BrisBIM Gathering, August 2017BrisBIM
BIM IN TUNNELLING BIM information content management for major underground projects
Martin Lah
BIM Implementation planning
„Behind the Scenes“
Content
▪ Strategy (Austria, Slovenia)
▪ EIR, BEP (Roles, processes, LOD, IT infrastructure)
Start of activities: 2014 2016
No. of involved companies: 9 3
No. of partial models: 160 29
3D BIM and Coordination:
4D BIM:
5D BIM:
6D BIM:
LoD: 300 - 400 300
LoI: 400 500
Summary of BIM related activities
INFRA BIM DATA
STRUCTURE
Research project
IFC INFRAIFC ROAD
IFC RAIL
IFC BRIDGE
IFC TUNNEL
PLATFORM 4.0ASI, ÖBV, OIAV, FMA
BIM PILOT PROJECTSINFRASTRUCTURE, TUNNELLING
GR
AN
ITZT
AL
TUN
NEL
RA
ILW
AY
STAT
ION
LA
VA
NTA
L
KARAVANKE TUNNEL
DesignConstruction
TRADITIONAL APPROACH
BIM METHODOLOGY
Operation
3D BIM, Coordination
6D BIM
EIR, BEP
The StrategyAUSTRIAN SIDE
The StrategySLOVENIAN SIDE
KARAVANKE TUNNEL
TRADITIONAL APPROACH
BIM METHODOLOGY
Operation
3D BIM(Design team)
BIM STRATEGY, EIR
Execution
4D, 5D BIM(Design team)
4D, 5D BIM (Contractor)
3D BIM(Design team)
?
4D, 5D BIM(Supervision)
BIM EXECUTION PLAN (BEP)
Projectassignment
Design phase
BIM COORDINATION
BIM implementation planning – EIR, BEP
▪ Identification of project goals and BIM Uses
▪ Project organization (BIM specific roles)
▪ Definition of processes for identified BIM uses
▪ LOD Definitions (LoD, LoI, LoC)
▪ Collaboration protocol
▪ Quality control
▪ IT infrastructure
▪ Modelling guidelines
▪ BIM Deliverables
Project organization
BIM Manager
BIM Overall coordination
BIM Discipline/Trade
coordination
Definition of processes
Input data Process
Project phase
Responsible party
Reference to detailed process maps
Output data
▪ BIM Overview process map
▪ Detailed process maps for each BIM Use (BIM Coordination, Revision, QTO, 4D, 5D, etc.
Definition of processes (BIM Coordination)
LOD Definitions
LOD Definitions (DARS)
LODsElements Responsibility Attributes
LOD Definitions (DARS) IFC TUN Data Structure (ASFINAG)
IFC Rail – ChinaIFC Road – KoreaIFC Infra OverallArchitecture
+
=
Partial ModelsElementsAttributes
bSI RAIL/ROAD comparisonPROF. BORRMANN TU München
IFC TUN Data Structure (Implementation to IFC 2x3)
bSI INFRA OVERALL ARCHITECTURE (Spatial elements)
3 „Classification“ attributes (TUNNEL)
▪ Discipline: TUNN
▪ Element: IfcInnerlining
▪ Type: ABUTMENT
Currently 478 unique elements are defined
IfcBeam
IfcBeamIfcBeam
IfcBeamIfcBeam
?
Are we using OPEN BIM or CLOSED BIM approach?
IFC, BCF
CLOSED BIMUse only
CLOSED BIMUse only
CLOSED BIMUse only
IT infrastructure
CLOSED BIM
CLOSED BIM