britannia mine remediation project water...

54
BRITANNIA MINE REMEDIATION PROJECT Water Management Gerry O’Hara P.Eng., Golder Associates Ltd Dr. Ross Hammett, P.Eng., Golder Associates Ltd

Upload: others

Post on 24-Mar-2020

15 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

BRITANNIA MINE REMEDIATION PROJECT Water Management

Gerry O’Hara P.Eng., Golder Associates LtdDr. Ross Hammett, P.Eng., Golder Associates Ltd

Page 2: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Overview of the Britannia Mine Remediation ProjectBackgroundSummary of environmental problems at BritanniaProvince’s remediation concept

Water Management – the Key to RemediationSurface waterMine waterGroundwater

Lessons Learned/Next StepsQuestions

Scope of Presentation

Page 3: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Where and What is Britannia?

– Located on Sea-to-Sky Hwy– Copper Mine from 1904 to 1974– Was the ‘Largest copper mine in British Empire’– Ore produced: 48 million tonnes

Page 4: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Porteau Cove

Furry Creek

Victoria Camp

Jane Basin

Britannia Creek

Britannia Beach

Howe Sound

Page 5: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

4100 L

2700L

4100 Portal

4100 Plug

Mineral Creek

Britannia Creek

Howe Sound

Britannia Beach #10 Shaft

Victoria Shaft

3D Cutaway of Britannia Mine

2200 Portal

2700 Portal

Jane Basin

Mine Levels defined in feet measureddownwards from highest elevation in mine

Page 6: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

What’s the Problem?Naturally occurring metal sulphide orebody

Many underground openings

Massive disturbance of rock from historical mining

Most of the workings not permanently flooded

Almost unrestricted flow of surface drainage into workings

Mining voids convey water to 4100 Level

“The largest point source of metal pollution in North America discharging to a marine environment”

Page 7: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

What’s the Problem?Issues:

~5million m3/year ARD from mine workings copper, zinc, cadmium, pH~3.5

Metal-contaminated groundwater discharging to Howe Sound:

Alluvial Fan of Britannia CreekWaste dump leaching

Metal-contaminated surface water (run-off)Impact of aquatic life in Howe Sound and local waterways:

Squamish River salmon run

Page 8: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Howe Sound

Howe Sound Metal Loading Estimates

(URS, 2002)

Furry Creek: ~1kg/d Cu, ~1kg/d Zn)

Additional Areas: ~4kg/d Cu, ~5kg/d Zn

Mine Discharge: ~3kg/d Cu, ~4kg/d Zn

2200 L Tunnel

4100 L Tunnel

Mine Discharge: ~293kg/d Cu, ~287kg/d Zn

Outfall

Groundwater: ~10kg/d Cu, ~16kg/d Zn

Page 9: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Howe Sound

Remedial Concepts

2200 L Tunnel

4100 L Tunnel

Outfall

Prevention:Inflow diversion

Collection:2200 Level Plug

Management:Contaminated wasterock and groundwater

Additional Areas: ~4kg/d Cu, ~5kg/d Zn

Mine Discharge: ~3kg/d Cu, ~4kg/d Zn

Mine Discharge: ~293kg/d Cu, ~287kg/d Zn

Groundwater: ~10kg/d Cu, ~16kg/d Zn

Use of mine void as storage/balancing reservoir

Plug with control valveTreatment: Mine drainage

Management: Contaminated groundwater

Risk Management: Tailings (Env. Can.)

Page 10: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Water ManagementManagement of mine water, groundwater & surface water:

Key to the Province’s remediation plan for the siteThree main components:

Reduce volume of clean water becoming contaminated:• In the mine• In surface water courses

Capture and treat contaminated groundwater to prevent its discharge to the shallow marine environmentManage mine water storage to allow efficient treatment (and generate micro-hydro power)

Page 11: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Surface Water Diversions80% of mine water enters through the open pits in Jane Basin (SRK study)Three catchment areas had the potential for partial diversion of surface flows:

Likely that the diversions would be most effective at ‘shaving’ the peak inflows during freshet and summer/fall rainstorm eventsUp to 15% of the mine inflow had the potential to be captured and diverted as clean waterCost benefits

Three diversions constructedUpper Jane CreekEast BluffVictoria

Page 12: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Jane Basin

Upper Jane Creek

East Bluff

Lower Jane Creek

Fairview Pits/Glory Holes

East BluffGlory Hole

Jane Glory Hole

Page 13: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water
Page 14: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water
Page 15: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Surface runoff direction

Upper Jane CreekIntake Structure

Discharge to LJC Discharge to Talus Slope

Jane C

reek

Energy Dissipater

East Bluff Intake Pond

Diversion Pipe

Surface Water Diversions

Victoria GloryHole Diversion

Jane Basin

Page 16: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Jane Basin

Upper Jane Creek

Pipes

Collection Pond

East Bluff Diversion

Lower Jane Creek

Energy Dissipater

Intake Structure

Page 17: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Surface Water Diversions

Upper Jane Creek Diversion

Intake Structure

Pipe Bundle

Energy Dissipator Chamber

Page 18: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

East Bluff Diversion Performance

Water treatment cost savings ~$35,000/annumPayback in treatment costs ~6 years

Page 19: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Water Treatment PlantTreat mine water and groundwaterDesign capacity - 1,050m3/hr Hydraulic capacity - 1,400m3/hrProvince opted for a Design-Build-Finance-Operate (DBFO) contract in a Public Private Partnership:

Single entity responsible to design, build, operate and finance plantProvince pays periodic operating fee when discharge within permit limitsContract includes 20 year operation

Page 20: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Water Treatment PlantSelected contractor (EPCOR)

HDS technologyCommitted to reviewing alternates for future

Construction commenced March 3, 2005First water treated (24hr operation) October 20, 2005, Tests up to 1,400m3/hr (~400L/s) indicate successful treatment

Page 21: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir ManagementWTP capacity based on estimated mine inflows and reservoir modellingMine inflows estimated for 25 year period using:

Records of historical mine outflows Simulations and correlations linked to historical meteorological data (‘UBC watershed model’ applied by SRK)

Page 22: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Estimated Total Inflows to Mine (including flows that reported to 2200 level)

0

200

400

600

800

1000

1200

1977

Jan

01

1978

Jan

01

1979

Jan

01

1980

Jan

01

1980

Dec

31

1981

Dec

31

1982

Dec

31

1983

Dec

31

1984

Dec

30

1985

Dec

30

1986

Dec

30

1987

Dec

30

1988

Dec

29

1989

Dec

29

1990

Dec

29

1991

Dec

29

1992

Dec

28

1993

Dec

28

1994

Dec

28

1995

Dec

28

1996

Dec

27

1997

Dec

27

1998

Dec

27

1999

Dec

27

2000

Dec

26

2001

Dec

26

Month

Min

e In

flow

(L/s

)

Mine InflowsDesign CapacityHydraulic Capacity

Estimate Of Mine Inflows Over 25 YearsM

ine

Inflo

w L

/s

25 Year Record

Design Capacity

Hydraulic Capacity

Page 23: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Estimate Of Mine Inflows Over 25 YearsEstimated Total Inflows to Mine (including flows that reported to 2200 level)

0

200

400

600

800

1000

1200

1977

Jan

01

1978

Jan

01

1979

Jan

01

1980

Jan

01

1980

Dec

31

1981

Dec

31

1982

Dec

31

1983

Dec

31

1984

Dec

30

1985

Dec

30

1986

Dec

30

1987

Dec

30

1988

Dec

29

1989

Dec

29

1990

Dec

29

1991

Dec

29

1992

Dec

28

1993

Dec

28

1994

Dec

28

1995

Dec

28

1996

Dec

27

1997

Dec

27

1998

Dec

27

1999

Dec

27

2000

Dec

26

2001

Dec

26

Month

Min

e In

flow

(L/s

)

-500

0

500

1000

1500

2000

2500

3000

3500

4000

4500

SWE

(mm

)

Mine InflowsDesign CapacityHydraulic CapacitySWE

Min

e In

flow

L/s

25 Year Record

Snow Pack

Inflow as a result of rainfall

Design Capacity

Hydraulic Capacity

Page 24: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir ManagementGoal: to minimize number and duration of by-pass events, with paramount importance placed on preventing overtopping of the mine reservoir (uncontrolled discharge)

Potential uncontrolled discharge at 3250 Level

4100 Level

Page 25: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir ManagementTests in 2002 & 2004 by SRK confirmed/indicated:

Approximately 430,000m3 of ‘dynamic’ storage available between 4100 Level and 3250 Level Some restrictions to flow that change with time and discharge rate:

Possibly the result of silting-up/release of sediments, and/or debris accumulation and release

The mine is a dynamic system that is subject to change over time:

Internal flow regime may change from the time to timeContingencies considered and engineering concepts developed for problems that may develop

Water chemistry changes with storageEffect reduces with reservoir operation

Page 26: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir Management

Storage 1000 m3

Wat

er L

evel

In M

ine

m

~ 430,000m3 ‘dynamic’storage available

Page 27: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir ManagementReservoir Operation Simulation

Proposed reservoir operating plan• Design Capacity - 1050 m3/hr• Hydraulic Capacity - 1400 m3/hr• Maximum possible flow through Plug – 3276 m3/hr• Up to 1400 m3/hr released through plug when available from

0-150m head in mine• Release rate increased quickly up to 3276 m3/hr from >150m

head in minePercentage of outflow by-passed/untreated by WTP –96.9%

Page 28: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

0

200

400

600

800

1000

1200

1977

Jan

01

1978

Jan

01

1979

Jan

01

1980

Jan

01

1981

Jan

01

1982

Jan

01

1983

Jan

01

1984

Jan

01

1985

Jan

01

1986

Jan

01

1987

Jan

01

1988

Jan

01

1989

Jan

01

1990

Jan

01

1991

Jan

01

1992

Jan

01

1993

Jan

01

1994

Jan

01

1995

Jan

01

1996

Jan

01

1997

Jan

01

1998

Jan

01

1999

Jan

01

2000

Jan

01

2001

Jan

01

2002

Jan

01

Date

Dai

ly O

utflo

w R

ate

(L/s

)

0

500

1000

1500

2000

2500

3000

3500

4000

Dai

ly O

utflo

w R

ate

(m3 /h

r)

WTP

Plug Capacity

Design Capacity

Hydraulic Capacity

Mine Reservoir SimulationM

ine

Inflo

w L

/s

25 Year Record

By-pass – untreated by WTP, though pH adjusted to precipitate metals

Water treated by WTP

Page 29: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

0

50

100

150

200

250

1977

Jan

01

1978

Jan

01

1979

Jan

01

1980

Jan

01

1981

Jan

01

1982

Jan

01

1983

Jan

01

1984

Jan

01

1985

Jan

01

1986

Jan

01

1987

Jan

01

1988

Jan

01

1989

Jan

01

1990

Jan

01

1991

Jan

01

1992

Jan

01

1993

Jan

01

1994

Jan

01

1995

Jan

01

1996

Jan

01

1997

Jan

01

1998

Jan

01

1999

Jan

01

2000

Jan

01

2001

Jan

01

2002

Jan

01

Date

Wat

er le

vel i

n m

ine

(m)

Mine Reservoir SimulationW

ater

Lev

el In

Min

e m

25 Year Record

No overtopping

In 1999 1:50 year event

Page 30: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Penstock

4150 Level Portal

By-Pass Line

Page 31: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Micro-hydro Plant

Page 32: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Mine Reservoir ManagementWater Treatment Plant

Page 33: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Discharge PermitPermit discharge limits (dissolved, mg/L) :

copper ≤ 0.1iron ≤ 0.1zinc ≤ 0.2aluminium ≤ 1manganese ≤ 0.4cadmium ≤ 0.01total suspended solids ≤ 30

No overtopping predicted for 25 year history and 1:200 mine inflow eventPermit acknowledges controlled by-passes as ‘emergency conditions’

Predicted ~3% of outflow will be by-passedUntreated but pH adjusted to precipitate metals mixed with fully-treated water: blended water discharged to deep outfall/diffuser

Page 34: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

WTP Discharge QualityParameter (mg/L) Permit Limit Plant (July 2006)

dissolved copper ≤ 0.1 < 0.005dissolved iron ≤ 0.1 < 0.005dissolved zinc ≤ 0.2 0.008dissolved aluminium ≤ 1 0.61dissolved manganese ≤ 0.4 0.265dissolved cadmium ≤ 0.01 < 0.002total suspended solids ≤ 30 < 4

- - - - - - - - - - - - - - - - - - - - - - - - - -pH range 6.5 to 9.5 8.696HRLC50 fish bioassay 100% (non-acutely toxic) 100%Authorized discharge 25,200m3/day 24,200m3/day

Page 35: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

New Deep OutfallOld outfall extends to only 26 metres depth

- Is located on unstable sub-sea terrain- Susceptible to blockages

Requires 50 m depth and diffuser to meet receiving environment criteriaGeotechnically stable location required to reduce risk of future failures:

- Cost of replacement- Environmental effects

Site selected south of Britannia Beach

Page 36: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

WTP Outfall

New Outfall Under Construction

Diffuser

Page 37: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Fan Area Surface Water Management• Storm water system

upgraded in 2003/4 to divert most run-off away from beach;

• Assessment underway to identify further improvements;

• Proposed actions include:– Diversion of

streams from leachable mine waste on Mill slope;

– Collection of mine water seepage from West Mill slope.

Leaching waste rock

Page 38: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Fan Area Groundwater Management

Modelling (Feflow)

Page 39: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Fan Area Groundwater Remedial OptionsOperational Constraints:

Saline water corrosive to treatment plant components/may affect processCapacity and Operational requirements of treatment plant:

- Limit pumping rate (100m3/hr)- Limit chlorides concentration (1000ppm)

Physical constraints on system installation:- Hwy99- BCRail

Page 40: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

GMS System Design

Pumping Wells

Monitoring Wells

BC Rail Line

Page 41: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Groundwater Management StatusSystem constructed by EPCOR between March and May, 2005Pumping trials commenced in May, 2005System operational and currently in optimization phase:– Correlation of chlorides to conductivity– Maximise (fresh) groundwater capture

efficiency within design constraints and minimise salt water pumping

– Identify control and/or installation improvements

Page 42: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Groundwater pump installation

Groundwater pumphouse

Wellhead installation

Page 43: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Groundwater Management System

Transfer Pumps

Flow monitoring equipment

Page 44: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Phase 1 – Operation DataElectrical Conductivity (mS/cm) Before of Pumping

1.5 5.54.5

4.3

15.1

28.6

2.6

20 40 60 80 100 120-20

-10

0

10

EX04-4 EX-3EX-1

MW01-21I

MW01-21D

MW01-21DD

MW01-22

E W

South Fan Howe Sound

Saltwater Interface

Page 45: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Phase 1 – Operation Data

7.7 9.46.0

8.1

15.4

28.9

4.8

20 40 60 80 100 120-20

-10

0

10

EX04-4 EX-3EX-1

MW01-21I

MW01-21D

MW01-21DD

MW01-22

E W

South Fan Howe Sound

Saltwater Interface

Electrical Conductivity (mS/cm) End of Pumping

Page 46: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

July 7, 2005 Capture ZoneQtotal = 1339 m3/day

Phase 1 System Performance

Mill

Howe Sound

Hw

y99High pumping rate (system controlled byflowrate set point):• Very high capture efficiency of plume• High salinity (>1000ppm chlorides)

Page 47: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

August 10, 2005 Capture ZoneQtotal = 567 m3/day

Phase 1 System Performance

Mill

Howe Sound Hw

y99

Lower pumping rate (system controlled bysalinity set point):• ~50% capture of plume, system inefficientat northern end of array due to higherpermeability zone and connection to HoweSound• Low salinity (<1000ppm chlorides)

Page 48: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Capture zone with 1 new well.

Phase 2 System Optimization

Mill

Howe Sound

Hw

y99• Higher plume capture efficiency• Reduced saline intrusion but>1000ppm for >90% plume capture

Page 49: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Capture zone with 2 new wells.

Phase 2 System Optimization

Mill

Howe Sound

Hw

y99• Still higher plume capture efficiency• Further reduced saline intrusion(<1000ppm for >90% plume capture)

Page 50: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

2006 GMS Monitoring Data

Page 51: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Howe Sound

Howe Sound Metal Loading Improvements

Furry Creek: ~1kg/d Cu, ~1kg/d Zn)

Additional Areas: ~4kg/d Cu, ~5kg/d Zn

Mine Discharge: ~3kg/d Cu, ~4kg/d Zn

2200 L Tunnel

4100 L Tunnel

Mine Discharge:~293kg/d Cu, ~287kg/d Zn

Old outfall

Groundwater: ~10kg/d Cu, ~16kg/d Zn

~4kg/d Cu, ~5kg/d Zn

0 kg/d Cu, 0 kg/d Zn

<0.07kg/d Cu, <0.1kg/d Zn

New deep outfall with diffuser

<2kg/d Cu, <2kg/d Zn

Improvements planned to groundwaterand surface water management

Page 52: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Some Lessons LearnedCost benefit of surface water diversions must be balanced against desirability of undertaking this for long-term ‘sustainability’ or other reasonsThe availability of the mine reservoir greatly benefited the project, though efficient management is criticalAutomated groundwater management of the saline/freshwater blend linked to the WTP control systems needed a long period of optimization (>2 years)

Page 53: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Ongoing Water Management WorkAdditional Areas Review/Implementation

Other portal seepsWaste dump seeps

Environmental Monitoring and Risk AssessmentHave we done enough/do we need to do more/

if so, what?Surface Water Drainage Review/Implementation

4100 Level and Britannia Creek Fan AreaGroundwater Management Optimization

Program will continue following planned system enhancements

Page 54: BRITANNIA MINE REMEDIATION PROJECT Water Managementbc-mlard.ca/files/presentations/2006-22-OHARA-HAMMETT-britannia-mine-remediation-water...BRITANNIA MINE REMEDIATION PROJECT Water

Province’s website (MAL):– www.britanniamine.ca– Contains progress reports, technical reports, regulatory

correspondence, permits, background information, contact detailsand correspondence with Province

Information Sources

Questions?