1. Question 1 10 1,000During the pre-spud meeting, the tool pushertells the WSL that his rig manager will notallow a hard shut-in for a suspected kick.The BP-contractor WCBD states that thehard shut-in method will be used. Whatshould be the WSLs response?Request that a meeting beset up for them to speakwith the Rig Manager andresolve the issue.9 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Plan to use the hard shut-inmethod only if the drillerknows the well is kicking.Send an email to the BP WellsTeam Leader requesting adeviation from the WCBD.A. B.The tool pusher should speak tothe drilling contractorsrepresentative who signed theBP-contractor WCBD.Times UpC. D. 2. AnswerRequest that a meeting beset up for them to speakwith the Rig Manager andresolve the issue.Where can the WSL find support in UP 4.1-0004 for this response?Sections 3.B & 3.CC. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000During the pre-spud meeting, the tool pushertells the WSL that his rig manager will notallow a hard shut-in for a suspected kick.The BP-contractor WCBD states that thehard shut-in method will be used. Whatshould be the WSLs response?A. B.Plan to use the hard shut-inmethod only if the drillerknows the well is kicking.Send an email to the BP WellsTeam Leader requesting adeviation from the WCBD.The tool pusher should speak tothe drilling contractorsrepresentative who signed theBP-contractor WCBD. 3. A driller asks for clarification of theobjective of the Well Control Bridgingdocument. What is the correct answer?It serves as a database forimportant HSE issues specific tothe drilling contractor safetymanagement system.It identifies gaps between BP wellcontrol requirements and practices, thedrilling contractors well controlrequirements and practices, andmutually develops an agreed pathforward to rectify gaps.It defines roles andresponsibilities for bridgingBP and contractor gaps.All of the above.Question 2A. B.C. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times Up 4. AnswerA driller asks for clarification of theobjective of the Well Control Bridgingdocument. What is the correct answer?It serves as a database forimportant HSE issues specific tothe drilling contractor safetymanagement system.A. B.It defines roles andresponsibilities for bridgingBP and contractor gaps.It identifies gaps between BP wellcontrol requirements and practices, thedrilling contractors well controlrequirements and practices, andmutually develops an agreed pathforward to rectify gaps.C. D. All of the above.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Where is this requirement found in UP 4.1-0004? Section1 IntroductionHas the WCBD been organized around this objective?Yes 5. Question 3The WSL asks the drilling contractors HSErepresentative for a copy of the contractors HSEPolicy. The HSE representative says that the HSEpolicies agreed to under the rig contract can befound in the BP-contractor WCBD. Is this correct?A. B.YES NO10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times Up 6. Answer 10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000The WSL asks the drilling contractors HSErepresentative for a copy of the contractors HSEPolicy. The HSE representative says that the HSEpolicies agreed to under the rig contract can befound in the BP-contractor WCBD. Is this correct?A. YES B. NOWhere is this found in UP 4.1-0004?Section 1 - Introduction 7. What well control documents are used toidentify and resolve gaps between BP and rigcontractor well control policies?UP 4.1-0004 Well ControlBridging DocumentsDrilling Well Control Manual,EP SG 4.1-0035Question 4GDP 3.1-0001 Managementof RiskUG 2.1-0004 How we workwith S&ORGP 10-10, 10-11, 10-45, 10-65,and UP 4.1-0005 and drillingcontractors well control policies.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000A. B.C. D.E.Times UpF. All of the above 8. Answer 10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000What well control documents are used toidentify and resolve gaps between BP and rigcontractor well control policies?UP 4.1-0004 Well ControlBridging DocumentsA. B.Where is this found in UP 4.1-0004?Section 4.1 - Gap Identification and RegistrationC. D.Drilling Well Control Manual,EP SG 4.1-0035GDP 3.1-0001 Managementof RiskUG 2.1-0004 How we workwith S&ORE.GP 10-10, 10-11, 10-45, 10-65, andUP 4.1-0005 and drilling contractorswell control policies.F. All of the above 9. The BP-contractor WCBD appended to a drilling contract has apolicy different from what the BP WSL has previously seen. What isthe probable basis of this difference?A change was required by BP attorneys.A new government requirementA mistake. Only BP practices are used on BPoperations.The different policy was the resultof an identified gap and was resolved using the drillingcontractors policy or a combination of BP and drillingcontractor policies.Question 5A. B.C. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times Up 10. AnswerWhere is this requirement found in UP 4.1-0004?Section 4.2 Gap ResolutionC. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000The BP-contractor WCBD appended to adrilling contract has a policy different from whatthe BP WSL has previously seen. What is theprobable basis of this difference?A. A change was required by B.BP attorneys.A new government requirementA mistake. Only BP practicesare used on BP operations.The different policy was the resultof an identified gap and was resolvedusing the drilling contractors policy or acombination of BP and drilling contractorpolicies. 11. Question 6 10 1,000The tool pusher tells the WSL that a crew is coming from a sister rig operating in the area withsimilar drilling conditions. The crew is unfamiliar with the well control policies as per the BP-contractorWCBD. Since the rigs are the same and drilling conditions are also essentially thesame, he recommends the crew operate under policies they are familiar with until they havebeen trained in the new policies. What should be the WSLs reply?9 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000A. B.Times UpAfter the crew arrives at the rig, drills and observing thecrews work needs to confirm understanding of andproficiency with policies agreed in the WCBD.This would be a deviation. Training crews to becomeproficient in the implementation of BP-ContractorWCBD policies needs to commence before arriving atthe rig.Give his approval. The recommendation is notunreasonable. Both A and B.C. D. 12. Answer 10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000The tool pusher tells the WSL that a crew is coming from a sisterrig operating in the area with similar drilling conditions. The crew isunfamiliar with the well control policies as per the BP-contractorWCBD. Since the rigs are the same and drilling conditions arealso essentially the same, he recommends the crew operateunder policies they are familiar with until they have been trained inthe new policies. What should be the WSLs reply?Where can the WSL find support in UP 4.1-0004for this response?Section 4.2 Gap ResolutionGive his approval. Therecommendation is notunreasonable.Both A and B.After the crew arrives at the rig, drillsand observing the crews work needsto confirm understanding of andproficiency with policies agreed in theWCBD.This would be a deviation. Trainingcrews to become proficient in theimplementation of BP-ContractorWCBD policies needs to commencebefore arriving at the rig.A. B.C. D. 13. Question 7 10 1,000The BP-contractor WCBD appended to a drilling contract has a policy stateddifferently from what the BP WSL has previously seen. The tool pusher says thatthe policy is as per the drilling contractors policy. Where can the WSL find thedocuments in support of this deviation to BP policy?9 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times UpRequest it from the drilling operations manager. BPdeviation documents are held on file as part of theauditable trail. Contractor deviation documents areavailable from the contractor upon request.Deviation documents are attached to the BP-ContractorWCBD.Deviation documents are BP confidential andnot available for WSLs to review.Reasons for the change can be found in theapproved drilling procedures.A. B.C. D. 14. Answer 10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000The BP-contractor WCBD appended to a drillingcontract has a policy stated differently from what the BPWSL has previously seen. The tool pusher says that thepolicy is as per the drilling contractors policy. Wherecan the WSL find the documents in support of thisdeviation to BP policy?Request it from the drilling operationsmanager. BP deviation documents areheld on file as part of the auditabletrail. Contractor deviation documentsare available from the contractor uponrequest.Deviation documents are attachedA. B. to the BP-Contractor WCBD.Deviation documents are BPconfidential and not availablefor WSLs to review.Reasons for the change can befound in the approved drillingprocedures.C. Where is this requirement founDd.?Section 4.4.B.3 Review and Approval 15. Question 8The WSL is told that the BP team agreed that a contractor policy would beused to drill an upcoming well. Where can the WSL find a date by which thework on the required BP deviation is expected to be completed?A deviation is not required if followingeither BP or drilling contractors policy.Prior to the well entering the pressureenvelopeA. B.In the last column of the gap register. Before the drilling contract is signedC. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times Up 16. The WSL is told that the BP team agreed that a contractor policy would beused to drill an upcoming well. Where can the WSL find a date by which thework on the required BP deviation is expected to be completed?A deviation is not required if followingeither BP or drilling contractors policyA. B.Prior to the well entering the pressureenvelopeAnswerWhere is this requirement found in UP 4.1-0004?Section 4.2.E.3 Gap ResolutionC. D.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000In the last column of the gap register. Before the drilling contract is signed 17. Question 9 10 1,000The WSL sees a policy in the BP-Contractor WCBD appended to the rigcontract that he cannot find in BP policy documents. What is the probableorigin of this policy?9 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times UpA gap identified during Gap Resolution meetingsinvolving a contractor policy for which there wasno BP policy.The well the WSL is on is a special caserequiring a number of new requirements notincluded in BP documents.BPs Partners often require that theirrequirements be implemented in Fieldsoperated by BP.It was negotiated by PSCM and the drillingcontractor.A. B.C. D. 18. Answer 10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000The WSL sees a policy in the BP-Contractor WCBDappended to the rig contract that he cannot find inBP policy documents. What is the probable origin ofthis policy?A gap identified during GapResolution meetings involving acontractor policy for which therewas no BP policy.The well the WSL is on is aspecial case requiring anumber of new requirementsnot included in BP documents.A. B.BPs Partners often require thattheir requirements beimplemented in Fields operatedby BP.Where is this requirement found in UP 4.1-0004?Section 4.1 Gap Identification and RegistrationIt was negotiated by PSCMand the drilling contractor.C. D. 19. Question 10During the Pre-Spud meeting, the WSL advises the tool pusher and driller thata review of the BP-contractor WCBD needs to be performed. The tool pusheradvises the WSL the contractor HSE department will manage implementationof the document. Is this an acceptable answer?A. B.YES NO10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000Times Up 20. Question 10During the Pre-Spud meeting, the WSL advises the tool pusher and driller thata review of the BP-contractor WCBD needs to be performed. The tool pusheradvises the WSL the contractor HSE department will manage implementationof the document. Is this an acceptable answer?A. B.10 1,0009 1,0008 1,0007 1,0006 1,0005 1,0004 1,0003 1,0002 1,0001 1,000YES NOWhy? Contractors well site personnel need to know with clarity the requirements to drill the well so agreed firstactions can be made without consultation. In reality, someone much higher than a tool pusher within the contractororganization should have communicated the WCBD to the troops.