brownfield cleanup program coc process agenda coc process technical lessons learned bca amendments...

22
April 24, 2018 Brownfield Cleanup Program COC Process

Upload: hakhue

Post on 19-Mar-2019

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

1

April 24, 2018

Brownfield Cleanup Program COC Process

Page 2: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

2

AgendaCOC ProcessTechnical Lessons LearnedBCA AmendmentsCalendar Call MeetingsSMP TemplateBackfill and Soil Cover MaterialEnvironmental EasementsPost COC ObligationsTips for Claiming Tax Credits

Page 3: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

3

HandoutsAgendaMilestones and Calendar Call DateImportant Links• Revised DER-32• COC Process and Templates (Easement, Site Management Plan,

Final Engineering ReportSurvey & Title Requirements Post-COC Documents & Procedures

• Electronic Data Deliverables

Page 4: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

4

Site Information Sheets• Verify Site InformationExact Applicant NameContact informationOwnershipAcreageEn-Zone %

• Verify email addresses• Markup and mail to [email protected]• PRINT NEATLY!

Page 5: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

5

Guide to the COC Process

Critical path and schedule of deliverables. Submittals after the established dates:• Will jeopardize the issuance of the COC by December 31st

• Will affect the timing of any tax credits.

Page 6: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

6

Guide to the COC ProcessReflects Recent ExperienceEasement packages have been problematic• Easement package is first submittal• Resolve Title and Survey issuesReview of Draft Final Engineering Report• Leave placeholders for incomplete itemsRecord drawingsCertifications

• FER Certification includes the Electronic Data Deliverable

Page 7: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

7

Guide to the COC ProcessProject deliverables should be developed on parallel tracksHowever the sequence of approvals is as follows:• Environmental Easement Documents are approved;• the Site Management Plan is approved; • the Environmental Easement is executed and recorded; • the Final Engineering Report is developed, reviewed and,

when “approvable”;• the COC is issued.

Page 8: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

8

Environmental EasementTrack 2-4 and Conditional Track 1 Sites

Step 1 - The remedial party submits the supporting documentation (“Easement Package”)Request letters sent or about to be sent

Step 2 – DEC prepares the Environmental Easement

Page 9: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

9

COC Milestone• June 1, 2018* - Applicant Submits Complete Easement

PackageSurvey which defines “Easement Area”Include Stub Search or Title ReportInclude Attorney Checklist

*Earlier if special circumstances (Quit Claim deed, multiple owners, paper streets, lands under water, etc.)

Page 10: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

10

COC Milestones

Applicant Executes Environmental Easement prepared by DEC

•October 1, 2018DEC accepts easementEnvironmental Easement Recorded and notices provided

•October 15, 2018

Page 11: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

11

Site Management Plan

Plan for implementing• Institutional Controls (ICs) • Engineering Controls (ECs) • Monitoring and/or operation and maintenance of the remedy

after the COC is issued.

Page 12: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

12

Site Management Plan• Must be approved by DEC prior to approval of the Final

Engineering Report• Is referenced in the easement, but may be approved after

easement is executed• Requires coordination with NYSDOH• Begin developing the SMP during the construction phase of

the project

Page 13: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

13

Final Engineering Report• Final Engineering Report (FER) documents

implementation of the complete remedial program• Includes required certifications for the remedial

program by the project Professional EngineerWork is completeSMP is approvedEasement is recordedData has been submitted electronically

Page 14: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

14

Electronic Data Deliverables• EDDs should be submitted as the data becomes

available• FER data appropriate for EDDsPost-excavation sampling data

• Confirmation sampling – Confirms that goals have been met• Documentation sampling – Documents remaining contamination if excavation is limited

Baseline groundwater monitoring dataSoil vapor intrusion dataEmerging Contaminant Data

Page 15: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

15

EDD Tips

If inexperienced, consider outsourcingRead the manualContact [email protected] FER-related EDDs by October 1, 2018

Page 16: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

16

Final Engineering Report

• Approval of the FER coincides with issuance of the COC• Issued by DER Division Director to the remedial party

Page 17: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

17

Professional Engineering Issues

• Individual currently licensed and registered in NYS• Firm authorized by NYSED (except sole proprietorship)• Direct contract with client• Direct responsibility / supervision• Review certification language early & carefully• Details & links – Search “Professional Engineering”

http://www.dec.ny.gov/regulations/90487.html

Page 18: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

18

COC Principles

• Only one Certificate of Completion will be issued per site May comprise multiple Cleanup Tracks or Land Uses

• The Department will issue the Certificate of Completion to the remedial party or parties listed in the Brownfield Cleanup Agreement.

Page 19: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

19

COC Milestones

Applicant submits Draft FER

•October 1, 2018Applicant submits Final FER for Approval

•November 15, 2018

Page 20: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

20

October 19, 2018 Calendar Call

Applicants will be required to attend unless they have:• Executed and recorded an Environmental Easement• Submitted an approvable Site Management Plan• Uploaded an Electronic Data Deliverable• Submitted a Draft Final Engineering ReportVideo conference held in Albany, each DEC Regional Office & White Plains

Page 21: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

21

Page 22: Brownfield Cleanup Program COC Process Agenda COC Process Technical Lessons Learned BCA Amendments Calendar Call Meetings SMP Template Backfill and Soil Cover Material Environmental

22

Thank You• George Heitzman• Director, Remedial Bureau C• 625 Broadway Albany, NY 12233-7014

[email protected]• 518-402-9662

Connect with us:Facebook: www.facebook.com/NYSDECTwitter: twitter.com/NYSDECFlickr: www.flickr.com/photos/nysdec