Buckeye FRS No. 1 Rehabilitation Project
Phase 2A
February 18, 2015
Phase 2A
![Page 2: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/2.jpg)
Agenda
Introduction
Background
Roadways Johnson Road Sun Valley Parkway
Schedule
Open House
![Page 3: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/3.jpg)
Background
![Page 4: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/4.jpg)
Background
![Page 5: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/5.jpg)
Background
![Page 6: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/6.jpg)
Detour - Johnson
![Page 7: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/7.jpg)
Sun Valley Parkway
![Page 8: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/8.jpg)
Sun Valley Parkway
![Page 9: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/9.jpg)
Sun Valley Parkway
![Page 10: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/10.jpg)
Schedule & Milestones
• Project Schedule – NTP March/April 2015
– Completion March/April 2016
• Johnson Road – Closure Start: ± October 2015
– Duration Approx: 2 months
• Sun Valley Parkway – Lane Restrictions Start: April/May 2015
– Duration: Off & On During Construction
![Page 11: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson](https://reader034.vdocuments.net/reader034/viewer/2022052104/603f0983efde6272d50165d0/html5/thumbnails/11.jpg)
Questions?