bpa - wisp project

14
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA - WISP Project NASPI Work Group Meeting October 12-13, 2011 Scott Lissit – Project Manager, Integration Lawrence Carter – Project Manager, PMU Installation Nick Leitschuh – Control Center Lead Dmitry Kosterev – Transmission Planning

Upload: emmanuel-hale

Post on 04-Jan-2016

123 views

Category:

Documents


0 download

DESCRIPTION

BPA - WISP Project. NASPI Work Group Meeting October 12-13, 2011 Scott Lissit – Project Manager, Integration Lawrence Carter – Project Manager, PMU Installation Nick Leitschuh – Control Center Lead Dmitry Kosterev – Transmission Planning. Project Overview. Phase 1 - WISP. Phase 2. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: BPA - WISP Project

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

BPA - WISP Project

NASPI Work Group Meeting

October 12-13, 2011

Scott Lissit – Project Manager, Integration

Lawrence Carter – Project Manager, PMU Installation

Nick Leitschuh – Control Center Lead

Dmitry Kosterev – Transmission Planning

Page 2: BPA - WISP Project

2

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Project Overview

Phase 1 - WISP Phase 2

Apr 2010 Apr 2013 Apr 2015Apr 2011 Apr 2012

- PMU Installation• ~132 PMUs• 45 sites (32 500kV sites, 13 230kV

sites)• 10 wind sites (data only)

- No DOE funding used. Matching SGIG grant goes to WECC

- Control Center network design/install

- Situational awareness applications (near-term)

- SynchroPhasor RAS development

Apr 2014

- SP RAS deployment

- Additional applications

- Wind site integration

Page 3: BPA - WISP Project

3

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Existing PMU

Existing/Replace PMU, Group 1

Existing/Replace PMU, Group 2

Existing/Replace PMU, Group 3

New PMU, Group 1

New PMU, Group 2

New PMU, Group 3

New PMU, Group 4

BPA PMU Deployment

Page 4: BPA - WISP Project

4

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

PMUs

• SEL 487e chosen, with customized features:

• Multicast capability• On-the-fly configuration for main/aux bus• Two fully-configurable data streams from a single

PMU (PDCs and RAS)

• Stand-alone units, deployed in pairs or quads

• IEEE C37.118 standard, M-class

• 60 samples per second

• Measurements:

• Voltage and line current phasors in polar format, bus frequency, calculated line MW and MVAR, PCB and MOD statuses

• No PDCs in substations

Page 5: BPA - WISP Project

5

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

PMU Installation

Redundant PMUs with redundant communication paths (to two control centers)

Current Status: “Standard” designs complete 6 PMUs installed at 2 initial “Beta” sites “Beta” data being analyzed

Contractor installation (Wilson/SAIC) Schedule

• Group 1 (Sites 3 – 14): February, 2012• Group 2 (Sites 15 – 26):June, 2012• Group 3 (Sites 27 – 40):October, 2012• Group 4 (Sites 41 – 45):March, 2013• Wind sites 1-10: December 2012

Page 6: BPA - WISP Project

6

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Communications Network

BPA-operated telecom network SONET backbone

• Digital microwave with legacy analog microwave PMU network is IP over TDM using fractional

T1s. UDP protocol. High-capacity routers chosen to enable

migration to future applications (Ethernet devices) and evolution of PMU requirements

RAS performance driving design (latency requirements)

NERC CIP compliance driving design, network monitoring

Telecom backup battery and charger replacement required at most sites

Page 7: BPA - WISP Project

7

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Control Centers

Redundant PDCs in each control center• Currently in testing, final selection not yet made

Control Center Architecture• Evaluating feasibility of in-house design based on OSI PI

architecture and dedicated application server

Data archives in each control center (short-term), and lab (long-term)• Currently in testing, final selection not yet made

Responsible for PMU network monitoring and NERC CIP compliance

WISP WAN gateway Communications link between control centers

Page 8: BPA - WISP Project

8

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Network Architecture

Same as DCC

PDCMCCPMU

DCCPMU

Router

Router

MCC(Alternate CC)

MCCPMU

DCCPMU

Router

EncryptedNetwork

SA PI

WECCowned

Partners

PDC

C37.118

SP RAS

PDCs

WECC

BPA WAN

WISP WAN

DCC(Primary CC)

SCADA

M

Substation AAA

M

Substation BBB

Historian PI

C37.118

2 secdownsampled

AlarmEvent

SA Users(including

Dispacher)

Alarm

Dispatcher

Page 9: BPA - WISP Project

9

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Applications Strategy: Deploy “WASA light” and WECC shared view in Phase 1. Situational Awareness

• Phase angle alarm • Event detection • Oscillation Detection• Mode Meter (Montana Tech)

Engineering Applications• Event analysis• Dynamic performance baselining• Model validation

Other applications under development by BPA Technology Innovation:• Robust state estimation and contingency analysis• Wide area visualization

Page 10: BPA - WISP Project

10

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Model-Based Tools:• Contingency Analysis• State EstimationMeasurement-based Tools:• Dynamic reactive reserve monitor• Phase angle monitor …

Synchro-phasors SCADA

Malin500 voltage (kV)

554

554.2

554.4

554.6

554.8

555

555.2

555.4

555.6

555.8

556

0 100 200 300 400 500 600 700 800 900

Time (sec)

Volta

ge (k

V)

Trend Displays (PMU, SCADA)

Wide-Area View: SCADA, PMU, Results of Contingency Analysis

DAT

AAN

ALYT

ICAL

AP

PLIC

ATIO

NS

PRES

ENTA

TIO

N

Measurement-Based Applications:• Event Detection• Oscillation Detection• Mode Meter

DashboardAlarms

BPA WASA Strategy

Page 11: BPA - WISP Project

11

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Simulated PMU data streams

Wide Area Controls

Test Controller Running Response Based Logic

Testing

System

Digital Outputs

Historical Data

Raw Data

User values Inject errors, delays, bad data, etc

• Developmental version of PMU-based Remedial Action Scheme (RAS)

PHASE 1

Page 12: BPA - WISP Project

12

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Build on Existing Control Architecture

500-kV Line A-BLine Loss Logic

500-kV Line B-CLine Loss Logic

ExistingRAS

Controller

SWITCH

Existing Local

ControllerMeasured Local Voltage

Voltage Set-PointSwitching

Sequence

Response-Based Logic

Controller

Wide-AreaMeasurements

PHASE 2

Page 13: BPA - WISP Project

13

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Challenges

PMU Installation• Short timeline • Scheduling equipment outages

Telecom• Equipment selection impacted by RAS latency

requirements, and bandwidth for future traffic • Necessity for upgrades of back-up batteries and chargers at

substations Cyber security

• PMUs will be CCAs, with associated PSP, ESP and operational requirements

Selection/development of near-term situational awareness applications and environment (compatibility with legacy systems)

Training for operations and maintenance of new equipment and network

Page 14: BPA - WISP Project

14

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

¨  Acknowledgment: This material is based upon work supported by the Department of Energy under Award Number(s) DE-OE0000364¨  Disclaimer: This report was prepared as an account of work sponsored by an agency of the United States Government.  Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or

implied, or assumes any legal liability or responsibility for the accuracy, completeness, usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.  Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof.  The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

Contact Information

Scott Lissit, PM

360-619-6415

[email protected]

Lawrence Carter, PM (PMU Installation)

360-619-6675

[email protected]

Nick Leitschuh, PM (Control Center, SA Apps)

360-418-8739 

[email protected]