brito3 presentation
TRANSCRIPT
-
7/18/2019 Brito3 Presentation
1/36
International Seminar on Tunnels and Underground Works
Jos A. Mateus de Brito,[email protected]
Carlos de Oliveira Baio,[email protected]
Antnio C. Ambrsio,[email protected]
TUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION IN
MADEIRA ISLANDMADEIRA ISLANDMADEIRA ISLANDMADEIRA ISLAND
SocorridosSocorridosSocorridosSocorridos pumping station andpumping station andpumping station andpumping station and
water storage tunnelwater storage tunnelwater storage tunnelwater storage tunnel
-
7/18/2019 Brito3 Presentation
2/36
International Seminar on Tunnels and Underground Works
MADEIRA ISLAND
-
7/18/2019 Brito3 Presentation
3/36
International Seminar on Tunnels and Underground Works
(5,5m wide)(7m wide)
Pumping station
Hydroelectric plant
Stream
Access tunnelStorage tunnel
-
7/18/2019 Brito3 Presentation
4/36
International Seminar on Tunnels and Underground Works
Sediment
evacuation channel Main channel
Penstock
Hydroelectric plant
Access tunnel
Pumping station
Storage tunnel
Stream
-
7/18/2019 Brito3 Presentation
5/36
International Seminar on Tunnels and Underground Works
12,5 m
26,5
mAccesstunnel
Pumpingstation
Storagetunnel
Temporaryrockfill
Mainchannel
Sedimentevacuation channel
4 pumps (16 mhigh): 40.000 m3
raised in 6h by the
existing penstock
(460m)
Sediment traps
Existingpenstock
-
7/18/2019 Brito3 Presentation
6/36
International Seminar on Tunnels and Underground Works
Jul.05
-
7/18/2019 Brito3 Presentation
7/36
International Seminar on Tunnels and Underground Works
GEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICAL
CHARACTERISTICSCHARACTERISTICSCHARACTERISTICSCHARACTERISTICS
GEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICAL
CHARACTERISTICSCHARACTERISTICSCHARACTERISTICSCHARACTERISTICS
-
7/18/2019 Brito3 Presentation
8/36
International Seminar on Tunnels and Underground Works
Consolidated alluvia
(pumping station roof)
Breccia(side and front walls)
- Laboratory tests:(rock material)
.Uniaxial compression Compressive
strength
Deformabilitymodulus
Poissons ratio
.Unit weight
.Porosity
- Field tests:(rock mass)
.Boreholes (76mm) Lugeon tests Dilatometer tests
.Test pits (penstockalignment)
-
7/18/2019 Brito3 Presentation
9/36
International Seminar on Tunnels and Underground Works
CONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHOD
AND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEM
CONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHOD
AND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEM
-
7/18/2019 Brito3 Presentation
10/36
International Seminar on Tunnels and Underground Works
First forepole umbrella:
Schedule 73mm (12 m)Hill consolidation:shotcrete (10 cm), steel-wire mesh and soil nails
-
7/18/2019 Brito3 Presentation
11/36
International Seminar on Tunnels and Underground Works
Hill consolidation and executionof the first forepole umbrella
Jan.05
Feb.05
-
7/18/2019 Brito3 Presentation
12/36
International Seminar on Tunnels and Underground Works
Mar.05
-
7/18/2019 Brito3 Presentation
13/36
International Seminar on Tunnels and Underground Works
First forepole
umbrella
Pilot tunnelandPrimarysupportexecution
-Roofs primary support:
.Forepole umbrellas(3x12 m) - SCH 73 mm
.Steel ribs HEB200 // 1 m
.Shotcrete reinforcedwith steel fibers (20 cm)
.Steel wire-meshreinforcement (AQ50).
-
7/18/2019 Brito3 Presentation
14/36
International Seminar on Tunnels and Underground Works
Apr.05
Mar.05
Pilot tunnel
-
7/18/2019 Brito3 Presentation
15/36
International Seminar on Tunnels and Underground Works
Execution of cavernsroof:right side
Execution ofcaverns roof:
left side
Elephant feet(1stlevel)
-Roofs primary support:
.Forepole umbrellas(3x12 m) - SCH 73 mm
.Steel ribs HEB200 // 1 m
.Shotcrete reinforcedwith steel fibers (20 cm)
.Steel wire-meshreinforcement (AQ50).
-
7/18/2019 Brito3 Presentation
16/36
International Seminar on Tunnels and Underground Works
Apr.05
May05
Execution of caverns roof(right and left sides)
-
7/18/2019 Brito3 Presentation
17/36
International Seminar on Tunnels and Underground Works
Execution of caverns roof:conclusion
Elephant feet(2ndlevel)
-Roofs primary support:
.Forepole umbrellas(3x12 m) - SCH 73 mm
.Steel ribs HEB200 // 1 m
.Shotcrete reinforcedwith steel fibers (20 cm)
.Steel wire-meshreinforcement (AQ50).
Rockbolts(at thebase of the steel ribs)
-
7/18/2019 Brito3 Presentation
18/36
International Seminar on Tunnels and Underground Works
Apr.05
May05
Conclusion of cavernsroof execution
-
7/18/2019 Brito3 Presentation
19/36
International Seminar on Tunnels and Underground Works
-Wallss primary support:
.Rockbolts: SuperSwellex(6 m) Mesh 1,5 m x 2 m
.Self-drilling anchors (9 m)MAI R38 Mesh 1,5 m x 2 m
.Shotcrete reinforcedwith steel fibers (20 cm)
Downwards execution ofcaverns walls
-
7/18/2019 Brito3 Presentation
20/36
International Seminar on Tunnels and Underground Works
Jun.05
-
7/18/2019 Brito3 Presentation
21/36
International Seminar on Tunnels and Underground Works
-
7/18/2019 Brito3 Presentation
22/36
International Seminar on Tunnels and Underground Works
NUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THE
FINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHOD
NUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THE
FINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHOD
-
7/18/2019 Brito3 Presentation
23/36
International Seminar on Tunnels and Underground Works
Alluvia:
.E = 1,0 GPa; = 0,38
.= 21 kN/m3
.c = 60 kPa; = 32
Breccia:
.E = 1,5 GPa; = 0,38
. = 22 kN/m3
.c = 80 kPa; = 36
-
7/18/2019 Brito3 Presentation
24/36
International Seminar on Tunnels and Underground Works
-3D analysis (using Plaxis):
.Total of142phases
.Mesh with29.000elements
. Rock mass: Elastoplastic (Mohr-Coulomb)
. Forepoles: Linear elastic (solid elements)
. Shotcrete: Linear elastic (plate elements)
. Rockbolts: Linear elastic (geogrid elements)
-
7/18/2019 Brito3 Presentation
25/36
International Seminar on Tunnels and Underground Works
Principal stresses Plastic points Vertical displacements
-
7/18/2019 Brito3 Presentation
26/36
International Seminar on Tunnels and Underground Works
INSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATION
AND OBSERVATIONAND OBSERVATIONAND OBSERVATIONAND OBSERVATION
INSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATION
AND OBSERVATIONAND OBSERVATIONAND OBSERVATIONAND OBSERVATION
-
7/18/2019 Brito3 Presentation
27/36
International Seminar on Tunnels and Underground Works
-Instrumentation in 6 cross sections;
-For the 2 main cross sections (P2 e P4):.2 inclinometers (average depth of 50 m);.6 vertical extensometers (in 3 holes);.12 horizontal extensometers (in 4 holes).
-For all cross sections:
.5 survey targets on the ground surface;
.Convergence meters (7 reading points in the
roof and 2 points at the sidewalls).
-On the pumping stations front wall:
.5 survey targets placed on the wall (5 levels,
in about 2/3 of the pumping stations height).
-In the hydroelectric plant:
.1 portable seismograph.
-
7/18/2019 Brito3 Presentation
28/36
International Seminar on Tunnels and Underground Works
B
6.00
9.00
12.00
1.80
2.002.00
7.80
0.50
0.50
0.50
0.50
0.50
CFI
H
D
E
A
GJ
KLM
NOP
P.V. - E0P.V. - E1P.V. - E2
I1
2.00
5.00
9.75
Galeriapiloto
Alargamento
s
Destroadir.
Destroaesq
.
Rebaixo1
Rebaixo2
Rebaixo3
Rebaixo4
Rebaixo5
Rebaixo6
-10,0
-9,0
-8,0
-7,0
-6,0
-5,0
-4,0
-3,0
-2,0
-1,0
0,0
1,0
Desloc
.verticais-PontoC(mm)
Galeriapiloto
Alargamentos
Destroadir.
Destroaesq.
Rebaixo1
Rebaixo2
Rebaixo3
Rebaixo4
Rebaixo5
Rebaixo6
-10,0
-9,0
-8,0
-7,0
-6,0
-5,0
-4,0
-3,0
-2,0
-1,0
0,0
1,0
Desloc.verticais-PontoB(mm)
VERTICAL EXTENSOMETERS
AT THE ROOFS AXIS
Plaxis 3D
Plaxis 2D
Alert
criteria
Observation(cross section P2)
Observation(cross section P4)
Pumping
stations axis
-
7/18/2019 Brito3 Presentation
29/36
International Seminar on Tunnels and Underground Works
REINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LINING
AND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURES
REINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LINING
AND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURES
-
7/18/2019 Brito3 Presentation
30/36
International Seminar on Tunnels and Underground Works
Pumps (16 m high)
Access
tunnel
Crane
Storagetunnel
-
7/18/2019 Brito3 Presentation
31/36
International Seminar on Tunnels and Underground Works
-
7/18/2019 Brito3 Presentation
32/36
International Seminar on Tunnels and Underground Works
Jun.05
Jul.05
Sept.05
-
7/18/2019 Brito3 Presentation
33/36
International Seminar on Tunnels and Underground Works
Mar.06Sept.05
-
7/18/2019 Brito3 Presentation
34/36
International Seminar on Tunnels and Underground Works
Mar.06
-
7/18/2019 Brito3 Presentation
35/36
International Seminar on Tunnels and Underground Works
CONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKS
-
7/18/2019 Brito3 Presentation
36/36
International Seminar on Tunnels and Underground Works
- The geological / geotechnical characterization included 20 dilatometer tests, very im-portant to determine the geological formations deformability characteristics it wasessential to obtain reliable parameters to the models used in the caverns design;
- The existence of a thick consolidated alluvia deposit around the pumping stationsroof, in all its length, had great importance in the construction methods and to theprimary supports that were considered;
- Important dimensions of the cavern height of 26,5 m and width of 12,5 m;
- The cavern is located at the hills toe justification to a 3D analysis, using the finiteelement method; 2D analysis were also carried out, as well as parametric analysis;
- The existing penstock was always functioning (water supply to Funchal) it had tobe protected to support the temporary rockfill and to allow vehicle passage;
- The instrumentation was defined in order to follow permanently the displacements
evolution, with the results being daily analysed the design predictions revealed agood adjustment to the observed displacements;
- Demanding design and construction schedules and deadlines.