brito3 presentation

Upload: ray-chan

Post on 14-Jan-2016

2 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/18/2019 Brito3 Presentation

    1/36

    International Seminar on Tunnels and Underground Works

    Jos A. Mateus de Brito,[email protected]

    Carlos de Oliveira Baio,[email protected]

    Antnio C. Ambrsio,[email protected]

    TUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION INTUNNEL DESIGN AND CONSTRUCTION IN

    MADEIRA ISLANDMADEIRA ISLANDMADEIRA ISLANDMADEIRA ISLAND

    SocorridosSocorridosSocorridosSocorridos pumping station andpumping station andpumping station andpumping station and

    water storage tunnelwater storage tunnelwater storage tunnelwater storage tunnel

  • 7/18/2019 Brito3 Presentation

    2/36

    International Seminar on Tunnels and Underground Works

    MADEIRA ISLAND

  • 7/18/2019 Brito3 Presentation

    3/36

    International Seminar on Tunnels and Underground Works

    (5,5m wide)(7m wide)

    Pumping station

    Hydroelectric plant

    Stream

    Access tunnelStorage tunnel

  • 7/18/2019 Brito3 Presentation

    4/36

    International Seminar on Tunnels and Underground Works

    Sediment

    evacuation channel Main channel

    Penstock

    Hydroelectric plant

    Access tunnel

    Pumping station

    Storage tunnel

    Stream

  • 7/18/2019 Brito3 Presentation

    5/36

    International Seminar on Tunnels and Underground Works

    12,5 m

    26,5

    mAccesstunnel

    Pumpingstation

    Storagetunnel

    Temporaryrockfill

    Mainchannel

    Sedimentevacuation channel

    4 pumps (16 mhigh): 40.000 m3

    raised in 6h by the

    existing penstock

    (460m)

    Sediment traps

    Existingpenstock

  • 7/18/2019 Brito3 Presentation

    6/36

    International Seminar on Tunnels and Underground Works

    Jul.05

  • 7/18/2019 Brito3 Presentation

    7/36

    International Seminar on Tunnels and Underground Works

    GEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICAL

    CHARACTERISTICSCHARACTERISTICSCHARACTERISTICSCHARACTERISTICS

    GEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICALGEOLOGICAL AND GEOTECHNICAL

    CHARACTERISTICSCHARACTERISTICSCHARACTERISTICSCHARACTERISTICS

  • 7/18/2019 Brito3 Presentation

    8/36

    International Seminar on Tunnels and Underground Works

    Consolidated alluvia

    (pumping station roof)

    Breccia(side and front walls)

    - Laboratory tests:(rock material)

    .Uniaxial compression Compressive

    strength

    Deformabilitymodulus

    Poissons ratio

    .Unit weight

    .Porosity

    - Field tests:(rock mass)

    .Boreholes (76mm) Lugeon tests Dilatometer tests

    .Test pits (penstockalignment)

  • 7/18/2019 Brito3 Presentation

    9/36

    International Seminar on Tunnels and Underground Works

    CONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHOD

    AND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEM

    CONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHODCONSTRUCTION METHOD

    AND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEMAND PRIMARY SUPPORT SYSTEM

  • 7/18/2019 Brito3 Presentation

    10/36

    International Seminar on Tunnels and Underground Works

    First forepole umbrella:

    Schedule 73mm (12 m)Hill consolidation:shotcrete (10 cm), steel-wire mesh and soil nails

  • 7/18/2019 Brito3 Presentation

    11/36

    International Seminar on Tunnels and Underground Works

    Hill consolidation and executionof the first forepole umbrella

    Jan.05

    Feb.05

  • 7/18/2019 Brito3 Presentation

    12/36

    International Seminar on Tunnels and Underground Works

    Mar.05

  • 7/18/2019 Brito3 Presentation

    13/36

    International Seminar on Tunnels and Underground Works

    First forepole

    umbrella

    Pilot tunnelandPrimarysupportexecution

    -Roofs primary support:

    .Forepole umbrellas(3x12 m) - SCH 73 mm

    .Steel ribs HEB200 // 1 m

    .Shotcrete reinforcedwith steel fibers (20 cm)

    .Steel wire-meshreinforcement (AQ50).

  • 7/18/2019 Brito3 Presentation

    14/36

    International Seminar on Tunnels and Underground Works

    Apr.05

    Mar.05

    Pilot tunnel

  • 7/18/2019 Brito3 Presentation

    15/36

    International Seminar on Tunnels and Underground Works

    Execution of cavernsroof:right side

    Execution ofcaverns roof:

    left side

    Elephant feet(1stlevel)

    -Roofs primary support:

    .Forepole umbrellas(3x12 m) - SCH 73 mm

    .Steel ribs HEB200 // 1 m

    .Shotcrete reinforcedwith steel fibers (20 cm)

    .Steel wire-meshreinforcement (AQ50).

  • 7/18/2019 Brito3 Presentation

    16/36

    International Seminar on Tunnels and Underground Works

    Apr.05

    May05

    Execution of caverns roof(right and left sides)

  • 7/18/2019 Brito3 Presentation

    17/36

    International Seminar on Tunnels and Underground Works

    Execution of caverns roof:conclusion

    Elephant feet(2ndlevel)

    -Roofs primary support:

    .Forepole umbrellas(3x12 m) - SCH 73 mm

    .Steel ribs HEB200 // 1 m

    .Shotcrete reinforcedwith steel fibers (20 cm)

    .Steel wire-meshreinforcement (AQ50).

    Rockbolts(at thebase of the steel ribs)

  • 7/18/2019 Brito3 Presentation

    18/36

    International Seminar on Tunnels and Underground Works

    Apr.05

    May05

    Conclusion of cavernsroof execution

  • 7/18/2019 Brito3 Presentation

    19/36

    International Seminar on Tunnels and Underground Works

    -Wallss primary support:

    .Rockbolts: SuperSwellex(6 m) Mesh 1,5 m x 2 m

    .Self-drilling anchors (9 m)MAI R38 Mesh 1,5 m x 2 m

    .Shotcrete reinforcedwith steel fibers (20 cm)

    Downwards execution ofcaverns walls

  • 7/18/2019 Brito3 Presentation

    20/36

    International Seminar on Tunnels and Underground Works

    Jun.05

  • 7/18/2019 Brito3 Presentation

    21/36

    International Seminar on Tunnels and Underground Works

  • 7/18/2019 Brito3 Presentation

    22/36

    International Seminar on Tunnels and Underground Works

    NUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THE

    FINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHOD

    NUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THENUMERICAL MODELLING USING THE

    FINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHODFINITE ELEMENT METHOD

  • 7/18/2019 Brito3 Presentation

    23/36

    International Seminar on Tunnels and Underground Works

    Alluvia:

    .E = 1,0 GPa; = 0,38

    .= 21 kN/m3

    .c = 60 kPa; = 32

    Breccia:

    .E = 1,5 GPa; = 0,38

    . = 22 kN/m3

    .c = 80 kPa; = 36

  • 7/18/2019 Brito3 Presentation

    24/36

    International Seminar on Tunnels and Underground Works

    -3D analysis (using Plaxis):

    .Total of142phases

    .Mesh with29.000elements

    . Rock mass: Elastoplastic (Mohr-Coulomb)

    . Forepoles: Linear elastic (solid elements)

    . Shotcrete: Linear elastic (plate elements)

    . Rockbolts: Linear elastic (geogrid elements)

  • 7/18/2019 Brito3 Presentation

    25/36

    International Seminar on Tunnels and Underground Works

    Principal stresses Plastic points Vertical displacements

  • 7/18/2019 Brito3 Presentation

    26/36

    International Seminar on Tunnels and Underground Works

    INSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATION

    AND OBSERVATIONAND OBSERVATIONAND OBSERVATIONAND OBSERVATION

    INSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATIONINSTRUMENTATION

    AND OBSERVATIONAND OBSERVATIONAND OBSERVATIONAND OBSERVATION

  • 7/18/2019 Brito3 Presentation

    27/36

    International Seminar on Tunnels and Underground Works

    -Instrumentation in 6 cross sections;

    -For the 2 main cross sections (P2 e P4):.2 inclinometers (average depth of 50 m);.6 vertical extensometers (in 3 holes);.12 horizontal extensometers (in 4 holes).

    -For all cross sections:

    .5 survey targets on the ground surface;

    .Convergence meters (7 reading points in the

    roof and 2 points at the sidewalls).

    -On the pumping stations front wall:

    .5 survey targets placed on the wall (5 levels,

    in about 2/3 of the pumping stations height).

    -In the hydroelectric plant:

    .1 portable seismograph.

  • 7/18/2019 Brito3 Presentation

    28/36

    International Seminar on Tunnels and Underground Works

    B

    6.00

    9.00

    12.00

    1.80

    2.002.00

    7.80

    0.50

    0.50

    0.50

    0.50

    0.50

    CFI

    H

    D

    E

    A

    GJ

    KLM

    NOP

    P.V. - E0P.V. - E1P.V. - E2

    I1

    2.00

    5.00

    9.75

    Galeriapiloto

    Alargamento

    s

    Destroadir.

    Destroaesq

    .

    Rebaixo1

    Rebaixo2

    Rebaixo3

    Rebaixo4

    Rebaixo5

    Rebaixo6

    -10,0

    -9,0

    -8,0

    -7,0

    -6,0

    -5,0

    -4,0

    -3,0

    -2,0

    -1,0

    0,0

    1,0

    Desloc

    .verticais-PontoC(mm)

    Galeriapiloto

    Alargamentos

    Destroadir.

    Destroaesq.

    Rebaixo1

    Rebaixo2

    Rebaixo3

    Rebaixo4

    Rebaixo5

    Rebaixo6

    -10,0

    -9,0

    -8,0

    -7,0

    -6,0

    -5,0

    -4,0

    -3,0

    -2,0

    -1,0

    0,0

    1,0

    Desloc.verticais-PontoB(mm)

    VERTICAL EXTENSOMETERS

    AT THE ROOFS AXIS

    Plaxis 3D

    Plaxis 2D

    Alert

    criteria

    Observation(cross section P2)

    Observation(cross section P4)

    Pumping

    stations axis

  • 7/18/2019 Brito3 Presentation

    29/36

    International Seminar on Tunnels and Underground Works

    REINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LINING

    AND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURES

    REINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LININGREINFORCED CONCRETE LINING

    AND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURESAND INTERNAL STRUCTURES

  • 7/18/2019 Brito3 Presentation

    30/36

    International Seminar on Tunnels and Underground Works

    Pumps (16 m high)

    Access

    tunnel

    Crane

    Storagetunnel

  • 7/18/2019 Brito3 Presentation

    31/36

    International Seminar on Tunnels and Underground Works

  • 7/18/2019 Brito3 Presentation

    32/36

    International Seminar on Tunnels and Underground Works

    Jun.05

    Jul.05

    Sept.05

  • 7/18/2019 Brito3 Presentation

    33/36

    International Seminar on Tunnels and Underground Works

    Mar.06Sept.05

  • 7/18/2019 Brito3 Presentation

    34/36

    International Seminar on Tunnels and Underground Works

    Mar.06

  • 7/18/2019 Brito3 Presentation

    35/36

    International Seminar on Tunnels and Underground Works

    CONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKSCONCLUDING REMARKS

  • 7/18/2019 Brito3 Presentation

    36/36

    International Seminar on Tunnels and Underground Works

    - The geological / geotechnical characterization included 20 dilatometer tests, very im-portant to determine the geological formations deformability characteristics it wasessential to obtain reliable parameters to the models used in the caverns design;

    - The existence of a thick consolidated alluvia deposit around the pumping stationsroof, in all its length, had great importance in the construction methods and to theprimary supports that were considered;

    - Important dimensions of the cavern height of 26,5 m and width of 12,5 m;

    - The cavern is located at the hills toe justification to a 3D analysis, using the finiteelement method; 2D analysis were also carried out, as well as parametric analysis;

    - The existing penstock was always functioning (water supply to Funchal) it had tobe protected to support the temporary rockfill and to allow vehicle passage;

    - The instrumentation was defined in order to follow permanently the displacements

    evolution, with the results being daily analysed the design predictions revealed agood adjustment to the observed displacements;

    - Demanding design and construction schedules and deadlines.