buckeye frs no. 1 rehabilitation project phase...

11
Buckeye FRS No. 1 Rehabilitation Project Phase 2A February 18, 2015 Phase 2A

Upload: others

Post on 10-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Buckeye FRS No. 1 Rehabilitation Project

Phase 2A

February 18, 2015

Phase 2A

Page 2: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Agenda

Introduction

Background

Roadways Johnson Road Sun Valley Parkway

Schedule

Open House

Page 3: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Background

Page 4: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Background

Page 5: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Background

Page 6: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Detour - Johnson

Page 7: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Sun Valley Parkway

Page 8: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Sun Valley Parkway

Page 9: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Sun Valley Parkway

Page 10: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Schedule & Milestones

• Project Schedule – NTP March/April 2015

– Completion March/April 2016

• Johnson Road – Closure Start: ± October 2015

– Duration Approx: 2 months

• Sun Valley Parkway – Lane Restrictions Start: April/May 2015

– Duration: Off & On During Construction

Page 11: Buckeye FRS No. 1 Rehabilitation Project Phase 2Aapps.fcd.maricopa.gov/Projects/PPM/downloads/...•Project Schedule –NTP March/April 2015 –Completion March/April 2016 •Johnson

Questions?