building the world's largest reciprocating engine power ... · building the world's...
TRANSCRIPT
Power-Gen Middle East 2014 1
Building the World's Largest Reciprocating
Engine Power Plant in Jordan, 600MWPower-Gen Middle East, Abu Dhabi, October 2014
Al Azzam, Amani Mohamed 1; Koul, Upma2 and Paldanius, Risto3
1. Abstract
In the energy industry, known for its inertia, technological change is often slow and gradual.
However, with thorough technical and financial analysis new exiting opportunities can
emerge. This joint paper with the National Electric Power Company (NEPCO) of Jordan and
Wärtsilä Corporation describes one such a project.
Such a new opportunity arose in Jordan in the fall of 2010, when the NEPCO published a
tender for an independent power producer (IPP) project, the third such project in the country
(hence the name "IPP3"). What separated IPP3 from the two previous IPP projects was its
size and technology: it included an option for a 600 MW power plant using tri-fuel
reciprocating engines.
This paper is divided into two sections. The first section represents NEPCO's needs and
approach to the IPP3 project. An analysis of the power demand trends, existing portfolio, and
fuel supply issues in Jordan provides background for the paper. The main steps in NEPCO's
analysis are later analysed in detail, leading to the conclusion that IPP3 should be
approximately 600 MW and based on reciprocating engines. The second section of the paper
represents Wärtsilä’s view, the equipment supplier and EPC consortium leader for IPP3
project. The initial phases of the process, that is, information exchange with NEPCO and
various technological comparisons by various consultants are overviewed. The main steps in
establishing relations and coming to an agreement with the developer, KEPCO/Mitsubishi,
are considered. An overview of the environmental impact assessment and the consequent
adoption of new emissions regulation in Jordan is provided. Finally, challenges of managing a
large-scale project in Jordan are covered.
1 Deputy Managing Director for Operation & Planning, National Electric Power Company, Jordan2 Business Development Manager, Wärtsilä Corporation Power Plants, UAE. Corresponding author.3 Director, Business Development, Wärtsilä Corporation Power Plants, Finland
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 2
IPP3 is a ground-breaking project for Jordan, supplying not only base load, but also load
following and grid stability reserves for the Jordan power system. The IPP3 power plant will
be world’s largest tri-fuel power plant in the world, providing Jordan with much needed fuel
and operational flexibility.
2. Introduction
Jordan has experienced decades of robust electric demand growth due to an expanding
population of 6.41 million people and an electrification rate of 100 percent. Although located
in a fossil fuel-rich region of the world, Jordan lacks significant indigenous energy resources
and relies on imports to provide more than 97 percent of the country’s energy needs. The
electricity sector accounts for 42% of the energy resources consumed. Historically Jordan has
depended heavily on natural gas for electric power generation. In 2009, 89 percent of the
electricity produced was from natural gas. Natural gas is supplied from a single source – the
Arab Gas Pipeline which runs from Egypt to Jordan and other neighbouring countries. The
reliance on a single source of fuel for the bulk of electric power posed significant energy
security concerns for the National Electric Power Company (NEPCO) of Jordan. NEPCO is
the state-owned transmission system operator and is responsible for planning, constructing,
and maintaining the country’s power system. NEPCO purchases electricity from power
generation companies and from neighbouring countries Egypt and Syria via electrical
interconnection lines (single buyer) and sells the power to distribution companies and large
industries.
In 2010, NEPCO conducted studies to forecast demand growth and analyse projected reserve
margins through 2040. The analyses identified key vulnerabilities, actionable timelines, and
assessed technology and fuel options to meet the country’s growing electric power
requirements. These studies identified the need for 600 megawatts (MW) of new generating
capacity to avoid shortfalls in supply and reserve margin deficits projected to occur by 2015.
A significant conclusion of NEPCO’s analysis was that the new capacity needed to have
operational flexibility to meet fluctuations in electrical demand. NEPCO’s issuance of a
tender for the construction of a third independent power producer project in Jordan – the IPP3
project – was pioneering for a number of reasons: scale, technology selection and
environmental standards. This paper discusses the technological, energy security and
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 3
economic factors that led to the construction of the world’s largest tri-fuel reciprocating
engine power plant.
3. Background on Jordan’s Power System
Annual peak electric load in Jordan has risen by an average of 9 percent from 1980 through
2010. The peak load in 2012 was 2770 MW, serving 1.65 million electricity customers. The
consumer sector consumed 43 percent of the electricity generated while the industrial sector
accounted for 24 percent of consumption. Electric power demand varies by as much as 30
percent daily, presenting operational and planning challenges for the transmission system
operator, NEPCO. Electric demand has been met primarily with steam turbine and combined
cycle gas turbine (CCGT) capacity. The current and historical profile of the generating fleet is
shown in Table 1. The heavy reliance on plants that are designed to run at high load factors
provides limited ability to adapt to daily fluctuations in demand. This is reflected in an overall
average thermal efficiency of the generating fleet of 40.2 percent in 2012.
Table 1: Installed electric generating capacity in Jordan (MW)
Year Steam Diesel-
fired
GT
Gas-
fired
GT
CCGT Diesel Wind Hydro Biogas TOTAL
2006 1010 156.5 189.4 585 54.3 1.44 12 3.5 2012
2007 1010 156.5 289.4 585 54.3 1.44 12 3.5 2112
2008 1010 156.5 677.4 585 54.3 1.44 12 3.5 2500
2009 1010 156.5 389.4 965 54.3 1.44 12 3.5 2592
2010 1010 156.5 600.4 1317 46.8 1.44 12 3.5 3148
2011 1010 141.5 499.4 1737 46.8 1.44 12 3.5 3452
2012 1010 141.5 499.4 1737 46.8 1.44 12 3.5 3452
Prior to 2011, the bulk of electric generation in Jordan had been from natural gas. In 2009
natural-gas fired generation accounted for 12,986 gigawatt hours (GWh) or 89 percent of total
electric generation as shown in Figure 1. Then in 2011 a major disruption to Jordan’s single
source natural gas supply, the Arab Gas Pipeline, intensified energy security concerns.
Natural gas imports to Jordan were reduced from 89 billion cubic feet (Bcf) in 2010 to 29 Bcf
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 4
in 2011. To compensate for the natural gas shortages, Jordan’s fuel oil imports increased by
more than 25 percent. Diesel and heavy fuel oil (HFO) accounted for 64 percent of total
electric generation in 2011 and 78 percent in 2012, as shown in Figure 1. This abrupt shift
from natural gas to fuel oil and diesel also affected the efficient and economic dispatch of
Jordan’s generating units. As a result, the cost of energy relative to Jordan’s gross domestic
product (GDP) increased from 11.5 percent in 2009 to 21.3 percent in 2012.
Figure 1: Energy generated by fuel type in Jordan, 2009-2013
NEPCO hired a consultant to evaluate the power system needs, K&M Engineering and
Consulting, evaluated peak load supply and reserve margins with existing capacity alone,
extensions to planned retirements, and capacity additions. With the currently installed
capacity, a supply deficit of 306 MW was projected for 2013. By 2015, 910 MW of new
capacity would be needed to meet demand and avoid reserve margin deficits as high as 25
percent. The electricity demand forecast and the expected shortfalls without new builds are
shown in Figure 2. The feasibility of getting 300 MW of new capacity online by 2013
presented significant challenges. However, by extending the retirement dates of some existing
units, NEPCO could meet peak load and maintain positive reserve margins in 2013. Even
with those extensions, the system would still experience supply deficits of 283 MW in 2014
and 529 MW in 2015. NEPCO identified that a third IPP tender, with a commercial operation
date by 2014, should be issued to prevent these capacity shortfalls.
89
69
2517
35
7
24
32
29
27
1 3
3249
34
3 411
5 4
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2009 2010 2011 2012 2013 (jan-may)
Imported electricity
Diesel
HFO
Natural gas
Building the world’s largest reciprocating engine power plant.
Power-Gen Middle East 2014
Figure 2: Peak electricity demand forecast and deficits, 2011
4. Power System Modelling and Optimization
Severe dependency on unreliable natural gas
flexibility in NEPCO’s power generating portfolio prompted Wärtsilä to undertake a power
system optimization study in 2009. While the Jordan electric power system was a combined
cycle dominated market, Wärtsilä rec
was not fully optimized for efficiency and generation cost, for example CCGT plants were
being used as spinning reserve. Fluctuations in plant load factor increases production costs
due to loss of fuel efficiency and higher maintenance costs associated with CCGT plant
cycling. Wärtsilä undertook a study of the Jordan power system to identify the how the
existing generating fleet operations could be optimized with the addition of highly flexible
generating sources. Flexible generating sources can provide, for example, quick
capability for variable loads, without sacrificing efficiency.
Model results showed that existing baseload capacity was sufficient, but Jordan needed
operational flexibility to meet peak demand. An analysis of the load profile revealed that one
third of the daily load was flexible, with the remaining two
Wärtsilä demonstrated that the overall system efficiency would dramatically increase,
reducing fuel costs, by converting open cycle GTs to combined cycle, enabling CCGTs to
operate at high plant load factors and using efficient and flexible generating resources to meet
fluctuations in demand. These types of generating resources we call Smart Power Genera
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
: Peak electricity demand forecast and deficits, 2011-2040
Power System Modelling and Optimization
Severe dependency on unreliable natural gas supply from Egypt and lack of needed fuel
flexibility in NEPCO’s power generating portfolio prompted Wärtsilä to undertake a power
system optimization study in 2009. While the Jordan electric power system was a combined
cycle dominated market, Wärtsilä recognized that the use of CCGTs to meet flexible demand
was not fully optimized for efficiency and generation cost, for example CCGT plants were
being used as spinning reserve. Fluctuations in plant load factor increases production costs
efficiency and higher maintenance costs associated with CCGT plant
cycling. Wärtsilä undertook a study of the Jordan power system to identify the how the
existing generating fleet operations could be optimized with the addition of highly flexible
g sources. Flexible generating sources can provide, for example, quick
capability for variable loads, without sacrificing efficiency.
Model results showed that existing baseload capacity was sufficient, but Jordan needed
eet peak demand. An analysis of the load profile revealed that one
third of the daily load was flexible, with the remaining two-thirds load being baseload.
Wärtsilä demonstrated that the overall system efficiency would dramatically increase,
costs, by converting open cycle GTs to combined cycle, enabling CCGTs to
operate at high plant load factors and using efficient and flexible generating resources to meet
fluctuations in demand. These types of generating resources we call Smart Power Genera
Azzam, A.M.; Koul, U. and Paldanius, R.
5
supply from Egypt and lack of needed fuel
flexibility in NEPCO’s power generating portfolio prompted Wärtsilä to undertake a power
system optimization study in 2009. While the Jordan electric power system was a combined-
ognized that the use of CCGTs to meet flexible demand
was not fully optimized for efficiency and generation cost, for example CCGT plants were
being used as spinning reserve. Fluctuations in plant load factor increases production costs
efficiency and higher maintenance costs associated with CCGT plant
cycling. Wärtsilä undertook a study of the Jordan power system to identify the how the
existing generating fleet operations could be optimized with the addition of highly flexible
g sources. Flexible generating sources can provide, for example, quick-start
Model results showed that existing baseload capacity was sufficient, but Jordan needed
eet peak demand. An analysis of the load profile revealed that one-
thirds load being baseload.
Wärtsilä demonstrated that the overall system efficiency would dramatically increase,
costs, by converting open cycle GTs to combined cycle, enabling CCGTs to
operate at high plant load factors and using efficient and flexible generating resources to meet
fluctuations in demand. These types of generating resources we call Smart Power Generation.
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 6
Smart Power Generation is the combination of energy efficiency, operational flexibility, and
fuel flexibility. This type of generation provides stability to a power system with rapid starts,
stops and quick ramp up or down capacities while retaining high efficiency at partial loads.
The optimized daily load cycle estimated for 2014 is shown in Figure 3 and Figure 4 for high
demand and minimum demand periods, respectively. Major variations in demand are
absorbed by a Smart Power Generation IPP (in purple), allowing CCGTs (in green) to run at a
stable load with higher efficiency. The estimated IPP plant load factor for the high demand
period would be approximately 57 percent. During low demand periods, steam plants would
remain in stand-by mode and flexible power run at about 50 percent load factor. Wärtsilä
presented the results to NEPCO and introduced the concept of reciprocating engine
technology which can serve as Smart Power Generation.
Figure 4: Optimized daily load cycle – High demand period
Figure 4: Optimized daily load cycle – Minimum demand period
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 7
In addition to this, there is a glaring need for the Jordanian power system to become ready for
the upcoming development plans and accommodate the growing shares of renewable energy
that are scheduled to become available in the near future. Jordan is planning to undertake
major investments in renewable energy, capitalising on their privileged geography by
harnessing the power of the abundant solar irradiation and strong winds in certain regions.
In the Master Strategy of the Energy Sector in Jordan for the 2007-2020 period, the Jordanian
government set a target to obtain 1800 MW, an amount equivalent to 10 per cent of the
country’s energy generation base, from renewable sources by 2020. Of this, about 1200 MW
will come from wind energy, 600 MW from solar power, and between 30 and 50 MW from
waste-to-energy facilities, according to the mentioned Master Strategy.
This requires the Jordanian power system to incorporate a sizeable amount of flexible
generation capacity that can quickly respond and come online in a matter of minutes when the
renewable sources falter. For that reason, the operational flexibility dimension of the
technology assessment, which will now be presented in the next chapter, becomes of
paramount importance.
5. Technology Assessment
To evaluate fuel selection, operational modes, and generating technologies that would provide
the best solution, NEPCO tasked K&M Engineering and Consulting to conduct a project
technology assessment for IPP3. The assessment examined fuel types, expected dispatch
strategy and capacity factors, and technology options and plant configurations. The
technologies considered were combustion turbines in simple and combined cycle,
reciprocating engines, and oil-fired boiler power plants. Technologies were evaluated for fuel
use, efficiency, availability, emissions, longevity, water consumption, risks, capital costs,
fixed and variable O&M costs, and estimated time for construction. Table 2 presents a
summary of the technology evaluation.
The assessment considered natural gas, heavy fuel oil, crude oil, and light distillate oil as
viable energy sources for IPP3 and examined the projected availability and costs of each fuel
type. Due to anticipated shortages in natural gas supply, heavy fuel oil-fired capacity
represented the most economically viable short-term alternative for a new IPP. However,
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 8
NEPCO also began the process of securing liquefied natural gas (LNG) and regasification
infrastructure for future energy needs. The ability of a new IPP to utilize either fuel oil or
natural gas depending on changing supply conditions would provide much needed flexibility
for the power system. K&M strongly recommended against using HFO in combustion
turbines because of increased maintenance requirements, resulting probably lower availability
and reliability numbers.
Table 2: Summary of IPP3 Technology Evaluation
Technology Fuel
Cycling
/peaking
mode Efficiency Availability
Environmental
characteristics
Water
consumption
Medium-speed
reciprocating
engines
Gas or
1%
sulphur
HFO
Well
suited44% 95%
Meets
requirements
burning gas or
low-sulphur
HFO
Low
Conventional
HFO-fired
boiler
Gas,
low- and
high-
sulphur
HFO
Not well
suited35-35% >90%
Can meet
requirements
with FGD
system
Moderate,
but requires
very large dry-
cooled
condenser
Combined
Cycle Gas
Turbine
Gas,
light
distillate
Not well
suited55% 92-94%
Clean on natural
gas, needs water
injection on oil
Moderate
with dry
cooled
condenser
K&M analysed load duration curves for 2012 – 2019 and the capacity utilization that IPP3
would be expected to have each year. During the maximum load day in 2015, 1200 MW of
capacity would need to be started during peak load hours and shut down or unloaded when
demand is at lowest levels. The analysis concluded that the most economical operation of
existing plants would be to operate combined cycle plants as baseload and use IPP3 for
cycling. The load factor for IPP3 was expected to range from 38 to 69 percent, with capacity
utilization under 50 percent for several years. Further, the assessment identified that the
selected technology and capacity of individual IPP3 units should be sized so that the outage of
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 9
one unit would not compromise transmission system stability. NEPCO’s analysis confirmed
the operational and efficiency benefits of Smart Power Generation in providing tri-fuel
flexibility and suitability for cycling operations.
NEPCO then conducted a tariff study to compare the cost of reciprocating engine plant
following Smart Power Generation principles to CCGT plants and boiler plants under various
dispatch and fuel conditions. The financial methodology enabled the technology evaluation to
take into consideration heat rate and the impact of fuel costs over a period of 25 years. Using
natural gas, CCGTs posed the lowest cost for load capacity, whereas supercritical boiler
plants provided the lowest cost for HFO-fired baseload capacity.
However, the Smart Power Generation option, represented by medium-speed reciprocating
engines, presented the lowest cost for meeting the flexible demand, and enabled existing
CCGTs to operate at high load factors with higher efficiency. Comparing tariffs for flexible
load, which included part load operation impacts, starting costs, substitution costs, and
transmission line losses, Smart Power Generation provided the lowest cost with both natural
gas and liquid fuels. Based on the studies conducted by K&M, the RFP for IPP3 was issued
with tri-fuel reciprocating engine technology fulfilling all the aspects of Smart Power
Generation.
It is because of the special characteristics of modern medium-speed reciprocating engines that
they are such a good fit for the needs of IPP3. First of all, the fact that a reciprocating engine
plant is made of several units of close to 20MW each ensures that even if one unit suffers an
unexpected outage or needs maintenance, the practical totality of the plant power is still
available. Adding to that, the reliability of each individual unit is the highest of all the
analysed alternatives – a winning combination. As an added benefit, the engines perform
especially well in load cycles. They are able to start up, run just enough time to cover the
demand peak and shut down immediately after, with no impact on maintenance. Since they
can be started and stopped individually, the magnitude of the peak does not impact the plant
efficiency either: only the needed number of engines are started to deal with the load peak,
keeping the plant efficiency at its maximum.
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 10
On top of the previously discussed factors, the specific conditions affecting IPP3 made the
project even more challenging: the hot and dry ambient conditions, plus the strict limitation of
water usage, posed a major challenge to all of the three possible technologies. However,
according to the evaluation, reciprocating engines are the technology that can best deal with
these conditions. Contrary to that of other technologies, engines only suffer minimal derating
in the desert climate, and their water consumption is negligible in comparison with that of gas
turbines or HFO-fired boilers. This is a key point in the case of IPP3, because as one may
guess, a cooling system that uses large amounts of water would pose a great risk to the mid-
and long-term success of the project. This could even potentially impact the energy
independence of the country, forcing the mothballing of a key generation asset in times of
drought.
The ability of reciprocating engines to start up in a matter of minutes, faster than any other
thermal technology, makes them especially suitable for supporting grids with increasing
shares of renewable sources. Since the output from solar and wind power is highly
intermittent and can vary heavily in a matter of minutes, it is necessary to have power
reserves in place that can kick in when renewable power output decreases, in order to
guarantee the stability of the whole national power system. A lack of flexible balancing
capacity could seriously jeopardize the bet for renewable power that Jordan has made, but
thanks to the careful planning and technological evaluation, the country will be able to fully
utilize its renewable potential without endangering the power system stability, hence setting a
valuable precedent for other countries to develop in a similar fashion.
6. Environmental Regulation
The increasing reliance on diesel and heavy fuel oil for electric power generation in Jordan
spurred environmental concerns. Prior to engagement with the project developers, Jordan’s
existing environmental regulations were based on combined cycle gas turbine and boiler
technology, and emissions standards were not technology-specific. The prospective project
developers informed NEPCO prior to issuance of the IPP3 tender that the existing
environmental standards were not applicable for tri-fuel reciprocating engines, which had
high efficiency and low emission rates. The updated World Bank/IFC Environmental Health
and Safety (EHS) Guidelines (2008) reflected the latest industry technologies and emissions
control for different categories of thermal power station prime movers. After a comprehensive
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 11
environmental impact assessment conducted in 2012, Jordan adopted the IFC Guidelines.
NEPCO’s analysis further demonstrated that a 600 MW tri-fuel reciprocating engine power
plant, while burning HFO, produced 35 percent less carbon emissions than an existing steam
electric plant using HFO because of the high engine efficiency performance.
7. Project Collaboration and Innovation
The IPP3 project represents a unique level of international cooperation toward providing a
turnkey engineering, procurement, and construction (EPC) solution to fulfil the needs of
Jordan’s power system. The scope and schedule of the project presented numerous challenges.
To meet the tender offer, Wärtsilä of Finland teamed with the Korea Electric Power Company
of South Korea (KEPCO) and Mitsubishi Corporation of Japan to form a new entity, Amman
Asia Electric Power (AAEPCO) that would supply electricity to NEPCO. The development
team members KEPCO and Mitsubishi brought impressive track records of successfully
completing a number of power projects worldwide and access to competitive project
financing, while Wärtsilä provided the reciprocating engine technology expertise. The EPC
consortium is led by Wärtsilä with South Korea-based Lotte Engineering and Construction as
EPC consortium partner.
Figure 5: IPP3 in a computer-generated image (l) and in construction (r)
NEPCO awarded the IPP3 project to the KEPCO-led consortium in January 2012. IPP3 will
have 38 high efficiency Wärtsilä 50DF engines capable of running on HFO, light fuel oil
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 12
(LFO), or natural gas. In the event of a fuel supply interruption, the engines have the ability to
switch fuels while operating without load reduction
To help NEPCO meet immediate peak load needs, the first 16 engines of IPP3 came online in
February 2014, with 14 more engines planned to begin operation in the upcoming July. The
full IPP3 plant is expected to be in service by September 2014. This represents an incredibly
short development schedule. IPP3, nominally rated as 600 MW, can produce 632 MW under
ISO conditions and a firm and consistent 573 MW under extreme Jordanian ambient
conditions. The expected running regime is 60 percent for base load, and 40 percent for
flexible operation. The plant is planned to run on HFO with LFO backup through 2015, then
switching over to natural gas as NEPCO completes gas infrastructure projects. NEPCO has
entered into a 25-year purchase power agreement with AAEPCO.
Managing such a large project in an EPC Consortium posed significant challenges for the
developers, EPC Consortium members and the various advisors. A proactive collaboration
between the EPC Consortium members prior to submission of bid helped in overcoming the
cultural differences and different ways of working. The EPC Consortium members were
committed to completing the project in accordance with NEPCO’s requirements and tight
timeline. Close cooperation between KEPCO, Mitsubishi, Wärtsilä Development & Financial
Services (WDFS), and the EPC Consortium members paved the way for winning the project
and successful implementation of the largest tri-generation reciprocating engine power plant
in the world.
8. Conclusion
Collaboration early on in the tender process was essential for identifying the lowest cost
technology that would provide Jordan with much needed fuel and operational flexibility and
led to the inclusion of reciprocating engine technology in the tender. This was the first time
that NEPCO had ever issued a tender for a reciprocating engine power plant. The IPP3 power
plant will ensure that Jordan has flexible generating capacity that can provide baseload, load-
following, and peaking power to meet projected increasing demand, thus preserving essential
reserve margins. The tri-fuel capability of the IPP3 reciprocating engines enables the power
plant to instantaneously adapt to interruptions in fuel supply while maintaining load, ensuring
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 13
a reliable and efficient source of electricity. Power system analysis showing the value from
optimizing generating resources was essential to identifying the need for Smart Power
Generation. Environmental concerns were addressed using a collaborative and informative
approach, allowing Jordan to adopt 2008 IFC EHS Guidelines which represent best industry
performance. IPP3 will be the world’s largest reciprocating engine power plant, as well as
provide a model for Smart Power Generation, providing operational flexibility, fuel flexibility
and high energy efficiency for the electric power system.
Building the world’s largest reciprocating engine power plant. Al Azzam, A.M.; Koul, U. and Paldanius, R.
Power-Gen Middle East 2014 14
9. References
EIA (2013), International Energy Statistics. “Jordan.” U.S. Energy Information
Administration, March 2013.
International Finance Corporation (2008), Environmental, Health, and Safety Guidelines for
Thermal Power Plants. World Bank Group, 18 December 2008.
K&M Engineering and Consulting (2011), “Development of the IPP3 Power Project In
Jordan.” K&M Engineering and Consulting LLC, Washington D.C.
K&M Engineering & Consulting (2010), “Project Technology Assessment Report prepared
for the National Electric Power Corporation of Jordan.” K&M Engineering and Consulting
LLC, Washington D.C., January 2010.
Ma’abreh, G. (2013), “Jordan’s Power System: Present and Future Development.” National
Electric Power Company of Jordan, 2013.
NEPCO (2012), “Electricity Generation in Jordan.” National Electric Power Company of
Jordan, 2012.
Wärtsilä Power Plants (2013), “Smart Power Generation, Optimizing system efficiency.”
Wärtsilä, 25 June 2013.