Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009. AWCC Chairperson Kerryn Dwyer-Parish with Graeme Connelly undertaking site inspections. Kerryn braved the situation – high heels and all. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/1.jpg)
Building for Learning ProjectPhoto Progress Report 4
November 2009 – December 2009
Project commencement 21st September 2009
![Page 2: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/2.jpg)
AWCC Chairperson Kerryn Dwyer-Parish with Graeme Connelly undertaking site inspections
Kerryn braved the situation – high heels and all
![Page 3: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/3.jpg)
The 65mm of rain made for 4 ‘internal swimming pools’ but
the task is completed
![Page 4: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/4.jpg)
And no photographic record is complete without some ‘rabbit ears’
![Page 5: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/5.jpg)
November Internal Refurbishments continue
![Page 6: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/6.jpg)
Internal Refurbishments Administration Area
![Page 7: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/7.jpg)
New ceilings, plaster, office and painting
![Page 8: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/8.jpg)
Key workers without who the job could not be done.
![Page 9: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/9.jpg)
December new on-site substation for power required.
![Page 10: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/10.jpg)
December – carpet, ceilings and windows in modernised Administration area
![Page 11: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/11.jpg)
December – steel, bond deck arrives for 1st Floor
![Page 12: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/12.jpg)
December – underground cable boring and concrete footings for stairways and elevator
![Page 13: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/13.jpg)
December – Company Directors tour with Graeme Connelly – girls were happy, boys were serious.
L-R. Chairperson Kerryn Dwyer-Parish, Director Jan Wyatt-Brown, Director Alison Mitchell, Corporate Services Manager Pauline Butler, Builder Graeme
Connelly, Director Rod Jones, Director David Ryan.
![Page 14: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/14.jpg)
December – bracing underneath bond deck and steel ready for concrete floor above
![Page 15: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/15.jpg)
Final preparations and then concrete pour starting 6am, 22nd December – 150 tonne concrete
![Page 16: Building for Learning Project Photo Progress Report 4 November 2009 – December 2009](https://reader033.vdocuments.net/reader033/viewer/2022052604/56815117550346895dbf33a7/html5/thumbnails/16.jpg)
22nd December – 11 truck loads of concrete