• Commodity Experience: 10 years- Iron Ore (2 years); Mineral Sands (3 years); Diamonds (5 years).- Combined production and capital projects experience throughout.
• LIMN Simulation Software: 10 years experience- LIMN Agent for Western Australia (software sales and support).- LIMN Training: 2 day beginner; advanced training; 1 on 1 coaching.- Plant Flowsheets: A0 plant overviews; detailed sectional flowsheets.- LIMN simulations: flowsheet option trade offs; constraint studies; de-
bottlenecking; scenarios; calibrated against plant performance.
• Capital Projects:- Financial analysis and trade off studies (NPV, IRR, payback etc).- Pre-feasibility through to Commissioning, Optimisation and Handover.
• Natural leadership skills. • Problem solving and trouble shooting.• Green Belt Six Sigma (Define, Measure, Analyse, Improve,
Control).• Mentoring of junior process engineers. Lead process engineer
on projects.• Climate Change: calculation of carbon footprints and
implementation of projects to reduce GHG emissions.
The Proven Method
Step 1: 1. Draw the flowsheet2. Unit operation information3. Check material flow4. Check metallurgical accounting
Step 2: 1. Develop LIMN model2. Calibrate with plant performance3. Constraints simulations4. De-bottlenecking scenarios
Step 3: 1. Scope Of Work for options2. Capital and Operating Costs for options3. Revenue, NPV, IRR, payback for options4. Select desired option
Step 4: 1. Finance capital project2. Detailed design3. Install, commission, optimise4. Update flowsheet
The ContinuosImprovement
Cycle