BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE Presented by Chloe Obi 25 th January 2017

Upload: others

Post on 11-Jul-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE

Presented by Chloe Obi25th January 2017

Page 2: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

1. BIM Level 2 Requirements 2. Benefits for Industry3. BIM for FM (COBie Extraction)4. Next Steps

Presentation Structure

Page 3: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

StructuralModel

Protocols Structuraloptimisation

Planning, Phasing and Methods (4D)

CAFM AssetManagement

Software

Templates

Components

Thermal Analysis

Space planning and cost

SustainabilityBREEAM, Carbon

Component Detailing

Test &Commission

BIM Field QC, H&S

Point Cloud Survey

Opex (6D)

Virtual / Augmented Reality

Capex (5D)

ArchitecturalModel

MEPModel

3DMerged model

3DFederated

model+

IFC+

COBie

3DUpdated model

OpexDatabase (6D)

Capex Database

(5D)

0 Preparation 1 Brief 2 Concept 3 Detail 4 Technical 5 Construction 7 Operation6 Handover

3DAs built model

+IFC+

COBie

Clash Detection

Life cycle, Energy and Carbon (6D)

Life cycle cost and Carbon 6D)

COBie export

BIM ImplementationHow can BIM be mapped as a process?

There are various facets associated with the implementation of BIM.

Page 4: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

BIM Level 2The UK Government has mandated the requirement for industry to produce intelligent 3D models at Level 2 by 2016.

Government have requested the information is provided in 3 different formats.

These are as follows:• Building Information Models• 2D information (directly extracted from the models)• COBie Information

Page 5: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

BIM Level 2To facilitate the BIM initiative, the UK Government has released an array of BIM Management documents, these are as follows:

1. PAS 1192-2:2013 Specification for information management for the capital/delivery phase of construction projects using building information modelling (CAPEX)2. PAS 1192-3:2014 Specification for information management for the operational phase of assets using building information modelling (OPEX)3. BS 1192-4:2014 Fulfilling employers information exchange requirements using COBie – Code of practice4. PAS 1192-5:2014 BIM and Security5. Building Information Model (BIM) Protocol (CIC Documents)6. GSL (Government Soft Landings)7. dPOW (Digital Plan of Works)8. Classification System (Uniclass2015)

Page 6: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

• Effective engagement• Aids decision making• Communicates the client’s requirements more clearly• Aids client confidence in our approach• Better project understanding and increased transparency• Better collaboration • Optimisation of Schedule and Cost • Aids in the capture of Asset Information requirements • Aids in the ability to create O&M data linked to the model

Benefits for Bouygues UK

Page 7: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

BIM for FM

What is COBie?

Construction Operation Building Information Exchange

COBie:• Is an internationally recognised data exchange standard

• It allows for building information exchange between design, construction and building owners

Page 8: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

BIM for FM

Page 9: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

COBie is an essential part of the UK government’s BIM strategy.

It is designed to automatically transfer data from the design and construction phase through to facilities management CAFM systems.

COBie *.xls

Maximo*.max

Archibus*.bus

COBie *.xls

IFC*.ifc

Revit*.rvt

Revit export

IBMImport

Common data exchange“the cloud”

BIM for FM

Page 10: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

COBie Extraction from BYUK Scheme

Exporting Revit to COBie:

This enables us to transfer the asset information data to an external Facilities Management software (CAFM system).

This has been used to extract the COBie data on a number of BYUK schemes.

Page 11: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

• Bouygues UK and Bouygues Energies & Services FM have processes and procedure for information requirements and information exchange.

• Bouygues UK began initially by testing the process of COBie extraction on a pilot project • the COBie data was then shared with BYES • and a mapping process (of COBie data into the CAFM system) was identified

From COBie to CAFM (CAFM Migration)

Page 12: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

Above is an example demonstrating how we have mapped the parameters from Revit to COBie to Maximo.

COBie to Maximo

Page 13: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and

1. Continued integration with Bouygues UK and Bouygues Energies & Services 2. Further integration of BIM for FM on Bouygues UK projects

3. Further integration of BIM to Inform Lifecycle Costs4. Further integration of BIM for Performance Monitoring

Next Steps

Page 14: BUILDING INFORMATION MODELLING BOUYGUES UK THE USE …constructingexcellence.org.uk/wp...obi-bouygues... · • Bouygues UK and Bouygues Energies & Services FM have processes and