    FTQInventoryaccuracy

    High impact

    Med impact

    Visual management Practical problem solving

    Strong performance dialogs Shared leadership vision Leadership standard work

    Culture, Mind-sets, Behaviors

    Performancemanagement

    Process flow

    Low impact

    Production scheduling automated and streamlined Orders and quotations integrated material Effective control procedures that ensure accurate inventory parameters

    InformationFlow

    Balance line to takt and build capability Redesign line layout Design and document safer, more ergonomic and more efficient operations

    Execution of PFEP across all MML parts Improvement of material flow via sequencing Standard work for all conveyance and material management

    Material flow

    Keys to drivingsustained impactacross MixedModel valuestream and E-Z-GO

    Productivity

    Design Principles - Metrics

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    17/27

    Future state manningrequirements are~30% less:

    Total work content per2+2G* = 2 hr 15 min

    Cars per day = 85

    Work content per day= 191 hr 15 min

    Number of operatorsrequired** = 21(current = 31)

    Some stations very close or over takt (when

    walking time included) limiting production

    capacity and causing waiting elsewhere

    Red = walking

    Orange = sub-assemblies

    Yellow = variation

    Green/blue = 2+2G work elements

    On average, station cycle time is

    30% lower than takt to meet 85

    vehicles/daythere is significant

    opportunity to rebalance to fewer

    stations Takt = 85vehicles/day

    Process Flow: Manage to Takt

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    18/27

    Business Level Metrics Cascaded throughoutOrganization

    Safety, Quality, Delivery, Cost (SQDC)

    COUNTER MEASURES COUNTER MEASURES COUNTER MEASURES COUNTER MEASURESISSUE ACTION WHO DUE STATUS ISSUE ACTION WHO DUE STATUS ISSUE ACTION WHO DUE STATUS ISSUE (P/N) ACTION WHO DUE STATUS

    # of Safety/Ergo Improvements Implemented TSS Survey Results # Projects Closed $ Cash Improvement

    DELIVERY

    Key Performance Indicators - Textron Six Sigma

    CloseTSSProjects that generateCash$(reducedinventory, usedcars,

    receivables; increaseNOP)Numberof distinct safetyand ergonomic improvements implementedi nall

    Black Belt and GreenBelt projects closedduringthemonth

    SatisfactionSurveyof overallexperiencewithTSSfrompartic ipants

    (Process Owners, Champions, Teammembers)onBBproject. Numberof GreenBelt andBlack Belt projects closedduringthemonth

    COST/ PRODUCTIVITY5s / SAFETY QUALITY

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    0

    1

    2

    3

    4

    5

    6

    7

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    0.0

    100,000.0

    200,000.0

    300,000.0

    400,000.0

    500,000.0

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    J

    M

    M

    A

    D

    F

    A

    J

    J

    S

    O

    N

    J

    F

    A

    M

    J

    J

    A

    O

    N

    S

    D

    M

    J

    F

    A

    M

    J

    J

    A

    O

    N

    D

    M

    J

    F

    A

    M

    J

    M

    J

    A

    O

    S

    N

    D

    J F M A M J SAJ O N D J F M A M J SAJ O N D J F M A M J SAJ O N D J F M A M J SAJ O N D

    MonthlyObjectiveAchived MontlhyObjectiveNot Achived

    MonthlyObjectiveAchived MontlhyObjectiveNot Achived

    MonthlyObjectiveAchived MontlhyObjectiveNot Achived

    MonthlyObjectiveAchived MontlhyObjectiveNot Achived

    MonthlyObjective MontlhyActual MonthlyObjective MontlhyActual MonthlyObjective MontlhyActual MonthlyObjective MontlhyActual

    S

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500 MonthlyObjective MontlhyActual

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    19/27

    Material Flow: Sequence Center to Assembly

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    20/27

    Control Block

    SEQ - STEP (What) -

    2

    On Option line of main screen, Type in

    the part number, buyer number, the

    warehouse, and the delivery date

    SYM -

    3 Type "F-8" to update

    Send e-mail or call applicable supplier

    to determine shipping schedule

    4

    1Log onto the 36/PMR session on AS400

    system.

    A Textron Company

    1

    Improvements Made

    Short-Term MPS Tool

    Expanded MRP visibility to

    configured quotes

    Reduced PAR volume

    SIOP impact tool for what-if analysis

    Standard work for

    Buyer/Planners

    Standard work for ChangeNotice Implementations

    Piloting A2 Kanban processfor windshields

    Information Flow: Scheduling

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    21/27

    The work has been very hard butin the end has been very

    rewarding.We know that there are still some

    things that need to be checkedand worked out

    You can movearound the areas

    a lot easier

    With the new waythe line moves, it

    give me more timeto get done what I

    need to do

    Parts are

    stocked up all ofthe time now

    Now we run bythe schedule,

    unless wehappen to be

    out of aparticular part

    Now it is not ascluttered and

    things are wellorganized, so

    we have plentyof room

    Before the changes on the assembly manypeople were weary of it and didnt think

    actually that it would work.So far it has worked out extremely well.

    I think the process has been beneficial toeveryone on the line as well as to E-Z-GO.

    Partspresentationis a MAJOR

    change

    The big differenceI see is how the

    line runs now itlooks like the lineis running slower

    Communicationboards help usknow what is

    going on and whatwe have to face

    for the day

    Now it is a lotSAFER to

    work

    CMB Team: Employee Engagement

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    22/27

    Cultures Mindsets and Behaviors

    Most Important Link

    Begin to See Shift in Lean Capabilities

    John Ward Lean Team Video

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    23/27

    Evolution to Business Level Improvement Goal Deployment Process (Hoshin Planning)

    Targets to Improve (TTIs)

    Key Process Improvement Metrics (KPIVs)

    Rigorous Reviews with Countermeasuresl Operations - Key Operational Improvements l l l l m l m m l

    l Growth - Develop and Execute Growth Agenda l m u m m m m m l m

    l Customer - Develop and Execute Action Plans l l l l u l m

    GrowRevenue

    X%byYYear

    ImproveCustom

    erSatisfactionbyX%

    ImproveCustom

    erOnTimeDeliveryfromX%toY%by(date)

    ImproveDPMO

    fromXtoYby(date)

    ImproveFillRatefromXtoYby(date)

    ReduceNewProductIntroductionCycleTimebyX%by(date)

    ReduceFreight

    CostbyX%by(date)

    ImproveWarran

    tyas%SalesbyX%by(date)

    ReduceSG&AExpensebyXby(date)

    VicePresident,

    GlobalSales

    VicePresident,

    BusinessDevelopment

    VicePresident,

    HumanResources

    VicePresident,

    Quality

    VicePresident,

    Operations

    ChiefFinancialOfficer

    ChiefInformatio

    nOfficer

    VicePresident,

    Engineering

    VicePresidentCommunicationsandBrandManagement

    l l World Class Customer Satisfaction

    l l Engaged Employees u

    l l Achieve Shingo Prize for Enterprise Level l

    l l Grow Business m Enabling Resource

    Action Plan Owner

    Primary IP Owner

    Top LevelPriorities/Actions

    2009 AnnualPremier Objectives

    4 Year Premier

    Objectives

    Targets toIm rove

    KPI Owner 2008 JOP2009 YTD

    ACTJUN JUL AUG SEP OCT NOV DEC Full Year

    Talent0.90 KPI Stretch 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.901.35 Act. / Fore. 1.15 1.26 1.09 0.97 0.99 0.90 0.85 0.85

    30.1% KPI Stretch 30.1% 30.1% 30.1% 30.1% 30.1% 30.1% 30.1% 30.1%32.6% Act. / Fore. 32.6% 32.6% 32.6% 32.6% 32.6% 32.6% 32.6% 32.6%

    0.9% KPI Stretch 1.1% 1.2% 1.4% 1.5% 1.7% 1.8% 2.0% 2.0%0.6% Act. / Fore. 0.6% 0.6% 0.6% 0.6% 0.6% 0.6% 0.6% 0.6%

    Cash11,375$ KPI Stretch 11,325$ 11,275$ 11,225$ 11,175$ 11,125$ 11,075$ 11,075$ 11,075$

    $10,754 Act. / Fore. $11,200 $10,600 $10,200 $9,800 $9,500 $9,000 $9,000 9,000$

    9,188$ KPI Stretch 8,267$ 7,992$ 8,128$ 8,324$ 8,332$ 8,002$ 7,786$ 7,786$$8,118 Act. / Fore. $7,500 $ 9, 30 0 $ 8, 72 6 $8,274 $ 8, 78 6 $ 8, 82 3 $7,586 7,586$

    2,400$ KPI Stretch 2,600$ 2,600$ 2,100$ 2,000$ 1,900$ 1,800$ 1,700$ 1,700$2,521$ Act. / Fore. 1,715$ 1,635$ 1,555$ 1,475$ 1,395$ 1,315$ 1,300$ 1,300$

    1,629 KPI Stretch 233 300 638 500 700 700 700 5,4001,865 Act. / Fore. 233 225 130 403 306 419 460 4,041

    2,399$ KPI Stretch 2,356$ 2,313$ 2,269$ 2,226$ 2,183$ 2,139$ 2,096$ 2,096$7,135$ Act. / Fore. 3,584$ 4,244$ 4,803$ 5,103$ 7,003$ 4,149$ 2,095$ 2,095$

    23,809 KPI Stretch 5,753 3,060 5,451 5,559 8,502 5,858 4,677 65,22324,139 Act. / Fore. 5,004 3,060 5,451 5,559 8,502 5,858 4,677 62,250

    8,396 KPI Stretch 1,599 1,679 2,162 1,819 2,349 1,981 1,453 24,700

    8,038 Act. / Fore. 2,000 1,679 2,162 1,835 2,535 1,981 1,453 21,68319,205 KPI Stretch 6,424 6,240 6,240 6,240 6,224 6,214 6,214 63,00024,113 Act. / Fore. 4,800 5,860 5,860 5,860 5,900 5,900 5,907 64,200

    31,930$ KPI Stretch 30,954$ 29,853$ 28,942$ 27,774$ 26,952$ 25,995$ 25,559$ 25,559$32,225$ Act. / Fore. 33,255$ 29,559$ 28,635$ 27,972$ 31,723$ 31,410$ 29,759$ 29,171$

    40,358$ KPI Stretch 39,450$ 38,542$ 37,633$ 36,725$ 35,817$ 34,908$ 34,000$ 34,000$34,800$ Act. / Fore. 39,450$ 38,542$ 37,633$ 36,725$ 35,817$ 34,908$ 34,000$ 34,000$

    5,167$ KPI Stretch 5,000$ 4,833$ 4,667$ 4,500$ 4,333$ 4,167$ 4,000$ 4,000$4,859$ Act. / Fore. 3,639$ 3,840$ 3,622$ 3,750$ 3,421$ 3,053$ 2,644$ 2,644$

    NOP$56,286 KPI Stretch 10,493$ 12,346$ 12,787$ 12,052$ 11,503$ 11,399$ 7,880$ 134,748$$43,218 Act. / Fore. $9,668 $9,071 $11,589 $9,894 $13,489 $10,486 $7,888 115,302$

    16,622$ KPI Stretch 3,397$ 4,921$ 3,910$ 2,860$ 4,749$ 2,403$ 1,181$ 40,043$14,357$ Act. / Fore. 2,792$ 4,520$ 4,123$ 3,758$ 4,362$ 2,770$ 1,177$ 37,859$

    3,807$ KPI Stretch 497$ 693$ 516$ 476$ 525$ 671$ 1,071$ 8,256$4,753$ Act. / Fore. 497$ 693$ 516$ 476$ 508$ 577$ 821$ 8,842$

    (1,053)$ KPI Stretch 266$ 931$ (270)$ (538)$ (505)$ (607)$ 298$ (1,479)$(2,511)$ Act. / Fore. 574$ 1,060$ (211)$ (904)$ (1,138)$ (184)$ 1,148$ (2,167)$

    9.0 KPI Stretch 9.3 10.7 7.1 7.6 7.5 7.5 7.4 8.47.2 Act. / Fore. 9.3 10.7 7.1 7.6 7.5 7.5 7.4 8.4

    Process98% KPI Stretch 98% 98% 98% 98% 98% 98% 98% 98%98% Act. / Fore. 98% 98% 98% 98% 99% 99% 99% 98%

    157 KPI Stretch 147 138 128 119 109 100 90 90145 Act. / Fore. 147 138 128 119 109 100 90 90

    $8.9M

    Collins $12.3M

    Collins

    Moinikunta

    $9.3M

    $38.8M

    141

    Specialty SIOP demand forecast accuracy of 95% Miller

    Total Net Warranty from $9.3M to $8.3M by 12/31/09 Younger

    60,958

    Decrease Branch Stock Specialty inv by $1.3M by

    12/31/09 ($5.3M to $4M / Units - 1,511 to 1,000)5.3M

    Miller

    Miller

    Reduce Specialty floorplan from $44.9m to $34m

    by 12/31/09 (Units 8,600 to 6,515)Miller

    Decrease Used Car Inventory by $5.8M (to 17,379

    units) by 12/31/09 ($1,473 per unit)

    Jhant/Miller $2.6M

    Decrease Branch Parts Inventory from $2.2M to

    $1.7M by 12/31/09Jhant $2.2M

    Sell 5,400 additional used golf cars to fleet channel

    by 12/31/09Jhant 0

    Exceed AOP targets for Raw/WIP inventory by

    $1.3m by 12/31/09

    Reduce Labor Hours Per Vehicle from 8.9 to 8.4 for

    2009

    Decrease Augusta Finished Goods Inventory from

    $2.6M to $2.1 by 12/31/09

    Miller

    Achieve Used car sales of 63,000 by 12/31/09

    (includes used cars to the fleet channel)

    Fleet SIOP demand forecast accuracy of 95% Jhant

    Decrease Parts inventory by $3.3M by 12/31/09

    Achieve AOP Specialty sales of $134.7M

    Improve FTQ from 96% to 98% by 12/31//09

    Miller

    Achieve AOP Parts sales of $40M Kopay

    Neely

    Safety - Achieve TRIR of .90 by 12/31/09 Johnson

    Reduce Regretted Turnover from 4% to 2% by

    12/31/09

    Improve CR/CN Cycle Time from 141 days to 90

    days by 12/31/09

    K. Reeves

    Sustain Inclusive Workforce at 30.1% by 12/31/09 K. Reeves

    Achieve AOP targets for total manufacturing

    variancesDraper

    Heffline

    30.1%

    0.69

    $3.5M

    134.7M

    $44.9M

    $31M

    NA

    4.0%

    NA

    8.9 est

    96%

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    24/27

    Driving CI Responsibility to Operator

    Developed Curriculum and Schedule to Train 80%Workforce in Lean Techniques

    Attend 24 Hours of Training

    Complete 2 projects (team or individual) in 12 Month Period

    Certify as an E-Z-GO Lean Technician

    Promotes Kaizen as Way of Life: Everyone EmpoweredSession Course Location Instuctor

    Time

    allotment in

    minutes

    Session 1Material Movement Kanban Simulation Bldg III T/Room Deb Smith/Eric Ethington 110

    What is World Class Bldg III Plant Renee Stern 55

    Finance Bldg III Plant Jason Alford 55

    Session 3 Standard Work Bldg III Plant Rick McCoy / Allen Evans 110

    Visual Management Bldg III Plant Scott Seigler 55

    Poka Yoke Bldg III Plant Chris Furman 55

    Session 5 5S Bldg III Plant Eric Safford 110

    Question & Answer with Plant Manager QA T/Room Darryl Heffline 45

    Team Building QA T/Room Vito Corradino 65

    Session 7 7 Wastes Bldg II plant Jay Johnson/Mike Rouse 110

    Quality Bldg II plant Vivek Moinikunta 55Supply Chain Bldg II plant John Collins 55

    Intro to Rack Building Bldg II plant Shawn Flanagan/Marlon Bray 55

    Total Productive Maintenance (TPM) Bldg II plant Mark Thrasher 55

    Session 10One Piece Flow (Lego race cars) LeanSimulation

    Bldg I T/Room Goran Rajkovic/Poppie Blue 110

    Practical Problem Solving (PPS-5whys/

    Bldg II plant Brad Hanson 55

    SQDC - Metrics (Safety, Quality,Delivery, Cost)

    Bldg II plant John Thomann 55

    "Jeopardy" Reinforcement Questions This will be conducted in the lastclass of the day by all instructors

    All Instructors 55

    Session 2

    Session 4

    Session 6

    Session 8

    Session 11

    Session 9

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    25/27

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    26/27

    Accelerator is Results Driven:

    Metric Before After

    Operator Load Efficiency 54% 98%

    First Time Quality 51% 98%

    Inventory Accuracy 82% 97%

    Schedule Adherence 62% 95%

    Be Patient: Likely to Get Worse BeforeImprovement is Realized

  • 8/11/2019 Bowen E Z GO Shingo Prize Case Study

    27/27

    What is Next?

    Sustain is more important than ever

    Continuous improvement is part of everyones job

    Other recognition for best in class (Industry Week)

    Benchmarking tours

    Pushing Continuous Improvement to Suppliers andCustomers

    The Journey Continues