Bridge 1-717: I-95 over SR7 Precast Panel Deck Replacement
Delaware Department of Transportation
Presented to: FHWA/DelDOT Accelerated Bridge Construction Workshop on September 17, 2015 Presented by: John Milius, PE AECOM
![Page 2: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/2.jpg)
Agenda
• Project Overview • Why use ABC? • ABC Superstructure Replacement Alternatives
Considered • Precast Panel Options Considered • Staging Alternatives Considered • Selected Deck Replacement Option • ABC Design Details • Questions
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 3: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/3.jpg)
Project Overview
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
• I-95 NB over SR7/SR1 – 4 travel lanes + entrance
ramp lane – Length ~ 208.5’ – 4 steel simple spans – Full depth deck
replacement needed
![Page 4: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/4.jpg)
Project Goals
• Replace bridge deck
• Update bridge barrier to meet AASHTO TL-4 requirements (currently TL-4 adjacent to structure)
• Minimize impacts to traffic
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 5: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/5.jpg)
Project Constraints
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Limited staging area adjacent to structure
![Page 6: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/6.jpg)
Why Accelerated Bridge Construction?
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
• I-95 is a key artery in Delaware (ADT = 85,000 in 2011)
• Traffic impacts must be minimized
BR 1-717
![Page 7: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/7.jpg)
ABC Superstructure Replacement Alternatives
• Only Steel Alternatives Considered – Existing Substructures to Remain – Vertical Clearance
• New Steel Girders w/ Pre-Fabricated Deck Sections
• Simple Spans vs. Continuous Span Options Explored
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 8: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/8.jpg)
ABC Superstructure Replacement Alternatives
• Longitudinal Launching
• Slide-In Construction
• Conventional Crane Construction – Modular Superstructure Segments (Inverset)
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 9: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/9.jpg)
Decision for Deck Replacement
• Existing Steel Beams in Good Condition – Recently Cleaned and Painted
• Replacement of superstructure would cause: – Likely need to strengthen or modify substructures – Subsequent increases in construction costs – Delay in construction schedule
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 10: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/10.jpg)
Precast Panel Options Considered
Panel Orientation
• Panels oriented in transverse direction (typical) – Not feasible due to skew angle and large width to span ratio of structure – For skews > 30 degrees, panel joints must be perpendicular to beams
• Panels oriented in longitudinal direction
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Full Depth Precast Concrete Deck Slabs. PCINER-02-FDPCDS. p. 6.
Transverse Panel Layout BR 1-717 Transverse Layout
![Page 11: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/11.jpg)
Precast Panel Options Considered Cont’d
Panel Orientation
• Panels oriented in transverse direction (typical) – Not feasible due to skew angle and large width to span ratio of structure
• Panels oriented in longitudinal direction
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Longitudinal Panel Layout
![Page 12: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/12.jpg)
Precast Panel Options Considered Cont’d
Deck Joint Considerations – Currently 4 Simple Spans with Joints over each Support – Deck Replacement Options:
• Install New Deck Joints (5 Deck Joints to Remain) • Provide Link Slab to Eliminate Deck Joints • Simple-Made-Continuous Steel Beams to Eliminate Deck Joints (Uplift at End Supports)
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 13: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/13.jpg)
Single Stage Alternative
MOT Considerations
• Provide cross-over to SB structure? – Not feasible given proximity of RT1 interchange.
• Half-width Construction – Additional Bridge Width Due to Ramp
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 14: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/14.jpg)
Dual Stage Alternative
MOT = Half-width Re-decking – Construction Staging = 2 Stages – 10 days per stage – Divide stages at girder line 20 – Maintain 3 lanes of traffic within each phase
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 15: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/15.jpg)
Dual Stage Alternative Cont’d
• Construction Stage Schedule Continued
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 16: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/16.jpg)
Selected Deck Replacement Option
• Panels run longitudinally and span across two bays
• UHPC joints utilized to reduce lap lengths
• Deck joints to be placed in field using blockouts
• Use of UHPC eliminates need for post-tensioning
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 17: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/17.jpg)
ABC Design Details - Panel Design
• Panels designed as typical CIP deck • Use of UHPC joints provides rebar continuity • Barrier precast onto exterior panels to expedite construction
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Design and Construction of Field-Cast UHPC Connections. FHWA-HRT-14-084. p. 28.
![Page 18: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/18.jpg)
ABC Design Details - Panel Joints
• 7” nominal joint width
• UHPC permits use of non-contact lap splices within joint
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Design and Construction of Field-Cast UHPC Connections. FHWA-HRT-14-084. p. 29.
![Page 19: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/19.jpg)
ABC Design Details - Panel to Girder Connection Details
• Panels connected through cast-in-place UHPC trough/joint
• Shear studs remain below rebar mat to avoid interference
• Panel elevation set by angles to avoid need for leveling screws
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
Ultra-High Performance Concrete Composite Connections for Precast Concrete Bridge Decks. FHWA-HRT-12-042. p. 5.
![Page 20: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/20.jpg)
ABC Design Details - Strip Seal Blockout Details
• Strip seals field cast into closure pours – Eliminates issues with alignment of extrusion – Closure pour required at diaphragms anyway – High early strength concrete used rather than UHPC to minimize
cost
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 21: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/21.jpg)
ABC Design Details - Deck Finish
• PPC (Polyester Polymer Concrete) Overlay Proposed
– Deck panels include additional ¼” of cover on top for grinding profile if necessary
– 1” PPC overlay provided on bridge deck to:
• Provide smooth riding surface • Protect concrete joints from water / chlorides infiltration • Adjust for final profile
DelDOT BR 1-717: I-95 over SR7 – Precast Panel Deck Replacement
![Page 22: Bridge 1-717: I-95 over SR7](https://reader031.vdocuments.net/reader031/viewer/2022012014/61595f93f0808357c3745b54/html5/thumbnails/22.jpg)
Questions & Answers