bus coupler installation guide

60
Installation Guide BUS Couplers Epoxy Mica Capacitor Partial Discharge Sensors This document is a guideline only. It is not a machine-specific detailed instruction. The installation of bus couplers should be directed by an IRIS specialist or performed by a person trained in the installation procedure to ensure that the integrity of the system is not impaired. A companion document, the Iris Verification Guide, provides guidance on how to validate the installation. Iris Power LP cannot take responsibility for installations performed by others. Iris Power LP

Upload: mauritzmanurung

Post on 24-Dec-2015

354 views

Category:

Documents


35 download

TRANSCRIPT

Page 1: Bus Coupler Installation Guide

Installation Guide

BUS Couplers

Epoxy Mica Capacitor Partial Discharge Sensors

This document is a guideline only. It is not a machine-specific detailed instruction.

The installation of bus couplers should be directed by an IRIS specialist or performed by a person trained in the installation procedure to ensure that the integrity of the system is not impaired. A companion document, the Iris Verification Guide, provides guidance on how to validate the installation.

Iris Power LP cannot take responsibility for installations performed by others.

Iris Power LP

Page 2: Bus Coupler Installation Guide

The information contained in this document is the property of Iris Power LP., and is to be considered proprietary material. No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photocopying and recording, for

distribution to a Third Party without the express written permission of Iris Power LP.

BUS Coupler Installation Guide -Version 4.4 Nov 2010 Version 4.4 [Addition of IECEx] Oct 2009 Version 4.3 [Incorporate changes from 3.7 version; Clarification of section 2.2, Fig 12 & 14 changed, Appendix F updated &Figure 1] June 2009 Version 4.2 [remove item #5 Shock Mounts on page 58] Apr 2009 Version 4.1 [Appendix G added for ATEX] Nov 2008 Version 3.5 [copper strap in Appendix B] Nov 2008 Version 3.4 [copper strap] Aug 2008 Version 3.3 [surge capacitor] Mar 2008 Version 3.2 [company address] Dec 2005 Version 3.1 [Appendix F added] Aug 2003 Version 3.0 May 2003 Version 2.4 May 2000 Version 2.3 Jul 1999 Version 2.2 Mar 1999 Version 2.1 © Iris Power LP, 2010. All rights reserved

Page 3: Bus Coupler Installation Guide

Contents 1. Introduction .............................................................................................. 5

1.1 EMCs .................................................................................................................................. 51.2 Description of EMCs ......................................................................................................... 61.3 Installation Schedule ........................................................................................................ 7

2. EMC Installation ....................................................................................... 92.1 Overview ............................................................................................................................ 92.2 EMC Location .................................................................................................................... 92.3 High Voltage Connection ............................................................................................... 122.4 EMC Mounting Considerations ..................................................................................... 152.5 Insulating the EMC ......................................................................................................... 17

3. Termination Box Installation ................................................................. 213.1 Overview .......................................................................................................................... 213.2 Installation ........................................................................................................................ 21

4. Coaxial Cable Installation ...................................................................... 234.1 Overview .......................................................................................................................... 234.2 Installation ........................................................................................................................ 234.3 Preparing Coaxial Cable at EMC End ......................................................................... 254.4 Preparing Coaxial Cables for Soldering ...................................................................... 27

5. Customer Support .................................................................................. 315.1 Technical Support ........................................................................................................... 315.2 Sales Support .................................................................................................................. 315.3 Product Updates & New Product Information ............................................................ 31

Appendix A. Dimensional Drawings ............................................................ 35EMC Mounting Clamps ........................................................................................................... 35Termination Box Dimensions ................................................................................................. 36

Appendix B. lnstallation Materials ............................................................... 37Appendix C. Off-line Testing ......................................................................... 41

Hi-pot Testing ........................................................................................................................... 41Other Off-Line Tests ................................................................................................................ 41

Appendix D. ISO Phase BUS Considerations .............................................. 43Typical IPB Configurations ..................................................................................................... 43Ground Loop ............................................................................................................................. 44Typical Conduit Runs with IPB Systems .............................................................................. 45

Appendix E. 25kV EMC Mounting Blocks .................................................... 47Labadie Block ........................................................................................................................... 4745° Angle EMC Mounting Bracket ......................................................................................... 50

Appendix F. Motor Applications within Nuclear Plant Containment ........ 51Appendix G. Instructions for ATEX & IECEx ............................................... 53

Page 4: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide 2 Iris Power LP

This page has been left blank intentionally

Page 5: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide 3 Iris Power LP

ATTENTION

Read Before Starting Installation

WARNING: Installations are often carried out in conjunction with rewinds or remedial work on a machine. It is possible to have a bus coupler installation partially completed but interrupted for high voltage testing. Refer to Appendix C for technical guidance. NOTES:

The Epoxy Mica Capacitor (EMC) should be kept clean during the installation. Painting or coating the EMC with foreign materials may degrade the electrical tracking resistance of the EMCs. The surface of the EMC may be cleaned with cloth moistened with alcohol or approved solvents. If in doubt of the compatibility of the solvent with the EMC, contact Iris Field Service Technical Support [ref. Section 5.1]. The 6.9kV and 16kV EMCs may be mounted in any position - vertical, horizontal or suspended - where there is sufficient electrical clearance using the supplied metal clamps. The 25kV EMCs can only be mounted in the vertical position when using the standard metal mounting clamps. For horizontal, suspended or tilted mountings of the 25kV EMCs refer to Appendix E for technical guidance. Special mounting plates for installing EMCs within the ISO phase bus duct on curved surfaces are optional and can be supplied upon request. For machines with operating temperatures exceeding 90°C at the copper, mica tape and epoxy resin (not supplied) or high temperature silicone rubber tapes (not supplied) should be used in place of the supplied Boot. Copper temperatures tend to be 5° to 15° hotter than indicated on the imbedded RTD or Thermocouples.

NOTE: If proposing to use a PDA-IV™ test instrument to measure PD using a Bus coupler configuration, consult Iris Field Service Technical Support for details on appropriate coaxial cable installation and verification requirements.

Page 6: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide 4 Iris Power LP

Do’s and Don’ts

Do… • Pay attention to electrical clearances, both phase-to-phase and phase-to-

ground.

• Solidly ground the termination box.

• Ground the conduit to the termination box and ensure that this is the only point of grounding.

• Follow IRIS installation procedures. Don’t…

• Don’t ever use adhesive backed cable tie anchors unless secured by mechanical means to fasten the coaxial cables in place.

• Don’t run coaxial cables over top of the high voltage components where they could eventually fall onto those components.

• Don’t ever connect ISO phase bus ducts together, or ground across insulated supports using solid runs of metal conduit. Use non-conducting spacers, conduit, or insulators to maintain isolation between phases and ground.

• Don’t bend HV cables to a radius greater than 7 times the cable diameter.

• Don’t mount 25kV EMCs in any orientation other than upright unless special mounting blocks are used.

Page 7: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Introduction - 5 Iris Power LP

1. Introduction 1.1 EMCs Epoxy Mica Capacitors or EMCs are high frequency sensors used to detect Partial Discharges (PD) occurring within switchgears, transformers and stator windings of motors and generators [Figure 1]. The sensors are often referred to as Bus Couplers. EMC sensors can be used with the TGA-B™ and TGA Bantam™ portable instruments, or the PDTrac™, BusTrac™, and BusGuard™ continuous monitors. 1

The EMCs are permanently installed external to the actual machine winding on the main power connection or “bus”, hence the name “bus coupler”. For installations on transformers or switchgear, the EMCs are often located within the apparatus cubicles. Contact Iris Field Service Technical Support for further information on installations for transformers and switchgear [ref. Section

5.1]. After installation, the time for a high frequency pulse to travel between the two bus EMCs is measured. This “time delay” is used by the test instrument as an additional method to discriminate between “partial discharges” originating within the machine and “noise” originating from the bus or system. This is called a directional install. It is this ability to separate the machine and system pulses, which allows for accurate assessments of the PD data obtained during testing.

1 TGA-B, TGA Bantam, PDTrac, BusTrac and BusGuard are products of Iris Power

Figure 1. 6.9kV, 16kV and 25kV EMCs

NOTE: For information about the instruments or systems, please refer to the appropriate users manual or contact your Iris Sales Representative [ref. Section 5.2].

NOTE: For information about verification and measuring time delay, please refer to the Iris Verification Guide or contact Iris Field Service Technical Support [ref. Section 5.1].

Page 8: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Introduction - 6 Iris Power LP

Often motors (and sometimes generators) are connected to the system using long lengths of power cable. Where the cable distance is greater than 30m (100ft), a single EMC can be mounted at the motor/generator terminals and still achieve the same noise discrimination as a directional system. This is possible because the high frequency “system” pulses that might normally be detected by the test instrument are severely attenuated by the cable and, therefore, are not recognized by the test instrument as a partial discharge pulse. Please contact Iris Field Service Technical Support if unsure whether a single-ended installation is appropriate for your application [ref. Section 5.1].

1.2 Description of EMCs EMCs are made from high quality tracking resistant electrical grade epoxy, fully-rated for 6.9kV, 16kV or 25kV phase-to-phase class installations [Figure 1]. This epoxy encapsulates an internal epoxy-mica capacitor stack having a capacitance of 80pF +/-4 pF for the 25kV EMCs and 80pF +/-3 pF for the 6.9kV and 16kV EMCs [Figure 2]. The EMCs have a minimum partial discharge extinction voltage of 6.9kV, 16kV and 25kV AC rms respectively, at 5pC sensitivity, tested according to ASTM D1868 and IEC 60270. All Iris EMCs are AC hi-pot (proof) tested for 1 minute accordingly:

EMC Voltage Rating Test Voltage 6.9kV 15kV 16kV 33kV 25kV 51kV

The EMCs resemble post type insulators and, except for the high voltage termination, require no further insulation to be applied in the field. Figure 1 shows the three EMC sizes offered by Iris.

EMC Voltage Rating Height Diameter 6.9kV 95mm (3.75) 89 mm (3.5in) 16kV 130mm (5.1in) 89 mm (3.5in) 25kV 205mm (8.1in) 89 mm (3.5in)

All three voltage classes have embedded brass terminals, top and bottom, to which the electrical connections are made [Figure 2]. The low voltage terminal is recessed into the bottom of the epoxy and contains a 3/8in stainless steel plug. This plug is drilled and tapped to accept a small slotted screw to which the centre

Figure 2. EMC cross-section

Page 9: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Introduction - 7 Iris Power LP

conductor of a 50-Ohm (Ω) coaxial cable is attached. The brass terminal on the high voltage end (top) of the EMC is drilled and tapped to accept a 3/8in brass bolt. The high voltage cable supplied comes with an “L” shaped ring lug crimped on one end, which is used for bolting to the top of the EMC.

1.3 Installation Schedule A typical double-ended (6 EMC) installation can take from 2 to 4 days depending on the unit, mounting locations, amount of pre-work performed and the number of people assigned to the job. For a typical installation supervised by an Iris specialist, the customer should provide 2 to 3 people based on the complexity of the installation to support the Iris specialist on-site. For single-ended (3 EMC) installations, 1 to 1.5 days with 2 people for support is typical. The bus coupler installation procedure is divided into several components. However, some aspects of the various components are interdependent and should be done in a logical order to avoid repeating work. With this in mind, a suggested schedule is as follows:

Part 1 • Safety Training and Site Orientation of Iris specialist (if required)

• Isolate unit / get the required permits / access machine / remove covers etc…

• Select the locations for mounting the EMCs and termination box. Select routing for any conduit.

• Consult the Iris Verification Guide to confirm the suitability of the selected locations using the site verification procedures.

• Review list of materials required (conduit lengths, mounting hardware tooling required etc.).

• Start to layout and drill the holes for the EMC mounting plates – design and fabricate any mounting bracket supports required.

Part 2 • Install the termination box.

• Install metallic conduit (rigid or flexible) between the EMCs and termination box where required.

Page 10: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Introduction - 8 Iris Power LP

NOTE: The coaxial cable must run along a grounded metal surface. When routing the coaxial cable inside a protected enclosure, it may not be necessary to run in conduit.

• Cut and prepare coaxial cable ends – each pair of coaxial cables must be of equal length.

• Attach the high voltage (HV) cable to the EMC and insulate for the required voltage class.

NOTE: The HV end of the EMC must be insulated, even if installed in an area of all bare bus.

• Connect the coaxial cables in the appropriate manner to the EMCs.

Part 3 • Mount the EMCs in the required locations and run the coaxial cables to

the termination box.

• Connect the HV lead from the EMC to the HV bus or terminal.

• Perform initial verification and trim coaxial cables to their final lengths according the Iris Verification Guide.

• Hard wire (solder) the coaxial cables in the termination box.

• Perform final verification according to the Iris Verification Guide.

• Insulate the HV bus connection point as required and secure the coaxial cables.

Page 11: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 9 Iris Power LP

2. EMC Installation 2.1 Overview Normally, two EMCs are installed on each phase (6 per machine) and are referred to as a “coupler pair”. A typical bus EMC installation for generators normally consists of 3 machine EMCs, 3 system EMCs and a termination box (double-ended installation). For some motors and smaller generators, only 3 machine EMCs and a termination box may be required (single-ended installation) [last paragraph of Section 1.1, page 6]. The EMCs are normally located in metal enclosures such as machine terminal boxes, phase bus ducts, breaker cubicles or transformer and/or surge protection cubicles. The termination box is usually located midpoint between the EMC locations for a generator or on the outside of the motor terminal box for a motor.

2.2 EMC Location A review of the electrical arrangement and schematic drawings will assist in the preplanning of the installation and will help identify the most probable location for the couplers. However, once at site, a visual inspection of the proposed EMC locations is always necessary to confirm that EMC placements will not interfere with the designed electrical integrity of the equipment. Consult Iris Field Service Technical Support if in doubt about the correct application and location of EMCs [ref. Section 5.1]. For each phase, one EMC is mounted at the motor, generator, switchgear or transformer terminals and is referred to as the “machine” coupler [Figure 3]. This EMC measures the partial discharge (PD) originating within the machine stator winding or high voltage apparatus.

Install the Machine coupler at the main leads (or as close as possible) for maximum sensitivity to machine PD.

For double-ended installations, the second EMC must be installed a minimum distance of 2 meters (≈ 6 ft) from the “machine” coupler and is referred to as the “system” coupler. This second coupler permits the test instrument to recognize system noise and ensure that it is not counted as unit PD. System noise and unit PD are recognized and classified by the test instrument based on time of arrival and direction of pulse travel.

Page 12: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 10 Iris Power LP

Figure 3. Schematic of a Bus EMC Installation

The “system” couplers are typically installed within the generator main bus duct or ISO-phase bus duct. In some cases the EMC may be installed in the potential transformer (PT) cubicle or in the circuit breaker cubicle. Please contact Iris Field Service Technical Support if the system coupler is to be placed on a tap off of the main bus to ensure the verification for installations involving taps has been satisfied. [See the Iris Verification Guide.] If there is no PT cubicle, then the system couplers can be fitted into the circuit breaker cubicle. It is desirable that there be no feeders, splits, CTs, PTs, or similar devices located between the coupler pairs on any given phase. The presence of such between the EMCs can lead to signal distortion and imperfect noise reduction. It is therefore preferred to connect both “Machine” and “System” couplers between the main terminals and these devices. Where there is insufficient length of busbar (less than 2m or 7ft) or insufficient space between the high voltage terminals of the winding and such devices, then the “Machine” coupler should still be installed as close to the terminals as possible. The “System” coupler, in this case, will have to be mounted beyond these devices and there may be some effect on the response from the “System” coupler. If under special circumstances both couplers have to be installed after such devices, a sensitivity comparison is recommended to find the extent of attenuation that may have been caused. It is the purpose of the coupler installation verification to determine the behaviour and coupler response in order to understand how data collection may be affected in these cases. Please contact Iris Power for more information, assistance or the verification service. In some cases surge capacitors are present near the machine terminals. In this situation, it may be necessary to install either the machine end or the system end EMCs on the bus near the surge capacitors. Do not connect the EMC to the top of the surge capacitor or after the cable connecting the surge capacitor to the bus, connect the EMCs directly to the bus. Connect the EMC closer to the winding than to the surge capacitor, and at least 1 m away from the surge

Page 13: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 11 Iris Power LP

capacitor. If the separation is less than 1 m, a coupler response comparison with and without the surge capacitor is recommended. Please contact Iris Power if this service is required. When selecting the location for mounting the EMCs, ensure there is sufficient space to install the EMCs without compromising the high voltage integrity (BIL) of the output bus. There must be adequate voltage clearance between the low voltage portion of the EMC and coaxial cable to any high voltage component. Similarly, the high voltage portion of the EMC and the HV leads must be a safe distance from any grounded structures and other phases. The recommended and absolute minimum distances in air between insulated high voltage and low voltage components are: Table 2-1. High voltage clearance requirements

EMC Rated Voltage Recommended Minimum

6.9kV 25 mm (1 in) 6mm (0.25 in) 16kV 50 mm (2 in) 20mm (0.75 in) 25kV 150mm (6 in) 63mm (2.5 in)

Figure 4. EMC mounted in a bus duct

Generally there is sufficient room within the terminal box or bus duct. However, it is not uncommon to modify the existing bus duct or terminal box to accommodate the EMC installation, provided electrical clearances can be maintained. Figure 4 shows where an access point was cut in the bus duct to accommodate the installation. When selecting the location to install the EMCs, consideration must be given to the necessary conduit run [see Section 4].

Coaxial cables may be run inside machine terminal boxes, PT cubicles, etc. to a suitable exit point for the conduit. When routing the coaxial cables from the EMCs to the coupler termination box, the coaxial cables must be run along a grounded metallic surface.

Once a site is selected, then site verification using site verification couplers should be performed in accordance with the Iris Verification Guide.

Page 14: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 12 Iris Power LP

2.3 High Voltage Connection The high voltage (HV) side of the EMC is connected to the generator or motor terminals/bus using the supplied HV cable. The cable is fully insulated for 15kV or 35kV class of operation (supplied according to machine voltage rating) and is unshielded; therefore, no stress relief is required. The HV cable should be routed so as to maintain adequate electrical clearances to ground or other phases for the voltage class of the machine [Table 2-1].

The high voltage cables should be kept as short as practical. The 6.9kV and 16kV EMCs may be mounted in any orientation (vertical, horizontal, or suspended); however, the 25kV style EMCs should only be mounted upright unless optional mounting clamps are used [see Appendix E]. Refer to Section 2.4 for EMC Mounting considerations.

Determine where the EMC high voltage cable connection will be made to the machine. There are basically three choices as shown below:

1. The 15kV and 35kV insulated high voltage (HV) cable supplied by Iris can be connected directly to a machine bus.

[These EMCs have yet to be insulated.]

2. Copper strap can be used. It is formed to make connection clips or stand offs, as required, to connect the high voltage cable to the bus. Such a connection is optional at the discretion of the user.

[This connection has yet to be insulated.]

Page 15: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 13 Iris Power LP

3. Alternative copper conductor can be used in large generators to connect directly between the EMC HV terminal and the generator bus. Note that the conductor should have a bend in it to allow for bus movement due to thermal expansion and 120/100 Hz vibrations. Care should be taken if the HV bus experiences large thermal movement; otherwise the EMC can be damaged by a tight connection. Braid type conductor is not recommended.

Steps for preparing the HV cable or copper strap:

1. Temporarily attach a high voltage cable to the EMC and select the most suitable mounting location. See Section 2.4 for EMC Mounting Considerations.

Figure 5. Typical Installation

Ensure that the bend radius of the HV cable is not less than 7 times the cable diameter. It is preferable that the HV cable be oriented to curve back across the top of the EMC once installed [Figure 5].

• Ensure main clearances phase-to-phase and phase-to-ground are not compromised [Table 2-1].

2. Determine where the high voltage cable will connect to the machine bus and whether existing connection bolts can be used or if new holes are required. The installation kit provides the appropriate brass hardware in both metric (10mm) and imperial (3/8in).

3. Assuming the insulated HV cable (supplied) is to be connected to the EMC, determine the length of cable required to connect the top terminal of the EMC to the selected spot on the bus or connector. Allow sufficient length so the

Page 16: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 14 Iris Power LP

cable will not be under tension. Trim the HV cable to suit and crimp on the straight ring lug (supplied) or one suitable for the installation.

NOTE: Where there is minimum separation, <2m (6ft) between the Machine and System couplers, the HV cables must be cut to identical lengths for each coupler pair.

4. If the supplied HV cable is not used, then a cable of equivalent rating (unshielded) must be used and kept to a minimum length. Iris recommends a maximum of 60cm (2 ft).

NOTE: The EMC should be kept clean during the installation. Painting or coating the EMC with foreign materials may degrade the electrical tracking resistance of the EMCs. The surface of the EMC may be cleaned with a cloth moistened with alcohol or approved solvents. If in doubt of the compatibility of the solvent with the EMC, contact Iris Field Service Technical Support [ref. Section 5.1].

Page 17: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 15 Iris Power LP

2.4 EMC Mounting Considerations Each EMC is clamped into place on a suitably flat surface using the two-piece mounting clamp (supplied). The mounting clamp should fit snugly and securely in the machined groove at the base of the EMC. If this is not the case, please contact Iris Field Service Technical Support. The 6.9kV and 16kV EMCs may be mounted in any position (vertical, horizontal or suspended) - where there is sufficient electrical clearance.

NOTE: The 25 kV EMCs should only be mounted upright unless optional mounting clamps are used.

For installations requiring mounting of the 25kV EMC in the horizontal or suspended position, Iris can, as an option, supply special mounting blocks manufactured for that purpose. Iris can also supply as an option mounting brackets fabricated to “tilt” the EMC at no greater than a 45° angle. See Appendix E for further information, or contact your Iris Field Service Technical Support.

The standard two-piece mounting bracket slides into a machined groove at the base of the EMC and has four slotted holes to accommodate 6mm (¼in) bolts for securing the brackets in place. Using the dimensional drawing in [Appendix A], layout and drill the holes for the EMC mounting brackets. The holes can be drilled using a 7mm (5/16in) drill bit, or if the hole is to be tapped use a 5mm (13/64in) drill bit.

Page 18: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 16 Iris Power LP

Iris also supplies as an option, steel mounting plates for installing EMCs within the ISO-phase bus duct or other curved surfaces as shown in Figure 6. Please contact your Iris Field Service Technical Support for further information [ref. Section 5.2]. The plate is used to give the EMC a flat mounting surface inside the ISO-phase bus. Mounting the plate and brackets lengthwise along the duct allows for the maximum clearance and stability to reduce mechanical stress on the EMC.

Figure 6. Curved mounting bracket

Figure 7. Fabricated mounting plate

In some situations, a plate to which the EMCs will be secured will need to be fabricated on-site and installed as shown in Figure 7. The only time new holes should be drilled through the supplied mounting clamps is when the EMC is sitting upright on a flat smooth surface.

When installing 6.9kV & 16kV couplers in the horizontal position, the mounting brackets should be aligned vertically (12 and 6 o’clock of the EMC) as shown in Figure 8.

Figure 8. Horizontal mounting of a 16kV EMC

Page 19: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 17 Iris Power LP

2.5 Insulating the EMC The HV connection at the top of the EMC must be insulated regardless of the location selected for the installation. The only exception is when the EMC is installed inside an ISO-phase bus and there is insufficient room for the insulation.

A preformed silicone rubber mould, or “Boot” (supplied) seals tightly over the high voltage cable and the first shed of the EMC. For customers who prefer tape insulation, please refer to the Product Update for Tape Insulation. Both the Boot and tapes are designed for normal operating temperatures (<90°C or 219°F) and non-radiation environments. For other application areas, the customer must provide suitable insulation.

Steps for Insulating the EMC with the Boot:

1. Prior to installing the Boot, position the EMC and determine which way the EMC clamps will be mounted, and the position where the coaxial cable will exit the EMC in relationship to the mounting clamps.

Due to the nature of the HV cable connection to the top of the EMC, the cable will be offset from centre and may influence the preferred orientation with respect to the coaxial cable. Therefore, when installing the HV cable, ensure the slot for the coaxial cable exit (at the bottom of the EMC) is oriented in the right direction.

2. The boot has a two-step “neck” to accommodate either the 15kV or 35kV HV cables. When installing with the 35kV cable, trim off the smaller diameter “neck”. Care must be taken to ensure that the remaining part of the boot is not damaged. Use a sharp knife or razor knife for trimming the boot.

3. Take the boot in hand and collapse the boot like an accordion. The boot will be installed over top of the right angle lug. If desired, smear a light coat of silicone approximately 7cm (2in) up the HV cable from the ring lug, which will act as a lubricant and facilitates the installation. The recommended silicone is “Clear Guide”, a wire pulling lubricant or SU5005RTV silicone adhesive (not provided), which is both a lubricant and a sealant.

Page 20: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 18 Iris Power LP

4. Carefully insert the ring lug through the neck of the boot. Push the boot high enough so that there is sufficient clearance to install and tighten the bolt through the ring lug to the EMC.

5. Bolt the HV cable to the top of the EMC; check the orientation of the cable before tightening to ensure that the cable will bend over top of the EMC. Place a small dab of “loc-tite” (not provided) on the brass bolt and tighten in place. Do not over tighten to the point where the lock washer starts to spread.

6. Start the lip of the boot over the first shed of the EMC, place hands on each side and gently stretch and roll the boot to the front of the EMC using a slightly downward pressure. This will force the boot over the shed and snap into place. The boot should ONLY cover the first shed of the EMC. No lubrication or sealing is required.

Page 21: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 19 Iris Power LP

7. Once the boot is positioned over the EMC, straighten the HV cable and position the neck of the boot so that it is in a relaxed position as shown.

8. Wipe off any excess silicone. If RTV silicone adhesive is being used, allow it to set for ½ hour before installation.

Caution: Do not paint the silicone boot or EMC.

9. To remove the boot from the EMC - with both hands hold the rim of the boot and gently pull it away from the EMC and at the same time peal it back towards the HV cable.

NOTE: In the event the boot is a loose fit over the 15kV cables, it is recommended that two half-lap layers of Silicone Guideline tape be wrapped around the top of the boot/cable. This will seal the top of the boot to the cable preventing the ingress of moisture and contaminants. Iris recommends a full layer (i.e. the width of the tape) of Silicone Guideline tape on the boot and a full layer on the HV cable as shown.

Page 22: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide EMC Installation - 20 Iris Power LP

This page has been left blank intentionally

Page 23: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Termination Box Installation - 21 Iris Power LP

3. Termination Box Installation 3.1 Overview

Note: For ATEX/IECEx Standard (Stainless Steel) Termination Box Installation Instructions see Appendix G

Figure 9. Coupler Termination Box

The termination box contains the BNC jacks/terminal board to which the coaxial cables from the EMC sensors are terminated [Figure 9]. RG58 (50Ω) coaxial cables are used to connect the EMCs to the termination box. The termination box contains a 1500Ω resistor and 75V surge arrestor (spark gap) on each connector. This ensures that the normal voltage from all EMCs will be less than 600 mV. For Iris continuous monitors (Tracs & Guards) please refer to the appropriate installation guides.

3.2 Installation Both coaxial cables on a given phase are required to be of identical lengths. Mount the termination box in a central location between the coupler pairs to minimize the coaxial cable required. If it is not possible to centrally locate the termination box, excess cable (<11m/36ft) can be stored in an open loop (not coiled) inside the termination box. A second box (not supplied) is required to store longer lengths of coaxial cable. The termination box is mounted with the door hinge at the bottom and the locking clips at the top as shown in Figure 9.

Page 24: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Termination Box Installation - 22 Iris Power LP

The standard termination box is a NEMA 4X corrosion-resistant fibreglass box with no knockout provision for coaxial cable access. Iris has an optional stainless steel box for special applications and corrosive environments, however this would have to be specified at the time of order. The coaxial cable access location (top, bottom, sides or back) and hole size is determined at the time of installation and punched or drilled before mounting. The termination box can be mounted on any vertical surface, such as a wall, the side of a cubical, structural I-beam or motor/generator terminal box at approximately eye level. The termination box itself does not require power but should have reasonable access to a 110/220V power outlet for performing tests with the Iris portable instrument.

Steps for Installing the Termination Box: 1. Determine a suitable location for the termination box. 2. Remove the internal circuit board from the box, and set safely aside for

later use. 3. Drill/punch out the appropriate size hole for the coaxial cable conduit at

the desired location in the termination box and install a suitable adapter. [See Table 4-1 for information about conduit sizes]

4. Using the dimensional drawing in Appendix A, mark the location for holes. 5. Mount the termination box by drilling and tapping, or using bolts as

necessary.

Figure 10. Ground bolt

6. Run the #4 copper wire (supplied, green jacket) from the ground bolt on the right side of the termination box [Figure 10] to a permanent station ground location. This bolt is used to ground the components inside the termination box and also the metallic conduit. This should be the only point where the conduit is grounded to minimize the risk of circulating currents due to differing ground potentials.

Page 25: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 23 Iris Power LP

4. Coaxial Cable Installation 4.1 Overview The coaxial cable connects the low voltage terminal of the EMC to the termination board inside the termination box. The coaxial cables from a coupler pair in a phase must be the same length and must be routed along a grounded metal surface from the EMC to the termination box. To minimize conduit runs, all six coaxial cables can be run through a common conduit.

4.2 Installation Depending on the routing, the coaxial cables may be run through enclosures or metallic conduit, or a combination of both to the termination box. Whenever the coaxial cables exit a metal enclosure, they must run in grounded rigid or flexible metallic conduit. The coaxial cables should preferably run away from and not on open cable trays alongside power cables. The conduit must provide a continuous ground plane and should only be grounded at the termination box.

NOTE: Multiple ground points along a conduit may result in high circulating currents, which may cause the conduit to overheat and melt the coaxial cable insulation. This is especially true in ISO phase bus arrangements.

Important for ISO Phase Bus Installations: When installing conduit between various ISO Phase Bus (IPB) components, be very careful not to inadvertently short circuit or jumper any IPB insulated gaps. An insulated nylon bushing or a short section ~ 5-10cm (2-4in) of PVC conduit installed at the EMC coaxial cable exit point will be sufficient to insulate the conduit from the bus. It may also be necessary to insulate the conduit from the clamps and hangers to avoid ground loops [Appendix D].

In order to avoid damage to the coaxial cables, all conduit sizes should comply with local electrical safety codes. In the absence of local codes, the minimum conduit sizes in Table 4-1 are recommended.

Page 26: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 24 Iris Power LP

Coaxial Cables Conduit Size ID NOTE: These measurements are for rigid conduit only and should be increased 1 size for the 3 to 12 coaxial cable installations if a flexible conduit is used.

3 to 6 Coaxial Cables 2cm (¾in)

9 Coaxial Cables 2.5cm (1in)

12 Coaxial Cables 3cm (1¼in)

18 Coaxial Cables 4cm (1½in)

24 Coaxial Cables 5cm (2in)

Table 4-1. Conduit sizes Meets or exceeds Canadian Electrical Safety Code, Part 1, Rule 12-1014

Steps for Installing the Coaxial Cable:

1. Determine the route for conduit runs from each set of EMCs to the termination box. Conduit is not required in cubicles and enclosures where the coaxial cable can be securely fastened continuously against a grounded metal surface.

2. For each coupler, determine the path the cable will take from the coupler to the termination box.

3. Install the conduit between the coupler and the termination box. Since the conduit is only grounded once at the termination box, install conduit insulators as required.

4. Determine the total length of coaxial cable required to reach each coupler in a pair. Often, more coaxial cable will be needed for one coupler in a pair than the other, since the termination box cannot always be centred between the pair. Select the longest cable length measured for each pair, add 3m (10ft) extra and cut two cables of this length. Coaxial cable lengths should be within +/-25mm (1in) per coupler pair.

NOTE: If a PDA-IV instrument is to be used, the coaxial cables will be of different lengths. (Contact Iris Field Service Technical Support for PDA-IV cable details.)

5. Label the coaxial cables according to the chart below for easy identification:

Phase Machine Coupler System Coupler A M1 S1 B M2 S2 C M3 S3

Page 27: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 25 Iris Power LP

4.3 Preparing Coaxial Cable at EMC End For Motor Applications within Nuclear Plant Containment, see Appendix F

Figure 11. Trimming of coaxial cable

1. Cut the outer jacket back approximately 2.5cm (1in).

2. Carefully trim off the exposed shield flush with the jacket.

3. Trim back the centre conductor insulation approximately 9.5mm (3/8in).

4. Crimp on the supplied ring lug.

5. Position the black heat shrink tube centred over the trimmed area of the jacket and centre conductor.

6. Using a heat gun shrink the tubing into position to ensure the coaxial shield will be isolated from ground.

Figure 12. Coaxial cable connection

Caution: Overheating during the shrink process (step 6) may damage the centre conductor insulation, resulting in the centre conductor grounding to the outer shield.

Figure 13. Bottom of EMC

7. Prior to installing the coaxial cable, check that the stainless steel plug is tight in the bottom of the EMC.

8. Dab a small quantity of “loc-tite” on the coaxial terminal screw, and then wipe off any excess.

Page 28: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 26 Iris Power LP

9. Position the ring lug at the 9 o’clock position from the machined groove and tighten the screw. Do not exit directly through the groove or try to press the shrink-covered portion into the groove, instead form a half-loop as shown in Figure 14.

If the EMC is to be installed in a caustic environment, such as petrol-chemical plants or subject to severe vibration, a covering of RTV (silicone rubber) can be applied over the exposed brass insert, ring lug and coaxial cable.

Figure 14. Coaxial cable connection

10. Once all the coaxial cables have been connected to the EMCs, the EMCs can be permanently mounted in the unit. Once mounted, route the coaxial cable to the conduit, ensuring that the cable is run along a grounded surface. Fasten the coaxial cables in place using mechanical fasteners.

NOTE: Never secure the coaxial cables in place using adhesive backed clips etc.

The coaxial cables MUST only be placed adjacent to the low voltage portion of the EMC and secured to a ground plane.

Never place the coaxial cable adjacent to the high voltage end (top) of the EMC or any high voltage component of the machine.

Avoid running the coaxial cable over top of the HV bus or terminals, where failure of a clamp or support may allow the coaxial cable to fall onto a HV component.

11. It is often necessary to pull slack or excess lengths of coaxial cable back through the conduits to a suitable storage location. Therefore, the practice of bundling and taping the coaxial cables together should be avoided. Although this practice does make the cable pulling process more manageable, it will create difficulties as the installation process continues.

Page 29: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 27 Iris Power LP

12. Pull any excess cable through the conduit and out through the termination box. Note that unless the termination box is centred between the couplers, three of the coaxial cables will have longer lengths. When pulling the cables, take care not to kink or damage them.

13. Once the coaxial cables have been pulled, there should be about 3m (10ft) of cable from each EMC extending out of the termination box. Perform the initial (trial) verification test as per the Iris Verification Guide.

14. Once satisfied with the verification, trim the coaxial cable leaving about 40cm (16in) extending from the box to provide enough slack to allow for hard wiring to the BNC jacks.

NOTE: When trimming the coaxial cable trim the same amount off each pair of cables.

15. Approximately 11m (36ft) of excess coaxial cable can be stored in open loops inside the termination box. If there is an excessive length of coaxial cable to be stored, it may be necessary to install a second box, or the coaxial cable can be pulled back into the machine or generator terminal box and secured in open loops there.

16. The excess cable should be formed into an open loop NOT a coil. A coil can increase the inductance of the cable and may distort the partial discharge pulses. If the coaxial cable is pulled back into the machine, or terminal box, ensure that it is securely fastened by mechanical means away from the electrical components.

4.4 Preparing Coaxial Cables for Soldering

Figure 15. Trimmed coaxial cable

1. Trim the outer shield of the coaxial cable about 9mm (5/8in).

2. Carefully un-braid the shield and divide into two equal parts and then twist the strands together to consolidate the loose strands [Figure 15].

3. Strip the centre conductor insulation to approximately 6mm (¼in) from the twisted shield.

Page 30: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 28 Iris Power LP

Figure 16. Coaxial cable connected to termination board

4. Insert the exposed conductors into the fork terminals with the centre conductor in the middle fork and each of the shield conductors on the two side forks [Figure 16].

5. Secure all the coaxial cables in place with cable ties (not supplied). At this point, use only the cable tie nearest the connection to be soldered.

NOTE: Care must be taken during soldering to avoid overheating the shield conductors and melting the insulation between the shield and the centre conductor. Do not try to solder all 3 points on a given cable in quick succession.

6. Solder the connections. Soldering the same terminal on each of the coaxial cables will allow sufficient time for the insulation to cool before soldering the next terminal.

7. Trim the excess strands flush with the solder terminal.

Figure 17. Trimmed and soldered connection

Page 31: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 29 Iris Power LP

Figure 18. Securing coaxial cable with cable ties

8. Inspect the soldered joints to ensure proper soldering and no missed or cold (dry) soldered joints exist.

9. Check that no stray strands are shorting out the terminals.

10. Position the coaxial cables and use the last remaining cable ties on the board to secure the three cables in a bundle [Figure 18].

11. Secure the excess coaxial cable neatly inside the termination box.

12. For most installations, the excess coaxial cable (no more than 11m or 36 ft) can be stored in an open loop inside the fibreglass termination box [Figure 20]. Secure the excess cable as described in Section 4.3 steps 15 and 16.

Figure 19. Completed installation

Figure 20. Securing excess coaxial cable

in termination box

13. Secure the circuit board to the box using the screws provided.

14. Verify the connection of the ground wire.

Page 32: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Coaxial Cable Installation - 30 Iris Power LP

This page has been left blank intentionally

Page 33: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Customer Support - 31 Iris Power LP

5. Customer Support 5.1 Technical Support If you require additional technical support, please contact Iris’s Field Service Technical Support at e-mail [email protected] or fax 001-416-620-1995 or telephone 001-416-620-5600

5.2 Sales Support If you would like to obtain additional installation materials, please contact Iris’s Sales Department at 001-416-620-5600 or [email protected].

5.3 Product Updates & New Product Information For firmware and software upgrades, product updates and new product information, visit our website www.irispower.com regularly or contact our Sales Department at e-mail [email protected] or telephone 001-416-620-5600.

Page 34: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Customer Support - 32 Iris Power LP

This page has been left blank intentionally

Page 35: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Customer Support - 33 Iris Power LP

Glossary Terms Definitions

BusGuard™ Continuous PD monitoring system using bus couplers in a double-ended installation as PD sensors with the ability to trigger off of operating conditions based on analog inputs – provides 2D &3D results.

BusTrac™ Continuous PD monitoring system using bus couplers in a double-ended installation as PD sensors – provides 2D results.

Coupler Pair Two EMCs on a given phase, to allow noise discrimination. Delay Time The time measured in nanoseconds that it takes for a high frequency pulse to

travel from one coupler to the other in a directional (Bus) installation. Directional (BUS) Installation

Coupler Pair - One connected to the machine terminals and a second at least 1.8m (6ft) away. Noise separation is done by direction and time of pulse arrival.

EMC Epoxy Mica Capacitor – 80pF high voltage partial discharge sensor. Single-Ended Installation

An installation using 3 EMCs (one per phase) installed at the machine terminals.

Double-Ended Installation

A directional (BUS) installation using 6 EMCs (two per phase), one installed at the machine terminals and the second toward the system.

Machine Coupler EMC mounted on/near the machine terminals. PDTrac™ Continuous PD monitoring system using 3 EMCs in a single-ended installation

as PD sensors with the ability to trigger off of operating conditions based on analog inputs – provides 2D results.

System Coupler In a double-ended installation the EMC mounted closest to the system. Post Insulators An insulator that is used to support high voltage bus bars. Feeders, splits Taps off of the bus to auxiliary circuits.

CTs, PTs Current and potential transformers used to monitor machine parameters.

TGA-B™ Portable test instrument to measure PD using bus couplers as PD sensors – provides 2D & 3D results.

TGA Bantam™ Portable test instrument to measure PD using bus couplers as PD sensors – provides 2D results.

Rise-time Time it takes for a pulse to increase from 10%-90% of its magnitude.

Page 36: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Customer Support - 34 Iris Power LP

This page has been left blank intentionally

Page 37: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix A – Dimensional Drawings - 35 Iris Power LP

Appendix A. Dimensional Drawings

EMC Mounting Clamps

Mounting clamp arrangement & dimensions.

(not exactly to scale)

Page 38: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix A – Dimensional Drawings - 36 Iris Power LP

Termination Box Dimensions

End

View

Bot

tom

Vie

w

Side

Vie

w

0.12

"(3

mm

)

8.5"

(216

mm

)0.

41"

10 m

m

6.0"

(152

mm

)

6.0"

(152

mm

)#1

0-32

Pan

Hea

d

0.31

"

0.5

0"8

mm

1

3 m

mx

Slo

t

1.31

" (33

mm

)

10.9

4" (2

78 m

m)

10.5

" (26

7 m

m)

9.12

" (23

2 m

m)

4.94

"(1

25 m

m)

10.5

" (26

7 m

m)

Qui

ck-R

elea

se C

over

Enc

losu

re

Not

es:

1) M

ount

ing

feet

are

0.1

6" (4

mm

) thi

ck.

2) Q

uick

rele

ase

clam

ps n

ot s

how

n in

"En

d Vi

ew".

3) T

he g

roun

ding

stu

d M

UST

be

conn

ecte

d to

sta

tion

grou

nd.

Dra

wn

By:

Dav

e Pr

osse

rD

ate

Dra

wn:

July

9, 1

999

App

rove

d B

y:

Dat

e A

ppro

ved:

ct

b-di

ms.c

drD

raw

ing

#: IS

O- 0

39R

evis

ion

#: 0

0IR

ISP

OW

ER

E

NG

IN

EE

RI

NG

Iris

Pow

er E

ngin

eerin

g1

Wes

tsid

e D

r., U

nit 2

Etob

icok

e, O

ntar

io, C

anad

a M

9C 1

B2

tel (

416)

620

-560

0, fa

x (4

16) 6

20-1

995

Cou

pler

Ter

min

atio

n B

ox M

ount

ing

Dim

ensi

ons

3/8“

NC

G

roun

ding

Stu

d

Termination box dimensions.

Page 39: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix B – Installation Materials - 37 Iris Power LP

Appendix B. lnstallation Materials

Bus coupler kits may be comprised of either 3 or 6 EMCs. The table below shows the contents of a full 6-EMC coupler installation kit supplied by Iris. Other materials may be substituted provided the materials used are intended for electrical use and are compatible with the electrical installation.

NOTE: Additional items, NOT SUPPLIED by Iris but which may be required to provide a complete installation, are shown on the next page of this Appendix.

Contents of a six EMC bus coupler kit Item Quantity Product Description

Epoxy Mica Capacitor 6 80 pF coupling capacitor, fitted with coaxial cable crimp ring lug and screw at base

High Voltage Jumper Cable

6 15kV #2 AWG- or 35kV #1/0 AWG- insulated jumper cable 60 cm (24 in) with L-shaped ring lug attached

Straight Ring Lug 6 Burndy–1/2 in lug for #2 AWG HV jumper cable

Bolts/Washers/Lock-Washers

6 sets 6 - 3/8 in bolts (1in imperial thread) 6 – 10mm washers 6 – 10mm lock washers

Insulated Boot 6 Preformed high-voltage insulating boot

Mounting Clamps 6 sets Preformed stainless-steel brackets.

Coaxial Cable 150 m (500 ft) RG58 C/U 50 Ω coaxial cable

Polyolefin Shrink Tube 6 5 cm (2 in)

Termination Box 1 NEMA 4X corrosion proof moulded polyester fibreglass enclosure with termination boards.

Ground Wire 3 m (10 ft) 600V insulated wire #4 AWG (Green)

Page 40: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix B – Installation Materials - 38 Iris Power LP

Optional Materials and Hardware Item Typical

Quantities Product Description

25kV EMC Mounting Block 3 2 piece fibreglass mounting block.

Angled Support Bracket 3 45° angle aluminum bracket.

ISO Phase Bus Mounting Bracket

3 Steel mounting plate.

++SAP Tape - 2 rolls 5cm (2in) wide Self-Amalgamating Polymeric Tape Black in colour ROTUNDA 2501

++Silicone Rubber Tape 2 rolls 2.5cm (1in) wide Self Fusing –silicone rubber tape. Orange in colour.

++Electrical Putty 8 strips 5cm (2in) wide Electrical putty Supplied in strips 33cm (13in) long

++NOTE: Only required if boot is NOT used.

Page 41: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix B – Installation Materials - 39 Iris Power LP

ADDITIONAL MATERIALS For a complete bus coupler installation, depending on the configuration and layout, additional materials (not supplied by Iris) may be required. These additional materials may include some or all of the following:

Metallic Conduit Rigid or flexible may be used Conduit should have continuity over the length and may require simple point grounding to avoid ground current circulation. Ground at the termination box

Recommended conduit sizes for: 3 coaxial cables – 2 cm (¾ in) 6 coaxial cables – 2.5 cm (1 in) 12 coaxial cables – 3 cm 1¼ in)

Miscellaneous Conduit Fittings To run conduit from the EMC to the termination box Note pull boxes are recommended ~ every 15 ft

Conduit Mounting Brackets Insulated clamps/brackets may be required to avoid circulating currents in the conduit.

Nuts, bolts, lock & plate washers ¼-20 x 1in (??)

For Termination Box mounting – Qty 4 For EMC Mounting Clamps:

3 EMCs- Qty 12 6 EMCs- Qty 24

Miscellaneous Hardware Depending on the installation, additional hardware and materials for fabricating mounting brackets, and for electrical connections may be required.

Cable ties and clamps Required to fasten the coaxial cables into place. No adhesive backed fasteners can be used, unless also secured mechanically.

Miscellaneous hand tools Electric drill, drill bits, and taps Vacuum Crimping tool for Burndy #2 AWG – ½ in ring lug or #1/0 AWG – ½ in ring lug Razor knives, wood chisels, files Loc-tite, RTV, epoxy

Page 42: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix B – Installation Materials - 40 Iris Power LP

This page has been left blank intentionally

Page 43: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix C – Off-line Testing - 41 Iris Power LP

Appendix C. Off-line Testing

Hi-pot Testing PROVIDED the EMCs are correctly terminated into the grounded termination box in accordance with the Iris installation manual, it is safe to carry out both AC and DC hi-pot tests of the stator winding. Should there be a need to conduct a winding test AFTER the high voltage connection to the EMC has been made, but BEFORE the coaxial cables have been properly terminated, [see Section 4.4] then the ends of the coaxial cable must be stripped bare, shields and centre conductors twisted together and the whole lot grounded. Each EMC is Hi-pot (proof) tested by Iris at twice the rated voltage plus 1kV

6.9kV EMCs are tested to 15kV for one minute 16kV EMCs are tested to 33kV for one minute 25kV EMCs are tested to 51kV for one minute

The design of the EMC is such that the breakdown and tracking voltages exceed the hi-pot values above. The only factor that may affect performance during hi-pot testing of the winding is heavy contamination on the EMC. If this is the case, a visual inspection and cleaning is recommended prior to testing, especially if there is heavy contamination on the bus or other components. Hi-pot testing of machines that have Iris EMCs installed can safely be carried out without risk of any damage to the EMC up to industry standard levels of:

AC Hi-pot: twice rated machine voltage + 1000 volts DC Hi-pot: 1.7 x (twice rated machine voltage + 1000 volts)

Other Off-Line Tests

The presence of the EMCs during other off-line diagnostic tests, for example Partial Discharge, Dissipation/Power Factor tests, Megger and PI, will not affect the machine winding characteristics or have a detectable impact on measured results. The EMCs are 80pF capacitors, which is negligible in comparison to the winding capacitance and are certified by Iris as partial discharge free up to twice the rated phase-to-ground voltage.

If you still have questions or concerns regarding off-line testing of your machine that has Iris EMCs installed, please feel free to contact Iris Field Service Technical Support.

Page 44: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix C – Off-line Testing - 42 Iris Power LP

This page has been left blank intentionally

Page 45: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix D – IPB Installs - 43 Iris Power LP

Appendix D. ISO Phase BUS Considerations

Important: When installing conduit between various ISO Phase Bus (IPB) components, be very careful not to inadvertently short circuit or jumper some IPB insulated gaps. An insulated nylon bushing or a short section ~ 5-10cm (2-4in) of PVC conduit installed at the EMC coaxial cable exit point is sufficient to insulate the conduit from the bus. It may also be necessary to insulate the conduit from the conduit clamps and hangers to avoid ground loops.

Typical IPB Configurations Figures 21a, 21b and 22 illustrate three simplified IPB configurations, showing insulated bus support mounts and insulated bellows with segregation at the Generator Transformer (Figure 21a) or Generator (Figure 21b). Figures 21a and 21b show systems where each phase is insulated separately and Figure 22 where they are common. The KEY factor is that the phase buses are grounded at ONE point only to ensure that circulating currents within the system are prevented.

Figure 21a. Segregated at the generator transformer

Page 46: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix D – IPB Installs - 44 Iris Power LP

Figure 21b. Segregated at the generator

Figure 22. Common phase insulation – segregated at the transformer

Ground Loop Figure 23 illustrates the effects of a ground loop in an IPB. The dotted line indicates the circulating currents in the IPB should it be grounded at both the Generator and Generator Transformer. The dotted/dashed line indicates the effects of a metallic conduit that is grounded and attached to the IPB. It should be noted that thousands of amps could flow through a conduit introducing a second ground on the IPB system and will eventually cause damage to internal cables.

Page 47: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix D – IPB Installs - 45 Iris Power LP

Figure 23. Ground loops

Typical Conduit Runs with IPB Systems Figure 24 and Figure 25 illustrate typical conduit runs with insulated conduit supports. Note the conduit is grounded only at the termination box. Figure 26 illustrates an alternative method where flexible plastic conduit is used at the connection between the IPB and the conduit; therefore, the conduit is not in a continous run. Insulated bushings are installed to break up the conduit run, each section of conduit is grounded individually so as to prevent circulating currents.

Figure 24. Conduit run for IPB

Page 48: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix D – IPB Installs - 46 Iris Power LP

Figure 25. Conduit run for IPB

NOTE: Both for safety and measurement, the conduit MUST be grounded. It is essential that the coaxial cable runs in grounded metal conduit or against a grounded plane to reduce unwanted noise.

Figure 26. Alternate conduit run for IPB

Page 49: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix E –25kV Mounting Brackets - 47 Iris Power LP

Appendix E. 25kV EMC Mounting Blocks

Due to its weight and length, the largest Iris EMC (25kV) can only be mounted vertically (upright), using the standard metal mounting clamps. Optional horizontal mounting blocks, called Labadie Blocks, are used when the 25kV EMCs require mounting in any position other than vertical. The blocks may be assembled directly to the unit in horizontal or suspended positions, or mounted to an angled bracket.

Labadie Block The Labadie Block2

A typical installation would require using three Labadie Blocks installed at the generator terminals (machine couplers). On most large turbo generators, the second set of EMCs (system couplers) would be installed inside the generator ISO phase bus in an upright position.

was designed for ease of retro-fitting existing installations where the conventional Iris mounting clamps were used. While physically larger, the slotted mounting holes are drilled to the same centres as the conventional steel mounting clamps.

Figure 27. Labadie block for 25kV EMC

Selecting Mounting Location • Temporarily assemble (finger tighten) one block to be used for laying out

the mounting positions for the EMC and drilling the mounting holes.

• When selecting location for mounting, ensure there is sufficient room for the mounting block and adherence to all electrical clearances [Table 2-1].

2 This specialized mounting block was designed for and named after the Ameren UE, Labadie Power Plant.

Page 50: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix E –25kV Mounting Brackets - 48 Iris Power LP

Assembling the Block:

Figure 28. Trial fit of the Labadie block

1. Trial fit the EMCs to the Labadie Block. Due to machine tolerances, it may be necessary to try several EMCs in a given block to achieve the best fit. Once properly fitted, the EMC should contact the block in two positions. The space between the two mounting block sections should be equally spaced. The bottom of the EMC should be flush with the mounting block [Figure 28].

2. Once the EMC has been paired with the block, disassemble and apply a bead of epoxy around the machine mating surfaces of the block [Figure 29]. The epoxy is used to fill the voids where the EMC is not in contact with the block. The epoxy has a setting time of approximately 20 minutes, so prepare the assemblies one at a time.

Figure 29. Epoxy bead in Labadie block

3. Match the coaxial cable duct machined in the block with the cut–out on the EMC [Figure 28]. This is extremely important since there must be a channel for the coaxial cable. Once the epoxy sets, it is impossible to adjust the base.

4. Bolt the assembly together using “loc-tite” and apply equal pressure on each bolt. Once tight, the spacing should be equal on each side and the faces parallel [Figure 30].

Figure 30. Labadie block attached to EMC

NOTE: When tightening the bolts, only sufficient pressure should be applied so that the EMC cannot be rotated within the block. Over tightening may damage the EMC. Loc-tite must be used.

Page 51: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix E –25kV Mounting Brackets - 49 Iris Power LP

Figure 31. Bottom of EMC with Labadie block

5. After tightening, wipe off the excess epoxy that has extruded out and then allow it to set (approximately 20 minutes).

6. If the base of the EMC is not flush with the bottom of the mounting block, file the bottom of the EMC using a medium file until flush.

7. Fill the bolt holes with epoxy to permanently lock the block.

8. Assemble the coaxial cable as described in Section 4. A small amount of epoxy can be applied inside the cut-out to secure the coaxial cable in place [Figure 31].

Figure 32. Taped insulated 25kV EMC

9. Insulate the top of the EMC as described in Section 2.5 using the pre-formed boot or the Product Update for Tape Insulation.

10. The assembled EMC is now ready to be mounted on the unit.

Page 52: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix E –25kV Mounting Brackets - 50 Iris Power LP

Figure 33. 25kV EMC mounted horizontally

A 25kV EMC mounted horizontally using a Labadie block at a generator terminal.

45° Angle EMC Mounting Bracket

Figure 34. 25kV angle mounting

The 45° bracket requires no special instructions. The optional bracket is mounted at a suitable location and then the standard installation procedures are followed.

Page 53: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

Appendix F. Motor Applications within Nuclear Plant Containment

1. Cut the coaxial cable outer jacket back approximately 2.5 cm (1 in.) 2. Carefully trim off the exposed wire mesh and metal foil shields. 3. Trim back the centre conductor insulation approximately 9.5 mm (3/8 in.)

4. Crimp on the supplied ring lug. 5. Position self amalgamating EPR tape

centered over trimmed area of jacket and centre conductor.

6. Wrap at least two layers of EPR tape around coaxial cable so that it covers both the jacket and centre conductor insulation as shown in Figure 2.

7. Prior to installing the coaxial cable, check that the stainless steel plug is tight in the bottom of the EMC.

8. Dab a small quantity of “loc-tite” on the coaxial cable terminal screw, and then wipe off excess.

Figure 35: Trimming of the coaxial cable

Figure 36: Coaxial cable insulated connection

Figure 37: Bottom of EMC

To complete the coax cable installation follow steps 9 to 16 in Section 4.3 of this guide.

Page 54: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

This page has been left blank intentionally

Page 55: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

Appendix G. Instructions for ATEX & IECEx

ATEX Marking labels

IECEx Marking labels

The PDTrac Termination Box uses the small Fiberglass Stahlin Box. Plastic enclosures are to be cleaned or wiped only with a damp cloth to avoid static electricity hazards.

The Standard Termination Box uses the Stainless Steel Hoffman Enclosure.

DEMKO Previously the Danish government-owned testing and certification laboratory now wholly owned by Underwriters Labs (UL)

09 ATEX 143404X This is the EC-Type Examination certification number – Equipment or Protective system intended for use in Potentially explosive atmospheres Directive 94/9/EC and in compliance with EN 60079-0:2006 and EN60079-15:2005. The x denotes special warning conditions marked.

IECEx UL 10.0050X This is the International IECEx certification number Certification based on standards: IEC60079-0:2004 IEC60079-15:2005) Non-Incendive construction ‘nA’ Gas group: II Temperature class: T3

Page 56: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

CE Marking Directive. CE Mark is a visible declaration by the manufacturer (or his representative, importer, etc.) that the equipment which is marked, complies with all the requirements of all the applicable European Union (EU) directives.

ATEX – from the French – ATmospheres EX

II

plosibles. - Electrical Equipment for Use in Explosive Atmospheres (Directive 94/9/EC). Directive 94/9/EC is a directive adopted by the European Union (EU) to facilitate free trade in the EU by aligning the technical and legal requirements in the Member States for products intended for use in potentially explosive atmospheres.

Equipment Group- Non-mining (Above Ground)

3 Equipment Category, which is equal to ZONE 2 – normal protection used where explosive atmosphere is unlikely to occur and would be infrequent or for a short time.

G Type of explosive atmosphere - Gas, vapour, mist

Ex Explosive protection symbol.

nA Protection concept is non-sparking. How it works is that there are no no arcs, sparks or hot surfaces

II Gas group – all gases

T3 Maximum surface temperature is 200˚C -20˚C ≤ Tamb +50˚C Rated ambient temperature range IP66 Ingress Protection Solids=6=Totally protected against dust Liquids=6=Protected

against high pressure water jets and heavy seas. Must utilize IP66 ATEX/IECEx Certified suitable fittings for Installation to maintain IP66 rating.

For Instructions on putting the EMS’s into service, use, assembling and dismantling, maintenance, installation and adjustment see sections 1 and 2 of this Guide

The electrical ratings of the Termination Boxes are: 1 VAC, 0.6mA , 50/60Hz

Page 57: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

Installation of ATEX / IECEx 1) Standard Termination Box (Stainless Steel) & 2)PDTrac Termination Box (Fiberglass)

Overview The termination box contains the BNC jacks/terminal board to which the coaxial cables from the EMC sensors are terminated. RG58 (50Ω) coaxial cables are used to connect the EMCs to the termination box. The termination box contains a 1500Ω resistor and 75V surge arrestor (spark gap) on each connector. This ensures that the normal voltage from all EMCs will be less than 600 mV. Both coaxial cables on a given phase are required to be of identical lengths. Mount the termination box in a central location between the coupler pairs to minimize the coaxial cable required. If it is not possible to centrally locate the termination box, excess cable (<11m/36ft) can be stored in an open loop (not coiled) inside the termination box. A second box (not supplied) is required to store longer lengths of coaxial cable. For Iris continuous monitors (Tracs & Guards) please refer to the appropriate installation guides.

1 The ATEX & IECEx Standard Termination box is a 316 Stainless Steel Box. It has lift-off door hinges and one removable gland plate, located on the bottom. (The drawing shown has 3).

This gland is used for the coaxial cable access.

2 Hole size is determined at the time of installation and punched or drilled before mounting (see conditions on next

Page 58: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

page).

Utilize IP66 ATEX/ IECEx Certified suitable fittings for Installation to maintain IP66 rating.

Note:

1. Only drill holes in gland plates (see gland plate location).

2. Do not drill holes closer than .25 inches from the edge.

3. Visually inspect gaskets, locks and screws after each opening of covers or removing of gland plates.

3 Steps for Installing the Termination Box: • Determine a suitable location for the termination box. • Remove the internal circuit board from the box, and set safely aside for later use. • Drill/punch out the appropriate size hole for the coaxial cable conduit in the bottom gland plate of the

termination box and install a suitable adapter. [See Table 4-1 for information about conduit sizes] 4

• Mark the location for holes.

Page 59: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

5

ATEX/IECEx Coupler Termination Box with ground bolt

To Ground, run the #4 copper wire (supplied, green jacket) from the ground bolt on the left side of the termination box to a permanent station ground location. This bolt is used to ground the components inside the termination box and also the metallic conduit. This should be the only point where the conduit is grounded to minimize the risk of circulating currents due to differing ground potentials.

6 The termination box can be mounted on any vertical surface, such as a wall, the side of a cubical, structural I-beam or motor/generator terminal box at approximately eye level. The termination box itself does not require power but should have reasonable access to a 110/220V power outlet for performing tests with the Iris portable instrument.

7 The ATEX/IECEx PDTrac Termination Box is Fiberglass.

The coaxial cable access location (top, bottom, sides or back) and hole size is determined at the time of installation and punched or drilled before mounting. Use IP66 ATEX/IECEx Certified suitable fittings for Installation to maintain IP66 rating.

Page 60: Bus Coupler Installation Guide

ATEX/IECEx APPROVED, NO REVISIONS WITHOUT NOTIFIED BODY APPROVAL

Bus Coupler Installation Guide Appendix G Iris Power LP

8

9 Follow the “Steps for Installing the Termination Box:” from item 3 previously (same as Standard Termination Box). As well items 6 & 7 apply. Plastic enclosures are to be cleaned or wiped only with a damp cloth.