brae area decommissioning environmental impact … area decommissioning environmental impact...
TRANSCRIPT
Brae Area Decommissioning
Environmental Impact Assessment (EIA)
Scoping Report
Prepared for:
Marathon Oil UK LLC Aberdeen, UK
Prepared by: Ramboll Environ UK Limited
Edinburgh, UK
Date: February 2016
Project or Issue Number:
UK12_21217
Contract No: UK12_21217 Issue: 8 Author Felicity Arthur/Sarah Cressy/ Peter Bruce
(signature):
Project Manager/Director Nathan Swankie
(signature):
Date: 10th February 2016
This report has been prepared by Ramboll Environ with all reasonable skill, care and diligence, and taking account of the Services and the Terms agreed between Ramboll Environ and the Client. This report is confidential to the client, and Ramboll Environ accepts no responsibility whatsoever to third parties to whom this report, or any part thereof, is made known, unless formally agreed by Ramboll Environ beforehand. Any such party relies upon the report at their own risk.
Ramboll Environ disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the Services.
Version Control Record
Issue Description of Status Date Reviewer Initials
Author Initials
8 Final Issue for Consultation 10/02/2016 NS PB
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Contents
1 Introduction 1
1.1 Regulatory Context 1
1.2 Purpose of this Report 1
1.3 Scoping and the Environmental Impact Assessment (EIA) Process 2
2 Brae Area Decommissioning Programmes 5
3 Decommissioning Activities 8
3.1 Transportation of Workers and Materials 8
3.2 Topsides Preparation 8
3.3 Platform Subsea Installations Decommissioning 9
3.4 Topsides Removal 9
3.5 Drill Cuttings Piles Decommissioning 9
3.6 Steel Jacket Removal 10
3.7 Area Wide Subsea Installations Decommissioning 10
3.8 Well Decommissioning 11
4 Scoping Methodology 12
4.1 Approach to the Identification of Activity/Receptor Interactions 12
4.2 Multi-Stage Scoping Process 12
5 Stage 1: Preliminary Scoping 15
5.1 Stage 1 Scoping Summary 15
5.2 Stage 1 Effect Rating – Summary Matrices 15
5.3 Habitat Regulations Assessment (HRA) Screening 19
6 Stage 2 - Detailed Scoping 20
6.1 Stage 2 Scoping Summary 20
7 EIA technical studies 23
7.1 Designated Sites and Species 23
7.2 Seabed Disturbance Effects 23
7.3 Water Quality Effects 23
7.4 Noise Effects 24
7.5 Socio-economic Effects 24
7.6 Accidental Events 24
7.7 Cumulative Effects and Transboundary 24
7.8 Issues Scoped Out 25
List of Annexes
Annex A: Environmental Baseline
Annex B: Preliminary Scoping Parameters: Frequency/Likelihood; Magnitude and Environmental Effect/Risk Matrices
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Annex C1: Activity/Receptor interactions scoped as ‘high’ potential for significant environmental effect
Annex C2: Activity/Receptor interactions considered ‘medium’ potential for significant environmental effect and therefore taken forward to Stage 2 scoping
Annex C3: Activity/Receptor interactions considered ‘low’ potential for significant environmental effect and therefore scoped out of the EIA
Annex D1: Detailed Scoping Parameters: Sensitivity; Duration of Impact; Geographic Extent.
Annex D2: Summary of Stage 2 Scoping Outputs
Annex D3: Schedule of Mitigation Commitments
List of Tables
Table 2.1: Marathon Oil Brae Area Production Platforms 6
Table 2.2: Marathon Oil Brae Area Subsea Installations 7
Table 4.1: Definitions of Potential for Significant Effect 12
Table 5.1: Stage 1 Scoping - Brae Alpha, Brae Bravo and East Brae Platform Decommissioning 16
Table 5.2: Stage 1 Scoping for Area Wide Subsea Installations 17
Table 5.3: Legend for Matrices 18
Table 6.1: Stage 2 Scoping - Brae Alpha, Brae Bravo and East Brae Platform Decommissioning 21
Table 6.2: Stage 2 Scoping for Subsea Installations 22
Table A.1: Seabirds likely to be present in the area of the Brae Area 30
Table B.1: Frequency/Duration of an Activity (Planned) / Likelihood (Accidental) of the Activity 36
Table B.2: Magnitude of the Change 36
Table B.3: Scoping Effect Category Matrix 37
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA 39
Table C.2: Activity/receptor interactions for further scoping consideration 45
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA 51
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.1: Duration of an Effect 64
Table D.2: Summary of Stage 2 Scoping 66
Table D.3. Schedule of Scoping Stage Mitigation Commitments 77
List of Figures
Figure 1.1: Location and Summary Schematic of Brae Area Infrastructure 3
Figure 1.2 Overview of the EIA Process 4
Figure A.1: Digital Terrain Models of Drill Cuttings Piles at Brae Alpha, Brae Bravo and East Brae (Marathon Oil, UK Ltd (2013)(2)) 27
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 1 Ramboll Environ
1 Introduction
Marathon Oil UK LLC (Marathon Oil) has commenced planning for the decommissioning of the Brae Area in the UK sector of the central North Sea. The Brae Area lies approximately 170 miles (274 km) north-east of Aberdeen, as illustrated in Figure 1.1, principally within three UK Blocks: 16/7a, 16/3a and 16/3b. Marathon Oil is the operator and equity partners are TAQA Bratani Limited, TAQA Bratani LNS Limited, Centrica Resources Limited, and JX Nippon Exploration and Production (U.K.) Limited.
1.1 Regulatory Context
The decommissioning of offshore oil and gas installations and pipelines on the United Kingdom Continental Shelf (UKCS) is controlled through the Petroleum Act 1998 (as amended by the Energy Act 2008). The Petroleum Act requires Marathon Oil to prepare a Decommissioning Programme (DP) to request permission for decommissioning. The DP would include a summary of an Environmental Impact Assessment (EIA).
The requirement for an EIA under the terms of the Offshore Production and Pipelines (Assessment of Environmental Effects) Regulations 1999, as amended (the EIA Regulations) is set out within DECC guidance (DECC, 2011). In addition, subsequent licence applications under the Marine and Coastal Access Act (2009) will require to be supported by an appropriately scoped EIA and resultant Environmental Statement (ES).
1.2 Purpose of this Report
This Scoping Report is to be used as the basis for consultation with relevant stakeholders on the proposed scope of the technical assessments of the EIA. This Scoping Report is structured to provide:
a summary of the proposed decommissioning activities based on information provided by Marathon Oil;
a description of the potential environmental receptors within the Brae Area based on publically available information and previous surveys (see Annex A);
details of potential interactions between decommissioning activities and environmental receptors;
a description of the multi-stage process of scoping used to identify potential for significant environmental effects (see Annex B)1; and
the identification of proposed scope of the technical assessments.
It is noted that the scoping process will remain iterative throughout the EIA process. A further review of the scope of the EIA may be required throughout the ongoing development of the DPs, should there be a material change in parameter or method within the DPs. Under these circumstances potential for additional significant effect over and above the scope currently identified within this scoping report will be considered and consulted upon as appropriate.
1 ‘Significant’ environmental effects are identified with reference to the criteria set out in Section 4 of this report.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 2 Ramboll Environ
1.2.1 Scoping Questions
In formulating any response to the considerations set out within this scoping report, it may be helpful to consider the following questions:
Does the description of the project and level of available data relating to current environmental conditions provide sufficient information to support the proposed scope of the EIA?
Have the potential significant effects been suitably identified and considered?
1.2.2 Contact Details
Please direct comments on the proposed scope of the EIA to:
Email: [email protected]
The consultation period for representations on the content of the proposed environmental statements will be open for four weeks from the issue of the report, closing 9th March 2016.
1.3 Scoping and the Environmental Impact Assessment (EIA) Process
This Scoping Report and the consultation responses received will inform a single, integrated EIA process for the decommissioning of the whole of the Brae Area. However, it is proposed that the Brae Area will be brought forward for decommissioning through two separate DPs covering:
East Brae Platform with Braemar infrastructure; and
Brae Alpha and Bravo Platforms with West Brae (including Sedgwick), Central Brae and all associated pipelines and subsea structures.
As a result, the EIA process will be reported as two separate Environmental Statements (ESs), in order to support the two separate proposed DPs.
The overall EIA process is illustrated by a flow chart in Figure 1.2.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 3 Ramboll Environ
Figure 1.1: Location and Summary Schematic of Brae Area Infrastructure
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 4 Ramboll Environ
Figure 1.2 Overview of the EIA Process
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 5 Ramboll Environ
2 Brae Area Decommissioning Programmes
The proposed activities would include the decommissioning of the following structures and materials:
platform jackets;
platform topside modules;
subsea wellhead infrastructure and drilling templates;
flowlines and umbilicals;
pipelines and cables;
drill cuttings piles; and
protection structures and other seabed debris.
The Brae Area includes three production platforms: Brae Alpha, Brae Bravo and East Brae. The three platforms are supported on steel jackets with modular topsides. Brae Bravo has a secondary jacket supporting the flare, which is connected to the main platform by a steel bridge.
A summary of the platform assets included within the scope of the proposed DPs is included in Table 2.1. All measurements are approximate.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 6 Ramboll Environ
Table 2.1: Marathon Oil Brae Area Production Platforms
Brae Alpha
Location UK Block 16/7a, 259 km north-east of Aberdeen
Water Depth 112 m
Production Start Date 1983
Substructure Steel Description
8 legged steel jacket, >17,300 tonnes
Topsides Description 25 modules, >30,200 tonnes (dry), >34,000 tonnes (operating)
Accommodation 211
Wells 34 (1 to Central Brae)
Brae Bravo
Location UK Block 16/7a, 269 km north-east of Aberdeen
Water Depth 99 m
Production Start Date 1988
Substructure Steel Description
8 legged steel jacket, > 18,700 tonnes
Topsides Description 28 modules, >36,200 tonnes (Dry), >42,000 tonnes (Operating)
Accommodation 191
Wells 28 (2 to Central Brae)
East Brae
Location UK Block 16/3a, 282 km north-east of Aberdeen
Water Depth 116 m
Production Start Date 1993
Substructure Steel Description
4 legged steel jacket, > 10,000 tonnes
Topsides Description 10 modules, >20,200 tonnes (Dry), >22,500 tonnes (Operating)
Accommodation 188
Wells 21
In addition to the production platforms, Marathon Oil operates three equity subsea installations in the form of Central Brae, West Brae (including Sedgwick) and Braemar. Subsea installations also include a network of connecting flowlines, chemical injection and control umbilicals, pipelines and utility/power cables. Table 2.2 provides a summary of the subsea installations included within the scope of the proposed DPs. All measurements are approximate.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 7 Ramboll Environ
Table 2.2: Marathon Oil Brae Area Subsea Installations
Central Brae
Water Depth 105 m
Production Start Date 1989
Weight > 650 tonnes
Number of Wells 8
Distance from Host 7 km from Brae Alpha
West Brae and Sedgwick
Water Depth 107 m
Production Start Date 1997
Weight > 140 tonnes
Number of Wells 10
Distance from Host 8.8 km from Brae Alpha
Braemar
Water Depth 120 m
Production Start Date 2003
Weight > 20 tonnes
Number of Wells 2 (1 suspended)
Distance from Host 12.5 km from East Brae
Flowlines/Umbilicals
Total Length of flowlines >75 km
Total length of umbilicals >38 km
Pipelines /Cables
Total length of pipelines >195 km
Total length of submarine cables
>57 km
Liquids from the Brae Area are exported via the Forties pipeline to Cruden Bay, and then on to Kinneil near Grangemouth. Gas is transported via the St Fergus SAGE pipeline.
The Marathon Oil operated Brae Area platforms, pipelines and infrastructure are also used by a number of third parties. Decommissioning of third party infrastructure and tie-ins with the Brae Area infrastructure will be the responsibility of the third party operator and therefore are excluded from consideration here.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 8 Ramboll Environ
3 Decommissioning Activities
This scoping report considers the potential for significant environmental effects associated with the potential offshore decommissioning activities2 (including alternative options). At the time of writing this scoping report, the consideration of the alternative options for decommissioning activities is ongoing as part of a parallel comparative assessment (CA) process.
The CA process will consider the potential to leave elements of the Brae area infrastructure in situ. In the event that the CA process identifies leaving items, such as the sub-structure footings for Brae Alpha, Brae Bravo and East Brae platforms in situ, a derogation application (under OSPAR Decision 98/3) would be required; however at the time of writing no decision has yet been reached. For this reason, the scoping process has considered both partial and full removal of some elements of infrastructure, where relevant.
For the purpose of this scoping exercise it has also been assumed that removal and/or management of wastes will follow all relevant methodologies, consents and discharges as set out within the Brae Area Decommissioning Waste Management Strategy (WMS) documents. The principal, overarching objectives being:
protection of the environment and achievement of compliance with environmental and waste legislation and industry standards in order to satisfy Marathon Oil’s Duty of Care with respect to wastes including (but not limited to) the principles of the waste hierarchy as established by the European Waste Framework Directive (implemented at national level by country specific regulations and regulated in Scotland by SEPA);
Stakeholder satisfaction (e.g. customer/client/regulatory authority) in relation to their expectation of continual improvement in environmental and sustainability management, this includes meeting project targets and objectives with respect to waste management;
Deliverance of a resource efficient decommissioning process, achieving both waste reduction and improved business efficiency and cost savings.
3.1 Transportation of Workers and Materials
This activity relates to general worker and materials movement and covers anticipated supply vessel and helicopter movements throughout the duration of the decommissioning activities. Vessel activity specifically associated with particular tasks are considered under the individual activity.
3.2 Topsides Preparation
This relates to activities required to ensure hydrocarbons and hazardous materials have been removed from the topside infrastructure, all processing plant has been isolated from the reservoir and pipelines have been cleaned, with all conductors, casing, tubing and other well equipment removed.
2 Activities were identified during an informal environmental scoping methodology workshop with Marathon Oil held 12th
December 2014 in Marathon Oil offices and supplemented through further, ongoing discussion and a further environmental
scoping workshop held on 4th March 2015.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 9 Ramboll Environ
3.3 Platform Subsea Installations Decommissioning
This relates to the activities required to decommission those subsea installations directly associated with Brae Alpha, Brae Bravo, East Brae and Braemar, including mattresses, grout bags, formwork, risers, umbilicals and pipelines, and the drill template at East Brae. This would include all installations within the platform jackets, or where there would be the potential to directly disturb drill cuttings piles. This scoping report assumes that risers, umbilicals and pipelines will be cleaned and flushed. Where removal is selected through the CA process, removal would be via lift vessel or crane vessel.
For the purposes of this scoping exercise it has also been assumed that a post decommissioning debris survey would be undertaken within a 500 m radius of each platform location and a 200 m corridor along the pipelines.
3.4 Topsides Removal
Four options for topsides removal have been considered as part of this scoping exercise:
removal by a single lift;
removal by reverse installation involving modular removal by lift vessel;
demolition to small transportable sized pieces and then removal; or
hybrid methodology comprising elements of both modular removal and demolition.
3.5 Drill Cuttings Piles Decommissioning
Drill cuttings piles have been identified and quantified beneath the Brae Alpha, Brae Bravo and East Brae platforms. Biological and contaminant sampling has been completed for the Brae Alpha, Brae Bravo and East Brae drill cuttings piles and these have been used to inform this scoping report.
A Stage 1 OSPAR assessment (under the terms of OSPAR Recommendation 2006/5) was undertaken (Marathon Oil, 2008) and concluded that the drill cutting piles located at all three platforms could be expected to fall below the thresholds set out within this recommendation and could therefore be left in place to degrade naturally. Further assessment has been carried out based on a survey programme commissioned by Marathon Oil, with samples recovered from the drill cuttings piles in 2013 and 2015 (Fugro, 2013; Fugro, 2013 (2), Fugro, 2015; Fugro, 2015 (2)). Fugro calculated OSPAR screening criteria on the basis of leachate testing results (Fugro, 2015(3)). The assessments utilised the methodology set out within UKOOA (2000 and 2000(2)). Even under the worst case scenarios, the estimated values are well below the thresholds set out within OSPAR 2006/5 (as described above) and may therefore be left in situ to degrade naturally.
Notwithstanding this, Marathon Oil have proactively commissioned a Net Environmental Benefit Analysis (NEBA) to complete further evaluation of the management options for the Brae Area drill cuttings piles in order to ensure best practice and to ensure that any decision as to drill cuttings pile management draws on the strongest available evidence base.
The NEBA assessment is currently underway for three different options for drill cuttings piles management, comprising:
leave in situ to degrade naturally;
removed for onshore disposal; and
relocate from current location and redistribute across the surrounding seabed.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 10 Ramboll Environ
3.6 Steel Jacket Removal
The following options for steel jacket removal have been considered for the Brae Alpha, Brae Bravo and East Brae jackets:
Partial removal of upper jacket by Section Cut and Lift using a Heavy Lift Vessel (HLV);
Full removal of the complete jacket by Section Cut and Lift using an HLV; and
Full removal of complete jacket by Single Lift Vessel (SLV) using a vessel such as the Allseas vessel – Pioneering Spirit.
3.6.1 Flare Stack and Bridge Removal (Brae Bravo only).
The flare stack and bridge associated with Brae Bravo will be removed in its entirety using a lift vessel. The footings of the flare tower jacket will be removed to 3 m below the seabed.
3.7 Area Wide Subsea Installations Decommissioning
3.7.1 Subsea Drill Template and Wellhead Removal
This scoping report assumes that the wellheads at Braemar, West Brae (including Sedgwick) and the drill template at Central Brae will be removed.
3.7.2 Pipeline and Flowline Decommissioning
Pipelines, umbilicals and power cables within the Brae Area have been installed in a number of configurations, including: surface laid; trenched; rock covered; and trenched with mattress protection. Pipelines considered under this heading are those pipelines running between platforms, where there is no potential to disturb drill cuttings piles (those which are not considered under Section 3.3 above). All measurements provided in the description of decommissioning activities are approximate.
3.7.3 Pipeline and Flowline Characteristics
Within the Brae Area, available data indicates approximately 80 km of pipelines are surface laid; 35 km are partially trenched with surface-laid sections around the pipeline ends and in the 500 m exclusion zones around platforms; 28 km are partially trenched except for short surface-laid sections around crossings; and 12 km are trenched and rock covered.
It has been assumed that the full 117 km length of the Brae Alpha to Forties Charlie Oil export trunk line is surface laid.
It has been assumed that approximately 23 km of the chemical control and electrical-hydraulic umbilicals associated with the flowlines from the subsea developments are buried with the flowlines, with the exception of the umbilical for the West Brae (including Sedgwick) flowline which is understood to be rock covered, whereas the flowline is trenched. Of the remaining umbilicals, it is estimated between 1.5 km and 2.2 km are surface laid with mattress protection, 12 km are trenched and rock covered.
An estimated total of between 64 km to 69 km of power cables are assumed to be buried, with mattress protection provided to surface laid sections located within approximately 100 m to 200 m of the platforms.
All pipelines would be isolated, flushed, purged and cleaned. The CA process relating to pipeline decommissioning is currently ongoing but for the purposes of this scoping exercise,
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 11 Ramboll Environ
anticipated impacts associated with both leaving pipelines, umbilicals and cables in situ, and with removal, have been considered.
3.8 Well Decommissioning
Well Plug and Abandonment (P&A) will be managed under existing permitting requirements. Well P&A will be delivered as the host platforms reach cessation of production (CoP) and as the market availability of appropriate vessels allows. As such, well P&A has not specifically been considered as an activity to be covered within this Scoping Report.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 12 Ramboll Environ
4 Scoping Methodology
4.1 Approach to the Identification of Activity/Receptor Interactions
The scoping methodology draws on best practice guidance to identify definitions of the potential significant environmental effects. Potential significant environmental effects are considered to be those activity/receptor interactions assigned a Medium or High category. The categorisation of effect has been made with reference to the summary criteria set out in Table 4.1 (a more detailed methodology for allocating categories is provided in Annex B).
Table 4.1: Definitions of Potential for Significant Effect
Categories Definition
High A high potential for significant environmental effect or an unacceptable risk associated with an unplanned or accidental event which would require alterations to the proposed activity and/or development of effect/risk-specific mitigation proposals in order to eliminate/mitigate to an acceptable level.
High potential activity/receptor interactions at stage 1 will be taken forward into the detailed EIA process.
Medium A medium potential for significant environmental effect or risk associated with an unplanned or accidental event that may be acceptable, but only if further investigated and/or appropriately mitigated through the implementation of best practice/generic mitigation.
Medium potential activity/receptor interactions at stage 1 will be taken forward into the Stage 2 Detailed Scoping process
Low A low potential for significant environmental effect or risk associated with an unplanned or accidental event that is considered to be of little consequence and can be further reduced by generic mitigation and controls.
Low potential activity/receptors interactions will be scoped out from further assessment.
Negligible Negligible potential for significant environmental effect or risk associated with an unplanned or accidental event that is considered to be inconsequential. Often will not require mitigation or control.
Insignificant activity/receptors interactions will be scoped out from further assessment.
No Impact/ Positive No potential for significant environmental effect or a positive environmental effect. No identified risk of accidental or unplanned event.
Where no activity/receptors interaction is identified, this will be documented and discounted.
Where a potentially positive activity/impact interaction is identified, this will be documented.
4.2 Multi-Stage Scoping Process
The aim of this scoping process is to ensure a focused and proportionate EIA and ES, targeted to the specific requirements of the proposed Brae Area decommissioning activities. To achieve this aim, the EIA has been scoped by means of a multi stage scoping process. These stages comprise:
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 13 Ramboll Environ
4.2.1 Preliminary scoping (Stage 1)
Stage 1 scoping includes:
the identification of the proposed decommissioning activities that could interact with the environment (biological, physical and human);
the identification of potential environmental receptors based on publically available information and field specific information available from previous surveys (as outlined in Annex A);
the completion of environmental effect matrices to identify potential interactions between decommissioning activities and specific environmental receptors; and
the allocation of an initial effect category based on the Table 4.1 criteria using professional judgement.
At the conclusion of Stage 1, the initial effect categories are used as follows:
High potential activity/receptor interactions are taken forward into the detailed EIA process;
Medium potential activity/receptor interactions are taken forward into Stage 2 – Detailed Scoping Process; and
Low/insignificant or no potential activity/receptor interactions are scoped out from further assessment as part of the EIA.
Where interactions have been categorised across a range of effect levels (for example low – high potential for significant environmental effect), these have been allocated to the highest category within the matrices. A range arises when the impact magnitude has the potential to vary (e.g. accidental events could vary from a small oil release to a substantial oil spill from a vessel) and/or where only a subsection of receptors may be affected (e.g. where a high risk of potential effect from underwater noise is anticipated on marine mammals, where the same noise may be anticipated to have a low potential to result in significant effects on seabirds).
4.2.2 Detailed scoping (Stage 2)
This stage provides an additional level of scoping consideration for those potential activity/receptor interactions identified as ‘Medium’ at Stage 1, in order to further characterise the potential for environmental effect, considering the following factors:
a qualitative assessment of the sensitivity of the receptor, based on a scale of high, medium and low, with reference to criteria set out in Annex D1;
the duration of the effect, based on the criteria for long, medium and short term in Annex D1;
information available on the geographic extent of potential interactions, based on local, regional and national/international levels; and
the anticipated standard and best practice working methods to which Marathon Oil is committed to using and the extent to which they would avoid or reduce the environmental effect or risk of accidental event.
As with the Stage 1 scoping, the effect categories allocated at Stage 2 have been used to define the proposed scope of the EIA, with Medium and High activity/receptor interactions taken forward into the EIA process.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 14 Ramboll Environ
4.2.3 Further Scoping Consideration (Stage 3)
The CA process may rule out some potential activity/receptor interactions. As such, it is anticipated that further consideration would be given to reducing the scope of the EIA prior to completion of the detailed technical impact assessment based on the outcomes of the CA process.
This document reports on both Stage 1 and Stage 2 scoping, which has been sufficient for the majority of issues to confirm the proposed scope of the technical assessment prior to preparation of the Environmental Statements. The ESs would provide further commentary on further scoping stages (Stage 3).
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 15 Ramboll Environ
5 Stage 1: Preliminary Scoping
5.1 Stage 1 Scoping Summary
The potential for activity/receptor interactions have been grouped into environmental effect categories as follows:
Designated Sites/Species Disturbance Effects: this includes the consideration of potential effects associated with seabed disturbance or the removal of subsea installations on sites or species designated for protection under the Habitats Directive3. The consideration of potential effects associated with underwater noise and pollution on marine mammals are considered separately below.
Seabed Disturbance Effects: this includes potential for effects on marine benthos, geology, natural seabed sediments and drill cuttings piles associated with seabed disturbance.
Noise Effects: this includes potential for effects on fish, seabirds and marine mammals.
Water Quality Effects: this includes potential for direct effects on water quality and secondary/indirect effects on plankton, fish, shellfish and marine mammals associated with the potential for contamination of water quality through either the disturbance of drill cuttings pile sediments or planned discharges of waste water, chemicals or oils to the sea.
Socio-economic and Other Effects: this includes potential for effects on commercial fisheries, shipping and navigation, human health, recreation and tourism, marine archaeology.
Atmospheric Emissions Effects; this includes consideration of likely consumption of natural resources associated with vessel movements and the emissions to atmosphere, with the potential for local air pollution, global climate change and acidification effects.
Accidental Events: this includes a consideration of potential risk to water quality and supported marine ecosystems, and other users of the sea as a result of accidental release of contaminants.
5.2 Stage 1 Effect Rating – Summary Matrices
Table 5.1 provides a summary of the Stage 1 effect categorisation for the activity/receptor interactions identified for Brae Alpha, Brae Bravo and East Brae platforms. Table 5.2 provides a summary of the Stage 1 effect categorisation for decommissioning subsea installations (area wide). Table 5.3 provides a legend for the colours used in Table 5.1 and 5.2. The reference provided in each cell of the matrices relates to the rationale provided in Annex C1, C2 and C3, for example, reference C3.1 is found in Annex C3.
3 Council Directive 92/43/EEC on the Conservation of Natural Habitats and of Wild Fauna and Flora
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 16 Ramboll Environ
Table 5.1: Stage 1 Scoping - Brae Alpha, Brae Bravo and East Brae Platform Decommissioning
Decommissioning Activity Des
ign
ated
Sit
es/
Sp
ecie
s D
istu
rban
ce
Eff
ects
Sea
bed
Dis
turb
ance
E
ffec
ts (
mar
ine
ben
tho
s,
geo
log
y, n
atu
ral s
eab
ed
sed
imen
t an
d d
rill
cutt
ing
s p
ile)
No
ise
Eff
ect
s (f
ish
, m
arin
e m
amm
als,
se
abir
ds)
Wat
er Q
ual
ity
Eff
ect
s (w
ater
qu
alit
y, p
lan
kto
n,
fish
, sh
ellf
ish
, mar
ine
mam
mal
s)
So
cio
-eco
no
mic
an
d
Oth
er E
ffec
ts
(co
mm
erci
al f
ish
erie
s,
ship
pin
g/n
avig
atio
n,
recr
eati
on
)
Atm
osp
her
ic E
mis
sio
n
Eff
ects
(en
erg
y u
se,
clim
ate
chan
ge,
air
q
ual
ity)
Acc
iden
tal E
ven
ts (
ris
k to
wat
er q
ual
ity
and
su
pp
ort
ed m
arin
e lif
e)
Transportation of materials to and from Brae Area
C3.1 C3.10 C3.15 C3.19 C3.23 C3.25 C3.26
Topsides Preparation C3.2 C3.11 C3.16 C3.20 C3.23 C3.25 C1.5
Platform Subsea Installations Removal#
C3.3 C2.1 C2.4 C1.4 C3.24 C2.11 C1.6
Topsides Removal C3.4 C3.12 C2.5 C3.21 C3.24 C2.11 C1.6
Drill Cuttings Piles (Remove / Relocate)
C3.5 C2.1 C2.1 C1.4 C3.24 C2.11 C1.6
Drill Cuttings Piles (left in situ) C3.6 C3.13 C3.17 C2.8 C3.24 C3.25 C3.27
Steel Jacket - Full Removal^ C3.7 C2.1 C1.2 C1.4 C3.24 C2.11 C1.6
Steel Jacket – Partial Removal* C3.8 C2.1 C1.2 C2.8 C2.10 C2.11 C1.6
*(footings left in situ); # (directly associated with the platform); ^ (including Brae Bravo Flare Jacket removal)
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 17 Ramboll Environ
Table 5.2: Stage 1 Scoping for Area Wide Subsea Installations
Decommissioning Activity Des
ign
ated
Sit
es/
Sp
ecie
s D
istu
rban
ce
Eff
ects
Sea
bed
Dis
turb
ance
E
ffec
ts (
mar
ine
ben
tho
s,
geo
log
y, n
atu
ral s
eab
ed
sed
imen
t an
d d
rill
cutt
ing
s p
ile)
No
ise
Eff
ect
s (f
ish
, m
arin
e m
amm
als,
se
abir
ds)
Wat
er Q
ual
ity
Eff
ect
s (w
ater
qu
alit
y, p
lan
kto
n,
fish
, sh
ellf
ish
, mar
ine
mam
mal
s)
So
cio
-eco
no
mic
an
d
Oth
er E
ffec
ts
(co
mm
erci
al f
ish
erie
s,
ship
pin
g/n
avig
atio
n,
recr
eati
on
)
Atm
osp
her
ic E
mis
sio
n
Eff
ects
(en
erg
y u
se,
clim
ate
chan
ge,
air
q
ual
ity)
Acc
iden
tal E
ven
ts (
ris
k to
wat
er q
ual
ity
and
su
pp
ort
ed m
arin
e lif
e)
Subsea Installations* (drill templates, wellheads, mattresses, formwork) – removal
C3.9 C2.2 C2.7 C2.9 C3.24 C2.11 C1.6
Subsea Installations (Central Brae Template) - removal
C3.9 C2.2 C1.3 C2.9 C3.24 C2.11 C1.6
Braemar Subsea Installations (wellhead and flow line tie back to East Brae) - removal
C1.1 C.2.2 C2.7 C2.9 C3.24 C2.11 C1.6
Pipelines / Cables / Flowlines / Umbilicals – full or partial removal
C3.9 C2.3 C2.7 C2.9 C3.24 C2.11 C1.6
Pipelines / Cables / Flowlines / Umbilicals – left in situ
C3.9 C3.14 C3.18 C3.22 C3.24 C3.25 C3.28
* including West Brae and Sedgwick
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 18 Ramboll Environ
Table 5.3: Legend for Matrices
Legend Effect Category
High
Medium
Low
Negligible/ No Impact / Positive
Stage 2 - Low (downgraded from medium)
Stage 2 – Medium (taken forward to EIA)
5.2.1 High Potential for Significant Environmental Effect
A high potential for significant environmental effect was identified as follows:
seabed disturbance (and effects on designated sites) through the removal of the Braemar wellhead protection structures and flowlines to East Brae;
noise effects on marine mammals associated with steel jacket removal and subsea installation (Central Brae template) removal;
water quality effects and effects on supported marine life associated with drill cuttings piles removal or disturbance as a result of full steel jacket removal and platform subsea installation removal; and
accidental events associated with topsides preparation, removal and steel jacket and subsea installation removal.
Habitats Regulations Assessment (HRA) is considered in Section 5.3 below. Potential environmental effects categorised as high are described further in Annex C1. These will be taken forward for further consideration within the EIA.
5.2.2 Medium Potential for Significant Environmental Effect
A medium potential for significant environmental effect was identified as follows:
seabed disturbance associated with steel jacket removal at Brae Alpha, Brae Bravo and East Brae;
seabed disturbance associated with the removal of subsea installations (area wide) as defined in Table 2.2;
Noise Effects on marine mammals, fish and seabirds associated with removal of area wide subsea installations and topsides;
water quality effects and effects on supported marine life associated with drill cuttings piles (left in situ) at Brae Alpha, Brae Bravo and East Brae and the removal of area subsea installations);
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 19 Ramboll Environ
socioeconomic effects, specifically related to commercial fisheries, associated with steel jacket partial removal at Brae Alpha, Brae Bravo and East Brae; and
atmospheric emissions and resource use associated with energy use and vessel emissions during topside preparation, removal, steel jacket removal at Brae Alpha, Brae Bravo and East Brae and the area wide removal of subsea installations.
Potential environmental effects categorised as ‘medium’ are discussed within Annex C2 and were taken forward to more detailed scoping analysis (see Stage 2 below) before confirming the proposed scope of the EIA technical assessments.
5.2.3 Low, Insignificant or No Potential for Significant Environmental Effect
Those activity/receptor interactions which are categorised as ‘low’, ‘negligible’ or ’no impact/positive’ and which are therefore not considered likely to give rise to significant environmental effect have been scoped out from further consideration within the EIA. Potential environmental effects categorised as ‘low’ ‘negligible’ or ’no impact/positive’ are discussed within Annex C3.
5.3 Habitat Regulations Assessment (HRA) Screening
Neither Brae Alpha, Brae Bravo or East Brae platforms or associated subsea infrastructure lie within any sites designated for protection under the Habitats Directive (Council Directive 92/43/EEC) and no currently designated features have been identified associated with these platforms. Likewise the Central Brae template and wellheads and other subsea installations at West Brae and at Sedgwick lie outside any designated sites.
Potential for significant effect on the Braemar Pockmarks SAC as a result of decommissioning activities at Braemar and along the associated flowlines to East Brae will be considered within the EIA and sufficient information will be provided within the East Brae and Braemar ES to allow the Competent Authority – in this case DECC - to give due consideration to the potential for significant effects on the Braemar pockmarks SAC.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified on Brae Area infrastructure. As a result, the consideration of potential effects on designated species has been scoped out of the EIA. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 20 Ramboll Environ
6 Stage 2 - Detailed Scoping
Those activity/receptor interactions identified as having ‘Medium’ potential for significant environmental effect during Stage 1 scoping have been given further scoping consideration as detailed below.
6.1 Stage 2 Scoping Summary
Table 6.1 provides a summary of the Stage 2 effect categorisation for the activity/receptor interactions identified for Brae Alpha, Brae Bravo and East Brae platforms. Table 6.2 provides a summary of the Stage 2 effect categorisation for area wide decommissioning of subsea installations. Environmental receptors have been grouped by effect as described previously.
Where, following additional consideration, it is concluded that insufficient evidence exists to justify an amendment to the effect categorisation (i.e. the interactions remain ‘Medium’ in Table 6.1 and 6.2), the activity/receptor interaction in question has been taken forward into the detailed EIA process for further analysis.
Effects downgraded to ‘Low’ or ‘Insignificant’ following further consideration during the Stage 2 scoping, will not be considered further within the EIA, however any generic/best practice mitigation on which the scoping decision depends will be itemised and carried forward into the schedule of commitments to be included within the final ESs.
The further consideration given to activity/receptor interactions has been summarised within Annex D2. The scoping stage schedule of mitigation commitments is provided in Annex D3.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 21 Ramboll Environ
Table 6.1: Stage 2 Scoping - Brae Alpha, Brae Bravo and East Brae Platform Decommissioning
Decommissioning Activity Des
ign
ated
Sit
es/
Sp
ecie
s D
istu
rban
ce
Eff
ects
Sea
bed
Dis
turb
ance
E
ffec
ts (
mar
ine
ben
tho
s,
geo
log
y, n
atu
ral s
eab
ed
sed
imen
t an
d d
rill
cutt
ing
s p
ile)
No
ise
Eff
ect
s (f
ish
, m
arin
e m
amm
als,
se
abir
ds)
Wat
er Q
ual
ity
Eff
ect
s (w
ater
qu
alit
y, p
lan
kto
n,
fish
, sh
ellf
ish
, mar
ine
mam
mal
s)
So
cio
-eco
no
mic
an
d
Oth
er E
ffec
ts
(co
mm
erci
al f
ish
erie
s,
ship
pin
g/n
avig
atio
n,
recr
eati
on
)
Atm
osp
her
ic E
mis
sio
n
Eff
ects
(en
erg
y u
se,
clim
ate
chan
ge,
air
q
ual
ity)
Acc
iden
tal E
ven
ts (
ris
k to
wat
er q
ual
ity
and
su
pp
ort
ed m
arin
e lif
e)
Transportation of materials to and from Brae Area
Topsides Preparation
Subsea Installations Removal# D2.1 D2.3 D2.7
Topsides Removal D2.3 D2.7
Drill Cuttings Piles (Remove / Relocate)
D2.1 D2.3 D2.7
Drill Cuttings Piles (left in situ) D2.5
Steel Jacket - Full Removal D2.2 D2.7
Steel Jacket – Partial Removal* D2.1 D2.5 D2.6 D2.7
*(footings left in situ); # (directly associated with the platform)
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 22 Ramboll Environ
Table 6.2: Stage 2 Scoping for Subsea Installations
Decommissioning Activity Des
ign
ated
Sit
es/
Sp
ecie
s D
istu
rban
ce
Eff
ects
Sea
bed
Dis
turb
ance
E
ffec
ts (
mar
ine
ben
tho
s,
geo
log
y, n
atu
ral s
eab
ed
sed
imen
t an
d d
rill
cutt
ing
s p
ile)
No
ise
Eff
ect
s (f
ish
, m
arin
e m
amm
als,
se
abir
ds)
Wat
er Q
ual
ity
Eff
ect
s (w
ater
qu
alit
y, p
lan
kto
n,
fish
, sh
ellf
ish
, mar
ine
mam
mal
s)
So
cio
-eco
no
mic
an
d
Oth
er E
ffec
ts
(co
mm
erci
al f
ish
erie
s,
ship
pin
g/n
avig
atio
n,
recr
eati
on
)
Atm
osp
her
ic E
mis
sio
n
Eff
ects
(en
erg
y u
se,
clim
ate
chan
ge,
air
q
ual
ity)
Acc
iden
tal E
ven
ts (
ris
k to
wat
er q
ual
ity
and
su
pp
ort
ed m
arin
e lif
e)
Subsea Installations* (drill templates, wellheads, mattresses, formwork) – Removal
D2.1 D2.4 D2.5 D2.7
Subsea Installations (Central Brae Template)
D2.1 D2.5 D2.7
Braemar Subsea Installations (wellhead and flow line tie back to East Brae)
D2.1 D2.4 D2.5 D2.7
Pipelines / Cables / Flowlines / Umbilicals – full or partial removal
D2.1 D2.4 D2.5 D2.7
Pipelines / Cables / Flowlines / Umbilicals – left in situ
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 23 Ramboll Environ
7 EIA technical studies
The EIA technical studies will draw on available literature, existing survey data and reports including but not limited to, those listed within Annex A.
The following technical studies will be delivered in support of the Brae Area EIA. No additional baseline surveys involving primary data collection are proposed.
7.1 Designated Sites and Species
Sufficient information will be provided within the EIA to allow consideration by the Competent Authority of the potential for significant effect on the Braemar Pockmarks SAC as a result of the decommissioning of the Braemar wellhead, suspended well and flowlines as required to undertake a Habitat Regulations Assessment (HRA) under the Habitats Directive4.
7.2 Seabed Disturbance Effects
The assessment of seabed disturbance effects will include consideration of the potential for effects on marine benthos, geology, natural seabed sediments and drill cuttings piles sediments. The study will be undertaken using baseline information previously collected for the ongoing Brae Area NEBA study.
Consideration will be given to:
the potential for significant effect on both soft sediment and hard substrate benthic communities as a result of jacket removal (with and without footings) (including removal of marine growth) at each of the production platforms (Brae Alpha, Brae Bravo and East Brae), including Priority Marine Features as defined by the Marine (Scotland) Act 2010; and
the potential for significant seabed disturbance as a result of the full or partial removal of the subsea installations associated with the Braemar wells, flowlines/umbilicals and pipelines/cables.
Potential for significant effects as a result of short term sediment disturbance resulting from removal of other Brae Area subsea infrastructure (West Brae and Sedgwick wellheads, flowlines, Central Brae drill template and other subsea installations) where resettlement may be expected to be rapid with limited potential for the formation of persistent mounds has been scoped out the EIA.
7.3 Water Quality Effects
The assessment of water quality effects will include consideration of the potential for effects on water quality, plankton, fish and shellfish, benthos and marine mammals.
Within this workscope further consideration will be given to:
the potential for significant effect as a result of increases in contaminant levels in the water column and in surrounding seabed sediments as a result of drill cuttings piles
4 Council Directive 92/43/EEC on the Conservation of Natural Habitats and of Wild Fauna and Flora.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 24 Ramboll Environ
removal or disturbance as a result of jacket removal at the three platforms, Brae Alpha, Brae Bravo and East Brae.
The detailed scope of this assessment will draw on and be integrated with the ongoing NEBA study currently being delivered in support of the Comparative Assessment process.
7.4 Noise Effects
The assessment of underwater noise will include the potential for effects on marine mammals as a result of steel jacket removal for the three main platforms, and the removal of other subsea installations (including the potential use of explosives).
The study will be undertaken using baseline information previously collected and reported in the technical reports on fish, shellfish and marine mammals referenced in Annex A.
Potential for significant effects on marine mammals and seabirds as a result of topside removal has been scoped out of the EIA. Potential for significant effects on fish and seabirds associated with jacket removal has been scoped out of the EIA.
7.5 Socio-economic Effects
Further consideration will be given to the potential for significant socio-economic effects on demersal commercial fishing activities as a result of the proposed decommissioning programme, particularly associated with the full or partial removal (and derogation to leave footings in situ) for the Brae Alpha, Brae Bravo and East Brae platform jackets.
7.6 Accidental Events
The assessment of accidental events will give consideration to the potential for significant effect on water quality and supported marine ecosystems as a result of:
accidental release of contaminants during topside preparation for removal;
accidental spills associated with vessel activities; and
risk of dropped objects during decommissioning, particularly associated with lift operations.
7.7 Cumulative Effects and Transboundary
Cumulative effects fall into one of three categories, as follows:
The potential for individual activity/receptor interactions associated with each of the Brae Area decommissioning activities to combine and have a significant cumulative effect will be considered where there is the potential for the activity/receptor interaction to be either spatially or temporally concurrent, for example in combination effects on marine mammals associated with discharges to sea and underwater noise.
In addition the potential for cumulative effects to result from the addition or combination of activities to decommission East Brae and Braemar, with the activities proposed to decommission Brae Alpha, Brae Bravo and other area wide subsea installations, and vice versa will be considered.
Finally, consideration will be given to the potential for cumulative effects associated with the addition or combination of the Marathon Oil Brae Area decommissioning activities, with other known proposed DPs submitted to DECC by other operators, where it is considered likely that there would be a spatial or temporal overlap (e.g. those third party assets shown on Figure 1.1). Where there is no valid DP, there may
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 25 Ramboll Environ
be insufficient information to provide a meaningful cumulative effects assessment, in which case the ES will acknowledge the potential for cumulative effect, and set out a proposed process through which the potential interactions between DPs would be communicated and managed between operators.
The potential effects of each of the decommissioning activities will also be considered in respect to any implications for the territory of another country, in this case potentially significant effects which may extend across the Norwegian boundary line 4.4 km to the East of the East Brae platform, where their occurrence has the potential to result in environmental and/or socio-economic impacts across international borders.
7.8 Issues Scoped Out
7.8.1 Atmospheric Emissions
It is noted that the potential emissions associated with decommissioning would represent a reduction in emissions relative to the normal operational emissions associated with operating the Brae Area platforms and infrastructure. However, the comparative consideration given to ensuring that energy use and air quality effects will be as low as reasonably practical will be documented within the section of the ESs describing Alternatives/Comparative Assessment. All vessels will comply with MARPOL 73/78 Annex VI on air pollution; plant will comply with relevant air pollution regulations (The Offshore Combustion Installations (Prevention and Control of Pollution) (Amendment) Regulations 2007. On this basis it is considered that there is no potential for significant effect as a result of atmospheric emissions and this activity/receptor interaction has been scoped out of the EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Annex A: Environmental Baseline
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
This section summarises available information relating to the likely environmental characteristics of the offshore environment in the area of the Brae area.
Geology and Sediments
Surface geology of the seabed is primarily determined by the reworking of seabed sediments by tides and sea waves.
Parts of the Brae area have been mapped as deep circalittoral mud (European Nature Information System (EUNIS) classification A5.37) which is described as ‘mud and cohesive sandy mud in the offshore circalittoral zone, typically below 50-70m depth’ (Gatliff et al., 1994). To the south, seabed sediments in the Brae area comprise very fine to medium sands (ranging to well-sorted to very poorly sorted). Environmental monitoring surveys indicate a gradient in sediment type from north (finer and muddier) to south (coarser sediments with less mud).
Monitoring undertaken at Brae Bravo (Fugro, 2013, Fugro, 2013 (2)) indicates that sediments have a low organic and carbonate content, with metal contents within the range of natural background concentrations. Immediately adjacent to and under the Brae area platforms, mounds of previously discharged drill muds and cuttings are known to exist which will contain elevated concentrations of hydrocarbons and some metals (see Figure A.1) (Marathon Oil, UK LLC (2013) (2)). Mounds range in height from 7.59 – 11.45 m high (Brae Alpha being the highest), with a minimum observed depth of 92.33 m bsl (at Brae Bravo).
Figure A.1: Digital Terrain Models of Drill Cuttings Piles at Brae Alpha, Brae Bravo and East Brae (Marathon Oil, UK Ltd (2013)(2))
The seabed in the Brae area is relatively flat, with depths averaging between 90 - 140 m.
In the central and northern North Sea the spreads of soft muds are locally characterised by small depressions or ‘pockmarks’, seabed pockmarks are shallow seabed depressions likely caused by the venting of fluids gases into the water column (Hartley, 2005) (discussed further in Section: Designations). The pockmarks identified in the vicinity of the Brae Area range in size from a diameter of 5 - 10 m and a maximum depth of 0.5 m, to larger less frequent pockmarks with a diameter of 50 - 130 m and a maximum depth of approximately 5 m (Hartley, 2005) . The Braemar Pockmarks to the north of the Brae area, in the region of the Braemar infrastructure, are designated as a Special Area for Conservation (SAC).
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Bathymetry and Hydrography
The East Shetland Atlantic Inflow is the dominant current in the region, with the Fair Isle current dominating the local hydrography around the Brae Area. Non-tidal currents in the Brae Area are dependent on meteorological conditions and are therefore irregular in nature but generally have an easterly set. The northern North Sea experiences the highest 50 year extreme maximum wave height in the North Sea of 30 - 32 m with a corresponding wave period of 18-19 seconds (OSPAR, 2000). However, the mean wave height for the Brae Area is much lower, at 2.3 m.
During the summer, the temperature and nutrient content of the central and northern North Sea is determined by the formation of a thermal stratification at approximately 30 - 50 m depth. This results in reduced vertical mixing, lowering the temperature and nutrient concentrations at depth. Increased wave strength and frequency in autumn, caused by stronger winds, increases vertical mixing in the water column and breaks down the thermocline.
Water Quality
The offshore areas of the northern North Sea have some of the best water quality in the North Sea. Levels of anthropogenic radionuclides in seawater in the region are low compared to the naturally occurring radionuclides and concentrations of trace metals in the seawater of the region are also expected to be low (OSPAR, 2000). Nutrient levels (including nitrate and phosphate levels) in the region vary seasonally, primarily influenced by the inflow of Atlantic water, stratification and utilisation by phytoplankton. Nutrient levels decrease in spring with reduced water inflow and the start of phytoplankton blooms (DECC, 2001). The salinity in the central and northern North Sea is fairly constant, rising slightly in the summer.
Plankton
The plankton composition within the Brae area is expected to reflect the composition found in this area of the North Sea. The Atlantic inflow to this region introduces extra nutrients allowing the area to sustain higher primary production by plankton than further south in the North Sea. Physical factors, such as stratification, have a dominant role in the composition of plankton communities in the central and northern North Sea (DECC, 2001). Phytoplankton communities in the North Sea are dominated by diatoms, dinoflagellates and smaller flagellates.
Zooplankton biomass follows a seasonal variation in primary productivity (caused by changes in phytoplankton), with a peak in May followed by a sharp decline in the winter. The rate of population response in zooplankton is much slower than phytoplankton, which allows algal populations to bloom (DECC, 2001); furthermore, as a result of the slower response, much of the phytoplanktonic production within the central and northern North Sea is thought to sink to the seabed rather than being consumed by zooplankton, providing a major source of carbon and energy to support the offshore marine ecosystem. Phytoplankton is dominated by copepods, mainly Calanus species (C. finmarchicus and C. helgolandicus), though larger zooplankton such as krill (euphausiids), salps and doliolids (thaliacea) and jellyfish (siphonophores and medusae) (DECC, 2001) can also reach large densities and provide a primary food source for fish and whales.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Benthos
The benthic communities in the central and northern North Sea often show a characteristic relationship to sediment type in terms of biomass, productivity, diversity and species composition. Monitoring undertaken at Brae Bravo (Marathon Oil UK LLC, 2013 (2)) has indicated that the composition of benthic communities is also influenced by distance and bearing from the platform jacket and footings.
Therefore, on the basis of the fine sediments identified within the Brae Area, communities in the region may be expected to correspond closely to those identified by Basford et al., (1990) from the deeper water silty sand habitats within the North Sea, either:
Group III (characterised by the brittlestars Amphiura filiformis and Amphiura chiajei, the scaphopod mollusc Antalis entalis and the cumacean Brachydiastylis resima); or
Group IV (characterised by the polychaetes Lumbrineris fragilis and Levinsenia gracilis, and the amphipod Eriopisa elongata).
The deep circalittoral mud (EUNIS classification A5.37) benthic habitats mapped within the Brae area can support a variety of faunal communities, depending upon the level of silt/clay and the organic composition of the sediment. Communities are typically dominated by polychaetes but often with high numbers of bivalves such as Thyasira spp., echinoderms and foraminifera (EUNIS, 2012):
Capitella spp: Polychaete annelid worm which is typically used as a bio-indicator of disturbed marine habitats as it is known to require organically enriched sediment to support normal physiological development;
Paramphinome jeffreysii: Polychaete worm identified as a defining species in the macro-faunal assemblage of the EUNIS habitat classification for offshore circa-littoral sandy mud; and
Thyasira sarsi: Bivalve mollusc typically found in the north-central North Sea and associated with hydrocarbon enriched sediments.
With the exception of the bivalve mollusc Arctica islandica and the potentially the cold water coral Lophelia pertusa, the fauna of the Brae Area does not contain large, long lived species. Arctica islandica is widely distributed in the North Sea, though the Arctica found in the seabed surveys around the Brae area are typically small, young specimens (Marathon Oil UK LLC, 2013 (2)). Evaluation of available ROV footage of the Brae area infrastructure is currently ongoing and therefore the presence of biogenic reef forming organisms such as Lophelia spp has not yet been confirmed.
Fish, Shellfish and Cephalopods
Several fish species are known to present in the area surrounding the Brae Area and use the area for spawning and/or nursery grounds; these include the Norway pout (Tisopterus esmarkii), Nephrops, mackerel (Scomber scombrus), haddock (Melanogrammus aeglefinus) and blue whiting (Merlangus merlangus) (CEFAS, 2001; DTi (2001) (2); O&G UK, 1998). Spawning grounds extend over large areas of the North Sea, with eggs often developing on the seabed or in the water column, making them vulnerable to pollutants and disturbance.
A number of fish species known to be present within marine waters are protected under UK or international legislation, though few of these have distributions that extend into the offshore waters of the northern and central North Sea (DTi (2001) (2)). During zooplankton
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
abundance the following protected elasmobranch species may occur in small numbers: basking shark (Cetorhinus maximus), tope (Galeorhinus galeus) and porbeagle (Lamna nasus). The common skate (Raja batis) and the Angel Shark (Squatina californica) can also be found at low densities.
Seabirds
Seabirds are present in the central and northern North Sea throughout the year, though densities in the Brae area tend to be lower due to the distance from coastal colonies.
Seabird densities in the Brae area are at their lowest in late spring/early summer when many birds are at their coastal colonies nesting and foraging distances out to sea are reduced (see Table A.1). Species and birds remaining in the offshore areas during late spring/early summer are often dominated by immature birds or non-breeders. At the end of the breeding season, the diversity and density of seabirds offshore increases as breeding birds leave their colonies and disperse into the North Sea. Birds and their chicks are particularly vulnerable to surface pollutants when they are gathering for breeding season and when they undergo a moult of primary feathers (which leaves them flightless) (i.e. Guillemots are most sensitive during July during their moult).
Table A.1: Seabirds likely to be present in the area of the Brae Area
Species Months Present in the North Sea
Fulmar (Fulmarus glacialis) All year
Gannet (Morus bassanus) May to February
Common gull (Larus canus) July – February
Herring gull (Larus argentatus) July – April
Great black-backed gull (Larus marinus) November – February
Kittiwake (Rissa tridactyla) All year
Guillemot (Uria aalge) All year
Little auk (Alle alle) November – February
Puffin (Fratercula arctica) April – September
Source: Stone et al, 1995
Marine Mammals
Twenty seven species of cetacean (which include whales, dolphins and porpoises) have been recorded in the waters around the British Isles, although only seven are regularly sighted in proximity of the Brae area. The most commonly sighted species is the harbour porpoise (Phocoena phocoena), though the range of the Atlantic white-sided dolphin (L. actus), white-beaked dolphin (Lagenorhynchus albirostris), Risso’s dolphin (Grampus griseus), killer whale (Orcinus orca), minke whale (Balaenoptera acutorostrata) and long-finned pilot whale (Globicephala melas) are also known to extend into the North Sea (Joint Nature Conservancy Committee (JNCC), 2003).
The most abundant species in the North Sea (including grey and harbour seals, minke whales, harbour porpoises and white-beaked dolphins) are important predators, influencing
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
the food chain by feeding on a wide range of prey including a number of commercially important fish species (CEFAS, 2001) .
Designations
Seabed pockmarks supporting benthic communities rare to the North Sea are known to exist in the area immediately surrounding the Braemar infrastructure, including the designated Braemar Pockmarks Special Area of Conservation (SAC). This SAC has been described as ‘a series of crater-like depressions on the sea floor reflect the Annex I habitat ‘Submarine structures made by leaking gases’. Braemar pockmarks SAC has a global assessment grade of A (i.e. excellent conservation value) (JNCC, 2012), with a specific benthic assemblage associated with the carbon structures. The boundary of the SAC overlaps with the location of the Braemar infrastructure.
The occurrence of seabed pockmarks indicates potential gas or fluid release, causing suspension and winnowing of sediments and carbon structures. Pockmarks are recognised as potentially providing sheltered habitats for a variety of marine organisms, as well as being active gas seeps which may be of ecological significance due to:
potential utilisation of methane and its by-product, hydrogen sulphide, by chemosynthesisers; and
formation of hard substrate suitable for colonisation by certain benthic organisms.
Commercial Fisheries
The North Sea is an important fishing ground, with Peterhead the main landing port for the Brae area. The commercial species comprise (Xodus 2015; CEFAS, 2001):
pelagic species such as herring (Clupea harengus), mackerel (Scomber scombrus), horse mackerel (Trachurus trachurus);
demersal species such as cod (Gadus morhua), haddock (Melanogrammus aeglefinus), whiting (Merlangius merlangus) and saithe (Pollachius virens); and
shellfish such as Nephrops(Nephrops norvegicus).
Spawning and nursery grounds for various commercially important species are located in the vicinity of the Brae area, including: cod, haddock, Norway pout, saithe, nephrops and mackerel (Xodus, 2015).
Commercial fishing in the vicinity of the Brae area is dominated by demersal and shellfish fisheries, with fishing effort peaking during the spring and autumn (Xodus, 2015). The pelagic fishery peaks for herring in May to September and for mackerel in August to February (Xodus, 2015).
The gear types used for fishing in the Brae area are trawlers and seine nets which were found to account for 100 % of fishing effort in terms of fishing days from 2009 – 2013 (within ICES rectangle 46F1). The shellfish (Nephrops) fishery is the most productive in terms of landings value and the pelagic fishery is the most productive in terms of tonnage (Xodus, 2015).
The average annual economic value of fish landings within 12 nm of each jacket is £1,058,842; this represents a small component (0.2%) of the total landings value by Scottish vessels in 2013, highlighting the relatively low commercial value of the study area (Xodus 2015).
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Other Sea Users and Recreation and Tourism
The North Sea contains some of the busiest shipping routes in the world (DTi (2002) (3)) though a significant proportion of the shipping activity consists of ferries and vessels on fixed routes. A small proportion of peacetime military exercises also takes place within the North Sea, though these activities are mainly concentrated off the south coast of the UK.
The North Sea has been extensively explored for oil and gas, with several production fields currently in operation. Infrastructure comprises platforms (including topsides and jackets), pipelines, drilling templates, drill cuttings piles and other associated infrastructure. Oil and gas activities have been known to result in drilling discharges from exploration and development wells, produced water discharges, accidental oil spills and various other minor discharges (DTi (2002) (3)).
There are no military uses known in the vicinity of the Brae area. The Atlantic Crossing Telecommunication cable is charted to the north of the Brae area.
In respect of recreation and tourism, activities in the offshore North Sea are limited to the occasional yachts in passage.
Marine Archaeology
No designated wreck sites or known marine archaeological features are located within the Brae Area (DTi (2002) (3)).
References
Basford, D J., Eleftheriou, A., and Raffaelli, D., (1990). The infauna and epifauna of the northern North Sea. Netherlands Journal of Sea Research, Vol 25, 165 – 173.
BMT Cordah for CNR International (2013): Environmental Assessment of Options for the Management of the Murchison Drill Cuttings Pile. Rep Ref: A.CNR.038. CNRI Ref. MURDECOM_BMT_EN_STU_00132.
BP (2011): Miller Decommissioning Programme. MLR-A-D0-PM-PRO-00217.
CEFAS (2001): North Sea Fish and Fisheries, Technical report TR_003.
CNR International (2013): Murchison Facilities Decommissioning Environmental Statement. Revised Post-Statutory Consultation. MURDECOM-BMT-EN-REP-00198.
CNRI, 2012. Murchison Decommissioning Comparative Assessment report. Murdocom_CNR_PM_REP_00225.
Council Directive 92/43/EEC on the Conservation of Natural Habitats and of wild fauna and flora.
Curtis, T. Nesse, S. and Picken, G,B. (2001): Guidelines for Energy and Emissions Calculation in Offshore Decommissioning. Society of Petroleum Engineers (SPE). SPE 66498.
DECC (2011). Decommissioning of Offshore Oil and Gas Installations and Pipelines under the Petroleum Act 1998.
DECC (2009): Guidance Notes on the Offshore Petroleum Production and Pipelines (Assessment of the Environmental Effects) Regulations 1999 (as amended).
DECC (2001), Strategic Environmental Assessment of the “Mature Areas of the Offshore North Sea”, SEA 2, Consultation Document.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Department of Trade and Industry (DTi) (2001): Technical Report TR_003, Technical Report Produced for Strategic Environmental Assessment – SEA2, North Sea Fish and Fisheries.
DTi (2001) (2): Strategic Environmental Assessment - SEA2, Technical Report 003 - Fish & Fisheries.
DTi (2002) (3): Strategic Environmental Assessment - SEA2 Technical Report 007 - Existing activities.
ENVIRON (2014). Brae Field Decommissioning EIA Strategy.
EUNIS Habitat classification (2007) – Revised descriptions 2012. Excel spreadsheet. http://www.eea.europa.eu/data-and-maps/data/eunis-habitat-classification#tab-european-data.
Fairfield Energy (2012): Dunlin Alpha Decommissioning Environmental Statement and Environmental Impact Assessment.
FUGRO EMU Ltd (Fugro), 2013. Brae Bravo Cuttings Pile Characterisation Survey UKCS Block 16/7a. Fugro EMU Doc Ref J/1/20/2386-1(3)
FUGRO EMU Ltd (Fugro), 2013 (2). Brae Bravo Environmental Monitoring Survey UKCS Block 16/7A. September 2013. Project Number J/1/20/2386
FUGRO EMU Ltd (Fugro), 2015. Brae Alpha Pre-Decommissioning Environmental Survey UKCS Block 16/7A. Fugro EMU on behalf of Marathon Oil Decommissioning Services LLC. March 2015 Doc Ref J/3/20/2805
FUGRO EMU Ltd (Fugro), 2015 (2). East Brae Cuttings Pile Characterisation Survey UKCS Block 16/3A. April and May 2015. Project Number J/3/20/2805
FUGRO EMU Ltd (Fugro), 2015 (3). Brae Field Cuttings Pile Leachate Analysis Report, November 2015, Project Number J/3/20/2805
Gatliff, R.W., Richards, P.C., Smith, K., Graham, C.C., McCormac, M., Smith, N.J.P., Long, L., Cameron, T.D.J., Evans, D., Stevenson, A.G., Bulat, J. and Ritchie, J.D. 1994. United Kingdom offshore regional report: the geology of the Central North Sea. HMSO, London.
Hartley, J.P. (2005) Seabed Investigations of Pockmark Features in UKCS Block 16/3. Report to Joint Nature Conservation Committee. Aberdeenshire: Hartley Anderson Marathon Oil (October 2014) Brae Field Decommissioning Slide Pack.
Joint Nature Conservation Committee (2012). Braemar Pockmarks SAC Selection Assessment: Version 4.1.
Joint Nature Conservation Committee (2003), Atlas of Cetacean distribution in north-west European waters.
Marathon Oil UK LLC. (2013). Corporate Responsibility (CR) Risk Management.
Marathon Oil UK LLC (2013) (2): NCS 3D mapping Survey of Brae Alpha, Brae Bravo and East Brae Cuttings Piles. Marathon Oil UK LLC. (2009) West Brae Production Consent Environmental Statement.
Marathon Oil UK LLC, 2008. OSPAR Recommendation 2006/5 in a Management Regime for Offshore Cuttings Piles: Stage 1 Screening of the Cuttings Piles at Marathon UK Ltd North Sea installations. Marathon Oil Decommissioning Services LLC. June 2008, Aberdeen
Marathon Oil UK LLC. (2002). Braemar Field Development Environmental Statement.
Oil and Gas UK (2014): HSO88 Guidance on Risk Related Decision Making Issue 2.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Oil and Gas UK (2013). Decommissioning of Pipelines in the North Sea Region.
Oil & Gas UK (1998): Fisheries Sensitivity Maps in British Waters.
OSPAR Commission for the Protection of the Marine Environment of the North-East Atlantic (2000): Quality Status Report 2000 Region II Greater North Sea.
OSPAR Commission for the Protection of the Marine Environment of the North-East Atlantic (1998) Decision 98/3 on the Disposal of Disused Offshore Installations. Ministerial Meeting of the OSPAR Commission. Sintra 22/23 July 1998.
Stone, C.J. et al, (1995), An Atlas of Seabird Distribution in North-West European waters, 326 pages, A4 softback, ISBN 1 873701 94 2.
UKOOA, 2000. Phase I Summary Report. UKOOA Decommissioning Committee. January 2000, Aberdeen, Doc Ref 29003500
UKOOA, 2000(2). Phase II Research & Development Programme. UKOOA Decommissioning Committee. August 2000.
Xodus Group (2014) (1): Brae Bravo Comparative Assessment: Comparison of Energy Use and Emissions. A-1000057-S02-REPT-004.
Xodus Group (2014) (2): Brae Bravo Decommissioning: Comparative Assessment. Comparison of Underwater Noise Emissions and potential impact. A-10000057_S02_REPT_006.
Xodus Group (2015) Fishing Intensity & Socioeconomic Study. A-100057-S03-REPT-003.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Annex B: Preliminary Scoping Parameters: Frequency/Likelihood; Magnitude and Environmental Effect/Risk Matrices
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Evaluating Potential Frequency
The criteria used to evaluate frequency in respect to planned activities are set out within Table B.1 below.
With respect to accidental events, rather than frequency, the likelihood of an identified risk occurring has been considered. The criteria used to evaluate likelihood of an accidental event occurring is also set out within Table B.1 below.
Table B.1: Frequency/Duration of an Activity (Planned) / Likelihood (Accidental) of the Activity
Frequency/Duration of an Activity (Planned Activities)
Likelihood (Accidental Events)
1: High frequency (activity occurring multiple times (>3) daily or for more than 3 hours daily or for a duration of > 1 year).
1: High - More than 10 times in Project Lifetime.
2: Medium frequency (activity occurring at least once a day or for a period of up to 3 hours daily or for a duration of > 6 months but < 1 year).
2: Medium - 5 – 10 times in Project Lifetime.
3: Low frequency (activity occurring at least once a week or for a duration of > 7 days but < 6 months).
3: Low - 3 – 5 times in Project Lifetime.
4: Infrequent (activity occurring at least once a month or one off event over project lifetime for > 24 hours but < 7 days).
4: Infrequent - Twice in Project Lifetime.
5: Highly infrequent (less than a monthly occurrence or one off event over project lifetime for < 24 hours).
5: Highly Infrequent/Remote – Unlikely to occur in the Project Lifetime, once or never.
Evaluating Potential Magnitude
The magnitude of the potential change, based on scale of high, medium, small, neutral and positive/no change based on an assessment across three categories, as set out in Table B.2.
Table B.2: Magnitude of the Change
Magnitude Description
1: High If an identified impact would:
Result in the complete loss of, or loss of integrity and/or functionality of an environmental feature; result in national or international concerns from stakeholders.
Major consequences to the environment.
2: Medium If an identified impact would:
Result in loss of a significant proportion of an environmental feature with potential risk to integrity and/or functionality of that feature; result in regional concerns from stakeholders.
Moderate consequences to the environment.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table B.2: Magnitude of the Change
Magnitude Description
3: Small If an identified impact would:
Result in loss of small parts of an environmental feature, not affecting integrity and/or functionality; result in local concerns from stakeholders.
Minor consequences to the environment.
4: Neutral If the activity under consideration follows best practice guidance, is anticipated to have negligible impact on the receiving environment and there is limited interest from stakeholders.
No or very minor consequences to the environment.
5: Positive/No Impact
If an identified impact would result in:
Long-term improvement of an environmental feature, improving its functionality; and/or
Long-term improvement of ecosystem services, improving functionality.
If an impact would have:
No impact on environmental features, and therefore have no effect on their integrity and/or functionality.
Table B.3 summarises the activity/receptor interaction and sets out the basis for allocating the potential environmental effect or risk category. A summary definition of each category is provided in Table 4.1.
Table B.3: Scoping Effect Category Matrix
Frequency/Likelihood
Magnitude 1 2 3 4 5
1 High High High Medium Medium
2 High High Medium Medium Low
3 Medium Medium Low Low Negligible
4 Low Low Negligible Negligible Negligible
5 No Impact/ Positive
No Impact/ Positive
No Impact/ Positive
No Impact/ Positive
No Impact/ Positive
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Annex C1: Activity/Receptor interactions scoped as ‘high’ potential for significant environmental effect
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category5
Discussion
C1.1
Seabed Disturbance (Designated Sites and Species)
Removal of Braemar wellhead and flowlines to East Brae and potential effects on seabed pockmarks, benthic communities and natural seabed sediments.
Braemar infrastructure and flow lines
Medium to High In the Brae Area, the seabed comprises silt and clay (mud) in the surface few metres, underlain by increasingly stiff silts and clays. Seabed pockmarks supporting benthic communities rare to the North Sea are known to exist in the area immediately surrounding the Braemar wellhead, suspended well and associated flowlines. The Braemar wellhead is located approximately 90 m south of the Braemar pockmarks SAC designation boundary, and the Suspended Well (16/03c-12) is located within the SAC boundary.
Seabed disturbance and subsequent resettlement has the potential to disturb and/or smother benthic organisms. Benthic assemblage associated with the pockmarks may also be subject to localised disturbance/smothering.
On this basis the potential for significant effect is considered to be medium to high. This issue will be considered in more detail as part of the EIA.
Consideration of the likely effects on the Braemar Pockmarks Special Area of Conservation (Habitat Regulations
5 In the case of ‘accidental events’ the risk grading could be low – high depending on the extent of any accidental event.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category5
Discussion
Assessment (HRA)) will be taken forward as part of the EIA process.
C1.2 Noise Effects (fish, marine mammals, seabirds)
Full or partial removal of the platform jacket structure and potential to affect noise sensitive species of marine mammals.
Brae Alpha, Brae Bravo and East Brae
High It is anticipated that noise generation from both cutting operations and from vessel activity would result in underwater noise which would represent a potential change from ambient conditions.
These works have the potential to result in noise impacts to marine mammals (disturbance and/or displacement). Early calculations completed in relation to this activity (Xodus, 2014) indicate the potential for behaviour disturbance to marine mammals from cutting over a range of up to 10 km. Disturbance from vessel noise may extend up to 3 km for larger crane vessels. As such, jacket removal is considered to have a high potential to result in significant environmental effect on marine mammals.
See consideration of effects on fish under reference C2.6. There is considered to be a medium potential for jacket removal to affect noise sensitive species of fish and seabirds. This is considered further in Annex D2.
C1.3 Removal of subsea installations through the use of explosives and the potential for
Central Brae template
High These works have a high potential to result in significant noise effects to marine mammals (disturbance and/or displacement). Further consideration will be given to the use of explosives as part of the EIA process.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category5
Discussion
noise effects on marine mammals.
C1.4 Water Quality Effects (water quality, plankton, fish, shellfish, marine mammals)
Removal or disturbance to the drill cuttings piles either through:
i) removal or relocation of the drill cuttings piles; and
ii) removal of the steel jacket footings, or removal of the subsea installations directly associated with the platforms e.g. umbilicals, risers, cables, pipelines/flowlines, drill templates. Potential to mobilise sediments and for elevated levels of contaminants in the water column, with secondary effects on marine species (benthos, fish and shellfish) and water quality.
Brae Alpha, Brae Bravo and East Brae
High Stage 1 OSPAR assessment (Marathon, 2008) concluded that drill cuttings piles at all three platforms fall below the specified OSPAR thresholds and therefore may be left in situ to degrade naturally.
Removal or disturbance of the drill cuttings piles would result in remobilisation of contaminants beneath the platforms with resultant localised changes to sediments, organic carbon content and water quality with contaminants in the water column. This has the potential to indirectly affect benthic species, fish and shell-fish and marine mammals.
The scope of this assessment will be developed in parallel with ongoing Net Environmental Benefit Analysis (NEBA) in support of the Comparative Assessment for cuttings pile management.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category5
Discussion
C1.5 Accidental Events Accidental release of contaminants during topside preparation affecting water quality with secondary effects on marine ecosystems.
Brae Alpha, Brae Bravo and East Brae
Low – High Topside preparation has been taken to include activities required to ensure hydrocarbons and chemicals have been removed; all processing plant has been shut down and isolated from the reservoir; and all conductors, casings, tubing and other well equipment removed. There is the potential for an unplanned spill (hydrocarbons, hazardous materials or cleaning materials) which would result in elevated levels of contaminants reaching water column and seabed. Scale of spill would be dependent on activity and chemicals/contaminants being handled, as such there is range of risk from low to high. Further consideration will be given to the potential for significant environmental effect from accidental or unplanned events as part of the EIA process.
C1.6 Risk of accidental spills associated with vessel activities.
Risk of dropped objects, particularly during lift operations.
Topside preparation, removal, jacket removal and subsea installation removal
Drill cuttings piles (remove/relocate)
Low – High A range of vessels of types, sizes will be required to facilitate decommissioning activities. Risk of accidental spills from vessel activity will remain throughout the decommissioning programme particularly associated with, but not limited to, topside preparation, topside removal and jacket removal. Further consideration will be given to the potential for significant environmental effect from accidental or unplanned events as part of the EIA process.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.1 : Activity/receptor interactions scoped in for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category5
Discussion
Further consideration of the potential effects associated with dropped objects during the main lifts will be given within the accidental events section of the EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Annex C2: Activity/Receptor interactions considered ‘medium’ potential for significant environmental effect and therefore taken forward to Stage 2 scoping
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.2: Activity/receptor interactions for further scoping consideration
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infrastructure affected
Initial Effect Category
Discussion
C2.1 Seabed Disturbance Effects (marine benthos, geology, natural seabed sediment and drill cuttings pile)
Disturbance to natural seabed sediments and drill cuttings pile sediments during jacket removal with or without footings) and removal or preparation of footings, risers, umbilicals etc. to leave in situ.
Potential effects on both soft sediment and hard substrate benthic communities.
Localised disturbance to seabed during removal of flare stack jacket at Brae Bravo and potential effects on benthic communities.
Effects associated with drill cuttings pile removal or relocation.
Brae Alpha, Brae Bravo, East Brae
Low - Medium
In the event of derogation, certain decommissioning activities will be required in order to leave risers, umbilicals and other infrastructure in situ underlying the known extent of drill cuttings piles beneath Brae Alpha, Brae Bravo and East Brae.
An estimated 1,400 Te each (Brae Alpha and Brae Bravo) and 460 Te (East Brae) of hard substrate benthic assemblage (not designated) on the jacket legs is anticipated to require removal by water jetting prior to jacket lift. This could result in the loss of potentially ecologically valuable hard substrate habitat and/or disturbance to natural seabed sediments.
Potential disturbance to natural seabed sediments and/or drill cuttings pile sediments during decommissioning activities which mobilise sediment into the water column (temporary local increase in turbidity). Potential indirect effects include smothering benthic communities (including Priority Marine Features as defined by the Marine (Scotland) Act 2010. Potential for water quality effects are considered separately.
Taken forward into Stage 2: detailed scoping
C2.2
Localised disturbance to seabed during removal of area wide subsea installations affecting benthic communities and natural seabed sediments.
Central Brae template, West Brae and Sedgewick wellheads and
Low - Medium
Seabed sediment disturbance by removal of infrastructure as well as settlement of marine growth removed from infrastructure by water jetting prior to removal, and potential for effects on benthic communities.
Taken forward into Stage 2: detailed scoping
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.2: Activity/receptor interactions for further scoping consideration
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infrastructure affected
Initial Effect Category
Discussion
Braemar Infrastructure
C2.3
Localised disturbance to seabed in event of pipeline/cable, flowline/umbilical removal affecting benthic communities, natural seabed sediments and water quality.
Pipeline/cable, flowline/umbilical
Medium It is known that a combination of surface laid, trenched and rock-covered sections of pipeline exist. Removal of surface laid pipelines would result in surface silt being mobilised into the water column, however this would be expected to settle quickly and in a similar composition to that found before the pipeline removal. It has been assumed that adequately trenched or rock-covered pipelines would remain in place in accordance with DECC guidelines (DECC, 2011).
Overall there is considered to be a medium potential for significant effect.
Taken forward into Stage 2: detailed scoping
C2.4 Underwater noise
Removal of pipeline/ cable / flowline / umbilical, risers and other subsea infrastructure directly associated with the platform and potential to affect noise sensitive species including fish and marine mammals.
Pipeline/ cable / flowline / umbilicals associated with Brae Alpha, Brae Bravo, East Brae
Medium Vessel activity, and physical removal of pipeline /cable / flowline / umbillical, may result in underwater noise from cutting operations which would represent a potential change from the ambient conditions during operations.
Taken forward into Stage 2: detailed scoping
C2.5 Topside removal and potential to affect noise sensitive species including
Brae Alpha, Brae Bravo and East Brae
Medium It is anticipated that noise generation from vessel activity would result in underwater noise which would represent a potential change from ambient conditions.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.2: Activity/receptor interactions for further scoping consideration
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infrastructure affected
Initial Effect Category
Discussion
fish, seabirds and marine mammals.
Taken forward into Stage 2: detailed scoping
C2.6 Jacket removal and potential to affect noise sensitive species of fish and seabirds.
Drill Cutting Piles (Remove/ Relocate
Brae Alpha, Brae Bravo and East Brae
Medium It is anticipated that noise generation both from cutting activity, and associated vessel activity would result in underwater noise which would represent a potential change from ambient conditions.
Taken forward into Stage 2: detailed scoping
C2.7 Removal of pipelines/ cables / flowlines / umbilicals and the potential to affect noise sensitive species including fish and marine mammals.
Pipelines/ cables / flowlines / umbilicals (area wide)
Medium Vessel activity, and physical removal of pipeline /cable / flowline / umbilical, may result in underwater noise from cutting operations which would represent a potential change from the ambient conditions during operations.
Taken forward into Stage 2: detailed scoping
C2.8 Water Quality Effects (water quality, plankton, fish, shellfish, marine mammals)
Localised disturbance of drill cuttings pile contaminants when left in situ
Steel Jacket – Partial Removal
Brae Alpha, Brae Bravo and East Brae
There would be a limited potential for disturbing the drill cuttings piles associated with activities such as water jetting off the jacket structures. Further consideration is given to potential for significant effects in Stage 2: detailed scoping.
C2.9 Water Quality Effects (water quality, plankton, fish, shellfish, marine mammals)
Localised seabed disturbance during the area wide removal of pipelines/cables / flowlines / umbilicals and other subsea installations resulting in potential direct effects on water quality
Pipelines/ cables / flowlines / umbilicals (area wide) and other subsea installations
Low - Medium
Seabed disturbance during cutting and lifting activities leading to local mobilisation of sediments with effects on water clarity (turbidity) and quality in a local area, result in changes water column, with potential effects on plankton.
Taken forward into Stage 2: detailed scoping
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.2: Activity/receptor interactions for further scoping consideration
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infrastructure affected
Initial Effect Category
Discussion
and indirect effects on plankton, fish and shellfish and marine mammals.
Any discharges to sea from the cleaning of pipelines/flowlines will be managed and assessed under the existing permitting regime (e.g. The Offshore Petroleum Activities (Oil Pollution
Prevention and Control) Regulations 2005 (as
amended), UK Oil Pollution Prevention, Offshore Chemical Regulations 2002 Chemical Permit). As such, these discharges have been scoped out of the decommissioning EIA.
C2.10 Socio-economic and Other Effects (commercial fisheries, shipping/ navigation, recreation, marine archaeology)
Potential for steel jacket footings presenting a long term hazard to demersal fisheries.
Brae Alpha, Brae Bravo and East Brae
Medium There is already a 500 m safety zone around surface infrastructure in place, and it is assumed that this will remain in place for the duration of the decommissioning works. This represents no change from existing conditions.
Following removal of the jacket (with the a derogation agreed to leave the footings in situ), the footings and cutting piles would continue to present an obstruction on the seabed preventing demersal trawl fishing As such it is proposed that the safety zone would be retained to mitigate fishing risks.
Taken forward into Stage 2: detailed scoping to consider potential socioeconomic effect.
C2.11 Atmospheric Emission Effects (energy use, climate change, air quality)
Emissions to air will occur as a result of vessel movements associated with topside removal, jacket removal (including Brae Bravo flare stack), drill cuttings pile removal
All infrastructure Medium Potential for environmental effect relates to energy use (resource use) as a result of vessel movements. Climate change effects and air quality effects relate primarily to CO2 emission as a primary greenhouse gas and also NOx and particulates. Further consideration is given to natural resource use, air
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.2: Activity/receptor interactions for further scoping consideration
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infrastructure affected
Initial Effect Category
Discussion
and pipeline and other subsea installation removal, with implications for energy use.
quality and climate change effects in Stage 2: detailed scoping.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Annex C3: Activity/Receptor interactions considered ‘low’ potential for significant environmental effect and therefore scoped out of the EIA
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.1
Designated Sites and Species Disturbance
Transportation of Materials and Personnel to and from Brae Area
Brae Alpha, Brae Bravo, East Brae
Negligible Transportation of Materials and Personnel to and from the Brae Area would be conducted primarily by helicopter with infrequent vessel use. There is no potential for interaction with designated sites or species.
Birds are considered to be sensitive to airborne noise (as a result of helicopter movements) which could cause displacement. However given the low frequency at which movements would occur and low magnitude of change (low consequence) for bird populations it is considered unlikely to result in more than a negligible impact.
C3.2
Topsides Preparation
Brae Alpha, Brae Bravo, East Brae
No Impact Topside preparation activities would have no interaction with designated sites or species.
C3.3
Subsea Installations Removal, including removal of marine growth by water jetting
Brae Alpha, Brae Bravo, East Brae, Area Wide infrastructure (excluding Braemar)
Low Excluding the Braemar infrastructure, there would be no interaction between the removal of subsea installations and designated sites.
Displacement or disturbance of species of interest from noise and Vessel Presence and decommissioning activities are likely to be low
6 In the case of ‘accidental events’ the risk grading could be low – high depending on the extent of any accidental event.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
frequency, short duration and as such small magnitude of change for this activity.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Overall the potential for significant environmental effect is considered to be low.
C3.4
Topsides Removal Brae Alpha, Brae Bravo, East Brae
No Impact Topside removal activities would have no interaction with designated sites or species.
C3.5
Drill Cutting Piles (Remove/ Relocate)
Brae Alpha, Brae Bravo, East Brae
No Impact No impacts are predicted during standard operating conditions on designated sites and species since there are no currently designated or proposed Special Areas of Conservation or Special Protection Areas in the vicinity of the Brae Alpha, Brae Bravo or East Brae drill cuttings piles.
C3.6
Drill Cutting Piles (left in situ)
Brae Alpha, Brae Bravo, East Brae
No Impact Drill cuttings piles left in situ would have no interaction with designated sites or species.
C3.7
Steel Jacket – Full Removal, including removal of marine
Brae Alpha, Brae Bravo, East Brae
Low Jacket removal activities would have no interaction with designated sites.
Displacement or disturbance of species of interest from noise and Vessel Presence and
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
growth by water jetting
decommissioning activities are likely to be low frequency, short duration and as such small magnitude of change for this activity.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Overall the potential for significant environmental effect is considered to be low.
C3.8
Steel Jacket – Partial Removal
Brae Alpha, Brae Bravo, East Brae
Low Jacket removal activities would have no interaction with designated sites.
Displacement or disturbance of species of interest from noise and Vessel Presence and decommissioning activities are likely to be low frequency, short duration and as such small magnitude of change for this activity.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
Overall the potential for significant environmental effect is considered to be low...
C3.9
Pipeline/ Cable/ Flowline and Umbilical (removal or left in situ)
Area Wide Infrastructure (excluding Braemar and East Brae tie-back)
Low Displacement or disturbance of species of interest from noise and Vessel Presence and decommissioning activities are likely to be low frequency, short duration and as such small magnitude of change for this activity.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Where infrastructure would be left in place, there would be no potential for interaction with designated sites or species.
Overall the potential for significant environmental effect is considered to be low.
C3.10
Seabed Disturbance Effects (marine benthos, geology, natural seabed sediment
Transportation of Materials and Personnel to and From Brae Area
Brae Alpha, Brae Bravo, East Brae
Negligible Seabed disturbance is likely to be negligible with the majority of transportation using helicopter flights with occasional/ infrequent vessel movements.
C3.11 Topsides Preparation
Brae Alpha, Brae Bravo, East Brae
No Impact No seabed disturbance is predicted during topsides preparation - all operations would be conducted above water.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.12
and drill cuttings pile)
Topsides Removal Brae Alpha, Brae Bravo, East Brae
Low There is the potential for physical disturbance to the seabed and suspension of sediment into the water column associated with anchoring vessels. It is considered that site survey data would be used to select appropriate anchor locations resulting in a small magnitude of change and, overall, a low impact.
C3.13
Drill Cutting Piles (left in situ)
Brae Alpha, Brae Bravo, East Brae
Low Stage I OSPAR assessment (Recommendation 2006/5) undertaken for each of the drill cuttings piles concludes that drill cutting pile sediment fall below the OSPAR screening thresholds. Therefore the drill cutting piles may be left in situ to degrade naturally.
Overall the potential for significant environmental effect is considered to be low.
C3.14
Pipelines/cables, flowlines/umbillical (left in situ)
Area wide subsea pipelines/cables, flowlines/umbilicals
No Impact - Low It has been assumed that adequately trenched or rock-covered pipelines/cables, flowlines/umbilicals would remain in situ in accordance with DECC guidelines (DECC, 2011). This would result in no impact on natural seabed sediments or benthic communities. Additional rock covering of infrastructure may be required; however this would be over a local extent and is considered to represent a low potential to result in significant environmental effect.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.15 Noise effects (fish, marine mammals, seabirds)
Transportation of Materials and Personnel to and from Brae Area
Brae Alpha, Brae Bravo, East Brae
Negligible - Low Low frequency and small magnitude disturbance to birds flying in the area due to the noise produced by the helicopters. Assessed as low potential for significant environmental effect.
Infrequent and small magnitude of change associated with vessel movements required to transport materials/personnel to and from the Brae Area. Majority of transportation will be by helicopter. Assessed as negligible potential for significant effect on fish or marine mammals.
C3.16 Topsides Preparation
Brae Alpha, Brae Bravo, East Brae
Low Vessel activity associated with decommissioning has been considered against the existing vessel activity in the area. Topside decommissioning will result in infrequent short term vessel noise, which is unlikely to represent more than a small/local change from the ambient conditions.
As a result a low potential for significant environmental effect has been identified.
C3.17 Drill Cutting Piles (left in situ)
Brae Alpha, Brae Bravo, East Brae
No Impact No underwater noise source if drill cuttings piles left in situ. No impact.
C3.18 Pipeline/ cable/ flowline/ umbilical – left in situ
Area wide infrastructure
No Impact No underwater noise source if installations left in situ. No impact.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.19 Water Quality Effects (water quality, plankton, fish, shellfish, marine mammals)
Transportation of Materials and Personnel to and From Brae Area
Brae Alpha, Brae Bravo, East Brae
No Impact There are no planned discharges to sea associated with transportation of materials and personnel by helicopter, and negligible pollution to water quality associated with infrequent vessel use. No impact is anticipated.
C3.20 Topsides Preparation
Brae Alpha, Brae Bravo, East Brae
No Impact Any discharges to sea from topsides preparation will be managed and assessed under the existing permitting regime (e.g. The Offshore Petroleum Activities (Oil Pollution Prevention and Control) Regulations 2005 (as amended), UK Oil Pollution Prevention, Offshore Chemical Regulations 2002 Chemical Permit). As such, these discharges have been scoped out of the decommissioning EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.21 Topsides Removal Brae Alpha, Brae Bravo, East Brae
No Impact Topsides will be free from gross hydrocarbon. Other stored chemicals or potential contamination sources present during operation of the platforms will have been removed during the Topsides preparation for decommissioning. As such there will be no potential source of pollution associated with the topside removal activity. Any discharges of waste water, chemicals and oils to sea will be managed and assessed under the existing permitting regime (e.g. (Oil Pollution Prevention and Control) Regulations 2005 (as amended), UK Oil Pollution Prevention). As such, these discharges have been scoped out of the decommissioning EIA.
C3.22 Pipeline/ cable/ flowline/ umbilical – left in situ
Area wide infrastructure
No Impact Any discharges to sea from the cleaning of pipelines/flowlines will be managed and assessed under the existing permitting regime (e.g. The Offshore Petroleum Activities (Oil Pollution Prevention and Control) Regulations 2005 (as amended), UK Oil Pollution Prevention, Offshore Chemical Regulations 2002 Chemical Permit). As such, these discharges have been scoped out of the decommissioning EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.23 Socio-economic and Other Effects (commercial fisheries, shipping/ navigation, recreation, marine archaeology)
Topsides Preparation
Brae Alpha, Brae Bravo, East Brae
No Impact Operations would take place only on the platforms. There is no potential for interaction with other sea users.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
C3.24 Socio-economic and Other Effects (commercial fisheries, shipping/ navigation, recreation, marine archaeology)
Platform subsea installations removal;
Topsides Removal;
Drill Cutting Piles (Remove/ Relocate;
Drill Cutting Piles (left in situ);
Steel jacket – full removal;
Subsea Installations Removal;
Pipeline/ cable/ flowline/ umbilical – removal and left in situ
Brae Alpha, Brae Bravo, East Brae
No Impact There is a 500 m safety zone in place around the platforms, and it is assumed that this will remain in place for the duration of the decommissioning works to avoid conflict with navigation or commercial fishery interests. As such there would be no change from ambient conditions.
Drill cuttings would only be left in situ where a derogation was in place to leave the steel jacket footings in place. In this scenario the 500 m safety zone would remain in place around the platforms, in order to prevent interaction between commercial fishing and the remaining contaminated sediments associated with the drill cuttings piles.
Where pipelines / cable/ flowline/ umbilical are proposed to be left in situ it is assumed that they would be either trenched or suitably rock covered such that there would be no interaction with commercial fishery interests. It has been assumed that adequately trenched or rock-covered pipelines would remain in place in accordance with DECC guidelines (DECC, 2011) and that there would be no potential to create berms on the seabed.
There are no RYA racing areas, sailing areas, recreational cruising routes, dive sites, sea angling sites, windsurfing locations or education research locations in the area.
No designated wreck sites or known marine archaeological features are located within the Brae Area.
Full removal of infrastructure would allow the area to potentially become suitable for pelagic
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
and demersal fishing. No Impact / potential positive effect.
C3.25 Atmospheric Emission Effects (energy use, climate change, air quality)
Transportation of Materials and Personnel to and From Brae Area
Topside Preparation
Drill Cutting Piles (left in situ)
Pipelines/ cables/ flowlines/ umbilicals – removal and left in situ
Brae Alpha, Brae Bravo, East Brae
Negligible Energy use and emissions associated with helicopter or infrequent vessel movements during the decommissioning works would comprise a small or neutral magnitude of change resulting in minor or very minor consequences in terms of air quality or climate change effect. Given the meteorological conditions, emissions will likely disperse rapidly. All vessel will comply with MARPOL 73/78 Annex VI on air pollution; plant will comply with relevant air pollution regulations (The Offshore Combustion Installations (Prevention and Control of Pollution) (Amendment) Regulations 2007.
On this basis the overall potential for significant environmental effect is considered to be negligible. The potential for significant effect as a result of this activity/receptor interaction has therefore been scoped out of the EIA.
C3.26 Accidental Events
Transportation of Materials and Personnel to and from Brae Area
Brae Alpha, Brae Bravo, East Brae
Low There is only potential for accidental spills in the event of a transport accident. This is considered to be a highly infrequent/remote possibility with a potential medium magnitude of change. Overall the risk of accidental spill is considered low.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Table C.3: Activity/receptor interactions scoped out for consideration within the EIA
Reference (see Table 5.1 and 5.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Initial effect category6
Discussion
C3.27 Drill Cutting Piles (left in situ)
Brae Alpha, Brae Bravo, East Brae
Low The only accidental event that might occur would be linked to dropped items or water jetting of steel jackets and other infrastructure resulting in unintended/unplanned disturbance to the drill cuttings piles. A Stage 1 OSPAR assessment (under the terms of OSPAR Recommendation 2006/5) was undertaken in 2008 (updated in 2015 following additional sampling) and concluded that the drill cutting piles located at all three platforms fall below the thresholds set out within this recommendation and could therefore be left in place to degrade naturally. Any accidental mobilisation of contaminants would be short term and localised, and therefore low risk.
C3.28 Accidental Events
Pipelines / Cables / Flowlines / Umbilicals – left in situ
Brae Alpha, Brae Bravo, East Brae and area wide subsea installations
Negligible It has been assumed that only adequately trenched or rock-covered pipelines would remain in place in accordance with DECC guidelines (DECC, 2011). Additional rock cover would be added where necessary to reduce the potential risk associated with ‘snagging’ of fishing nets.
The result is a negligible risk of significant environmental effect.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Annex D1: Detailed Scoping Parameters: Sensitivity; Duration of Impact; Geographic Extent.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Considering Potential Sensitivity
The sensitivity of the receptor is based on consideration of known information relating to the following four characteristics:
Adaptability (how well a receptor can avoid or adapt to an effect);
Tolerability (the ability of a receptor to be either affected or unaffected);
Recoverability (how well a receptor recovers following exposure to an effect); and
Value (the scale of importance).
These parameters would vary according to each technical discipline and thus, sensitivity is a concept that has been applied to individual disciplines/receptors based on professional judgement.
Considering Potential Duration of Effect
The duration of an effect is based on an assessment across four categories, long-term, medium term, short term and very short term as set out in Table D.1.
Table D.1: Duration of an Effect
Duration Description
1: Long Term Recovery to original state in more than 10 years, or not at all.
2: Medium Term Recovery to original state in more than a year, but less than 10 years.
3: Short Term Recovery to original state in more than one month, but less than a year.
4: Very Short Term Recovery to original state in less than one month.
Considering Potential Geographical Extent
The geographical extent of an impact is based on an assessment across three categories, local, regional and national/international.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_5 Ramboll Environ
Annex D2: Summary of Stage 2 Scoping Outputs
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
D2.1 Seabed Disturbance
Disturbance to seabed during partial removal of jackets, risers, pipelines (other than surface laid, see below) umbilicals, power cables and other subsea installations, with resultant potential effects on benthic communities, natural seabed sediments and cuttings pile sediments. Disturbance may also occur during preparation for the footings to be left in situ.
All (excluding Braemar)
Low - Medium
Seabed disturbance would occur throughout the duration of the decommissioning programme, associated with a range of proposed decommissioning activities. This would result in the potential mobilisation of sediment into the water column, including potential contaminants.
Geographical Extent
It is anticipated that impacts would be focused in proximity to the installation, though the potential for sediment and contaminant movement may be influenced by variations in localised water currents over time. Sediment would be expected to re-settle quickly as a result impacts would occur at a local scale only.
Sensitivity
Natural turbidity in the water column would be dependent on meteorological conditions and tides, but is not expected to be high. The seabed comprises silt and clay (mud) in the surface few metres, underlain by increasingly stiff silts and clays. (Hartley 2005).
Disturbance of the sediment in the surface area would be expected to be short term, with resettlement occurring rapidly, with limited potential for the formation of persistent mounds. Impacts would be focused in close
Low
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
proximity to the installation/route of subsea infrastructure or cables.
Mitigation
Cutting and lifting operations associated with the removal of subsea infrastructure would be controlled by ROV to ensure accuracy in all activities and therefore minimise the potential for seabed sediment disturbance.
Summary
The potential for significant effect as a result of this activity/receptor interaction is considered low to positive and has therefore been scoped out of the EIA.
D2.2 Seabed disturbance
Disturbance to seabed during full removal of jackets, footings, drill cuttings piles.
All (excluding Braemar)
Low - Medium
Cuttings pile removal (to surface for onshore treatment and disposal) could be expected to result in 90 – 95% recovery rate of cuttings pile dredged material (BMT Cordah, 2013). However, assuming the use of a closed recovery system (CNRI, 2013), effects would arise as a result of the re-suspension of drill cuttings by placement of the suction dredge in the pile; and through) the likely requirement to back-flush the dredge in order to dislodge any debris that becomes lodged within the suction hose. Back-flushing of the suction dredge would be considered to be the worst case disturbance scenario, as it is expected that this would result in the discharge to sea of the
Low - Medium
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
entire contents of the closed system hose, from the suction dredge to the vessel on the surface (CNRI 2012). In this regard, further assessment is required to evaluate the potential effect of back-flushing on the adjacent soft bottom habitat.
The benthic communities in the Brae Area typically comprise deeper water sand communities. Typical species may include Priority Marine Features as defined by the Marine (Scotland) Act 2010. The potential for significant effect on this assemblage remains scoped in to the EIA.
D2.3 Noise Topside removal; platform subsea installation removal and drill cuttings piles removal or relocation with the potential airborne noise to affect noise sensitive seabirds and underwater noise to affect fish and marine mammals.
Brae Alpha, Brae Bravo and East Brae
Medium The frequent movement of vessels associated with current operations within the area indicate that a certain degree of habituation and tolerance in marine mammals to vessel related underwater noise can reasonably be assumed. Vessel movements associated with topside removal would be intermittent, spanning a period of time dependent on the final chosen method of removal. Vessel movement associated with the removal of drill cuttings piles has been estimated at 1928 workdays. Disturbance from vessel underwater noise may extend up to 3km for larger crane vessels. Noise from vessel activity may also displace/disturb seabirds within 100m (Xodus, 2014). Vessel noise is
Low
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
not considered to be a significant source of disturbance to fish.
Impacts associated with vessel activity are likely to be temporary. Disturbance from vessel underwater noise may extend up to 3km for larger vessels Under these circumstances, should displacement or disturbance occur to an individual it is considered likely that these individuals would recover and return to the location following cessation of the decommissioning activity.
Seabirds have the potential to be affected by the noise and presence of vessels, either directly or indirectly through prey displacement. In general the Brae Area has lower densities of seabird activity in comparison to other areas of the central North Sea due to the distance from coastal colonies, with the lowest densities during late spring/early summer (Stone 1995). However the frequent movement of vessels and industrial activity in the area indicates that the bird species which habituate the Brae Area would be tolerant to vessel presence and associated noise impacts.
The potential for significant effect as a result of this activity/receptor interaction is considered to be low has therefore been scoped out of the EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
D2.4 Pipeline and subsea installation removal and potential to produce underwater noise with effects on noise sensitive fish and marine mammals.
Pipelines and other subsea installations
Medium Marine mammals are considered to be highly sensitive and have the potential to be affected by the noise and presence of vessels, directly, or indirectly through prey displacement. In general, marine mammals are considered to show the highest sensitivity to noise, although effects on fish species such as cod and herring remain possible over 4-5km from source. All cetaceans are listed in Annex IV of the EC Habitats Directive (92/43/EEC) as species being in need of strict protection. In general, the area has lower densities of marine mammals than in other areas, though numbers are likely to increase during the summer months. It is noted that the North Sea contains some of the busiest shipping routes in the world, though the Brae Area is relatively light, dominated by oilfield supply boats and fishing boats. However, the frequent movement of vessels and industrial activities in the area indicates that the species present would be tolerant to vessel presence and associated impacts.
The duration or effects is considered to be short term due to the common occurrence of vessel movements in the North Sea, it is considered that should any impacts associated with displacement and disturbance occur, the species would recover and return
Medium
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
to these locations at the cessation of the decommissioning activities.
Noise from the vessels and cutting activities may displace/disturb marine mammals (and to a lesser extent, fish) in the immediate vicinity and in the wider area (due to noise travelling long distances underwater).
Overall the effect of cutting operations means that the potential for significant effect remains medium and is scoped in to the EIA..
D2.5 Water Quality Effects (water quality, plankton, fish, marine mammals)
Localised disturbance of drill cuttings pile contaminants when left in situ and potential effects on benthic communities, natural seabed sediments and drill cuttings piles sediments.
Brae Alpha, Brae Bravo and East Brae
Low - Medium
In the event that drill cuttings piles will be left in situ, impacts will be limited to localised seabed disturbance and subsequent resettlement of sediment associated with marine organisms (e.g. water jetting off structures) falling to the seabed and potentially disturbing the drill cuttings piles. Disturbance would be limited to the surface/upper layers of the drill cuttings piles where contamination as a result of natural remediation processes is already reduced. Stage 1 OSPAR assessment (Marathon, 2008) concluded that drill cuttings piles at all three platforms fall below the specified OSPAR thresholds and therefore may be left in situ to degrade naturally
The potential for significant effect as a result of this activity/receptor interaction has therefore been scoped out of the EIA.
Low
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
D2.6 Socio-economic and Other Effects (commercial fisheries, shipping/navigation, recreation, marine archaeology)
Derogated footings presenting a long term hazard to demersal fisheries.
Brae Alpha, Brae Bravo and East Brae
Medium The North Sea represents an important fishing ground in European and North Atlantic context, with Peterhead the main landing port for the activities including in the Brae Area. Commercial species comprise pelagic species (herring, mackerel, horse mackerel), demersal species (cod, haddock, whiting and saith) and shellfish (Nephrops). The gear types used for fishing are trawlers and seine nets which were found to account for 100 % of fishing effort in terms of fishing days from 2009 – 2013 (within ICES rectangle 46F1) (Xodus, 2015).
A 500 m safety zone around surface infrastructure is in place, and it is assumed that this will remain in place for the duration of the decommissioning works. This represents no change from existing conditions.
In the longer term, it has been estimated that full removal would result in fishermen regaining access to approximately 2,500 m2 (Xodus, 2015). In the event of derogated footings, the immediate area of the jacket footprint, approximately 70 x 50 m per platform would remain inaccessible, however consideration would be given to maintaining the existing 500 m safety zone.
In the event of derogation the presence of the footings would be marked on relevant charts and communicated to other sea users through
Low/Medium
(Scoped into Stage 3 Scoping to consider implications of comparative assessment analysis.)
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
the normal communication channels (for example, FishSAFE).
It is recognised that the area around the platforms forms a very small part of the much greater Fladen Ground fishery, and therefore effort and landings from the area are low at a national UK level. Any short-term or long-term potential impacts from decommissioning (of platforms or other infrastructure, such as pipelines) should therefore be viewed in this overall context.
The potential for significant effect as a result of this activity/receptor interaction is considered likely to be low/medium at this stage. Further consideration will be given to the potential for significant effects following the completion of the Comparative Assessment studies and will be reported as part of the Environmental Statements.
D2.7 Atmospheric Emission Effects (energy use, climate change, air quality)
Emissions to air will occur as a result of vessel movements associated with subsea installations removal, topside removal, drill cuttings piles
All infrastructure Medium The greatest concern relates to the potential for emissions with global warming potential (GWP) and the contribution to climate change. Emissions with GWP anticipated as a result of Brae Area decommissioning activities include (but are not limited to) carbon dioxide (CO2) associated with vessel emissions. In addition nitrogen oxide (NOx) emissions associated with vessel emissions
Low
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
removal, jacket removal with implications for energy use.
can result indirectly in an increase in ozone (03) and nitrous oxide (N20), with GWP.
Preliminary Energy Use and Emissions calculations have been completed to inform the Comparative Assessment process (Xodus, 2014 (1)) and will be given due account within the Comparative Assessment decision making process. As such the potential to minimise emissions to As Low as Reasonable Practicable (ALARP) is already inherent within the DP. The comparative consideration given to ensure ALARP options in terms of Energy Use and Air Quality will also be documented within the Alternatives/Comparative Assessment section of the ESs. Overall, the potential emissions associated with decommissioning would represent a reduction in emissions relative to the normal operational emissions associated with operating the Brae Area platforms and infrastructure.
Localised air quality sensitive receptors in close proximity to the Brae Area are limited. Human receptors will be limited to offshore operators on vessels and/or nearby infrastructure. Ecological receptors would be limited to seabirds which would be transient through the area.
Contributions of the emissions would be at a local scale, within approximately 100m of the
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.2: Summary of Stage 2 Scoping
Reference (table 6.1 and 6.2)
Technical Study Area
Activity/receptor interaction
Infra- structure affected
Stage 1 effect category
Discussion Stage 2 effect category
source in addition, due to the offshore location and dominant wind climate (Beaufort 4 – 6) emissions would disperse rapidly.
All vessels will comply with MARPOL 73/78 Annex VI on air pollution; plant will comply with relevant air pollution regulations (The Offshore Combustion Installations (Prevention and Control of Pollution) (Amendment) Regulations 2007.
The potential for significant effect as a result of this activity/receptor interaction has therefore been scoped out of the EIA.
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Annex D3: Schedule of Mitigation Commitments
Marathon Oil UK LLC Brae Area Decommissioning
Scoping Report
UK12_21217_8 Ramboll Environ
Table D.3. Schedule of Scoping Stage Mitigation Commitments
Reference Activity/Receptor Interaction
Mitigation Commitment
Designated Sites/Species
Disturbance to biogenic reef forming species settled on hard surfaces during removal of jackets, footings, risers, pipelines, flowlines, umbilicals, power cables and other subsea installations.
An evaluation of available ROV footage of the Brae Area infrastructure has been completed. No evidence of biogenic reef forming organisms e.g. Lophelia spp has been identified on Brae Area infrastructure. Further pre-decommissioning survey to check for the presence of designated species would be completed prior to the decommissioning activities taking place.
Seabed disturbance
Disturbance to seabed during removal of footings, risers, pipelines, flowlines, umbilicals, power cables and other subsea installations, with resultant potential effects on benthic communities, natural seabed sediments and cuttings pile sediments. Disturbance may also occur during preparation for the footings to be left in situ.
Cutting and lifting operations associated with the removal of subsea infrastructure would be controlled by ROV to ensure accuracy in all activities and therefore minimise the potential for seabed sediment disturbance.
Underwater Noise
Topside preparation and removal and potential for vessel activity to affect noise sensitive species including seabirds, fish and marine mammals.
All equipment will be maintained to manufacturers’ specifications.
Number of vessels travelling or on standby in the Brae Area at any one time will be kept to a minimum.
Socioeconomic and Other Effects
Derogated footings presenting a long term hazard to demersal fisheries.
In the event of derogation the presence of the footings would be marked on relevant charts and communicated to other sea users through the normal communication channels (for example, FishSAFE).
The existing 500 m safety zone around each platform would be maintained.
Atmospheric Emission Effects
Emissions associated with vessel activity during decommissioning activities.
All vessels will comply with MARPOL 73/78 Annex VI on air pollution; plant will comply with relevant air pollution regulations (The Offshore Combustion Installations (Prevention and Control of Pollution) (Amendment) Regulations 2007.