building for learning project photo progress report 3 october 2009 – november 2009 project...
TRANSCRIPT
Building for Learning ProjectPhoto Progress Report 3
October 2009 – November 2009
Project commencement 21st September 2009
Classrooms 6-9 Demolition continues Oct 2009
Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor
Roof on – Roof Off (29th November 2009)
Over a period of about 2 weeks the roof and all timber roof trusses, wiring, air-conditioners, chimneys and a satellite dish were removed and prepared for a new 1st storey floor slab to be created.
This change meant that the possums who had taken residence in the ceiling over the last 100+ years have now moved on!!!